PROCUREMENT PLAN (Textual Part) Project information: Burkina Faso-Solar Energy and Access Project- P166785 Project Implementation agency: Ministry of Energy, Mines and Quarries Date of the Procurement Plan: March 21, 2023 Period covered by this Procurement Plan: April 2023-December 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Law No. 039/2016/AN of 2 December 2016 "on the General regulation of public procurement" and its implementing texts including Decree 2017-0049/PRES/PM/MINEFID of 1 February 2017 regulating public procurement and delegation of public services, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Depending on the evolution of the security situation in the country, the PPSD could be updated for efficient market procurement management. PROCUREMENT Burkina Faso : Solar Energy and Access Project PLAN General Information Country: Burkina Faso 2023-03-21 Bank’s Approval Date of the Original Procurement Plan: 2025-02-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166785 GPN Date: 2023-03-08 Project Name: Solar Energy and Access Project Loan / Credit No: TF / B5744, TF / B5738, IDA / 69190 Coordination Unit of Solar Energy and Access Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BF-UGP/SOLEER -398328-CW -RFB / Travaux de Constructi Component 2: Utility-Scale S Request for Bids - Open - Internationa Single Stage - Two E 17,000,000.0 2024-11-2 on du raccordement en 225 k TF / B5744 olar with Storage and VRE In Prior Request for Bids Plant SPD (withou 0.00 Signed 2023-12-28 2024-01-16 2024-01-02 2024-03-20 2024-02-13 2024-04-12 2024-04-27 2024-09-10 2024-06-01 2024-11-15 l nvelope 0 8 V (opéré en 90 kV) de la cent tegration t prequalification) rale solaire de Konéan au pos te existant de Kaya BF-UGP/SOLEER -398533-CW -RFB / Travaux de Constructi Component 2: Utility-Scale S Request for Bids - on du raccordement en 132 k Open - Internationa Single Stage - Two E 18,800,000.0 2024-11-2 TF / B5744 olar with Storage and VRE In Prior Request for Bids Plant SPD (withou 0.00 Signed 2023-12-29 2024-01-16 2024-01-03 2024-03-20 2024-02-14 2024-04-12 2024-04-28 2024-09-10 2024-06-02 2024-11-15 V de la centrale solaire de Ko l nvelope 0 9 tegration t prequalification) uritenga à la ligne 132 kV exi stante entre Zano et Koupèla BF-UGP/SOLEER -398536-CW Component 2: Utility-Scale S Request for Bids - Open - Internationa Single Stage - Two E 20,000,000.0 Under Imple 2024-11-2 -RFB / Travaux de renforcem TF / B5744 olar with Storage and VRE In Prior Request for Bids Plant SPD (withou 0.00 2023-12-29 2024-01-16 2024-01-03 2024-03-20 2024-02-14 2024-04-12 2024-04-28 2025-01-07 2024-06-02 l nvelope 0 mentation 9 ents sur le réseau national in tegration t prequalification) terconnecté (RNI) BF-UGP/SOLEER -419783-CW Request for Bids - -RFB / Travaux de constructio Component 2: Utility-Scale S Open - Internationa Single Stage - Two E Works (without pr 18,000,000.0 Under Imple 2026-05-0 n des Unités de stockage d'é TF / B5744 olar with Storage and VRE In Prior Request for Bids 0.00 2024-05-15 2024-12-11 2024-05-15 2024-07-24 2024-10-06 2024-11-10 l nvelope equalification) SP 0 mentation 4 nergie par batteries au poste tegration D source de Zagtouli d'une puis sance de 28 MWe BF-UGP/SOLEER -445879-CW -RFB / Travaux de renforcem Component 2: Utility-Scale S Request for Bids - Open - Internationa Single Stage - Two E Under Imple 2025-08-0 ent du système de télécomm TF / B5744 olar with Storage and VRE In Post Request for Bids Plant SPD (withou 