Procurement Plan Colombia - Plan PAZcifico: WSS Infrastructure & Service Delivery Project P156239 I. General 1. Bank’s approval Date of the procurement Plan: Original 2016/08/29; Revision 2016/12/15 and 2017/4/19 2. Date of General Procurement Notice: Dec 13, 2016 3. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank will be marked in the procurement plan according to the level of risk of the agency 2. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P156239 issued by National Unit For The Management Of Disaster Risk – UNGRD 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 40.00 1 No Prior of the ICB (Works) Summary 54.00 09 No Post of the NCB (Works) Summary 1.00 1 No Post of the NCB (Goods) III. Selection of Consultants July 9, 2010 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank will be marked in the procurement plan according to the level of risk of the agency 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_400,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 11.6 6 Post of number of contracts that will be let under QCBS Summary 1.6 5 Post CQS, of number LCBS of contracts that will be let under other methods July 9, 2010 PROCUREMENT Colombia : CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2024-05-08 Revised Plan Date(s): (comma delineated, leave blank if 2025-01-27 none) Project ID: P156239 GPN Date: 2016-12-13 Project Name: CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project Loan / Credit No: IBRD / 86490 Ministerio de Igualdad y Equidad Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PTSP-BIRF-8649-299 / Obras de optimización y ampliación Component 2. Water Supply Solicitud de Cotiz del sistema de acueducto del and Basic Sanitation Improv Solicitud de cotiza Single Stage - One E ación (no docume Ejecución p 2025-08-2 IBRD / 86490 Posterior Open - National 2,364,857.00 0.00 2024-12-28 2025-02-22 distrito especial de Tumaco, ements in the Municipality o ciones nvelope nto estándar del endiente 1 departamento de Nariño, Col f Tumaco Banco) ombia - Fase V Etapa III - GP D Isla Tumaco GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF-8649-251 / Brinda r apoyo profesional en la ges tión jurídica y administrativa Component 4. Project Manag en los procesos de adquisicio IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 10,264.00 0.00 Firmado 2024-05-10 2024-05-10 2024-05-15 2024-05-14 2024-06-05 2024-07-04 2024-07-10 2024-06-28 2025-01-06 nes que adelanta el MIE com nd Social Management o entidad ejecutora del FTSP, según las Políticas, normas y regulaciones del BID y el Ban co Mundial. PTSP-BIRF-8649-253 / Recon tratación Leidy Leguizamón, Apoyo Profesional Planeación Component 4. Project Manag - Brindar apoyo profesional a IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 14,375.00 0.00 Firmado 2024-05-06 2024-05-10 2024-05-16 2024-06-04 2024-06-06 2024-07-04 2024-07-11 2024-06-28 2025-01-07 los procesos de planificación, nd Social Management seguimiento y gestión de los Préstamos del BM ejecutados por el MIE como entidad ejec utora del FTSP. PTSP-BIRF-8649-279 / Recon tratación Mauricio Otálvaro, Especialista Jurídico Contract Component 4. Project Manag ual y en Relaciones Jurídico-N IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 14,454.00 0.00 Firmado 2024-05-10 2024-05-10 2024-05-20 2024-06-04 2024-06-10 2024-07-04 2024-07-15 2024-06-28 2025-01-11 egociales - Realizar apoyo co nd Social Management mo profesional especializado en los procesos contractuale s y relaciones jurídico negoci ales del FTSP. PTSP-BIRF-8649-280 / Recon tratación Carlos Marulanda, A poyo Profesional Financiero - Component 4. Project Manag Brindar apoyo profesional en IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 7,187.00 0.00 Firmado 2024-05-03 2024-05-10 2024-05-13 2024-06-04 2024-06-03 2024-07-09 2024-07-08 2024-06-28 2025-01-04 las actividades administrativ nd Social Management as de la gestión presupuestal y financiera de los Préstamos del BID y Banco Mundial. PTSP-BIRF-8649-281 / Recon tratación Alexander Segura, Apoyo Profesional Financiero Component 