PROCUREMENT PLAN (Textual Part) Project Country: Kyrgyz Republic information Full Project Name: Climate Resilient Water Services Project Total Finance ($): USD 100.0 Mln Project Number: P173734 Project Implementation agency THE WATER RESOURCES SERVICE UNDER THE MINISTRY OF AGRICULTURE OF THE KYRGYZ REPUBLIC DEPARTMENT FOR DEVELOPMENT OF DRINKING WATER SUPPLY AND WASTEWATER DISPOSAL Date of the Procurement Plan 15 March 22, 2022 Period covered by this Procurement 15 March 22, 2022 - 31-Dec-2028 Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), Borrower may use the procedures of “Unrestricted” and “Request for Quotations” methods as set forth in the Public Procurement Law dated April 14, 2022 № 27 with amendments dated January 30, 2023 N19 and July 25 2023 N147. When using the Unrestricted method the arrangements shall be subject to the provisions of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. • The request for bids/request for proposals document for civil works and supervision consultants shall require that Bidders/Proposers submitting Bids/Proposals present a signed Code of conduct form, Environmental and Social Performance Declaration and Management Strategies and Implementation Plans. Procurement Documents shall include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. • Bidding documents, including contract forms, acceptable to the Bank shall be used. Bidding documents including contract forms should include appropriate requirements for price adjustment (when applicable), insurance and contract termination. The contract conditions shall provide an appropriate allocation of responsibilities, risks, and liabilities informed by an analysis of which party is best placed to manage the risks, considering the costs and incentives of risk allocation. Goods: Requirements to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts, including child labor standards, should be added to country’ own procurement documents. All Unrestricted Bidding for civil works will be conducted using the Standard Procurement Document for Small Works (SPD) issued by the Bank until the country’ own procurement documents are revised and found acceptable. • The bidding process shall not be cancelled solely on the reason that the bid price of the lowest evaluated bidder is larger than the amount allocated by the Borrower for this procurement. • There shall be no preference of any kind applied during procurement of goods and civil works. • Banking support requirement shall not be applied for contracts under World Bank Project. • During the bidding process for civil works, the borrower shall require bidders to submit bids using the format of the Bill of Quantities acceptable to the Bank and provided in the bidding documents issued by the Borrower. The bidders shall use market prices for calculating the unit rates and the bid price. • Foreign bidders shall be allowed to participate in Unrestricted Bidding without restrictions of any kind. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement method such as “Request for Quotation” may be applied on the same conditions stated above for procuring limited quantities of readily available off-the-shelf goods and for simple works (current repairs, finishing repairs of premises, including existing utilities). Not less than three quotations shall be requested to ensure competition and adequate time should be provided to the participants to prepare their quotations. Use of the Direction Selection method may be appropriate when there is only one suitable firm or there is a justification in line with circumstances included in paragraph 6.9 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement “Not Applicable” PROCUREMENT Kyrgyz Republic : Climate Resilient Water Services Project PLAN General Information Country: Kyrgyz Republic 2022-12-28 Bank’s Approval Date of the Original Procurement Plan: 2025-01-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173734 GPN Date: 2023-01-31 Project Name: Climate Resilient Water Services Project Loan / Credit No: IDA / 70810 State Institution for Development of Drinking Water Supply and Wastewater Disposal Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Request for B IDA-CRWSP-CW-RFB-10 / Re ids - Small W habilitation of WS, sanitation Infrastructure Investments a Single Stage - One E Pending Imp 2026-04-1 IDA / 70810 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-12-20 2024-12-25 2025-02-05 2025-03-07 2025-04-11 and hygiene (WASH) facilities nd Service Improvements nvelope lementation 1 nvelope proc in social institutions of subpr ess) ojects Request for B IDA-CRWSP-CW-RFB-11 / Re ids - Small W habilitation of water supply a Infrastructure Investments a Open - Internationa Single Stage - One E 2025-04-1 IDA / 70810 Prior Request for Bids orks SPD (1 e 0.00 Canceled 2023-12-22 2023-12-27 2024-02-07 2024-03-08 2024-04-12 nd sanitation system in Kyzyl nd Service Improvements l