2,000,000.00 0.00 2024-09-06 2024-10-08 2024-09-11 2024-10-08 2024-10-23 2025-01-05 2025-02-09 l nvelope mentation 8 unication du Réseau National tegration t prequalification) International (TELECOM) BF-UGP/SOLEER -451807-CW Component 2: Utility-Scale S Request for Bids - -RFB / Travaux de renforcem Open - Internationa Single Stage - Two E 20,000,000.0 Under Revie 2026-01-2 TF / B5744 olar with Storage and VRE In Prior Request for Bids Plant SPD (withou 0.00 2025-02-20 2025-02-25 2025-04-08 2025-06-21 2025-07-26 ent des postes et lignes du R l nvelope 0 w 2 tegration t prequalification) éseau National Interconnecté (RNI) en trois lots GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-UGP/SOLEER -352978-GO -RFQ / Acquisition de matérie Component 3: Private Sector Request for Quota Single Stage - One E l et équipement de Visio conf TF / B5744 Mobilization for Large-Scale Post Limited 29,412.00 0.00 Signed 2023-04-25 2023-05-18 2023-06-20 2023-08-24 2023-12-17 tions nvelope érence et vidéo surveillance Solar au profit de l'UGP SOLEER BF-UGP/SOLEER -352985-GO Component 3: Private Sector Request for Quota Single Stage - One E -RFQ / Acquisition de matérie TF / B5744 Mobilization for Large-Scale Post Limited 9,191.00 0.00 Signed 2023-04-25 2023-05-18 2023-06-20 2023-06-26 2023-12-17 tions nvelope l électroménager et équipem Solar ents divers BF-UGP/SOLEER -352990-GO -RFQ / Acquisition de fournitu Component 3: Private Sector Request for Quota Single Stage - One E res de bureau, de consomma TF / B5744 Mobilization for Large-Scale Post Limited 11,029.00 0.00 Signed 2023-04-24 2023-05-18 2023-06-19 2023-08-23 2023-12-16 tions nvelope bles informatiques et de prod Solar uits d'entretien au profit de l' UGP SOLEER BF-UGP/SOLEER -352995-GO Component 3: Private Sector Request for Quota Single Stage - One E -RFQ / Acquisition de matérie TF / B5744 Mobilization for Large-Scale Post Limited 386,029.00 0.00 Signed 2023-04-23 2023-05-18 2023-06-18 2023-08-31 2023-12-15 tions nvelope l roulant au profit de l'UGP S Solar OLEER BF-UGP/SOLEER -352997-GO Component 3: Private Sector -RFQ / Acquisition de matérie Request for Quota Single Stage - One E TF / B5744 Mobilization for Large-Scale Post Limited 58,824.00 0.00 Signed 2023-04-23 2023-05-18 2023-06-18 2023-08-14 2023-12-15 l et mobilier de bureau au pr tions nvelope Solar ofit de l'UGP SOLEER BF-UGP/SOLEER -353004-GO Component 3: Private Sector -RFQ / Acquisition de matérie Request for Quota Single Stage - One E TF / B5744 Mobilization for Large-Scale Post Limited 91,912.00 0.00 Completed 2023-05-22 2023-05-18 2023-07-17 2023-10-26 2024-01-13 2024-01-18 l et équipement informatique tions nvelope Solar au profit de l'UGP SOLEER BF-UGP/SOLEER -419769-GO Component 3: Private Sector Request for Quota Single Stage - One E Pending Impl -RFQ / Acquisition d'un group TF / B5744 Mobilization for Large-Scale Post Limited - National 83,333.00 0.00 2024-04-25 2024-06-20 2024-07-19 tions nvelope ementation e électrogène au profit de l'U Solar GP SOLEER BF-UGP/SOLEER -419777-GO -RFQ / Acquisition de matérie Component 1: Sustainable R Request for Quota Single Stage - One E l et équipement informatique IDA / 69190 Post Limited - National 174,433.00 0.00 Signed 2024-04-26 2024-08-06 2024-06-21 2024-09-24 2024-07-22 ural Electrification tions nvelope au profit de l'ABER, de la SO NABEL et de l'UGP SOLEER BF-UGP/SOLEER -419778-GO -RFQ / Acquisition de matérie Component 1: Sustainable R Request for Quota Single Stage - One