PROCUREMENT PLAN (Textual Part) Project information: DRC Kananga Emergency Urban Resilience Project (P179292) Project Implementation agency: MINISTÈRE DE L'URBANISME ET DE L'HABITAT Date of the Procurement Plan: July 20th, 2023 Period covered by this Procurement Plan: July 2023 – July 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information. “There is no further relevant procurement information”. PROCUREMENT Congo, Democratic Republic of : Kananga Emergency Urban Resilience Project PLAN General Information Country: Congo, Democratic Republic of 2023-07-21 Bank’s Approval Date of the Original Procurement Plan: 2025-02-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P179292 GPN Date: Project Name: Kananga Emergency Urban Resilience Project Loan / Credit No: IDA / 72160 Ministère de l'Urbanisme et de l'Habitat Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-PURUK-404333-CW-RFB / Travaux de construction des Demande d'offres Micropieux dans le cadre des Component 1: Emergency R Single Stage - One E - DTPM Travaux (s 2024-12-1 IDA / 72160 A posteriori Appel d'offres Open - National 2,000,000.00 0.00 Annulé 2024-03-01 2024-03-06 2024-04-17 2024-05-17 2024-06-21 travaux d'urgence de lutte a esponse Interventions nvelope ans préqualificati 8 ntiérosive dans la ville de Ka on) nanga (Sites érosifs de PK 70 6 et SNCC) Demande de cota ZR-PURUK-426215-CW-RFQ / tions - DTPM Petit Travaux conservatoires de lu Component 1: Emergency R Single Stage - One E 2025-02-2 IDA / 72160 A priori Demande de prix Limited - National s travaux (urgenc 5,000,000.00 0.00 Annulé 2024-07-06 2024-08-31 tte antiérosive sur les 21 site esponse Interventions nvelope 7 e) - Avec compéti s additionnels dans la ville de tion Kananga ZR-PURUK-426216-CW-DIR / Demande de cota Travaux de réhabilitation et tions - DTPM Petit Component 2: Integrated Re Passation de marc 10,000,000.0 2025-02-0 de modernisation de la route IDA / 72160 A priori Direct - National s travaux (urgenc 0.00 Annulé 2024-07-01 2024-07-06 2024-08-10 silient Urban Development hé de gré à gré 0 6 nationale (RN) 41 (marché pa e) - Sans compétit r ED avec le Groupement CEJ ion IC/GHE) ZR-PURUK-426214-CW-RFQ / Demande de cota Travaux de sauvegarde de lu tions - DTPM Petit tte antiérosive sur les 3 sites Component 1: Emergency R Single Stage - One E 2025-11-0 IDA / 72160 A priori Demande de prix Limited - National s travaux (urgenc 7,000,000.00 0.00 Annulé 2024-09-14 2024-11-09 prioritaires (SNCC, MONUSCO esponse Interventions nvelope 4 e) - Avec compéti et PK 706) y compris la paus tion e des micropieux dans la vill e de Kananga ZR-PURUK-447114-CW-RFQ / Travaux de réhabilitation et Demande de cota modernisation de la Route N tions - DTPM Petit ationale (RN) 41 dans sa trav Component 2: Integrated Re Single Stage - One E 10,000,000.0 En attente d 2025-05-1 IDA / 72160 A priori Demande de prix Limited - National s travaux (urgenc 0.00 2024-09-21 2024-11-16 ersée de la ville de Kananga, silient Urban Development nvelope 0 'exécution 5 e) - Avec compéti comprenant la boucle de la c tion ommune de Ndesha et de la commune de Lukonga (7,5 k m), assortie de 96 amorces ( 1,50 km) ZR-PURUK-454998-CW-DIR / Travaux d’entretien de lutte Demande de cota antiérosive sur les trois (3) si tions - DTPM Petit Component 1: Emergency R Passation de marc 2025-05-2 tes prioritaires dans la ville d IDA / 72160 A posteriori Direct - National s travaux (urgenc 86,935.00 0.00 Annulé 2024-10-15 2024-10-15 2024-10-20 2024-11-24 esponse Interventions hé de gré à gré 3 e Kananga (sites : SNCC, PK e) - Sans compétit 706 et MONUSCO) - En Lot U ion nique (Marché par Entente Di recte avec l’ONG ORS) ZR-PURUK-462142-CW-DIR / Travaux urgents de sauvegar Demande de cota de de lutte antiérosive sur le tions - DTPM Petit s 3 sites prioritaires (SNCC, Component 1: Emergency R Passation de marc En cours d'e 2025-07-0 IDA / 72160 A priori Direct - National s travaux (urgenc 7,000,000.00 0.00 2024-11-30 2024-12-05 2025-01-09 MONUSCO et PK 706) y comp esponse Interventions hé de gré à gré xécution 8 e) - Sans compétit ris la pause des micropieux d ion ans la ville de Kananga (Marc hé par Entente Directe avec l 'Entreprise ARAB CONTRACT OR) ZR-PURUK-462143-CW-DIR / Travaux urgents conservatoir Demande de cota es de lutte antiérosive sur cin tions - DTPM Petit q (5) sites et comprenant les Component 1: Emergency R Passation de marc En cours d'e 2025-07-0 IDA / 72160 A posteriori Direct - National s travaux (urgenc 1,700,000.00 0.00 2024-11-30 2024-11-13 2024-12-05 2024-12-11 2025-01-09 travaux confortatifs d’assaini esponse Interventions hé de gré à gré xécution 8 e) - Sans compétit ssement dans l’enceinte de l’ ion Athénée Royale de Kananga (Marché par Entente Directe avec l'Entreprise SAFRIMEX) ZR-PURUK-463856-CW-RFB / Demande d'offres Travaux définitifs de lutte ant Component 2: Integrated Re Open - Internationa Single Stage - Two E - DTPM Petits trav 45,000,000.0 En attente d 2026-01-3 iérosive sur vingt et un (21) s IDA / 72160 A priori Appel d'offres 0.00 2025-02-28 2025-03-05 2025-04-16 2025-06-29 2025-08-03 silient Urban Development l nvelope aux (processus à 0 'exécution 0 ites érosifs dans la ville de K deux enveloppes) ananga en quatre (04) Lots. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PURUK-369603-GO-RFQ / Acquisition des outillages (pe tits matériels) et des équipe ments de protection individu Component 1: Emergency R Single Stage - One E IDA / 72160 A posteriori Demande de prix Open - National 110,639.00 0.00 Signé 2023-07-22 2023-09-16 2023-09-14 2024-03-14 elle (EPI) dans le cadre des tr esponse Interventions nvelope avaux d'urgence de lutte anti érosive dans la ville de Kana nga (sites SNCC, PK 706 et M ONUSCO) ZR-PURUK-369605-GO-RFQ / Fourniture des matériaux de Carrière (Moellon, Sable, etc. Component 1: Emergency R Single Stage - One E IDA / 72160 A posteriori Demande de prix Open - National 393,590.00 0.00 Signé 2023-07-22 2023-09-16 2023-09-18 2024-03-14 ) pour les travaux d'urgence esponse Interventions nvelope de lutte antiérosive dans la vi lle de Kananga (sites SNCC; P K 706 et MONUSCO) ZR-PURUK-370072-GO-RFQ / Acquisition des matériaux de quincaillerie (clous, fer à bét Component 1: Emergency R Single Stage - One E on, tuyau, etc.) pour les trav IDA / 72160 A posteriori Demande de prix Open - National 1,651,450.00 0.00 Signé 2023-07-22 2023-09-16 2023-09-14 2024-03-14 esponse Interventions nvelope aux d'urgence de lutte antiér