nvelope 2 nvelope proc -Suu sub-project (Kyzyl-Suu) ess) Request for B IDA-CRWSP-CW-RFB-14 / Re ids - Small W habilitation of water supply s Infrastructure Investments a Single Stage - Two E 2025-03-1 IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 Signed 2023-04-10 2023-04-26 2023-04-15 2023-04-26 2023-05-27 2023-05-26 2023-08-09 2023-06-22 2023-09-13 2023-07-21 ystem in Kyzyl-Suu sub-proje nd Service Improvements nvelope 4 nvelope proc ct (3 Lots) 1st Stage ess) Request for B IDA-CRWSP-CW-RFB-15 / Re ids - Small W habilitation of water supply s Infrastructure Investments a Single Stage - Two E 2025-04-1 IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 Signed 2023-05-10 2023-12-11 2023-05-15 2023-12-11 2023-06-26 2024-01-16 2023-09-08 2024-01-25 2023-10-13 2024-03-28 ystem in Kyzyl-Suu sub-proje nd Service Improvements nvelope 3 nvelope proc ct (2 Lots) 2nd Stage ess) IDA-CRWSP-CW-RFB-1 / Reh Request for B abilitation of water supply an ids - Small W d sanitation system in Ak-Tur Infrastructure Investments a Single Stage - One E 2026-01-1 IDA / 70810 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2024-09-20 2024-09-25 2024-11-06 2024-12-06 2025-01-10 pak sub-project (Otukchu, Ky nd Service Improvements nvelope 0 nvelope proc zyl-Korgon, Tokoi, Chogorok, ess) Ak-Turpak, Kalacha, Chon-Ka ra) Request for B IDA-CRWSP-CW-RFB-2 / Reh ids - Small W abilitation of water supply an Infrastructure Investments a Single Stage - One E 2024-11-1 IDA / 70810 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2023-07-25 2023-07-30 2023-09-10 2023-10-10 2023-11-14 d sanitation system in Sovets nd Service Improvements nvelope 3 nvelope proc koe sub-project (Sovetskoe) ess) IDA-CRWSP-CW-RFB-3 / Reh Request for B abilitation of water supply an ids - Small W Infrastructure Investments a Single Stage - One E 2026-01-1 d sanitation system in Katra IDA / 70810 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2024-09-20 2024-09-25 2024-11-06 2024-12-06 2025-01-10 nd Service Improvements nvelope 0 n sub-project (Jany-Turmush nvelope proc (Baul)) and Kulundu sub-proj ess) ect (Bulak-Bashy) 2 lots Request for B IDA-CRWSP-CW-RFB-4 / Reh ids - Small W abilitation of water supply an Infrastructure Investments a Single Stage - One E 2024-11-1 IDA / 70810 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2023-07-25 2023-07-30 2023-09-10 2023-10-10 2023-11-14 d sanitation system in Katra nd Service Improvements nvelope 3 nvelope proc n Sub-project (Katran) ess) Request for B IDA-CRWSP-CW-RFB-5 / Reh ids - Small W abilitation of water supply an Infrastructure Investments a Single Stage - One E 2024-11-1 IDA / 70810 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2023-07-25 2023-07-30 2023-09-10 2023-10-10 2023-11-14 d sanitation system in Toguz- nd Service Improvements nvelope 3 nvelope proc y sub-project (Aibiyke (Mada ess) niyat)) IDA-CRWSP-CW-RFB-6 / Reh Request for B abilitation of water supply an ids - Small W Infrastructure Investments a Single Stage - One E 2026-01-1 d sanitation system Dara sub IDA / 70810 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2024-09-20 2024-09-25 2024-11-06 2024-12-06 2025-01-10 nd Service Improvements nvelope 0 -project (Kayindy, Kan, Sary- nvelope proc Talaa, Chek, Jany-Jer) and Su ess) u-Bashy sub-project (Apkan) IDA-CRWSP-CW-RFB-7 / Reh Request for B abilitation of water supply an ids - Small W Infrastructure Investments a Single Stage - One E 2026-01-1 d sanitation system in Toguz- IDA / 70810 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2024-09-20 2024-09-25 2024-11-06 2024-12-06 2025-01-10 nd Service Improvements nvelope 0 Bulak sub-project (Sabyrov ( nvelope proc 50 let Kirgizii) and Margun su ess) b-project (Margun) 2 Lots IDA-CRWSP-CW-RFB-8 / Reh Request for B abilitation of water supply an ids - Small W d sanitation system in Tort-G Infrastructure Investments a Single Stage - One E 2024-11-1 IDA / 70810 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2023-07-25 2023-07-30 2023-09-10 2023-10-10 2023-11-14 ul sub-project (Ak-Otok, Ak-T nd Service Improvements nvelope 3 nvelope proc urpak, Zar-Tash, Chon-Gara, ess) Chon-Talaa) and Suu-Bashy s ub-project (Boz-Adyr) IDA-CRWSP-CW-RFB-9 / Reh Request for B abilitation of water supply an ids - Small W Infrastructure Investments a Single Stage - One E 2024-11-1 d sanitation system in Kara-B IDA / 70810 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2023-07-25 2023-07-30 2023-09-10 2023-10-10 2023-11-14 nd Service Improvements nvelope 3 ulak sub-project (Kara-Bulak) nvelope proc and Suu-Bashy sub-project (A ess) igul-Tash) Request for B IDA-CRWSP-CW-RFB-12 / Re ids - Small W habilitation of water supply a Infrastructure Investments a Open - Internationa Single Stage - One E 2025-04-1 IDA / 70810 Prior Request for Bids orks SPD (1 e 0.00 Canceled 2023-12-22 2023-12-27 2024-02-07 2024-03-08 2024-04-12 nd sanitation system in Kun- nd Service Improvements