PROCUREMENT PLAN (Textual Part) Project information: [ETHIOPIA] [ETHIOPIA FLOOD MANAGEMENT PROJECT] [P176327] Project Implementation agency: [MINISTRY OF WATER AND ENERGY, ETHIOPIA DISASTER RISK MANAGEMENT COMMISSION, ETHIOPIA METEROLOGY INSTITUTE] Date of the Procurement Plan: [29 JUNE 2023] Period covered by this Procurement Plan: [29 JUNE 2023-29 DECEMBER 2024] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in THE FEDERAL GOVERNMENT’S PROCUREMNET PROCEDURES such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is applicable for those contracts identified in the Procurement Plan tables]; Works: [is applicable for those contracts identified in the Procurement Plan tables] PROCUREMENT Ethiopia : Ethiopia Flood Management Project PLAN General Information Country: Ethiopia 2023-06-29 Bank’s Approval Date of the Original Procurement Plan: 2025-01-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176327 GPN Date: 2023-06-29 Project Name: Ethiopia Flood Management Project Loan / Credit No: IDA / E1240 Ministry of Water and Energy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-MOWE-427000-CW-RFB / Procurement of Awash River Request for Bids - bed dredging/widening and r Component 2: Accelerating f Single Stage - One E Small Works SPD 2024-09-2 IDA / E1240 Post Request for Bids Limited - National 1,500,000.00 0.00 Signed 2024-05-20 2024-05-24 2024-05-22 2024-05-24 2024-06-06 2024-06-07 2024-06-11 2024-06-17 2024-06-27 2024-06-27 elated works in lower Awash lood risk management nvelope (1 envelope proce 5 - Asayta and Afambo woreda ss) s under fast track approach b efore the flood period ET-MOWE-426994-CW-RFB / Procurement of Awash River Request for Bids - bed dredging/widening and r Component 2: Accelerating f Single Stage - One E Small Works SPD 2024-09-2 elated works in Upper Awash IDA / E1240 Post Request for Bids Limited - National 3,950,000.00 0.00 Signed 2024-05-20 2024-05-24 2024-05-22 2024-05-24 2024-06-06 2024-06-05 2024-06-11 2024-06-11 2024-06-27 2024-06-27 lood risk management nvelope (1 envelope proce 5 - Illu, Ejire, Sebeta Hawas, Da ss) wo, Ejeresa lefo, Bora and Lib en Chikala woredas under fas t track approach before the fl ood period ET-MOWE-426999-CW-RFB / Procurement of River bed dr Request for Bids - edging/widening and related Component 2: Accelerating f Single Stage - One E Small Works SPD 2024-09-2 works in Middle Awash - Ami IDA / E1240 Post Request for Bids Limited - National 2,000,000.00 0.00 Signed 2024-05-20 2024-05-24 2024-05-22 2024-05-24 2024-06-06 2024-06-07 2024-06-11 2024-06-17 2024-06-27 2024-06-27 lood risk management nvelope (1 envelope proce 5 bara, Dulessa, Gewane and G ss) elehalo woredas under fast tr ack approach before the floo d period ET-MOWE-469044-CW-RFB / Procurement of Rift valley ch Request for Bids - annel widening, detention po Component 2: Accelerating f Single Stage - One E Small Works SPD Pending Imp 2025-06-1 nd, crossing and related wor IDA / E1240 Post Request for Bids Open - National 2,000,000.00 0.00 2025-01-08 2025-01-13 2025-02-12 2025-02-22 2025-03-13 lood risk management nvelope (1 envelope proce lementation 1 ks in three different sites of K ss) ulifo, Boyo & Goflala rivers of Rift valley basin under fast tr ack approach before the floo d period in lots National Procure ET-MOWE-469047-CW-RFB / Component 4: Project mana ment Document - Procurement of new office Re Single Stage - One E Pending Imp 2025-05-2 IDA / E1240 gement and implementation Post Request for Bids Open - National 1 Envelope proce 270,000.00 0.00 2025-01-17 2025-01-22 2025-02-21 2025-03-03 2025-03-22 novation Works for Ethiopia F nvelope lementation 1 support ss (Non Bank-SPD lood Management Project - P ) MU office of MoWE GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWE-371389-GO-RFQ / Procurement of office equip Component 4: Project mana Request for Quota Single Stage - One E ment (computers, printers, la IDA / E1240 gement and implementation Post Limited 100,000.00 0.00 Signed 2023-08-16 2023-12-07 2023-09-07 2024-01-10 2023-09-22 tions nvelope ptops, accessories etc.) for Et support hiopian Flood Management P roject PMU staff ET-MOWE-386233-GO-RFQ / Component 4: Project mana Request for Quota Single Stage - One E Procurement of Office Furnitu IDA / E1240 gement and implementation Post Limited - National 100,000.00 0.00 Signed 2024-03-05 2024-05-02 2024-04-30 2024-08-05 2024-10-27 tions nvelope re (Tables, Chairs, Shelves) support ET-MOWE-393999-GO-RFB / Component 4: Project mana Procurement of 12 Field Vehi Single Stage - One E Under Imple IDA / E1240 gement and implementation Post Request for Bids Open - National 870,530.00 0.00 2024-02-29 2024-08-23 2024-03-07 2024-04-06 2024-04-16 2024-05-10 2024-11-06 cles(Double Cabin Pick-up an nvelope mentation support d Land cruiser ) for MOWE Pr ojects Supervision ET-MOWE-394000-GO-RFB / Component 4: Project mana Single Stage - One E Under Imple IDA / E1240 Post Request for Bids Open - National 150,000.00 0.00 2024-02-29 2024-08-23 2024-03-10 2024-04-09 2024-04-19 2024-05-13 2024-11-09 Procurement of Mini Mounted gement and implementation nvelope mentation Crane support ET-MOWE-394001-GO-RFB / Component 4: Project mana Request for Quota Single Stage - One E Under Imple Procurement of Motor Bikes f IDA / E1240 gement and implementation Post Limited - National 74,375.00 0.00 2024-03-15 2024-05-19 2024-06-18 tions nvelope mentation or MOWE Projects Supervisio support n ET-MOWE-469057-GO-RFQ / Component 4: Project mana Request for Quota Single Stage - One E Pending Impl Procurement of stationary & IDA / E1240 gement and implementation Post Open - National 25,000.00 0.00 2025-01-18 2025-03-06 2025-04-05 tions nvelope ementation toners for E-FMP project staff support s of MoWE ET-MOWE-469064-GO-RFQ / Procurement of Mobile devic Component 2: Accelerating f Request for Quota Single Stage - One E Pending Impl IDA / E1240 Post Limited - National 50,000.00 0.00 2025-01-18 2025-02-27 2025-03-29 e and application software an lood risk management tions nvelope ementation d installation for mobiles use d for data collection ET-MOWE-469049-GO-RFB / Procurement of 40 Motor Bik Component 4: Project mana es for FMP Project hydro-met Single Stage - One E Pending Impl IDA / E1240 gement and implementation Post Request for Bids Open - National 170,000.00 0.00 2025-01-17 2025-01-22 2025-02-21 2025-03-08 2025-03-27 2025-06-25 station field observers and Pr nvelope ementation support oject focal persons at basin o ffices and data collection site s of MoWE ET-MOWE-469053-GO-RFB / Procurement of Office Equip Component 4: Project mana Single Stage - One E Pending Impl ment (Computer, printer, Lap IDA / E1240 gement and implementation Post Request for Bids Open - National 100,000.00 0.00 2025-01-17 2025-01-22 2025-02-21 2025-03-03 2025-03-22 2025-04-21 nvelope ementation top, tablets, Hard Disk, Acces support sories etc) for new employed project staffs NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWE-368687-CS-QCBS / Consultancy service fo Basi n level study for Awash basin to identify and prioritize phys Component 2: Accelerating f Quality And Cost- Open - Internationa Under Implement IDA / E1240 Prior 500,000.00 0.00 2023-06-24 2023-07-20 2023-07-15 2023-08-24 2023-08-28 2024-04-30 2023-09-25 2024-06-27 2023-10-25 2023-11-29 2024-01-03 2025-01-02 ical flood risk reduction inves lood risk management Based Selection l ation tments and conceptual