osive dans la ville de Kanang a (sites SNCC, PK 706 et MO NUSCO) Page 1 ZR-PURUK-370073-GO-RFQ / Acquisition des matériaux de construction Ex-Marché (Bois Component 1: Emergency R Single Stage - One E de coffrage, stick de bois, etc IDA / 72160 A posteriori Demande de prix Open - National 109,220.00 0.00 Signé 2023-07-22 2023-09-16 2023-09-14 2024-03-14 esponse Interventions nvelope .) pour les travaux d'urgence de lutte antiérosive dans la vi lle de Kananga (sites : SNCC, PK 706 et MONUSCO) ZR-PURUK-370077-GO-RFQ / Fourniture en Ciment (matéri aux de construction Ex-Usine Component 1: Emergency R Single Stage - One E IDA / 72160 A posteriori Demande de prix Open - National 918,541.00 0.00 Signé 2023-07-22 2023-09-16 2023-09-14 2024-03-14 ) pour les travaux d'urgence esponse Interventions nvelope de lutte antiérosive dans la vi lle de Kananga (sites : SNCC, PK 706 et MONUSCO) ZR-PURUK-370078-GO-RFQ / Acquisition de Cage Gabion p Component 1: Emergency R Single Stage - One E En cours d'ex our les travaux d'urgence de IDA / 72160 A posteriori Demande de prix Open - National 468,750.00 0.00 2023-07-22 2023-09-16 2024-03-14 esponse Interventions nvelope écution lutte antiérosive dans la ville de Kananga (sites SNCC, PK 706 et MONUSCO) ZR-PURUK-370079-GO-RFQ / Acquisition des équipements et matériels informatiques de Component 1: Emergency R Single Stage - One E la base vie pour les travaux d IDA / 72160 A posteriori Demande de prix Limited 17,098.00 0.00 Annulé 2023-08-12 2023-10-07 2024-04-04 esponse Interventions nvelope 'urgence de lutte antiérosive dans la ville de Kananga (site s SNCC, PK 706 et MONUSCO ) ZR-PURUK-370086-GO-RFQ / Fourniture en carburant pour Component 1: Emergency R Single Stage - One E les travaux d'urgence de lutt IDA / 72160 A posteriori Demande de prix Open - National 834,240.00 0.00 Annulé 2023-07-22 2023-09-16 2024-03-14 esponse Interventions nvelope e antiérosive dans la ville de Kananga (sites SNCC, PK 706 et MONUSCO) ZR-PURUK-370143-GO-RFQ / Acquisition des équipements et Matériels Techniques (Top ographie, Géomatique, Hydro Component 1: Emergency R Single Stage - One E logique, Hydraulique, Géologi IDA / 72160 A posteriori Demande de prix Limited 68,391.00 0.00 Annulé 2023-08-12 2023-10-07 2024-04-04 esponse Interventions nvelope que, Géotechnique, etc.) pou r les travaux d'urgence de lut te antiérosive dans la ville de Kananga (sites SNCC, PK 706 et MONUSCO) ZR-PURUK-370146-GO-RFQ / Acquisition Equipement Médi cal et Produits Pharmaceutiq Component 1: Emergency R Single Stage - One E ues de premier secours dans IDA / 72160 A posteriori Demande de prix Limited 6,839.00 0.00 Annulé 2023-07-22 2023-09-16 2024-03-14 esponse Interventions nvelope le cadre des travaux d'urgen ce de lutte antiérosive dans l a ville de Kananga (sites SNC C, PK 706 et MONUSCO) ZR-PURUK-370166-GO-RFQ / Acquisition matériels de com Component 3: Project Manag Single Stage - One E En attente d' munication et de visibilité po IDA / 72160 ement and Implementation A posteriori Demande de prix Limited 45,600.00 0.00 2023-09-02 2023-10-28 2024-04-25 nvelope exécution ur le PURUK (chasubles, képi, Support t-shirt, équipement pour les c rieurs, etc.) ZR-PURUK-370181-GO-RFQ / Acquisition des équipements Component 3: Project Manag Single Stage - One E En attente d' et matériels informatiques et IDA / 72160 ement and Implementation A posteriori Demande de prix Open - National 151,550.00 0.00 2023-08-12 2023-10-07 2024-04-04 nvelope exécution de bureautique pour l'Unité d Support e Gestion du PURUK ZR-PURUK-370182-GO-RFQ / Component 3: Project Manag Acquisition des Mobiliers de Single Stage - One E En cours d'ex IDA / 72160 ement and Implementation A posteriori Demande de prix Open - National 80,000.00 0.00 2023-08-12 2023-10-07 2024-04-04 bureau (tables, chaises, arm nvelope écution Support oires etc…) pour l'Unité de G estion du PURUK ZR-PURUK-370183-GO-RFQ / Acquisition des équipements Component 3: Project Manag Single Stage - One E de communication (Tablettes IDA / 72160 ement and Implementation A posteriori Demande de prix Limited 9,600.00 0.00 Annulé 2023-08-12 2023-10-07 2024-04-04 nvelope , Téléphones et Dictaphones) Support pour l'Unité de Gestion du PU RUK ZR-PURUK-370227-GO-RFQ / Component 3: Project Manag Acquisition et installation d'u Single Stage - One E En attente d' IDA / 72160 ement and Implementation A posteriori Demande de prix Limited 30,000.00 0.00 2023-09-06 2023-11-01 2024-04-29 n Groupe électrogène pour le nvelope exécution Support bureau de l'Unité de Gestion du PURUK ZR-PURUK-370276-GO-RFQ / Component 3: Project Manag Single Stage - One E Acquisition des équipements IDA / 72160 ement and Implementation A posteriori Demande de prix Limited 5,800.00 0.00 Annulé 2023-07-22 2023-09-16 2024-03-14 nvelope pour le fonctionnement du M Support GP du PURUK ZR-PURUK-370282-GO-RFQ / Acquisition d'un Logiciel de G Component 3: Project Manag Single Stage - One E estion des Plaintes (LGP) – ge IDA / 72160 ement and Implementation A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2023-08-12 2023-10-07 2024-04-04 nvelope stion numérique des plaintes Support et formation pour le PURUK ZR-PURUK-370292-GO-DIR / Acquisition d'un Logiciel de g Component 3: Project Manag estion comptable TOM2PRO Passation de marc Direct - Internation IDA / 72160 ement and Implementation A posteriori 60,000.00 0.00 Signé 2023-08-07 2023-11-07 2023-08-12 2023-12-07 2023-09-16 2024-01-03 2024-03-14 Type mono site, y compris l'i hé de gré à gré al Support nstallation et la formation de s utilisateurs (RAF & Compta ble) ZR-PURUK-370449-GO-RFQ / Fourniture en lubrifiant pour l Component 1: Emergency R Single Stage - One E es travaux d'urgence de lutte IDA / 72160 A posteriori Demande de prix Open - National 379,200.00 0.00 Annulé 2023-07-22 2023-09-16 2024-03-14 esponse Interventions nvelope antiérosive dans la ville de K ananga (sites SNCC, PK 706 et MONUSCO) ZR-PURUK-370376-GO-DIR / Acquisition des matériaux de concassage (concassés ou gr aviers) pour les travaux d'urg Component 1: Emergency R Passation de marc IDA / 72160 A posteriori Direct - National 287,625.00 0.00 Signé 2023-09-29 2023-08-07 2023-10-04 2023-08-25 2023-11-08 2023-08-31 2024-05-06 ence de lutte antiérosive dan esponse Interventions hé de gré à gré s la ville de Kananga (sites S NCC, PK 706 et MONUSCO) : avec l'Office des Routes/Kan anga (Protocole d'Accord) ZR-PURUK-370202-GO-RFQ / Acquisition de 7 véhicules de Component 1: Emergency R Single Stage - One E IDA / 72160 A posteriori Demande de prix Limited 450,000.00 0.00 Signé 2023-10-04 2023-09-29 2023-11-29 2024-01-03 2024-05-27 liaison pour l'Unité de Gestio esponse Interventions nvelope n du PURUK et pour l'OVD Page 2 ZR-PURUK-397768-GO-RFQ / Component 3: Project Manag Acquisition d'un Véhicule de l Single Stage - One E En attente d' IDA / 72160 ement and Implementation A posteriori Demande de prix Limited 75,000.00 0.00 2024-02-20 2024-04-16 2024-10-13 iaison pour la coordination d nvelope exécution Support e l'Unité de Gestion du PURU K ZR-PURUK-418038-GO-RFQ / Component 3: Project Manag Acquisition et installation des Single Stage - One E IDA / 72160 ement and Implementation A posteriori Demande de prix Limited - National 9,500.00 0.00 Annulé 2024-04-15 2024-06-10 2024-07-09 climatiseurs SPLIT pour les b nvelope Support ureaux de l'UG-PURUK à Kan anga ZR-PURUK-426423-GO-DIR / Acquisition et installation des Component 3: Project Manag Passation de marc En attente d' climatiseurs SPLIT pour les b IDA / 72160 ement and Implementation A posteriori Direct - National 9,500.00 0.00 2024-07-01 2024-07-06 2024-08-10 2025-02-06 hé de gré à gré exécution ureaux de l'UG-PURUK à Kan Support anga (par Entente Directe av ec UAC/Kananga) ZR-PURUK-426434-GO-RFQ / Component 3: Project Manag Acquisition et installation des Single Stage - One E En attente d' IDA / 72160 ement and Implementation A posteriori Demande de prix Limited - National 17,500.00 0.00 2024-09-07 2024-11-02 2025-05-01 panneaux métalliques géants nvelope exécution Support pour la visibilité des activités du PURUK ZR-PURUK-426598-GO-RFQ / Component 3: Project Manag Acquisition et installation d'u Single Stage - One E En attente d' IDA / 72160 ement and Implementation A posteriori Demande de prix Limited - National 20,215.00 0.00 2024-10-06 2024-12-01 2025-05-30 n Serveur et service internet nvelope exécution Support dédié pour l'UG-PURUK ZR-PURUK-426422-GO-RFQ / Component 3: Project Manag Acquisition d'un drone pour l' Single Stage - One E En attente d' IDA / 72160 ement and Implementation A posteriori Demande de prix Limited - National 7,500.00 0.00 2024-10-19 2024-12-14 2025-06-12 UG-PURUK pour les études et nvelope exécution Support la cartographie NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PURUK-370085-NC-RFQ / Location Engins et Matériels de génie civil pour les travau Component 1: Emergency R Single Stage - One E IDA / 72160 A posteriori Demande de prix Open - National 552,000.00 0.00 Annulé 2023-07-22 2023-09-16 2024-03-14 x d'urgence de lutte antiérosi esponse Interventions nvelope ve dans la ville de Kananga ( sites : SNCC, PK 706 et MON USCO) ZR-PURUK-370153-NC-RFQ / Fourniture et Equipements In ternet dans le cadre des trav Component 1: Emergency R Single Stage - One E IDA / 72160 A posteriori Demande de prix Limited 85,489.00 0.00 Annulé 2023-08-12 2023-10-07 2024-04-04 aux d'urgence de lutte antiér esponse Interventions nvelope osive dans la ville de Kanang a (sites SNCC, PK 706 et MO NUSCO) ZR-PURUK-370497-NC-DIR / Protocole de collaboration en tre le Laboratoire National de Component 1: Emergency R Passation de marc s travaux publics de l’Office IDA / 72160 A posteriori Direct - National 150,000.00 0.00 Annulé 2023-10-02 2023-10-07 2023-11-11 2024-05-09 esponse Interventions hé de gré à gré des Routes et le PURUK pour les différents essais d’échant illon des matériaux destinés aux travaux ZR-PURUK-375971-NC-DIR / Recrutement d'une ONG loca le chargée de la végétalisatio n et couvert végétal, y compr Component 1: Emergency R Passation de marc En attente d' is le montage des pépinières, IDA / 72160 A posteriori Direct - National 175,365.00 0.00 2023-09-29 2023-10-04 2023-11-08 2024-05-06 esponse Interventions hé de gré à gré exécution dans le cadre des travaux d'u rgence de lutte antiérosive d ans la ville de Kananga (sites SNCC, PK 706 et MONUSCO) : avec l'ONG "ORS" ZR-PURUK-375782-NC-DIR / Location des camion-citerne pour la Fourniture en Eau de gâchage dans le cadre des tr Component 1: Emergency R Passation de marc IDA / 72160 A posteriori Direct - National 118,820.00 0.00 Annulé 2023-09-29 2023-10-04 2023-11-08 2024-05-06 avaux d'urgence de lutte anti esponse Interventions hé de gré à gré érosive dans la ville de Kana nga (sites : SNCC, PK 706 et MONUSCO) : avec la société SS CONSTRUCTION ZR-PURUK-387796-NC-DIR / Accord-cadre pour la location Component 1: Emergency R Passation de marc des engins et matériels de g IDA / 72160 A posteriori Direct - National 673,534.00 0.00 Signé 2023-11-20 2023-08-18 2023-11-25 2023-08-21 2023-12-30 2023-08-30 2024-03-29 esponse Interventions hé de gré à gré énie civil avec la société Bio Agro-Business SAS « BAB » ZR-PURUK-387799-NC-DIR / Accord-cadre pour la location Component 1: Emergency R Passation de marc IDA / 72160 A posteriori Direct - National 239,966.50 0.00 Signé 2023-11-20 2023-08-18 2023-11-25 2023-08-21 2023-12-30 2023-08-30 2024-03-29 des engins et matériels de g esponse Interventions hé de gré à gré énie civil avec la société S.S. CONSTRUCTION ZR-PURUK-387804-NC-DIR / Accord-cadre pour la location Component 1: Emergency R Passation de marc IDA / 72160 A posteriori Direct - National 62,398.00 0.00 Signé 2023-11-20 2023-08-18 2023-11-25 2023-08-21 2023-12-30 2023-08-30 2024-03-29 des engins et matériels de g esponse Interventions hé de gré à gré énie civil avec l’Etablissemen t K.K ZR-PURUK-387805-NC-DIR / Accord-cadre pour la location Component 1: Emergency R Passation de marc IDA / 72160 A posteriori Direct - National 59,938.00 0.00 Signé 2023-11-20 2023-08-18 2023-11-25 2023-08-21 2023-12-30 2023-08-30 2024-03-29 des engins et matériels de g esponse Interventions hé de gré à gré énie civil avec la Fondation D ITEKEMENA ZR-PURUK-404340-NC-DIR / Renouvellement du contrat d e location des engins et maté Component 1: Emergency R Passation de marc riels de génie civil avec l'Eta IDA / 72160 A posteriori Direct - National 62,398.00 0.00 Annulé 2023-12-18 2023-12-23 2024-01-27 2024-07-25 esponse Interventions hé de gré à gré blissement KK pour les trava ux d'urgence de lutte antiéro sive dans la ville de Kananga (Phase 2) ZR-PURUK-396226-NC-DIR / Renouvellement du contrat d e location des engins et maté Component 1: Emergency R Passation de marc riels de génie civil avec la so IDA / 72160 A posteriori Direct - National 239,966.50 0.00 Annulé 2023-12-18 2023-12-23 2024-01-27 2024-07-25 esponse