E IDA / 69190 Post Limited - National 500,000.00 0.00 Signed 2024-04-28 2024-08-06 2024-06-21 2024-09-12 2024-07-22 l roulant au profit de l'ABER, l ural Electrification tions nvelope a SONABEL et l'UGP SOLEER BF-UGP/SOLEER -419776-GO -RFQ / Acquisition de matérie ls et fournitures de bureau, Component 1: Sustainable R Request for Quota Single Stage - One E IDA / 69190 Post Limited - National 200,000.00 0.00 Signed 2024-06-02 2024-08-06 2024-07-28 2024-09-23 2025-01-24 de consommables informatiq ural Electrification tions nvelope ues au profit de l'ABER, de la SONABEL, de l'UGP SOLEER e t du MEMC Page 1 BF-UGP/SOLEER -419774-GO -RFQ / Acquisition de mobilier Component 1: Sustainable R Request for Quota Single Stage - One E Pending Impl s de bureau au profit de l'AB IDA / 69190 Post Limited - National 200,000.00 0.00 2024-09-21 2024-11-16 2025-05-15 ural Electrification tions nvelope ementation ER, de la SONABEL, du Minist ère en charge de l'énergie et de l'UGP SOLEER BF-UGP/SOLEER -419772-GO -RFQ / Acquisition d’équipem ents de collecte de données Component 3: Private Sector du Projet SOLEER (Tablettes, Request for Quota Single Stage - One E TF / B5744 Mobilization for Large-Scale Post Limited - National 45,834.00 0.00 Signed 2024-09-30 2024-09-11 2024-11-25 2024-10-21 2025-05-24 Dictaphone, Multi paramètre, tions nvelope Solar PH/MV) pour le suivi numériq ue des PGES, PAR, cartograp hie des prestataires VBG/EAS /HS et la mise en œuvre du G EMS BF-UGP/SOLEER -436233-GO Component 3: Private Sector -RFQ / Acquisition d'équipem Request for Quota Single Stage - One E Pending Impl TF / B5744 Mobilization for Large-Scale Post Limited - National 25,000.00 0.00 2024-10-05 2024-11-30 2025-05-29 ents de protection individuel tions nvelope ementation Solar (EPI) au profit de l'UGP SOLE ER NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-UGP/SOLEER -347820-NC -RFQ / Acquisition, installatio Component 3: Private Sector Request for Quota Single Stage - One E n, formation des utilisateurs TF / B5744 Mobilization for Large-Scale Post Limited 64,338.00 0.00 Completed 2023-03-25 2023-03-31 2023-05-20 2023-10-23 2023-11-16 2024-01-15 tions nvelope du logiciel de gestion financi Solar ère et comptable (TOM 2 PR O) de l'UGP SOLEER BF-UGP/SOLEER -352969-NC -RFQ / Recrutement d'une ag Component 3: Private Sector Request for Quota Single Stage - One E ence chargée des prestations TF / B5744 Mobilization for Large-Scale Post Limited 47,794.00 0.00 Completed 2023-04-26 2023-05-18 2023-06-21 2023-06-26 2023-12-18 2023-12-31 tions nvelope de service d'assurance mala Solar die au profit du personnel de l'UGP SOLEER BF-UGP/SOLEER -445887-NC -RFQ / Recrutement d'une ag Component 1: Sustainable R Request for Quota Single Stage - One E Pending Impl ence pour la réalisation de la TF / B5744 Post Limited - National 166,667.00 0.00 2024-09-21 2024-11-16 2025-05-15 ural Electrification tions nvelope ementation stratégie de communication dans le cadre de la mise en œuvre du Projet SOLEER CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-UGP/SOLEER -352962-CS- LCS / Recrutement d'un cabi Component 3: Private Sector Least Cost Selecti net chargé de l'audit des co TF / B5744 Mobilization for Large-Scale Post Open - National 50,000.00 0.00 Signed 2023-04-27 2023-08-22 2023-05-18 2023-09-06 2023-07-01 2023-10-27 2023-07-29 2024-02-05 2023-08-28 2024-02-08 2023-10-02 2024-04-03 2023-11-06 2024-05-27 2024-05-04 on mptes du projet SOLEER pou Solar r les exercices 2023, 2024 et 