PROCUREMENT PLAN (Textual Part) Project information: Country: Bolivia Project name: Bolivia Urban Resilience Project P-number: P165861 Project Implementation Agencies: Municipality of Santa Cruz (GAMSC) and Municipality of La Paz (GAMLP) Date of the Procurement Plan: September 09, 2021 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers”, dated July 2016, revised November 2017 and August 2018” (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures acceptable for the Bank by the may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not Applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations may be Applicable. Other Relevant Procurement Information. Procurement activities will be undertaken by GAMSC for Part 1 and 3.1; and by the GAMLP for Parts 2 and 3.2. Procurement of Goods, Works and Non-Consulting Services. According the Project Procurement Strategy for Development (PPSD), the open international competitive bidding approach should be applied when the Procurement Plan establishes it, while for small contracts the open national competitive bidding approach is supported by the availability of bidders in the local market. For Works and Gods the Borrower is able to specify detailed requirements to which bidders respond by offering bids; the Request for Bids or the Request for Quotations would be the selection methods for these contracts. Procurement of Consulting Services. Technical Assistance, designs, supervision services, and other studies: Considering that these will be small and medium magnitude contracts, the suitable market approach would be an open competition in the international or national market or direct market approach, while the Quality-Cost- Based Selection or Direct Selection (when a sole firm with needed capabilities is identified and justified) would be the selection methods. Project implementation support personnel. Individuals contracted to support project implementation (project staff), other than individual consulting positions identified in the Legal Agreement, may be selected by the Borrower according to their personnel hiring procedures for such activities, as reviewed and found acceptable by the Bank and described in the POMs. Individual consultants. Individual consultants will be selected for an assignment for which: (i) a team of experts is not required; (ii) no additional office support is required; and (iii) the experience and qualifications of the individual are of paramount requirement. The evaluation shall be based on the relevant qualifications and experience of the individual consultant in accordance with provision of paragraphs 7.34 to 7.39 of the Procurement Regulations. PROCUREMENT Bolivia : Bolivia Urban Resilience PLAN General Information Country: Bolivia 2021-09-09 Bank’s Approval Date of the Original Procurement Plan: 2025-01-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165861 GPN Date: 2021-08-12 Project Name: Bolivia Urban Resilience Loan / Credit No: IDA / 65170 Municipal Autonomous Government of Santa Cruz Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SMOP LPI 001 2021 / Obras Solicitud de Ofert de construccion del canal em Resilient Infrastructure and Solicitud de oferta Open - Internationa Single Stage - One E as - DEA Obras M 22,188,412.0 2024-10-0 isario 8vo Anillo suroeste y m IDA / 65170 Urban Upgrading in Santa Cr Previa 0.00 Cancelado 2021-11-15 2021-11-20 2022-01-04 2022-02-03 2022-03-10 s l nvelope enores (Proceso d 0 3 ejoramiento del espacio publi uz e 1 sobre) co. Incluye salvaguardas soci ales y ambientales SMOP LPI 002-2022 / Constr Solicitud de Ofert Resilient Infrastructure and ucción Canal Emisario 8vo An Solicitud de oferta Open - Internationa Single Stage - One E as - DEA Obras M 23,294,667.3 2025-01-0 IDA / 65170 Urban Upgrading in Santa Cr Previa 0.00 Firmado 2022-02-14 2022-04-08 2022-02-19 2022-06-03 2022-04-05 2022-06-13 2022-05-05 2022-10-13 2022-06-09 2022-12-07 illo Sur Oeste y Mejoramiento s l nvelope enores (Proceso d 4 2 uz de Espacio Público e 1 sobre) Documento de Ad SMOP UT COT 001/2022 / Ma quisiciones con e ntenimiento de Espacio Públi Solicitud de cotiza Single Stage - One E nfoque nacional - 2022-12-2 IDA / 65170 Project Management Posterior Open - National 120,000.00 0.00 Rescindido 2022-09-27 2022-11-22 2023-07-26 co con Urbanismo Táctico en ciones nvelope Proceso de un sob 2 la Zona Central re (No documento estándar del Banc o) Solicitud de Cotiz SES COT 001 2022 / Obras d Resilient Infrastructure and Solicitud de cotiza Single Stage - One E ación (no docume 2022-10-1 e Regeneracion Urbana. Pilot IDA / 65170 Urban Upgrading in Santa Cr Posterior Open - National 120,000.00 0.00 Cancelado 2022-02-20 2022-04-17 ciones nvelope nto estándar del 4 o de Urbanismo Tactico uz Banco) UODPRU-CW-RFQ-001 / MAN TENIMIENTO DE ESPACIO PÚ Solicitud de Cotiz BLICO CON URBANISMO TÁC Resilient Infrastructure and Solicitud de cotiza Single Stage - One E ación (no docume Ejecución p 2025-04-2 TICO EN LA ZONA CENTRAL IDA / 65170 Urban Upgrading in Santa Cr Posterior Open - National 30,000.00 0.00 2025-02-15 2025-03-11 ciones nvelope nto estándar del endiente 5 DM-11 - EL RINCÓN DE LA CR uz Banco) UZ DEL MUNICIPIO DE SANTA CRUZ DE LA SIERRA, SEMPLA DYMA UODPRU-CW-RFB-001 / CON Documento de Ad STRUCCION RED DE CICLOVÍ quisiciones con e AS SOSTENIBLES, ECOLOGIC Resilient Infrastructure and nfoque nacional - AS Y RESILIENTES ZONAS OE Solicitud de oferta Single Stage - One E 11,200,000.0 Ejecución p 2026-04-2 IDA / 65170 Urban Upgrading in Santa Cr Posterior Open - National Proceso de un sob 0.00 2025-02-17 2025-02-18 2025-03-20 2025-04-03 2025-05-02 STE Y NORESTE, UNIDAD OPE s nvelope 0 endiente 7 uz re (No documento RATIVA DESCONCENTRADA D estándar del Banc EL PROYECTO DE RESILIENCI o) A URBANA EN BOLIVIA, SEMP LADYMA GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DPI COT 003 2021 / Utiles d Solicitud de cotiza Single Stage - One E IDA / 65170 Project Management Posterior Open - National 10,000.00 0.00 Cancelado 2021-10-23 2021-12-18 2022-02-01 e escritorio ciones nvelope DPI COT 002 2021 / Adquisic Solicitud de cotiza Single Stage - One E IDA / 65170 Project Management Posterior Open - National 16,961.00 0.00 Cancelado 2021-10-23 2021-12-18 2022-02-01 ión de Muebles y Enseres ciones nvelope DPI COT 001 2021 / Adquisci on de equipos de computacio Solicitud de cotiza Single Stage - One E IDA / 65170 Project Management Posterior Open - National 45,950.00 0.00 Cancelado 2021-10-23 2021-12-23 2022-02-06 n, scanner, fotocopiadora, im ciones nvelope presoras y proyectores DPI COT 002 2022 / Adquisic ión de: Computadoras de esc ritorio, Impresora de plotter, Solicitud de oferta Single Stage - One E IDA / 65170 Project Management Posterior Open - National 82,492.71 0.00 Finalizado 2022-06-10 2022-07-13 2022-06-25 2022-07-13 2022-07-16 2022-08-11 2022-08-03 2022-08-29 2022-09-29 2022-09-13 2022-10-29 2022-11-11 Computadoras portátiles, Pro s nvelope yector multimedia, fotocopia doras, Impresoras de inyecci ón de tinta. DPI COT 001 2022 / Adquisic Solicitud de cotiza Single Stage - One E IDA / 65170 Project Management Posterior Open - National 32,912.39 0.00 Finalizado 2022-07-22 2022-09-22 2022-09-22 2022-11-06 2022-12-01 ión de Equipos de Oficina y M ciones nvelope uebles DPI COT 006 2021 / Adquisi Resilient Infrastructure and Solicitud de cotiza Single Stage - One E IDA / 65170 Posterior Open - National 10,500.00 0.00 Cancelado 2021-11-27 2022-01-22 2022-03-08 cion de 1 Dron Urban Upgrading in Santa Cr ciones nvelope uz DPI COT 004 2021 / Adquisic ion de Equipos de comunicac Solicitud de cotiza Single Stage - One E IDA / 65170 Project Management Posterior Open - National 2,620.00 0.00 Cancelado 2021-10-30 2021-12-25 2022-02-08 ión, GPS, distanciador, radios ciones nvelope walkie talkie, telefonos inala mbricos DPI SDO BS 001 2022 / Adqu isicion de Equipos de comuni Solicitud de oferta Single Stage - One E IDA / 65170 Project Management Posterior Open - National 51,841.11 0.00 Finalizado 2022-08-15 2022-10-11 2022-08-30 2022-09-20 2022-11-10 2022-10-08 2022-11-06 2022-11-07 2022-12-16 2022-12-07 2023-01-30 cación, Mobile phones, Digita s nvelope l cameras, Televisions y Audi o visual technology DPI SDO BS 002 2022 / Adqu Solicitud de oferta Single Stage - One E isiciones de Dos Vehiculos, u IDA / 65170 Project Management Posterior Open - National 66,427.76 0.00 Cancelado 2022-09-05 2022-09-10 2022-10-01 2022-10-19 2022-11-17 2022-12-17 s nvelope na camioneta y una camione ta DPI LPN 001 2021 / Adquisic Solicitud de oferta Single Stage - One E ion de 2 Vehiculos 1 Vagonet IDA / 65170 Project Management Posterior Open - National 75,802.00 0.00 Cancelado 2021-11-01 2021-11-06 2021-12-04 2022-01-03 2022-02-07 2022-03-24 s nvelope a 4x4 y 1 Camioneta 4x4 DPI COT 003 2022 / Calzado Solicitud de cotiza Single Stage - One E IDA / 65170 Project Management Posterior Open - National 7,653.00 0.00 Cancelado 2022-02-06 2022-04-08 2022-05-23 s ciones nvelope DPI COT 002 2022 / Prendas Solicitud de cotiza Single Stage - One E IDA / 65170 Project Management Posterior Open - National 12,755.00 0.00 Cancelado 2022-02-06 2022-04-03 2022-05-18 de vestir ciones nvelope Page 1 DPI-SD-001 / Adquisicion de Adquisición direct IDA / 65170 Project Management Posterior Direct - National 7,200.00 0.00 Finalizado 2022-12-19 2022-12-16 2022-12-24 2023-05-09 2023-01-28 2023-07-06 2023-02-27 2023-11-07 un Software Contable a DPI COT 003 2022 / ADQUISI Solicitud de cotiza Single Stage - One E IDA / 65170 Project Management Posterior Open - National 9,397.00 0.00 Cancelado 2022-09-17 2022-11-12 2022-12-12 CIÓN DE UTILES