Interventions hé de gré à gré ciété SS CONSTRUCTION pou r les travaux d'urgence de lut te antiérosive dans la ville de Kananga (Phase 2) Page 3 ZR-PURUK-396228-NC-DIR / Renouvellement du contrat d e location des engins et maté Component 1: Emergency R Passation de marc riels de génie civil avec la Fo IDA / 72160 A posteriori Direct - National 59,938.00 0.00 Annulé 2023-12-18 2023-12-23 2024-01-27 2024-07-25 esponse Interventions hé de gré à gré ndation DITEKEMENA pour le s travaux d'urgence de lutte antiérosive dans la ville de K ananga (Phase 2) ZR-PURUK-396225-NC-DIR / Renouvellement du contrat d e location des engins et maté Component 1: Emergency R Passation de marc riels de génie civil avec la so IDA / 72160 A posteriori Direct - National 673,534.00 0.00 Annulé 2023-12-18 2023-12-23 2024-01-27 2024-07-25 esponse Interventions hé de gré à gré ciété BAB pour les travaux d' urgence de lutte antiérosive dans la ville de Kananga (Pha se 2) ZR-PURUK-447111-NC-RFQ / Component 3: Project Manag Services de Gardiennage du Single Stage - One E En attente d' IDA / 72160 ement and Implementation A posteriori Demande de prix Limited - National 18,000.00 0.00 2024-10-06 2024-12-01 2025-05-30 Bâtiment abritant le siège de nvelope exécution Support l'Unité de Gestion du PURUK à Kananga CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PURUK-376105-CS-CQS / Recrutement d'une ONG char gée de la mise en œuvre des Component 3: Project Manag Sélection fondée s activités de prévention et rép IDA / 72160 ement and Implementation A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2023-09-29 2023-10-20 2023-12-03 2024-01-02 2024-02-06 2024-08-04 onse aux violences basées su Support s des consultants r le genre (VBG), y compris l’ EAS/HS, dans le cadre du Proj et d'Urgence et de Résilience Urbaine de Kananga (PURUK) ZR-PURUK-404336-CS-CQS / Component 3: Project Manag Sélection fondée s Consultant (ONG) chargé de l IDA / 72160 ement and Implementation A posteriori ur les qualification Open - National 120,000.00 0.00 Annulé 2024-03-01 2024-03-22 2024-05-05 2024-06-04 2024-07-09 2025-07-08 a prise en charge psychosoci Support s des consultants ale et juridique des survivant (e)s des VBG ZR-PURUK-404339-CS-CQS / Consultant (firme) pour l’audi Component 3: Project Manag Sélection fondée s t des comptes du Projet d’Ur IDA / 72160 ement and Implementation A posteriori ur les qualification Open - National 250,000.00 0.00 Annulé 2024-03-01 2024-03-22 2024-05-05 2024-06-04 2024-07-09 2026-07-08 gence et de Résilience Urbai Support s des consultants ne de Kananga (PURUK) pour les exercices 2023, 2024 et 2 025 ZR-PURUK-408901-CS-CQS / Consultant (firme) pour l'audi Component 3: Project Manag Sélection fondée s t des comptes du Projet d'Ur En attente d'exéc IDA / 72160 ement and Implementation A posteriori ur les qualification Limited 250,000.00 0.00 2024-03-01 2024-03-15 2024-04-14 2024-05-19 2026-05-18 gence et de Résilience Urbai ution Support s des consultants ne de Kananga (PURUK) pour les exercices 2023, 2024 et 2 025 ZR-PURUK-413781-CS-CQS / Recrutement d'un Consultant (ONG) pour la prise en charg Component 3: Project Manag Sélection fondée s En cours d'exécut e psycho-sociale et juridique IDA / 72160 ement and Implementation A posteriori ur les qualification Limited - National 120,000.00 0.00 2024-04-15 2024-04-29 2024-05-29 2024-07-03 2025-07-03 ion des survivant(e)s des VBG/E Support s des consultants AS/HS dans le cadre du Proje t d’Urgence et de Résilience Urbaine de Kananga (PURUK) ZR-PURUK-426416-CS-CQS / Recrutement d'un consultant (firme) pour l'élaboration de l Sélection fondée s 'EIES/Plan de gestion environ Component 2: Integrated Re En cours d'exécut IDA / 72160 A posteriori ur les qualification Limited - National 286,920.00 0.00 2024-07-01 2024-08-28 2024-07-15 2024-08-14 2024-09-18 2025-03-17 nemental et social des trava silient Urban Development ion s des consultants ux de réhabilitation et moder nisation de la RN41 et des tr avaux conservatoires sur les 21 sites additionnels ZR-PURUK-426425-CS-CQS / Recrutement d’un consultant Component 3: Project Manag Sélection fondée s (firme) pour l’élaboration du En attente d'exéc IDA / 72160 ement and Implementation A posteriori ur les qualification Limited - National 252,530.00 0.00 2024-08-26 2024-09-09 2024-10-09 2024-11-13 2025-05-12 PAR des travaux définitifs de ution Support s des consultants lutte antiérosive sur les 21 si tes additionnels dans la ville de Kananga ZR-PURUK-426426-CS-CQS / Component 3: Project Manag Sélection fondée s Recrutement d'une ONG pour En attente d'exéc IDA / 72160 ement and Implementation A posteriori ur les qualification Limited - National 20,000.00 0.00 2024-09-02 2024-09-16 2024-10-16 2024-11-20 2025-05-19 l'évaluation des moyens de s ution Support s des consultants ubsistances des PAP ZR-PURUK-426428-CS-CQS / Recrutement d’un consultant (firme) pour la réalisation de Component 3: Project Manag Sélection fondée s s Enquêtes d’évaluation des i IDA / 72160 ement and Implementation A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2024-09-02 2024-09-23 2024-11-06 2024-12-06 2025-01-10 2025-07-09 mpacts environnementaux, s Support s des consultants ocio-économiques ,VBG et de satisfaction des bénéficiaires (impacts des THIMO) ZR-PURUK-426429-CS-CQS / Recrutement d’un consultant Component 3: Project Manag Sélection fondée s (firme) pour l’évaluation du d IDA / 72160 ement and Implementation A posteriori ur les qualification Open - National 50,000.00 0.00 Annulé 2024-09-02 2024-09-23 2024-11-06 2024-12-06 2025-01-10 2025-07-09 egré de mise en œuvre du Pr Support s des consultants ojet une année après son lan cement ZR-PURUK-426430-CS-CQS / Consultant (firme) pour le So ndage de Satisfaction des Bé néficiaires SFN et évaluation Component 3: Project Manag Sélection fondée s d'impact sur la protection de IDA / 72160 ement and Implementation A posteriori ur les qualification Open - National 50,000.00 0.00 Annulé 2024-09-02 2024-09-23 2024-11-06 2024-12-06 2025-01-10 2025-07-09 la ville de KANANGA contre le Support s des consultants s érosions, ainsi que l’impact des THIMO sur l’amélioration des conditions de vie de la p opulation de KANANGA ZR-PURUK-426433-CS-QCBS Sélection fondée s / Recrutement d’un consulta Component 2: Integrated Re IDA / 72160 A priori ur la qualité et le Open - National 520,000.00 0.00 Annulé 2024-10-01 2024-10-22 2024-12-05 2025-01-02 2025-02-01 2025-03-08 2025-04-12 