l nvelope 2 nvelope proc Chygysh sub-project (Bokonb ess) aeva) Request for B IDA-CRWSP-CW-RFB-13 / Re ids - Small W habilitation of water supply a Infrastructure Investments a Single Stage - One E 2025-04-1 IDA / 70810 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2023-12-22 2023-12-27 2024-02-07 2024-03-08 2024-04-12 nd sanitation system in Ton s nd Service Improvements nvelope 2 nvelope proc ub-project (Kadzhi-Sai) ess) Request for B IDA-CRWSP-CW-RFB-16 / Co ids - Small W Infrastructure Investments a Open - Internationa Single Stage - Two E 2027-05-0 nstruction of sanitation syste IDA / 70810 Prior Request for Bids orks SPD (2 e 0.00 Canceled 2025-06-02 2025-06-07 2025-07-19 2025-10-01 2025-11-05 nd Service Improvements l nvelope 7 m in Kyzyl-Suu sub-project nvelope proc ess) Request for B IDA-CRWSP-CW-RFB-3-3 / Re ids - Small W habilitation of water supply s Infrastructure Investments a Single Stage - Two E Pending Imp 2025-10-0 IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2023-10-30 2023-11-04 2023-12-16 2024-02-28 2024-04-10 ystem in Toguz-Bulak sub-pr nd Service Improvements nvelope lementation 7 nvelope proc oject (Sabyrov (50 years of K ess) yrgyzstan) Request for B IDA-CRWSP-CW-RFB-7-7 / Re ids - Small W Infrastructure Investments a Single Stage - Two E Pending Imp 2026-01-0 habilitation of water supply s IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2024-01-25 2024-01-30 2024-03-12 2024-05-25 2024-07-06 nd Service Improvements nvelope lementation 2 ystem in Suu-Bashy sub-proj nvelope proc ect (Aigul-Tash) ess) Page 1 Request for B IDA-CRWSP-CW-RFB-17-17 / ids - Small W Rehabilitation of water suppl Infrastructure Investments a Single Stage - Two E Pending Imp 2026-09-1 IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2024-10-09 2024-10-14 2024-11-25 2025-02-07 2025-03-21 y system Dara sub-project (K nd Service Improvements nvelope lementation 7 nvelope proc ayindy, Kan, Sary-Talaa) ess) Request for B IDA-CRWSP-CW-RFB-5-5 / Re ids - Small W habilitation of water supply s Infrastructure Investments a Single Stage - Two E Pending Imp 2026-01-0 IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2024-01-25 2024-01-30 2024-03-12 2024-05-25 2024-07-06 ystem in Toguz-Bulak sub-pr nd Service Improvements nvelope lementation 2 nvelope proc oject (Aibiyke (Madaniyat)) ess) Request for B IDA-CRWSP-CW-RFB-8-8 / Re ids - Small W Infrastructure Investments a Single Stage - Two E Pending Imp 2026-01-0 habilitation of water supply s IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2024-01-25 2024-01-30 2024-03-12 2024-05-25 2024-07-06 nd Service Improvements nvelope lementation 2 ystem in Kara-Bulak sub-proj nvelope proc ect (Kara-Bulak) ess) Request for B IDA-CRWSP-CW-RFB-18-18 / ids - Small W Rehabilitation of water suppl Infrastructure Investments a Single Stage - Two E 2026-01-0 IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 Signed 2024-02-01 2024-04-25 2024-02-06 2024-03-19 2024-06-12 2024-06-01 2024-07-10 2024-07-13 2024-09-25 y system in Kun-Chygysh sub nd Service Improvements nvelope 9 nvelope proc -project (Bokonbaeva) ess) Request for B IDA-CRWSP-CW-RFB-6-6 / Re ids - Small W Infrastructure Investments a Single Stage - Two E 2026-01-0 habilitation of water supply s IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 Signed 2024-01-25 2024-07-04 2024-01-30 2024-03-12 2024-08-19 2024-05-25 2024-09-20 2024-07-06 2024-10-18 nd Service Improvements nvelope 2 ystem in Margun sub-project nvelope proc (Margun) ess) Request for B IDA-CRWSP-CW-RFB-1-1 / Re ids - Small W habilitation of water supply s Infrastructure Investments a Single Stage - Two E Pending Imp 2025-10-0 IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2023-10-29 2023-11-03 2023-12-15 2024-02-27 2024-04-09 ystem in Baul sub-project (Ja nd Service Improvements nvelope lementation 6 nvelope proc ny-Turmush (Baul)) ess) Request for B IDA-CRWSP-CW-RFB-4-4 / Re ids - Small W Infrastructure Investments a Single Stage - Two E Pending Imp 2026-01-0 habilitation of water supply s IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2024-01-25 2024-01-30 2024-03-12 2024-05-25 2024-07-06 nd Service Improvements nvelope lementation 2 ystem in Katran Sub-project nvelope proc (Katran) ess) Request for B IDA-CRWSP-CW-RFB-11-11 / ids - Small W Infrastructure Investments a Single Stage - Two E Pending Imp 2026-09-1 Rehabilitation of water suppl IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2024-10-09 2024-10-14 2024-11-25 2025-02-07 2025-03-21 nd Service Improvements nvelope lementation 7 y system in Suu-Bashy sub-p nvelope proc roject (Apkan) ess) Request for B IDA-CRWSP-CW-RFB-12-12 / ids - Small W Infrastructure Investments a Single Stage - Two E Pending Imp 2026-09-1 Rehabilitation of water suppl IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2024-10-09 2024-10-14 2024-11-25 2025-02-07 2025-03-21 nd Service Improvements nvelope lementation 7 y