PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Urban Productive Safety Net and Jobs Project (P169943) Project Implementation agency: Ministry of Labor and Social Affairs (MoLSA), Ministry of Urban Development and Construction (MoUDC), Urban Job Creation and Food Security Agency (UJCFSA) Date of the Procurement Plan: November 2020. Period covered by this Procurement Plan: December 2020 to December 2021. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from page 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : Urban Productive Safety Net and Jobs Project PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2021-08-27 Revised Plan Date(s): (comma delineated, leave blank if2025-01-24 none) Project ID: P169943 GPN Date: 2020-12-18 Project Name: Urban Productive Safety Net and Jobs Project Loan / Credit No: IDA / D7320, IDA / E3010 Oromya Regional State Urban Development and Housing Bureau Executing Agency(ies): WORKS Activity Reference No. Procurement Estimate Actual A Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl / Description Component Review Type Method Document Ty d Amount mount ( rt and Recommenda Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe (US$) US$) tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planne d ET-OROMIA-GINCHI-28117 Expand the Urban Product Request for Qu 6-CW-RFQ / Procurement o Request for Quo Single Stage - On Complete 2022-03-2 2022-03-2 2022-04-2 2022-04-2 2022-05- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 1,918.00 0.00 f Labor Semi-Skill for Fenc tations e Envelope d 1 5 8 1 28 the Urban Environment ank-SPD) e Construction Green Area ET-OROMIA-MATU-281211 Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-03-2 2022-05-0 2022-04-2 2022-05-1 2022-06- -CW-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 4,640.52 0.00 tations e Envelope d 2 3 8 2 26 Labor Semi-Skill for the Pu the Urban Environment ank-SPD) blic Toilet ET-OROMIA-CHIRO-28122 Expand the Urban Product Request for Qu 0-CW-RFQ / procurement o Request for Quo Single Stage - On Complete 2022-03-2 2022-03-2 2022-04-2 2022-04-1 2022-06- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 4,270.00 0.00 f Labor sem-skill for Public tations e Envelope d 1 8 7 4 30 the Urban Environment ank-SPD) Toilet in Lot -1 and Fence Construction in Lot- 2 ET-OROMIA-MAKI-281315- Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-03-2 2022-04-1 2022-04-2 2022-05-1 2022-07- CW-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 3,784.00 0.00 tations e Envelope d 2 1 8 0 04 Labor sem-skill for the con the Urban Environment ank-SPD) struction of Public Toilet ET-OROMIA-YABELO-2813 Expand the Urban Product Request for Qu 14-CW-RFQ / Procurement Request for Quo Single Stage - On Complete 2022-03-2 2022-04-2 2022-05-0 2022-05-2 2022-07- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 4,442.00 0.00 of Labor sam-skill for the c tations e Envelope d 3 0 2 7 01 the Urban Environment ank-SPD) onstruction of Public Toilet ET-OROMIA-AGARO-28131 Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-03-2 2022-05-1 2022-05-0 2022-06-0 2022-07- 6-CW-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 4,784.00 0.00 tations e Envelope d 3 6 2 1 06 f Labor sem-skill for the co the Urban Environment ank-SPD) nstruction of Public Toile ET-OROMIA-NEGELE BORA NA-281454-CW-RFQ / Proc Expand the Urban Product Request for Qu Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-07- urement of Labor Sem-skill IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 3,400.00 0.00 Canceled tations e Envelope 1 8 02 for the Construction of Fen the Urban Environment ank-SPD) ce Construction in Lot-1 an d Watershed Management work in Lot-2 ET-OROMIA-BURAYU-2814 Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-03-2 2022-04-0 2022-05-0 2022-04-2 2022-07- 86-CW-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 4,900.00 0.00 tations e Envelope d 3 6 7 5 06 of Skill Labor for the Const the Urban Environment ank-SPD) ruction of Public Toilet ET-OROMIA-BADESA-2815 Expand the Urban Product Request for Qu 56-CW-RFQ / Procurement Request for Quo Single Stage - On Complete 2022-03-2 2022-05-2 2022-04-2 2022-07-0 2022-07- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 5,180.00 0.00 of Labor sem-skill for the C tations e Envelope d 2 7 8 4 01 the Urban Environment ank-SPD) onstruction of Public Toile ET-OROMIA-WALISO-2817 Expand the Urban Product Request for Qu 17-CW-RFQ / Procurement Request for Quo Single Stage - On Complete 2022-03-2 2022-05-2 2022-04-2 2022-06-1 2022-07- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 5,000.00 0.00 of Labor sem-skill for the c tations e Envelope d 2 3 8 0 01 the Urban Environment ank-SPD) onstruction of public Toilet ET-OROMIA-HARAMAYA-2 Expand the Urban Product Request for Qu 81778-CW-RFQ / Procurem Request for Quo Single Stage - On 2022-03-2 2022-06-2 2022-04-2 2022-07-1 2022-07- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 3,330.00 0.00 Signed ent of Labor sem-skill for t tations e Envelope 2 1 8 6 04 the Urban Environment ank-SPD) he Construction of Public T oilet ET-OROMIA-BISHOFTU-28 Expand the Urban Product Request for Qu 1800-CW-RFQ / Procureme Request for Quo Single Stage - On Complete 2022-03-2 2022-05-1 2022-05-1 2022-06-0 2022-07- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 5,050.00 0.00 nt of Labor sem-skill for th tations e Envelope d 8 1 2 7 06 the Urban Environment ank-SPD) e Construction of Public To ilet Request for Qu ET-JIMMA-UDHB-281813-C Expand the Urban Product otations - Small Request for Quo Single Stage - On Complete 2022-03-2 2022-03-2 2022-05-1 2022-06-2 2022-06- W-RFQ / Procurement of sk IDA / D7320 ive Safety Net to Improve Post Limited Works (Emerge 4,900.00 0.00 tations e Envelope d 3 5 8 1 17 illed labor for the construct the Urban Environment ncy) SPD -Comp ion of public toilet etitive ET-OROMIA-SHAMBU-282 Expand the Urban Product Request for Qu Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-07- 112-CW-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 882.00 0.00 Canceled tations e Envelope 2 6 05 t of Skilled Labor for the C the Urban Environment ank-SPD) onstruction of Fence ET-OROMIA-GIMBI-282132 Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-03-2 2022-06-0 2022-05-0 2022-07-0 2022-07- -CW-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 2,650.00 0.00 tations e Envelope d 7 8 7 2 06 Skilled Labor for the Const the Urban Environment ank-SPD) ruction of Public Toilet ET-OROMIA-BATU-282189 Expand the Urban Product Request for Qu -GO-RFQ / Procurement of Request for Quo Single Stage - On Complete 2022-03-2 2022-05-0 2022-05-0 2022-06-0 2022-07- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 3,100.00 0.00 Skilled Labor for the Const tations e Envelope d 8 7 9 1 08 the Urban Environment ank-SPD) ruction of Greenery Fence ET-OROMIA-BULE HORA-2 Expand the Urban Product Request for Qu 82198-CW-RFQ / Procurem Request for Quo Single Stage - On Complete 2022-03-2 2022-04-2 2022-05-0 2022-05-2 2022-07- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 4,370.00 0.00 ent of Skilled Labor for the tations e Envelope d 8 0 9 5 08 the Urban Environment ank-SPD) construction of Public Toile ET-OROMIA-BEDELE-2852 37-CW-RFQ / Procurement Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-03-3 2022-05-2 2022-05-1 2022-06-0 2022-07- of Skill Labor for the Const IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 7,250.00 0.00 tations e Envelope d 0 7 4 3 08 ruction of Public Toilet in L the Urban Environment ank-SPD) ot -1 and Fence Constructi on for the Greenery in Lot- 2 ET-OROMIA-ADAMA-30970 7-CW-RFQ / Procurement o Expand the Urban Product Request for Qu f Skilled Labor for the cons Request for Quo Single Stage - On 2022-09-2 2023-05-2 2022-11-1 2024-06-1 2023-01- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 25,961.00 0.00 Signed truction of Public Toilet, co tations e Envelope 6 4 5 4 19 the Urban Environment ank-SPD) nstruction of additional cla ss room for education and the construction of Fence f or Greenery ET-OROMIA-JIMA-309729- Expand the Urban Product Request for Qu Request for Quo Single Stage - On 2022-10-0 2023-03-0 2022-11-2 2023-04-1 2023-01- CW-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 17,307.00 0.00 Signed tations e Envelope 4 2 3 2 27 Skilled labor for the Procur the Urban Environment ank-SPD) ement of Public Toilet ET-OROMIA-AGARO-30975 Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-10-0 2023-05-0 2022-11-2 2023-05-3 2023-01- 9-CW-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 6,730.00 0.00 tations e Envelope d 4 9 2 1 26 f Skilled Labor for the cons the Urban Environment ank-SPD) truction of Public Toile ET-OROMIA-CHIRO-30987 Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-10-0 2023-02-2 2022-11-2 2023-03-3 2023-01- 1-CW-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 5,777.00 0.00 tations e Envelope d 5 7 3 1 27 f Skilled labor for the Cons the Urban Environment ank-SPD) truction of Public Toilet ET-OROMIA-DERA-309922 Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-10-0 2023-04-2 2022-11-2 2023-03-3 2023-01- -CW-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 3,695.00 0.00 tations e Envelope d 4 8 2 0 26 Skilled Labor for the constr the Urban Environment ank-SPD) uction of Public Toilet ET-OROMIA-FICH-310440- Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-09-2 2023-06-0 2022-11-0 2023-06-2 2023-01- CW-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 4,807.00 0.00 tations e Envelope d 0 6 8 7 12 Skilled Labor for the constr the Urban Environment ank-SPD) uction of Public Toilet ET-OROMIA-NEGELE ARSI- Expand the Urban Product Request for Qu 310502-CW-RFQ / Procure Request for Quo Single Stage - On Complete 2022-10-0 2023-04-2 2022-11-2 2023-05-1 2023-01- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 16,000.00 0.00 ment of Skilled Labor for t tations e Envelope d 4 0 2 7 26 the Urban Environment ank-SPD) he construction of Public T oilet ET-OROMIA-SABATA-3109 Expand the Urban Product Request for Qu Request for Quo Single Stage - On 2022-10-0 2023-06-1 2022-11-2 2023-07-0 2023-01- 51-CW-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 7,668.00 0.00 Signed tations e Envelope 3 2 1 5 25 of skilled Labor for the con the Urban Environment ank-SPD) struction of public Toile ET-OROMIA-SHASHAMANE -311128-CW-RFQ / procure Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-10-0 2023-06-0 2022-11-2 2023-06-2 2023-01- ment of Skilled Labor for t IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 14,846.00 0.00 tations e Envelope d 3 6 2 3 26 he construction of children the Urban Environment ank-SPD) play ground and the constr uction Public Toile ET-OROMIA-ASALA-31146 Expand the Urban Product Request for Qu 7-CW-RFQ / Procurement o Request for Quo Single Stage - On Complete 2022-10-0 2023-04-2 2022-11-2 2023-05-2 2023-01- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 28,846.00 0.00 f Skilled Labor for the Main tations e Envelope d 3 8 1 2 25 the Urban Environment ank-SPD) tenance of school educatio n class rooms ET-OROMIA-BURAYU-3115 63-CW-RFQ / Procurement Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-10-0 2022-12-1 2022-11-2 2023-01-1 2023-01- of Skilled Labor for the con IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 19,580.00 0.00 tations e Envelope d 3 9 2 9 26 struction of Public Toilet a the Urban Environment ank-SPD) nd Maintenance of school education class Rooms ET-OROMIA-NEKEMTE-311 Expand the Urban Product Request for Qu 585-CW-RFQ / Procuremen Request for Quo Single Stage - On Complete 2022-10-0 2023-06-2 2022-11-2 2023-07-0 2023-01- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 25,000.00 0.00 t of Skilled labor for the co tations e Envelope d 3 3 1 6 25 the Urban Environment ank-SPD) nstruction of public Toile a nd Fence for Greenery ET-OROMIA-GINCHI-31191 7-CW-RFQ / Procurement o Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-10-0 2023-02-0 2022-11-2 2023-03-1 2023-02- f Skilled Labor for the cons IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 7,565.00 0.00 tations e Envelope d 3 6 2 3 20 truction of Public Toilet, Dr the Urban Environment ank-SPD) ainage construction and C alvert Construction ET-OROMIA-BADESA-3124 Expand the Urban Product Request for Qu 79-CW-RFQ / Procurement Request for Quo Single Stage - On Complete 2022-10-0 2023-05-1 2022-11-2 2023-06-0 2023-01- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 6,250.00 0.00 of Skilled Labor for the con tations e Envelope d 3 9 2 2 26 the Urban Environment ank-SPD) struction of store and Addi tional education class Roo ms ET-OROMIA-BATU-312489 Expand the Urban Product Request for Qu -CW-RFQ / Procurement of Request for Quo Single Stage - On Complete 2022-10-0 2023-05-0 2022-11-2 2023-06-0 2023-01- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 7,746.00 0.00 Skilled Labor for the constr tations e Envelope d 3 8 2 2 26 the Urban Environment ank-SPD) uction of store and the con struction of Fence for Gree nery ET-OROMIA-WALISO-3125 Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-09-2 2023-05-0 2022-11-1 2023-05-1 2023-01- 69-CW-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 5,000.00 0.00 tations e Envelope d 7 3 5 8 19 of Skilled Labor for the con the Urban Environment ank-SPD) struction of Public Toile ET-OROMIA-NEGELE BORA NA-313235-CW-RFQ / Proc Expand the Urban Product Request for Qu Request for Quo Single Stage - On 2022-10-0 2023-03-2 2022-11-2 2023-04-1 2023-01- urement of Skilled labor fo IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 12,692.00 0.00 Signed tations e Envelope 5 9 4 9 28 r the construction of Public the Urban Environment ank-SPD) Toilet, Water line Installati on and Fence for Greenery ET-OROMIA-BULE HORA-3 Expand the Urban Product Request for Qu 13744-CW-RFQ / Procurem Request for Quo Single Stage - On Complete 2022-10-0 2022-04-1 2022-11-2 2023-03-2 2023-01- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 17,154.00 0.00 ent of Skilled Labor for the tations e Envelope d 5 9 4 7 28 the Urban Environment ank-SPD) Construction of Public Toil ets ET-OROMIA-DAMBI DOLO- Expand the Urban Product Request for Qu 314267-CW-RFQ / Procure Request for Quo Single Stage - On Complete 2022-10-1 2023-02-1 2022-11-2 2023-03-2 2023-02- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 5,769.00 0.00 ment of Skilled Labor for t tations e Envelope d 0 0 8 8 01 the Urban Environment ank-SPD) he maintenance of school class Rooms ET-OROMIA-BISHOFTU-31 4261-CW-RFQ / Procureme Expand the Urban Product Request for Qu nt of Skilled Labor for the c Request for Quo Single Stage - On Complete 2022-10-1 2023-03-1 2022-11-2 2023-04-0 2023-02- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 20,880.00 0.00 onstruction of water line in tations e Envelope d 0 3 9 8 02 the Urban Environment ank-SPD) stallation for greenery, sch ool class room Maintenanc e and Construction of Fenc e ET-OROMIA-HOLOTA-3145 Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-10-0 2023-03-0 2022-11-2 2023-03-1 2023-01- 08-CW-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 4,958.00 0.00 tations e Envelope d 4 8 2 5 26 of Skilled Labor for the con the Urban Environment ank-SPD) struction of public Toilet ET-OROMIA-ROBE-314703 Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-10-0 2022-12-0 2022-11-2 2023-06-2 2023-01- -CW-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 8,437.00 0.00 tations e Envelope d 4 2 2 2 26 Skilled labor for the constr the Urban Environment ank-SPD) uction of public Toilet ET-OROMIA-MAKI-314745- Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-10-0 2023-04-0 2022-11-2 2023-05-0 2023-01- CW-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 6,351.00 0.00 tations e Envelope d 5 8 4 5 28 skilled Labor for the constr the Urban Environment ank-SPD) uction of public Toilet ET-OROMIA-SHAMBU-314 768-CW-RFQ / Procuremen Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-10-0 2023-06-1 2022-11-2 2023-07-1 2023-01- t of skilled Labor for the co IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 10,089.00 0.00 tations e Envelope d 5 6 4 0 28 nstruction of Public Toilet, the Urban Environment ank-SPD) construction of Drainage li ne and construction of Fen ce for Greenery ET-OROMIA-GIMBI-314786 Expand the Urban Product Request for Qu -CW-RFQ / Procurement of Request for Quo Single Stage - On 2022-10-0 2023-05-1 2022-11-2 2023-07-0 2023-01- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 13,719.00 0.00 Signed Skilled Labor for the maint tations e Envelope 5 9 3 7 27 the Urban Environment ank-SPD) enance of student class ro om and the construction of store ET-OROMIA-YABELO-3148 08-CW-RFQ / Procurement Expand the Urban Product Request for Qu Request for Quo Single Stage - On Complete 2022-10-0 2023-04-1 2022-11-2 2023-05-2 2023-01- of skilled Labor for the mai IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 6,726.00 0.00 tations e Envelope d 5 8 3 6 27 ntenance of student class the Urban Environment ank-SPD) room and the construction of Fence for Greenery ET-OROMIA-ADAMA-28132 Expand the Urban Product Request for Qu Request for Quo Single Stage - On 2022-03-1 2022-04-2 2022-07- 2-CW-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 4,313.00 0.00 Canceled tations e Envelope 6 8 01 f Labor sem-skill for the co the Urban Environment ank-SPD) struction of Toilet Page 1 ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Qu -285256-CW-RFQ / Procure Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-07- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 6,500.00 0.00 Canceled ment of Skill Labor for the tations e Envelope 8 9 08 the Urban Environment ank-SPD) Construction of Public Toil et ET-OROMIA-DAMBI DOLO- Expand the Urban Product Request for Qu 282518-CW-RFQ / Procure Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-05- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 5,200.00 0.00 Canceled ment of Skill Labor for the tations e Envelope 8 4 10 the Urban Environment ank-SPD) construction of Public Toile t ET-OROMIA-NEKEMTE-285 186-CW-RFQ / Procuremen Expand the Urban Product Request for Qu Request for Quo Single Stage - On 2022-03-3 2022-05-1 2022-07- t of Skill Labor for the cons IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 13,930.00 0.00 Canceled tations e Envelope 0 4 08 truction of Public Toilet in the Urban Environment ank-SPD) Lot -1 and Fence Construct ion for the Greenery in Lot -2 ET-OROMIA-SHASHEMENE Request for Qu -347686-CW-RFQ / Refurbi Foster Urban Youth Emplo Request for Quo Single Stage - On Complete 2023-03-1 2023-04-2 2023-04-1 2023-05-1 2023-07- IDA / D7320 Post Limited otations (Non B 64,000.00 0.00 shment of Alelu OSSC in S yment tations e Envelope d 6 8 4 5 13 ank-SPD) hashemene by component 2.2 ET-OROMIA-ADAMA-34769 Request for Qu 1-CW-RFQ / Refurbishment Foster Urban Youth Emplo Request for Quo Single Stage - On Complete 2023-03-1 2023-04-2 2023-04-1 2023-05-2 2023-07- IDA / D7320 Post Limited otations (Non B 79,000.00 0.00 of Boku Shenen OSSC in A yment tations e Envelope d 6 4 4 4 13 ank-SPD) dama by component 2.2 ET-OROMIA-ADAMA-34769 Request for Qu Foster Urban Youth Emplo Request for Quo Single Stage - On Complete 2023-03-1 2023-04-2 2023-04-1 2023-05-2 2023-07- 3-CW-RFQ / Refurbishment IDA / D7320 Post Limited otations (Non B 79,000.00 0.00 yment tations e Envelope d 6 4 4 4 13 of Hangatu OSSC in Adam ank-SPD) a by component 2.2 ET-OROMIA-ASELA-34769 Request for Qu Foster Urban Youth Emplo Request for Quo Single Stage - On Complete 2023-03-1 2023-05-1 2023-04-1 2023-05-2 2023-07- 4-CW-RFQ / Refurbishment IDA / D7320 Post Limited otations (Non B 79,000.00 0.00 yment tations e Envelope d 6 1 4 9 13 of Chilalo OSSC in Assela b ank-SPD) y component 2.2 ET-OROMIA-SEBETA-3476 Request for Qu Foster Urban Youth Emplo Request for Quo Single Stage - On Complete 2023-03-1 2023-04-1 2023-04-1 2023-06-2 2023-07- 96-CW-RFQ / Refurbishme IDA / D7320 Post Limited otations (Non B 79,000.00 0.00 yment tations e Envelope d 6 3 4 0 13 nt of Kebele 08 OSSC in Se ank-SPD) beta by component 2.2 ET-OROMIA-BISHOFTU-34 Request for Qu 7699-CW-RFQ / Refurbish Foster Urban Youth Emplo Request for Quo Single Stage - On Complete 2023-03-1 2023-04-0 2023-04-1 2023-04-2 2023-07- IDA / D7320 Post Limited otations (Non B 71,000.00 0.00 ment of Dire Jitu OSSC in B yment tations e Envelope d 6 6 4 5 13 ank-SPD) ishoftu by component 2.2 ET-OROMIA-HARAMAYA-3 Request for Qu 47700-CW-RFQ / Refurbish Foster Urban Youth Emplo Request for Quo Single Stage - On Complete 2023-03-1 2023-04-2 2023-04-1 2023-05-0 2023-07- IDA / D7320 Post Limited otations (Non B 66,500.00 0.00 ment of Haramaya Kebele yment tations e Envelope d 6 1 4 7 13 ank-SPD) 01 OSSC in Haromaya by c omponent 2.2 ET-OROMIA-MATU-310925 Expand the Urban Product Request for Qu -CW-RFQ / Procurement of Request for Quo Single Stage - On 2022-10-0 2022-11-2 2023-01- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 5,954.00 0.00 Canceled Skilled Labor for the constr tations e Envelope 3 2 26 the Urban Environment ank-SPD) uction of Public Toilet and the construction of Draina ge line ET-OROMIA-HOLOTA-2852 Expand the Urban Product Request for Qu Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-07- 15-CW-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 5,800.00 0.00 Canceled tations e Envelope 8 9 08 of Skill Labor for the constr the Urban Environment ank-SPD) uction of Public Toile ET-OROMIA-BEDELE-3127 Expand the Urban Product Request for Qu Request for Quo Single Stage - On 2022-10-0 2022-11-2 2023-01- 37-CW-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 3,858.00 0.00 Canceled tations e Envelope 5 4 28 of Skilled Labor for the con the Urban Environment ank-SPD) struction of Public Toilet ET-OROMIA-HARAMAYA-3 Expand the Urban Product Request for Qu 10480-CW-RFQ / Procurem Request for Quo Single Stage - On 2022-09-2 2022-11-1 2023-01- IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 7,485.00 0.00 Canceled ent of Skilled labor for the tations e Envelope 7 5 19 the Urban Environment ank-SPD) construction of Public Toile t ET-OROMIA-ROBE-285437 Expand the Urban Product Request for Qu Request for Quo Single Stage - On 2022-03-2 2022-05-1 2022-07- -CW-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited otations (Non B 4,600.00 0.00 Canceled tations e Envelope 9 3 07 Skill Labor for the construc the Urban Environment ank-SPD) tion of public Toilet GOODS Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amou Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) nt (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-OROMIA-248276-GO-R Institutional Strengthenin Request for Quo Single Stage - On 2021-09-1 2021-12-1 2021-10-1 2022-02-1 2021-11-1 2022-03-0 FQ / Procurement of furnit IDA / D7320 g, Project Management an Post Limited 33,300.00 23,125.28 Completed tations e Envelope 0 4 1 7 0 5 ure for regional hub and pr d Monitoring and Evaluati oject beneficiary cities on ET-OROMIA-ADAMA-25017 Expand the Urban Product Single Stage - On 2021-09-1 2021-10-2 2021-09-1 2021-10-1 2021-11-2 2021-11-1 2021-12-1 2021-12-0 2022-01-3 2022-02-0 2022-03-1 3-GO-RFB / Procurement of IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 231,500.00 183,441.77 Completed e Envelope 0 7 5 5 6 4 3 9 0 7 2 safety materials for Adama the Urban Environment city ET-OROMIA-ADAMA-24828 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-12-0 2021-10-1 2022-01-3 2021-11-1 2022-02-2 7-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 29,800.00 47,925.09 Completed tations e Envelope 5 1 6 0 5 8 f Hand Tools Materials for the Urban Environment Adama City ET-OROMIA-ADAMA-24829 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2022-05-0 2021-10-1 2022-06-0 2021-11-1 2022-06-1 7-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 36,300.00 0.00 Completed tations e Envelope 5 6 7 3 6 3 f Industrial construction M the Urban Environment aterials for Adama City ET-OROMIA-JIMA-250081- Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2020-10-0 2021-10-1 2022-01-2 2021-11-1 2022-01-2 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 69,600.00 53,510.64 Completed tations e Envelope 5 6 6 7 5 9 Safety Materials for Jima Ci the Urban Environment ty ET-OROMIA-JIMA-248311- Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-09-2 2021-10-1 2021-11-2 2021-11-1 2021-12-1 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 13,500.00 8,580.77 Completed tations e Envelope 5 5 9 9 8 9 Hand Tools for Jima City the Urban Environment ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-2 2021-10-2 2021-12-1 2021-11-1 2022-01-1 -248314-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 73,400.00 89,350.82 Completed tations e Envelope 3 2 0 3 9 5 ment of Safety Materials fo the Urban Environment r shashamane City ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-2 2021-10-2 2021-12-1 2021-11-2 2022-01-0 -248318-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 17,200.00 5,697.09 Completed tations e Envelope 4 2 1 3 0 7 ment of Hand Tools for Sh the Urban Environment ashamane City ET-OROMIA-BISHOFTU-24 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-1 2021-10-2 2021-11-2 2021-11-2 2021-12-1 8321-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 73,700.00 38,040.59 Completed tations e Envelope 5 1 2 2 1 1 nt of Safety Materials for B the Urban Environment ishoftu City ET-OROMIA-BISHOFTU-24 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-2 2021-10-2 2021-12-1 2021-11-2 2021-12-1 8324-GO-RFQ / procureme IDA / D7320 ive Safety Net to Improve Post Limited 73,300.00 19,313.37 Completed tations e Envelope 5 7 2 1 1 9 nt of Hand Tools Materials the Urban Environment for Bishoftu City ET-OROMIA-NEKEMTE-248 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-1 2021-10-2 2022-01-0 2021-11-2 2022-01-0 327-GO-RFQ / procuremen IDA / D7320 ive Safety Net to Improve Post Limited 50,100.00 28,175.45 Completed tations e Envelope 5 9 2 1 1 7 t of Safety Materials for Ne the Urban Environment kemte City ET-OROMIA-NEKEMTE-248 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-1 2021-10-2 2021-12-2 2021-11-2 2021-12-3 329-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 17,200.00 12,524.09 Completed tations e Envelope 5 9 2 5 1 0 t of Hand Tools Materials f the Urban Environment or Nekemte City ET-OROMIA-ASELA-24833 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-0 2021-10-2 2021-12-0 2021-11-2 2021-12-2 4-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 44,800.00 34,710.27 Completed tations e Envelope 5 3 2 6 1 4 f Safety Materials for Asela the Urban Environment City ET-OROMIA-ASELA-24834 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-0 2021-10-2 2021-12-0 2021-11-2 2021-12-1 1-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 14,300.00 19,675.46 Completed tations e Envelope 5 3 2 6 1 7 f Hand Tools Materials fo A the Urban Environment sela City ET-OROMIA-SEBETA-2483 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-3 2021-10-2 2021-12-1 2021-11-2 2022-01-0 49-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 35,100.00 14,032.01 Completed tations e Envelope 5 0 2 3 1 8 of Safety Materials for Seb the Urban Environment eta City ET-OROMIA-SEBETA-2483 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-2 2021-10-2 2021-12-1 2021-11-2 2022-01-0 53-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 7,200.00 3,901.14 Completed tations e Envelope 5 9 2 3 1 9 of Hand Tools Materials for the Urban Environment Sebeta City ET-OROMIA-BURAYU-2483 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-2 2021-10-2 2021-12-0 2021-11-2 2022-01-0 54-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 34,200.00 20,950.46 Completed tations e Envelope 5 0 2 6 1 8 of Safety Materials for Bur the Urban Environment ayu City ET-OROMIA-BURAYU-2483 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-2 2021-10-2 2021-12-0 2021-11-2 2022-01-0 55-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 7,400.00 7,156.31 Completed tations e Envelope 5 0 2 6 1 7 of Hand Tools Materials for the Urban Environment Burayu City ET-OROMIA-AMBO-248356 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-2 2021-10-2 2021-12-0 2021-11-2 2021-12-3 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 33,900.00 26,782.01 Completed tations e Envelope 5 0 2 4 1 1 Safety Materials for Ambo the Urban Environment City ET-OROMIA-AMBO-248357 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-2 2021-10-2 2021-12-0 2021-11-2 2021-12-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 74,300.00 8,657.25 Completed tations e Envelope 5 0 2 4 1 7 Hand Tools Materials for A the Urban Environment mbo City ET-OROMIA-ARSI NEGELE- Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-0 2021-10-2 2021-12-2 2021-11-2 2021-12-2 248372-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 33,900.00 37,992.87 Completed tations e Envelope 5 2 4 0 3 0 ment of Safety Materials fo the Urban Environment r Arsi Negele City ET-OROMIA-ARSI NEGELE- Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-0 2021-10-2 2021-12-1 2021-11-2 2021-12-1 