4. Project Manag - Brindar apoyo profesional e IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 8,625.00 0.00 Firmado 2024-05-10 2024-05-10 2024-05-20 2024-06-03 2024-06-10 2024-07-04 2024-07-15 2024-06-28 2025-01-11 n las actividades administrati nd Social Management vas de la gestión presupuest al y financiera de los Préstam os del BID y Banco Mundial. PTSP-BIRF-8649-254 / Recon tratación Andrés Machado, E specialista Residuos Solidos - Component 1. Water Supply Brindar apoyo técnico como and Basic Sanitation Improv IBRD / 86490 Posterior Individual Direct - National 20,013.00 0.00 En ejecución 2024-05-06 2024-07-15 2024-05-16 2024-06-06 2024-07-11 2025-01-07 especialista en la estructurac ements in the Municipality o ión, seguimiento y gestión de f Guapi los proyectos de residuos sóli dos de los préstamos del BID y el Banco Mundial. Page 1 PTSP-BIRF-8649-255 / Recon tratación Lays Zúñiga, Enlace Social - Apoyar como Enlace Component 4. Project Manag Social la implementación del IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 16,817.00 0.00 En ejecución 2024-05-06 2024-07-15 2024-05-16 2024-06-06 2024-07-11 2025-01-07 componente social, con espe nd Social Management cial atención en los program as y proyectos que conforma n el Plan de Información, Co municación y Participación - PICP. PTSP-BIRF-8649-256 / Recon tratación Lidia Quiñones, Enl ace Social Tumaco - Brindar Component 4. Project Manag apoyo profesional en el comp IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 15,326.00 0.00 En ejecución 2024-05-06 2024-07-15 2024-05-16 2024-06-06 2024-07-11 2025-01-07 onente Social de los proyecto nd Social Management s que se generen en el Depar tamento de Nariño en el mar co de los préstamos del BID y el Banco Mundial PTSP-BIRF-8649-258 / Recon tratación Nini Gómez, Especi Component 1. Water Supply alista ASB - Brindar apoyo té and Basic Sanitation Improv cnico especializado en los pr IBRD / 86490 Posterior Individual Direct - National 33,635.00 0.00 En ejecución 2024-05-06 2024-07-15 2024-05-16 2024-06-06 2024-07-11 2025-01-07 ements in the Municipality o oyectos de Agua y Saneamie f Guapi nto Básico que hagan parte d el préstamo del Banco Mundi al BIRF 8649-CO. PTSP-BIRF-8649-257 / Recon tratación Jorge Silva, Especial Component 3. Capacity Buil ista Fortalecimiento Institucio ding and Institutional Streng nal - Brindar apoyo profesion IBRD / 86490 thening of Service Providers Posterior Individual Direct - National 13,342.00 0.00 Cancelado 2024-05-10 2024-05-20 2024-06-10 2024-07-15 2025-01-11 al como Especialista en la im in the Municipalities of Guap plementación y ejecución de i and Tum aco los componentes de Capacid ad y Fortalecimiento Instituci onal de Agua y Saneamiento Básico. PTSP-BIRF-8649-282 / Apoyo Adquisiciones - Brindar apoy o en los procedimientos admi nistrativos , logísticos y oper Component 4. Project Manag Ejecución pendien ativos necesarios para la imp IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 6,348.00 0.00 2024-05-10 2024-05-15 2024-06-05 2024-07-10 2025-01-06 te lementación y ejecución del nd Social Management Plan Todos Somos PAZcifico que adelanta como entidad e jecutora el Ministerio de Igual dad y Equidad. PTSP-BIRF-8649-262 / Recon tratación Lina Barón, Especia Component 1. Water Supply lista Predial - Brindar apoyo p and Basic Sanitation Improv rofesional en las gestiones ju IBRD / 86490 Posterior Individual Direct - National 12,608.00 0.00 En ejecución 2024-06-14 2024-07-15 2024-06-24 2024-05-28 2024-07-15 2024-07-10 2024-08-19 2025-02-15 ements in the Municipality o rídicas y administrativas que f Guapi se requieran para el saneami ento y proceso de adquisició n de los predios PTSP-BIRF-8649-263 / Recon tratación Carlos Muñoz, Apoy Component 4. Project Manag o Profesional Adquisiciones - IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 13,158.00 0.00 Firmado 2024-06-14 2024-07-15 2024-06-24 2024-05-21 2024-07-15 2024-07-10 2024-08-19 2024-07-04 2025-02-15 Brindar apoyo profesional en nd Social Management la estructuración, seguimient o y gestión de