DE ESCRITO ciones nvelope RIO Y PAPEL DPI SDO BS 003 / Adquisició Solicitud de oferta Single Stage - One E IDA / 65170 Project Management Posterior Open - National 182,653.00 0.00 Finalizado 2023-06-07 2023-06-20 2023-06-12 2023-07-24 2023-07-12 2023-08-23 2023-07-19 2023-09-27 2023-08-18 2023-11-26 2023-09-18 n de (4) Cuatro Vehículos livi s nvelope anos DPI COT 005 / Adquisición d Solicitud de cotiza Single Stage - One E IDA / 65170 Project Management Posterior Open - National 19,000.00 0.00 Finalizado 2023-04-14 2023-06-22 2023-08-04 2023-07-07 2023-08-16 e Útiles de Escritorio y Papel ciones nvelope UODPRU-RFQ-001 / Útiles de Solicitud de cotiza Single Stage - One E IDA / 65170 Project Management Posterior Open - National 9,500.00 0.00 Finalizado 2024-03-09 2024-04-20 2024-04-01 2024-05-20 2024-04-16 Escritorio, Tintas, Toners y Pa ciones nvelope pel DPI COT 004 / Adquisición D e Ropa de Trabajo, Equipos d Solicitud de cotiza Single Stage - One E IDA / 65170 Project Management Posterior Open - National 4,500.00 0.00 Finalizado 2024-08-25 2024-10-13 2024-10-10 2024-10-28 2024-10-25 e Protección Personal y Calza ciones nvelope dos de seguridad UODPRU-RFQ-002 / ADQUISI CIÓN DE EQUIPOS DE COMPU TACIÓN PARA LA UNIDAD OP Solicitud de cotiza Single Stage - One E Ejecución pe IDA / 65170 Project Management Posterior Open - National 30,000.00 0.00 2025-02-12 2025-02-28 2025-03-15 ERATIVA DESCONCENTRADA ciones nvelope ndiente DEL PROYECTO DE RESILIEN CIA URBANA EN BOLIVIA, SE MPLAD NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DPI COT 005 2021 / Seguro Solicitud de cotiza Single Stage - One E IDA / 65170 Project Management Posterior Open - National 3,207.00 0.00 Cancelado 2021-11-20 2022-01-15 2025-06-30 automotor ciones nvelope DPI COT 001 2022 / Publicid Solicitud de cotiza Single Stage - One E IDA / 65170 Project Management Posterior Open - National 14,577.00 0.00 Cancelado 2022-02-06 2022-04-03 2025-06-30 ad ciones nvelope UODPRU-NC-DIR-001 / Servi cio de Mantenimiento y Actu alización de Datos Rinex par Adquisición direct a Dron WINGTRA ONE GENII, IDA / 65170 Project Management Posterior Direct - National 2,000.00 0.00 Finalizado 2024-08-19 2024-09-02 2024-08-24 2024-09-04 2024-09-08 2024-09-16 2024-09-23 2024-09-30 a adquirido a través del proces o de contratación DPI SDO B S 001 2022 de la Unidad Ejec utora del Proyecto. UODPRU-NC-RFQ-001 / SERV ICIO DE ELABORACIÓN Y MO Solicitud de cotiza Single Stage - One E NTAJE DE STAND PARA EL PR IDA / 65170 Project Management Posterior Open - National 15,000.00 0.00 Finalizado 2024-08-28 2024-08-15 2024-09-14 2024-08-29 2024-10-14 2024-10-09 ciones nvelope OYECTO DE RESILIENCIA URB ANA EN BOLIVIA, SEMPLAD CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SMOP CONS 002 2021 / Serv Resilient Infrastructure and icios Consultoria especializad Selección basada IDA / 65170 Urban Upgrading in Santa Cr Posterior Open - National 174,710.00 0.00 Cancelado 2021-11-15 2021-12-06 2022-01-19 2022-02-16 2022-03-18 2022-04-22 2022-05-27 2024-09-30 a fiscalizacion de obras Sec. en calidad y costo uz Mcpal. Obras Publicas SMOP CONS 001 2021 / Serv icios Consultoría especializad a en Supervisión de las Obra Resilient Infrastructure and Selección basada Open - Internationa s Civiles Ambientales y Social IDA / 65170 Urban Upgrading in Santa Cr Posterior 926,023.00 0.00 Cancelado 2021-11-01 2021-11-11 2021-11-22 2022-01-05 2022-02-19 2022-03-21 2022-04-25 2022-05-30 2024-10-17 en calidad y costo l es. uz Obras de Construcción del Ca nal Emisario 8vo. Anillo sur-o este y mejoramiento del esp acio público SMOP LPI 001-2022 / Servici os Consultoría especializada para Supervisión de las Obra Resilient Infrastructure and Selección basada Open - Internationa s Civiles, Ambientales y Soci IDA / 65170 Urban Upgrading in Santa Cr Posterior 722,568.75 0.00 Firmado 2022-02-08 2022-02-10 2022-03-01 2022-03-28 2022-04-14 2022-06-06 2022-05-12 2022-07-20 2022-06-11 2022-08-31 2022-07-16 2022-09-30 2022-08-20 2022-11-17 2023-08-20 en calidad y costo l ales. Construcción del Canal uz Emisario 8vo. Anillo sur-oeste y mejoramiento del espacio p úblico DPI CP 002 2022 / Consultorí a por producto para la elabor ación a diseño final del estud Selección basada IDA / 65170 Project Management Posterior Open - National 150,000.00 0.00 Cancelado 2022-09-26 2022-12-13 2022-10-17 2022-11-30 2022-12-28 2023-01-27 2023-03-03 2023-04-07 2024-04-06 io de Diseño Técnico de Prein en calidad y costo versión del proyecto Constru cción de Obra de Regeneraci ón Urbana Zona Central DPI CP 001 2022 / Consultorí a por producto para la elabor ación del Plan Integral de Ma Selección basada Open - Internationa nejo de Parques Urbanos - PE IDA / 65170 Project Management Posterior 200,000.00 0.00 Cancelado 2022-08-31 2022-12-13 2022-09-21 2022-11-04 