248376-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 7,300.00 9,490.29 Completed tations e Envelope 5 2 2 2 1 7 ment of Hand Tools Materi the Urban Environment als for Arsi Negele City ET-OROMIA-ROBE-248377 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-1 2021-10-2 2021-12-2 2021-11-2 2021-12-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 32,300.00 13,755.77 Completed tations e Envelope 5 5 2 0 1 5 Safety Materials for Robe the Urban Environment City ET-OROMIA-ROBE-248379 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-1 2021-10-2 2021-11-2 2021-11-2 2021-12-3 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 6,200.00 5,142.69 Completed tations e Envelope 5 5 4 5 3 1 Hand Tools Materials for R the Urban Environment obe City ET-OROMIA-BATU-248380 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-0 2021-10-2 2021-12-0 2021-11-2 2021-12-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 29,800.00 21,962.29 Completed tations e Envelope 5 2 1 6 0 6 Safety Materials for Ziway the Urban Environment Batu City ET-OROMIA-BATU-248382 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-0 2021-10-2 2021-12-0 2021-11-2 2021-12-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 7,200.00 5,268.95 Completed tations e Envelope 5 2 2 6 1 6 Hand Tools Materials for Zi the Urban Environment way Batu City ET-OROMIA-WELISO-2483 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-1 2021-10-2 2021-12-0 2021-11-2 2021-12-2 84-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 45,200.00 33,029.60 Completed tations e Envelope 5 2 2 9 1 0 of Safety Materials for Weli the Urban Environment so City ET-OROMIA-WELISO-2483 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-1 2021-10-1 2021-12-0 2021-11-1 2021-12-1 87-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 14,300.00 7,074.13 Completed tations e Envelope 5 2 9 9 8 7 of Hand Tools Materials for the Urban Environment Weliso ET-OROMIA-MEKI-248388- Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-0 2021-10-2 2021-11-0 2021-11-2 2021-11-1 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 43,700.00 36,230.53 Completed tations e Envelope 5 8 2 8 1 0 Safety Materials for Meki C the Urban Environment ity ET-OROMIA-MEKI-248390- Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-0 2021-10-2 2021-11-0 2021-11-2 2021-11-1 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 14,600.00 14,952.76 Completed tations e Envelope 5 7 2 8 1 0 Hand Tools Materials for M the Urban Environment eki City ET-OROMIA-BULEHORA-24 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-2 2021-10-2 2021-12-0 2021-11-2 2021-12-2 8395-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 41,200.00 26,806.87 Completed tations e Envelope 5 8 2 9 1 7 nt of Safety Materials for B the Urban Environment ulehora City ET-OROMIA-BULEHORA-24 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-2 2021-10-2 2021-12-0 2021-11-2 2021-12-1 8396-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 14,900.00 13,370.56 Completed tations e Envelope 5 8 2 9 1 9 nt of Hand Tools Materials the Urban Environment for Bulehora City ET-OROMIA-BORENA-2483 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-2 2021-10-1 2021-11-0 2021-11-1 2021-12-0 97-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 41,200.00 0.00 Completed tations e Envelope 5 2 9 9 8 8 of Safety Materials for Neg the Urban Environment ele Borena City ET-OROMIA-BORENA-2483 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-2 2021-10-2 2021-11-1 2021-11-2 2021-12-1 98-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 14,900.00 0.00 Completed tations e Envelope 5 2 2 5 1 6 of Hand Tools Materials for the Urban Environment Negele Borena City ET-OROMIA-CHIRO-24839 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-0 2021-10-1 2021-12-1 2021-11-1 2022-01-2 9-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 40,200.00 29,013.69 Completed tations e Envelope 5 2 9 9 8 2 f Safety Materials for Chiro the Urban Environment City ET-OROMIA-CHIRO-24840 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-0 2021-10-2 2021-12-1 2021-11-2 2021-12-3 0-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 13,900.00 8,271.37 Completed tations e Envelope 5 2 2 9 1 0 f Hand Tools Materials for the Urban Environment Chiro City ET-OROMIA-GIMBI-248401 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-1 2021-10-2 2021-12-1 2021-11-2 2022-02-0 -GO-RFQ / procurement of IDA / D7320 ive Safety Net to Improve Post Limited 38,600.00 18,677.56 Completed tations e Envelope 5 4 2 0 1 6 Safety Materials for Gimbi the Urban Environment City ET-OROMIA-GIMBI-248402 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-1 2021-10-2 2021-12-2 2021-11-2 2022-01-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 10,500.00 13,983.59 Completed tations e Envelope 5 4 2 5 1 3 Hand Tools Materials for Gi the Urban Environment mbi City ET-OROMIA-DEMBIDOLO-2 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-1 2021-10-2 2021-12-2 2021-11-2 2021-12-3 48403-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 36,600.00 13,991.72 Completed tations e Envelope 5 8 2 3 1 1 ent of Safety Materials for the Urban Environment Dembidolo City Page 2 ET-OROMIA-DEMBIDOLO-2 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-1 2021-10-2 2021-12-1 2021-11-2 2021-12-3 48404-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 8,500.00 4,018.85 Completed tations e Envelope 5 8 2 8 1 1 ent of Hand Tools Material the Urban Environment s for Dembidolo City ET-OROMIA-HARAMAYA-2 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-0 2021-10-2 2021-12-1 2021-11-2 2022-01-3 48405-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 36,600.00 24,611.78 Completed tations e Envelope 5 9 2 5 1 1 ent of Safety Materials for the Urban Environment Haramaya City ET-OROMIA-HARAMAYA-2 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-0 2021-10-2 2021-11-2 2021-11-2 2021-12-1 48406-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 10,500.00 7,155.93 Completed tations e Envelope 5 5 2 5 1 7 ent of Hand Tools Material the Urban Environment s for Haramaya City ET-OROMIA-MATTU-24841 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-09-2 2021-10-2 2021-11-2 2021-11-2 2021-12-1 1-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 38,700.00 31,352.90 Completed tations e Envelope 5 4 2 8 1 6 f Safety Materials for Matt the Urban Environment u City ET-OROMIA-MATTU-24841 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-09-2 2021-10-2 2021-11-2 2021-11-2 2021-12-0 3-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 7,000.00 7,990.00 Completed tations e Envelope 5 4 2 8 1 6 f Hand Tools Materials for the Urban Environment Mattu City ET-OROMIA-FICHE-248422 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-2 2021-10-2 2021-12-1 2021-11-2 2022-01-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 33,500.00 30,864.90 Completed tations e Envelope 5 5 2 0 1 6 Safety Materials for Fiche the Urban Environment City ET-OROMIA-FICHE-248429 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-1 2021-10-2 2021-12-1 2021-11-2 2022-01-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 8,600.00 12,086.98 Completed tations e Envelope 5 2 2 9 1 3 Hand Tools Materials for Fi the Urban Environment che City ET-OROMIA-AGARO-24843 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-0 2021-10-2 2021-12-2 2021-11-2 2022-01-2 0-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 33,500.00 18,656.86 Completed tations e Envelope 5 7 2 2 1 7 f Safety Materials for Agar the Urban Environment o City ET-OROMIA-AGARO-24843 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-0 2021-10-2 2021-11-2 2021-11-2 2022-01-0 1-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 6,300.00 6,103.51 Completed tations e Envelope 5 7 2 2 1 9 f Hand Tools Materials for the Urban Environment Agaro City ET-OROMIA-HOLETA-2484 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-2 2021-10-2 2022-01-0 2021-11-2 2022-01-0 32-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 62,200.00 43,076.33 Completed tations e Envelope 5 5 2 2 1 4 of Safety Materials for Hol the Urban Environment eta city ET-OROMIA-HOLETA-2484 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-2 2021-10-2 2022-01-0 2021-11-2 2022-01-1 33-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 22,300.00 11,522.01 Completed tations e Envelope 5 5 2 2 1 1 of Hand Tools Materials for the Urban Environment Holeta City ET-OROMIA-BEDELE-2484 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-1 2021-10-2 2021-12-2 2021-11-2 2022-01-0 34-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 62,200.00 27,207.92 Completed tations e Envelope 5 2 2 3 1 7 of Safety Materials for Bed the Urban Environment ele City ET-OROMIA-BEDELE-2484 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-1 2021-10-2 2021-12-1 2021-11-2 2021-12-2 37-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 8,500.00 3,801.75 Completed tations e Envelope 5 1 2 0 1 3 of Hand Tools Materials for the Urban Environment Bedele city ET-OROMIA-BADESA-2484 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-1 2021-10-2 2021-12-2 2021-11-2 2022-01-0 39-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 48,900.00 27,429.00 Completed tations e Envelope 5 2 2 3 1 7 of Safety Materials for Bad the Urban Environment esa City ET-OROMIA-BADESA-2484 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-1 2021-10-2 2021-11-1 2021-11-2 2022-01-0 40-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 15,800.00 0.00 Completed tations e Envelope 5 9 2 2 1 4 of Hand Tools Materials for the Urban Environment Badesa City ET-OROMIA-GINCHI-24844 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-1 2021-10-2 2021-11-2 2021-11-2 2021-12-1 2-GO-RFQ / Procurement f IDA / D7320 ive Safety Net to Improve Post Limited 46,700.00 20,963.39 Completed tations e Envelope 5 5 2 5 1 3 o Safety Materials for Ginc the Urban Environment hi City ET-OROMIA-GINCHI-24844 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-1 2021-10-2 2021-11-2 2021-11-2 2021-12-1 5-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 17,200.00 13,740.56 Completed tations e Envelope 5 5 2 5 1 3 f Hand Tools Materials for the Urban Environment Ginchi City ET-OROMIA-YABELO-2484 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-10-0 2021-10-2 2021-11-0 2021-11-2 2021-12-1 48-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 45,700.00 35,948.01 Completed tations e Envelope 5 4 2 8 1 2 of Safety Materials for Yab the Urban Environment ello City ET-OROMIA-YABELO-2484 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-09-3 2021-10-2 2021-11-0 2021-11-2 2021-11-1 51-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 16,500.00 19,549.13 Completed tations e Envelope 5 0 2 3 1 3 of Hand Tools Materials for the Urban Environment Yabello City ET-OROMIA-DERA-248454 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-12-0 2021-10-2 2022-01-0 2021-11-2 2022-02-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 42,875.00 22,838.94 Completed tations e Envelope 5 2 2 7 1 8 Safety Materials for Dera C the Urban Environment ity ET-OROMIA-DERA-248459 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-12-0 2021-10-2 2022-01-0 2021-11-2 2022-01-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 9,800.00 10,057.92 Completed tations e Envelope 5 2 2 7 1 4 Hand Tools Materials for D the Urban Environment era City ET-OROMIA-SHAMBU-248 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-1 2021-10-2 2022-01-0 2021-11-2 2022-01-0 462-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 39,200.00 34,857.77 Completed tations e Envelope 5 8 2 1 1 1 t of Safety Materials for Sh the Urban Environment ambu City ET-OROMIA-SHAMBU-248 Expand the Urban Product Request for Quo Single Stage - On 2021-09-1 2021-11-1 2021-10-2 2021-12-0 2021-11-2 2021-12-0 465-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 13,800.00 10,555.59 Completed tations e Envelope 5 8 2 2 1 2 t of Hand Tools Materials f the Urban Environment or Shambu City ET-OROMIA-AMBO-281049 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-05-0 2022-04-2 2022-06-1 2022-05-1 2022-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 8,204.00 9,936.88 Completed tations e Envelope 5 3 1 7 1 4 Seedling the Urban Environment ET-OROMIA-AMBO-281029 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-05-0 2022-06-0 2022-05-2 2022-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 1,095.00 0.00 Completed tations e Envelope 6 3 2 7 2 8 Industrial Construction Mat the Urban Environment erials ET-OROMIA-AMBO-281041 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-05-0 2022-04-2 2022-06-2 2022-05-1 2022-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 550.00 0.00 Completed tations e Envelope 9 3 5 7 6 6 Local Construction Materia the Urban Environment ls ET-OROMIA-GINCHI-28115 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-03-2 2022-04-2 2022-04-2 2022-05-2 2022-07-0 7-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 7,136.00 2,569.62 Completed tations e Envelope 5 5 1 5 1 1 f Seedling the Urban Environment ET-OROMIA-GINCHI-28116 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-03-2 2022-05-0 2022-04-2 2022-05-2 2022-05-2 5-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 2,942.00 1,281.71 Completed tations e Envelope 6 5 2 5 2 4 f Tents for a child care cen the Urban Environment ter ET-OROMIA-GINCHI-28116 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-03-2 2022-04-2 2022-04-2 2022-05-2 2022-06-2 7-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 7,875.00 12,304.74 Completed tations e Envelope 9 5 5 5 5 1 f Industrials Construction the Urban Environment Materials ET-OROMIA-GINCHI-28117 Expand the Urban Product 4-GO-RFQ / Procurement o Request for Quo Single Stage - On 2022-03-2 2022-03-2 2022-04-2 2022-04-2 2022-05-1 2022-05-2 IDA / D7320 ive Safety Net to Improve Post Limited 8,863.00 6,472.65 Completed f Local Construction Materi tations e Envelope 0 5 6 5 6 1 the Urban Environment als for green area Fence C onstruction ET-OROMIA-SABATA-2811 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-04-0 2022-05-1 2023-05-2 2022-06-0 2023-05-3 79-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 6,832.00 0.00 Completed tations e Envelope 9 5 6 6 5 0 of Seedling the Urban Environment ET-OROMIA-SABATA-2811 Expand the Urban Product 82-GO-RFQ / Procurement Request for Quo Single Stage - On 2022-03-2 2022-04-0 2022-04-2 2022-05-1 2022-05-1 2022-05-2 IDA / D7320 ive Safety Net to Improve Post Limited 4,632.00 0.00 Completed of Industrials construction tations e Envelope 1 5 7 0 7 3 the Urban Environment Materials for Fence constr uction ET-OROMIA-SABATA-2811 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-0 2022-04-2 2023-05-2 2022-05-1 2023-05-3 89-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 4,910.00 0.00 Completed tations e Envelope 0 5 6 6 6 0 of Local construction Mate the Urban Environment rials ET-OROMIA-SABATA-2811 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-05-2 2022-04-2 2022-06-2 2022-05-1 2022-07-0 90-GO-RFQ / procurement IDA / D7320 ive Safety Net to Improve Post Limited 2,353.00 0.00 Completed tations e Envelope 5 7 1 0 1 6 of Tents for a child care ce the Urban Environment nter ET-OROMIA-MATU-281191 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-05-2 2022-05-1 2022-06-2 2022-06-0 2022-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 1,028.00 0.00 Completed tations e Envelope 9 5 6 3 5 7 Seedling the Urban Environment ET-OROMIA-MATU-281193 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-04-0 2022-04-2 2022-06-0 2022-05-2 2022-06-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 7,379.00 19,210.44 Completed tations e Envelope 5 4 1 5 1 8 Industrial construction mat the Urban Environment erials ET-OROMIA-MATU-281195 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-06-1 2022-04-2 2022-06-3 2022-05-2 2022-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 686.00 0.00 Completed tations e Envelope 3 4 9 0 9 7 Block for the construction the Urban Environment of public toilet ET-OROMIA-MATU-281197 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-0 2022-05-0 2022-06-2 2022-05-2 2022-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 1,099.00 0.00 Completed tations e Envelope 6 4 2 8 2 6 Finishing construction Mat the Urban Environment erials ET-OROMIA-MATU-281200 Expand the Urban Product Request for Quo Single Stage - On 2022-03-3 2022-04-0 2022-05-0 2022-05-1 2022-05-2 2022-05-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 286.00 0.00 Completed tations e Envelope 0 4 6 2 6 4 Waterline installation /sani the Urban Environment tary/ Materials ET-OROMI-MATU-281210- Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-04-0 2022-04-2 2022-05-1 2022-05-2 2022-07-0 GO-RFQ / Procurement of L IDA / D7320 ive Safety Net to Improve Post Limited 2,604.00 0.00 Completed tations e Envelope 9 4 5 2 5 5 ocal construction Materials the Urban Environment ET-OROMIA-CHIRO-28121 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-03-2 2022-05-1 2022-06-2 2022-06-0 2022-07-0 4-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 1,176.00 0.00 Completed tations e Envelope 9 8 6 3 5 1 f Seedling and Seeds the Urban Environment ET-OROMIA-CHIRO-28121 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-03-2 2022-04-2 2022-05-0 2022-05-2 2022-06-2 6-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 5,000.00 0.00 Completed tations e Envelope 5 8 1 2 1 2 f Industrial construction M the Urban Environment aterials ET-OROMIA-CHIRO-28121 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-03-2 2022-05-0 2022-05-0 2022-06-0 2022-06-2 8-GO-RFQ / Procurement t IDA / D7320 ive Safety Net to Improve Post Limited 530.00 0.00 Completed tations e Envelope 6 8 2 2 1 1 of Block for the Constructi the Urban Environment on of Public Toile ET-OROMIA-CHIRO-28121 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-04-0 2022-04-2 2022-05-0 2022-05-2 2022-06-2 9-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 2,835.00 0.00 Completed tations e Envelope 6 4 2 2 2 1 f Local construction Materi the Urban Environment als ET-OROMIA-MAKI-281221- Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-04-1 2022-05-1 2022-12-1 2022-06-1 2023-01-0 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 1,034.00 0.00 Completed tations e Envelope 6 1 3 9 3 7 Seedling the Urban Environment ET-OROMIA-MAKI-281222- Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-05-0 2022-04-2 2022-05-2 2022-05-1 2022-06-2 GO-RFQ / Procurement fo I IDA / D7320 ive Safety Net to Improve Post Limited 5,078.00 0.00 Completed tations e Envelope 5 6 1 0 6 3 ndustrial construction Mat the Urban Environment erials ET-OROMIA-MAKI-281223- Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-04-2 2023-06-1 2022-05-2 2023-06-2 GO-RFQ / procurement of IDA / D7320 ive Safety Net to Improve Post Limited 550.00 0.00 Completed tations e Envelope 1 4 8 9 8 3 Block for the construction the Urban Environment of Public Toilet ET-OROMIA-MAKI-281224- Expand the Urban Product GO-RFQ / Procurement of F Request for Quo Single Stage - On 2022-03-3 2022-05-0 2022-05-0 2022-05-2 2022-05-3 2022-06-2 IDA / D7320 ive Safety Net to Improve Post Limited 5,314.00 0.00 Completed inishing Materials in Lot -1 tations e Envelope 0 6 6 0 1 3 the Urban Environment and Waterline /sanitary/ M aterials in Lot-2 ET-OROMIA-MAKI-281225- Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-04-2 2022-05-2 2022-05-2 2022-07-0 GO-RFQ / Procurement of L IDA / D7320 ive Safety Net to Improve Post Limited 1,675.00 0.00 Completed tations e Envelope 2 5 8 0 3 7 ocal Construction Material the Urban Environment s ET-OROMIA-YABELO-2812 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-04-2 2022-05-1 2023-05-2 2022-06-0 2023-06-0 95-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 1,647.00 0.00 Completed tations e Envelope 9 0 6 6 5 1 of Seedling the Urban Environment ET-OROMIA-YABELO-2812 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-04-2 2022-04-2 2022-05-2 2022-05-2 2022-06-0 96-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 9,580.00 0.00 Completed tations e Envelope 5 0 1 7 1 9 of Industrial construction the Urban Environment Materials ET-OROMIA-YABELO-2813 05-GO-RFQ / Procurement Expand the Urban Product Request for Quo Single Stage - On 2022-03-3 2022-04-2 2022-05-0 2022-05-2 2022-06-0 2022-06-1 of Finishing Materials in Lo IDA / D7320 ive Safety Net to Improve Post Limited 1,903.00 0.00 Completed tations e Envelope 0 0 6 7 5 5 t- and Waterline installatio the Urban Environment n in Lot-2 for the construct ion of Public Toilet ET-OROMIA-YABELO-2813 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-05-0 2022-05-2 2022-06-0 2022-06-1 06-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 1,503.00 0.00 Completed tations e Envelope 6 0 2 7 1 4 of Local Construction Mate the Urban Environment rials ET-OROMIA-AGARO-28130 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-05-0 2022-04-2 2022-06-0 2022-05-1 2022-06-2 9-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 5,814.00 0.00 Completed tations e Envelope 9 6 9 1 9 8 f Industrials Construction the Urban Environment Materials ET-OROMIA-AGARO-28131 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-05-0 2022-06-0 2022-06-0 2022-06-2 1-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 571.00 0.00 Completed tations e Envelope 3 6 2 1 1 8 f Block for the construction the Urban Environment of Public Toilet ET-OROMIA-AGARO-28131 2-GO-RFQ / Procurement o Expand the Urban Product Request for Quo Single Stage - On 2022-03-3 2022-05-0 2022-05-0 2022-06-0 2022-06-0 2022-06-2 f Finishing Materials in Lot- IDA / D7320 ive Safety Net to Improve Post Limited 1,003.00 0.00 Completed tations e Envelope 0 6 9 2 8 8 1 and Waterline installatio the Urban Environment n /sanitary/ Materials in Lo t-2 for the construction of Public Toilet ET-OROMIA-AGARO-28131 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-05-0 2022-04-2 2022-06-0 2022-05-2 2022-06-2 3-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 2,066.00 0.00 Completed tations e Envelope 9 6 5 1 5 9 f Local Construction Materi the Urban Environment als Page 3 ET-OROMIA-ASALA-28131 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-05-0 2022-05-1 2022-05-2 2022-06-0 2022-08-0 8-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 7,149.00 0.00 Completed tations e Envelope 6 8 6 3 5 4 f Seedling the Urban Environment ET-OROMIA-ADAMA-28131 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-04-2 2022-05-1 2022-05-1 2022-06-0 2022-05-2 9-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 35,139.00 0.00 Completed tations e Envelope 6 5 6 3 5 6 f Seedling Tree in Lot-2 an the Urban Environment d Fruit Seeds in Lot-2 ET-OROMIA-ADAMA-28132 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-06-0 2022-04-2 2022-06-3 2022-05-1 2022-07-0 0-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 5,880.00 0.00 Completed tations e Envelope 6 7 1 0 1 7 f Tent for childe car center the Urban Environment ET-OROMIA-ADAMA-28132 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-05-0 2022-04-2 2022-06-0 2022-05-2 2022-07-0 1-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 8,045.00 0.00 Completed tations e Envelope 6 6 5 3 5 7 f Local Construction Materi the Urban Environment als ET-OROMIA-ADAMA-28134 Expand the Urban Product 1-GO-RFQ / Procurement o Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-05-0 2022-06-0 2022-06-0 2022-06-1 IDA / D7320 ive Safety Net to Improve Post Limited 31,700.00 0.00 Completed f Finishing Materials in Lot- tations e Envelope 1 6 2 3 1 3 the Urban Environment 1 and Waterline installatio n /sanitary/ Materials in Lo t-2 ET-OROMIA-NEGELE BORA Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-05-0 2022-05-1 2022-05-2 2022-06-1 2022-06-2 NA-281367-GO-RFQ / Proc IDA / D7320 ive Safety Net to Improve Post Limited 3,718.00 0.00 Completed tations e Envelope 6 3 6 6 0 6 urement of Seedling the Urban Environment ET-OROMIA-NEGELE BORA Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-04-2 2022-05-2 2022-05-2 2022-06-0 NA-281372-GO-RFQ / Proc IDA / D7320 ive Safety Net to Improve Post Limited 13,666.00 0.00 Completed tations e Envelope 1 3 8 6 8 6 urement of Industrial Cons the Urban Environment truction Materials ET-OROMIA-NEGELE BORA Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-06-1 2022-05-0 2022-06-2 2022-06-0 2022-07-0 NA-281381-GO-RFQ / Proc IDA / D7320 ive Safety Net to Improve Post Limited 3,355.00 0.00 Completed tations e Envelope 3 3 2 2 1 5 urement of Local Construc the Urban Environment tion Materials ET-OROMIA-BURAYU-2814 Expand the Urban Product Request for Quo Single Stage - On 2022-03-3 2022-04-0 2022-05-0 2022-04-2 2022-06-0 2022-07-0 58-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 1,030.00 0.00 Completed tations e Envelope 0 6 9 5 8 7 of Block for the Constructi the Urban Environment on of Public Toile ET-OROMIA-BURAYU-2814 Expand the Urban Product Request for Quo Single Stage - On 2022-03-1 2022-04-0 2022-04-2 2022-04-2 2022-05-2 2022-06-2 66-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 4,950.00 0.00 Completed tations e Envelope 9 6 5 5 5 0 of Industrial Construction the Urban Environment Materials ET-OROMIA-BURAYU-2814 Expand the Urban Product 76-GO-RFQ / Procurement Request for Quo Single Stage - On 2022-03-2 2022-04-0 2022-04-2 2022-04-2 2022-05-1 2022-06-1 IDA / D7320 ive Safety Net to Improve Post Limited 3,445.00 0.00 Completed of Finishing Materials in Lo tations e Envelope 2 6 8 5 8 7 the Urban Environment t-1 and Waterline installati on /Sanitary/ Materials in L ot-2 ET-OROMIA-BURAYU-2814 Expand the Urban Product 83-GO-RFQ / Procurement Request for Quo Single Stage - On 2022-03-2 2022-04-0 2022-04-2 2022-04-2 2022-05-2 2022-06-1 IDA / D7320 ive Safety Net to Improve Post Limited 3,255.00 0.00 Completed of Local Construction Mate tations e Envelope 1 6 8 5 8 7 the Urban Environment rials for the Construction o f Public Toilet ET-OROMIA-BADESA-2815 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-03-3 2022-05-0 2022-04-1 2022-06-0 2022-06-0 01-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 5,900.00 0.00 Completed tations e Envelope 2 1 2 1 1 8 of Industrial Construction the Urban Environment Materials ET-OROMIA-BADESA-2815 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-03-3 2022-05-0 2022-04-1 2022-06-0 2022-06-0 05-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 580.00 0.00 Completed tations e Envelope 6 1 2 8 1 9 of Block for the Constructi the Urban Environment on of Public Toilet ET-OROMIA-BADESA-2815 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-0 2022-04-2 2022-04-1 2022-05-2 2022-06-2 45-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 2,660.00 0.00 Completed tations e Envelope 1 9 7 9 7 8 of Local Construction Mate the Urban Environment rials ET-OROMIA-BADESA-2815 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-03-3 2022-05-0 2023-04-1 2022-05-2 2023-04-1 51-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 160.00 0.00 Completed tations e Envelope 9 1 5 8 5 8 of Waterline installation M the Urban Environment aterials ET-OROMIA-WALISO-2815 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-05-2 2022-05-1 2022-06-2 2022-06-0 2022-07-0 59-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 8,790.00 11,569.60 Completed tations e Envelope 6 0 2 8 1 8 of Seedlings the Urban Environment ET-OROMIA-WALISO-2815 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-04-2 2022-06-1 2022-05-2 2022-07-0 63-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 3,550.00 6,182.64 Completed tations e Envelope 1 9 8 4 8 2 of Industrial Construction the Urban Environment Materials ET-OROMIA-WALISO-2815 Expand the Urban Product 65-GO-RFQ / Procurement Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-04-2 2022-06-1 2022-05-1 2022-06-2 IDA / D7320 ive Safety Net to Improve Post Limited 515.00 193.10 Completed of Finishing Materials in Lo tations e Envelope 1 9 8 4 8 5 the Urban Environment t-1 and Waterline Installati on Materials in Lot-2 ET-OROMIA-WALISO-2817 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-04-2 2022-06-1 2022-05-2 2022-07-0 07-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 259.00 0.00 Completed tations e Envelope 1 9 8 0 3 7 of Block for the constructio the Urban Environment n of Public Toilet ET-OROMIA-WALISO-2817 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-04-2 2022-06-1 2022-05-2 2022-07-0 15-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 3,000.00 3,680.42 Completed tations e Envelope 2 9 8 4 8 3 of Local Construction Mate the Urban Environment rials ET-OROMIA-DERA-281729 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-04-2 2022-05-1 2023-06-2 2022-06-0 2023-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 910.00 0.00 Completed tations e Envelope 6 9 2 6 1 6 Seedling the Urban Environment ET-OROMIA-DERA-281737 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-04-2 2022-05-2 2022-05-1 2022-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 3,530.00 0.00 Completed tations e Envelope 2 9 8 3 8 7 Tent for childe car