system in Boz-Adyr sub-pro nvelope proc ject ess) IDA-CRWSP-CW-RFB-13-13 / Request for B Rehabilitation of water suppl ids - Small W Infrastructure Investments a Single Stage - Two E Pending Imp 2026-09-1 y system in Tort-Gul sub-proj IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2024-10-09 2024-10-14 2024-11-25 2025-02-07 2025-03-21 nd Service Improvements nvelope lementation 7 ect (Ak-Otok, Ak-Turpak, Zar- nvelope proc Tash, Chon-Gara, Chon-Talaa ess) ) Request for B IDA-CRWSP-CW-RFB-2-2 / Re ids - Small W Infrastructure Investments a Single Stage - Two E Pending Imp 2025-10-0 habilitation of water supply s IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2023-10-29 2023-11-03 2023-12-15 2024-02-27 2024-04-09 nd Service Improvements nvelope lementation 6 ystem in Kulundu sub-project nvelope proc (Bulak-Bashy) ess) IDA-CRWSP-CW-RFB-16-16 / Request for B Rehabilitation of water suppl ids - Small W Infrastructure Investments a Single Stage - Two E Pending Imp 2026-09-1 y system in Ak-Turpak sub-pr IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2024-10-09 2024-10-14 2024-11-25 2025-02-07 2025-03-21 nd Service Improvements nvelope lementation 7 oject (Otukchu, Kyzyl-Korgon nvelope proc , Tokoi, Chogorok, Ak-Turpak, ess) Kalacha, Chon-Kara) Request for B IDA-CRWSP-CW-RFB-10-10 / ids - Small W Infrastructure Investments a Single Stage - Two E Pending Imp 2026-09-1 Rehabilitation of water suppl IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2024-10-10 2024-10-15 2024-11-26 2025-02-08 2025-03-22 nd Service Improvements nvelope lementation 8 y system Dara sub-project (C nvelope proc hek, Jany-Jer) ess) Request for B IDA-CRWSP-CW-RFB-19-19 / ids - Small W Infrastructure Investments a Single Stage - Two E Pending Imp 2026-01-1 Rehabilitation of water suppl IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2024-02-02 2024-02-07 2024-03-20 2024-06-02 2024-07-14 nd Service Improvements nvelope lementation 0 y system in Ton sub-project ( nvelope proc Kadzhi-Sai) ess) Request for B IDA-CRWSP-CW-RFB-9-9 / Re ids - Small W Infrastructure Investments a Single Stage - Two E Pending Imp 2026-01-0 habilitation of water supply s IDA / 70810 Post Request for Bids Open - National orks SPD (2 e 0.00 2024-01-25 2024-01-30 2024-03-12 2024-05-25 2024-07-06 nd Service Improvements nvelope lementation 2 ystem in Sovetskoe sub-proje nvelope proc ct (Sovetskoe) ess) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-CRWSP-G-RFB-2 / Suppl Infrastructure Investments a Open - Internationa Single Stage - One E Pending Impl IDA / 70810 Post Request for Bids 0.00 2025-03-02 2025-03-07 2025-04-18 2025-05-18 2025-06-22 2025-12-19 y of water meters nd Service Improvements l nvelope ementation IDA-CRWSP-G-RFB-1 / Purch Institutional Strengthening f ase offfice furnuture and equ or Climate Resilient Service Open - Internationa Single Stage - One E IDA / 70810 Post Request for Bids 0.00 Canceled 2023-07-25 2023-07-30 2023-09-10 2023-10-10 2023-11-14 2024-05-12 ipment for billing system of b Delivery, Water Resources M l nvelope eneficiaries anagement and Dam Manag ement IDA-CRWSP-G-RFB-5 / Purch Institutional Strengthening f ase of laboratory equipment or Climate Resilient Service Single Stage - One E Pending Impl IDA / 70810 Post Request for Bids Open - National 0.00 2025-08-03 2025-08-08 2025-09-19 2025-10-19 2025-11-23 2026-05-22 for the target WSS enterprise Delivery, Water Resources M nvelope ementation s for the analysis of drinking anagement and Dam Manag water quality ement IDA-CRWSP-G-RFQ-4 / Purch Institutional Strengthening f ase of office furniture and eq or Climate Resilient Service Request for Quota Single Stage - One E Pending Impl IDA / 70810 Post Open - National 0.00 2025-10-15 2025-12-10 2026-06-08 uipment for the beneficiary b Delivery, Water Resources M tions nvelope ementation illing system (Phase 2) anagement and Dam Manag ement IDA-CRWSP-G-RFQ-7 / Purch Institutional Strengthening f ase of computer equipment f or Climate Resilient Service Request for Quota Single Stage - One E Pending Impl IDA / 70810 Post Open - National 0.00 2024-04-15 2024-05-20 2024-07-19 or the Kyzyl-Suu beneficiary Delivery, Water Resources M tions nvelope ementation billing system anagement and Dam Manag ement IDA-CRWSP-G-RFQ-3 / Purch Institutional Strengthening f ase of office furniture and eq or Climate Resilient Service Request for Quota Single Stage - One E Pending Impl IDA / 70810 Post Open - National 0.00 2024-10-15 2024-12-10 2025-06-08 uipment for the beneficiary b Delivery, Water Resources M tions nvelope ementation illing system (Phase 1) anagement and Dam Manag ement Institutional Strengthening f IDA-CRWSP-G-RFQ-6 / Purch or Climate Resilient Service Request for Quota Single Stage - One E Pending Impl ase auto for State Institution IDA / 70810 Post Open - National 0.00 2025-01-29 2025-03-26 2025-09-22 Delivery, Water Resources M tions nvelope ementation and PIU