2025 BF-UGP/SOLEER -352963-CS- Component 3: Private Sector CQS / Recrutement d'un cabi Consultant Qualifi TF / B5744 Mobilization for Large-Scale Post Limited 18,382.00 0.00 Signed 2023-04-24 2023-09-06 2023-05-08 2023-09-15 2023-06-07 2023-09-15 2023-07-12 2023-10-20 2024-01-08 net en charge du recrutemen cation Selection Solar t du personnel complémentai re de l'UGP BF-UGP/SOLEER -364659-CS- QCBS / Recrutement de l’ing énieur conseil chargé du cont Component 2: Utility-Scale S rôle et de la supervision des t Quality And Cost- Open - Internationa TF / B5744 olar with Storage and VRE In Post 800,000.00 0.00 Canceled 2023-06-30 2023-06-08 2023-07-21 2023-08-30 2023-09-03 2023-10-27 2023-10-01 2023-10-31 2023-12-05 2024-01-09 2025-01-08 ravaux dans le cadre de la co Based Selection l tegration nstruction des infrastructures d’évacuation de la productio n d’énergie des parcs solaire s régionaux au Burkina Faso. BF-UGP/SOLEER -383795-CS- CQS / Recrutement d’un bure au d’études pour l’élaboratio Component 2: Utility-Scale S n de notice d’impact environ Consultant Qualifi TF / B5744 olar with Storage and VRE In Post Limited 91,912.00 0.00 Signed 2023-10-10 2023-10-10 2023-10-24 2024-02-12 2023-11-23 2024-02-28 2023-12-28 2024-06-14 2024-06-25 nemental et social (NIES) et cation Selection tegration du plan d’action de réinstalla tion (PAR) d’un ouvrage de re nforcement du réseau nation al interconnecte du Burkina F aso BF-UGP/SOLEER -384010-CS- CQS / Recrutement d’un cabi net pour l’élaboration du pla Component 1: Sustainable R Consultant Qualifi Under Implement n de renforcement des capac IDA / 69190 Post Limited 55,147.00 0.00 2023-10-13 2024-01-09 2023-10-27 2023-11-26 2023-12-31 2024-06-28 ural Electrification cation Selection ation ités de l’Agence burkinabè d e l’électrification rurale (ABE R) et des délégataires de ser vices d'électrification rurale BF-UGP/SOLEER -384008-CS- QCBS / Recrutement de bure aux d’études pour la réalisati Component 1: Sustainable R Consultant Qualifi on d’une étude technique (A IDA / 69190 Post Limited 317,096.00 0.00 Signed 2023-11-10 2024-01-09 2023-11-24 2024-01-15 2023-12-24 2024-03-04 2024-01-28 2024-06-25 2024-07-26 ural Electrification cation Selection PS – APD – DAO) pour l’exten sion du réseau MT pour l’élec trification rurale de 115 nouv elles localités BF-UGP/SOLEER -384009-CS- QCBS / Recrutement de bure aux pour la réalisation d’une Component 1: Sustainable R Consultant Qualifi étude technique (APS – APD – IDA / 69190 Post Limited 228,860.00 0.00 Signed 2023-11-10 2024-01-05 2023-11-24 2024-01-24 2023-12-24 2024-03-04 2024-01-28 2024-06-05 2024-07-26 ural Electrification cation Selection DAO) pour la réhabilitation et la densification des réseaux de distribution électrique de 110 localités rurales BF-UGP/SOLEER -392595-CS- QCBS / Recrutement d’un ca binet d’ingénieur conseil cha Component 2: Utility-Scale S rgé du contrôle et de la supe Quality And Cost- Open - Internationa TF / B5744 olar with Storage and VRE In Prior 5,300,000.00 0.00 Signed 2023-11-14 2023-11-15 2023-11-14 2023-11-15 2023-11-28 2023-11-28 2023-12-26 2024-02-21 2024-01-25 2024-06-18 2024-02-29 2024-08-08 2024-04-04 2024-10-17 2025-04-04 rvision des travaux dans le c Based Selection l tegration adre de la construction des i nfrastructures d’évacuation d e la production d’énergie des centrales du PSVR au Burkina Faso. Page 2 BF-UGP/SOLEER -419636-CS- QCBS / Recrutement d'un co Component 1: Sustainable R Quality And Cost- Open - Internationa