center the Urban Environment ET-OROMIA-DERA-281741 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-05-0 2022-05-2 2022-05-2 2022-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 138.00 0.00 Completed tations e Envelope 8 9 5 3 5 7 Block for the construction the Urban Environment of Public Toile ET-OROMIA-DERA-281745 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-04-2 2022-06-0 2022-05-2 2022-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 7,975.00 0.00 Completed tations e Envelope 2 9 8 6 8 6 Industrial Construction Mat the Urban Environment erials ET-OROMIA-DERA-281753 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-04-3 2022-04-2 2022-05-3 2022-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 6,425.00 0.00 Completed tations e Envelope 2 9 0 9 0 7 Local Construction Materia the Urban Environment ls ET-OROMIA-HARAMAYA-2 Expand the Urban Product Request for Quo Single Stage - On 2022-04-1 2022-05-0 2022-05-1 2022-05-2 2022-06-0 2022-06-2 81762-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 725.00 0.00 Completed tations e Envelope 3 3 9 6 8 9 ent of Seedlings the Urban Environment ET-OROMIA-HARAMAYA-2 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-04-2 2022-05-1 2022-05-2 2022-12-0 81764-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 5,675.00 0.00 Completed tations e Envelope 2 3 8 8 3 8 ent of Industrial Constructi the Urban Environment on Materials ET-OROMIA-HARAMAYA-2 Expand the Urban Product 81772-GO-RFQ / Procurem Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-05-0 2022-05-0 2022-05-2 2022-12-0 IDA / D7320 ive Safety Net to Improve Post Limited 2,530.00 0.00 Completed ent of Finishing Materials i tations e Envelope 8 3 5 3 5 8 the Urban Environment n Lot -1 and Waterline Inst allation Materials in Lot-2 ET-OROMIA-HARAMAYA-2 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-04-2 2022-05-1 2022-05-3 2022-12-0 81776-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 1,750.00 0.00 Completed tations e Envelope 1 3 9 8 0 8 ent of Local Construction the Urban Environment Materials ET-OROMIA-BISHOFTU-28 Expand the Urban Product Request for Quo Single Stage - On 2022-04-1 2022-05-2 2022-05-2 2022-07-0 2022-06-1 2022-07-0 1791-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 4,900.00 0.00 Completed tations e Envelope 3 7 4 7 3 7 nt of Seedlings the Urban Environment ET-OROMIA-BISHOFTU-28 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-1 2022-04-2 2022-07-0 2022-05-1 2022-07-0 1792-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 2,940.00 0.00 Completed tations e Envelope 1 0 8 4 8 7 nt of Tent for child car cen the Urban Environment ter ET-OROMIA-BISHOFTU-28 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-1 2022-05-0 2022-06-0 2022-05-2 2022-07-0 1793-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 7,220.00 0.00 Completed tations e Envelope 2 0 2 3 2 7 nt of Industrial Constructio the Urban Environment n Materials ET-OROMIA-BISHOFTU-28 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-07-1 2022-04-2 2022-08-0 2022-05-2 2022-08-2 1795-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 3,670.00 0.00 Completed tations e Envelope 2 2 8 3 8 3 nt of Local Construction M the Urban Environment aterials ET-OROMIA-BISHOFTU-28 Expand the Urban Product 1796-GO-RFQ / Procureme Request for Quo Single Stage - On 2022-03-2 2022-05-1 2022-05-0 2022-06-0 2022-05-3 2022-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 5,640.00 0.00 Completed nt of Finishing Materials in tations e Envelope 1 3 1 6 1 7 the Urban Environment Lot-1 and Waterline Install ation Materials in Lot-2 ET-JIMMA-UDHB-281797-G Expand the Urban Product Request for Quo Single Stage - On 2022-05-2 2022-03-2 2022-07-1 2022-04-1 2022-08-0 2022-07-0 O-RFQ / Procurement of dif IDA / D7320 ive Safety Net to Improve Post Limited 14,020.00 0.00 Completed tations e Envelope 1 5 6 4 5 7 ferent seedlings for greene the Urban Environment ry activities ET-JIMMA-UDHB-281799-G Expand the Urban Product O-RFQ / Procurement of In Request for Quo Single Stage - On 2022-03-2 2022-03-2 2022-05-1 2022-04-2 2022-06-1 2022-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 15,600.00 0.00 Completed dustrial construction mater tations e Envelope 1 4 6 1 5 7 the Urban Environment ials for the construction of public toilet ET-JIMMA-UDHB-281803-G Expand the Urban Product O-RFQ / Procurement of w Request for Quo Single Stage - On 2022-03-2 2022-03-2 2022-05-1 2022-06-2 2022-06-0 2022-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 730.00 0.00 Completed ater line installation materi tations e Envelope 3 5 8 1 7 7 the Urban Environment als or fittings for greenery activities ET-JIMMA-UDHB-281807-G Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-03-2 2022-05-2 2022-06-2 2022-06-0 2022-07-0 O-RFQ / Procurement of ad IDA / D7320 ive Safety Net to Improve Post Limited 1,450.00 0.00 Completed tations e Envelope 6 5 1 1 5 7 ditional hand tools for publ the Urban Environment ic work activities ET-JIMMA-UDHB-281809-G Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-03-2 2022-05-2 2022-06-2 2022-06-0 2022-07-0 O-RFQ / Procurement of lo IDA / D7320 ive Safety Net to Improve Post Limited 3,800.00 0.00 Completed tations e Envelope 8 5 3 1 7 7 cal construction materials the Urban Environment ET-OROMIA-SHAMBU-282 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-05-2 2022-05-1 2022-06-2 2022-06-0 2022-07-0 098-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 532.00 0.00 Completed tations e Envelope 6 4 7 4 6 1 t of Different Seedlings for the Urban Environment greenery activities ET-OROMIA-SHAMBU-282 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-2 2022-06-1 100-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 882.00 0.00 Canceled tations e Envelope 8 3 7 t of Tent for childe car cen the Urban Environment ter ET-OROMIA-SHAMBU-282 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-2 2022-05-1 2022-06-2 2022-06-0 2022-07-0 102-GO-RFQ / procuremen IDA / D7320 ive Safety Net to Improve Post Limited 1,715.00 0.00 Completed tations e Envelope 2 4 7 4 6 6 t of Industrials Constructio the Urban Environment n Materials ET-OROMIA-SHAMBU-282 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-2 2022-05-1 2022-06-2 2022-06-1 2022-07-0 111-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 430.00 0.00 Completed tations e Envelope 8 4 2 4 1 1 t of Local Construction Mat the Urban Environment erials ET-OROMIA-GIMBI-282127 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-07-2 2022-05-0 2022-08-1 2022-05-2 2022-09-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 3,945.00 0.00 Completed tations e Envelope 2 7 6 9 6 6 Industrials Construction M the Urban Environment aterials ET-OROMIA-GIMBI-282130 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-07-2 2022-05-0 2022-08-1 2022-06-0 2022-10-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 2,500.00 0.00 Completed tations e Envelope 2 7 2 9 1 1 Local Construction Materia the Urban Environment ls ET-OROMIA-BATU-282181 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-05-0 2022-05-0 2022-06-0 2022-05-2 2022-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 1,240.00 0.00 Completed tations e Envelope 6 7 8 1 8 1 Different seedling for gree the Urban Environment nery activities ET-OROMIA-BATU-282186 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-05-0 2022-06-0 2022-05-2 2022-06-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 2,940.00 0.00 Completed tations e Envelope 1 7 2 1 7 6 Tent for chilled car center the Urban Environment ET-OROMIA-BATU-282187 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-05-0 2022-06-0 2022-05-2 2022-06-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 2,500.00 0.00 Completed tations e Envelope 1 7 2 1 7 0 Industrial construction Mat the Urban Environment erials ET-OROMIA-BATU-282188 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-05-0 2023-06-0 2022-05-2 2023-06-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 5,900.00 0.00 Completed tations e Envelope 3 7 3 1 3 1 Local Construction Materia the Urban Environment ls ET-OROMIA-BULE HORA-2 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-04-1 2022-05-1 2022-05-2 2022-06-0 2022-07-0 82190-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 1,250.00 0.00 Completed tations e Envelope 6 9 7 5 6 1 ent of Different seedlings f the Urban Environment or greenery activities ET-OROMIA-BULE HORA-2 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-05-0 2022-06-1 2022-05-3 2022-07-0 82191-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 1,960.00 0.00 Completed tations e Envelope 3 6 5 3 0 1 ent of Tent for chilled car c the Urban Environment enter ET-OROMIA-BULE HORA-2 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-05-0 2022-05-2 2022-05-2 2022-07-0 82194-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 3,800.00 0.00 Completed tations e Envelope 6 1 6 5 6 4 ent of Industrial Constructi the Urban Environment on Materials ET-OROMIA-BULE HORA-2 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-1 2022-05-0 2022-06-1 2022-06-0 2022-07-0 82196-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 1,870.00 0.00 Completed tations e Envelope 1 3 5 3 4 4 ent of Local construction M the Urban Environment aterials ET-OROMIA-DAMBI DOLO- Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-05-3 2022-06-0 2022-06-1 2022-06-2 2022-06-3 282325-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 1,990.00 0.00 Completed tations e Envelope 6 0 1 0 1 0 ment of Different Seedling the Urban Environment s for greenery Activities ET-OROMIA-DAMBI DOLO- Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-3 2022-05-0 2022-06-1 2022-06-0 2022-06-1 282465-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 11,900.00 0.00 Completed tations e Envelope 8 0 9 4 3 4 ment of Industrials constru the Urban Environment ction Materials ET-OROMIA-DAMBI DOLO- Expand the Urban Product 282467-GO-RFQ / Procure Request for Quo Single Stage - On 2022-03-2 2022-05-3 2022-05-2 2022-06-1 2022-06-1 2022-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 3,200.00 0.00 Completed ment of Finishing Materials tations e Envelope 9 0 0 0 4 7 the Urban Environment in Lot -1 and Waterline Inst allation Materials in Lot-2 Page 4 ET-OROMIA-282714-GO-R Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-10-1 2022-05-0 2022-11-0 2022-06-0 2022-11-1 FQ / Procurement of Lapto IDA / D7320 ive Safety Net to Improve Post Limited 10,780.00 0.00 Completed tations e Envelope 9 0 9 9 3 5 p computer and Printer for the Urban Environment the Regional staff ET-OROMIA-NEKEMTE-285 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-05-0 2022-05-1 2022-06-2 2022-06-0 2022-07-0 104-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 1,950.00 0.00 Completed tations e Envelope 6 4 3 0 2 5 t of Different Seedlings for the Urban Environment the greenery activities ET-OROMIA-NEKEMTE-285 Expand the Urban Product 180-GO-RFQ / Procuremen Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-05-0 2022-05-2 2022-06-0 2022-06-2 IDA / D7320 ive Safety Net to Improve Post Limited 8,500.00 0.00 Completed t of Industrials Constructio tations e Envelope 9 4 9 1 8 2 the Urban Environment n Materials for the constru ction of Public Toile ET-OROMIA-NEKEMTE-285 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-05-0 2022-05-1 2022-06-2 2022-06-0 2022-07-0 183-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 980.00 0.00 Completed tations e Envelope 2 4 3 0 7 5 t of Block for the construct the Urban Environment ion of Public Toilte ET-OROMIA-NEKEMTE-285 Expand the Urban Product 184-GO-RFQ / Procuremen Request for Quo Single Stage - On 2022-04-0 2022-05-0 2022-05-1 2022-06-2 2022-06-0 2022-06-2 IDA / D7320 ive Safety Net to Improve Post Limited 3,330.00 0.00 Completed t of Waterline installation tations e Envelope 2 4 3 0 7 2 the Urban Environment Materials in Lot-1 and Finis hing Materials in Lot-2 ET-OROMIA-NEKEMTE-285 Expand the Urban Product Request for Quo Single Stage - On 2022-03-3 2022-05-0 2022-05-1 2022-06-2 2022-06-0 2022-07-0 185-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 1,550.00 0.00 Completed tations e Envelope 0 4 0 0 9 5 t of Local Construction Mat the Urban Environment erials ET-OROMIA-NEGELE ARSI- Expand the Urban Product 285188-GO-RFQ / Procure Request for Quo Single Stage - On 2022-04-0 2022-05-3 2022-05-1 2022-06-2 2022-06-0 2022-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 3,750.00 3,809.77 Completed ment of Different Seedling tations e Envelope 6 0 3 6 2 8 the Urban Environment for the greenery Activities ET-OROMIA-HOLOTA-2851 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-03-2 2022-05-2 2022-04-1 2022-06-1 2022-06-0 90-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 1,270.00 0.00 Completed tations e Envelope 6 4 1 5 0 1 of Different seedlings for t the Urban Environment he greenery activietis ET-OROMIA-HOLOTA-2851 Expand the Urban Product 92-GO-RFQ / Procurement Request for Quo Single Stage - On 2022-03-2 2022-03-1 2022-05-0 2022-03-2 2022-05-2 2022-05-2 IDA / D7320 ive Safety Net to Improve Post Limited 7,340.00 0.00 Completed of Industrials Construction tations e Envelope 9 6 9 3 9 6 the Urban Environment Materials for the public toil et ET-OROMIA-HOLOTA-2852 Expand the Urban Product 10-GO-RFQ / Procurement Request for Quo Single Stage - On 2022-03-2 2022-03-1 2022-05-1 2023-03-1 2022-06-0 2023-05-2 IDA / D7320 ive Safety Net to Improve Post Limited 4,730.00 0.00 Completed of Finishing Materials in Lo tations e Envelope 9 0 3 6 2 4 the Urban Environment t-1 and Waterline Installati on Materials in Lot-2 ET-OROMIA-HOLOTA-2852 Expand the Urban Product Request for Quo Single Stage - On 2022-03-3 2023-03-2 2022-05-1 2022-03-2 2022-06-0 2022-07-0 12-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 3,280.00 0.00 Completed tations e Envelope 0 3 0 8 9 6 of Local Construction Mate the Urban Environment rials for public Toile ET-OROMIA-BEDELE-2852 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-06-1 2022-05-1 2022-06-1 2022-06-0 2022-06-2 21-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 1,950.00 0.00 Completed tations e Envelope 6 3 7 7 6 9 of Different Seedling for gr the Urban Environment eenery activities ET-OROMIA-BEDELE-2852 Expand the Urban Product Request for Quo Single Stage - On 2022-03-3 2022-05-2 2022-05-1 2022-06-0 2022-05-3 2022-06-0 27-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 14,450.00 0.00 Completed tations e Envelope 0 7 0 3 0 6 of Industrials Construction the Urban Environment Materials ET-OROMIA-BEDELE-2852 Expand the Urban Product 33-GO-RFQ / Procurement Request for Quo Single Stage - On 2022-03-3 2022-05-2 2022-05-1 2022-06-0 2022-06-0 2022-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 5,400.00 0.00 Completed of Finishing Materials in Lo tations e Envelope 0 7 0 2 9 5 the Urban Environment t-1 and Waterline Installati on Materials in Lot-2 ET-OROMIA-SHASHAMANE Expand the Urban Product -285241-GO-RFQ / procure Request for Quo Single Stage - On 2022-04-0 2022-04-2 2022-05-1 2022-05-1 2022-06-1 2022-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 5,800.00 0.00 Completed ment of Different Seedling tations e Envelope 6 1 7 9 6 6 the Urban Environment for the Greenery activities ET-OROMIA-SHASHAMANE Expand the Urban Product -285243-GO-RFQ / Procure Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-05-0 2022-05-1 2022-06-0 2022-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 6,400.00 0.00 Completed ment of Local Construction tations e Envelope 9 1 9 9 8 7 the Urban Environment Materials for Public Toilet ET-OROMIA-SHASHAMANE Expand the Urban Product -285244-GO-RFQ / Procure Request for Quo Single Stage - On 2022-03-3 2022-04-2 2022-05-0 2022-05-1 2022-06-0 2022-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 4,900.00 0.00 Completed ment of Industrial Constru tations e Envelope 0 1 9 9 3 7 the Urban Environment ction Materials for the Publ ic Toilet ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-04-2 2022-05-1 2023-05-1 2022-06-0 2023-05-1 -285246-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 475.00 0.00 Completed tations e Envelope 2 1 3 9 7 9 ment of Block for the Cons the Urban Environment truction of Public Toilet ET-OROMIA-SHASHAMANE Expand the Urban Product -285248-GO-RFQ / Procure Request for Quo Single Stage - On 2022-03-3 2022-04-2 2022-05-0 2022-05-1 2022-05-3 2022-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 3,500.00 0.00 Completed ment of Finishing Materials tations e Envelope 0 1 6 9 1 7 the Urban Environment in Lot-1 and Waterline Inst allation Materials in Lot-2 ET-OROMIA-FICHE-285410 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-06-1 2022-05-1 2022-07-0 2022-06-1 2022-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 1,360.00 0.00 Completed tations e Envelope 6 5 7 4 6 6 Different Seedlings for the the Urban Environment greenery activities ET-OROMIA-FICHE-285425 Expand the Urban Product -GO-RFQ / Procurement of Request for Quo Single Stage - On 2022-03-3 2022-04-2 2022-05-1 2022-06-0 2022-06-0 2022-06-1 IDA / D7320 ive Safety Net to Improve Post Limited 2,760.00 0.00 Completed Industrials construction Ma tations e Envelope 0 7 4 9 3 6 the Urban Environment terials for the construction of Fence ET-OROMIA-FICHE-285426 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-04-2 2022-05-1 2022-06-0 2022-06-0 2022-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 735.00 0.00 Completed tations e Envelope 2 7 3 2 2 2 Local construction Material the Urban Environment s for the Fence greenery ET-OROMIA-ROBE-285428 Expand the Urban Product -GO-RFQ / procurement of Request for Quo Single Stage - On 2022-03-3 2022-04-0 2022-05-1 2022-05-0 2022-06-0 2022-06-2 IDA / D7320 ive Safety Net to Improve Post Limited 7,150.00 0.00 Completed Industrials Construction M tations e Envelope 0 1 2 3 1 8 the Urban Environment aterials for the constructio n of public Toilet ET-OROMIA-ROBE-285431 Expand the Urban Product -GO-RFQ / Procurement of Request for Quo Single Stage - On 2022-04-0 2022-04-0 2022-05-1 2022-06-3 2022-06-1 2022-06-3 IDA / D7320 ive Safety Net to Improve Post Limited 1,455.00 0.00 Completed Finishing Materials in Lot-1 tations e Envelope 4 1 6 0 5 0 the Urban Environment and Waterline Installation Materials in Lot-2 ET-OROMIA-ROBE-285433 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-05-0 2022-05-0 2022-06-0 2022-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 4,420.00 0.00 Completed tations e Envelope 9 1 9 3 8 7 Local Construction Materia the Urban Environment ls ET-OROMIA-ROBE-285436 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-04-0 2022-05-1 2022-05-0 2022-06-1 2022-06-3 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 3,520.00 0.00 Completed tations e Envelope 4 1 6 3 5 0 Tent for the Child care cen the Urban Environment ter ET-OROMIA-ADAMA-30964 Expand the Urban Product Single Stage - On 2022-09-2 2022-12-0 2022-09-2 2022-10-2 2023-01-0 2022-11-1 2023-02-1 2022-12-0 2023-02-2 2023-01-1 2023-04-1 4-GO-RFB / Procurement of IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 208,810.00 0.00 Completed e Envelope 3 3 8 8 2 1 3 9 3 8 0 Safety Materials the Urban Environment ET-OROMIA-ADAMA-30964 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-02-0 2022-11-2 2023-03-0 2022-12-2 2023-04-1 6-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 16,826.00 0.00 Completed tations e Envelope 3 9 1 6 1 2 f Hand Tools Materials the Urban Environment ET-OROMIA-ADAMA-30968 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-04-0 2022-11-2 2023-06-1 2022-12-2 2023-07-0 4-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 77,265.00 0.00 Completed tations e Envelope 5 7 3 2 3 6 f Industrials construction M the Urban Environment aterials ET-OROMIA-ADAMA-30970 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-04-0 2022-11-1 2023-06-1 2022-12-1 2023-07-0 1-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 13,005.00 0.00 Completed tations e Envelope 7 7 2 2 2 5 f Local Construction Materi the Urban Environment als ET-OROMIA-ADAMA-30970 6-GO-RFQ / Procurement o Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-04-0 2022-11-1 2023-06-1 2022-12-1 2023-07-0 f Block for the construction IDA / D7320 ive Safety Net to Improve Post Limited 4,615.00 0.00 Completed tations e Envelope 6 7 4 2 4 5 of Public Toilet and the co the Urban Environment nstruction of School additi onal class ET-OROMIA-JIMA-309714- Expand the Urban Product Single Stage - On 2022-09-2 2022-12-0 2022-09-2 2023-10-1 2022-10-2 2023-01-0 2022-11-1 2023-02-0 2022-12-0 2023-02-2 2023-01-1 2023-05-1 GO-RFB / Procurement of S IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 266,610.00 0.00 Completed e Envelope 3 7 8 9 8 6 1 1 9 4 8 1 afety Materials the Urban Environment ET-OROMIA-JIMA-309716- Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-01-1 2022-11-1 2023-01-2 2022-12-1 2023-05-0 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 59,230.00 0.00 Completed tations e Envelope 8 0 6 7 6 3 Hand Tools Materials the Urban Environment ET-OROMIA-JIMA-309719- Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-02-2 2022-11-2 2023-03-0 2022-12-2 2023-07-0 GO-RFQ / Procurement of I IDA / D7320 ive Safety Net to Improve Post Limited 29,480.00 0.00 Completed tations e Envelope 4 4 2 3 2 7 ndustrial construction Mat the Urban Environment erials ET-OROMIA-JIMA-309723- Expand the Urban Product GO-RFQ / Procurement of F Request for Quo Single Stage - On 2022-10-0 2023-02-1 2022-11-1 2023-03-0 2022-12-1 2023-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 16,770.00 0.00 Completed inishing construction Mate tations e Envelope 5 6 9 9 9 6 the Urban Environment rials in Lot-1 and Waterline installation Materials in Lot -2 ET-OROMIA-JIMA-309728- Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-02-1 2022-11-2 2023-03-0 2022-12-2 2023-07-0 GO-RFQ / Procurement of L IDA / D7320 ive Safety Net to Improve Post Limited 19,206.00 0.00 Completed tations e Envelope 3 6 1 9 1 6 ocal Construction Material the Urban Environment s ET-OROMIA-AGARO-30974 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-11-0 2022-11-1 2022-12-2 2022-12-1 2023-01-0 9-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 48,560.00 0.00 Completed tations e Envelope 8 1 6 3 6 9 f Safety Materials the Urban Environment ET-OROMIA-AGARO-30975 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-02-1 2022-11-1 2023-03-0 2022-12-1 2023-03-2 2-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 12,708.00 0.00 Completed tations e Envelope 7 6 5 3 5 4 f Hand Tools Materials the Urban Environment ET-OROMIA-AGARO-30975 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-05-0 2022-11-2 2023-07-0 2022-12-2 2023-07-0 4-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 8,680.00 0.00 Completed tations e Envelope 5 3 3 1 3 3 f Industrial construction M the Urban Environment aterials ET-OROMIA-AGARO-30975 Expand the Urban Product 7-GO-RFQ / Procurement o Request for Quo Single Stage - On 2022-09-2 2023-05-0 2022-11-1 2023-05-2 2022-12-1 2023-06-1 IDA / D7320 ive Safety Net to Improve Post Limited 1,593.00 0.00 Completed f Finishing Construction Ma tations e Envelope 6 3 0 2 0 9 the Urban Environment terials in Lot-1 and Waterli ne Installation in Lot-2 ET-OROMIA-AGARO-30975 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-05-0 2022-11-2 2023-07-0 2022-12-2 2023-06-2 8-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 3,388.00 0.00 Completed tations e Envelope 3 3 1 1 1 3 f Local Construction Materi the Urban Environment als ET-OROMIA-CHIRO-30980 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-02-0 2022-11-1 2023-03-0 2022-12-1 2023-03-2 8-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 54,000.00 0.00 Completed tations e Envelope 8 6 6 1 6 0 f Safety Materials the Urban Environment ET-OROMIA-CHIRO-30981 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-1 2022-11-1 2023-01-1 2022-12-1 2023-03-0 5-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 20,480.00 0.00 Completed tations e Envelope 6 9 0 8 0 8 f Hand Tools Materials the Urban Environment ET-OROMIA-CHIRO-30983 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-1 2022-11-1 2023-01-1 2022-12-1 2023-02-0 8-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 13,903.00 0.00 Completed tations e Envelope 7 9 5 7 5 3 f Industrial construction M the Urban Environment aterials ET-OROMIA-CHIRO-30984 Expand the Urban Product 2022-09-2 2023-02-1 2022-10-0 2023-02-1 2022-10-2 2023-01-1 2022-11-1 2023-07-0 9-GO-DIR / Procurement of IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 3,526.00 0.00 Completed 8 4 3 4 7 8 6 4 Cement for the constructio the Urban Environment n of Public Toilet ET-OROMIA-CHIRO-30985 Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2023-03-2 2022-11-2 2023-04-1 2022-12-2 2023-07-0 2-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 675.00 0.00 Completed tations e Envelope 0 1 4 8 4 7 f Block for the construction the Urban Environment of Public Toilet ET-OROMIA-CHIRO-30985 Expand the Urban Product 5-GO-RFQ / Procurement o Request for Quo Single Stage - On 2022-09-2 2023-02-2 2022-11-1 2023-03-3 2022-12-1 2023-05-0 IDA / D7320 ive Safety Net to Improve Post Limited 2,768.00 0.00 Completed f Finishing construction Ma tations e Envelope 7 0 4 1 4 3 the Urban Environment terials in Lot-1 and Waterli ne Installation Materials in Lot-2 ET-OROMIA-CHIRO-30986 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-02-2 2022-11-2 2023-03-2 2022-12-2 2023-06-2 8-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 7,632.00 0.00 Completed tations e Envelope 4 4 2 1 2 7 f Local Construction Materi the Urban Environment als ET-OROMIA-ADAMA-31032 Expand the Urban Product 6-GO-DIR / Procurement of 2022-09-2 2023-05-0 2022-09-2 2023-05-0 2022-10-2 2023-05-1 2022-11-1 2023-06-1 IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 13,846.00 0.00 Completed Cement for the constructio 3 9 8 9 2 5 1 5 the Urban Environment n of Public Toilet, Addition al class room ET-OROMIA-JIMA-309883- Expand the Urban Product 2022-09-3 2023-02-2 2022-10-0 2023-03-0 2022-10-2 2023-03-2 2022-11-1 2023-07-0 GO-DIR / Procurement of C IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 7,210.00 0.00 Completed 0 1 5 1 9 7 8 6 ement for the procuremen the Urban Environment t of public Toilet ET-OROMIA-DERA-309891 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-01-1 2022-11-1 2023-01-2 2022-12-1 2023-04-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 26,899.00 0.00 Completed tations e Envelope 8 3 6 3 6 7 Safety Materials the Urban Environment ET-OROMIA-DERA-309897 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-01-1 2022-11-1 2023-07-0 2022-12-1 2023-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 2,267.00 0.00 Completed tations e Envelope 7 7 5 3 5 7 Hand Tools Materials the Urban Environment ET-OROMIA-DERA-309904 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-01-1 2022-11-2 2023-01-2 2022-12-2 2023-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 3,230.00 0.00 Completed tations e Envelope 3 2 1 6 1 7 Industrial Construction Mat the Urban Environment erials ET-OROMIA-DERA-309907 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-01-1 2022-11-2 2023-02-0 2022-12-2 2023-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 728.00 0.00 Completed tations e Envelope 5 3 3 6 3 7 Water line Installation Mat the Urban Environment erials ET-OROMIA-DERA-309921 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-02-0 2022-11-2 2023-02-1 2022-12-2 2023-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 7,537.00 0.00 Completed tations e Envelope 4 4 2 9 2 6 Local Construction Materia the Urban Environment ls Page 5 ET-OROMIA-FICHE-310407 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-0 2022-11-1 2023-02-2 2022-12-1 2023-02-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 67,406.00 0.00 Completed tations e Envelope 8 7 6 0 6 0 Safety Materials the Urban Environment ET-OROMIA-FICHE-310410 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-0 2022-11-1 2023-01-2 2022-12-1 2023-02-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 5,014.00 0.00 Completed tations e Envelope 6 7 4 0 4 0 Hand Tools Materials the Urban Environment ET-OROMIA-FICHE-310414 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-03-2 2022-11-2 2023-05-0 2022-12-2 2023-05-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 7,215.00 0.00 Completed tations e Envelope 3 0 1 2 1 7 Industrials Construction M the Urban Environment aterials ET-OROMIA-FICHE-310431 Expand the Urban Product 2022-09-2 2023-05-2 2022-10-0 2023-05-2 2022-10-2 2023-05-2 2022-11-1 2023-06-0 -GO-DIR / Procurement of IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 923.00 0.00 Completed 9 4 4 3 8 4 7 7 Cement for the constructio the Urban Environment n of public Toilet ET-OROMIA-FICHE-310433 Expand the Urban Product -GO-RFQ / Procurement of Request for Quo Single Stage - On 2022-09-2 2023-06-2 2022-11-1 2023-07-0 2022-12-1 2023-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 520.00 0.00 Completed Finishing Materials in Lot-1 tations