los procesos d e adquisiciones PTSP-BIRF-8649-264 / Recon Component 2. Water Supply tratación Martha Cortes, Inge and Basic Sanitation Improv Ejecución pendien niero Apoyo - Brindar apoyo IBRD / 86490 Posterior Individual Direct - National 6,386.00 0.00 2024-06-14 2024-06-24 2024-07-15 2024-08-19 2025-02-15 ements in the Municipality o te profesional en los proyectos f Tumaco de Agua y Saneamiento Bási co en el Distrito de Tumaco PTSP-BIRF-8649-267 / Recon tratación Gustavo Barreiro, E Component 4. Project Manag specialista Técnico ASB - Brin Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 8,846.00 0.00 2024-06-14 2024-06-24 2024-07-15 2024-08-19 2025-02-15 dar apoyo profesional a los p te nd Social Management royectos del componente de Agua y Saneamiento, en el Di strito de Tumaco. PTSP-BIRF-8649-268 / Recon tratación Natalie Garzón, Líd Component 4. Project Manag er Planeación - Liderar la pla IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 17,637.00 0.00 En ejecución 2024-06-14 2024-07-15 2024-06-24 2024-05-31 2024-07-15 2024-07-18 2024-08-19 2025-02-15 nificación, monitoreo, seguim nd Social Management iento y gestión de los présta mos del BID y el Banco Mund ial PTSP-BIRF-8649-270 / Recon tratación Yerlyn Urrutia, Inge Component 1. Water Supply niero Apoyo Guapi - Brindar a and Basic Sanitation Improv Ejecución pendien IBRD / 86490 Posterior Individual Direct - National 5,109.00 0.00 2024-06-14 2024-06-24 2024-07-15 2024-08-19 2025-02-15 poyo profesional en los proye ements in the Municipality o te ctos de Agua y Saneamiento f Guapi Básico en el Municipio de Gu api, Departamento del Cauca PTSP-BIRF-8649-271 / Recon tratación William Rodríguez, Especialista Catastral - Brind Component 4. Project Manag ar acompañamiento técnico IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 5,003.00 0.00 En ejecución 2024-06-14 2024-08-12 2024-06-24 2024-07-15 2024-08-19 2025-02-15 profesional catastral en la ge nd Social Management stión predial de los proyectos que se desarrollen en el mar co del FTSP PTSP-BIRF-8649-272 / Recon tratación Salomón Jiménez, E Component 2. Water Supply specialista ASB - Brindar apo and Basic Sanitation Improv Ejecución pendien yo técnico especializado en l IBRD / 86490 Posterior Individual Direct - National 10,006.00 0.00 2024-06-14 2024-06-24 2024-07-15 2024-08-19 2025-02-15 ements in the Municipality o te os proyectos de Agua y Sane f Tumaco amiento Básico que hagan p arte del préstamo del Banco Mundial BIRF 8649-CO. PTSP-BIRF-8649-274 / Recon tratación Isabel Medina, Líder Ambiental - Liderar la planific Component 4. Project Manag ación, seguimiento y gestión IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 17,637.00 0.00 En ejecución 2024-06-14 2024-10-20 2024-06-24 2024-07-15 2024-08-19 2025-02-15 ambiental de los proyectos q nd Social Management ue se adelanten en el marco de los préstamos del BID y el Banco Mundial. PTSP-BIRF-8649-265 / Especi alista Jurídico - Prestar los ser vicios jurídicos como especial ista para los procesos de adq Component 4. Project Manag uisiciones del FTSP que adela IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 13,342.00 0.00 En ejecución 2024-06-14 2024-07-20 2024-06-19 2024-07-10 2024-08-14 2025-02-10 nta como entidad ejecutora d nd Social Management el Ministerio de Igualdad y Eq uidad, en el marco de la ejec ución de sus proyectos y de s us préstamos Page 2 PTSP-BIRF-8649-259 / Recon tratación German Rojas, Apo yo Técnico Comunicaciones - Component 4. Project Manag Actualizar e implementar el p IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 6,982.00 0.00 En ejecución 2024-06-07 2024-07-15 2024-06-17 2024-07-08 2024-08-12 2025-02-08 lan de comunicaciones y el s nd Social Management ostenimiento de las estrategi as comunicativas (internas y externas) del FTSP. PTSP-BIRF-8649-273 / Recon tratación Viviana Panqueba, Apoyo Técnico Administrativ Component 4. Project Manag o - Brindar apoyo a la gestión IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 3,585.00 0.00 Cancelado 2024-06-28 2024-07-08 2024-07-29 2024-09-02 