anagement and Dam Manag ement NON CONSULTING SERVICES Page 2 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-CRWSP-QCBS-1 / Prepar Infrastructure Investments a Quality And Cost- Open - Internationa ation of detailed designs for IDA / 70810 Post 0.00 Canceled 2023-02-15 2023-03-08 2023-04-21 2023-05-19 2023-06-18 2023-07-23 2023-08-27 2024-08-26 nd Service Improvements Based Selection l 11 sub-projects in Batken obl ast IDA-CRWSP-QCBS-3 / Selecti Infrastructure Investments a Quality And Cost- Open - Internationa Pending Impleme on of the Construction Super IDA / 70810 Prior 0.00 2023-08-18 2023-09-08 2023-10-22 2023-11-19 2023-12-19 2024-01-23 2024-02-27 2025-02-26 nd Service Improvements Based Selection l ntation vision Company Infrastructure Investments a Least Cost Selecti Open - Internationa IDA-CRWSP-LCS-1 / Audit IDA / 70810 Post 0.00 Signed 2023-06-16 2023-04-02 2023-07-07 2023-08-20 2023-05-05 2023-09-17 2023-06-19 2023-10-17 2023-06-27 2023-11-21 2023-07-17 2023-12-26 2023-08-17 2026-12-31 nd Service Improvements on l IDA-CRWSP-СQS-2023-1 / Pr eparation of detailed designs Infrastructure Investments a Consultant Qualifi IDA / 70810 Post Open - National 0.00 Signed 2023-04-10 2023-05-19 2023-05-01 2023-06-05 2023-06-14 2023-07-13 2023-07-14 2023-08-09 2023-08-18 2023-09-01 2024-02-16 for 6 WSS sub-projects in Bat nd Service Improvements cation Selection ken oblast (1 Phase) Institutional Strengthening f IDA-CRWSP-QCBS-4 / Selecti or Climate Resilient Service Quality And Cost- Open - Internationa on of a Instituional Developm IDA / 70810 Post 0.00 Canceled 2023-08-18 2023-09-08 2023-10-22 2023-11-19 2023-12-19 2024-01-23 2024-02-27 2025-02-26 Delivery, Water Resources M Based Selection l ent Consultant anagement and Dam Manag ement IDA-CRWSP-СOMP2-CQS-202 Institutional Strengthening f 3-1 / Consultant on the devel or Climate Resilient Service Consultant Qualifi IDA / 70810 Post Open - National 0.00 Canceled 2024-01-15 2024-02-05 2024-03-20 2024-04-19 2024-05-24 2025-01-05 opment of by-laws in the fiel Delivery, Water Resources M cation Selection d of WSS anagement and Dam Manag ement IDA-CRWSP-СOMP2-CQS-202 Institutional Strengthening f 3-2 / Consultant on the devel or Climate Resilient Service opment of the National Progr Consultant Qualifi IDA / 70810 Delivery, Water Resources M Post Open - National 0.00 Signed 2023-09-01 2023-07-27 2023-09-22 2023-11-05 2023-10-18 2023-12-05 2023-12-20 2024-01-09 2023-12-22 2025-06-30 am for the Development of t cation Selection anagement and Dam Manag he WSS Sector and support f ement or the institutional capacity d evelopment of the DDWSWD IDA-CRWSP-CQS-1 / Baseline Project Management, M&E a Consultant Qualifi IDA / 70810 Post Open - National 0.00 Signed 2023-06-02 2023-07-03 2023-06-23 2023-08-06 2023-08-24 2023-09-05 2023-09-15 2023-10-10 2023-10-02 2024-04-07 Survey nd Professional Developmen cation Selection t IDA-CRWSP-CQS-2 / Impact Project Management, M&E a Consultant Qualifi Pending Impleme IDA / 70810 Post Open - National 0.00 2026-09-15 2026-10-06 2026-11-19 2026-12-19 2027-01-23 2027-07-22 Assestment nd Professional Developmen cation Selection ntation t IDA-CRWSP-СOMP2-CQS-202 Institutional Strengthening f 3-3 / Consultant for capacity or Climate Resilient Service Consultant Qualifi building of WSS enterprises a IDA / 70810 Delivery, Water Resources M Post Open - National 0.00 Canceled 2023-09-01 2023-09-15 2023-09-22 2023-11-05 2023-11-29 2023-12-05 2024-01-09 2026-12-31 cation Selection nd support in improving their anagement and Dam Manag financial management ement IDA-CRWSP-СQS-2023-2 / Pr eparation of detailed designs Infrastructure Investments a Consultant Qualifi IDA / 70810 Post Open - National 0.00 Signed 2023-05-22 2023-09-06 2023-06-12 2023-09-14 2023-07-26 2024-04-12 2023-08-25 2024-04-12 2023-09-29 2024-05-15 2024-06-30 for 6 WSS sub-projects in Bat nd Service Improvements cation Selection ken oblast (2 Phase) IDA-CRWSP-СQS-2024-3 / Te chnical Supervision of Civil W Infrastructure Investments a Consultant Qualifi IDA / 70810 Post Open - National 0.00 Canceled 2024-02-05 2024-02-27 2024-02-26 2024-04-10 2024-04-08 2024-05-10 2024-05-06 2024-06-14 2026-06-14 orks for Construction of Wate nd Service Improvements cation Selection r Supply Systems in Batken o blast (1 phase) IDA-CRWSP-СQS-2024-3-RT- 1 / Technical Supervision of C Infrastructure Investments a Consultant Qualifi Under Implement IDA / 70810 Post Open - National 0.00 2024-07-26 2024-07-26 2024-07-27 2024-09-09 2024-12-06 2024-10-09 2024-11-13 2026-05-17 ivil Works for Construction of nd Service Improvements cation Selection ation Water Supply Systems in Bat ken oblast (1 phase) IDA-CRWSP-QCBS-2 / Selecti on of a Design Institute for D etailed Design Development, Infrastructure Investments a Quality And Cost- Open - Internationa Under Implement IDA / 70810 Prior 0.00 2024-08-30 2024-09-30 2024-09-20 2024-11-06 2024-11-03 2024-12-01 