e Envelope 6 2 0 3 0 7 the Urban Environment and Waterline installation Materials in Lot-2 ET-OROMIA-FICHE-310436 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-03-2 2022-11-2 2023-04-2 2022-12-2 2023-05-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 3,709.00 0.00 Completed tations e Envelope 3 0 1 8 1 1 Local Construction Materia the Urban Environment ls ET-OROMIA-HARAMAYA-3 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-03-0 2022-11-1 2023-01-2 2022-12-1 2023-01-2 10446-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 33,080.00 0.00 Completed tations e Envelope 8 4 6 3 6 8 ent of Safety Materials the Urban Environment ET-OROMIA-HARAMAYA-3 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-01-0 2022-11-1 2023-01-2 2022-12-1 2023-03-1 10449-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 11,656.00 0.00 Completed tations e Envelope 7 3 5 6 5 3 ent of Hand Tools Material the Urban Environment s ET-OROMIA-NEGELE ARSI- Expand the Urban Product Single Stage - On 2022-09-2 2022-11-0 2022-09-2 2022-10-2 2022-12-0 2022-11-1 2023-01-1 2022-12-1 2023-01-3 2023-01-2 2023-02-1 310482-GO-RFB / Procure IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 109,715.00 0.00 Completed e Envelope 3 8 8 8 8 7 2 5 0 4 5 ment of Safety Materials the Urban Environment ET-OROMIA-NEGELE ARSI- Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-1 2022-11-1 2023-01-2 2022-12-1 2023-02-0 310485-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 36,666.00 0.00 Completed tations e Envelope 6 9 4 4 4 7 ment of Hand Tools Materi the Urban Environment als ET-OROMIA-NEGELE ARSI- Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-12-1 2022-11-2 2023-04-1 2022-12-2 2023-04-2 310487-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 2,527.00 0.00 Completed tations e Envelope 3 9 1 1 1 6 ment of Industrial construc the Urban Environment tion Materials ET-OROMIA-NEGELE ARSI- Expand the Urban Product 310493-GO-DIR / Procure 2022-10-0 2023-05-0 2022-10-1 2023-05-0 2022-11-0 2023-06-0 2022-11-2 2023-06-2 IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 3,846.00 0.00 Completed ment of Cement for the Co 5 5 0 5 4 9 4 7 the Urban Environment nstruction of Urban infrastr uctures ET-OROMIA-NEGELE ARSI- Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-05-0 2022-11-1 2023-05-3 2022-12-1 2023-06-0 310497-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 4,946.00 0.00 Completed tations e Envelope 7 5 5 1 5 5 ment of Local Construction the Urban Environment Materials ET-OROMIA-NEGELE ARSI- Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-12-1 2022-11-2 2023-01-2 2022-12-2 2023-02-0 310501-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 1,153.00 0.00 Completed tations e Envelope 5 9 3 4 3 7 ment of Block for the const the Urban Environment ruction of Public Toilet ET-OROMIA-MATU-310901 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-11-2 2022-11-1 2022-12-1 2022-12-1 2023-01-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 53,604.00 0.00 Completed tations e Envelope 6 8 4 9 4 6 Safety Materials the Urban Environment ET-OROMIA-MATU-310907 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-11-2 2022-11-1 2022-12-2 2022-12-1 2023-01-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 10,884.00 0.00 Completed tations e Envelope 7 8 5 8 5 3 Hand Tools Materials the Urban Environment ET-OROMIA-MATU-310912 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-11-2 2022-11-1 2022-12-1 2022-12-1 2023-03-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 11,080.00 0.00 Completed tations e Envelope 8 8 6 9 6 2 Industrial construction Mat the Urban Environment erials ET-OROMIA-MATU-310915 Expand the Urban Product 2022-09-3 2023-05-1 2022-10-0 2023-05-1 2022-10-2 2024-05-2 2022-11-1 2024-05-2 -GO-DIR / Procurement of IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 25,558.00 0.00 Completed 0 1 5 5 5 0 4 0 Cement for the constructio the Urban Environment n of Public Toilet ET-OROMIA-MATU-310916 Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2022-11-2 2022-11-2 2022-12-2 2022-12-2 2023-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 1,549.00 0.00 Completed tations e Envelope 0 8 8 9 8 1 Block for the construction the Urban Environment of public Toile ET-OROMIA-MATU-310918 Expand the Urban Product -GO-RFQ / Procurement of Request for Quo Single Stage - On 2022-10-1 2022-12-0 2022-11-2 2022-12-1 2022-12-2 2023-01-2 IDA / D7320 ive Safety Net to Improve Post Limited 2,505.00 0.00 Completed Finishing construction Mat tations e Envelope 1 8 9 9 9 6 the Urban Environment erials in Lot-1 and Waterlin e Installation Materials in L ot- 2 ET-OROMIA-MATU-310921 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-12-0 2022-11-2 2023-01-3 2022-12-2 2023-05-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 6,068.00 0.00 Completed tations e Envelope 4 9 2 1 2 4 Local construction Material the Urban Environment s ET-OROMIA-SABATA-3109 Expand the Urban Product Single Stage - On 2022-09-2 2022-11-0 2022-09-2 2022-10-2 2022-12-0 2022-11-1 2023-01-0 2022-12-1 2023-02-0 2023-01-2 2023-03-0 27-GO-RFB / Procurement IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 122,288.00 0.00 Completed e Envelope 1 8 6 6 8 5 6 4 7 3 9 of Safety Materials the Urban Environment ET-OROMIA-SABATA-3109 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-01-1 2022-11-1 2022-10-1 2022-12-1 2023-03-3 30-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 25,310.00 0.00 Completed tations e Envelope 7 1 5 7 5 1 of Hand Tools Materials the Urban Environment ET-OROMIA-SABATA-3109 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-06-1 2022-11-1 2023-07-0 2022-12-1 2023-07-0 35-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 5,587.00 0.00 Completed tations e Envelope 8 3 6 4 6 5 of Industrial construction the Urban Environment Materials ET-OROMIA-SABATA-3109 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-08-3 2022-11-2 2023-09-2 2022-12-2 2023-10-1 41-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 403.00 0.00 Completed tations e Envelope 5 0 3 9 3 6 of Block for the constructio the Urban Environment n of public Toilet ET-OROMIA-SABATA-3109 Expand the Urban Product 2022-09-2 2023-08-3 2022-10-0 2023-08-3 2022-10-2 2023-09-2 2022-11-1 2023-10-1 42-GO-DIR / Procurement IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 1,875.00 0.00 Completed 9 0 4 0 8 9 7 6 of Cement for the construc the Urban Environment tion of public Toilet ET-OROMIA-SABATA-3109 44-GO-RFQ / Procurement Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2023-06-1 2022-11-2 2023-07-0 2022-12-2 2023-08-0 of Finishing construction M IDA / D7320 ive Safety Net to Improve Post Limited 3,290.00 0.00 Completed tations e Envelope 0 3 8 4 8 4 aterials in Lot-1 and Water the Urban Environment line Installation Materials i n Lot-2 ET-OROMIA-SABATA-3109 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-08-3 2022-11-2 2023-09-0 2022-12-2 2023-10-0 46-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 7,307.00 0.00 Completed tations e Envelope 4 0 2 8 2 9 of Local Construction Mate the Urban Environment rials ET-OROMIA-SHASHAMANE Expand the Urban Product Single Stage - On 2022-09-2 2022-12-0 2022-09-2 2022-10-2 2023-01-0 2022-11-1 2023-01-2 2022-12-1 2023-02-1 2023-01-2 2023-03-0 -311053-GO-RFB / Procure IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 232,929.00 0.00 Completed e Envelope 1 2 6 6 2 5 3 4 4 3 8 ment of Safety Materials the Urban Environment ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-01-3 2022-11-1 2023-02-2 2022-12-1 2023-03-0 -311098-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 55,552.00 0.00 Completed tations e Envelope 7 1 5 7 5 9 ment of Hand Tools Materi the Urban Environment als ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-03-3 2022-11-1 2023-05-0 2022-12-1 2023-06-2 -311102-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 12,175.00 0.00 Completed tations e Envelope 8 1 6 9 6 6 ment of Industrial construc the Urban Environment tion Materials ET-OROMIA-SHASHAMANE Expand the Urban Product -311115-GO-DIR / Procure 2022-09-3 2023-06-0 2022-10-0 2023-06-0 2022-10-2 2023-06-3 2022-11-1 2023-07-0 IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 2,307.00 0.00 Completed ment of Cement for the co 0 6 5 6 9 0 8 5 the Urban Environment nstruction of Public Toilet ET-OROMIA-SHASHAMANE -311121-GO-RFQ / Procure Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2023-06-0 2022-11-2 2023-06-3 2022-12-2 2023-07-0 ment of Finishing construc IDA / D7320 ive Safety Net to Improve Post Limited 8,069.00 0.00 Completed tations e Envelope 0 6 8 0 8 5 tion Materials in Lot-1 and the Urban Environment Waterline Installation Mate rials in Lot-02 ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-03-3 2022-11-2 2023-05-0 2022-12-2 2023-06-2 -311126-GO-RFQ / procure IDA / D7320 ive Safety Net to Improve Post Limited 9,489.00 0.00 Completed tations e Envelope 4 1 2 9 2 6 ment of Local construction the Urban Environment Materials ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-03-3 2022-11-1 2023-05-0 2022-12-1 2023-06-2 -311135-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 1,046.00 0.00 Completed tations e Envelope 3 1 7 9 7 6 ment of Block for the publi the Urban Environment c Toile ET-OROMIA-ASALA-31118 Expand the Urban Product Single Stage - On 2022-09-2 2022-11-1 2022-09-2 2024-05-3 2022-10-2 2022-12-2 2022-11-1 2023-01-0 2022-12-1 2023-06-2 2023-01-2 2023-05-0 3-GO-RFB / Procurement of IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 170,298.00 0.00 Completed e Envelope 1 4 6 0 6 2 5 5 4 3 3 2 Safety Materials the Urban Environment ET-OROMIA-ASALA-31118 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-01-2 2022-11-1 2023-02-2 2022-12-1 2023-03-0 4-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 11,120.00 0.00 Completed tations e Envelope 7 6 5 1 5 6 f Hand Tools Materials the Urban Environment ET-OROMIA-ASALA-31118 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-03-2 2022-11-1 2023-04-2 2022-12-1 2023-06-2 5-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 9,823.00 0.00 Completed tations e Envelope 8 8 6 5 6 9 f Industrial construction M the Urban Environment aterials ET-OROMIA-ASALA-31118 Expand the Urban Product 2022-09-3 2023-03-2 2022-10-0 2023-03-2 2022-10-2 2023-04-2 2022-11-1 2023-06-0 6-GO-DIR / Procurement of IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 8,365.00 0.00 Completed 0 8 5 8 9 5 8 7 Cement for the constructio the Urban Environment n of public Toile ET-OROMIA-ASALA-31145 Expand the Urban Product 9-GO-RFQ / Procurement o Request for Quo Single Stage - On 2022-10-1 2023-03-2 2022-11-2 2023-04-2 2022-12-2 2023-06-2 IDA / D7320 ive Safety Net to Improve Post Limited 2,246.00 0.00 Completed f Finishing Construction Ma tations e Envelope 0 8 8 5 8 9 the Urban Environment terials in Lot -1 and Waterli ne Installation Materials in Lot-2 ET-OROMIA-ASALA-31146 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-03-2 2022-11-2 2023-04-1 2022-12-2 2023-07-0 4-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 11,754.00 0.00 Completed tations e Envelope 4 8 2 9 2 6 f Local Construction Materi the Urban Environment als ET-OROMIA-BURAYU-3115 Expand the Urban Product Single Stage - On 2022-09-2 2022-12-0 2022-09-2 2022-10-2 2023-01-0 2022-11-1 2023-01-0 2022-12-1 2023-02-0 2023-01-2 2023-03-0 00-GO-RFB / Procurement IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 97,705.00 0.00 Completed e Envelope 1 6 6 6 5 5 6 4 2 3 6 of Safety Materials the Urban Environment ET-OROMIA-BURAYU-3115 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-1 2022-11-1 2023-01-0 2022-12-1 2023-02-2 05-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 33,326.00 0.00 Completed tations e Envelope 7 2 5 2 5 1 of Hand Tools Materials the Urban Environment ET-OROMIA-BURAYU-3115 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-04-0 2022-11-1 2023-04-2 2022-12-1 2023-05-2 09-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 11,910.00 0.00 Completed tations e Envelope 8 7 6 8 6 3 of Industrials construction the Urban Environment Materials ET-OROMIA-BURAYU-3115 Expand the Urban Product 2022-09-2 2023-04-0 2022-10-0 2023-04-0 2022-10-2 2023-04-2 2022-11-1 2023-05-2 15-GO-DIR / Procurement IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 3,750.00 0.00 Completed 9 7 4 7 8 8 7 3 of Cement for the construc the Urban Environment tion of Public Toile ET-OROMIA-BURAYU-3115 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-04-0 2022-11-2 2023-04-2 2022-12-2 2023-07-0 17-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 3,461.00 0.00 Completed tations e Envelope 5 7 3 8 3 7 of Block for the constructio the Urban Environment n of public Toilet ET-OROMIA-BURAYU-3115 Expand the Urban Product 38-GO-RFQ / Procurement Request for Quo Single Stage - On 2022-10-1 2023-04-0 2022-11-2 2023-04-2 2022-12-2 2023-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 1,569.00 0.00 Completed of Finishing Materials and tations e Envelope 0 7 8 8 8 7 the Urban Environment Waterline Installation Mate rials ET-OROMIA-BURAYU-3115 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-04-0 2022-11-2 2023-04-2 2022-12-2 2023-07-0 39-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 10,102.00 0.00 Completed tations e Envelope 4 7 2 8 2 7 of Local construction Mate the Urban Environment rials ET-OROMIA-NEKEMTE-311 Expand the Urban Product Single Stage - On 2022-09-2 2022-12-1 2022-09-2 2022-10-2 2023-01-1 2022-11-1 2023-02-0 2022-12-1 2023-02-2 2023-01-2 2023-03-1 564-GO-RFB / Procurement IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 131,725.00 0.00 Completed e Envelope 1 2 6 6 2 5 6 4 4 3 0 of Safety Materials the Urban Environment ET-OROMIA-NEKEMTE-311 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-01-0 2022-11-1 2023-02-0 2022-12-1 2023-02-1 566-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 40,826.00 0.00 Completed tations e Envelope 7 3 5 8 5 7 t of Hand Tools Materials the Urban Environment ET-OROMIA-NEKEMTE-311 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-06-1 2022-11-1 2023-06-2 2022-12-1 2023-07-0 571-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 31,967.00 0.00 Completed tations e Envelope 8 3 6 7 6 7 t of Industrial construction the Urban Environment Materials ET-OROMIA-NEKEMTE-311 Expand the Urban Product 2022-09-3 2023-06-1 2022-10-0 2023-06-1 2022-10-2 2023-06-2 2022-11-1 2023-07-0 575-GO-DIR / Procurement IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 10,096.00 0.00 Completed 0 3 5 3 9 7 8 7 of Cement for the construc the Urban Environment tion of public Toilet ET-OROMIA-NEKEMTE-311 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-06-1 2022-11-2 2023-06-0 2022-12-2 2023-06-1 577-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 8,653.00 0.00 Completed tations e Envelope 4 3 2 7 2 2 t of Local construction Mat the Urban Environment erials ET-OROMIA-NEKEMTE-311 Expand the Urban Product 578-GO-RFQ / Procuremen Request for Quo Single Stage - On 2022-10-1 2023-06-1 2022-11-2 2023-06-2 2022-12-2 2023-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 19,230.00 0.00 Completed t of Finishing Materials in L tations e Envelope 0 3 8 7 8 7 the Urban Environment ot-1 and Waterline Installa tion Materials in Lot-2 ET-OROMIA-NEKEMTE-311 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-06-1 2022-11-1 2023-07-0 2022-12-1 2023-07-0 583-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 1,692.00 0.00 Completed tations e Envelope 5 3 9 7 9 7 t of Block for the construct the Urban Environment ion of public Toilet ET-OROMIA-GINCHI-31189 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-1 2022-11-1 2023-01-2 2022-12-1 2023-03-2 6-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 26,310.00 0.00 Completed tations e Envelope 6 5 4 0 4 1 f Safety Materials the Urban Environment Page 6 ET-OROMIA-GINCHI-31189 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-1 2022-11-1 2023-04-1 2022-12-1 2023-04-1 7-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 1,250.00 0.00 Completed tations e Envelope 7 5 6 0 6 0 f Hand Tools Materials the Urban Environment ET-OROMIA-GINCHI-31190 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-1 2022-11-1 2023-01-2 2022-12-1 2023-05-1 8-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 11,168.00 0.00 Completed tations e Envelope 8 5 6 0 6 1 f Industrial construction M the Urban Environment aterials ET-OROMIA-GINCHI-31191 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-12-1 2022-11-2 2023-01-2 2022-12-2 2023-04-1 1-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 1,760.00 0.00 Completed tations e Envelope 4 5 2 0 2 0 f Block for the construction the Urban Environment public Toilet ET-OROMIA-GINCHI-31191 Expand the Urban Product 2022-09-2 2023-04-0 2022-10-0 2023-04-0 2022-10-2 2023-04-0 2022-11-1 2023-04-0 2-GO-DIR / Procurement of IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 2,602.00 0.00 Completed 8 6 3 6 7 6 6 7 Cement for the constructio the Urban Environment n of public Toile ET-OROMIA-GINCHI-31191 Expand the Urban Product 3-GO-RFQ / Procurement o Request for Quo Single Stage - On 2022-10-1 2022-12-1 2022-11-2 2023-01-2 2022-12-2 2023-03-2 IDA / D7320 ive Safety Net to Improve Post Limited 832.00 0.00 Completed f Finishing Materials and W tations e Envelope 0 3 8 0 8 8 the Urban Environment aterline Installation Materi als ET-OROMIA-GINCHI-31191 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-12-1 2022-11-2 2023-01-2 2022-12-2 2023-03-0 6-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 8,393.00 0.00 Completed tations e Envelope 4 5 2 0 2 8 f Local Construction Materi the Urban Environment als ET-OROMIA-BADESA-3119 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-01-1 2022-11-1 2023-01-2 2022-12-1 2023-04-0 37-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 36,750.00 0.00 Completed tations e Envelope 6 3 4 7 4 4 of Safety Materials the Urban Environment ET-OROMIA-BADESA-3119 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-01-1 2022-11-1 2023-01-2 2022-12-1 2023-03-2 45-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 3,943.00 0.00 Completed tations e Envelope 6 3 4 7 4 4 of Hand Tools Materials the Urban Environment ET-OROMIA-BADESA-3119 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-02-0 2022-11-1 2023-02-2 2022-12-1 2023-05-3 49-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 5,480.00 0.00 Completed tations e Envelope 8 7 6 1 6 0 of Industrial construction the Urban Environment Materials ET-OROMIA-BADESA-3119 Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2023-02-0 2022-11-2 2023-02-1 2022-12-1 2023-05-2 55-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 424.00 0.00 Completed tations e Envelope 0 7 4 4 4 3 of Finishing Construction M the Urban Environment aterials ET-OROMIA-BADESA-3119 Expand the Urban Product 2022-09-3 2023-03-0 2022-10-0 2023-03-1 2022-10-2 2023-03-2 2022-11-1 2023-05-1 57-GO-DIR / Procurement IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 2,596.00 0.00 Completed 0 8 5 0 9 3 8 8 of Cement for the construc the Urban Environment tion of store ET-OROMIA-BADESA-3124 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-02-0 2022-11-2 2023-02-2 2022-12-2 2023-05-2 78-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 4,911.00 0.00 Completed tations e Envelope 3 7 1 1 1 3 of Local Construction Mate the Urban Environment rials ET-OROMIA-BATU-312480 Expand the Urban Product Single Stage - On 2022-09-2 2022-12-1 2022-09-2 2022-10-2 2023-01-2 2022-11-1 2023-01-2 2022-12-1 2023-04-0 2023-01-2 2023-06-1 -GO-RFB / Procurement of IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 101,240.00 0.00 Completed e Envelope 1 9 6 6 0 5 1 4 6 3 4 Safety Materials the Urban Environment ET-OROMIA-BATU-312481 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-01-1 2022-11-1 2023-03-1 2022-12-1 2023-03-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 19,606.00 0.00 Completed tations e Envelope 7 0 5 6 5 7 Hand Tools Martials the Urban Environment ET-OROMIA-BATU-312482 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-05-0 2022-11-1 2023-06-0 2022-12-1 2023-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 22,524.00 0.00 Completed tations e Envelope 8 8 6 2 6 4 Industrial construction Mat the Urban Environment erials ET-OROMIA-BATU-312485 Expand the Urban Product -GO-DIR / Procurement of 2022-09-3 2023-05-0 2022-10-0 2023-05-0 2022-10-2 2023-06-0 2022-11-1 2023-06-1 IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 5,770.00 0.00 Completed Cement for the constructio 0 8 5 8 9 2 8 5 the Urban Environment n of store and Fence for gr eenery ET-OROMIA-BATU-312486 Expand the Urban Product -GO-RFQ / Procurement of Request for Quo Single Stage - On 2022-10-1 2023-05-0 2022-11-2 2023-06-0 2022-12-2 2023-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 1,882.00 0.00 Completed Finishing Construction Mat tations e Envelope 0 8 8 2 8 4 the Urban Environment erials and Waterline Install ation Materials ET-OROMIA-BATU-312487 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-05-0 2022-11-1 2023-06-0 2022-12-1 2023-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 5,288.00 0.00 Completed tations e Envelope 8 8 6 2 6 3 Local Construction Materia the Urban Environment ls ET-OROMIA-BATU-312488 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-05-0 2022-11-2 2023-06-0 2022-12-2 2023-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 1,096.00 0.00 Completed tations e Envelope 4 8 2 2 2 3 Block for the construction the Urban Environment of store ET-OROMIA-WALISO-3125 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-11-2 2022-11-1 2023-02-2 2022-12-1 2023-04-2 56-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 78,210.00 0.00 Completed tations e Envelope 6 5 4 2 4 8 of Safety Materials the Urban Environment ET-OROMIA-WALISO-3125 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-11-2 2022-11-1 2023-02-2 2022-12-1 2023-04-0 60-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 15,656.00 0.00 Completed tations e Envelope 8 4 6 2 6 7 of Hand Tools Materials the Urban Environment ET-OROMIA-WALISO-3125 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-04-0 2022-11-1 2023-05-1 2022-12-1 2023-07-0 63-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 14,026.00 0.00 Completed tations e Envelope 7 3 5 5 5 5 of Industrial construction the Urban Environment Materials ET-OROMIA-WALISO-3125 Expand the Urban Product 65-GO-RFQ / Procurement Request for Quo Single Stage - On 2022-10-0 2023-04-0 2022-11-2 2023-05-1 2022-12-2 2023-06-0 IDA / D7320 ive Safety Net to Improve Post Limited 714.00 0.00 Completed of Finishing Materials and tations e Envelope 4 3 2 5 2 7 the Urban Environment Water line Installation Mat erials ET-OROMIA-WALISO-3125 Expand the Urban Product 2022-09-3 2023-04-0 2022-10-0 2023-03-3 2022-10-2 2023-05-0 2022-11-2 2023-06-0 68-GO-DIR / Procurement IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 1,884.00 0.00 Completed 0 3 5 1 5 9 4 2 of Cement for the constru the Urban Environment ction of Public Toilet ET-OROMIA-WALISO-3125 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-04-0 2022-11-1 2023-05-2 2022-12-1 2023-07-0 71-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 6,273.00 0.00 Completed tations e Envelope 8 3 6 9 6 6 of Local Construction Mate the Urban Environment rials ET-OROMIA-WALISO-3125 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-04-0 2022-11-2 2023-05-2 2022-12-2 2023-07-0 73-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 1,036.00 0.00 Completed tations e Envelope 5 3 3 9 3 7 of Block for the constructio the Urban Environment n of Public Toilet ET-OROMIA-BEDELE-3127 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-03-1 2022-11-1 2023-04-0 2022-12-1 2023-04-2 16-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 45,548.00 0.00 Completed tations e Envelope 6 7 4 7 4 0 of Safety Materials the Urban Environment ET-OROMIA-BEDELE-3127 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-1 2022-11-1 2023-08-1 2022-12-1 2023-08-1 17-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 8,014.00 0.00 Completed tations e Envelope 8 9 6 1 6 1 of Hand Tools Materials the Urban Environment ET-OROMIA-BEDELE-3127 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-12-1 2022-11-2 2023-04-2 2022-12-2 2023-04-2 27-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 1,682.00 0.00 Completed tations e Envelope 3 9 1 6 1 6 of Block for the constructio the Urban Environment n of public Toilet ET-OROMIA-BEDELE-3127 Expand the Urban Product 2022-09-3 2023-03-2 2022-10-0 2023-03-2 2022-10-2 2023-04-2 2022-11-1 2023-04-2 33-GO-DIR / Procurement IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 720.00 0.00 Completed 0 4 5 4 5 5 4 6 of Cement for the construc the Urban Environment tion of Public Toilet ET-OROMIA-AMBO-312773 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-0 2022-11-1 2023-01-1 2022-12-1 2023-02-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 82,125.00 0.00 Completed tations e Envelope 6 2 4 3 4 5 Safety Materials the Urban Environment ET-OROMIA-AMBO-312777 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-02-0 2022-11-1 2023-02-2 2022-12-1 2023-04-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 17,490.00 0.00 Completed tations e Envelope 7 2 5 0 5 3 Hand Tools Materials the Urban Environment ET-OROMIA-AMBO-312782 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-05-2 2022-11-2 2023-06-1 2022-12-2 2023-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 9,876.00 0.00 Completed tations e Envelope 4 5 2 4 2 6 Industrial construction Mat the Urban Environment erials ET-OROMIA-AMBO-312788 Expand the Urban Product 2022-09-2 2023-05-0 2022-10-0 2023-05-0 2022-10-2 2023-10-2 2022-11-1 2023-11-0 -GO-DIR / Procurement of IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 2,788.00 0.00 Completed 9 4 4 4 4 6 3 2 Cement for the constructio the Urban Environment n of Public Toilet ET-OROMIA-AMBO-312799 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-05-0 2022-11-2 2023-06-0 2022-12-2 2023-12-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 7,298.00 0.00 Completed tations e Envelope 5 4 3 5 3 6 Local Construction Materia the Urban Environment ls ET-OROMIA-AMBO-312803 Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2023-05-0 2022-11-2 2023-10-2 2022-12-2 2024-04-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 4,384.00 0.00 Completed tations e Envelope 0 4 8 6 8 1 Block for the construction the Urban Environment of Public Toile ET-OROMIA-AMBO-312805 Expand the Urban Product -GO-RFQ / Procurement of Request for Quo Single Stage - On 2022-10-1 2023-05-2 2022-11-2 2023-06-1 2022-12-2 2023-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 13,380.00 0.00 Completed Finishing construction Mat tations e Envelope 0 5 8 4 8 7 the Urban Environment erials and Waterline Install ation Materials ET-OROMIA-NEGELE BORA Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-1 2022-11-1 2023-01-0 2022-12-1 2023-01-1 NA-313049-GO-RFQ / Proc IDA / D7320 ive Safety Net to Improve Post Limited 42,985.00 0.00 Completed tations e Envelope 6 6 4 6 4 6 urement of Safety Material the Urban Environment s ET-OROMIA-NEGELE BORA Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-1 2022-11-1 2023-01-0 2022-12-1 2023-01-1 NA-313071-GO-RFQ / Proc IDA / D7320 ive Safety Net to Improve Post Limited 14,011.00 0.00 Completed tations e Envelope 7 6 5 6 5 6 urement of Hand Tools Ma the Urban Environment terials ET-OROMIA-NEGELE BORA Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-05-2 2022-11-2 2023-04-1 2022-12-2 2023-04-2 NA-313212-GO-RFQ / Proc IDA / D7320 ive Safety Net to Improve Post Limited 35,027.00 0.00 Completed tations e Envelope 3 1 1 1 1 6 urement of Industrial Cons the Urban Environment truction Materials ET-OROMIA-NEGELE BORA Expand the Urban Product NA-313219-GO-DIR / Procu 2022-09-2 2023-05-2 2022-10-0 2023-05-2 2022-10-2 2023-06-1 2022-11-1 2023-06-2 IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 1,115.00 0.00 Completed rement of Cement for the 8 5 3 5 7 6 6 1 the Urban Environment construction of Fence and Public Toilet ET-OROMIA-NEGELE BORA Expand the Urban Product NA-313224-GO-RFQ / Proc Request for Quo Single Stage - On 2022-10-0 2023-03-2 2022-11-2 2023-04-1 2022-12-2 2023-05-1 IDA / D7320 ive Safety Net to Improve Post Limited 1,108.00 0.00 Completed urement of Finishing Mater tations e Envelope 4 1 2 1 2 9 the Urban Environment ials and Water line Installa tion Materials ET-OROMIA-NEGELE BORA Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-04-1 2022-11-1 2023-05-0 2022-12-1 2023-06-2 NA-313228-GO-RFQ / Proc IDA / D7320 ive Safety Net to Improve Post Limited 4,678.00 0.00 Completed tations e Envelope 8 8 6 9 6 1 urement of Local Construc the Urban Environment tion Materials ET-OROMIA-NEGELE BORA Expand the Urban Product NA-313240-GO-RFQ / Proc Request for Quo Single Stage - On 2022-10-1 2023-03-2 2022-11-2 2023-04-1 2022-12-2 2023-06-2 IDA / D7320 ive Safety Net to Improve Post Limited 646.00 0.00 Completed urement of Block for the c tations e Envelope 1 8 2 9 2 1 the Urban