I Engagements (ISAE) 3000 (Revised). That standard requires that we comply with ethical requirements and plan and perform our procedures to obtain reasonable assurance about whether, in all material respects, the Project has maintained an effective internal control over compliance with requirements that could have a direct and material financial effect on the financial statements as well as internal control over financial reporting. Our examination included obtaining an understanding, testing, and evaluating the design and operating effectiveness of the internal control, and performing other procedures as we considered necessary in the circumstances to obtain sufficient appropriate evidence to provide a basis for our opinion. Because of the inherent limitations of internal control over financial reporting, including the possibility of collusion or improper management override of controls, material misstatements due to error or fraud may occur and not to be prevented or detected on a regular basis. In addition, projections of any evaluation of the effectiveness of the internal control over financial reporting to future periods are subject to the risk that controls may become inadequate because of changes in conditions, or that the degree of compliance with the policies or procedures may deteriorate. We believe that the audit evidence we have obtained is sufficient and appropriate to provide a basis for our opinion. LI T:(84) 24 3824 1990 I F:(84) 24 3825 3973 I 1 Le Phung Hieu, Hanoi, Vietnam 14OL S AASC AUDITING FIRM 16 Auditors' opinion In our opinion, the Project has maintained an effective internal control over misstatements that could have a direct and material financial effect on the Project's Financial Statements for the fiscal year ended 31 December 2023. ited CING TY AAS Cuong Nguyen Pham Hung Deputy General Director Auditor in-charge CPA Registered No.: CPA Registered No.: 0744-2023-002-1 2893-2020-002-1 Hanoi, 20 November 2024 [1 117 aasc No.: 201124.002/BCTC.FIS2 INDEPENDENT AUDITORS' REPORT ON THE COMPLIANCE To: Long Xuyen City Urban Upgrading Project Management Unit Vietnam Scaling Up Urban Upgrading Project - Long Xuyen City Sub-project We have audited, in accordance with International Standards on Auditing, the Financial Statements of the Vietnam Scaling Up Urban Upgrading Project - Long Xuyen City Sub-project ("the Project") for the fiscal year ended 31 December 2023 and issued the auditors' report thereon dated on 20 November 2024 expressing an opinion on those Financial Statements. In connection with the audit of the Financial Statements, we also performed procedures on the Project's compliance with the Credit Number 6055 - VN and the Credit Number 6056 - VN, law and regulations that have a direct and material effect on the Project's financial statements for the fiscal year ended 31 December 2023 ("the Requirements"). Responsibilities of the Project Management Unit The Project Management Unit is responsible for complying with the Requirements applicable to the Project. Auditor's Responsibility Our responsibility is to express an opinion on the Project's compliance with the Requirements based on our procedures. We limited our tests of compliance to the Requirements, and we did not test compliance with all laws and regulations applicable to the Project. We performed our work in accordance with the International Standard on Assurance Engagements (ISAE) 3000 (Revised). That standard requires that we comply with ethical requirements and plan and perform our procedures to obtain reasonable assurance about whether, in all material respects, the Project has complied with the Requirements. An assurance engagement to report on the compliance with the Requirements at the Project involves performing procedures to obtain evidence about whether the Project's activities are free of material non-compliance with the Requirements, including obtaining an understanding of the internal control relevant to the Project's compliance with the Requirements. The procedures selected depend on the auditors' judgment, including the assessment of risks that the Project does not comply with the Requirements and whether such non-compliance could have a direct and material financial effect on the Project's financial statements. Our procedures included testing the compliance with the Requirements we consider necessary to provide a reasonable assurance that the Requirements are complied by the Project. We believe that the audit evidence we have obtained is sufficient and appropriate to provide a basis for our opinion. T:(84) 24 3824 1990 I F:(84) 24 3825 3973 I 1 Le Phung Hieu, Hanoi, Vietnam AASCAUDITING FIRM 18 Auditors' opinion In our opinion, the Project has complied with the Requirements that could have a direct and material financial effect on the Project's Financial Statements for the fiscal year ended 31 December 2023. o -ited C ONG TY IACH tHNHIEM HiUI UI *HANG KIEM TO I AASC DoIa ong Nguyen Pham Hung , -eneral Director Auditor in-charge Registered No.: CPA Registered No.: 0744-2023-002-1 2893-2020-002-1 Hanoi, 20 November 2024 19 119