2025-03-01 en los procedimientos admini nd Social Management strativos y operativos requeri dos por el MIE como entidad ejecutora del FTSP PTSP-BIRF-8649-277 / Recon tratación Pilar Valero, Líder d e Adquisiciones - Liderar los Component 4. Project Manag Ejecución pendien procesos de adquisiciones qu IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 14,697.00 0.00 2024-06-28 2024-07-08 2024-07-29 2024-09-02 2025-03-01 te e adelanta el MIE como entid nd Social Management ad ejecutora del FTSP, según las Políticas, normas y regula ciones del BID y el Banco Mu ndial. PTSP-BIRF-8649-275 / Recon tratación Lina Grueso, Enlace Social Cauca - Brindar apoyo Component 4. Project Manag Ejecución pendien profesional en el component IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 1,277.00 0.00 2024-06-28 2024-07-08 2024-07-29 2024-09-02 2025-03-01 te e social de los proyectos que nd Social Management se generen en el Departame nto del Cauca en el marco de l préstamo del Banco Mundia l. PTSP-BIRF-8649-284 / Coordi nador General - Coordinar la i mplementación y supervisión Component 4. Project Manag de los préstamos del BID y el IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 20,002.00 0.00 En ejecución 2024-08-30 2024-09-02 2024-09-04 2024-09-03 2024-09-25 2024-10-25 2024-10-30 2025-04-28 Banco Mundial, ejecutados p nd Social Management or el Ministerio de Igualdad y Equidad como entidad ejecut ora del Fondo para el Desarr ollo del Plan Todos Somos PA Zcífico PTSP-BIRF-8649-285 / Apoyo Profesional Financiero - Brind ar apoyo profesional en las a Component 4. Project Manag ctividades administrativas de Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 9,165.00 0.00 2024-09-23 2024-09-28 2024-10-19 2024-11-23 2025-05-22 la gestión presupuestal y fina te nd Social Management nciera de los Préstamos del B ID y el Banco Mundial, ejecut ados por el MIE como entidad ejecutora del FTSP PTSP-BIRF-8649-286 / Viabili zador - Brindar apoyo prof co mo especialista en el proceso de viabilización ante el MVCT Component 4. Project Manag Ejecución pendien , de los proyectos de ASB qu IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 11,616.00 0.00 2024-09-23 2024-09-28 2024-10-19 2024-11-23 2025-05-22 te e hagan parte de los Préstam nd Social Management os BID 3610/0C-CO, BIRF 864 9-CO y BIRF 8798-CO ejecuta dos por el MIE como entidad ejecutora del FTSP PTSP-BIRF-8649-287 / Apoyo Técnico Administrativo - Brin dar apoyo a la gestión en los Component 4. Project Manag procedimientos administrativ Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 4,128.00 0.00 2024-09-23 2024-09-28 2024-10-19 2024-11-23 2025-05-22 os y operativos requeridos e te nd Social Management n el marco de la ejecución de los préstamos BID y Banco M undial, ejecutados por el MIE como entidad ejecutora del F TSP. PTSP-BIRF-8649-283 / Especi alista Fortalecimiento Instituc Component 3. Capacity Buil ional - Brindar apoyo profesio ding and Institutional Streng nal como Especialista en la i Ejecución pendien IBRD / 86490 thening of Service Providers Posterior Individual Limited - National 11,616.00 0.00 2024-09-23 2024-09-28 2024-10-19 2024-11-23 2025-05-22 mplementación y ejecución d te in the Municipalities of Guap e los componentes de Capaci i and Tum aco dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico PTSP-BIRF-8649-261 / Especi alista de Seguridad - Prestar servicios profesionales como Component 4. Project Manag especialista en las actividade IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 11,616.00 0.00 En ejecución 2024-09-23 2024-09-20 2024-09-28 2024-10-19 2024-11-23 2025-05-22 s relacionadas con protocolo nd Social Management s y herramientas de segurida d, para mitigar las posibles a menazas o riesgos en la ejec ución de los proyectos que s e desarrollan PTSP-BIRF-8649-269 / Viabili zador - Brindar apoyo prof co mo especialista en el proceso de viabilización ante el MVCT Component 4. Project Manag , de los proyectos de ASB qu IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 11,616.00 0.00 En ejecución 2024-09-23 2024-10-02 