Environment onstruction of Public Toilet ET-OROMIA-BULE HORA-3 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-12-1 2022-11-2 2023-01-2 2022-12-2 2023-03-1 13718-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 32,669.00 0.00 Completed tations e Envelope 3 4 1 3 1 3 ent of Safety Materials the Urban Environment ET-OROMIA-BULE HORA-3 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-12-1 2022-11-2 2023-01-2 2022-12-2 2023-03-1 13724-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 8,336.00 0.00 Completed tations e Envelope 4 4 3 3 3 3 ent of Hand Tools Material the Urban Environment s ET-OROMIA-BULER HORA- Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-12-1 2022-11-2 2023-01-2 2022-12-2 2023-03-2 313732-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 27,998.00 0.00 Completed tations e Envelope 5 4 3 3 3 0 ment of Industrial Constru the Urban Environment ction Materials ET-OROMIA-BULE HORA-3 Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2023-01-2 2022-12-0 2023-02-2 2023-01-0 2023-04-1 13742-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 13,192.00 0.00 Completed tations e Envelope 7 7 5 4 4 4 ent of Local Construction the Urban Environment Materials ET-OROMIA-DAMBI DOLO- Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-11-0 2022-11-1 2022-11-2 2022-12-1 2023-01-1 314180-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 58,013.00 0.00 Completed tations e Envelope 7 8 5 2 5 8 ment of Safety Materials the Urban Environment ET-OROMIA-DAMBI DOLO- Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-11-0 2022-11-1 2022-11-2 2022-12-1 2022-12-2 314182-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 10,848.00 0.00 Completed tations e Envelope 8 7 6 2 6 8 ment of Hand Tools Materi the Urban Environment als ET-OROMIA-DAMBI DOLO- Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-02-0 2022-11-2 2023-03-2 2022-12-2 2023-05-0 314187-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 6,653.00 0.00 Completed tations e Envelope 3 8 1 7 1 6 ment of Industrial Constru the Urban Environment ction Materials ET-OROMIA-DAMBI DOLO- Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-05-0 2022-11-2 2023-06-0 2022-12-2 2023-07-0 314188-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 1,846.00 0.00 Completed tations e Envelope 4 4 2 5 2 7 ment of Concrete Block for the Urban Environment school maintenance ET-OROMIA-DAMBI DOLO- Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2023-05-0 2022-11-2 2023-05-0 2022-12-2 2023-06-2 314194-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 425.00 0.00 Completed tations e Envelope 0 4 4 4 4 9 ment of Finishing construc the Urban Environment tion Materials ET-OROMIA-DAMBI DOLO- Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2023-02-0 2022-11-3 2023-03-2 2022-12-3 2023-05-0 314196-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 9,038.00 0.00 Completed tations e Envelope 2 8 0 7 0 6 ment of Local Construction the Urban Environment Materials ET-OROMIA-BISHOFTU-31 Expand the Urban Product Single Stage - On 2022-09-2 2022-12-1 2022-09-2 2022-10-2 2023-01-1 2022-11-1 2023-01-2 2022-12-1 2023-03-2 2023-01-2 2023-06-2 4242-GO-RFB / Procureme IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 222,102.00 0.00 Completed e Envelope 3 8 8 8 7 7 3 6 1 5 3 nt of Safety Materials the Urban Environment ET-OROMIA-BISHOFTU-31 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-02-2 2022-11-1 2023-03-2 2022-12-1 2023-04-2 4247-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 47,852.00 0.00 Completed tations e Envelope 8 4 4 0 4 0 nt of Hand Tools Materials the Urban Environment ET-OROMIA-BISHOFTU-31 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-03-1 2022-11-2 2023-04-0 2022-12-2 2023-07-0 4249-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 15,576.00 0.00 Completed tations e Envelope 3 7 2 6 2 4 nt of Industrial Constructio the Urban Environment n Materials Page 7 ET-OROMIA-BISHOFTU-31 Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2021-11-2 2022-11-2 2022-12-0 2022-12-2 2022-12-2 4253-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 3,230.00 0.00 Completed tations e Envelope 0 4 2 5 2 3 nt of Block for the construc the Urban Environment tion of Public Toilet ET-OROMIA-BISHOFTU-31 Expand the Urban Product 2022-10-0 2023-03-1 2022-10-1 2023-03-1 2022-11-0 2023-04-0 2022-11-2 2023-06-2 4255-GO-DIR / Procuremen IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 13,846.00 0.00 Completed 7 6 2 6 3 7 3 6 t of Cement for the constr the Urban Environment uction of public Toilet ET-OROMIA-BISHOFTU-31 Expand the Urban Product 4256-GO-RFQ / Procureme Request for Quo Single Stage - On 2022-10-1 2023-03-1 2022-11-2 2023-04-0 2022-12-2 2023-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 13,295.00 0.00 Completed nt of Finishing Materials an tations e Envelope 0 5 8 5 8 3 the Urban Environment d Waterline installation Ma terials ET-OROMIA-BISHOFTU-31 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-03-1 2022-11-2 2023-03-1 2022-12-2 2023-07-0 4258-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 22,625.00 0.00 Completed tations e Envelope 5 0 3 4 3 7 nt of Local Construction M the Urban Environment aterials ET-OROMIA-HOLOTA-3144 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-11-1 2022-11-1 2022-12-0 2022-12-1 2022-12-0 66-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 62,190.00 0.00 Completed tations e Envelope 7 4 5 2 5 5 of Safety Materials the Urban Environment ET-OROMIA-HOLOTA-3144 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-11-1 2022-11-1 2022-12-0 2022-12-1 2022-12-0 92-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 8,233.00 0.00 Completed tations e Envelope 8 4 6 2 6 5 of Hand Tools Materials the Urban Environment ET-OROMIA-HOLOTA-3144 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-05-3 2022-11-2 2023-06-3 2022-12-2 2023-07-0 96-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 1,447.00 0.00 Completed tations e Envelope 3 0 1 0 1 3 of Industrial construction the Urban Environment materials ET-OROMIA-ROBE-314627 Expand the Urban Product Single Stage - On 2022-09-2 2022-12-0 2022-09-2 2022-10-2 2023-01-0 2022-11-1 2023-01-2 2022-12-1 2023-02-0 2023-01-2 2023-02-1 -GO-RFB / Procurement of IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 103,552.00 0.00 Completed e Envelope 2 4 7 7 4 6 2 5 3 4 7 Safety Materials the Urban Environment ET-OROMIA-ROBE-314637 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-1 2022-11-1 2023-01-2 2022-12-1 2023-03-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 24,846.00 0.00 Completed tations e Envelope 8 4 6 8 6 7 Hand Tools Materials the Urban Environment ET-OROMIA-ROBE-314638 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-05-0 2022-11-2 2023-05-3 2022-12-2 2023-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 9,323.00 0.00 Completed tations e Envelope 3 9 1 0 1 2 Industrial construction Mat the Urban Environment erials ET-OROMIA-ROBE-314646 Expand the Urban Product 2022-09-3 2023-05-3 2022-10-0 2023-05-3 2022-10-2 2023-06-2 2022-11-1 2023-07-0 -GO-DIR / Procurement of IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 2,307.00 0.00 Completed 0 0 5 0 5 2 4 3 Cement for the constructio the Urban Environment n of public Toilet ET-OROMIA-ROBE-314647 Expand the Urban Product -GO-RFQ / Procurement of Request for Quo Single Stage - On 2022-10-1 2023-05-0 2022-11-2 2023-05-3 2022-12-2 2023-06-2 IDA / D7320 ive Safety Net to Improve Post Limited 2,735.00 0.00 Completed Finishing Construction Mat tations e Envelope 0 9 4 0 4 2 the Urban Environment erials and Water line Instal lation Materials ET-OROMIA-ROBE-314695 Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2023-05-3 2022-11-3 2023-06-2 2022-12-3 2023-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 1,692.00 0.00 Completed tations e Envelope 2 0 0 2 0 7 Block for the of public Toil the Urban Environment et ET-OROMIA-ROBE-314696 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-05-3 2022-11-2 2023-06-2 2022-12-2 2023-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 5,786.00 0.00 Completed tations e Envelope 5 0 1 2 1 3 Local construction Material the Urban Environment s ET-OROMIA-MAKI-314718- Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-10-0 2022-11-1 2023-02-0 2022-12-1 2023-02-1 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 68,440.00 0.00 Completed tations e Envelope 8 3 6 6 6 0 Safety Materials the Urban Environment ET-OROMIA-MAKI-314727- Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-01-2 2022-11-2 2023-02-0 2022-12-2 2023-02-0 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 22,044.00 0.00 Completed tations e Envelope 3 3 1 8 1 8 Hand Tools Materials the Urban Environment ET-OROMIA-MAKI-314730- Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-04-2 2022-11-2 2023-05-1 2022-12-2 2023-06-1 GO-RFQ / Procurement of I IDA / D7320 ive Safety Net to Improve Post Limited 4,802.00 0.00 Completed tations e Envelope 3 5 1 5 1 3 ndustrial construction Mat the Urban Environment erials ET-OROMIA-MAKI-314739- Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2023-04-2 2022-11-2 2023-05-1 2022-12-2 2023-06-2 GO-RFQ / Procurement of L IDA / D7320 ive Safety Net to Improve Post Limited 4,687.00 0.00 Completed tations e Envelope 0 5 6 5 6 1 ocal construction Materials the Urban Environment ET-OROMIA-MAKI-314740- Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2023-04-2 2022-12-0 2023-05-1 2023-01-0 2023-06-1 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 382.00 0.00 Completed tations e Envelope 7 5 5 5 4 3 Block for the construction the Urban Environment of public Toilet ET-OROMIA-MAKI-314741- Expand the Urban Product GO-RFQ / Procurement of F Request for Quo Single Stage - On 2022-10-1 2023-04-2 2022-12-0 2023-05-1 2023-01-0 2023-06-1 IDA / D7320 ive Safety Net to Improve Post Limited 4,267.00 0.00 Completed inishing Materials and Wat tations e Envelope 7 5 5 5 4 4 the Urban Environment er line Installation Material s ET-OROMIA-SHAMBU-314 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-12-1 2022-11-1 2023-02-2 2022-12-1 2023-04-2 746-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 18,816.00 0.00 Completed tations e Envelope 8 9 6 0 6 6 t of Safety Materials the Urban Environment ET-OROMIA-SHAMBU-314 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-05-1 2022-11-2 2023-07-1 2022-12-2 2023-07-1 758-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 11,118.00 0.00 Completed tations e Envelope 3 0 1 0 1 1 t of Industrial construction the Urban Environment Materials ET-OROMIA-SHAMBU-314 Expand the Urban Product 763-GO-RFQ / Procuremen Request for Quo Single Stage - On 2022-10-1 2023-05-1 2022-11-2 2023-06-0 2022-12-2 2023-10-1 IDA / D7320 ive Safety Net to Improve Post Limited 1,107.00 0.00 Completed t of Finishing Materials and tations e Envelope 1 0 1 1 1 6 the Urban Environment Water line Installation Mat erials ET-OROMIA-SHAMBU-314 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-05-1 2022-11-2 2023-07-0 2022-12-2 2023-07-0 764-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 4,346.00 0.00 Completed tations e Envelope 3 0 1 5 1 7 t of Local Construction Mat the Urban Environment erials ET-OROMIA-GIMBI-314774 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-01-1 2022-11-1 2023-02-1 2022-12-1 2023-03-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 58,683.00 0.00 Completed tations e Envelope 8 7 6 4 6 9 Safety Materials the Urban Environment ET-OROMIA-GIMBI-314777 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-01-2 2022-11-1 2023-03-0 2022-12-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 7,341.00 0.00 Signed tations e Envelope 3 5 7 1 7 Hand Tools Materials the Urban Environment ET-OROMIA-GIMBI-314778 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-06-2 2022-11-2 2023-07-0 2022-12-2 2023-10-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 10,367.00 0.00 Completed tations e Envelope 3 6 1 7 1 4 Industrial construction Mat the Urban Environment erials ET-OROMIA-GIMBI-314782 -GO-DIR / Procurement of Expand the Urban Product 2022-09-2 2023-06-2 2022-10-0 2023-06-2 2022-10-2 2023-07-0 2022-11-1 2023-08-2 Cement for the constructio IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 2,885.00 0.00 Completed 9 6 4 6 5 7 4 3 n of the maintenance stud the Urban Environment ent class room and the co nstruction of store ET-OROMIA-GIMBI-314783 Expand the Urban Product -GO-RFQ / Procurement of Request for Quo Single Stage - On 2022-10-1 2023-06-2 2022-11-2 2023-07-0 2022-12-2 2023-10-0 IDA / D7320 ive Safety Net to Improve Post Limited 2,602.00 0.00 Completed Finishing Materials and Wa tations e Envelope 0 6 8 7 8 4 the Urban Environment ter line Installation Materia ls ET-OROMIA-GIMBI-314784 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-06-2 2022-11-2 2023-07-0 2022-12-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 4,972.00 0.00 Signed tations e Envelope 3 6 1 7 1 Local construction Material the Urban Environment s ET-OROMIA-YABELO-3147 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2023-01-1 2022-11-1 2023-02-0 2022-12-1 2023-02-2 88-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 28,588.00 0.00 Completed tations e Envelope 8 3 6 1 6 1 of Safety Materials the Urban Environment ET-OROMIA-YABELO-3147 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-03-0 2022-11-2 2023-04-1 2022-12-2 2023-04-2 97-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 12,240.00 0.00 Completed tations e Envelope 3 9 1 0 1 4 of Hand Tools Materials the Urban Environment ET-OROMIA-YABELO-3148 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-04-1 2022-11-2 2023-05-2 2022-12-2 2023-06-0 00-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 4,034.00 0.00 Completed tations e Envelope 4 8 2 6 2 5 of Industrial construction the Urban Environment Materials ET-OROMIA-YABELO-3148 Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2023-04-1 2022-11-1 2023-05-2 2022-12-0 2023-06-0 06-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 787.00 0.00 Completed tations e Envelope 0 8 7 6 7 1 of Finishing construction M the Urban Environment aterials ET-OROMIA-YABELO-3148 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2023-04-1 2022-11-2 2023-05-1 2022-12-2 2023-06-0 07-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 1,434.00 0.00 Completed tations e Envelope 3 8 1 8 1 1 of Local Construction Mate the Urban Environment rials ET-OROMIA-JIMA-314914- Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2023-02-1 2022-11-2 2023-03-0 2022-12-2 2023-07-0 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 2,653.00 0.00 Completed tations e Envelope 0 6 8 9 8 6 Block for the construction the Urban Environment of Public Toilet ET-OROMIA-BADESA-2814 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-05-2 2022-06-1 93-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 4,750.00 0.00 Canceled tations e Envelope 6 3 2 of Seedlings the Urban Environment ET-OROMIA-AGARO-28130 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-05-1 2022-06-1 8-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 564.00 0.00 Canceled tations e Envelope 6 6 0 f Seedlig the Urban Environment ET-OROMIA-YABELO-2812 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-06-0 97-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 490.00 0.00 Canceled tations e Envelope 6 2 1 of Block for the constructio the Urban Environment n of Public Toile ET-OROMIA-BEDELE-2852 Expand the Urban Product 36-GO-RFQ / Procurement Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-05-2 IDA / D7320 ive Safety Net to Improve Post Limited 4,260.00 0.00 Canceled of Local Construction Mate tations e Envelope 9 9 9 the Urban Environment rials for the construction of public Toile ET-OROMIA-BEDELE-2852 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-1 2022-06-0 31-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 2,045.00 0.00 Canceled tations e Envelope 9 3 7 of Block for the constructio the Urban Environment n of Public Toile ET-OROMIA-UDHB-333838 -GO-RFQ / Procurement of Foster Urban Youth Emplo Request for Quo Single Stage - On 2023-01-2 2023-03-2 2023-02-2 2023-06-2 2023-03-1 2023-07-0 IDA / D7320 Post Limited 1,154.00 0.00 Completed Office Table and Chair for yment tations e Envelope 1 1 4 8 6 7 Adama, Jimma and Shasha mane City in apprenticeshi p ET-OROMIA-DAMBI DOLO- Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-06-0 282517-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 2,900.00 0.00 Canceled tations e Envelope 2 2 1 ment of Local Costruction the Urban Environment Materials ET-OROMIA-HARAMAYA-2 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-05-2 81768-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 390.00 0.00 Canceled tations e Envelope 9 5 5 ent of Block for the constr the Urban Environment uction of Public Toilet ET-OROMIA-UDHB-316325 -GO-RFQ / Procurement of Foster Urban Youth Emplo Request for Quo Single Stage - On 2022-09-2 2022-10-2 2023-10-2 IDA / D7320 Post Limited 576.00 0.00 Canceled Office table and chair for Ji yment tations e Envelope 7 8 8 mma, Shashemene, and A dama city in apprenticeshi p ET-OROMIA-UDHB-316324 -GO-RFQ / Procurement of Foster Urban Youth Emplo Request for Quo Single Stage - On 2022-09-2 2022-10-2 2022-11-2 laptop computer, Desktop IDA / D7320 Post Limited 40,000.00 0.00 Canceled yment tations e Envelope 7 8 7 Computer, printer, LCD Pro jector for Jimma, Shashem ene and Jimma for apprent iceship ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-06-0 2023-05-1 2023-06-3 2023-06-0 2023-07-0 -351322-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 39,282.00 0.00 Completed tations e Envelope 4 6 9 0 8 5 ment of Different Seedling the Urban Environment ET-OROMIA-YABELO-3513 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-04-1 2023-05-1 2023-05-2 2023-06-0 2023-07-0 52-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 3,520.00 0.00 Completed tations e Envelope 4 8 9 6 8 1 of Different Seedling the Urban Environment ET-OROMIA-ADAMA-35135 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-04-1 2023-05-1 2023-05-0 2023-06-1 2023-05-1 7-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 29,600.00 0.00 Completed tations e Envelope 4 3 9 2 3 9 f seedlings the Urban Environment ET-OROMIA-JIMMA-351373 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-03-2 2023-05-1 2023-04-1 2023-06-1 2023-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 34,900.00 0.00 Completed tations e Envelope 4 7 9 4 3 2 different seedlings the Urban Environment ET-OROMIA-CHIRO-35145 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-02-2 2023-05-1 2023-03-2 2023-06-1 2023-07-0 3-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 3,100.00 0.00 Completed tations e Envelope 4 7 9 1 3 4 f different seeds and seedl the Urban Environment ings ET-OROMIA-DERA-351465 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-07-0 2023-05-1 2023-07-0 2023-06-1 2023-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 4,400.00 0.00 Completed tations e Envelope 4 7 9 4 3 7 different seedlings the Urban Environment ET-OROMIA-FICHE-351471 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-06-2 2023-05-1 2023-07-0 2023-06-1 2023-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 1,200.00 0.00 Completed tations e Envelope 4 2 9 3 3 7 different seedlings the Urban Environment ET-OROMIA-NEGELE ARSI- Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-07-1 2023-05-1 2023-08-0 2023-06-0 2023-08-0 351482-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 3,000.00 0.00 Completed tations e Envelope 4 0 9 1 8 3 ment of different seedlings the Urban Environment ET-OROMIA-SEBATA-3514 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-06-0 2023-05-1 2023-07-0 2023-06-1 2023-07-0 86-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 7,000.00 0.00 Completed tations e Envelope 4 9 9 4 3 7 of different seedlings the Urban Environment ET-OROMIA-WOLISO-3514 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-05-2 2023-05-1 2023-06-1 2023-06-0 2023-07-0 88-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 18,700.00 0.00 Completed tations e Envelope 4 6 9 6 8 7 of different seedlings the Urban Environment Page 8 ET-OROMIA-MATU-351496 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-04-2 2023-05-1 2023-05-1 2023-06-0 2023-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 2,350.00 0.00 Completed tations e Envelope 4 6 9 9 8 7 Different Seedlings the Urban Environment ET-OROMIA-SHAMBU-351 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-05-0 2023-05-1 2023-07-0 2023-06-0 2023-07-0 498-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 1,090.00 0.00 Completed tations e Envelope 4 8 9 4 8 6 t of Different Seedling and the Urban Environment Seeds ET-OROMIA-MAKI-351499- Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-06-0 2023-05-1 2023-06-1 2023-06-0 2023-06-1 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 7,080.00 0.00 Completed tations e Envelope 4 1 9 4 8 5 Different Seedlings the Urban Environment ET-OROMIA-ROBE-351500 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-05-3 2023-05-1 2023-06-2 2023-06-0 2023-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 7,950.00 0.00 Completed tations e Envelope 4 0 9 2 8 7 Different Seedlings the Urban Environment ET-OROMIA-AMBO-351782 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-06-0 2023-05-1 2023-06-2 2023-06-0 2023-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 16,500.00 0.00 Completed tations e Envelope 4 2 9 1 8 3 Different Seedling the Urban Environment ET-OROMIA-NEKEMTE-351 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-05-1 2023-05-1 2023-06-2 2023-06-0 2023-07-0 795-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 13,200.00 0.00 Completed tations e Envelope 4 6 9 9 8 4 t of Different Seedlings the Urban Environment ET-OROMIA-HOLOTA-3517 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-06-0 2023-05-1 2023-06-2 2023-06-0 2023-06-2 97-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 3,300.00 0.00 Completed tations e Envelope 4 4 9 2 8 3 of Different Seedlings the Urban Environment ET-OROMIA-BURAYU-3518 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-05-1 2023-05-1 2023-06-0 2023-06-0 2023-07-0 01-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 3,000.00 0.00 Completed tations e Envelope 4 9 9 7 8 7 of Different Seedling the Urban Environment ET-OROMIA-BISHOFTU-35 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-03-2 2023-05-1 2023-05-1 2023-06-0 2023-07-0 1802-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 15,850.00 0.00 Completed tations e Envelope 4 3 9 3 8 6 nt of Different Seedlings the Urban Environment ET-OROMIA-BULE HORA-3 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-04-1 2023-05-1 2023-05-1 2023-06-0 2023-06-1 51810-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 15,000.00 0.00 Completed tations e Envelope 4 4 9 5 8 3 ent of Different Seedlings the Urban Environment ET-OROMIA-ASALA-35181 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-06-0 2023-05-1 2023-06-1 2023-06-0 2023-07-0 2-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 4,650.00 0.00 Completed tations e Envelope 4 1 9 9 8 7 f Different Seedlings the Urban Environment ET-OROMIA-NEGELE BORA Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-04-2 2023-05-1 2023-05-1 2023-06-0 2023-06-2 NA-351813-GO-RFQ / Proc IDA / D7320 ive Safety Net to Improve Post Limited 4,800.00 0.00 Completed tations e Envelope 4 0 9 1 8 6 urement of Different Seedl the Urban Environment ings ET-OROMIA-GINCHI-35181 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-05-3 2023-05-1 2023-06-1 2023-06-0 2023-07-0 4-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 1,200.00 0.00 Completed tations e Envelope 4 0 9 5 8 3 f Different Seedlings the Urban Environment ET-OROMIA-BATU-351818 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-05-0 2023-05-1 2023-06-0 2023-06-0 2023-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 2,000.00 0.00 Completed tations e Envelope 4 8 9 2 8 7 Different Seedlings the Urban Environment ET-OROMIA-UDHB-352046 -GO-RFQ / Procurement of Desk Top and Laptop Com Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-05-0 2023-05-1 2023-06-1 2023-06-2 2023-06-2 puter, Color Printer, Printer IDA / D7320 ive Safety Net to Improve Post Limited 69,300.00 0.00 Completed tations e Envelope 4 2 9 5 3 9 ,LCD Projector,Computer B the Urban Environment ag,Pointer and Mouse mai nly to be distributed for cit y level office of labor & soc ial affair AND Safety Net of ET-OROMIA-UDHB-357616 fice -GO-RFQ / Procurement of Expand the Urban Product Desktop computer, slide pr Request for Quo Single Stage - On 2023-06-0 2023-06-0 2023-07-0 2023-06-2 2023-07-2 2023-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 99,900.00 0.00 Completed ojector, Laser Printer and L tations e Envelope 3 2 7 3 7 7 the Urban Environment aptop Computer for Adam a, Jimma and shashamane apprenticeship ET-OROMIA-UDHB-333851 -GO-RFB / Procurement of Foster Urban Youth Emplo Single Stage - On 2023-01-1 2023-01-2 2023-02-2 2023-03-0 2023-04-0 2023-05-0 LCD Projector, Laptop Com IDA / D7320 Post Request for Bids Open - National 165,865.00 0.00 Canceled yment e Envelope 8 3 2 9 3 3 puter, Desktop Computer and Printer for Adama, Jim ma and Shashamane for a pprenticeship ET-OROMIA-MAKI-314732- Expand the Urban Product 2022-09-3 2022-10-0 2022-10-2 2022-11-1 GO-DIR / Procurement of C IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 2,019.00 0.00 Canceled 0 5 5 4 ement for the construction the Urban Environment of Public Toilet ET-OROMIA-AGARO-30988 Expand the Urban Product 2022-10-0 2022-10-1 2022-11-0 2022-11-2 7-GO-DIR / Procurement of IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 1,586.00 0.00 Canceled 5 0 3 3 Cement for the constructio the Urban Environment n of Public Toile ET-OROMIA-YABELO-3148 05-GO-DIR / Procurement Expand the Urban Product 2022-09-3 2022-10-0 2022-10-2 2022-11-1 of Cement for the construc IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 692.00 0.00 Canceled 0 5 5 4 tion of Fence for Greenery the Urban Environment and the maintenance of st udent class room ET-OROMIA-BULE HORA-3 Expand the Urban Product 2022-10-0 2022-10-1 2022-11-0 2022-11-2 13741-GO-DIR / Procureme IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 769.00 0.00 Canceled 7 2 1 1 nt of Cement for the Const the Urban Environment ruction of Public Toilet ET-OROMIA-SHAMBU-314 Expand the Urban Product 761-GO-DIR / Procurement 2022-09-3 2022-10-0 2022-10-2 2022-11-1 IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 1,826.00 0.00 Canceled of Cement for the construc 0 5 5 4 the Urban Environment tion of public Toilet and Fe nce for greenery ET-OROMIA-SHAMBU-314 Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2022-11-2 2022-12-2 762-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 480.00 0.00 Canceled tations e Envelope 0 2 2 t of Block for the construct the Urban Environment ion of Public Toilet ET-OROMIA-HOLOTA-3145 Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2022-11-2 2022-12-2 06-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 1,154.00 0.00 Canceled tations e Envelope 1 9 9 of Water line Installation M the Urban Environment aterials ET-OROMIA-HOLOTA-2851 Expand the Urban Product Request for Quo Single Stage - On 2022-03-3 2022-05-1 2022-06-1 91-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 170.00 0.00 Canceled tations e Envelope 0 4 3 of Block for the Public Toil the Urban Environment et ET-OROMIA-HOLOTA-3145 Expand the Urban Product 2022-09-3 2022-10-0 2022-10-2 2022-11-1 05-GO-DIR / Procurement IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 865.00 0.00 Canceled 0 5 7 6 of Cement for the construc the Urban Environment tion of public Toilet ET-OROMIA-FICHE-310438 Expand the Urban Product Request for Quo Single Stage - On 2022-10-1 2022-11-2 2022-12-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 673.00 0.00 Canceled tations e Envelope 0 8 8 Block for the construction the Urban Environment of Public Toilet ET-OROMIA-AGARO-35144 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-05-1 2023-06-1 6-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 1,400.00 0.00 Canceled tations e Envelope 4 9 3 f different Seedlings the Urban Environment ET-OROMIA-ROBE-285430 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-05-1 2022-06-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 518.00 0.00 Canceled tations e Envelope 2 3 7 Block for the construction the Urban Environment of public Toilet ET-OROMIA-SHAMBU-314 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-11-2 2022-12-2 756-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 948.00 0.00 Canceled tations e Envelope 3 1 1 t of Hand Tools Materials the Urban Environment ET-OROMIA-ADAMA-30968 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-11-2 2022-12-2 7-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 15,515.00 0.00 Canceled tations e Envelope 4 2 2 f Finishing Construction Ma the Urban Environment terials ET-OROMIA-GIMBI-351363 