2024-12-31 2025-02-04 2025-03-11 2029-03-10 Engineering, and Technical S nd Service Improvements Based Selection l ation upersition of Wastewater Tre atment Facility Construction i n the Issyk-Kul Oblast Subpro jects INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-CRWSP-IC-2022-1 / Sele Institutional Strengthening f ction of consultant for produc or Climate Resilient Service Individual Consult e a due diligence note on the IDA / 70810 Delivery, Water Resources M Post Open - National 0.00 Signed 2022-12-15 2022-12-01 2023-02-02 2022-11-15 2023-02-23 2022-11-21 2023-03-30 2022-12-15 2023-05-29 ant Selection security and conflict risk asse anagement and Dam Manag ssment in the Batken Region ement of the Kyrgyz Republic IDA-CRWSP-DS-2023-1 / Revi ew of previously prepared de Infrastructure Investments a tailed design estimates of Ky IDA / 70810 Post Direct Selection Direct - National 0.00 Signed 2023-02-03 2023-02-28 2023-02-20 2023-03-13 2023-03-20 2023-03-15 2023-06-18 nd Service Improvements zyl-Suu sub-project Issyk-Kul oblast, including author's sup ervision IDA-CRWSP-СOMP2-IC-2023- Institutional Strengthening f 6 / Consultant on the develop or Climate Resilient Service Individual Consult IDA / 70810 Post Open - National 0.00 Canceled 2023-07-03 2023-07-27 2023-08-21 2023-09-11 2023-10-16 2027-10-15 ment and implementation of Delivery, Water Resources M ant Selection the DDWSWD's communicati anagement and Dam Manag on strategy ement IDA-CRWSP-СOMP2-IC-2023- Institutional Strengthening f 5 / Consultant for developme or Climate Resilient Service Individual Consult Open - Internationa Pending Impleme nt of an energy efficiency im IDA / 70810 Delivery, Water Resources M Post 0.00 2024-07-01 2024-08-19 2024-09-09 2024-10-14 2025-10-14 ant Selection l ntation provement plan for priority anagement and Dam Manag WSS enterprises (internation ement al) Institutional Strengthening f IDA-CRWSP-СOMP2-IC-2023- or Climate Resilient Service Individual Consult 7 / Consultant on sanitation d IDA / 70810 Post Open - National 0.00 Canceled 2023-07-02 2023-07-27 2023-08-20 2023-09-10 2023-10-15 2028-12-31 Delivery, Water Resources M ant Selection evelopment anagement and Dam Manag ement Page 3 IDA-CRWSP-СOMP2-IC-2023- Institutional Strengthening f 8 / Regional Specialist on inst or Climate Resilient Service Individual Consult IDA / 70810 Post Open - National 0.00 Signed 2023-06-01 2023-06-13 2023-07-20 2023-07-28 2023-08-10 2023-07-31 2023-09-14 2023-08-01 2026-07-10 itutional development in Zhe Delivery, Water Resources M ant Selection ti-Oguz district anagement and Dam Manag ement IDA-CRWSP-СOMP2-IC-2023- Institutional Strengthening f 9 / Regional Specialist on inst or Climate Resilient Service Individual Consult IDA / 70810 Post Open - National 0.00 Signed 2025-02-03 2023-06-13 2025-03-24 2024-07-01 2025-04-14 2024-07-01 2025-05-19 2024-06-27 2028-03-14 itutional development in Ton Delivery, Water Resources M ant Selection district anagement and Dam Manag ement IDA-CRWSP-СOMP2-IC-2023- Institutional Strengthening f 10 / Regional Specialist on in or Climate Resilient Service Individual Consult Under Implement IDA / 70810 Post Open - National 0.00 2024-01-15 2023-06-13 2024-03-04 2024-03-25 2024-04-29 2027-02-28 stitutional development in Le Delivery, Water Resources M ant Selection ation ylek district anagement and Dam Manag ement IDA-CRWSP-СOMP2-IC-2023- Institutional Strengthening f 11 / Regional Specialist on in or Climate Resilient Service Individual Consult IDA / 70810 Post Open - National 0.00 Signed 2024-03-01 2023-06-13 2024-04-19 2024-07-19 2024-05-10 2024-07-22 2024-06-14 2024-06-24 2027-04-15 stitutional development in B Delivery, Water Resources M ant Selection atken distirct anagement and Dam Manag ement IDA-CRWSP-СOMP2-IC-2023- Institutional Strengthening f 12 / Regional Specialist on in or Climate Resilient Service Individual Consult Under Implement IDA / 70810 Post Open - National 0.00 2025-01-15 2023-06-13 2025-03-05 2025-03-26 2025-04-30 2028-02-29 stitutional development in Ka Delivery, Water Resources M ant Selection ation damjay district anagement and Dam Manag ement IDA-CRWSP-СOMP2-IC-2023- 4 / Consultant on automation Institutional Strengthening f of DDWSWD activities and im or Climate Resilient Service Individual Consult Pending Impleme plementation of the billing sy IDA / 70810 Delivery, Water Resources M Post Open - National 0.00 2023-07-16 2023-09-03 2023-09-24 2023-10-29 2026-08-31 ant Selection ntation stem for 8 target subprojects anagement and Dam Manag (Bokonbaev, Kaji-Say, Dara, ement Tort-Kul, Ak-Turpak, Apkan, B aul, Kulundu) IDA-CRWSP-СOMP2-IC-2023- 13 / Consultant on automatio Institutional Strengthening f n of DDWSWD activities and i or Climate Resilient Service Individual Consult Pending Impleme mplementation of the billing IDA / 70810 Delivery, Water Resources M Post Open - National 0.00 2023-09-17 2023-11-05 2023-11-26 