2026-04-12 nt (ONG) en charge de l'enga silient Urban Development coût gement Citoyen Page 4 ZR-PURUK-447112-CS-CQS / Recrutement d’un consultant Component 3: Project Manag Sélection fondée s (firme) pour l’élaboration du IDA / 72160 ement and Implementation A posteriori ur les qualification Limited - National 169,100.00 0.00 Annulé 2024-09-16 2024-09-30 2024-10-30 2024-12-04 2025-06-02 PAR des travaux conservatoir Support s des consultants es de lutte antiérosive sur les 21 sites additionnels dans la ville de Kananga ZR-PURUK-447113-CS-CQS / Sélection fondée s Component 2: Integrated Re En cours d'exécut Recrutement d’un consultant IDA / 72160 A posteriori ur les qualification Open - National 200,000.00 0.00 2024-10-15 2024-11-05 2024-12-19 2025-01-18 2025-02-22 2025-08-21 silient Urban Development ion (ONG) en charge de l'engage s des consultants ment Citoyen ZR-PURUK-454997-CS-CQS / Recrutement d'un Consultant Component 3: Project Manag Sélection fondée s En cours d'exécut (Firme) pour la mission d'aud IDA / 72160 ement and Implementation A posteriori ur les qualification Limited - National 100,000.00 0.00 2024-10-15 2024-10-29 2024-11-28 2025-01-02 2025-07-01 ion it interne du Projet d'Urgence Support s des consultants et de Résilience Urbaine de K ananga (PURUK) ZR-PURUK-454999-CS-QCBS / Recrutement d’un Consulta nt (Firme) pour l’élaboration Sélection fondée s du Plan Local d’Aménageme Component 2: Integrated Re En cours d'exécut IDA / 72160 A posteriori ur la qualité et le Open - National 396,538.00 0.00 2024-10-28 2024-11-18 2025-01-01 2025-01-29 2025-02-28 2025-04-04 2025-05-09 2026-05-09 nt (PLA), Schéma Directeur d silient Urban Development ion coût e Développement (SDD) et Pl an de Gestion des Risques d’I nondation (PGRI) de la ville d e Kananga ZR-PURUK-463597-CS-CQS / Recrutement d'un Consultant Sélection fondée s (Firme) pour l'élaboration du Component 2: Integrated Re En attente d'exéc IDA / 72160 A posteriori ur les qualification Limited - National 290,000.00 0.00 2025-01-06 2025-01-20 2025-02-19 2025-03-26 2025-09-22 Cadre de Gestion Environne silient Urban Development ution s des consultants mentale et Sociale pour le s villes de Kinshasa, Bukavu et Uvira. ZR-PURUK-463606-CS-CQS / Recrutement d'un Consultant Sélection fondée s Component 2: Integrated Re En attente d'exéc (Firme) pour l'élaboration du IDA / 72160 A posteriori ur les qualification Limited - National 290,000.00 0.00 2025-01-06 2025-01-20 2025-02-19 2025-03-26 2025-09-22 silient Urban Development ution Cadre de Politique de Réinsta s des consultants llation pour les villes de Kins hasa, Bukavu et Uvira ZR-PURUK-463639-CS-CQS / Recrutement d'un Constant ( Firme) pour les Études prélim inaires et analyses des risqu Sélection fondée s Component 2: Integrated Re En attente d'exéc es d’inondation et de glissem IDA / 72160 A posteriori ur les qualification Open - National 250,000.00 0.00 2025-01-15 2025-02-05 2025-03-21 2025-04-20 2025-05-25 2025-11-21 silient Urban Development ution ent de terrain dans les villes s des consultants de Kinshasa, Bukavu et Uvira (Études topographiques, Étu des géologiques et Études hy drologiques) ZR-PURUK-463640-CS-CQS / Recrutement d'un Consultant (Firme) pour la Conception d’ Sélection fondée s un système de drainage, de Component 2: Integrated Re En attente d'exéc IDA / 72160 A posteriori ur les qualification Open - National 290,000.00 0.00 2025-01-15 2025-02-05 2025-03-21 2025-04-20 2025-05-25 2025-11-21 protection et de rétention d’e silient Urban Development ution s des consultants au pour les villes de Kinshasa , Bukavu et Uvira (Études hy drauliques, Conception de ba ssins de rétention, etc.) ZR-PURUK-463643-CS-CQS / Recrutement d'un Consultant (Firme) chargé de mener des Sélection fondée s Etudes de Stabilisation des t Component 2: Integrated Re En attente d'exéc IDA / 72160 A posteriori ur les qualification Open - National 270,000.00 0.00 2025-01-20 2025-02-10 2025-03-26 2025-04-25 2025-05-30 2025-11-26 errains à risque dans les ville silient Urban Development ution s des consultants s de Bukavu et Uvira (Études de stabilité des pentes, Étud es sur les matériaux, Études de reboisement) ZR-PURUK-463649-CS-CQS / Recrutement d'un Consultant (Firme) chargé de mener l'An Sélection fondée s alyse des infrastructures exis Component 2: Integrated Re En attente d'exéc IDA / 72160 A posteriori ur les qualification Open - National 280,000.00 0.00 2025-01-20 2025-02-10 2025-03-26 2025-04-25 2025-05-30 2025-11-26 tantes dans les villes de Kins silient Urban Development ution s des consultants hasa, Bukavu et Uvira (Diagn ostic structurel des infrastruc tures et Conception ou ren forcement des ouvrages de p rotection) ZR-PURUK-463653-CS-CQS / Recrutement d'un Consultant Sélection fondée s Component 2: Integrated Re En attente d'exéc (Firme) pour l'élaboration de IDA / 72160 A posteriori ur les qualification Open - National 230,000.00 0.00 2025-01-27 2025-02-17 2025-04-02 2025-05-02 2025-06-06 2025-12-03 silient Urban Development ution s Plans de gestion des eaux p s des consultants luviales dans les villes de Kin shasa, Bukavu et Uvira ZR-PURUK-463656-CS-CQS / Recrutement d'un Consultant (Firme) pour la Modélisation, Sélection fondée s Component 2: Integrated Re En attente d'exéc simulations numériques et ét IDA / 72160 A posteriori ur les qualification Open - National 240,000.00 0.00 2025-01-27 2025-02-17 2025-04-02 2025-05-02 2025-06-06 2025-12-03 silient Urban Development ution udes de scénarios de change s des consultants ment climatique dans les vill es de Kinshasa, Bukavu et Uv ira ZR-PURUK-463664-CS-QCBS / Recrutement d'un Consulta Sélection fondée s Component 2: Integrated Re Open - Internationa En attente d'exéc nt (Firme) pour l’Elaboration IDA / 72160 A priori ur la qualité et le 1,350,000.00 0.00 2025-02-28 2025-03-21 2025-05-04 2025-06-01 2025-07-01 2025-08-05 2025-09-09 2026-09-09 silient Urban Development l ution des Instruments de Planificati coût on Spatiale des villes de Kins hasa, Bukavu et Uvira ZR-PURUK-463857-CS-QCBS / Recrutement d'un Consulta nt (Firme) pour la mission de Sélection fondée s contrôle et surveillance des t Component 2: Integrated Re Open - Internationa En attente d'exéc IDA / 72160 A priori ur la qualité et le 4,500,000.00 0.00 2025-02-28 2025-03-21 2025-05-04 2025-06-01 2025-07-01 2025-08-05 2025-09-09 2026-09-09 ravaux définitifs de lutte anti silient Urban Development l ution coût érosive sur 21 sites érosif et