Under Implement nsultant pour la supervision IDA / 69190 Post 1,500,000.00 0.00 2024-05-19 2024-11-11 2024-06-09 2025-01-08 2024-07-23 2024-08-20 2024-09-19 2024-10-24 2024-11-28 2025-11-28 ural Electrification Based Selection l ation et le suivi contrôle des trava ux d'extension du réseau BF-UGP/SOLEER -419767-CS- CQS / Recrutement d'un cons ultant en vue de l’élaboration Component 1: Sustainable R Consultant Qualifi Under Implement IDA / 69190 Post Limited - National 50,000.00 0.00 2024-05-15 2024-07-23 2024-05-29 2024-06-28 2024-08-02 2025-01-29 d’un plan stratégique de pro ural Electrification cation Selection ation motion de l’énergie productiv e et d’un plan d’assistance te chnique aux femmes BF-UGP/SOLEER -419639-CS- QCBS / Recrutement d'un co Component 1: Sustainable R Quality And Cost- Open - Internationa Under Implement nsultant pour la supervision IDA / 69190 Post 750,000.00 0.00 2024-06-20 2024-11-11 2024-07-11 2025-01-06 2024-08-24 2024-09-21 2024-10-21 2024-11-25 2024-12-30 2025-12-30 ural Electrification Based Selection l ation et le suivi contrôle des trava ux de densification et de renf orcement du réseau BF-UGP/SOLEER -436164-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati on d’une NIES et d’un (01) PA Component 1: Sustainable R Consultant Qualifi Under Implement R des activités d’extension d IDA / 69190 Post Open - National 65,000.00 0.00 2024-07-25 2024-07-18 2024-08-15 2024-09-28 2024-10-28 2024-12-02 2025-05-31 ural Electrification cation Selection ation u Réseau National Interconne cté dans treize (13) localités des régions de la Boucle du Mouhoun, des Cascades et d es Hauts Bassins (Lot 1) BF-UGP/SOLEER -436170-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati on d’une NIES et d’un (01) PA Component 1: Sustainable R Consultant Qualifi Under Implement IDA / 69190 Post Open - National 125,000.00 0.00 2024-07-25 2024-07-18 2024-08-15 2024-09-28 2024-10-28 2024-12-02 2025-05-31 R des activités d’extension d ural Electrification cation Selection ation u Réseau National Interconne cté dans vingt-cinq (25) local ités dans la région du Centre Est (Lot 2) BF-UGP/SOLEER -436191-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati on d’une NIES et d’un (01) PA Component 1: Sustainable R Consultant Qualifi Under Implement IDA / 69190 Post Open - National 110,000.00 0.00 2024-07-25 2024-07-18 2024-08-15 2024-09-28 2024-10-28 2024-12-02 2025-05-31 R) des activités d’extension d ural Electrification cation Selection ation u Réseau National Interconne cté dans vingt-deux (22) loca lités dans la région du Centre Ouest (Lot 3) BF-UGP/SOLEER -436193-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati on d’une NIES et d’un (01) PA Component 1: Sustainable R Consultant Qualifi Under Implement IDA / 69190 Post Open - National 70,000.00 0.00 2024-07-25 2024-07-18 2024-08-15 2024-09-28 2024-10-28 2024-12-02 2025-05-31 R des activités d’extension d ural Electrification cation Selection ation u Réseau National Interconne cté dans quatorze (14) localit és dans les régions du Centr e et du Plateau Central (Lot 4 ). BF-UGP/SOLEER -436197-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati on d’une NIES et d’un (01) PA Component 1: Sustainable R Consultant Qualifi Under Implement IDA / 69190 Post Open - National 40,000.00 0.00 2024-07-25 2024-07-18 2024-08-15 2024-09-28 2024-10-28 2024-12-02 2025-05-31 R des activités d’extension d ural Electrification cation Selection ation u Réseau National Interconne cté dans