desi gn, detailed design, bidding document of selected physic al investments (not including supervision ) ET-MOWE-410329-CS-QCBS / Consultancy service for Basi n level study for Rift valley t o identify and prioritise physi Component 2: Accelerating f Quality And Cost- Open - Internationa Under Implement IDA / E1240 Post 450,000.00 0.00 2024-02-29 2024-04-09 2024-03-25 2024-09-16 2024-05-08 2024-06-07 2024-06-27 2024-07-26 2024-08-24 2025-08-24 cal flood risk reduction invest lood risk management Based Selection l ation ments and conceptual desig n, detailed design, bidding d ocument of selected physical investments (not including su pervision ) ET-MOWE-410332-CS-QCBS / Consultancy service for Basi n level study for Omo to ide ntify and prioritise physical fl Component 2: Accelerating f Quality And Cost- Open - Internationa Under Implement ood risk reduction investmen IDA / E1240 Post 450,000.00 0.00 2024-02-29 2024-09-04 2024-03-21 2024-09-16 2024-05-04 2024-06-03 2024-06-23 2024-07-28 2024-09-01 2025-09-01 lood risk management Based Selection l ation ts and conceptual design, de tailed design, bidding docum ent of selected physical inves tments (not including supervi sion of civil work) ET-MOWE-411804-CS-QCBS / Consultancy Service for Bas in level study for strategic st udy basins to identify and pri Component 2: Accelerating f Quality And Cost- Open - Internationa Pending Impleme IDA / E1240 Prior 1,000,000.00 0.00 2024-02-29 2024-03-21 2024-05-04 2024-06-03 2024-07-03 2024-08-07 2024-09-11 2025-07-08 oritise physical flood risk red lood risk management Based Selection l ntation uction investments, and feasi bility study for prioritized inv estments (2 basins-Abay and Baro-Akobo) ET-MOWE-411805-CS-QCBS / Consultancy service for Dia Component 2: Accelerating f Quality And Cost- Open - Internationa Pending Impleme IDA / E1240 Post 450,000.00 0.00 2024-02-29 2024-03-21 2024-05-04 2024-06-03 2024-07-03 2024-08-07 2024-09-11 2025-07-08 gnostic of urban flood risk st lood risk management Based Selection l ntation atus and management at the country level ET-MOWE-411802-CS-QCBS / Consultancy service for Des igning flash flood forecasting & early warning system for A Component 2: Accelerating f Quality And Cost- Open - Internationa Pending Impleme wash, Wabishebele, Omo-Gib IDA / E1240 Prior 1,280,000.00 0.00 2024-05-20 2024-06-14 2024-07-28 2024-08-27 2024-09-26 2024-10-31 2024-12-06 2025-12-06 lood risk management Based Selection l ntation e, RVL & Genale dawa & syst em installation for selected a reas in priority basins & Rese arch based Operation of flash flood system & application ET-MOWE-411801-CS-QCBS / Consultancy services for De velopment of impact based fl ood forecasting & early warni Component 2: Accelerating f Quality And Cost- Open - Internationa Pending Impleme IDA / E1240 Prior 1,200,000.00 0.00 2024-05-20 2024-06-14 2024-07-28 2024-08-27 2024-09-26 2024-10-31 2024-12-05 2025-12-05 ng system for Awash, Omo, lood risk management Based Selection l ntation & Rift Valley Developing IBF system based on WMO guidel ine to minimize impacts inclu ding effective use radar prod ucts ET-MOWE-426982-CS-CQS / Component 4: Project mana Consultancy service for prep Consultant Qualifi Pending Impleme IDA / E1240 gement and implementation Post Limited - National 100,000.00 0.00 2024-05-26 2024-06-20 2024-07-05 2024-08-03 2024-11-01 aration of baseline document cation Selection ntation support for monitoring and evaluatio n of the project ET-MOWE-427001-CS-CQS / Consultancy service for Supe rvision of Awash River bed dr edging/widening and related Component 2: Accelerating f Consultant Qualifi IDA / E1240 Post Limited - National 50,000.00 0.00 Signed 2024-05-20 2024-05-31 