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-05-1 2023-06-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 2,390.00 0.00 Canceled tations e Envelope 4 9 8 Different Seedling the Urban Environment ET-OROMIA-GIMBI-282121 Expand the Urban Product Request for Quo Single Stage - On 2022-04-0 2022-06-0 2022-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 3,960.00 0.00 Canceled tations e Envelope 6 1 1 Different Seedling for gree the Urban Environment nery activities ET-OROMIA-GIMBI-282131 Expand the Urban Product Request for Quo Single Stage - On 2022-03-2 2022-04-2 2022-05-3 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 588.00 0.00 Canceled tations e Envelope 3 9 0 Block for the Construction the Urban Environment of Public Toilet ET-OROMIA-DAMBI DOLO- Expand the Urban Product 2022-09-2 2022-10-0 2022-10-2 2022-11-1 314191-GO-DIR / Procure IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 3,846.00 0.00 Canceled 9 4 4 8 ment of Cement for school the Urban Environment maintenance ET-OROMIA-DAMBI DOLO- Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-05-1 2023-06-0 351808-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 2,000.00 0.00 Canceled tations e Envelope 4 9 8 ment of Different Seedling the Urban Environment ET-OROMIA-HOLOTA-3145 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-11-2 2022-12-2 07-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 977.00 0.00 Canceled tations e Envelope 5 3 3 of Local Construction Mate the Urban Environment rials ET-OROMIA-BEDELE-3127 Expand the Urban Product Request for Quo Single Stage - On 2022-09-2 2022-11-1 2022-12-1 20-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 2,556.00 0.00 Canceled tations e Envelope 8 6 6 of Industrial construction the Urban Environment Materials ET-OROMIA-BEDELE-3127 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-11-2 2022-12-2 35-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 1,096.00 0.00 Canceled tations e Envelope 3 1 1 of Local Construction Mate the Urban Environment rials ET-OROMIA-HARAMAYA-3 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-11-2 2022-12-2 10451-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 22,972.00 0.00 Canceled tations e Envelope 3 1 1 ent of Industrial constructi the Urban Environment on Materials ET-OROMIA-HARAMAYA-3 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-05-1 2023-06-0 51477-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 5,600.00 0.00 Canceled tations e Envelope 4 9 8 ent of different seedlings the Urban Environment ET-OROMIA-HARAMAYA-3 Expand the Urban Product 10456-GO-RFQ / Procurem Request for Quo Single Stage - On 2022-10-1 2022-11-2 2022-12-2 IDA / D7320 ive Safety Net to Improve Post Limited 3,825.00 0.00 Canceled ent of Finishing constructio tations e Envelope 0 8 8 the Urban Environment n Materials in Lot-1 Waterli ne installation Materials in Lot-2 ET-OROMIA-HARAMAYA-3 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-11-2 2022-12-2 10471-GO-RFQ / procurem IDA / D7320 ive Safety Net to Improve Post Limited 1,019.00 0.00 Canceled tations e Envelope 5 3 3 ent of Block for the constr the Urban Environment uction of Public Toilet ET-OROMIA-HARAMAYA-3 Expand the Urban Product Request for Quo Single Stage - On 2022-10-0 2022-11-2 2022-12-2 10477-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 14,995.00 0.00 Canceled tations e Envelope 4 2 2 ent of Local Construction the Urban Environment Materials ET-OROMIA-HARAMAYA-3 Expand the Urban Product 2022-09-2 2022-10-0 2022-10-2 2022-11-1 10468-GO-DIR / Procureme IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 2,307.00 0.00 Canceled 9 4 8 7 nt of Cement for the const the Urban Environment ruction of Public Toilet ET-OROMIA-GIMBI-282129 Expand the Urban Product -GO-RFQ / Procurement of Request for Quo Single Stage - On 2022-04-0 2022-05-1 2022-06-0 IDA / D7320 ive Safety Net to Improve Post Limited 240.00 0.00 Canceled Finishing Materials in Lot-1 tations e Envelope 6 3 2 the Urban Environment and Waterline Installation Materials in Lot-2 ET-OROMIA-BADALE-3517 Expand the Urban Product Request for Quo Single Stage - On 2023-04-0 2023-05-1 2023-06-0 92-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 2,020.00 0.00 Canceled tations e Envelope 4 9 8 of Different Seedlings the Urban Environment ET-OROMIA-DERA-314962 Expand the Urban Product 2022-09-3 2022-10-0 2022-11-0 2022-11-2 -GO-DIR / Procurement of c IDA / D7320 ive Safety Net to Improve Post Direct Selection Direct - National 288.00 0.00 Canceled 0 5 2 2 ement for the construction the Urban Environment of public Toilet ET-OROMIA-DERA-281752 Expand the Urban Product -GO-RFQ / Procurement of Request for Quo Single Stage - On 2022-03-2 2022-05-0 2022-05-2 IDA / D7320 ive Safety Net to Improve Post Limited 625.00 0.00 Canceled Waterline installation Mate tations e Envelope 6 2 7 the Urban Environment rials in Lot -1 and Finishing Materials in Lot-2 ET-OROMIA-AMBO-391421 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-05-2 2024-01-0 2024-06-1 2024-02-0 2024-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 91,454.00 0.00 Completed tations e Envelope 2 2 8 3 7 4 Protective Safety Materials the Urban Environment ET-OROMIA-AMBO-391427 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-05-2 2024-01-1 2024-06-1 2024-02-1 2024-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 19,695.00 0.00 Completed tations e Envelope 2 2 5 3 4 4 Hand Tools the Urban Environment ET-OROMIA-AMBO-391490 Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-04-1 2024-02-1 2024-05-1 2024-03-1 2024-05-3 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 19,166.00 0.00 Completed tations e Envelope 5 1 6 7 8 0 Industrial Construction Mat the Urban Environment erials ET-OROMIA-AMBO-391498 Expand the Urban Product -GO-RFQ / Procurement of Request for Quo Single Stage - On 2024-01-1 2024-04-2 2024-02-2 2024-05-2 2024-03-2 2024-06-2 IDA / D7320 ive Safety Net to Improve Post Limited 8,288.00 0.00 Completed Local Construction Materia tations e Envelope 0 2 8 7 9 1 the Urban Environment ls ( Sand, Stone and Wood s) ET-OROMIA-AMBO-391508 Expand the Urban Product Request for Quo Single Stage - On 2024-04-0 2024-05-3 2024-05-1 2024-06-2 2024-07-1 2024-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 35,511.00 0.00 Completed tations e Envelope 9 0 7 0 6 2 Different Seedlings the Urban Environment ET-OROMIA-JIMA-391588- Expand the Urban Product Single Stage - On 2023-12-0 2024-01-1 2023-12-1 2024-06-1 2024-01-1 2024-02-1 2024-01-2 2024-02-1 2024-02-2 2024-03-1 2024-03-2 2024-05-3 GO-RFB / Procurement of P IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 233,570.00 0.00 Completed e Envelope 6 9 1 1 0 9 4 9 1 1 2 0 rotective safety Materials the Urban Environment Page 9 ET-OROMIA-JIMA-391589- Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-01-1 2024-01-0 2024-01-3 2024-02-0 2024-04-1 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 42,213.00 0.00 Completed tations e Envelope 2 5 9 0 8 2 Hand Tools for Public Wor the Urban Environment ks activities ET-OROMIA-JIMA-391590- Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-01-1 2024-01-2 2024-01-3 2024-02-2 2024-04-0 GO-RFQ / Procurement of I IDA / D7320 ive Safety Net to Improve Post Limited 46,914.00 0.00 Completed tations e Envelope 2 5 3 0 2 1 ndustrial Construction Mat the Urban Environment erials ET-OROMIA-JIMA-391592- Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-01-1 2024-02-1 2024-01-3 2024-03-1 2024-06-1 GO-RFQ / Procurement of L IDA / D7320 ive Safety Net to Improve Post Limited 26,417.00 0.00 Completed tations e Envelope 5 5 2 0 3 2 ocal Construction Material the Urban Environment s ET-OROMIA-JIMA-391594- Expand the Urban Product Request for Quo Single Stage - On 2024-04-1 2024-03-1 2024-05-2 2024-03-2 2024-06-1 2024-05-1 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 98,400.00 0.00 Completed tations e Envelope 5 1 0 9 9 4 Different seedlings the Urban Environment ET-OROMIA-SHAMBU-391 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-02-1 2024-01-2 2024-03-1 2024-02-2 2024-05-1 595-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 19,236.00 0.00 Completed tations e Envelope 9 9 3 3 2 3 t of Protective Safety Mate the Urban Environment rials ET-OROMIA-SHAMBU-391 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-01-2 2024-01-1 2024-03-1 2024-02-1 2024-04-1 596-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 11,157.00 0.00 Completed tations e Envelope 2 3 5 2 4 2 t of Industrial Construction the Urban Environment Materials ET-OROMIA-SHAMBU-391 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-01-2 2024-01-1 2024-03-0 2024-02-1 2024-03-2 597-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 1,509.00 0.00 Completed tations e Envelope 2 3 6 5 5 6 t of Local Construction Mat the Urban Environment erials ET-OROMIA-SHAMBU-391 Expand the Urban Product Request for Quo Single Stage - On 2024-04-0 2024-04-0 2024-05-1 2024-06-2 2024-06-1 2024-07-0 600-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 1,633.00 0.00 Completed tations e Envelope 8 5 3 6 2 8 t of Different seedlings the Urban Environment ET-OROMIA-BATU-391605 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-01-1 2024-01-2 2024-02-1 2024-02-2 2024-04-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 51,141.00 0.00 Completed tations e Envelope 1 7 9 6 8 7 Protective Safety Materials the Urban Environment ET-OROMIA-BATU-391606 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-01-1 2024-01-1 2024-02-1 2024-02-1 2024-04-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 7,308.00 0.00 Completed tations e Envelope 2 7 6 6 5 2 Hand Tools the Urban Environment ET-OROMIA-BATU-391607 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-01-1 2024-01-1 2024-02-1 2024-02-1 2024-06-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 73,446.00 0.00 Completed tations e Envelope 2 7 6 6 5 3 Industrial Construction Mat the Urban Environment erials ET-OROMIA-BATU-391608 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-01-1 2024-01-1 2024-02-1 2024-02-1 2024-05-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 18,016.00 0.00 Completed tations e Envelope 2 7 6 6 5 4 Local Construction Materia the Urban Environment ls ET-OROMIA-BATU-391610 Expand the Urban Product Request for Quo Single Stage - On 2024-04-0 2024-05-2 2024-05-1 2024-06-2 2024-06-1 2024-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 5,142.00 0.00 Completed tations e Envelope 8 7 3 1 2 5 Different Seedlings the Urban Environment ET-OROMIA-YABELO-3916 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-02-0 2024-01-1 2024-02-2 2024-02-1 2024-03-1 14-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 3,402.00 0.00 Completed tations e Envelope 2 2 6 3 5 9 of Protective safety Materi the Urban Environment als ET-OROMIA-YABELO-3916 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-02-0 2024-01-1 2024-02-2 2024-02-0 2024-03-1 16-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 5,114.00 0.00 Completed tations e Envelope 3 2 0 3 9 9 of Hand Tools the Urban Environment ET-OROMIA-YABELO-3916 Expand the Urban Product Request for Quo Single Stage - On 2024-01-2 2024-02-2 2024-02-1 2024-03-1 2024-02-2 2024-04-2 20-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 16,682.00 0.00 Completed tations e Envelope 2 3 9 5 2 6 of Industrial Construction the Urban Environment Materials ET-OROMIA-YABELO-3916 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-02-2 2024-01-1 2024-03-1 2024-02-1 2024-04-2 24-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 2,478.00 0.00 Completed tations e Envelope 2 3 6 5 5 4 of Local Construction Mate the Urban Environment rials ET-OROMIA-DAMBIDOLO-3 Expand the Urban Product Request for Quo Single Stage - On Under Impl 2024-01-0 2024-02-1 2024-03-1 91633-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 33,094.00 0.00 tations e Envelope ementation 9 3 4 ent of Protective Safety Ma the Urban Environment terials ET-OROMIA-DAMBIDOLO-3 Expand the Urban Product Request for Quo Single Stage - On Under Impl 2023-12-1 2024-01-1 2024-02-1 91636-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 7,242.00 0.00 tations e Envelope ementation 1 5 4 ent of Hand Tools the Urban Environment ET-OROMIA-DAMBIDOLO-3 Expand the Urban Product 91638-GO-RFQ / Procurem Request for Quo Single Stage - On Under Impl 2024-01-0 2024-02-1 2024-03-1 IDA / D7320 ive Safety Net to Improve Post Limited 29,869.00 0.00 ent of Industrial and Finish tations e Envelope ementation 9 3 4 the Urban Environment ing Construction Materials ET-OROMIA-DAMBIDOLO-3 Expand the Urban Product Request for Quo Single Stage - On Under Impl 2024-01-0 2024-02-1 2024-03-1 91639-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 6,487.00 0.00 tations e Envelope ementation 8 2 3 ent of Local Construction the Urban Environment Materials ET-OROMIA-DAMBIDOLO-3 Expand the Urban Product Request for Quo Single Stage - On Under Impl 2024-04-0 2024-05-1 2024-06-1 91641-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 2,265.00 0.00 tations e Envelope ementation 8 3 2 ent of Different Seedlings the Urban Environment ET-OROMIA-NEKEMTE-391 Expand the Urban Product Single Stage - On 2024-01-0 2024-01-0 2024-01-1 2024-01-1 2024-02-0 2024-01-3 2024-02-2 2024-02-1 2024-03-2 2024-04-0 2024-04-2 2024-05-2 696-GO-RFB / Procurement IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 161,013.00 0.00 Completed e Envelope 5 2 0 0 9 1 3 6 2 3 2 0 of Protective Safety Materi the Urban Environment als ET-OROMIA-NEKEMTE-391 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2023-12-2 2024-01-1 2024-02-1 2024-02-1 2024-03-0 721-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 54,636.00 0.00 Completed tations e Envelope 2 9 6 4 5 8 t of Hand Tools the Urban Environment ET-OROMIA-NEKEMTE-391 Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-02-1 2024-02-1 2024-04-1 2024-03-2 2024-05-2 731-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 34,380.00 0.00 Completed tations e Envelope 5 3 9 7 0 4 t of Industrial and Finishin the Urban Environment g Construction Materials ET-OROMIA-NEKEMTE-391 Expand the Urban Product Request for Quo Single Stage - On 2024-01-2 2024-02-1 2024-02-2 2024-04-1 2024-03-2 2024-05-2 740-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 6,933.00 0.00 Completed tations e Envelope 3 3 7 7 8 7 t of Local Construction Mat the Urban Environment erials ET-OROMIA-NEKEMTE-391 Expand the Urban Product Request for Quo Single Stage - On 2024-04-0 2024-03-2 2024-05-1 2024-04-2 2024-06-1 2024-05-2 745-GO-RFQ / Procuremen IDA / D7320 ive Safety Net to Improve Post Limited 20,156.00 0.00 Completed tations e Envelope 8 7 3 2 2 4 t of Different Seedlings the Urban Environment ET-OROMIA-BEDELE-3917 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-04-0 2024-01-2 2024-05-2 2024-02-2 2024-06-1 48-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 18,412.00 0.00 Completed tations e Envelope 1 4 2 4 1 8 of Safety Materials the Urban Environment ET-OROMIA-GIMBI-391762 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-06-0 2024-02-0 2024-07-0 2024-03-0 2024-07-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 6,998.00 0.00 Completed tations e Envelope 9 3 6 2 7 4 Hand Tools the Urban Environment ET-OROMIA-GIMBI-391763 Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-06-1 2024-03-0 2024-07-0 2024-04-0 2024-07-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 68,825.00 0.00 Completed tations e Envelope 5 1 4 2 3 5 Industrial and Finishing Co the Urban Environment nstruction Materials ET-OROMIA-GIMBI-391827 Expand the Urban Product Request for Quo Single Stage - On Under Impl 2024-01-2 2024-02-2 2024-03-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 4,612.00 0.00 tations e Envelope ementation 2 6 7 Local Construction Materia the Urban Environment ls ET-OROMIA-BEDELE-3918 Expand the Urban Product Request for Quo Single Stage - On 2023-12-2 2024-05-1 2024-02-0 2024-05-3 2024-03-0 2024-06-1 31-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 9,399.00 0.00 Completed tations e Envelope 2 4 2 1 3 7 of Industrial Construction the Urban Environment Materials ET-OROMIA-BEDELE-3918 Expand the Urban Product Request for Quo Single Stage - On Under Impl 2023-12-2 2024-04-0 2024-02-0 2024-03-0 38-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 5,487.00 0.00 tations e Envelope ementation 5 4 5 6 of Local Construction Mate the Urban Environment rials ET-OROMIA-WALISO-3918 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-02-2 2024-02-0 2024-04-1 2024-03-0 2024-06-0 57-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 39,808.00 0.00 Completed tations e Envelope 9 9 6 1 7 7 of Safety Materials the Urban Environment ET-OROMIA-BULEHORA-39 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-01-1 2024-01-2 2024-02-0 2024-02-2 2024-05-2 1859-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 3,589.00 0.00 Completed tations e Envelope 2 0 3 5 2 2 nt of Safety Material the Urban Environment ET-OROMIA-WALISO-3918 Expand the Urban Product Request for Quo Single Stage - On 2023-12-2 2024-03-0 2024-02-1 2024-04-1 2024-03-2 2024-05-2 63-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 6,735.00 0.00 Completed tations e Envelope 5 1 4 1 0 1 of Hand tools Materials the Urban Environment ET-OROMIA-BULEHORA-39 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-01-1 2024-01-2 2024-02-0 2024-02-2 2024-05-2 1864-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 5,869.00 0.00 Completed tations e Envelope 1 0 9 5 8 2 nt of Hand Tools the Urban Environment ET-OROMIA-BULEHORA-39 Expand the Urban Product 1865-GO-RFQ / Procureme Request for Quo Single Stage - On 2023-12-1 2024-01-1 2024-01-1 2024-02-0 2024-02-1 2024-06-0 IDA / D7320 ive Safety Net to Improve Post Limited 59,726.00 0.00 Completed nt of Industrial and Finishi tations e Envelope 2 0 6 5 5 5 the Urban Environment ng Construction Materials Materials ET-OROMIA-WALISO-3918 Expand the Urban Product 70-GO-RFQ / Procurement Request for Quo Single Stage - On 2024-01-1 2024-03-2 2024-03-0 2024-04-1 2024-04-0 2024-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 49,839.00 0.00 Completed of Industrials Construction, tations e Envelope 5 0 4 1 3 4 the Urban Environment Finishing and Waterline Ins tallation Materials ET-OROMIA-BULEHORA-39 Expand the Urban Product Request for Quo Single Stage - On Under Impl 2024-01-1 2024-02-1 2024-03-2 1874-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 13,875.00 0.00 tations e Envelope ementation 5 9 0 nt of Local Construction M the Urban Environment aterials ET-OROMIA-BULEHORA-39 Expand the Urban Product Request for Quo Single Stage - On Under Impl 2024-01-2 2024-02-2 2024-03-2 1878-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 5,293.00 0.00 tations e Envelope ementation 3 7 8 nt of Different Seedling the Urban Environment ET-OROMIA-WALISO-3918 Expand the Urban Product Request for Quo Single Stage - On 2023-12-2 2024-03-2 2024-02-1 2024-05-0 2024-05-1 2024-07-0 81-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 16,794.00 0.00 Completed tations e Envelope 9 1 6 1 6 2 of Local Construction Mate the Urban Environment rials ET-OROMIA-WALISO-3918 Expand the Urban Product Request for Quo Single Stage - On 2024-04-1 2024-05-2 2024-05-2 2024-06-2 2024-06-2 2024-07-0 87-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 6,657.00 0.00 Completed tations e Envelope 5 7 7 0 6 5 of Different Seedling the Urban Environment ET-OROMIA-MATU-391901 Expand the Urban Product Request for Quo Single Stage - On 2023-12-2 2024-01-1 2024-02-0 2024-02-0 2024-03-0 2024-04-3 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 39,607.00 0.00 Completed tations e Envelope 6 7 6 7 8 0 Safety Materials the Urban Environment ET-OROMIA-MATU-391925 Expand the Urban Product Request for Quo Single Stage - On 2023-12-2 2024-01-1 2024-02-0 2024-02-0 2024-03-0 2024-03-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 1,283.00 0.00 Completed tations e Envelope 5 7 5 7 6 1 Hand Tools Materials the Urban Environment ET-OROMIA-MATU-391927 -GO-RFQ / Procurement of Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-01-1 2024-02-1 2024-02-0 2024-04-1 2024-05-2 Industrial Construction, Fin IDA / D7320 ive Safety Net to Improve Post Limited 31,124.00 0.00 Completed tations e Envelope 2 7 5 7 5 3 ishing for Shade constructi the Urban Environment on and Waterline Installati on Materials ET-OROMIA-MATU-392001 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-01-1 2024-01-2 2024-02-0 2024-02-2 2024-03-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 7,659.00 0.00 Completed tations e Envelope 8 7 9 7 8 5 Local Construction Materia the Urban Environment ls ET-OROMIA-MATU-392004 Expand the Urban Product Request for Quo Single Stage - On 2024-04-2 2024-05-2 2024-05-2 2024-06-2 2024-06-2 2024-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 2,486.00 0.00 Completed tations e Envelope 3 8 9 4 8 5 Different Seedling the Urban Environment ET-OROMIA-AGARO-39200 Expand the Urban Product Request for Quo Single Stage - On Under Impl 2023-12-2 2024-02-2 2024-02-1 2024-03-1 6-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 23,215.00 0.00 tations e Envelope ementation 5 3 2 3 f Safety Materials the Urban Environment ET-OROMIA-AGARO-39200 Expand the Urban Product Request for Quo Single Stage - On 2023-12-2 2024-01-0 2024-02-0 2024-02-2 2024-03-0 2024-03-2 8-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 7,428.00 0.00 Completed tations e Envelope 6 9 6 8 7 5 f Hand tools Materials the Urban Environment ET-OROMIA-ROBE-392050 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-02-0 2024-01-3 2024-03-0 2024-02-2 2024-05-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 83,418.00 0.00 Completed tations e Envelope 2 9 0 8 9 0 Protective safety Materials the Urban Environment ET-OROMIA-ROBE-392051 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-02-0 2024-01-3 2024-03-0 2024-02-2 2024-04-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 35,932.00 0.00 Completed tations e Envelope 2 9 0 8 9 9 Hand Tools the Urban Environment ET-OROMIA-AGARO-39205 Expand the Urban Product Request for Quo Single Stage - On Under Impl 2024-01-0 2024-01-2 2024-02-1 2024-03-1 4-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 15,780.00 0.00 tations e Envelope ementation 2 4 3 4 f Industrial and Finishing C the Urban Environment onstruction Materials ET-OROMIA-ROBE-392056 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-05-2 2024-01-3 2024-06-1 2024-02-2 2024-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 37,350.00 0.00 Completed tations e Envelope 2 7 0 2 9 2 Industrial and Finishing Co the Urban Environment nstruction Materials ET-OROMIA-AGARO-39205 Expand the Urban Product Request for Quo Single Stage - On Under Impl 2024-01-0 2024-01-0 2024-02-1 2024-03-1 8-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 15,403.00 0.00 tations e Envelope ementation 1 8 2 3 f Local Construction Materi the Urban Environment als ET-OROMIA-ROBE-392061 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-02-2 2024-01-2 2024-03-2 2024-02-2 2024-06-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 8,489.00 0.00 Completed tations e Envelope 1 9 9 2 8 6 Local Construction Materia the Urban Environment ls ET-OROMIA-NAGELE BORA Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-01-0 2024-01-3 2024-01-2 2024-02-2 2024-02-0 NA-392071-GO-RFQ / Proc IDA / D7320 ive Safety Net to Improve Post Limited 39,056.00 0.00 Completed tations e Envelope 2 2 0 6 9 6 urement of Protective Safe the Urban Environment ty Materials ET-OROMIA-NAGELE BORA Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-01-0 2024-02-1 2024-01-2 2024-03-2 2024-02-0 NA-392074-GO-RFQ / Proc IDA / D7320 ive Safety Net to Improve Post Limited 2,586.00 0.00 Completed tations e Envelope 5 2 9 6 0 6 urement of Hand Tools the Urban Environment Page 10 ET-OROMIA-NAGEL BORA Expand the Urban Product NA-392077-GO-RFQ / Proc Request for Quo Single Stage - On 2024-01-1 2024-01-0 2024-03-0 2024-01-2 2024-04-0 2024-02-2 IDA / D7320 ive Safety Net to Improve Post Limited 34,378.00 0.00 Completed urement of Industrial and tations e Envelope 5 2 4 5 3 8 the Urban Environment Finishing Construction Mat erials ET-OROMIA-FICHE-392083 Expand the Urban Product Request for Quo Single Stage - On 2023-12-2 2024-01-0 2024-02-0 2024-02-1 2024-03-0 2024-03-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 36,742.00 0.00 Completed tations e Envelope 6 2 6 3 7 4 Safety Materials the Urban Environment ET-OROMIA-NAGELE BORA Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-02-1 2024-03-0 2024-03-2 2024-04-0 2024-05-1 NA-392084-GO-RFQ / Proc IDA / D7320 ive Safety Net to Improve Post Limited 7,492.00 0.00 Completed tations e Envelope 5 8 4 1 3 4 urement of Local Construc the Urban Environment tion Materials ET-OROMIA-NAGELE BORA Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-04-0 2024-03-0 2024-06-2 2024-04-0 2024-06-2 NA-392093-GO-RFQ / Proc IDA / D7320 ive Safety Net to Improve Post Limited 4,514.00 0.00 Completed tations e Envelope 5 5 4 1 3 8 urement of Different Seedl the Urban Environment ing ET-OROMIA-FICHE-392098 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-01-0 2024-02-1 2024-02-1 2024-03-1 2024-02-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 5,509.00 0.00 Completed tations e Envelope 2 2 3 3 4 7 Hand Tool Materials the Urban Environment ET-OROMIA-SHASHAMANE Expand the Urban Product Single Stage - On 2023-12-0 2024-01-1 2023-12-1 2024-08-2 2024-01-1 2024-02-1 2024-01-2 2024-03-1 2024-02-2 2024-03-2 2024-03-2 2024-05-3 -392146-GO-RFB / Procure IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 208,518.00 0.00 Completed e Envelope 7 6 2 0 1 4 5 8 2 9 5 0 ment of Protective safety the Urban Environment Materials ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-02-0 2024-01-3 2024-03-0 2024-02-2 2024-03-2 -392152-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 42,542.00 0.00 Completed tations e Envelope 2 9 0 6 9 9 ment of Hand Tools the Urban Environment ET-OROMIA-SHASHAMANE Expand the Urban Product -392155-GO-RFQ / Procure Request for Quo Single Stage - On 2024-01-1 2024-03-1 2024-03-0 2024-05-1 2024-03-0 2024-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 41,866.00 0.00 Completed ment of Industrial and Fini tations e Envelope 6 8 5 6 8 4 the Urban Environment shing Construction Materia ls ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-03-1 2024-02-0 2024-05-1 2024-03-0 2024-05-2 -392164-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 6,603.00 0.00 Completed tations e Envelope 2 8 6 5 7 4 ment of Local Construction the Urban Environment Materials ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Quo Single Stage - On 2024-04-0 2024-05-2 2024-05-2 2024-06-2 2024-06-2 2024-07-0 -392168-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 10,214.00 0.00 Completed tations e Envelope 8 7 7 8 6 6 ment of Different Seedling the Urban Environment ET-OROMIA-FICHE-392199 Expand the Urban Product -GO-RFQ / Procurement of Request for Quo Single Stage - On 2024-01-0 2024-01-2 2024-02-1 2024-02-2 2024-03-1 2024-03-2 IDA / D7320 ive Safety Net to Improve Post Limited 36,255.00 0.00 Completed Industrial and Finishing Co tations e Envelope 2 5 3 3 4 5 the Urban Environment nstruction Materials and W aterline Installation materi als ET-OROMIA-FICHE-392211 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-02-1 2024-02-1 2024-04-2 2024-03-1 2024-05-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 21,990.00 0.00 Completed tations e Envelope 2 9 3 6 4 9 Local Construction Materia the Urban Environment ls ET-OROMIA-FICHE-392228 Expand the Urban Product Request for Quo Single Stage - On 2024-04-1 2024-03-2 2024-05-2 2024-04-2 2024-06-2 2024-04-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 7,375.00 0.00 Completed tations e Envelope 5 2 7 2 6 5 different seedling the Urban Environment ET-OROMIA-CHIRO-39224 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-01-2 2024-02-1 2024-02-2 2024-03-1 2024-03-1 2-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 42,609.00 0.00 Completed tations e Envelope 1 5 2 0 3 1 f Safety Materials the Urban Environment ET-OROMIA-CHIRO-39224 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-03-0 2024-02-1 2024-02-2 2024-03-1 2024-03-1 7-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 11,222.00 0.00 Completed tations e Envelope 1 6 2 0 3 1 f hand tools materials the Urban Environment ET-OROMIA-CHIRO-39230 Expand the Urban Product 5-GO-RFQ / Procurement o Request for Quo Single Stage - On 2024-01-0 2024-01-2 2024-02-2 2024-02-1 2024-03-2 2024-03-0 IDA / D7320 ive Safety Net to Improve Post Limited 32,564.00 0.00 Completed f Industrial and Finishing C tations e Envelope 3 5 1 9 2 6 the Urban Environment onstruction Materials and Water Line Installation ET-OROMIA-NAGELE ARSI- Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2023-12-1 2024-01-3 2024-01-2 2024-02-2 2024-02-1 392310-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 77,389.00 0.00 Completed tations e Envelope 2 8 0 4 9 6 ment of Safety Materials the Urban Environment ET-OROMIA-CHIRO-39231 