2022-12-16 2023-01-15 2023-02-19 2023-03-26 2024-03-25 en calidad y costo l M: Proyecto del Parque Lineal Ecológico Metropolitano de S anta Cruz y su Plan Integral d e Manejo SMTT CP 001-2022 / Consult oría para la elaboración del P Selección basada Open - Internationa lan Maestro de Transporte N IDA / 65170 Project Management Posterior 500,000.00 0.00 Firmado 2022-09-28 2022-12-29 2022-10-19 2023-01-24 2022-11-19 2023-03-30 2022-12-30 2023-05-25 2023-01-20 2023-06-02 2023-02-24 2023-06-26 2023-03-31 2023-09-06 2024-03-30 en calidad y costo l o Motorizado y Proyecto de la Red de Ciclovías Ecológicas, Sustentables y Resilientes DPI SCC 001 / Consultoría pa Selección basada ra el diseño e implementació IDA / 65170 Project Management Posterior en calificaciones d Limited 58,000.00 0.00 Finalizado 2022-11-30 2022-12-01 2022-12-14 2022-12-21 2023-01-13 2023-07-04 2023-02-11 2023-08-09 2023-05-12 2024-05-20 n de Estrategia Comunicacio e consultores nal DPI CONS 002 / Consultoria para la Elaboracion del Plan I Selección basada Open - Internationa ntegral de Manejo de Parque IDA / 65170 Project Management Posterior 200,000.00 0.00 Firmado 2023-01-10 2023-01-18 2023-01-31 2023-02-24 2023-03-16 2023-08-22 2023-04-30 2023-10-03 2023-05-30 2023-11-13 2023-07-04 2023-12-08 2023-08-08 2024-03-08 2024-08-02 en calidad y costo l s Urbanos - PEM, Direccion d e Planificacion Integral, SEMP LAD Page 2 DPI CONS 004 / Servicio de c onsultoría para auditoría fina nciera por el periodo compre Selección basada ndido entre el 10 de marzo al IDA / 65170 Project Management Posterior Open - National 100,000.00 0.00 Finalizado 2023-03-27 2023-03-27 2023-03-27 2023-04-04 2023-05-24 2023-05-17 2023-06-26 2023-06-06 2023-06-30 2023-07-10 2023-07-17 2023-08-10 2024-01-11 2024-02-26 2024-05-03 en el menor costo 31 de diciembre del 2021; 1º de enero al 31 de diciembre de 2022 y 1º de enero al 31 de diciembre de 2023 DPI CONS 001 2022 / Audito Selección basada IDA / 65170 Project Management Posterior Open - National 100,000.00 0.00 Cancelado 2022-12-15 2022-09-12 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2023-12-23 ria Externa Gestiones 2021 - en el menor costo 2022 DPI CONS 003 / Consultoria para la Elaboracion de diseño final de Estudio Diseño Técni Selección basada co de Preinversión del proyec IDA / 65170 Project Management Posterior Open - National 150,000.00 0.00 Firmado 2023-06-02 2023-06-27 2023-06-23 2023-08-06 2024-01-03 2023-09-17 2024-02-09 2023-10-17 2024-02-27 2023-11-21 2024-07-12 2023-12-26 2024-07-31 2024-03-25 en calidad y costo to Construccion de la Obra R egeneracion Urbana Zona Ce ntral, Direccion de Planificaci on Integral, SEMPLAD UODPRU-CS-QCBS-001 / Con sultoría Para La Elaboración Resilient Infrastructure and Del Diseño Del Sistema Muni Selección basada IDA / 65170 Urban Upgrading in Santa Cr Posterior Open - National 190,972.09 0.00 Firmado 2023-12-07 2023-12-07 2023-12-27 2024-01-04 2024-02-09 2024-02-14 2024-03-08 2024-03-27 2024-04-07 2024-04-19 2024-05-12 2024-05-27 2024-06-16 2024-07-17 2024-10-14 cipal De Alerta Temprana, Un en calidad y costo uz idad Operativa Desconcentra da De Proyectos De Resilienc ia Urbana, SEMPLAD UODPRU-CS-LCS-001 / Servi cio de Consultoría para Audit oria Financiera correspondie Selección basada nte al Periodo Comprendido IDA / 65170 Project Management Posterior Open - National 50,000.00 0.00 Firmado 2024-10-02 2024-10-03 2024-10-03 2024-10-05 2024-10-07 2024-10-25 2024-10-23 2024-10-30 2024-10-29 2024-11-11 2024-11-07 2024-11-14 2024-12-24 2025-04-13 en el menor costo del 1 de enero al 31 de dicie mbre del 2024, para el Proye cto de Resiliencia Urbana en Bolivia, Crédito AIF N°6517-B O UODPRU-CS-QCBS-002 / SUP ERVISIÓN TÉCNICA DE OBRA S CIVILES, AMBIENTALES Y S OCIALES PARA LA CONSTRUC Resilient Infrastructure and Selección basada Open - Internationa CIÓN DE LA RED DE CICLOVI IDA / 65170 Urban Upgrading in Santa Cr Posterior 495,000.00 0.00 Cancelado 2024-11-29 2024-12-09 2025-01-03 2025-02-17 2025-03-09 2025-04-09 2025-05-20 2026-09-12 en calidad y costo l AS ECOLÓGICAS, SUSTENTAB uz LES, RESILIENTES Y EL MEJOR AMIENTO DE ESPACIO PÚBLI CO EN EL MUNICIPIO DE SAN TA CRUZ LA SIERRA UODPRU-CS-QCBS-003 / SUP ERVISION TECNICA PARA LA CONSTRUCCION DE PARQUE Resilient Infrastructure and LINEAL ECOLOGICO METROP Selección basada Open - Internationa Ejecución pendien IDA / 65170 Urban Upgrading in Santa Cr Posterior 460,000.00 0.00 2025-01-27 2025-02-11 2025-03-04 2025-04-18 2025-05-02 2025-05-19 2025-06-09 2026-06-09 OLITANO RESILENTE RIO PIR en calidad y costo l te uz AI, UNIDAD OPERATIVA DESC ONCENTRADA DEL PROYECT O DE RESILIENCIA URBANA E N BOLIVIA, SEMPLADYMA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DPI CI 001 2021 / Especialist IDA / 65170 Project Management Posterior Individual Open 116,790.00 0.00 