2024-06-10 2024-06-18 2024-06-15 2024-06-28 2024-07-02 2024-07-01 2024-09-30 works in Upper Awash - Illu, E lood risk management cation Selection jire, Sebeta Hawas, Dawo, Ej eresa lefo, Bora and Liben Ch ikala woredas under fast trac k approach before the flood p eriod ET-MOWE-427003-CS-CQS / Consultancy service for Supe rvision of Awash River bed dr edging/widening and related Component 2: Accelerating f Consultant Qualifi IDA / E1240 Post Limited - National 80,000.00 0.00 Signed 2024-05-20 2024-05-26 2024-06-10 2024-06-18 2024-06-15 2024-06-24 2024-07-02 2024-07-01 2024-09-30 works in Middle & Lower Awa lood risk management cation Selection sh - Amibara, Dulessa, Gewa ne and Gelehalo woredas un der fast track approach befor e the flood period ET-MOWE-426979-CS-QCBS / Selection and Employment of Independent procurement Component 4: Project mana Quality And Cost- Open - Internationa Audit service for three years IDA / E1240 gement and implementation Prior 200,000.00 0.00 Under Review 2024-10-07 2024-12-02 2024-10-28 2024-12-11 2025-01-08 2025-02-07 2025-03-14 2025-04-18 2028-04-17 Based Selection l procurement Audit (2016-20 support 18 Ethiopian Physical years) f or Ethiopia Flood Manageme nt Project (E-FMP) (P-176327) ET-MOWE-441375-CS-QCBS / Consultancy services for est ablishment of integrated hyd rology early warning data sh Component 2: Accelerating f Quality And Cost- Open - Internationa Pending Impleme aring, development of of pilo IDA / E1240 Post 450,000.00 0.00 2024-10-21 2024-11-11 2024-12-25 2025-01-22 2025-02-21 2025-03-28 2025-05-02 2025-12-28 lood risk management Based Selection l ntation t models & information produ cts for selected top priority h ydrological services(Omo-Gib e, Awash & rift valley) and de velopment of web portal ET-MOWE-464553-CS-CQS / Consultant Services for Sedi Component 2: Accelerating f Consultant Qualifi Pending Impleme IDA / E1240 Post Limited - National 75,000.00 0.00 2025-01-03 2025-01-17 2025-02-01 2025-02-20 2025-03-22 ment Sampling and Soil Testi lood risk management cation Selection ntation ng for Rift valley basin dredgi ng works ET-MOWE-469062-CS-CQS / Consultant Service for Enviro nmental and Social impact as Component 2: Accelerating f Consultant Qualifi Pending Impleme IDA / E1240 Post Open - National 180,000.00 0.00 2025-01-17 2025-02-07 2025-03-25 2025-04-09 2025-05-03 2025-08-01 sessment (ESIA) Study for flo lood risk management cation Selection ntation od protection infrastructure c ivil works of (Awash, Omo, an d Rift Valley Lakes) Page 2 ET-MOWE-469060-CS-CQS / Consultancy service for Supe rvision & design review of Rif t valley channel widening, de Component 2: Accelerating f Consultant Qualifi Pending Impleme IDA / E1240 Post Open - National 120,000.00 0.00 2025-01-14 2025-02-03 2025-03-15 2025-03-25 2025-04-13 2025-07-12 tention pond, crossing & rela lood risk management cation Selection ntation ted works in three different si tes of Kulifo, Boyo & Goflala r ivers of Rift valley basin unde r fast track approach before t he flood period ET-MOWE-464549-CS-CQS / Consultancy service for desig n review and draft bidding do cument preparation of Civil w Component 2: Accelerating f Consultant Qualifi Pending Impleme orks for three permanent div IDA / E1240 Post Limited - National 140,000.00 0.00 2025-01-17 2025-02-16 2025-03-09 2025-03-28 2025-05-27 lood risk management cation Selection ntation ersion head-works at (Nura H ira boset woreda, Abadir wor eda & Amibara Woreda) and gated side spillway on Gewa ne woreda of Awash basin INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWE-371959-CS-INDV / Selection and Employment of Component 4: Project mana Individual Consult individual Consultant for sec IDA / E1240 gement and implementation Post Limited 9,999.00 0.00 Signed 2023-07-20 2023-08-03 2023-08-04 2023-08-31 2023-08-14 2023-11-02 2023-08-24 2023-10-30 2023-09-23 ant Selection urity risk assessment study f support or the Ethiopia Flood Manage ment Project by MoWE ET-MOWE-371953-CS-INDV / Component 4: Project mana Selection and Employment of Individual Consult IDA / E1240 gement and implementation Post Open - National 28,000.00 0.00 Signed 2023-08-11 2023-10-15 2023-09-15 2023-12-13 2023-09-20 2023-12-30 2023-09-30 2024-01-16 2024-09-29 Social Specialist for the EFM- ant Selection support Project Management Unit (P MU) of MoWE ET-MOWE-371952-CS-INDV / Selection and Employment of Component 4: Project mana Individual Consult Financial Management speci IDA / E1240 gement and implementation Post Open - National 28,000.00 0.00 Signed 2023-08-11 2023-09-23 2023-09-15 2024-01-19 2023-09-20 2024-01-26 2023-09-30 2024-02-05 2024-09-29 ant Selection alist for the EFM-Project Man support agement Unit (PMU) of MoWE ET-MOWE-371921-CS-INDV / Selection and Employment of Component 4: Project mana Individual Consult Environmental specialist for t IDA / E1240 gement and implementation Post Open - National 28,000.00 0.00 Signed 2023-08-11 2023-10-08 2023-09-15 2023-12-13 2023-09-20 2023-12-28 2023-09-30 2024-01-16 2024-09-29 ant Selection he EFM-Project Management support Unit (PMU) of MoWE ET-MOWE-371946-CS-INDV / Selection and Employment of Component 4: Project mana Individual Consult Monitoring, Evaluation and re IDA / E1240 gement and implementation Post Open - National 28,000.00 0.00 Signed 2023-08-11 2023-10-08 2023-09-15 2023-12-13 2023-09-20 2023-12-29 2023-09-30 2024-01-16 2024-09-29 ant Selection porting officer for the EFM-Pr support oject Management Unit (PMU ) of MoWE ET-MOWE-371917-CS-INDV / Selection and Employment of Component 4: Project mana Individual Consult individual Consultant of Proc IDA / E1240 gement and implementation Prior Direct - National 28,000.00 0.00 Signed 2023-08-11 2023-10-12 2023-08-21 2023-11-22 2023-08-31 2024-01-03 2023-09-10 2024-01-11 2024-09-09 ant Selection urement specialist for the EF support M-Project Management Unit ( PMU) of MoWE ET-MOWE-371947-CS-INDV / Component 4: Project mana Selection and Employment of Individual Consult IDA / E1240 gement and implementation Post Open - National 28,000.00 0.00 Signed 2023-08-11 2023-10-15 2023-09-15 2023-12-13 2023-09-20 2023-12-29 2023-09-30 2024-01-19 2024-09-29 Senior Hydrologist for the EF ant Selection support M-Project Management Unit ( PMU) of MoWE ET-MOWE-371951-CS-INDV / Selection and Employment of Component 4: Project mana Individual Consult Under Implement Contract Management Specia IDA / E1240 gement and implementation Prior Open - National 28,000.00 0.00 2023-09-19 2023-09-28 2023-10-24 2023-10-31 2023-11-29 2024-11-28 ant Selection ation list for the EFM-Project Mana support gement Unit (PMU) of MoWE ET-MOWE-410334-CS-INDV / Component 4: Project mana Selection and Employment of Individual Consult Under Implement IDA / E1240 gement and implementation Post Open - National 28,000.00 0.00 2024-02-29 2024-04-12 2024-04-13 2024-05-04 2024-06-08 2025-06-08 Procurement specialist for th ant Selection ation support e FMP of MoWE ET-MOWE-410335-CS-INDV / Component 4: Project mana Selection and Employment of Individual Consult Under Implement IDA / E1240 gement and implementation Post Open - National 30,000.00 0.00 2024-02-29 2024-04-12 2024-04-13 2024-05-04 2024-06-08 2025-06-08 Senior Flood Risk Manageme ant Selection ation support nt Technical Team Leader for the FMP of MoWE ET-MOWE-410339-CS-INDV / Component 4: Project mana Selection and Employment of Individual Consult Under Implement