huit (08) localités d ans les régions du Nord et du Centre Nord (Lot 5) BF-UGP/SOLEER -436203-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati Component 1: Sustainable R Consultant Qualifi Under Implement on d’une NIES et d’un (01) PA IDA / 69190 Post Open - National 60,000.00 0.00 2024-07-25 2024-07-18 2024-08-15 2024-09-28 2024-10-28 2024-12-02 2025-05-31 ural Electrification cation Selection ation R des activités d’extension d u Réseau National Interconne cté dans douze (12) localités dans la région du Centre Sud (Lot 6) BF-UGP/SOLEER -436204-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati Component 1: Sustainable R Consultant Qualifi Under Implement on d’une NIES et d’un (01) PA IDA / 69190 Post Open - National 40,000.00 0.00 2024-07-25 2024-07-18 2024-08-15 2024-09-28 2024-10-28 2024-12-02 2025-05-31 ural Electrification cation Selection ation R des activités d’extension d u Réseau National Interconne cté dans huit (08) localités d ans la région de l’Est (Lot 7) BF-UGP/SOLEER -436208-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati Component 1: Sustainable R Consultant Qualifi Under Implement on d’une NIES et d’un (01) PA IDA / 69190 Post Open - National 60,000.00 0.00 2024-07-25 2024-07-18 2024-08-15 2024-09-28 2024-10-28 2024-12-02 2025-05-31 ural Electrification cation Selection ation R des activités d’extension d u Réseau National Interconne cté dans douze (12) localités dans la région du Sud Ouest (Lot 8) BF-UGP/SOLEER -436213-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati on d’une NIES et d’un (01) PA Component 1: Sustainable R Consultant Qualifi Under Implement IDA / 69190 Post Open - National 85,000.00 0.00 2024-07-29 2024-07-19 2024-08-19 2024-10-02 2024-11-01 2024-12-06 2025-06-04 R des activités de densificati ural Electrification cation Selection ation on du Réseau National Interc onnecté dans dix-sept (17) lo calités de la région du Centre Ouest (Lot 1) BF-UGP/SOLEER -436220-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati on d’une NIES et d’un (01) PA Component 1: Sustainable R Consultant Qualifi Under Implement IDA / 69190 Post Open - National 70,000.00 0.00 2024-07-29 2024-07-19 2024-08-19 2024-10-02 2024-11-01 2024-12-06 2025-06-04 R des activités de densificati ural Electrification cation Selection ation on du Réseau National Interc onnecté dans quatorze (14) l ocalités dans les régions de l’ Est et du Centre Est (Lot 2) BF-UGP/SOLEER -436221-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati on d’une NIES et d’un (01) PA Component 1: Sustainable R Consultant Qualifi Under Implement IDA / 69190 Post Open - National 110,000.00 0.00 2024-07-29 2024-07-19 2024-08-19 2024-10-02 2024-11-01 2024-12-06 2025-06-04 R des activités de densificati ural Electrification cation Selection ation on du Réseau National Interc onnecté dans vingt-deux (22) localités dans les régions du Nord et du Centre-Nord (Lot 3) Page 3 BF-UGP/SOLEER -436224-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati on d’une NIES et d’un (01) PA Component 1: Sustainable R Consultant Qualifi Under Implement IDA / 69190 Post Open - National 100,000.00 0.00 2024-07-29 2024-07-19 2024-08-19 2024-10-02 2024-11-01 2024-12-06 2025-06-04 R des activités de densificati ural Electrification cation Selection ation on du Réseau National Interc onnecté dans vingt (20) local ités dans la région du Centre- Sud (Lot 4) BF-UGP/SOLEER -436225-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati on d’une NIES et d’un PAR de