Cancelado 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Social DPI CI 002 2021 / Especialist IDA / 65170 Project Management Posterior Individual Open 116,790.00 0.00 Cancelado 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Ambiental DPI CI 003 2021 / Especialist IDA / 65170 Project Management Posterior Individual Open 116,790.00 0.00 Cancelado 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a en Monitoreo DPI CI 004 2021 / Especialist IDA / 65170 Project Management Posterior Individual Open 116,790.00 0.00 Cancelado 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Financiero DPI CI 005 2021 / Especialist IDA / 65170 Project Management Previa Individual Open 116,790.00 0.00 Cancelado 2021-10-01 2021-09-20 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a en Adquisiciones DPI CI 006 2021 / Especialist IDA / 65170 Project Management Posterior Individual Open 116,790.00 0.00 Cancelado 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Legal DPI CI 007 2021 / Especialist IDA / 65170 Project Management Posterior Individual Open 116,790.00 0.00 Cancelado 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Comunicador DPI CI 008 2021 / Especialist IDA / 65170 Project Management Posterior Individual Open 116,790.00 0.00 Cancelado 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Infraestructura Resiliente DPI CI 009 2021 / Profesiona IDA / 65170 Project Management Posterior Individual Open 63,289.00 0.00 Cancelado 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 l A Asistente Administrativo DPI CI 010 2021 / Chofer A IDA / 65170 Project Management Posterior Individual Open 37,854.00 0.00 Cancelado 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 DPI CI 001 2022 / Profesiona IDA / 65170 Project Management Posterior Individual Open 63,289.00 0.00 Cancelado 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 l A Contador Auditor Analista Contable DPI CI 002 2022 / Profesiona IDA / 65170 Project Management Posterior Individual Open 63,289.00 0.00 Cancelado 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 l A Analista Presupuestario DPI CI 003 2022 / Profesiona IDA / 65170 Project Management Previa Individual Open 63,289.00 0.00 Cancelado 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 l A Analista en Adquisiciones 1 DPI CI 004 2022 / Profesiona IDA / 65170 Project Management Posterior Individual Open 57,149.00 0.00 Cancelado 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 l B Asistente Legal DPI CI 005 2022 / Asistente IDA / 65170 Project Management Posterior Individual Open 51,464.00 0.00 Cancelado 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 A en Archivo DPI CI 006 2022 / Chofer A IDA / 65170 Project Management Posterior Individual Open 37,854.00 0.00 Cancelado 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 SMOP CI 001-2022 / Fiscal d Resilient Infrastructure and e Obra para el canal emisario IDA / 65170 Urban Upgrading in Santa Cr Posterior Individual Open 45,450.44 0.00 Firmado 2022-02-08 2022-10-24 2022-03-29 2022-10-26 2022-04-19 2022-11-30 2022-05-24 2022-12-01 2022-11-20 8vo. Anillo sur-oeste uz Page 3 SMOP CI 002-2022 / Fiscal A Resilient Infrastructure and mbiental para el canal emisa IDA / 65170 Urban Upgrading in Santa Cr Posterior Individual Open 45,450.44 0.00 Firmado 2022-02-08 2022-10-24 2022-03-29 2022-10-26 2022-04-19 2022-11-09 2022-05-24 2022-12-15 2022-11-20 rio 8vo. Anillo sur-oeste uz SMOP CI 003-2022 / Fiscal S Resilient Infrastructure and ocial para el canal emisario 8 IDA / 65170 Urban Upgrading in Santa Cr Posterior Individual Open 45,450.44 0.00 Firmado 2022-02-08 2022-10-24 2022-03-29 2022-10-26 2022-04-19 2022-11-30 2022-05-24 2022-12-01 2022-11-20 vo. Anillo sur-oeste uz DPI CI 008-2022 / Consultor de línea Especialista en Infra IDA / 65170 Project Management Posterior Individual Open 116,790.00 16,573.91 Finalizado 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-14 2025-11-10 2024-01-29 estructura Resiliente DPI CI 005-2022 / Consultor IDA / 65170 Project Management Previa Individual Open 116,790.00 0.00 Firmado 2022-02-11 2022-02-14 2022-04-01 2022-03-13 2022-04-22 2022-12-09 2022-05-27 2022-04-14 2025-11-10 de línea Especialista en Adqu isiciones DPI CI 001-2022 / Consultor de línea Especialista en Salva IDA / 65170 Project Management Posterior Individual Open 116,790.00 16,573.91 Rescindido 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-14 2025-11-10 guarda Social DPI CI 004-2022 / Consultor IDA / 65170 Project Management Posterior Individual Open 116,790.00 16,549.83 Rescindido 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-14 2025-11-10 de línea Especialista Financie ro DPI CI 007-2022 / Consultor IDA / 65170 Project Management Posterior Individual Open 116,790.00 16,573.91 Finalizado 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-14 