des travaux de réhabilitation et modernisation de 7,5 Km de la RN41 dans la ville de K ananga ZR-PURUK-476786-CS-CQS / Recrutement d'un Consultant Component 3: Project Manag Sélection fondée s En attente d'exéc (Firme) chargé de l'évaluatio IDA / 72160 ement and Implementation A posteriori ur les qualification Open - National 250,000.00 0.00 2025-04-15 2025-05-06 2025-06-19 2025-07-19 2025-08-23 2026-02-19 ution n à mi - parcours du Projet d' Support s des consultants Urgence et de Résilience Urb aine de Kananga (PURUK) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 ZR-PURUK-369615-CS-INDV / Recrutement d'un consultant Component 3: Project Manag individuel au poste de Spécia En attente d'exéc IDA / 72160 ement and Implementation A posteriori Individuel Open - National 57,600.00 0.00 2023-07-05 2023-08-23 2023-09-13 2023-10-18 2024-10-17 liste en Passation des Marché ution Support s du Projet d'Urgence et de R ésilience Urbaine de Kanang a ZR-PURUK-370031-CS-INDV / Recrutement d'un consultant Component 3: Project Manag En attente d'exéc individuel au poste de Coord IDA / 72160 ement and Implementation A posteriori Individuel Open - National 100,800.00 0.00 2023-07-05 2023-08-23 2023-09-13 2023-10-18 2024-10-17 ution onnateur du Projet d'Urgence Support et de Résilience Urbaine de K ananga ZR-PURUK-370032-CS-INDV / Recrutement d'un consultant Component 3: Project Manag En attente d'exéc individuel au poste de Charg IDA / 72160 ement and Implementation A posteriori Individuel Open - National 80,400.00 0.00 2023-07-05 2023-08-23 2023-09-13 2023-10-18 2024-10-17 ution é des Opérations du Projet d' Support Urgence et de Résilience Urb aine de Kananga ZR-PURUK-370033-CS-INDV / Recrutement d'un consultant Component 3: Project Manag individuel au poste de Respo En attente d'exéc IDA / 72160 ement and Implementation A posteriori Individuel Open - National 66,000.00 0.00 2023-07-05 2023-08-23 2023-09-13 2023-10-18 2024-10-17 nsable Administratif et Finan ution Support cier du Projet d'Urgence et d e Résilience Urbaine de Kana nga ZR-PURUK-370034-CS-INDV / Recrutement d'un consultant Component 3: Project Manag individuel au poste de Spécia En attente d'exéc IDA / 72160 ement and Implementation A posteriori Individuel Open - National 57,600.00 0.00 2023-07-05 2023-08-23 2023-09-13 2023-10-18 2024-10-17 liste en Développement Soci ution Support al du Projet d'Urgence et de Résilience Urbaine de Kanan ga ZR-PURUK-370035-CS-INDV / Recrutement d'un consultant Component 3: Project Manag En attente d'exéc individuel au poste de Spécia IDA / 72160 ement and Implementation A posteriori Individuel Open - National 54,000.00 0.00 2023-07-05 2023-08-23 2023-09-13 2023-10-18 2024-10-17 ution liste en Environnement du Pr Support ojet d'Urgence et de Résilien ce Urbaine de Kananga ZR-PURUK-370036-CS-INDV / Recrutement d'un consultant Component 3: Project Manag En attente d'exéc individuel au poste de Spécia IDA / 72160 ement and Implementation A posteriori Individuel Open - National 54,000.00 0.00 2023-07-05 2023-08-23 2023-09-13 2023-10-18 2024-10-17 ution liste en VBG du Projet d'Urge Support nce et de Résilience Urbaine de Kananga ZR-PURUK-370037-CS-INDV / Recrutement d'un consultant Component 3: Project Manag individuel au poste de Spécia En attente d'exéc IDA / 72160 ement and Implementation A posteriori Individuel Open - National 54,000.00 0.00 2023-08-02 2023-09-20 2023-10-11 2023-11-15 2024-11-14 liste en Suivi et Evaluation d ution Support u Projet d'Urgence et de Rési lience Urbaine de Kananga ZR-PURUK-370038-CS-INDV / Recrutement d'un consultant Component 3: Project Manag En attente d'exéc individuel au poste de Compt IDA / 72160 ement and Implementation A posteriori Individuel Open - National 36,000.00 0.00 2023-08-02 2023-09-20 2023-10-11 2023-11-15 2024-11-14 ution able du Projet d'Urgence et d Support e Résilience Urbaine de Kana nga ZR-PURUK-370039-CS-INDV / Recrutement d'un consultant Component 3: Project Manag En attente d'exéc individuel au poste de Spécia IDA / 72160 ement and Implementation A posteriori Individuel Open - National 48,000.00 0.00 2023-08-02 2023-09-20 2023-10-11 2023-11-15 2024-11-14 ution liste en Communication du Pr Support ojet d'Urgence et de Résilien ce Urbaine de Kananga ZR-PURUK-370042-CS-INDV / Recrutement d'un consultant Component 3: Project Manag individuel au poste d'Auditeu IDA / 72160 ement and Implementation A posteriori Individuel Open - National 57,600.00 0.00 Annulé 2023-08-21 2023-10-09 2023-10-30 2023-12-04 2024-12-03 r Interne du Projet d'Urgence Support et de Résilience Urbaine de K ananga ZR-PURUK-370043-CS-INDV / Recrutement d'un consultant Component 3: Project Manag En attente d'exéc individuel au poste de Spécia IDA / 72160 ement and Implementation A posteriori Individuel Open - National 48,000.00 0.00 2023-08-21 2023-10-09 2023-10-30 2023-12-04 2024-12-03 ution liste en VRD du Projet d'Urge Support nce et de Résilience Urbaine de Kananga ZR-PURUK-370044-CS-INDV / Recrutement d'un consultant Component 3: Project Manag En attente d'exéc individuel au poste d'Assista IDA / 72160 ement and Implementation A posteriori Individuel Limited 24,000.00 0.00 2023-08-02 2023-08-07 2023-08-28 2023-10-02 2024-10-01 ution nt du Coordonnateur du Proje Support t d'Urgence et de Résilience Urbaine de Kananga ZR-PURUK-370046-CS-INDV / Recrutement d'un consultant Component 3: Project Manag individuel au poste d'Assista En cours d'exécut IDA / 72160 ement and Implementation A posteriori Individuel Limited 18,000.00 0.00 2023-08-02 2023-08-07 2023-08-28 2023-10-02 2024-10-01 nt Administratif et Financier ion Support du Projet d'Urgence et de Ré silience Urbaine de Kananga ZR-PURUK-370047-CS-INDV / Recrutement d'un consultant Component 3: Project Manag En attente d'exéc individuel au poste de Caissi IDA / 72160 ement and Implementation A posteriori Individuel Limited 13,200.00 0.00 2023-08-02 2023-08-07 2023-08-28 2023-10-02 2024-10-01 ution er du Projet d'Urgence et de Support Résilience Urbaine de Kanan ga ZR-PURUK-370048-CS-INDV / Recrutement d'un consultant Component 3: Project Manag En attente d'exéc individuel au poste de Techni IDA / 72160 ement and Implementation A posteriori Individuel Limited 24,000.00 0.00 2023-08-02 2023-08-07 2023-08-28 2023-10-02 2024-10-01 ution cien Informaticien du Projet d Support 'Urgence et de Résilience Urb aine de Kananga ZR-PURUK-370050-CS-INDV / Recrutement d'un consultant Component 3: Project Manag En