2024-09-28 2024-10-19 2024-11-23 2025-05-22 e hagan parte de los Préstam nd Social Management os BID 3610/0C-CO, BIRF 864 9-CO y BIRF 8798-CO ejecuta dos por el MIE como entidad ejecutora del FTSP PTSP-BIRF-8649-266 / Líder Social - Liderar el component e social de los proyectos que Component 4. Project Manag se generen en el marco de lo IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 11,374.00 0.00 Cancelado 2024-09-23 2024-10-03 2024-10-24 2024-11-28 2025-05-27 s préstamos del Banco Mundi nd Social Management al ejecutados por el Ministeri o de Igualdad y Equidad com o entidad ejecutora del FTSP PTSP-BIRF-8649-260 / Apoyo Comunicaciones - Apoyar las actividades relacionadas con el diseño gráfico, el cubrimie Component 4. Project Manag Ejecución pendien nto fotográfico, la producción IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 6,141.00 0.00 2024-09-23 2024-09-28 2024-10-19 2024-11-23 2025-05-22 te audiovisual y las actividades nd Social Management del plan de comunicaciones r equeridas para la ejecución d e los préstamos del BID y del Banco Mundial Page 3 PTSP-BIRF-8649-252 / Apoyo Técnico Administrativo Adqui siciones - Brindar apoyo a la gestión en los procedimiento Component 4. Project Manag Ejecución pendien s administrativos y operativo IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 4,953.00 0.00 2024-09-23 2024-09-28 2024-10-19 2024-11-23 2025-05-22 te s requeridos en el marco de l nd Social Management a ejecución de los préstamos BID y Banco Mundial, ejecuta dos por el MIE como entidad ejecutora del FTSP PTSP-BIRF-8649-288 / Especi alista Jurídico - Prestar los ser vicios jurídicos como especial Component 4. Project Manag ista al Ordenador del Gasto, Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 8,605.00 0.00 2024-10-04 2024-10-09 2024-10-30 2024-12-04 2025-06-02 en los procesos de adquisicio te nd Social Management nes, así como en las activida des inherentes a la ejecución de los proyectos que se desa rrollan en el marco de los pré stamos PTSP-BIRF-8649-289 / Apoyo Profesional Administrativo de Adquisiciones - Brindar apoy Component 4. Project Manag o profesional en los procedim IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 4,176.00 0.00 Cancelado 2024-10-04 2024-10-09 2024-10-30 2024-12-04 2025-06-02 ientos administrativos y oper nd Social Management ativos requeridos por el FTSP a través del Ministerio de Igu aldad y Equidad como entida d ejecutora PTSP-BIRF-8649-290 / Apoyo Profesional Administrativo - B rindar apoyo a los procedimi Component 4. Project Manag entos administrativos y oper Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 4,176.00 0.00 2024-10-04 2024-10-09 2024-10-30 2024-12-04 2025-06-02 ativos requeridos en el marc te nd Social Management o de la ejecución de los prést amos BID y Banco Mundial, e jecutados por el MIE como en tidad ejecutora del FTSP PTSP-BIRF-8649-292 / Apoyo Técnico Comunicaciones - Ac Component 4. Project Manag tualizar e implementar el pla Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 8,105.00 0.00 2024-11-20 2024-11-30 2024-12-21 2025-01-25 2025-07-24 n de comunicaciones y el sos te nd Social Management tenimiento de las estrategias comunicativas (internas y ext ernas) del FTSP. PTSP-BIRF-8649-294 / Ingeni ero de Apoyo Guapi - Brindar Component 1. Water Supply apoyo profesional en los proy and Basic Sanitation Improv Ejecución pendien ectos de Agua y Saneamient IBRD / 86490 Posterior Individual Direct - National 17,791.00 0.00 2024-11-19 2024-11-29 2024-12-20 2025-01-24 2025-07-23 ements in the Municipality o te o Básico en el Municipio de G f Guapi uapi, Departamento del Cauc a que hagan parte del présta mo del Banco Mundial BIRF 8 649-CO. PTSP-BIRF-8649-295 / Ingeni ero de Apoyo a la Supervisió n - Brindar apoyo profesional Component 2. Water Supply a los proyectos del compone and Basic Sanitation Improv Ejecución pendien nte de ASB en el Distrito de T IBRD / 86490 Posterior Individual Direct - National 5,808.00 0.00 2024-11-19 2024-11-29 2024-12-20 2025-01-24 2025-07-23 ements in the Municipality o te umaco para