The World Bank Implementation Status & Results Report Renewable Energy Integration (P144534) Renewable Energy Integration (P144534) EUROPE AND CENTRAL ASIA | Turkiye | IBRD/IDA | Investment Project Financing (IPF) | FY 2014 | Seq No: 18 | Archived on 05-Mar-2025 | ISR03259 Implementing Agencies: TEIAS- Turkish Electricity Transmission Company 1. OBJECTIVE 1.1 Development Objective Original Development Objective (Approved as part of Approval package on 09-May-2014) The PDO is “To assist Turkey in meeting its increased power demand by strengthening the transmission system and facilitating large-scale renewable energy generation”. The GEO is “To avoid Green House Gas (GHG) emissions from fossil fuel based power through greater integration of renewable energy sources based generation in Turkey”. Has the Development Objective been changed since Board Approval of the Project Objective? Yes Current Development Objective (Approved as part of Additional Financing package Seq. 1 on 28-Feb-2020) The PDO is “To assist Turkey in meeting its increased power demand by strengthening the transmission system and facilitating large-scale renewable energy generation”. The GEO is “To avoid Green House Gas (GHG) emissions from fossil fuel based power through greater integration of renewable energy sources based generation in Turkey”. 2. COMPONENTS Name Component-2: Smart-grid investments to strengthen grid operation and management in face of higher wind energy generation:(Cost 35,000,000.00) Component-1: Upfront development of transmission infrastructure to facilitate faster development of WPPs:(Cost 62,200,000.00) Component-3: Lapseki-Sutluce 380 kV Submarine Power Cable to better inter-connect wind energy locations with other parts of Turkey:(Cost 336,300,000.00) Component-4: Strengthening of Transmission Networks to cater to growing demand and supply of electricity in Turkey:(Cost 207,868,297.00) 3. OVERALL RATINGS Mar 05, 2025 Page 1 of 9 The World Bank Implementation Status & Results Report Renewable Energy Integration (P144534) Name Previous Current Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Moderate Moderate 4. KEY ISSUES & STATUS 4.1 Implementation Status and Key Decisions The project is making steady progress towards meeting its development objective. All of the twenty-five sub-projects under the parent project have been completed, and are operating successfully. The additional financing loan became effective on January 8, 2021, and the procurement processes for the sixteen investments under nine contracts have been completed, two out of nine contracts have been completed, and the remaining seven are expected to be completed by the new closing date of September 30, 2025.. 5. SYSTEMATIC OPERATIONS RISK-RATING TOOL Rating at Approval Last Approved Rating Risk Category Approval Package - ISR Seq. 017 - 28 Jun Proposed Rating 09 May 2014 2024 Political and Governance Moderate Moderate Moderate Macroeconomic Substantial Substantial Substantial Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Substantial Substantial Substantial Sustainability Fiduciary Moderate Moderate Moderate Mar 05, 2025 Page 2 of 9 The World Bank Implementation Status & Results Report Renewable Energy Integration (P144534) Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Moderate Overall Moderate Moderate Moderate Mar 05, 2025 Page 3 of 9 The World Bank Implementation Status & Results Report Renewable Energy Integration (P144534) 6. RESULTS 6.1 PDO Indicators by PDO Outcomes To assist Turkey in meeting its increased power demand by strengthening the transmission system Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year Peak load handled by the 38.27 Nov/2013 59.83 19-Nov-2024 59.83 03-Feb-2025 60.35 Sep/2025 transmission system in Comments on This indicator measures the peak load handled by the transmission system in Turkey to Turkey (Gigawatt) achieving targets reflect the transmission system's overall capacity to handle power. To assist Turkey in facilitating large-scale renewable energy generation Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year Installed wind energy 2,700.00 Dec/2013 12,102.56 19-Nov-2024 12,864 03-Feb-2025 13,000.00 Sep/2025 capacity in Turkey Comments on This indicator measures the installed wind energy capacity in Turkey. (Megawatt) achieving targets Wind energy generation in 7,810.00 Dec/2013 12,226.74 19-Nov-2024 36,800 03-Feb-2025 37,570.00 Sep/2025 Turkey (Gigawatt-hour Comments on This indicator measures the annual wind energy generation in Turkey. (GWh)) achieving targets To avoid Green House Gas (GHG) emissions from fossil fuel based power through greater integration of Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year GHG emissions avoided 0.00 Dec/2013 1,817,000.00 19-Nov-2024 1,817,000.00 03-Feb-2025 1,959,272.00 Sep/2025 annually through wind power Comments on This indicator measures the GHG emissions avoided annually through wind power plants plants connected to achieving targets connected to substations funded under the project. substations funded under the