IDA / E1240 gement and implementation Post Limited - National 28,000.00 0.00 2024-02-29 2024-04-12 2024-03-15 2024-04-05 2024-05-10 2024-06-15 Financial Management speci ant Selection ation support alist for the FMP of MoWE ET-MOWE-411315-CS-INDV / Component 4: Project mana Individual Consult Under Implement Contract staff hiring for key t IDA / E1240 gement and implementation Post Open - National 12,000.00 0.00 2024-02-29 2024-04-12 2024-04-04 2024-04-09 2024-04-24 2025-04-24 ant Selection ation he position of Embankment E support ngineer ET-MOWE-411362-CS-INDV / Component 4: Project mana Individual Consult Under Implement Contract staff hiring for key t IDA / E1240 gement and implementation Post Open - National 10,000.00 0.00 2024-02-29 2024-04-12 2024-04-04 2024-04-09 2024-04-24 2025-04-24 ant Selection ation he position of Communicatio support n specialist ET-MOWE-411365-CS-INDV / Component 4: Project mana Individual Consult Under Implement Contract staff hiring for key t IDA / E1240 gement and implementation Post Open - National 12,000.00 0.00 2024-02-29 2024-04-12 2024-04-04 2024-04-09 2024-04-24 2025-04-24 ant Selection ation he position of Internal Audito support r Specialist ET-MOWE-411369-CS-INDV / Component 4: Project mana Individual Consult Under Implement Contract staff hiring for key t IDA / E1240 gement and implementation Post Open - National 12,000.00 0.00 2024-02-29 2024-04-12 2024-04-04 2024-04-09 2024-04-24 2025-04-24 ant Selection ation he position of Project Accoun support tant ET-MOWE-410801-CS-QCBS Component 4: Project mana / Selection and Employment Individual Consult Under Implement IDA / E1240 gement and implementation Post Open - National 28,000.00 0.00 2024-05-15 2024-09-30 2024-06-28 2024-07-19 2024-08-23 2025-08-23 of Urban flood management ant Selection ation support specialist for the FMP of MoW E ET-MOWE-411360-CS-INDV / Component 4: Project mana Individual Consult Pending Impleme Contract staff hiring for key t IDA / E1240 gement and implementation Post Open - National 12,000.00 0.00 2024-05-15 2024-06-19 2024-06-24 2024-07-09 2025-07-09 ant Selection ntation he position of GIS Expert support Page 3 ET-MOWE-441381-CS-INDV / Selection and employment of Component 4: Project mana Individual Consult Under Implement Project Coordinator individual IDA / E1240 gement and implementation Post Limited - National 40,000.00 0.00 2024-10-10 2024-11-08 2024-10-15 2024-11-05 2024-12-10 2025-12-10 ant Selection ation consultant for PMCU to be im support plemented by MOWE ET-MOWE-453895-CS-INDV / Selection and Employment of Component 4: Project mana Individual consultant (IC) – C Individual Consult IDA / E1240 gement and implementation Post Open - National 28,000.00 0.00 Under Review 2024-10-10 2024-10-23 2024-11-24 2024-12-15 2025-01-19 2026-01-19 ontract Management Speciali ant Selection support st for the ET-Flood Managem ent Project -Management Uni t (PMU) ET-MOWE-456383-CS-INDV / Selection and Employment of Component 4: Project mana Individual Consult Pending Impleme Senior Hydraulic Engineer for IDA / E1240 gement and implementation Post Limited - National 35,000.00 0.00 2024-10-21 2024-11-05 2024-11-26 2024-12-31 2025-12-31 ant Selection ntation the EFM-Project Management support Unit (PMU) of MoWE ET-MOWE-464547-CS-INDV / Consultancy service for Bid d ocument preparation of Civil Component 2: Accelerating f Individual Consult Pending Impleme works for Awash River bed dr IDA / E1240 Post Limited - National 50,000.00 0.00 2025-01-03 2025-01-13 2025-02-07 2025-02-26 2025-03-28 lood risk management ant Selection ntation edging/widening and related works in Upper, Middle & Low er Awash under fast track ap proach before the flood perio d Page 4