contribuir al cum f Tumaco plimiento de los objetivos del FTSP con la Banca Multilatera l que adelanta como entidad ejecutora el MIE PTSP-BIRF-8649-296 / Líder Agua y Saneamiento Básico Francisco Pizarro - Timbiquí, Component 1. Water Supply Liderar la planificación, estru and Basic Sanitation Improv Ejecución pendien IBRD / 86490 Posterior Individual Limited - National 20,474.00 0.00 2024-11-19 2024-11-24 2024-12-15 2025-01-19 2025-07-18 cturación, seguimiento y ges ements in the Municipality o te tión de los proyectos de Agu f Guapi a y Saneamiento Básico que hagan parte de los préstamo s del Banco Mundial. PTSP-BIRF-8649-293 / Ingeni ero de Apoyo a la Supervisió n - Brindar apoyo profesional a los proyectos del compone Component 4. Project Manag Ejecución pendien nte de ASB en el Distrito de T IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 5,808.00 0.00 2024-11-19 2024-11-29 2024-12-20 2025-01-24 2025-07-23 te umaco para contribuir al cum nd Social Management plimiento de los objetivos del FTSP con la Banca Multilatera l que adelanta como entidad ejecutora el MIE PTSP-BIRF-8649-297 / Especi alista Ambiental - Brindar ap oyo profesional como especi Component 4. Project Manag alista en la planificación, seg Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 6,508.00 0.00 2024-12-16 2024-12-26 2025-01-16 2025-02-20 2025-08-19 uimiento y gestión a la ejecu te nd Social Management ción del Marco de Gestión A mbiental y Social - MGAS en l os proyectos financiados con el préstamo del BM ejecutad o por el MIE PTSP-BIRF-8649-298 / Especi alista Social - Brindar apoyo profesional en el component Component 4. Project Manag e social de los proyectos que Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 23,232.00 0.00 2024-12-16 2024-12-21 2025-01-11 2025-02-15 2025-08-14 se generen en el marco de lo te nd Social Management s préstamos del BM ejecutad os por el Ministerio de Iguald ad y Equidad como entidad e jecutora del FTSP PTSP-BIRF-8649-301 / Lidera r el componente social de los proyectos que se generen en Component 4. Project Manag el marco de los préstamos de IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 34,123.00 0.00 En ejecución 2024-12-20 2024-12-04 2024-12-25 2025-01-15 2025-02-19 2025-08-18 l Banco Mundial ejecutados p nd Social Management or el Ministerio de Igualdad y Equidad como entidad ejecut ora del FTSP PTSP-BIRF-8649-300 / Audito Component 4. Project Manag ría de los Estados Financiero Selección directa IBRD / 86490 ement and Environmental a Posterior Direct - National 27,000.00 0.00 En ejecución 2024-12-20 2025-01-22 2024-12-30 2025-01-23 2025-03-05 2025-09-01 s de propósito especial de pr de consultores nd Social Management oyectos financiados por el Ba nco Mundial. PTSP-BIRF-8649-304 / Presta Component 4. Project Manag r servicios profesionales com Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 27,156.00 0.00 2025-01-31 2025-02-10 2025-03-03 2025-04-07 2026-04-07 o especialista de planeación, te nd Social Management seguimiento y gestión Page 4 PTSP-BIRF-8649-305 / Recon tratación servicios profesiona Component 4. Project Manag Ejecución pendien les del Líder Financiero en la IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 21,538.00 0.00 2025-01-31 2025-02-10 2025-03-03 2025-04-07 2026-04-07 te gestión presupuestal, financi nd Social Management era y contable de los proyect os PTSP-BIRF-8649-306 / Presta Component 4. Project Manag r servicios profesionales com Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 16,294.00 0.00 2025-01-31 2025-02-10 2025-03-03 2025-04-07 2026-04-07 o especialista para la gestión te nd Social Management presupuestal y financiera PTSP-BIRF-8649-307 / Lidera r los procesos de adquisicion es requeridos para la ejecuci Component 4. Project Manag ón de los proyectos que adel Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Limited - National 21,538.00 0.00 2025-02-06 2025-02-11 2025-03-04 2025-04-08 2026-04-08 anta el MIE como entidad eje te nd Social Management cutora del FTSP utilizando los estándares aplicables y las p olíticas de