project (Tones/year) Mar 05, 2025 Page 4 of 9 The World Bank Implementation Status & Results Report Renewable Energy Integration (P144534) 6.2 Intermediate Results Indicators by Components Component-2: Smart-grid investments to strengthen grid operation and management in face of higher wind energy generation Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year Proportion of TEIAS sub- 33.00 Nov/2013 97.00 19-Nov-2024 97.00 03-Feb-2025 97.00 Sep/2025 stations that are equipped with RTUs (Percentage) Renewable Energy Resource No Nov/2013 Yes 19-Nov-2024 Yes 03-Feb-2025 Yes Sep/2025 (RER) operator desk is functional (Yes/No) Component-1: Upfront development of transmission infrastructure to facilitate faster development of WPPs Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year Wind energy capacity 0.00 Nov/2013 911.08 19-Nov-2024 911.08 03-Feb-2025 1,175.00 Sep/2025 connected to sub-stations funded under the project (Megawatt) Wind energy generated 0.00 Nov/2013 3,260.00 19-Nov-2024 3,260.00 03-Feb-2025 3,395.00 Sep/2025 from plants connected to sub-stations funded under the project (Gigawatt-hour (GWh)) CTF co-financing delivered 0.00 Nov/2013 1,340,000,000.00 19-Nov-2024 1,340,000,000.00 03-Feb-2025 2,397,500,000.00 Sep/2025 (including IBRD, TEIAS and Private WPP investment) (Amount(USD)) Mar 05, 2025 Page 5 of 9 The World Bank Implementation Status & Results Report Renewable Energy Integration (P144534) Component-3: Lapseki-Sutluce 380 kV Submarine Power Cable to better inter-connect wind energy locations with other parts of Turkey Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year Energy transferred over the 0.00 Nov/2013 4,636,604 19-Nov-2024 5,500 03-Feb-2025 4,422.00 Sep/2025 2nd Lepsuki-Sutluce submarine power cable (Gigawatt-hour (GWh)) Energy transferred over the 0.00 Nov/2019 0 05-Nov-2024 0 05-Feb-2025 7,102.00 Nov/2024 3rd Lepsuki-Sutluce submarine power cable (Gigawatt-hour (GWh)) Energy transferred over the 0.00 Nov/2019 0 05-Nov-2024 0 05-Feb-2025 4,890.00 Nov/2024 Izmit Gulf Crossing submarne power cable (Gigawatt-hour (GWh)) Percentage of grievances 80.00 Nov/2019 85 19-Nov-2024 85 03-Feb-2025 85.00 Sep/2025 recorded by the Project and Comments on No grievences were received in this period. resolved within one-month achieving targets period (Percentage) Percentage of beneficiaries 0.00 Nov/2019 0.00 19-Nov-2024 0.00 19-Nov-2024 60.00 Sep/2025 in OIZs who report that Comments on Due to COVID 19 pandemic measures, no roundtables could be conducted. annual project roundtables achieving targets are effective in obtaining and responding to their feedback. (Percentage) Deployment of at least one No Nov/2019 Yes 19-Nov-2024 Yes 03-Feb-2025 Yes Sep/2025 female controller from TEIAS in each sub-project site for civil work supervision. (Yes/No) Mar 05, 2025 Page 6 of 9 The World Bank Implementation Status & Results Report Renewable Energy Integration (P144534) Percentage of beneficiaries 0.00 Nov/2019 0.00 19-Nov-2024 0.00 03-Feb-2025 80.00 Sep/2025 in OIZs who report that the power supply has improved. (Percentage) Component-4: Strengthening of Transmission Networks to cater to growing demand and supply of electricity in Turkey Baseline Actual (Previous) Actual (Current) Closing Period Indicator Name Value Month/Year Value Date Value Date Value Month/Year Transmission lines 0.00 Nov/2013 91.50 19-Nov-2024 91.50 03-Feb-2025 152.00 Sep/2025 constructed or rehabilitated under the project (Kilometers) Transmission lines 0.00 Nov/2013 91.50 19-Nov-2024 91.50 03-Feb-2025 152.00 Sep/2025 constructed under the project (Kilometers) Transformation capacity 0.00 Nov/2013 3,900,000.00 19-Nov-2024 3,900,000.00 19-Nov-2024 6,075,000.00 Sep/2025 added under the project (Kilovolt-Amphere(KVA)) Mar 05, 2025 Page 7 of 9 The World Bank Implementation Status & Results Report Renewable Energy Integration (P144534) 7. DATA ON FINANCIAL PERFORMANCE 7.1 Cumulative Disbursements 7.2 Disbursements (by loan) Loan/Credit/TF Status Original Revised Cancelled Disbursed Undisbursed % Disbursed IBRD-90510 Effective 325.00 288.97 36.03 259.89 20.28 92.76% IBRD-83710 Closed 300.00 300.00 0.00 247.93 0.00 100.00 % TF-16958 Closed 50.00 50.00 0.00 50.00 0.00 100.00 % 7.3 Key Dates (by loan) Mar 05, 2025 Page 8 of 9 The World Bank Implementation Status & Results Report Renewable Energy Integration (P144534) Loan/Credit/TF Status Approval Signing Effectiveness Orig. Closing Rev. Closing IBRD-83710 Closed 09-May-2014 10-Jul-2014 11-Aug-2014 30-Jun-2019 31-Dec-2024 IBRD-90510 Effective 28-Feb-2020 01-Dec-2020 08-Jan-2021 31-Dec-2024 30-Sep-2025 TF-16958 Closed 09-May-2014 10-Jul-2014 11-Aug-2014 30-Jun-2019 31-Dec-2024 8. KEY DATES Key Events Planned Actual Approval 09-May-2014 09-May-2014 Effectiveness 11-Aug-2014 11-Aug-2014 Mid-Term Review No. 01 03-Nov-2014 Operation Closing/Cancellation 30-Sep-2025 9. RESTRUCTURING HISTORY Restructuring Level 2 Approved on 14-Jun-2019 Restructuring Level 2 Approved on 17-Dec-2024 10. ASSOCIATED OPERATION(S) There are no associated operations Mar 05, 2025 Page 9 of 9