attente d'exéc individuel au poste de Récep IDA / 72160 ement and Implementation A posteriori Individuel Limited 12,000.00 0.00 2023-08-02 2023-08-07 2023-08-28 2023-10-02 2024-10-01 ution tionniste du Projet d'Urgence Support et de Résilience Urbaine de K ananga ZR-PURUK-370045-CS-INDV / Recrutement d'un consultant Component 3: Project Manag individuel au poste d'Assista En attente d'exéc IDA / 72160 ement and Implementation A posteriori Individuel Open - National 24,000.00 0.00 2023-10-02 2023-11-20 2023-12-11 2024-01-15 2025-01-14 nt en Passation des Marchés ution Support du Projet d'Urgence et de Ré silience Urbaine de Kananga Page 6 ZR-PURUK-375960-CS-INDV / Recrutement d'un Consultant Architecte et/ou Ingénieur po ur les études et évaluation d' Component 3: Project Manag En attente d'exéc une partie des travaux de raf IDA / 72160 ement and Implementation A posteriori Individuel Limited 2,000.00 0.00 2023-08-31 2023-09-05 2023-09-26 2023-10-31 2024-04-28 ution raichissement, de stockage e Support t approvisionnement en eau potable de l'immeuble devan t abriter le siège de l'UG/PUR UK à Kananga ZR-PURUK-375962-CS-INDV / Recrutement d'un consultant Electricien et/ou Electroméca nicien pour les études et éval Component 3: Project Manag En attente d'exéc uation d'une partie des trava IDA / 72160 ement and Implementation A posteriori Individuel Limited 1,500.00 0.00 2023-08-31 2023-09-05 2023-09-26 2023-10-31 2024-04-28 ution ux d'alimentation en énergie Support avec le photovoltaïque et le générateur de l'immeuble de vant devant abriter le siège d e l'UG/PURUK à Kananga ZR-PURUK-388051-CS-INDV / Recrutement de cinq (5) con Component 3: Project Manag sultants individuels au poste En attente d'exéc IDA / 72160 ement and Implementation A posteriori Individuel Limited 66,000.00 0.00 2023-12-11 2023-12-16 2024-01-06 2024-02-10 2025-02-04 de Chauffeurs de l'Unité de G ution Support estion du Projet d'Urgence et de Résilience Urbaine de Kan anga ZR-PURUK-388052-CS-INDV / Recrutement d'un consultant Component 3: Project Manag individuel au poste de Comm En attente d'exéc IDA / 72160 ement and Implementation A posteriori Individuel Limited 14,400.00 0.00 2023-11-06 2023-11-11 2023-12-02 2024-01-06 2024-12-31 is de Bureau pour l'Unité de ution Support Gestion du Projet d'Urgence et de Résilience Urbaine de K ananga ZR-PURUK-388054-CS-INDV / Recrutement d'un consultant individuel Architecte Urbain a Component 3: Project Manag En attente d'exéc u poste d'Assistant du Charg IDA / 72160 ement and Implementation A posteriori Individuel Limited 24,000.00 0.00 2023-12-15 2023-12-20 2024-01-10 2024-02-14 2025-02-08 ution é des Opérations de l'Unité d Support e gestion du Projet d'Urgence et de Résilience Urbaine de K ananga ZR-PURUK-393972-CS-INDV / Recrutement d'un (e) consult Component 3: Project Manag ant (e) individuel (le) Assista IDA / 72160 ement and Implementation A posteriori Individuel Open - National 18,000.00 0.00 Annulé 2024-01-05 2024-02-23 2024-03-15 2024-04-19 2024-10-16 nt (e) Genre et Protection EA Support S/HS dans le cadre du Projet d'Urgence et de Résilience Ur baine de Kananga ZR-PURUK-393973-CS-INDV / Recrutement d'un consultant Component 3: Project Manag individuel Expert Internation Open - Internationa En cours d'exécut IDA / 72160 ement and Implementation A posteriori Individuel 120,000.00 0.00 2024-01-15 2023-12-02 2024-03-04 2024-03-25 2024-04-29 2024-10-26 al en Passation des Marchés l ion Support du Projet d'Urgence et de Ré silience Urbaine de Kananga ZR-PURUK-413749-CS-CDS / Recrutement d’un cabinet ou d’une firme pour une Mission Sélection de cons d’Assistance Technique à la Component 1: Emergency R Direct - Internation En cours d'exécut IDA / 72160 A posteriori ultants par entent 250,000.00 0.00 2024-04-08 2024-10-16 2024-04-18 2024-08-15 2024-06-22 2025-06-22 Maîtrise d’Ouvrage du Projet esponse Interventions al ion e directe d’Urgence et de Résilience U rbaine de la Ville de Kananga "PURUK" (Entente Directe av ec la Firme KUROBA QUATRE SL) ZR-PURUK-413788-CS-INDV / Recrutement par ED d’un Co nsultant en charge de prépar er l'analyse des causes profo Component 3: Project Manag En cours d'exécut ndes de l'incident mortel sur IDA / 72160 ement and Implementation A posteriori Individuel Direct - National 25,990.00 0.00 2024-04-01 2024-04-11 2024-05-02 2024-06-06 2024-12-03 ion venu lors des travaux de la lu Support tte antiérosive sur le site prio ritaire SNCC, à Kananga, en République Démocratique du Congo (Marcellin LUKONGO) ZR-PURUK-426211-CS-INDV / Component 3: Project Manag Recrutement d'un consultant En cours d'exécut IDA / 72160 ement and Implementation A posteriori Individuel Open - National 81,600.00 0.00 2024-07-01 2024-08-19 2024-09-09 2024-10-14 2025-10-14 individuel au poste de Coord ion Support onnateur Adjoint de l'Unité d e Gestion du PURUK ZR-PURUK-426213-CS-INDV / Component 3: Project Manag Recrutement d'un consultant En cours d'exécut IDA / 72160 ement and Implementation A posteriori Individuel Open - National 48,000.00 0.00 2024-07-01 2024-08-19 2024-09-09 2024-10-14 2025-10-14 individuel au poste d'Agrono ion Support me de l'Unité de Gestion du PURUK ZR-PURUK-426217-CS-CDS / Recrutement consultant (Fir me) pour la mission de contr ôle des travaux de lutte antié Sélection de cons Component 1: Emergency R En cours d'exame rosive sur les 3 sites prioritai IDA / 72160 A priori ultants par entent Direct - National 1,500,000.00 0.00 2024-07-01 2024-11-17 2024-07-11 2024-12-18 2024-09-14 2025-03-13 esponse Interventions n res et les 21 sites additionnel e directe s et des travaux de réhabilita tion et modernisation de la R N41 (marché par ED avec la f irme (AIC PROGETTI) ZR-PURUK-426427-CS-INDV / Component 3: Project Manag Recrutement d’un consultant IDA / 72160 ement and Implementation A posteriori Individuel Open - National 20,000.00 0.00 Annulé 2024-08-02 2024-09-20 2024-10-11 2024-11-15 2025-05-14 individuel pour l’audit social Support du PAR des sites MONUSCO, SNCC et PK706 ZR-PURUK-447098-CS-INDV / Recrutement par Entente Dir ecte d'un consultant individu Component 3: Project Manag En attente d'exéc el au poste de Coordonnateu IDA / 72160 ement and Implementation A posteriori Individuel Direct - National 50,400.00 0.00 2024-08-22 2024-09-01 2024-09-22 2024-10-27 2025-04-25 ution r ai du Projet d'Urgence et de Support Résilience Urbaine de Kanan ga (avec Jean Michel MBUNG U NGUMBA) ZR-PURUK-447099-CS-INDV / Recrutement par