adquisiciones de l a banca multilateral PTSP-BIRF-8649-308 / Recon tratación servicios profesiona Component 4. Project Manag les Especialista Senior ASB e Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 21,538.00 0.00 2025-01-31 2025-02-10 2025-03-03 2025-04-07 2026-04-07 n la articulación integral del te nd Social Management equipo ejecutor en los proyec tos de Agua y Saneamiento B ásico PTSP-BIRF-8649-309 / Lidera r la planificación, estructurac Component 1. Water Supply ión, seguimiento y gestión de and Basic Sanitation Improv Ejecución pendien los proyectos de agua y sane IBRD / 86490 Posterior Individual Limited - National 71,794.00 0.00 2025-01-29 2025-02-03 2025-02-24 2025-03-31 2026-03-31 ements in the Municipality o te amiento básico, que adelanta f Guapi el Ministerio de Igualdad y Eq uidad como entidad ejecutor a del FTSP. PTSP-BIRF-8649-310 / Recon Component 4. Project Manag tratación servicios profesiona Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 16,294.00 0.00 2025-01-31 2025-02-10 2025-03-03 2025-04-07 2026-04-07 les como especialista en los te nd Social Management procesos jurídicos y de adqui siciones PTSP-BIRF-8649-311 / Recon tratación servicios profesiona Component 4. Project Manag les como especialista en los Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 14,700.00 0.00 2025-01-31 2025-02-10 2025-03-03 2025-04-07 2026-04-07 procesos de estructuración y te nd Social Management ejecución de los proyectos d e agua y saneamiento básico . PTSP-BIRF-8649-312 / Recon tratación servicios profesiona Component 4. Project Manag Ejecución pendien les como Viabilizador en los IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 14,700.00 0.00 2025-01-31 2025-02-10 2025-03-03 2025-04-07 2026-04-07 te procesos de viabilización, est nd Social Management ructuración y ejecución. PTSP-BIRF-8649-313 / Presta r servicios como apoyo técni Component 4. Project Manag co en los procesos administr Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 10,200.00 0.00 2025-01-31 2025-02-10 2025-03-03 2025-04-07 2026-04-07 ativos, logísticos y operativos te nd Social Management en el marco de la ejecución d el componente de agua y san eamiento básico PTSP-BIRF-8649-314 / Presta r servicios profesionales com Component 4. Project Manag o especialista para la planific Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 48,880.00 0.00 2025-01-31 2025-02-10 2025-03-03 2025-04-07 2026-04-07 ación, seguimiento y ejecució te nd Social Management n del marco de gestión ambi ental y social - MGAS y segur idad y salud en el trabajo - S &ST PTSP-BIRF-8649-315 / Presta Component 1. Water Supply r servicios profesionales com and Basic Sanitation Improv Ejecución pendien o especialista para la estruct IBRD / 86490 Posterior Individual Direct - National 24,440.00 0.00 2025-01-31 2025-02-10 2025-03-03 2025-04-07 2026-04-07 ements in the Municipality o te uración, seguimiento y gestió f Guapi n de los proyectos de residuo s sólidos PTSP-BIRF-8649-316 / Presta r servicios profesionales com o especialista para las gestio Component 4. Project Manag nes catastrales y prediales re Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 14,664.00 0.00 2025-01-31 2025-02-10 2025-03-03 2025-04-07 2026-04-07 queridas en el saneamiento y te nd Social Management adquisición de predios, a trav és de las modalidades de en ajenación voluntaria, expropi ación o reasentamiento PTSP-BIRF-8649-317 / Presta Component 2. Water Supply r servicios profesionales com and Basic Sanitation Improv Ejecución pendien o Enlace Social en la implem IBRD / 86490 Posterior Individual Direct - National 22,300.00 0.00 2025-01-31 2025-02-10 2025-03-03 2025-04-07 2026-04-07 ements in the Municipality o te entación del componente soc f Tumaco ial en la ejecución de los pro yectos PTSP-BIRF-8649-318 / Presta Component 4. Project Manag Ejecución pendien r servicios profesionales com IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 54,313.00 0.00 2025-02-03 2025-02-13 2025-03-06 2025-04-10 2026-04-10 te o especialista de adquisicion nd Social Management es Page 5