Expand the Urban Product Request for Quo Single Stage - On 2023-12-2 2024-02-0 2024-02-0 2024-03-0 2024-03-0 2024-03-2 5-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 8,373.00 0.00 Completed tations e Envelope 5 2 5 1 6 0 f Local Construction Materi the Urban Environment als ET-OROMIA-NAGEL ARSI-3 Expand the Urban Product Request for Quo Single Stage - On 2023-11-1 2023-12-1 2024-01-0 2024-01-2 2024-02-0 2024-02-1 92319-GO-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 41,088.00 0.00 Completed tations e Envelope 4 8 9 4 8 6 ent of Hand Tools the Urban Environment ET-OROMIA-CHIRO-39232 Expand the Urban Product Request for Quo Single Stage - On 2024-04-0 2024-06-1 2024-05-2 2024-06-2 2024-06-1 2024-07-0 2-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 3,499.00 0.00 Completed tations e Envelope 8 0 0 7 9 2 f Seedling the Urban Environment ET-OROMIA-NAGELE ARSI- Expand the Urban Product 392337-GO-RFQ / Procure Request for Quo Single Stage - On 2023-12-1 2024-02-2 2024-01-3 2024-04-0 2024-02-2 2024-05-1 IDA / D7320 ive Safety Net to Improve Post Limited 15,844.00 0.00 Completed ment of industrial and Fini tations e Envelope 2 3 0 3 9 5 the Urban Environment shing Construction Materia ls ET-OROMIA-NAGELE ARSI- Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-02-2 2024-02-2 2024-04-0 2024-03-2 2024-05-1 392347-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 8,094.00 0.00 Completed tations e Envelope 9 3 7 3 8 7 ment of Local Construction the Urban Environment Materials ET-OROMIA-NAGELE ARSI- Expand the Urban Product Request for Quo Single Stage - On Under Impl 2024-04-0 2024-05-2 2024-06-2 392388-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 4,514.00 0.00 tations e Envelope ementation 8 7 6 ment of Different Seedling the Urban Environment s ET-OROMIA-ADAMA-39278 Expand the Urban Product Single Stage - On 2024-01-0 2024-01-2 2024-01-0 2024-02-0 2024-02-2 2024-02-2 2024-02-1 2024-03-2 2024-04-1 2024-04-1 2024-05-2 2-GO-RFB / Procurement of IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 203,249.00 0.00 Completed e Envelope 4 9 9 8 7 2 9 0 1 9 1 Protective safety materials the Urban Environment ET-OROMIA-ADAMA-39278 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-03-0 2024-02-2 2024-05-0 2024-03-2 2024-05-1 3-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 44,436.00 0.00 Completed tations e Envelope 9 6 7 8 8 6 f Hand Tools the Urban Environment ET-OROMIA-ADAMA-39278 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-03-0 2024-02-2 2024-06-1 2024-03-2 2024-07-0 6-GO-RFQ / Procurement I IDA / D7320 ive Safety Net to Improve Post Limited 91,186.00 0.00 Completed tations e Envelope 9 6 7 8 8 5 ndustrial and Finishing Co the Urban Environment nstruction Materials ET-OROMIA-ADAMA-39282 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-01-2 2024-02-2 2024-04-1 2024-03-2 2-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 10,598.00 0.00 Terminated tations e Envelope 9 9 6 1 7 f Local Construction Materi the Urban Environment als ET-OROMIA-GINCHI-39306 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-02-1 2024-02-2 2024-03-1 2024-03-2 2024-05-1 5-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 13,652.00 0.00 Completed tations e Envelope 9 6 0 8 1 0 f Safety Materials the Urban Environment ET-OROMIA-GINCHI-39306 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-02-1 2024-02-2 2024-03-1 2024-03-2 2024-06-1 6-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 15,345.00 0.00 Completed tations e Envelope 9 6 7 8 8 9 f Industrial Construction M the Urban Environment aterials ET-OROMIA-GINCHI-39306 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-02-1 2024-02-2 2024-03-1 2024-03-2 2024-06-1 7-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 8,267.00 0.00 Completed tations e Envelope 9 6 7 9 8 9 f Local Construction Materi the Urban Environment als ET-OROMIA-MAKI-393072- Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-02-0 2024-02-2 2024-02-2 2024-03-2 2024-03-2 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 68,954.00 0.00 Completed tations e Envelope 8 9 6 8 7 6 Safety Materials the Urban Environment ET-OROMIA-MAKI-393074- Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-04-0 2024-02-2 2024-02-2 2024-03-2 2024-03-1 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 17,025.00 0.00 Completed tations e Envelope 8 9 6 8 7 9 Hand Tools the Urban Environment ET-OROMIA-MAKI-393082- Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-04-0 2024-02-2 2023-12-2 2024-03-2 2024-05-2 GO-RFQ / Procurement of I IDA / D7320 ive Safety Net to Improve Post Limited 9,727.00 0.00 Completed tations e Envelope 8 1 6 2 7 2 ndustrial Contraction Mate the Urban Environment rials ET-OROMIA-MAKI-393091- Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-04-0 2024-02-2 2024-04-1 2024-03-2 2024-05-1 GO-RFQ / Procurement of L IDA / D7320 ive Safety Net to Improve Post Limited 2,946.00 0.00 Completed tations e Envelope 0 1 8 2 9 3 ocal Construction Material the Urban Environment s ET-OROMIA-MAKI-393096- Expand the Urban Product Request for Quo Single Stage - On 2024-04-0 2024-04-0 2024-05-1 2024-04-2 2024-06-1 2024-05-2 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 3,524.00 0.00 Completed tations e Envelope 8 9 3 3 2 4 Different Seedlings the Urban Environment ET-OROMIA-HOLOTA-3931 Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-02-2 2024-02-1 2024-02-0 2024-03-2 2024-02-1 24-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 40,438.00 0.00 Completed tations e Envelope 5 3 9 6 0 3 of Safety Materials the Urban Environment ET-OROMIA-HOLOTA-3931 Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-01-2 2024-02-1 2024-02-1 2024-03-1 2024-02-1 27-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 2,854.00 0.00 Completed tations e Envelope 5 3 9 9 1 9 of Hand Tools the Urban Environment ET-OROMIA-HOLOTA-3931 Expand the Urban Product 28-GO-RFQ / procurement Request for Quo Single Stage - On 2024-01-1 2024-05-2 2024-02-1 2024-07-0 2024-03-1 2024-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 1,400.00 0.00 Completed of Water tanker( Fiberglas tations e Envelope 5 7 9 5 1 5 the Urban Environment 3000 L) and Metal Doors fo r Public Toilet and Shower ET-OROMIA-MAYA-393155 Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-01-1 2024-02-2 2024-02-1 2024-03-2 2024-04-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 21,631.00 0.00 Completed tations e Envelope 5 0 6 3 7 2 Safety Materials the Urban Environment ET-OROMIA-MAYA-393162 Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-01-1 2024-02-1 2024-02-1 2024-03-2 2024-04-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 10,690.00 0.00 Completed tations e Envelope 5 0 9 3 0 5 Hand Tools the Urban Environment ET-OROMIA-MAYA-393167 Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-01-1 2024-02-2 2024-02-1 2024-03-2 2024-05-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 48,047.00 0.00 Completed tations e Envelope 5 0 6 4 7 2 Industrial Construction Mat the Urban Environment erials ET-OROMIA-MAYA-393178 Expand the Urban Product Request for Quo Single Stage - On 2023-12-2 2023-12-2 2024-02-1 2024-02-1 2024-03-1 2024-05-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 23,173.00 0.00 Completed tations e Envelope 6 1 3 3 4 2 Local Construction Materia the Urban Environment ls ET-OROMIA-MAYA-393182 Expand the Urban Product Request for Quo Single Stage - On 2024-04-0 2024-04-0 2024-05-2 2024-05-0 2024-06-2 2024-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 6,377.00 0.00 Completed tations e Envelope 9 4 2 2 1 5 Different Seedlings the Urban Environment ET-OROMIA-BADESA-3934 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-02-1 2024-02-2 2024-02-2 2024-03-2 2024-05-0 92-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 24,472.00 0.00 Completed tations e Envelope 2 2 0 6 1 3 of Safety Materials the Urban Environment ET-OROMIA-BADESA-3934 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-02-1 2024-02-2 2024-02-2 2024-03-2 2024-04-3 93-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 1,662.00 0.00 Completed tations e Envelope 2 2 0 6 1 0 of Hand Tools the Urban Environment ET-OROMIA-BADESA-3934 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-02-1 2024-02-0 2024-03-0 2024-02-2 2024-07-0 99-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 1,518.00 0.00 Completed tations e Envelope 2 9 6 6 6 3 of Industrial Construction the Urban Environment Materials ET-OROMIA-BADESA-3935 Expand the Urban Product Request for Quo Single Stage - On 2024-04-0 2024-05-1 2024-06-1 04-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 3,054.00 0.00 Canceled tations e Envelope 8 6 5 of Different Seedlings the Urban Environment ET-OROMIA-DERA-393517 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-01-2 2024-02-0 2024-03-0 2024-02-2 2024-03-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 14,268.00 0.00 Completed tations e Envelope 2 2 6 7 6 0 Safety Materials the Urban Environment ET-OROMIA-DERA-393519 Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-02-0 2024-02-1 2024-04-0 2024-03-1 2024-06-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 8,482.00 0.00 Completed tations e Envelope 5 7 9 8 1 9 Industrial Construction Mat the Urban Environment erials ET-OROMIA-DERA-393521 Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-02-0 2024-02-1 2024-04-1 2024-03-1 2024-06-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 2,063.00 0.00 Completed tations e Envelope 5 7 9 2 1 4 Local Construction Materia the Urban Environment ls ET-OROMIA-ASALA-39353 Expand the Urban Product Single Stage - On 2023-12-0 2024-04-0 2023-12-1 2024-05-3 2024-01-1 2024-05-0 2024-01-1 2024-05-0 2024-02-0 2024-05-1 2024-03-0 2024-07-0 0-GO-RFB / Procurement of IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 159,624.00 0.00 Completed e Envelope 6 7 1 0 0 6 1 8 7 6 8 4 Protective Safety Materials the Urban Environment ET-OROMIA-ASALA-39353 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-01-2 2024-02-0 2024-02-2 2024-03-0 2024-05-1 2-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 31,668.00 0.00 Completed tations e Envelope 8 4 5 1 6 0 f Hand Tools the Urban Environment ET-OROMIA-ASALA-39353 Expand the Urban Product Request for Quo Single Stage - On 2023-12-2 2024-02-1 2024-02-1 2024-04-0 2024-03-1 2024-05-2 3-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 40,219.00 0.00 Completed tations e Envelope 5 9 2 4 3 2 f Industrial and Finishing the Urban Environment Construction Materials ET-OROMIA-ASALA-39353 Expand the Urban Product Request for Quo Single Stage - On 2023-12-2 2024-02-2 2024-02-1 2024-04-1 2024-03-1 2024-06-1 9-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 16,711.00 0.00 Completed tations e Envelope 5 7 2 7 3 2 f Local Construction Materi the Urban Environment als ET-OROMIA-ASALA-39355 Expand the Urban Product Request for Quo Single Stage - On 2024-04-0 2024-05-2 2024-05-2 2024-06-2 2024-06-1 2024-07-0 4-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post Limited 3,833.00 0.00 Completed tations e Envelope 8 0 1 0 0 5 f Different Seedlings the Urban Environment ET-OROMIA-BISHOFTU-39 Expand the Urban Product Single Stage - On 2023-12-2 2024-01-1 2023-12-2 2024-05-3 2024-01-2 2024-02-2 2024-02-0 2024-03-2 2024-03-0 2024-05-1 2024-04-0 2024-07-0 3585-GO-RFB / Procureme IDA / D7320 ive Safety Net to Improve Post Request for Bids Open - National 204,666.00 0.00 Completed e Envelope 0 8 5 0 4 0 7 7 6 5 5 5 nt of Protective Safety Mat the Urban Environment erials ET-OROMIA-BISHOFTU-39 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-03-1 2024-02-1 2024-04-0 2024-03-2 2024-05-0 3589-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 39,571.00 0.00 Completed tations e Envelope 1 2 9 5 0 6 nt of Hand Tools the Urban Environment ET-OROMIA-BISHOFTU-39 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-03-2 2024-02-1 2024-04-1 2024-03-2 2024-06-0 3598-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 32,292.00 0.00 Completed tations e Envelope 1 2 9 1 0 6 nt of Industrial Constructio the Urban Environment n materials Page 11 ET-OROMIA-BISHOFTU-39 Expand the Urban Product 3605-GO-RFQ / Procureme Request for Quo Single Stage - On 2024-01-2 2024-03-2 2024-02-1 2024-04-1 2024-03-1 2024-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 25,105.00 0.00 Completed nt of Finishing Contraction tations e Envelope 2 2 9 2 1 5 the Urban Environment and water Line Installation materials ET-OROMIA-BISHOFTU-39 Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-03-2 2024-02-1 2024-04-0 2024-03-1 2024-07-0 3617-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 11,410.00 0.00 Completed tations e Envelope 5 2 2 8 3 5 nt of Local Construction M the Urban Environment aterials ET-OROMIA-BISHOFTU-39 Expand the Urban Product Request for Quo Single Stage - On 2024-05-0 2024-04-2 2024-05-3 2024-01-2 2024-06-1 2024-07-0 3621-GO-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 13,036.00 0.00 Completed tations e Envelope 6 2 1 6 4 5 nt of Different Seedlings the Urban Environment ET-OROMIA-BOLSA-39363 0-GO-RFQ / Procurement o f 4 Core i 5 Disc Top com Foster Urban Youth Emplo Request for Quo Single Stage - On Under Impl 2024-02-0 2024-01-1 2024-03-1 2024-04-1 IDA / D7320 Post Limited 12,561.00 0.00 puters for Sheger, Shash yment tations e Envelope ementation 6 1 2 1 amane,Adama and Bishoft u City’s and 2 core i 7 Lap top computers for Region al Bureau. ET-OROMIA-BOLSA-39363 Foster Urban Youth Emplo Request for Quo Single Stage - On Under Impl 2024-02-0 2024-03-0 2024-03-2 3-GO-RFQ / Procurement o IDA / D7320 Post Limited 2,871.00 0.00 yment tations e Envelope ementation 6 5 5 f 2 office Shelf’s for Region al Bureau ET-OROMIA-UDHB-394414 Institutional Strengthenin -GO-RFQ / Procurement of g, Project Management an Request for Quo Single Stage - On 2024-02-0 2024-03-2 2024-04-1 IDA / D7320 Post Limited 34,990.00 0.00 Canceled 12 Desktop Computer for d Monitoring and Evaluati tations e Envelope 6 6 5 City's, 1 LCD Projector and on 1 Scanner for Regional HU B ET-OROMIA-OJCVB-39446 3-GO-RFB / Procurement of Furniture’s (Coordinators T able 7, Coordinator’s Chair Foster Urban Youth Emplo Single Stage - On Under Impl 2023-12-0 2024-01-0 2023-12-1 2024-01-1 2024-01-1 2024-01-2 2024-02-2 2024-03-2 7, Gust Chair 63, Table 16 IDA / D7320 Post Request for Bids Open - National 139,409.00 0.00 yment e Envelope ementation 6 3 1 6 0 4 1 2 1, Chair 128, and Shelf 14 for OSSC’s ( Adama Tadac ha & Boku Shana OSSC, Bi shoftu- Dire Jitu OSSC, Asal a-Chilalo OSSC, Sabata 08 OSSC, Shashamane- Alelu ET-OROMIA-ROBE-392064 OSSC, Expand the Urban Product Request for Quo Single Stage - On 2024-04-0 2024-05-2 2024-05-1 2024-06-1 2024-06-1 2024-07-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 3,819.00 0.00 Completed tations e Envelope 8 8 3 8 2 2 Different Seedlings the Urban Environment ET-OROMIA-GIMBI-401865 Expand the Urban Product Request for Quo Single Stage - On 2024-01-2 2024-06-0 2024-03-0 2024-07-0 2024-04-0 2024-08-0 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 36,648.00 0.00 Completed tations e Envelope 9 3 4 2 3 1 Protective Safety Materials the Urban Environment ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Quo Single Stage - On 2024-01-2 2024-03-1 2024-03-0 2024-05-1 2024-04-0 2024-05-2 -401874-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 48,469.00 0.00 Completed tations e Envelope 9 8 4 5 3 4 ment of Finishing Construc the Urban Environment tion Materials ET-OROMIA-SABATA-4173 Expand the Urban Product 12-GO-RFQ / Lot 1 Procure Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-04-2 2024-05-2 2024-05-2 2024-06-1 2024-06-1 IDA / D7320 ive Safety Net to Improve Post 37,275.00 0.00 Completed ment of Safety Materials tations l e Envelope 5 4 0 1 9 3 the Urban Environment Lot 2 Procurement of Hand Tools ET-OROMIA-SABATA-4173 Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-05-2 2024-05-0 2024-06-1 2024-06-0 2024-07-0 19-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post 17,818.00 0.00 Completed tations l e Envelope 5 9 6 9 5 4 of Industrial and Finishing the Urban Environment construction Materials ET-OROMIA-SABATA-4173 Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-2 2024-05-2 2024-05-2 2024-07-1 2024-06-1 2024-07-2 24-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post 4,484.00 0.00 Completed tations l e Envelope 2 9 0 9 9 3 of Local Construction Mate the Urban Environment rials ET-OROMIA-SABATA-4173 Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-2 2024-05-2 2024-05-2 2024-06-1 2024-06-1 2024-07-0 30-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post 2,818.00 0.00 Completed tations l e Envelope 9 9 8 9 7 3 of Different seedlings the Urban Environment ET-OROMIA-GALAN GUDA- Expand the Urban Product 417366-GO-RFQ / Lot 1 Pro Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-04-2 2024-05-2 2024-05-3 2024-06-1 2024-07-0 IDA / D7320 ive Safety Net to Improve Post 53,370.00 0.00 Completed curement of Protective Saf tations l e Envelope 5 5 0 0 9 2 the Urban Environment ety Materials Lot 2 Hand Tools ET-OROMIA-GALAN GUDA- Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-2 2024-05-3 2024-05-2 2024-06-1 2024-06-2 2024-07-0 417372-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post 17,226.03 0.00 Completed tations l e Envelope 9 0 7 4 6 8 ment of Different Seedling the Urban Environment s ET-OROMIA-FURI-417474- Expand the Urban Product GO-RFQ / Lot 1 Procureme Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-04-2 2024-05-2 2024-06-0 2024-06-1 2024-06-2 IDA / D7320 ive Safety Net to Improve Post 38,383.00 0.00 Completed nt of Protective Safety Ma tations l e Envelope 5 2 0 6 9 8 the Urban Environment terials Lot 2 Procurement of Hand Tools ET-OROMIA-FURI-417477- Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-04-2 2024-05-2 2024-06-0 2024-06-1 2024-07-0 GO-RFQ / Procurement of I IDA / D7320 ive Safety Net to Improve Post 12,655.00 0.00 Completed tations l e Envelope 5 2 0 6 9 2 ndustrial Construction and the Urban Environment Finishing Materials ET-OROMIA-FURI-417481- Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-2 2024-04-2 2024-05-2 2024-06-0 2024-06-2 2024-07-0 GO-RFQ / Procurement of L IDA / D7320 ive Safety Net to Improve Post 2,422.00 0.00 Completed tations l e Envelope 2 2 7 6 6 3 ocal Construction Material the Urban Environment s ET-OROMIA-BURAYU-4174 Expand the Urban Product 91-GO-RFQ / Lot 1 Procure Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-05-2 2024-05-2 2024-06-1 2024-06-1 2024-07-0 IDA / D7320 ive Safety Net to Improve Post 62,017.00 0.00 Completed ment of Protective Safety tations l e Envelope 5 9 0 7 9 5 the Urban Environment Materials Lot 2 Procurement of Hand Tools ET-OROMIA-BURAYU-4174 Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-05-2 2024-05-2 2024-06-1 2024-06-1 2024-07-0 96-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post 31,807.00 0.00 Completed tations l e Envelope 5 7 0 3 9 5 of Construction and Finish the Urban Environment ing Industrial Materials ET-OROMIA-BURAYU-4175 Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-05-2 2024-05-2 2024-06-1 2024-06-1 2024-07-0 04-GO-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post 8,733.00 0.00 Completed tations l e Envelope 5 9 0 7 9 5 of Local Construction Mate the Urban Environment rials ET-OROMIA-MALKA NONO- Expand the Urban Product 417510-GO-RFQ / Lot 1 Pro Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-05-1 2024-06-1 IDA / D7320 ive Safety Net to Improve Post 28,219.00 0.00 Canceled curement of Protective Saf tations l e Envelope 5 6 5 the Urban Environment ety Materials Lot 2 Procurement of Hand tools ET-OROMIA-MALKA NONO- Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-05-0 2024-06-0 417515-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post 12,347.00 0.00 Canceled tations l e Envelope 5 6 5 ment of Construction and the Urban Environment Finishing Materials ET-OROMIA-MALKA NONO- Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-05-1 2024-06-1 417528-GO-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post 3,102.00 0.00 Canceled tations l e Envelope 6 4 3 ment of Local Construction the Urban Environment Materials ET-OROMIA-GAFARSA GUJ Expand the Urban Product E-417537-GO-RFQ / lot 1 P Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-05-3 2024-05-2 2024-06-2 2024-06-1 2024-07-0 IDA / D7320 ive Safety Net to Improve Post 20,899.00 0.00 Completed rocurement of Protective S tations l e Envelope 5 0 0 5 9 6 the Urban Environment afety Materials Lot 2 Procurement of hand tools ET-OROMIA-GAFARSA GUJ Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-05-2 2024-06-1 E-417546-GO-RFQ / Procur IDA / D7320 ive Safety Net to Improve Post 23,687.00 0.00 Canceled tations l e Envelope 5 0 9 ement of Industrial Constr the Urban Environment uction Materials ET-OROMIA-GAFARSA GUJ Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-05-2 2024-06-2 E-417549-GO-RFQ / Procur IDA / D7320 ive Safety Net to Improve Post 5,787.00 0.00 Canceled tations l e Envelope 6 1 0 ement of Local Constructio the Urban Environment n materials ET-OROMIA-ROBE-466436 Expand the Urban Product Pending Im -GO-RFQ / Procurement of Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-0 IDA / D7320 ive Safety Net to Improve Post 57,517.00 0.00 plementati protective safety Materials tations l e Envelope 5 2 9 the Urban Environment on for public work Beneficiari es ET-OROMIA-MAYA-466442 Expand the Urban Product Pending Im -GO-RFQ / Procurement of Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-0 IDA / D7320 ive Safety Net to Improve Post 36,446.00 0.00 plementati Protective Safety Material f tations l e Envelope 5 2 9 the Urban Environment on or public work beneficiarie s ET-OROMIA-BADESA-4664 Expand the Urban Product Pending Im 43-GO-RFQ / Procurement Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 20,838.00 0.00 plementati protective Safety Materials tations l e Envelope 5 2 4 the Urban Environment on for Public work beneficiarie s ET-OROMIA-CHIRO-46644 Expand the Urban Product Pending Im 4-GO-RFQ / Procurement o Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 47,076.00 0.00 plementati f Protective safety Material tations l e Envelope 5 2 4 the Urban Environment on s for Public work beneficiar ies ET-OROMIA-YABELO-4664 Expand the Urban Product Pending Im 45-GO-RFQ / Procurement Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 25,011.00 0.00 plementati of Protective Safety Materi tations l e Envelope 5 2 4 the Urban Environment on als for Public work benefici aries ET-OROMIA-DERA-466446 Expand the Urban Product Pending Im -GO-RFQ / Procurement of Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-0 IDA / D7320 ive Safety Net to Improve Post 17,143.00 0.00 plementati Protective Safety Materials tations l e Envelope 5 2 9 the Urban Environment on for public work beneficiari es ET-OROMIA-NEGELE ARSI- Expand the Urban Product Pending Im 466450-GO-RFQ / Procure Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 83,760.00 0.00 plementati ment of Protective Safety tations l e Envelope 5 2 4 the Urban Environment on Materials for public work b eneficiaries ET-OROMIA-WALISO-4665 Expand the Urban Product Pending Im 77-GO-RFQ / Procurement Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 36,848.00 0.00 plementati of protective Safety Materi tations l e Envelope 5 2 4 the Urban Environment on als for public work benefici aries ET-OROMIA-AMBO-466581 Expand the Urban Product Pending Im -GO-RFQ / Procurement of Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 83,479.00 0.00 plementati protective Safety Materials tations l e Envelope 5 2 4 the Urban Environment on for public work beneficiari es ET-OROMIA-BEDELE-4665 Expand the Urban Product Pending Im 85-GO-RFQ / Procurement Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 30,500.00 0.00 plementati of Protective safety Materi tations l e Envelope 5 2 9 the Urban Environment on als for public work benefici aries ET-OROMIA-MATU-466587 Expand the Urban Product Pending Im -GO-RFQ / Procurement of Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 23,428.00 0.00 plementati Protective Safety Materials tations l e Envelope 5 2 9 the Urban Environment on for public work beneficiari es ET-OROMIA-GINCHI-46659 Expand the Urban Product Pending Im 0-GO-RFQ / Procurement o Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 20,985.00 0.00 plementati f Protective Safety Material tations l e Envelope 5 2 4 the Urban Environment on for public work beneficiari es ET-OROMIA-SHAMBU-466 Expand the Urban Product Pending Im 591-GO-RFQ / procuremen Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-2 IDA / D7320 ive Safety Net to Improve Post 17,711.00 0.00 plementati t of protective Safety Mate tations l e Envelope 5 2 4 the Urban Environment on rials for public work benefi ciaries ET-OROMIA-GIMBI-466592 Expand the Urban Product Pending Im -GO-RFQ / Procurement of Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 56,544.00 0.00 plementati Protective Safety Materials tations l e Envelope 5 2 9 the Urban Environment on for public work beneficiari es ET-OROMIA-FICHE-466594 Expand the Urban Product Pending Im -GO-RFQ / Procurement of Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 50,004.00 0.00 plementati Protective Safety Materials tations l e Envelope 5 2 4 the Urban Environment on for public work beneficiari es ET-OROMIA-HOLOTA-4665 Expand the Urban Product Pending Im 95-GO-RFQ / Procurement Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-0 IDA / D7320 ive Safety Net to Improve Post 27,014.00 0.00 plementati protective safety Materials tations l e Envelope 5 2 9 the Urban Environment on for public work beneficiari es ET-OROMIA-AGARO-46670 Expand the Urban Product Pending Im 5-GO-RFQ / Procurement o Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 33,336.00 0.00 plementati f Protective Safety Material tations l e Envelope 5 2 9 the Urban Environment on s for public work beneficiar ies ET-OROMIA-DAMBI DOLO- Expand the Urban Product Pending Im 466706-GO-RFQ / Procure Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-2 IDA / D7320 ive Safety Net to Improve Post 37,004.00 0.00 plementati ment of Protective Safety tations l e Envelope 5 2 4 the Urban Environment on Materials for public work b eneficiaries ET-OROMIA-MAKI-466707- Expand the Urban Product Pending Im GO-RFQ / Procurement of Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-0 IDA / D7320 ive Safety Net to Improve Post 63,653.00 0.00 plementati protective safety materials tations l e Envelope 5 2 9 the Urban Environment on for public work beneficiari es ET-OROMIA-BATU-466708 Expand the Urban Product Pending Im -GO-RFQ / procurement pr Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-0 IDA / D7320 ive Safety Net to Improve Post 77,329.00 0.00 plementati otective Safety Materials f tations l e Envelope 5 2 9 the Urban Environment on or public work beneficiarie s ET-OROMIA-NEGELE BORA Expand the Urban Product Pending Im NA-466710-GO-RFQ / proc Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 41,166.00 0.00 plementati urement of protective safe tations l e Envelope 5 2 4 the Urban Environment on ty materials for public wor k beneficiaries ET-OROMIA-BULE HORA-4 Expand the Urban Product Pending Im 66711-GO-RFQ / procurem Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 37,525.00 0.00 plementati ent protective safety mate tations l e Envelope 5 2 4 the Urban Environment on rials for public work benefi ciaries Page 12 ET-OROMIA-KOYE FECHE- Expand the Urban Product Pending Im 466713-GO-RFQ / Procure Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-0 IDA / D7320 ive Safety Net to Improve Post 21,491.00 0.00 plementati ment protective safety ma tations l e Envelope 5 2 9 the Urban Environment on terials for public work ben eficiaries ET-OROMIA-ADAMA-46671 5-GO-RFQ / Procurement o Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 f Protective safety material IDA / D7320 ive Safety Net to Improve Post 90,530.00 0.00 plementati tations l e Envelope 5 2 4 s for public work beneficiar the Urban Environment on ies(Protective clothes or co verall, reflector coats and Hats) ET-OROMIA-ADAMA-46671 Expand the Urban Product Pending Im 6-GO-RFQ / Procurement o Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 65,911.00 0.00 plementati f protective safety Material tations l e Envelope 5 2 4 the Urban Environment on s for public work beneficiar ies(Men and Women shoes ) ET-OROMIA-ADAMA-46671 7-GO-RFQ / Procurement o Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 f Protective safety material IDA / D7320 ive Safety Net to Improve Post 34,302.00 0.00 plementati tations l e Envelope 5 2 4 s for public work beneficiar the Urban Environment on ies(Gloves, first aid kits, Ey e google glass and masks) ET-OROMIA-BISHOFTU-46 6718-GO-RFQ / Procureme Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 nt of Protective Safety Mat IDA / D7320 ive Safety Net to Improve Post 76,598.00 0.00 plementati tations l e Envelope 5 2 4 erials for public work bene the Urban Environment on ficiaries(safety clothes, Ha ts, rain