Component 1: Sustainable R Consultant Qualifi Under Implement s activités de densification d IDA / 69190 Post Open - National 110,000.00 0.00 2024-07-29 2024-07-19 2024-08-19 2024-10-02 2024-11-01 2024-12-06 2025-06-04 ural Electrification cation Selection ation u Réseau National Interconne cte dans vingt-deux (22) loca lités dans les régions du Sud- Ouest, Cascades, Hauts Bassi ns et Boucle du Mouhoun BF-UGP/SOLEER -436226-CS- CQS / Recrutement d’un cons ultant (firme) pour la réalisati on d’une NIES et d’un PAR de Component 1: Sustainable R Consultant Qualifi Under Implement IDA / 69190 Post Open - National 125,000.00 0.00 2024-07-29 2024-07-19 2024-08-19 2024-10-02 2024-11-01 2024-12-06 2025-06-04 s activités de densification d ural Electrification cation Selection ation u Réseau National Interconne cte dans vingt-cinq (25) local ités dans les régions du Plate au Central et du Centre Est ( Lot 6) BF-UGP/SOLEER -445881-CS- CQS / Recrutement d'un cons Component 1: Sustainable R Consultant Qualifi Under Implement ultant pour la réalisation d'un TF / B5744 Post Limited - National 50,000.00 0.00 2024-09-10 2024-09-23 2024-09-24 2024-10-24 2024-11-28 2025-05-27 ural Electrification cation Selection ation e Evaluation des risques sécu ritaires (ERS) assortis d'un pl an d'actions BF-UGP/SOLEER -445888-CS- CQS / Recrutement d'un cons ultant pour la réalisation de l' Component 2: Utility-Scale S Consultant Qualifi Under Implement audit de mise en œuvre des TF / B5744 olar with Storage and VRE In Post Limited - National 33,334.00 0.00 2024-10-15 2024-09-23 2024-10-29 2024-11-28 2025-01-02 2025-07-01 cation Selection ation PAR pour les sites des central tegration es et des couloirs de ligne de s centrales solaires de Kaya et du Kouritenga BF-UGP/SOLEER -445889-CS- CQS / Recrutement d'un cons Component 2: Utility-Scale S Consultant Qualifi Under Implement ultant pour la réalisation d'un TF / B5744 olar with Storage and VRE In Post Limited - National 83,334.00 0.00 2024-10-25 2025-01-17 2024-11-08 2024-12-08 2025-01-12 2025-07-11 cation Selection ation e NIES et d''un PAR pour le tr tegration acé de ligne Ouaga 1 et Oua ga 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-UGP/SOLEER -360611-CS- CDS / Recrutement d'un Con Component 3: Private Sector seil en transaction pour orga Direct - Internation TF / B5738 Mobilization for Large-Scale Prior Direct Selection 1,665,000.00 0.00 Under Review 2023-05-22 2023-07-06 2023-06-01 2023-05-06 2023-08-05 2023-11-06 2024-02-01 niser une enchère (phase 2) al Solar dans le cadre du Parc Solaire à Vocation Régionale au Burk ina Faso BF-UGP/SOLEER -419628-CS- CDS / Recrutement du consor tium VIDA.place GmbH (« VI DA ») et Odyssey Energy Sol Component 1: Sustainable R Direct - Internation utions (« Odyssey ») pour le IDA / 69190 Post Direct Selection 325,000.00 0.00 Under Review 2024-05-19 2024-05-10 2024-05-29 2024-08-02 2025-01-29 ural Electrification al Développement d'une platef orme SIG dans le cadre de l'é lectrification rurale hors rése au par des systèmes solaires photovoltaïques BF-UGP/SOLEER -476743-CS- INDV / Recrutement d’un (e) Component 2: Utility-Scale S consultant (e) pour l’élaborat Individual Consult Pending Impleme TF / B5744 olar with Storage and VRE In Post Limited - National 35,000.00 0.00 2025-03-05 2025-03-10 2025-03-31 2025-05-05 2025-11-01 ion de la Notice d’impact Env ant Selection ntation tegration ironnemental et Social (NIES) du Centre National de TELEC ONDUITE (CNC) de Zagtouli Page 4