2023-12-31 2026-12-30 ant Selection ntation system for 7 target subprojec anagement and Dam Manag ts (Kyzyl-Suu, Katran, Aibike, ement Margun, Suu-Bashy, Kara-Bul ak, Sovetskoe) IDA-CRWSP-IC-2023-1 / Seni Infrastructure Investments a Individual Consult or technical supervision cons IDA / 70810 Post Open - National 0.00 Signed 2023-07-15 2023-07-13 2023-09-02 2023-10-03 2023-09-23 2023-10-04 2023-10-28 2023-10-05 2025-04-25 nd Service Improvements ant Selection ultant for Kyzyl-Suu subproje ct IDA-CRWSP-IC-2023-2 / Tech Infrastructure Investments a Individual Consult nical supervision consultant f IDA / 70810 Post Open - National 0.00 Signed 2023-07-17 2023-07-13 2023-09-04 2023-10-03 2023-09-25 2023-10-04 2023-10-30 2023-10-05 2025-04-27 nd Service Improvements ant Selection or Kyzyl-Suu subproject IDA-CRWSP-СOMP2-IC-2023- Institutional Strengthening f 6-1 / Consultant on the devel or Climate Resilient Service Individual Consult IDA / 70810 Post Open - National 0.00 Signed 2023-09-08 2023-09-06 2023-10-27 2023-10-19 2023-11-17 2023-10-20 2023-12-22 2023-11-01 2024-05-16 opment and implementation Delivery, Water Resources M ant Selection of the DDWSWD's communic anagement and Dam Manag ation strategy ement Institutional Strengthening f IDA-CRWSP-СOMP2-IC-2023- or Climate Resilient Service Individual Consult 7-1 / Consultant on sanitation IDA / 70810 Post Open - National 0.00 Signed 2023-09-08 2023-09-06 2023-10-27 2023-10-19 2023-11-17 2023-10-20 2023-12-22 2023-10-23 2028-12-20 Delivery, Water Resources M ant Selection development anagement and Dam Manag ement IDA-CRWSP-IC-2023-3 / Sele ction of environmental consu Infrastructure Investments a Individual Consult Under Implement IDA / 70810 Post Open - National 0.00 2023-09-15 2023-09-06 2023-11-03 2023-11-24 2023-12-29 2028-06-27 ltant for WSS subprojects in nd Service Improvements ant Selection ation Batken and Issyk-Kul oblasts IDA-CRWSP-IC-2023-4 / Sele ction of hydrogeologist for W Infrastructure Investments a Individual Consult IDA / 70810 Post Open - National 0.00 Signed 2023-09-15 2023-09-06 2023-11-03 2023-12-20 2023-11-24 2023-12-20 2023-12-29 2024-01-09 2028-06-27 SS subprojects in Batken and nd Service Improvements ant Selection Issyk-Kul oblasts IDA-CRWSP-IC-2023-5 / Sele Infrastructure Investments a Individual Consult ction of surveyor for WSS sub IDA / 70810 Post Open - National 0.00 Signed 2023-09-15 2023-09-06 2023-11-03 2023-12-20 2023-11-24 2023-12-20 2023-12-29 2024-01-09 2028-06-27 nd Service Improvements ant Selection projects in Batken and Issyk- Kul oblasts IDA-CRWSP-IC-2023-6 / Sele ction of electrical engineer fo Infrastructure Investments a Individual Consult IDA / 70810 Post Open - National 0.00 Signed 2023-09-15 2023-09-06 2023-11-03 2023-12-20 2023-11-24 2023-12-20 2023-12-29 2024-01-09 2028-06-27 r WSS subprojects in Batken nd Service Improvements ant Selection and Issyk-Kul oblasts IDA-CRWSP-IC-2 / Internatio Infrastructure Investments a Individual Consult Open - Internationa Under Implement IDA / 70810 Post 0.00 2023-12-15 2023-12-07 2024-02-02 2024-02-23 2024-03-29 2025-03-29 nal Process Engineer nd Service Improvements ant Selection l ation IDA-CRWSP-DS-2023-4 / Revi ew of previously prepared de Infrastructure Investments a tailed design estimates of Ba IDA / 70810 Post Direct Selection Direct - National 0.00 Signed 2024-02-01 2024-03-29 2024-02-11 2024-05-13 2024-03-03 2024-05-15 2024-06-01 nd Service Improvements ul sub-project (Jany-Turmush (Baul)) Batken oblast IDA-CRWSP-DS-2023-5 / Revi ew of previously prepared de Infrastructure Investments a tailed design estimates of To IDA / 70810 Post Direct Selection Direct - National 0.00 Signed 2024-02-01 2024-02-12 2024-02-11 2024-03-11 2024-03-03 2024-05-15 2024-06-01 nd Service Improvements guz-Bulak sub-project (Sabyr ov (50 let Kirgizii) Batken obl ast IDA-CRWSP-DS-2023-3 / Revi ew of previously prepared de Infrastructure Investments a Pending Impleme IDA / 70810 Post Direct Selection Direct - National 0.00 2024-02-01 2024-02-11 2024-03-03 2024-03-12 tailed design estimates of Ka nd Service Improvements ntation dzhi-Sai sub-project Issyk-Kul oblast IDA-CRWSP-DS-2023-6 / Mon itoring of water analysis for r Infrastructure Investments a IDA / 70810 Post Direct Selection Direct - National 0.00 Signed 2024-02-01 2023-12-07 2024-02-11 2023-12-18 2024-03-03 2024-01-08 2024-07-01 adiation of the Kadzhi Say, B nd Service Improvements okonbaevo and Kyzyl-Suu su bprojects IDA-CRWSP-DS-2023-2 / Revi ew of previously prepared de Infrastructure Investments a IDA / 70810 Post Direct Selection Direct - National 0.00 Signed 2023-12-04 2023-11-01 2023-12-14 2023-11-10 2024-01-04 2023-11-14 2024-01-13 tailed design estimates of Bo nd Service Improvements konbaeva sub-project Issyk-K ul oblast Page 4 IDA-CRWSP-CS-2024-1 / Envi ronmental Consultant for the preparation of the Environm Project Management, M&E a ental and Social Managemen Individual