coats) ET-OROMIA-BISHOFTU-46 6719-GO-RFQ / Procureme Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 nt of protective safety mat IDA / D7320 ive Safety Net to Improve Post 68,063.00 0.00 plementati tations l e Envelope 5 2 4 erials for public work bene the Urban Environment on ficiaries(men and women s hoes) ET-OROMIA-BISHOFTU-46 6720-GO-RFQ / procureme Expand the Urban Product Pending Im nt of protective safety mat Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 36,749.00 0.00 plementati erials for public work bene tations l e Envelope 5 2 4 the Urban Environment on ficiaries(hand gloves, mas ks, first aid kits and an Eye google glasses) ET-OROMIA-ASALA-46672 1-GO-RFQ / procurement o Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2024-12-2 2025-02-0 2025-02-2 f protective safety materia IDA / D7320 ive Safety Net to Improve Post 52,416.00 0.00 plementati tations l e Envelope 5 1 1 ls for public work beneficia the Urban Environment on ries(men and Women cloth es, Hats) ET-OROMIA-ASALA-46672 Expand the Urban Product Pending Im 2-GO-RFQ / procurement p Request for Quo Limited - Nationa Single Stage - On 2024-12-2 2025-02-0 2025-02-2 IDA / D7320 ive Safety Net to Improve Post 53,274.00 0.00 plementati rotective safety materials f tations l e Envelope 5 1 1 the Urban Environment on or public work beneficiarie s(Men and Women shoes) ET-OROMIA-ASALA-46672 3-GO-RFQ / Procurement p Expand the Urban Product Pending Im rotective safety materials f Request for Quo Limited - Nationa Single Stage - On 2024-12-2 2025-02-0 2025-02-2 IDA / D7320 ive Safety Net to Improve Post 16,658.00 0.00 plementati or public work beneficiarie tations l e Envelope 5 1 1 the Urban Environment on s (safety cleaning materia ls hand gloves, masks, firs t aid kits, eye google glass es) ET-OROMIA-SHASHAMANE -466724-GO-RFQ / procure Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 ment of protective safety IDA / D7320 ive Safety Net to Improve Post 69,145.00 0.00 plementati tations l e Envelope 5 2 4 materials for public work b the Urban Environment on eneficiaries(Men and Wom en clothes and overall, Hat s, rain coats) ET-OROMIA-SHASHAMANE -466725-GO-RFQ / Procure Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 ment of protective safety IDA / D7320 ive Safety Net to Improve Post 81,944.00 0.00 plementati tations l e Envelope 5 2 4 materials for public work b the Urban Environment on eneficiaries(Men and Wom en shoes) ET-OROMIA-SHASHAMANE -466726-GO-RFQ / procure Expand the Urban Product Pending Im ment of protective safety Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 42,694.00 0.00 plementati materials for public work b tations l e Envelope 5 2 4 the Urban Environment on eneficiaries(safety cleanin g materials hand Gloves, fi rst aid kits, masks, an eye google glasses) ET-OROMIA-JIMA-466727- GO-RFQ / procurement pro Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 tective safety materials for IDA / D7320 ive Safety Net to Improve Post 94,204.00 0.00 plementati tations l e Envelope 5 2 9 public work beneficiaries( the Urban Environment on Men and Women Clothes a nd Hats) ET-OROMIA-JIMA-466728- Expand the Urban Product Pending Im GO-RFQ / Procurement of Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 78,503.00 0.00 plementati protective safety materials tations l e Envelope 5 2 9 the Urban Environment on for public work beneficiari es(Men and women Shoes) ET-OROMIA-JIMA-466729- GO-RFQ / procurement of Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 protective safety materials IDA / D7320 ive Safety Net to Improve Post 46,638.00 0.00 plementati tations l e Envelope 5 2 9 for public work beneficiari the Urban Environment on es(hand gloves, masks, fir st aid kits, Eye glasses) ET-OROMIA-NEKEMTE-466 730-GO-RFQ / procuremen Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 t of protective safety mate IDA / D7320 ive Safety Net to Improve Post 81,147.00 0.00 plementati tations l e Envelope 5 2 9 rials for public work benefi the Urban Environment on ciaries(safety clothes, hats , rain coats) ET-OROMIA-NEKEMTE-466 Expand the Urban Product Pending Im 731-GO-RFQ / procuremen Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 40,430.00 0.00 plementati t protective safety materia tations l e Envelope 5 2 9 the Urban Environment on ls for public work beneficia ries(men and Women shoe s) ET-OROMIA-NEKEMTE-466 732-GO-RFQ / procuremen Expand the Urban Product Pending Im t of protective safety mate Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 33,270.00 0.00 plementati rials for public work benefi tations l e Envelope 5 2 9 the Urban Environment on ciaries(cleaning safety mat erials hand gloves, first Aid kits, masks, eye glasses) ET-OROMIA-FURI-466754- Expand the Urban Product Pending Im GO-RFQ / procurement of Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-0 IDA / D7320 ive Safety Net to Improve Post 39,908.00 0.00 plementati protective safety materials tations l e Envelope 5 2 9 the Urban Environment on for public work beneficiari es ET-OROMIA-BURAYU-4667 Expand the Urban Product Pending Im 56-GO-RFQ / procurement Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-0 IDA / D7320 ive Safety Net to Improve Post 33,061.00 0.00 plementati of protective safety materi tations l e Envelope 5 2 9 the Urban Environment on als for public work benefici aries ET-OROMIA-MALKA NONO- Expand the Urban Product Pending Im 466757-GO-RFQ / procure Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-0 IDA / D7320 ive Safety Net to Improve Post 38,647.00 0.00 plementati ment of protective safety tations l e Envelope 5 2 9 the Urban Environment on materials for public work b eneficiaries ET-OROMIA-GAFARSA GUJ Expand the Urban Product Pending Im E-466758-GO-RFQ / procur Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-0 IDA / D7320 ive Safety Net to Improve Post 14,673.00 0.00 plementati ement of protective safety tations l e Envelope 5 2 9 the Urban Environment on materials for public work b eneficiaries ET-OROMIA-SABATA-4667 Expand the Urban Product Pending Im 91-GO-RFQ / procurement Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-0 IDA / D7320 ive Safety Net to Improve Post 24,474.00 0.00 plementati of protective safety materi tations l e Envelope 5 2 9 the Urban Environment on als for public work benefici aries ET-OROMIA-GALAN GUDA- Expand the Urban Product Pending Im 466915-GO-RFQ / procure Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-1 2025-03-0 IDA / D7320 ive Safety Net to Improve Post 27,310.00 0.00 plementati ment of protective safety tations l e Envelope 5 9 6 the Urban Environment on materials for public work b eneficiaries ET-OROMIA-BURAYU-4694 Expand the Urban Product Pending Im 18-GO-RFQ / Procurement Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 12,273.00 0.00 plementati of Hand tools Materials for tations l e Envelope 8 5 2 the Urban Environment on public work beneficiaries ET-OROMIA-SABATA-4695 Expand the Urban Product Pending Im 21-GO-RFQ / Procurement Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 17,637.00 0.00 plementati of Hand tools Materials for tations l e Envelope 8 5 2 the Urban Environment on public work beneficiaries ET-OROMIA-MALKA NONO- Expand the Urban Product Pending Im 469523-GO-RFQ / procure Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 8,614.00 0.00 plementati ment of Hand tools Materi tations l e Envelope 8 5 2 the Urban Environment on als for public work benefici aries ET-OROMIA-GAFARSA GUJ Expand the Urban Product Pending Im E-469524-GO-RFQ / Procur Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 6,125.00 0.00 plementati ement of Hand tools Mater tations l e Envelope 8 5 2 the Urban Environment on ials for public work benefic iaries ET-OROMIA-JIMA-469525- Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-2 GO-RFQ / procurement of IDA / D7320 ive Safety Net to Improve Post 35,687.00 0.00 plementati tations l e Envelope 8 5 2 Hand tools Materials for pu the Urban Environment on blic work beneficiaries ET-OROMIA-AMBO-469527 Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 -GO-RFQ / procurement of IDA / D7320 ive Safety Net to Improve Post 8,709.00 0.00 plementati tations l e Envelope 8 5 7 Hand tools materials for p the Urban Environment on ublic work beneficiaries ET-OROMIA-AGARO-46967 Expand the Urban Product Pending Im 1-GO-RFQ / procurement o Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-2 IDA / D7320 ive Safety Net to Improve Post 12,231.00 0.00 plementati f Hand Tools materials for tations l e Envelope 8 5 2 the Urban Environment on public work beneficiaries ET-OROMIA-NEKEMTE-469 Expand the Urban Product Pending Im 673-GO-RFQ / procuremen Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-2 IDA / D7320 ive Safety Net to Improve Post 28,055.00 0.00 plementati t of Hand tools materials f tations l e Envelope 8 5 2 the Urban Environment on or public work beneficiarie s ET-OROMIA-SHAMBU-469 Expand the Urban Product Pending Im 674-GO-RFQ / procuremen Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-2 IDA / D7320 ive Safety Net to Improve Post 7,263.00 0.00 plementati t of Hand tools materials f tations l e Envelope 8 5 2 the Urban Environment on or public work beneficiarie s ET-OROMIA-DAMBI DOLO- Expand the Urban Product Pending Im 469675-GO-RFQ / Procure Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-2 IDA / D7320 ive Safety Net to Improve Post 6,419.00 0.00 plementati ment of Hand tools Materi tations l e Envelope 8 5 2 the Urban Environment on als for public work benefici aries ET-OROMIA-HOLOTA-4696 Expand the Urban Product Pending Im 76-GO-RFQ / procurement Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 6,726.00 0.00 plementati of Hand tools materials for tations l e Envelope 8 5 2 the Urban Environment on public work beneficiaries ET-OROMIA-ADAMA-46967 Expand the Urban Product Pending Im 7-GO-RFQ / Procurement o Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 24,909.00 0.00 plementati f Hand tools Materials for p tations l e Envelope 8 5 7 the Urban Environment on ublic work beneficiaries ET-OROMIA-BISHOFTU-46 Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 9681-GO-RFQ / procureme IDA / D7320 ive Safety Net to Improve Post 15,947.00 0.00 plementati tations l e Envelope 8 5 2 nt of Hand tools for public the Urban Environment on work beneficiaries ET-OROMIA-BATU-469684 Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post 14,028.00 0.00 plementati tations l e Envelope 8 5 7 Hand tools Materials for pu the Urban Environment on blic work beneficiaries ET-OROMIA-SHASHAMANE Expand the Urban Product Pending Im -469688-GO-RFQ / procure Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 36,699.00 0.00 plementati ment of Hand tools Materi tations l e Envelope 8 5 7 the Urban Environment on als for public work benefici aries ET-OROMIA-ROBE-469727 Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post 16,391.00 0.00 plementati tations l e Envelope 8 5 2 Hand Tools Materials for p the Urban Environment on ublic work beneficiaries ET-OROMIA-MAYA-469728 Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-2 -GO-RFQ / Procurement of IDA / E3010 ive Safety Net to Improve Post 5,295.00 0.00 plementati tations l e Envelope 8 5 2 Hand tools materials for p the Urban Environment on ublic work beneficiaries ET-OROMIA-BADESA-4697 Expand the Urban Product Pending Im 29-GO-RFQ / Procurement Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-2 IDA / E3010 ive Safety Net to Improve Post 5,117.00 0.00 plementati of Hand Tools Materials for tations l e Envelope 8 5 2 the Urban Environment on Public work beneficiaries ET-OROMIA-CHIRO-46973 Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 0-GO-RFQ / Procurement o IDA / D7320 ive Safety Net to Improve Post 13,593.00 0.00 plementati tations l e Envelope 8 5 7 f Hand tools materials for the Urban Environment on public work beneficiaries ET-OROMIA-YABELO-4697 Expand the Urban Product Pending Im 31-GO-RFQ / Procurement Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-2 IDA / D7320 ive Safety Net to Improve Post 7,763.00 0.00 plementati of Hand tools Materials for tations l e Envelope 8 5 2 the Urban Environment on public work beneficiaries ET-OROMIA-NEGELE ARSI- Expand the Urban Product Pending Im 469733-GO-RFQ / procure Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 20,840.00 0.00 plementati ment of Hand tools materi tations l e Envelope 8 5 7 the Urban Environment on als for public work benefici aries ET-OROMIA-KOYE FECHE- Expand the Urban Product Pending Im 469736-GO-RFQ / Procure Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 7,843.00 0.00 plementati ment of Hand tools materi tations l e Envelope 8 5 2 the Urban Environment on als for public work benefici aries Page 13 ET-OROMIA-FURI-469738- Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post 20,410.00 0.00 plementati tations l e Envelope 8 5 2 Hand Tools Materials for p the Urban Environment on ublic work beneficiaries ET-OROMIA-GALAN GUDA- Expand the Urban Product Pending Im 469740-GO-RFQ / Procure Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-1 IDA / D7320 ive Safety Net to Improve Post 11,886.00 0.00 plementati ment of Hand tools Materi tations l e Envelope 8 5 2 the Urban Environment on als for public work benefici aries ET-OROMIA-MATU-469741 Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-2 -GO-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post 6,063.00 0.00 plementati tations l e Envelope 8 5 2 Hand tools materials for p the Urban Environment on ublic work beneficiaries ET-OROMIA-GIMBI-469742 Expand the Urban Product Pending Im Request for Quo Limited - Nationa Single Stage - On 2025-01-1 2025-02-2 2025-03-2 -GO-RFQ / procurement of IDA / D7320 ive Safety Net to Improve Post 5,574.00 0.00 plementati tations l e Envelope 8 5 2 Hand tools materials for p the Urban Environment on ublic work beneficiaries NON CONSULTING SERVICES Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amou Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) nt (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-OROMIA-MATU-351497 -NC-RFQ / Procurement of Expand the Urban Product semi skilled labor for the c Request for Quo Single Stage - On 2023-04-0 2023-04-2 2023-05-1 2023-05-1 2023-08-1 2024-08-0 IDA / D7320 ive Safety Net to Improve Post Limited 5,100.00 0.00 Completed onstruction of one block sh tations e Envelope 4 6 9 9 7 9 the Urban Environment ade with three small sectio ns and construction of gre enery area fence & walkw ay ET-OROMIA-AMBO-391503 Expand the Urban Product -NC-RFQ / Procurement of Request for Quo Single Stage - On 2023-12-2 2024-04-1 2024-02-1 2024-05-1 2024-04-1 2024-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 13,999.00 0.00 Completed Semiskilled Lobar for Cons tations e Envelope 5 1 2 7 2 5 the Urban Environment truction of poultry farming shed ET-OROMIA-JIMA-391593- Expand the Urban Product NC-RFQ / Procurement of S Request for Quo Single Stage - On 2023-12-2 2024-03-1 2024-02-1 2024-04-1 2024-04-1 IDA / D7320 ive Safety Net to Improve Post Limited 27,177.00 0.00 Signed emiskilled Lobar For Const tations e Envelope 5 7 2 6 2 the Urban Environment ruction of Sheds for Poultr y Farming ET-OROMIA-SHAMBU-391 Expand the Urban Product 598-NC-RFQ / procurement Request for Quo Single Stage - On Under Impl 2024-01-1 2024-03-0 2024-05-0 IDA / D7320 ive Safety Net to Improve Post Limited 3,970.00 0.00 of Semiskilled Lobar to Co tations e Envelope ementation 0 4 3 the Urban Environment nstruction of Shed for poul try farming ET-OROMIA-BATU-391609 Expand the Urban Product -NC-RFQ / Procurement Se Request for Quo Single Stage - On 2023-12-2 2024-03-3 2024-02-0 2024-05-2 2024-03-0 2024-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 15,446.00 0.00 Completed miskilled for Construction tations e Envelope 0 0 7 9 8 3 the Urban Environment of Shed and additional Cla ss room for school ET-OROMIA-YABELO-3916 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-02-2 2024-01-2 2024-04-0 2024-03-2 2024-07-0 27-NC-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 6,280.00 0.00 Completed tations e Envelope 2 3 9 5 9 4 of semiskilled for Construc the Urban Environment tion of Shed ET-OROMIA-DAMBIDOLO-3 Expand the Urban Product Request for Quo Single Stage - On Under Impl 2024-01-0 2024-02-2 2024-04-2 91640-NC-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post Limited 9,626.00 0.00 tations e Envelope ementation 8 6 6 ent of Semiskilled for Cons the Urban Environment truction of Sheds ET-OROMIA-NEKEMTE-391 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-02-2 2024-01-2 2024-04-0 2024-03-2 743-NC-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 17,007.00 0.00 Signed tations e Envelope 2 9 9 3 9 Semiskilled Lobar for Cons the Urban Environment truction of Shed ET-OROMIA-GIMBI-391828 Expand the Urban Product Request for Quo Single Stage - On Under Impl 2023-12-1 2024-01-2 2024-03-2 -NC-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 16,202.00 0.00 tations e Envelope ementation 3 5 5 Semiskilled Lobar the Urban Environment ET-OROMIA-BEDELE-3918 Expand the Urban Product 39-NC-RFQ / Procurement Request for Quo Single Stage - On 2024-01-0 2024-02-1 2024-04-1 IDA / D7320 ive Safety Net to Improve Post Limited 4,488.00 0.00 Canceled of Skilled labor for the Con tations e Envelope 8 9 9 the Urban Environment struction of Shade in Block for poultry production ET-OROMIA-BULEHORA-39 Expand the Urban Product 1875-NC-RFQ / Procureme Request for Quo Single Stage - On 2023-12-1 2024-04-1 2024-01-3 2024-05-1 2024-03-3 IDA / D7320 ive Safety Net to Improve Post Limited 19,804.00 0.00 Signed nt of Skill Lobar for Constr tations e Envelope 2 5 0 3 0 the Urban Environment uction of Shed , Fence and School ET-OROMIA-WALISO-3918 Expand the Urban Product 85-NC-RFQ / Procurement Request for Quo Single Stage - On 2023-12-1 2024-03-2 2024-01-2 2024-05-1 2024-03-2 2024-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 13,381.00 0.00 Completed of Skilled Labor for the con tations e Envelope 2 1 9 7 9 8 the Urban Environment struction of shade in block ET-OROMIA-ROBE-391960 Expand the Urban Product Request for Quo Single Stage - On 2023-12-1 2024-04-2 2024-01-2 2024-05-1 2024-03-2 2024-07-0 -NC-RFQ / Procurement Ski IDA / D7320 ive Safety Net to Improve Post Limited 25,564.00 0.00 Completed tations e Envelope 2 4 9 3 9 5 lled Lobar for Construction the Urban Environment of Shed ET-OROMIA-MATU-392003 Expand the Urban Product -NC-RFQ / Procurement Ski Request for Quo Single Stage - On 2024-01-0 2024-01-2 2024-02-2 2024-02-2 2024-05-2 IDA / D7320 ive Safety Net to Improve Post Limited 10,442.00 0.00 Signed lled labor for Construction tations e Envelope 9 6 7 1 7 the Urban Environment shade and drainage line ET-OROMIA-AGARO-39206 Expand the Urban Product 2-NC-RFQ / Procurement of Request for Quo Single Stage - On 2024-01-1 2024-01-1 2024-03-1 2024-02-2 2024-05-1 2024-05-1 IDA / D7320 ive Safety Net to Improve Post Limited 15,073.00 0.00 Completed Labor skill For Constructio tations e Envelope 5 1 1 8 0 0 the Urban Environment n of Shade for Poultry prod uction ET-OROMIA-NAGELE BORA Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-02-2 2024-03-0 2024-03-1 2024-04-0 2024-05-1 NA-392091-NC-RFQ / Procu IDA / D7320 ive Safety Net to Improve Post Limited 18,051.00 0.00 Completed tations e Envelope 5 8 4 9 3 4 rement of Skilled Lobar the Urban Environment ET-OROMIA-FICHE-392219 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-04-0 2024-02-2 2024-05-2 2024-04-2 2024-07-0 -NC-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 17,614.00 0.00 Completed tations e Envelope 4 2 2 4 2 5 Skilled Labor for Constructi the Urban Environment on of shade ET-OROMIA-CHIRO-39231 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-03-0 2024-02-2 2024-03-2 2024-04-2 2024-07-0 8-NC-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 9,057.00 0.00 Completed tations e Envelope 9 1 3 7 3 5 Skilled Labor for the Const the Urban Environment ruction of shade ET-OROMIA-NAGELE ARSI- Expand the Urban Product Request for Quo Single Stage - On Under Impl 2024-01-0 2024-02-2 2024-03-2 392349-NC-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 38,460.00 0.00 tations e Envelope ementation 9 7 8 ment of Skilled Lobar for the Urban Environment Construction of Sheds ET-OROMIA-ADAMA-39280 Expand the Urban Product 9-NC-RFQ / Procurement of Request for Quo Single Stage - On 2024-01-0 2024-04-1 2024-02-2 2024-05-1 2024-04-2 IDA / D7320 ive Safety Net to Improve Post Limited 48,013.00 0.00 Terminated Skilled Lobar for Constructi tations e Envelope 9 6 6 3 6 the Urban Environment on of Shed, Fence and Cal vert ET-OROMIA-GINCHI-39306 Expand the Urban Product Request for Quo Single Stage - On 2023-11-2 2024-02-2 2024-01-1 2024-03-2 2024-03-1 9-NC-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 3,818.00 0.00 Signed tations e Envelope 7 6 5 2 5 Skilled Lobar for Constructi the Urban Environment on of Shed ET-OROMIA-MAKI-393095- Expand the Urban Product Request for Quo Single Stage - On 2024-01-2 2024-03-1 2024-03-1 2024-03-2 2024-05-1 2024-05-2 NC-RFQ / Procurement of S IDA / D7320 ive Safety Net to Improve Post Limited 6,873.00 0.00 Completed tations e Envelope 2 9 8 9 7 0 killed Lobar for Constructio the Urban Environment n of Public Toilet ET-OROMIA-MAYA-393179 Expand the Urban Product -NC-RFQ / Procurement of Request for Quo Single Stage - On 2024-01-0 2023-12-2 2024-02-1 2024-02-0 2024-04-1 2024-07-0 IDA / D7320 ive Safety Net to Improve Post Limited 24,339.00 0.00 Completed Skilled Lobar for constructi tations e Envelope 2 8 9 5 9 5 the Urban Environment on of Shed, Fence and Pub lic Toilet ET-OROMIA-BADESA-3935 Expand the Urban Product Request for Quo Single Stage - On 2024-01-1 2024-02-1 2024-02-2 2024-06-1 2024-04-1 2024-08-0 02-NC-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post Limited 4,484.00 0.00 Completed tations e Envelope 5 2 6 2 1 6 of Skilled lobar for Constru the Urban Environment ction of Fence ET-OROMIA-DERA-393525 Expand the Urban Product Request for Quo Single Stage - On 2024-01-0 2024-05-3 2024-02-1 2024-06-0 2024-04-1 2024-07-0 -NC-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 3,589.00 0.00 Completed tations e Envelope 2 0 9 3 9 3 Skilled Lobar for Constructi the Urban Environment on of Sheds ET-OROMIA-ASALA-39354 Expand the Urban Product Request for Quo Single Stage - On 2023-12-2 2024-03-2 2024-02-1 2024-04-2 2024-04-1 1-NC-RFQ / Procurement of IDA / D7320 ive Safety Net to Improve Post Limited 17,944.00 0.00 Signed tations e Envelope 6 6 2 2 2 skilled Lobar for Constructi the Urban Environment on of Shed ET-OROMIA-SHASHAMANE Expand the Urban Product Request for Quo Single Stage - On 2024-01-2 2024-03-1 2024-03-2 2024-05-1 2024-05-2 2024-07-0 -392167-NC-RFQ / Procure IDA / D7320 ive Safety Net to Improve Post Limited 34,072.00 0.00 Completed tations e Envelope 9 8 5 5 4 5 ment of Skilled Lobar the Urban Environment ET-OROMIA-BISHOFTU-39 Expand the Urban Product Request for Quo Single Stage - On 2024-01-2 2024-03-1 2024-03-1 2024-05-2 2024-05-1 2024-07-0 3619-NC-RFQ / Procureme IDA / D7320 ive Safety Net to Improve Post Limited 54,153.00 0.00 Completed tations e Envelope 9 9 1 0 0 5 nt of Skilled Lobar for Cons the Urban Environment truction of Shed ET-OROMIA-SABATA-4173 Expand the Urban Product 27-NC-RFQ / Procurement Request for Quo Limited - Nationa Single Stage - On 2024-04-2 2024-05-3 2024-05-2 2024-07-0 2024-07-2 IDA / D7320 ive Safety Net to Improve Post 5,383.00 0.00 Signed of Skill Labor Cost for Cons tations l e Envelope 2 0 7 3 6 the Urban Environment truction of Public Toilet Co nstruction ET-OROMIA-BURAYU-4175 Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On Under Impl 2024-04-1 2024-05-2 2024-05-2 2024-06-2 07-NC-RFQ / Procurement IDA / D7320 ive Safety Net to Improve Post 15,308.00 0.00 tations l e Envelope ementation 5 7 7 6 of Skill Labor for constructi the Urban Environment on of sheds ET-OROMIA-MALKA NON-4 Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-05-2 2024-07-1 17536-NC-RFQ / Procurem IDA / D7320 ive Safety Net to Improve Post 3,589.00 0.00 Canceled tations l e Envelope 5 0 9 ent skilled Labor Cost for C the Urban Environment ontraction of Shed ET-OROMIA-GAFARSA GUJ Expand the Urban Product Request for Quo Limited - Nationa Single Stage - On 2024-04-1 2024-05-2 2024-07-2 E-417550-NC-RFQ / Procur IDA / D7320 ive Safety Net to Improve Post 7,177.00 0.00 Canceled tations l e Envelope 6 1 0 ement of Skilled Labor the Urban Environment CONSULTING FIRMS Activity Reference No. Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Intere Request for Proposa Opening of Technica Evaluation of Techn / Description Component Review Type Method Terms of Reference Request for Proposa n Report and Draft Signed Contract Contract Completion No. ch ount (US$) nt (US$) s st Notice ls as Issued l Proposals / Minutes ical Proposal ls Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. Invitation to Identifi Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co / Description Component Review Type Method Terms of Reference ed/Selected Consult Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract ant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-OROMIA-UDHB-248184 Institutional Strengthenin -CS-INDV / Recruitment of i g, Project Management an Individual Cons 2021-09-0 2023-01-1 2021-10-1 2023-04-1 2021-10-2 2023-04-2 2021-11-2 2023-04-2 2022-11-2 ndividual consultant/ Publi IDA / D7320 Post Open 5,400.00 0.00 Signed d Monitoring and Evaluati ultant Selection 8 0 2 3 7 5 1 5 1 c work specialist with abilit on y to handle livelihood for O romia Regional Hub ET-OROMIA-UDHB-248186 Institutional Strengthenin -CS-INDV / Recruitment of i g, Project Management an Individual Cons 2021-09-0 2023-01-1 2021-10-1 2023-04-1 2021-10-2 2023-04-2 2021-11-2 2023-04-2 2022-11-2 IDA / D7320 Post Open 5,300.00 0.00 Signed ndividual consultant/ safeg d Monitoring and Evaluati ultant Selection 8 0 2 3 7 5 1 5 1 uard specialist for Oromya on regional Hub ET-OROMIA-UDHB-316304 Institutional Strengthenin Individual Cons 2022-09-2 2023-01-1 2022-10-2 2023-04-1 2022-11-1 2023-04-1 2022-11-2 2023-04-2 2023-11-2 -CS-INDV / Recruit Gender IDA / D7320 g, Project Management an Post Open - National 5,000.00 0.00 Terminated ultant Selection 2 0 6 3 0 3 7 5 7 Specialist for Oromya Regi d Monitoring and Evaluati onal Hub on ET-OROMIA-UDHB-316307 -CS-INDV / Recruit Youth E Foster Urban Youth Emplo Individual Cons 2022-09-2 2023-01-1 2022-10-2 2023-04-2 2022-11-1 2023-04-2 2022-11-2 2023-04-2 2023-11-2 2023-10-1 IDA / D7320 Post Open - National 5,000.00 0.00 Completed mployment apprenticeship yment ultant Selection 2 0 6 7 0 0 7 9 7 0 specialist for Adama city ET-OROMIA-UDHB-316310 -CS-INDV / Recruit Youth E Foster Urban Youth Emplo Individual Cons Under Impleme 2022-09-2 2023-01-1 2022-10-2 2022-11-1 2022-11-2 2023-12-0 IDA / D7320 Post Open - National 500.00 0.00 mployment apprenticeship yment ultant Selection ntation 2 0 6 0 7 8 specialist for Shashemene city ET-OROMIA-UDHB-316314 -CS-INDV / Recruit Youth E Foster Urban Youth Emplo Individual Cons Under Impleme 2022-09-2 2023-01-1 2022-10-2 2022-11-1 2022-11-2 2023-11-2 IDA / D7320 Post Open - National 5,000.00 0.00 mployment apprenticeship yment ultant Selection ntation 2 0 6 0 7 7 specialist for Jimma city ET-OROMIA-UDHB-316317 Institutional Strengthenin -CS-INDV / Recruitment of g, Project Management an Individual Cons 2022-09-2 2023-01-1 2022-09-2 2023-02-1 2022-10-1 2023-04-1 2022-10-2 2023-04-2 2023-10-2 2024-04-0 IDA / D7320 Post Limited 6,000.00 0.00 Signed procurement specialist 2 f d Monitoring and Evaluati ultant Selection 2 0 7 3 2 3 9 5 9 1 or Oromya Regional Hub on ET-OROMIA-OJCVB-40848 6-CS-INDV / Recruit Youth Foster Urban Youth Emplo Individual Cons Under Impleme 2024-03-2 2024-05-3 2024-04-2 2024-04-2 2024-05-1 2025-05-1 IDA / D7320 Post Open - National 3,876.00 0.00 Employment apprenticeshi yment ultant Selection ntation 2 0 2 9 3 3 p specialist for Adama City ET-OROMIA-UDHB-426085 Expand the Urban Product Individual Cons Limited - Nationa Under Impleme 2024-05-1 2024-07-2 2024-05-2 2024-08-0 2024-06-0 2024-12-1 2024-06-2 2025-06-2 -CS-INDV / Recruitment of IDA / D7320 ive Safety Net to Improve Prior 5,000.00 0.00 ultant Selection l ntation 5 4 0 7 3 9 0 0 1 Procurement Specialist the Urban Environment ET-OROMIA-UDHB-437479 -CS-INDV / Recruitment of Expand the Urban Product Individual Cons Under Impleme 2024-07-2 2024-07-2 2024-09-0 2024-09-1 2024-10-1 2025-10-1 Monitoring and Evaluation IDA / D7320 ive Safety Net to Improve Post Open - National 5,100.00 0.00 ultant Selection ntation 6 6 9 9 0 0 Specialist for Oromia Housi the Urban Environment ng and Urban Developmen t Bureau(Regional UPSNJP HUB) ET-OROMIA-UDHB-444515 Institutional Strengthenin Individual Cons Limited - Nationa Under Impleme 2024-08-1 2024-09-1 2024-08-2 2024-08-3 2024-09-1 2025-09-1 -CS-INDV / Recruitment of IDA / D7320 g, Project Management an Post 5,000.00 0.00 ultant Selection l ntation 6 6 3 0 3 3 1 Gender Specialist for Oro d Monitoring and Evaluati mia Regional Hub on Page 14