2025-11-10 2023-01-03 de línea Especialista Comuni cador DPI CI 006-2022 / Consultor IDA / 65170 Project Management Posterior Individual Open 116,790.00 16,573.91 Rescindido 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-14 2025-11-10 de línea Especialista Legal DPI CI 003-2022 / Consultor IDA / 65170 Project Management Posterior Individual Open 116,790.00 16,549.83 Rescindido 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-14 2025-11-10 de línea Especialista en Moni toreo DPI CI 014-2022 / Consultor IDA / 65170 Project Management Posterior Individual Open 37,854.00 0.00 Firmado 2022-02-11 2023-10-09 2022-06-17 2023-10-24 2022-07-08 2023-11-13 2022-08-12 2023-11-20 2026-01-26 de línea Chofer A DPI CI 002-2022 / Consultor de línea Especialista en Salva IDA / 65170 Project Management Posterior Individual Open 116,790.00 16,549.83 Firmado 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-14 2025-11-10 guarda Ambiental DPI CI 009-2022 / Consultor de línea Profesional A – Asist IDA / 65170 Project Management Posterior Individual Open 63,288.00 8,994.49 Firmado 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-14 2025-11-10 ente Administrativo DPI CI 010-2022 / Consultor IDA / 65170 Project Management Posterior Individual Open 63,288.00 8,968.37 Rescindido 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-14 2025-07-10 de línea Profesional A - Analis ta Contable DPI CI 011-2022 / Consultor de línea Profesional A - Analis IDA / 65170 Project Management Posterior Individual Open 63,288.00 8,981.41 Rescindido 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-27 2025-07-10 2022-09-11 ta Presupuestario DPI CI 012-2022 / Consultor de línea Profesional A - Analis IDA / 65170 Project Management Posterior Individual Open 63,288.00 8,968.37 Rescindido 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-07 2022-05-27 2022-04-14 2025-07-10 ta de Procesos de Adquisicio nes DPI CI 013-2022 / Consultor IDA / 65170 Project Management Posterior Individual Open 57,149.00 8,110.08 Rescindido 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-05 2022-05-27 2022-04-14 2025-07-10 de línea Profesional B – Técni co Legal SES CI 002 2022 / Consultor Resilient Infrastructure and especialista Fiscal de Obras d IDA / 65170 Urban Upgrading in Santa Cr Posterior Individual Open 10,700.00 0.00 Cancelado 2022-02-07 2022-03-28 2022-04-18 2022-05-23 2022-11-19 e Regeneracion Urbana. Pilot uz o de Urbanismo Tactico SMOP UT CI 002-2022 / Cons ultor de linea Fiscal de Obra IDA / 65170 Project Management Posterior Individual Open - National 6,060.06 0.00 Finalizado 2022-09-22 2023-05-10 2022-11-05 2023-06-12 2022-11-26 2023-06-12 2022-12-27 2023-07-26 2023-06-25 2024-01-29 para el Mantenimiento de Es pacio Público con Urbanismo Táctico Zona Central SMOP UT CI 001-2022 / Cons ultor de linea Supervisor de o bra para el Mantenimiento d IDA / 65170 Project Management Posterior Individual Open - National 6,060.06 0.00 Firmado 2022-09-22 2023-05-10 2022-11-05 2023-06-20 2022-11-26 2023-06-29 2022-12-27 2023-07-20 2023-06-25 e Espacio Público con Urbani smo Táctico Zona Central SES CI 001 2022 / Consultor especialista Supervisor de la IDA / 65170 Project Management Posterior Individual Open 10,700.00 0.00 Cancelado 2022-02-07 2022-03-28 2022-04-18 2022-05-23 2022-11-19 Obras de Regeneracion Urba na. Piloto de Urbanismo Tacti co SMOP UT CP 001-2022 / Con sultor por producto para la cr eación de trabajos de pintura Selección directa IDA / 65170 Project Management Posterior Direct - National 9,475.22 0.00 Rescindido 2022-09-22 2022-10-10 2022-10-02 2023-05-31 2022-12-06 2023-06-26 2023-03-06 mural para el Mantenimiento de consultores de Espacio Público con Urban ismo Táctico Zona Central pa ra la Pascana de la Recova SMOP UT CP 002 2022 / Con sultor por producto para la cr eación de trabajos de pintura Selección directa IDA / 65170 Project Management Posterior Direct - National 2,478.13 0.00 Rescindido 2022-09-22 2022-08-19 2022-10-02 2023-05-31 2022-12-06 2023-07-10 2023-03-06 mural para el Mantenimiento de consultores de Espacio Público con Urban ismo Táctico Zona Central pa ra la Zona Hospitalaria SMOP UT CP 003 2022 / Con sultor por producto para la cr eación de trabajos de pintura Selección directa IDA / 65170 Project Management Posterior Direct - National 947.52 0.00 Rescindido 2022-09-01 2023-05-10 2022-09-11 2023-05-31 2022-11-15 2023-07-10 2023-05-14 mural para el Mantenimiento de consultores de Espacio Público con Urban ismo Táctico Zona Central pa ra el Rincon de la Cruz DPI CI 015 / Consultor de Lin IDA / 65170 Project Management Posterior Individual Open - National 31,645.00 0.00 Cancelado 2023-04-10 2023-05-19 2023-05-23 2023-07-25 2023-06-13 2023-08-09 2023-07-08 2025-06-13 ea Profesional A - Analista Pr esupuestario DPI