Entente Dir ecte d'un consultant individu Component 3: Project Manag el au poste de Chargé des Op IDA / 72160 ement and Implementation A posteriori Individuel Direct - National 40,200.00 0.00 Annulé 2024-08-22 2024-09-01 2024-09-22 2024-10-27 2025-04-25 érations ai du Projet d'Urgen Support ce et de Résilience Urbaine d e Kananga (avec Corneille KA BAMBA MANONGO) Page 7 ZR-PURUK-447102-CS-INDV / Recrutement d'un consultant individuel pour l'évaluation d Component 2: Integrated Re En cours d'exécut es besoins en renforcement IDA / 72160 A posteriori Individuel Limited - National 7,500.00 0.00 2024-10-01 2024-10-06 2024-10-27 2024-12-01 2025-05-30 silient Urban Development ion des capacités institutionnelle s des structures étatiques (M etelsat, Office des Routes, BT C, OVD et Mairie de Kananga ) ZR-PURUK-447106-CS-INDV / Recrutement d'un (e) consult Component 3: Project Manag ant (e) individuel (le) Assista En attente d'exéc IDA / 72160 ement and Implementation A posteriori Individuel Limited - National 18,000.00 0.00 2024-09-16 2024-09-21 2024-10-12 2024-11-16 2025-05-15 nt (e) en Genre et Protection ution Support EAS/HS pour l'Unité de Gesti on du Projet d'Urgence et de Résilience Urbaine de Kanan ga ZR-PURUK-447110-CS-INDV / Recrutement de deux (2) con Component 3: Project Manag sultants individuels Nettoyeu En cours d'exécut IDA / 72160 ement and Implementation A posteriori Individuel Limited - National 7,200.00 0.00 2024-10-15 2024-10-20 2024-11-10 2024-12-15 2025-06-13 rs/Nettoyeuses pour l'Unité d ion Support e Gestion du Projet d'Urgenc e et de Résilience Urbaine de Kananga ZR-PURUK-426219-CS-CDS / Recrutement d'un consultant (Firme) pour l'élaboration d'é tudes des travaux définitifs d Sélection de cons Component 2: Integrated Re En cours d'exécut e lutte antiérosive sur les 21 IDA / 72160 A priori ultants par entent Direct - National 2,213,080.00 0.00 2024-10-28 2024-10-23 2024-11-07 2025-01-11 2025-07-10 silient Urban Development ion sites additionnels ainsi que d e directe es travaux sur la RN 41 dans la ville de Kananga (marché par Entente Directe avec la fi rme AIC PROGETTI) ZR-PURUK-455000-CS-INDV / Recrutement d'un consultant Component 3: Project Manag individuel pour la révision du En cours d'exécut IDA / 72160 ement and Implementation A posteriori Individuel Limited - National 15,000.00 0.00 2024-10-15 2024-12-20 2024-10-20 2024-11-10 2024-12-15 2025-06-13 Manuel d'exécution (Opératio ion Support ns et Procédures) du Projet d' Urgence et de Résilience Urb aine de Kananga (PURUK) ZR-PURUK-455002-CS-INDV / Component 3: Project Manag Recrutement d'un consultant En cours d'exécut IDA / 72160 ement and Implementation A posteriori Individuel Limited - National 18,000.00 0.00 2024-10-21 2024-10-26 2024-11-16 2024-12-21 2025-06-19 individuel au poste de Trésori ion Support er de l'Unité de Gestion du P URUK (UG-PURUK) ZR-PURUK-455004-CS-INDV / Recrutement d'un consultant Component 3: Project Manag En attente d'exéc individuel au poste de Jardini IDA / 72160 ement and Implementation A posteriori Individuel Limited - National 3,600.00 0.00 2024-10-21 2024-10-26 2024-11-16 2024-12-21 2025-06-19 ution er pour l'entretien de la cour Support des bâtiments de l'UG-PURUK ZR-PURUK-454995-CS-CDS / Recrutement d’un consultant (firme) chargé de la réalisati on de l’audit social de la mis Component 3: Project Manag Sélection de cons Direct - Internation En cours d'exécut e en œuvre du PAR pour les t IDA / 72160 ement and Implementation A posteriori ultants par entent 51,060.00 0.00 2024-10-28 2024-12-20 2024-11-07 2025-01-11 2025-07-10 al ion ravaux de lutte antiérosive s Support e directe ur les 3 sites de MONUSCO, S NCC et PK706 (Recrutement par ED avec la firme HPR AN KH CONSULTANTS). ZR-PURUK-455012-CS-INDV / Recrutement par Entente Dir ecte (ED) d'un consultant ind Component 3: Project Manag ividuel Ingénieur Géomètre T En cours d'exécut IDA / 72160 ement and Implementation A posteriori Individuel Direct - National 17,734.00 0.00 2024-10-28 2024-11-07 2024-11-28 2025-01-02 2025-07-01 opographe pour un appui tec ion Support hnique à l'Unité de Gestion d u Projet d'Urgence et de Rési lience Urbaine de Kananga (E D avec Abdallah MOHAMED). ZR-PURUK-455007-CS-INDV / Recrutement par Entente Dir ecte (ED) d’un consultant ind Component 3: Project Manag ividuel Ingénieur Civil pour u En cours d'exécut IDA / 72160 ement and Implementation A posteriori Individuel Direct - National 14,234.00 0.00 2024-10-28 2024-11-07 2024-11-28 2025-01-02 2025-07-01 n appui technique à l'Unité d ion Support e Gestion du Projet d’Urgenc e et de Résilience Urbaine de Kananga (Entente Directe av ec MUTEBA ILUNGA KABONG O) ZR-PURUK-455008-CS-INDV / Recrutement par Entente Dir ecte (ED) d’un consultant ind ividuel Chargé des études sp Component 3: Project Manag En cours d'exécut écifiques sur la modélisation IDA / 72160 ement and Implementation A posteriori Individuel Direct - National 14,234.00 0.00 2024-10-28 2024-11-07 2024-11-28 2025-01-02 2025-07-01 ion hydrologique pour un appui t Support echnique à l'Unité de Gestion du Projet d’Urgence et de Ré silience Urbaine de Kananga (ED avec Luc LISSA TEMO) ZR-PURUK-462144-CS-CDS / Recrutement d’un Consultant (firme) chargé d'élaborer le P lan d’Action de Réinstallation Sélection de cons Component 2: Integrated Re En cours d'exécut (PAR) des travaux sur 21 site IDA / 72160 A posteriori ultants par entent Direct - National 169,100.00 0.00 2024-11-30 2024-12-10 2025-02-13 2025-08-12 silient Urban Development ion s érosifs et de réhabilitation e directe et modernisation d’un tronço n de la Route Nationale 41 ( Marché par ED avec le Group ement LRC & BIOCENOSE) ZR-PURUK-469885-CS-INDV / Recrutement d'un consultant Component 3: Project Manag individuel Spécialiste en Dév En attente d'exéc IDA / 72160 ement and Implementation A posteriori Individuel Open - National 60,000.00 0.00 2025-01-31 2025-03-21 2025-04-11 2025-05-16 2025-11-12 eloppement Social de l'Unité ution Support de Gestion du Projet d'Urgen ce et de Résilience Urbaine d e Kananga (UG-PURUK) ZR-PURUK-476789-CS-INDV / Recrutement d'un consultant Component 3: Project Manag individuel au poste de Spécia En attente d'exéc IDA / 72160 ement and Implementation A posteriori Individuel Open - National 60,000.00 0.00 2025-03-03 2025-04-21 2025-05-12 2025-06-16 2026-06-11 liste en VBG de l'Unité de Ge ution Support stion du Projet d'Urgence et de Résilience Urbaine de Kan anga (UG-PURUK) Page 8