Consult IDA / 70810 nd Professional Developmen Post Limited 0.00 Signed 2023-12-13 2023-12-13 2023-12-18 2024-01-14 2023-12-20 2023-12-22 2024-01-08 2023-12-25 2024-02-12 t Framework (ESMF), Environ ant Selection t mental and Social Commitme nt Plan (ESCP) for the new up coming project “Unified acce ss to the water supply and sa nitation” IDA-CRWSP-CS-2024-2 / Soci al Development Consultant f or the preparation of the Sta Project Management, M&E a keholder Engagement Plan (S Individual Consult IDA / 70810 nd Professional Developmen Post Limited 0.00 Signed 2023-12-13 2023-12-15 2023-12-18 2024-01-14 2023-12-20 2023-12-22 2024-01-08 2023-12-25 2024-02-12 EP), Labor Management Proc ant Selection t edures (LMP), Resettlement a ction plan (RAP), Code of Co nduct, as well as contribute t o ESMF for the new upcomin g project IDA-CRWSP-CS-2024-3 / Dev Project Management, M&E a elopment of the full package Individual Consult IDA / 70810 nd Professional Developmen Post Open - National 0.00 Signed 2024-01-12 2024-01-17 2024-03-01 2024-04-08 2024-03-22 2024-04-08 2024-04-26 2024-04-09 2024-07-25 of the detailed design for the ant Selection t PIU office renovation IDA-CRWSP-СOMP2-IC-2023- Institutional Strengthening f 14 / Second Regional Speciali or Climate Resilient Service Individual Consult IDA / 70810 Post Open - National 0.00 Signed 2024-03-26 2024-04-16 2024-05-14 2024-06-19 2024-06-04 2024-07-01 2024-07-09 2024-06-27 2025-01-05 st on institutional developme Delivery, Water Resources M ant Selection nt in Zheti-Oguz district anagement and Dam Manag ement IDA-CRWSP-СOMP2-IC-2023- Institutional Strengthening f 1 / Legal Consultant for Capa or Climate Resilient Service Individual Consult IDA / 70810 Post Open - National 0.00 Signed 2024-07-17 2024-08-07 2024-09-04 2024-07-30 2024-09-25 2024-07-30 2024-10-30 2024-07-22 2028-10-29 city Building of the State Insti Delivery, Water Resources M ant Selection tution anagement and Dam Manag ement IDA-CRWSP-IC-2024-7 / Assis Infrastructure Investments a Individual Consult tant Technical Supervision En IDA / 70810 Post Open - National 0.00 Canceled 2024-08-20 2024-08-20 2024-10-08 2024-10-29 2024-12-03 2025-11-30 nd Service Improvements ant Selection gineer for Kyzyl-Suu Subproj ect IDA-CRWSP-IC-2024-8 / Regi Infrastructure Investments a Individual Consult Under Implement IDA / 70810 Post Open - National 0.00 2024-08-20 2024-08-20 2024-10-08 2024-10-29 2024-12-03 2028-12-29 onal Engineer in Batken obla nd Service Improvements ant Selection ation st IDA-CRWSP-IC-2024-9 / Seco Infrastructure Investments a Individual Consult Under Implement IDA / 70810 Post Open - National 0.00 2024-08-20 2024-08-20 2024-10-08 2024-10-29 2024-12-03 2028-12-29 nd Regional Engineer in Batk nd Service Improvements ant Selection ation en oblast IDA-CRWSP-СOMP2-IC-2025- 15 / Consultant-trainer for tra Institutional Strengthening f ining of employees of local g or Climate Resilient Service overnment employees, muni Individual Consult Pending Impleme IDA / 70810 Delivery, Water Resources M Post Open - National 0.00 2025-01-24 2025-03-14 2025-04-04 2025-05-09 2028-11-29 cipal water supply entities an ant Selection ntation anagement and Dam Manag d other rural water supply or ement ganizations on topics: Funda mentals of accounting, taxati on and office work in water s upply enterprises IDA-CRWSP-СOMP2-IC-2025- 16 / Consultant-trainer for tra Institutional Strengthening f ining of employees of local g or Climate Resilient Service overnment employees, muni Individual Consult Pending Impleme IDA / 70810 Delivery, Water Resources M Post Open - National 0.00 2025-01-24 2025-03-14 2025-04-04 2025-05-09 2028-11-29 cipal water supply entities an ant Selection ntation anagement and Dam Manag d other rural water supply or ement ganizations on topics: Drinkin g water disinfection and wate r quality testing IDA-CRWSP-СOMP2-IC-2025- 17 / Consultant-trainer for tra Institutional Strengthening f ining of employees of local g or Climate Resilient Service overnment employees, muni Individual Consult Pending Impleme IDA / 70810 Delivery, Water Resources M Post Open - National 0.00 2025-01-24 2025-03-14 2025-04-04 2025-05-09 2028-11-29 cipal water supply entities an ant Selection ntation anagement and Dam Manag d other rural water supply or ement ganizations on improving the efficiency of water supply ent erprises, operation, maintena nce of WSS... IDA-CRWSP-СOMP2-IC-2025- 18 / Consultant-trainer for tra Institutional Strengthening f ining of employees of local g or Climate Resilient Service overnment employees, muni Individual Consult Pending Impleme IDA / 70810 Delivery, Water Resources M Post Open - National 0.00 2025-01-24 2025-03-14 2025-04-04 2025-05-09 2028-11-29 cipal water supply entities an ant Selection ntation anagement and Dam Manag d other rural water supply or ement ganizations on topics: Develo pment of an economically so und tariff for water supply... Page 5