CI 016 / Consultor de Lin ea Profesional A - Analista de IDA / 65170 Project Management Posterior Individual Open - National 31,645.00 0.00 Finalizado 2023-04-10 2023-05-19 2023-05-23 2023-07-25 2023-06-13 2023-08-09 2023-07-08 2023-08-24 2025-06-13 2024-01-03 Procesos de Adquisiciones DPI CI 018 / Consultor de Lin ea Profesional B - Personal d IDA / 65170 Project Management Posterior Individual Open - National 28,575.00 0.00 Finalizado 2023-04-10 2023-05-19 2023-05-24 2023-07-25 2023-06-07 2023-08-09 2023-07-08 2023-08-24 2025-06-13 2024-01-03 e Apoyo - Archivo Page 4 DPI CI 017 / Consultor de Lin Resilient Infrastructure and IDA / 65170 Posterior Individual Open - National 58,395.00 0.00 Cancelado 2023-06-15 2023-09-15 2023-07-29 2023-07-28 2023-08-12 2023-08-15 2023-09-12 2025-06-30 ea Especialista Comunicador Urban Upgrading in Santa Cr uz DPI CI 019 / Consultor de lín IDA / 65170 Project Management Posterior Individual Open - National 58,395.00 0.00 Firmado 2023-06-15 2023-06-07 2023-07-28 2023-08-31 2023-08-18 2023-09-11 2023-09-12 2023-09-19 2025-06-30 ea Especialista Legal UODPRU-CS-INDV-002 / Con sultor de Línea Encargado de IDA / 65170 Project Management Posterior Individual Open - National 29,460.00 0.00 Rescindido 2023-10-11 2023-11-03 2023-10-27 2023-11-08 2023-10-29 2023-11-14 2023-11-09 2023-11-20 2025-07-01 Inversión e Ingresos Públicos UODPRU-CS-INDV-005 / Con sultor de Línea Especialista e IDA / 65170 Project Management Posterior Individual Open - National 38,930.00 0.00 Firmado 2023-10-12 2023-11-13 2023-10-22 2023-11-20 2023-10-24 2023-11-27 2023-11-14 2023-12-01 2025-07-06 n Monitoreo UODPRU-CS-INDV-001 / Con sultor de Línea en Especialist IDA / 65170 Project Management Posterior Individual Open - National 38,930.00 0.00 Rescindido 2023-10-13 2023-10-16 2023-11-16 2023-10-24 2023-12-07 2023-11-06 2024-01-11 2023-11-13 2025-06-30 a Comunicador UODPRU-CS-INDV-004 / Con sultor de Línea Analista en Pr IDA / 65170 Project Management Posterior Individual Open - National 21,096.00 0.00 Firmado 2023-11-15 2023-11-10 2023-12-01 2023-12-08 2023-12-06 2023-12-12 2023-12-16 2023-12-15 2025-06-30 ocesos de Adquisición UODPRU-CS-INDV-D-001 / Co ntratacion de dos (2) Consult or Individual De Línea Superv isor De Obras Civiles, Ambien tales Y Sociales Para La Cons IDA / 65170 Project Management Posterior Individual Direct - National 18,110.20 0.00 Cancelado 2023-12-07 2024-01-09 2023-12-17 2024-02-19 2023-12-28 2024-02-22 2024-01-07 2024-06-05 trucción Del Canal Emisario 8 vo Anillo Sur Oeste Y Mejora miento De Espacio Público En El Municipio De Santa Cruz D e La Sierra UODPRU-CS-INDV-006 / Con sultor individual de linea Enc IDA / 65170 Project Management Posterior Individual Open - National 28,675.00 0.00 Firmado 2023-12-08 2024-01-03 2024-01-07 2024-02-06 2024-01-17 2024-02-06 2024-02-21 2024-02-15 2025-06-30 argado de Proyectos para la UEP UODPRU-CS-INDV-009 / Espe IDA / 65170 Project Management Posterior Individual Open - National 35,037.00 0.00 Firmado 2023-12-29 2024-01-09 2024-02-16 2024-02-07 2024-03-08 2024-02-07 2024-04-05 2024-02-19 2025-06-30 cialista en Infraestructura Re siliente UODPRU-CDS-001 / Servicios Consultoría especializada par a Supervisión de las Obras Ci Resilient Infrastructure and Selección directa Direct - Internation viles, Ambientales y Sociales. IDA / 65170 Urban Upgrading in Santa Cr Posterior 444,155.69 0.00 Firmado 2024-01-15 2023-12-19 2024-01-25 2024-03-01 2024-03-30 2024-06-12 2025-06-30 de consultores al Construcción del Canal Emisa uz rio 8vo. Anillo sur-oeste y me joramiento del espacio públic o UODPRU-CS-INDV-007 / CON SULTOR INDIVIDUAL DE LINE IDA / 65170 Project Management Posterior Individual Open - National 12,200.00 0.00 Firmado 2024-03-11 2024-03-26 2024-03-19 2024-04-08 2024-03-21 2024-04-16 2024-04-04 2024-04-16 2024-12-31 A RESPONSABLE DE ARCHIV O UODPRU-CS-INDV-D-001-1 / CONTRATACION DE DOS (2) CONSULTOR INDIVIDUAL DE LINEA INSPECTOR DE OBRA P ARA LA EJECUCIÓN DE OBRA IDA / 65170 Project Management Posterior Individual Direct - National 14,500.00 0.00 Finalizado 2024-03-06 2024-03-05 2024-03-16 2024-03-06 2024-03-21 2024-03-14 2024-03-31 2024-03-15 2024-08-28 2024-09-11 S CIVILES, AMBIENTALES Y S OCIALES PARA LA CONTRUCC IÓN DEL CANAL EMISARIO 8V O ANILLO SUR OESTE Y MEJO RAMIENTO DE ESPACIO PUBL ICO EN El MUNICIPIO DE SAN TA CRUZ UODPRU-CS-INDV-008 / CON SULTOR INDIVIDUAL DE LÍNE A ESPECIALISTA EN SALVAGU ARDA SOCIAL, PARA LA UNID IDA / 65170 Project Management Posterior Individual Open - National 19,500.00 0.00 Firmado 2024-03-20 2024-04-01 2024-04-24 2024-04-29 2024-05-15 2024-04-30 2024-06-08 2024-05-13 2024-12-19 AD OPERATIVA DESCONCENT RADA DEL PROYECTO DE RES ILIENCIA URBANA EN BOLIVIA , SEMPLAD UODPRU-CS-INDV-010 / CON SULTOR INDIVIDUAL DE LÍNE A CHOFER, PARA LA UNIDAD IDA / 65170 Project Management Posterior Individual Open - National 6,200.00 0.00 Firmado 2024-03-20 2024-03-07 2024-04-14 2024-03-26 2024-04-25 2024-03-25 2024-05-30 2024-04-02 2024-12-30 OPERATIVA DESCONCENTRA DA DEL PROYECTO DE RESILI ENCIA URBANA EN BOLIVIA, SEMPLAD UODPRU-CS-INDV-012 / CON SULTOR INDIVIDUAL DE LINE A EXPERTO EN DISEÑO URBA IDA / 65170 Project Management Posterior Individual Open - National 21,500.00 0.00 Firmado 2024-04-29 2024-04-19 2024-06-01 2024-05-03 2024-06-22 2024-05-14 2024-07-13 2024-05-21 2025-06-30 NO PARA LA UNIDAD OPERAT IVA DESCONCENTRADA DEL PROYECTO DE RESILIENCIA U RBANA EN BOLIVIA, SEMPLA D UODPRU-CS-INDV-011 / CON SULTOR INDIVIDUAL DE LÍNE A ESPECIALISTA FINANCIERO IDA / 65170 Project Management Posterior Individual Open - National 23,358.00 0.00 Firmado 2024-07-15 2024-06-28 2024-08-14 2024-08-07 2024-09-04 2024-08-08 2024-10-09 2024-08-16 2025-06-30 PARA LA UNIDAD OPERATIVA DESCONCENTRADA DEL PRO YECTO DE RESILIENCIA URBA NA EN BOLIVIA, SEMPLAD UODPRU-CS-INDV-013 / CON SULTOR INDIVIDUAL DE LÍNE A ENCARGADO DE INVERSIÓ N E INGRESOS PÚBLICOS PAR IDA / 65170 Project Management Posterior Individual Open - National 18,180.00 0.00 Firmado 2024-07-15 2024-08-07 2024-07-31 2024-08-20 2024-08-02 2024-08-21 2024-08-13 2024-08-30 2025-06-30 A LA UNIDAD OPERATIVA DE SCONCENTRADA DEL PROYE CTO DE RESILIENCIA URBANA EN BOLIVIA, SEMPLAD UODPRU-CS-INDV-014 / CON SULTOR INDIVIDUAL DE LINE A TÉCNICO EN SALVAGUARD A AMBIENTAL PARA LA UNIDA IDA / 65170 Project Management Posterior Individual Open - National 18,180.00 0.00 Firmado 2024-07-22 2024-07-18 2024-08-25 2024-08-08 2024-09-15 2024-08-09 2024-10-13 2024-08-15 2024-12-31 D OPERATIVA DESCONCENTR ADA DEL PROYECTO DE RESI LIENCIA URBANA EN BOLIVIA, SEMPLAD UODPRU-CS-INDV-003 / Con IDA / 65170 Project Management Posterior Individual Open - National 16,000.00 0.00 Firmado 2024-09-02 2024-06-24 2024-09-18 2024-07-04 2024-09-20 2024-07-05 2024-10-01 2024-07-15 2026-06-30 sultor de Línea Analista Finan ciero Page 5 UODPRU-CS-INDV-016 / CON SULTOR INDIVIDUAL DE LÍNE A ANALISTA DE PROCESOS D E ADQUISICION PARA LA UNI IDA / 65170 Project Management Posterior Individual Open - National 12,000.00 0.00 Cancelado 2024-10-15 2024-10-15 2024-12-03 2024-10-29 2024-12-10 2024-10-29 2024-12-24 2024-12-31 DAD OPERATIVA DESCONCE NTRADA DEL PROYECTO DE RESILIENCIA URBANA EN BOL IVIA, SEMPLAD UODPRU-CS-IND-D-003 / CO Selección directa NSULTOR INDIVIDUAL DE LIN IDA / 65170 Project Management Posterior Direct - National 2,500.00 0.00 Finalizado 2024-10-14 2024-10-14 2024-10-19 2024-10-14 2024-10-31 2024-10-23 2024-12-30 2024-12-23 de consultores EA TÉCNICO LEGAL UODPRU-CDS-002 / SUPERVI SIÓN TÉCNICA PARA LA CON Resilient Infrastructure and Selección directa Direct - Internation STRUCCIÓN RED DE CICLOVI IDA / 65170 Urban Upgrading in Santa Cr Posterior 554,000.00 0.00 En ejecución 2024-12-10 2024-12-11 2024-12-20 2025-02-23 2026-06-18 de consultores al AS SOSTENIBLES, ECOLOGIC uz AS Y RESILIENTES ZONA OES TE y ZONA NORESTE UODPRU-CS-INDV-018 / CON SULTOR INDIVIDUAL DE LÍNE A TÉCNICO EN SALVAGUARD A SOCIAL PARA LA UNIDAD O IDA / 65170 Project Management Posterior Individual Open - National 30,000.00 0.00 Firmado 2024-12-04 2024-12-02 2024-12-12 2024-12-12 2024-12-14 2024-12-12 2024-12-20 2024-12-18 2026-08-31 PERATIVA DESCONCENTRAD A DEL PROYECTO DE RESILIE NCIA URBANA EN BOLIVIA, S EMPLADYMA UODPRU-CS-INDV-019 / CON SULTOR INDIVIDUAL DE LÍNE A ESPECIALISTA COMUNICAD OR PARA LA UNIDAD OPERAT IDA / 65170 Project Management Posterior Individual Open - National 38,200.00 0.00 Firmado 2024-12-05 2024-12-02 2024-12-13 2024-12-20 2024-12-15 2024-12-23 2024-12-22 2024-12-27 2026-08-31 IVA DESCONCENTRADA DEL PROYECTO DE RESILIENCIA U RBANA EN BOLIVIA, SEMPLA DYMA UODPRU-CS-INDV-015 / CON SULTOR INDIVIDUAL DE LINE A PROFESIONAL ADMINISTRA IDA / 65170 Project Management Posterior Individual Open - National 17,000.00 0.00 Bajo Revision 2025-01-20 2025-01-23 2025-02-10 2025-02-15 2025-02-22 2025-12-31 TIVO LEGAL PARA LA UNIDAD OPERATIVA DESCONCENTRA DA DEL PROYECTO DE RESILI ENCIA URBANA EN BOLIVIA UODPRU-CS-INDV-020 / CON SULTOR INDIVIDUAL DE LÍNE Resilient Infrastructure and A FISCAL AMBIENTAL PARA L Ejecución pendien IDA / 65170 Urban Upgrading in Santa Cr Posterior Individual Open - National 16,500.00 0.00 2025-01-24 2025-02-03 2025-02-05 2025-02-11 2025-12-31 A UNIDAD OPERATIVA DESCO te uz NCENTRADA DEL PROYECTO DE RESILIENCIA URBANA EN BOLIVIA, SEMPLADYMA UODPRU-CS-INDV-017 / CON SULTOR INDIVIDUAL DE LÍNE A ANALISTA DE PROCESOS D Ejecución pendien E ADQUISICION PARA LA UNI IDA / 65170 Project Management Posterior Individual Open - National 20,000.00 0.00 2025-02-23 2025-03-05 2025-03-07 2025-03-12 2025-12-31 te DAD OPERATIVA DESCONCE NTRADA DEL PROYECTO DE RESILIENCIA URBANA EN BOL IVIA, SEMPLAD Page 6