PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Urban Productive Safety Net and Jobs Project (P169943) Project Implementation agency: Ministry of Labor and Social Affairs (MoLSA), Ministry of Urban Development and Construction (MoUDC), Urban Job Creation and Food Security Agency (UJCFSA) Date of the Procurement Plan: November 2020. Period covered by this Procurement Plan: December 2020 to December 2021. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from page 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : Urban Productive Safety Net and Jobs Project PLAN General Information Country: Ethiopia 2021-08-19 Bank’s Approval Date of the Original Procurement Plan: 2025-01-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169943 GPN Date: 2020-12-18 Project Name: Urban Productive Safety Net and Jobs Project Loan / Credit No: IDA / D7320 SNNPRS Urban Job Creation and Food Security Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-SNNP WOLKETE-324040- Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E 2023-05-0 CW-RFQ / Semi skill labor for IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 15,000.00 0.00 Completed 2022-11-27 2023-05-16 2023-01-02 2023-06-15 tions nvelope 2 Wolkete city to build social in Urban Environment PD) frastructure ET-SNNP HOSAENA-324052- Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E 2023-03-1 CW-RFQ / Semi Skill for Socia IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 4,000.00 0.00 Signed 2022-11-27 2023-06-06 2023-01-02 2023-06-30 tions nvelope 8 l Infrastructure in Hosaena Ci Urban Environment PD) ty ET-SNNP HALABA-324060-C Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E 2023-03-1 W-RFQ / Semi skill for Social i IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 15,000.00 0.00 Completed 2022-11-20 2023-05-24 2022-12-26 2023-06-16 tions nvelope 1 nfrastructure in Halaba city Urban Environment PD) ET-SNNP DILLA -324070-CW- Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E 2023-02-2 RFQ / Semi Skill for Dilla City IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 23,000.00 0.00 Signed 2022-11-15 2023-05-08 2022-12-14 2023-06-15 tions nvelope 7 Social Infrastructure Urban Environment PD) ET-SNNP BUTA JIRA-324075- Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E 2023-01-1 CW-RFQ / Semi Skill for Socia IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 6,000.00 0.00 Completed 2022-11-15 2023-04-17 2022-12-14 2023-05-12 tions nvelope 3 l Infrastructure for Buta Jira C Urban Environment PD) ity ET-SNNP AREKA 324089-CW- Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E 2023-02-1 RFQ / Semi Skill labor for soci IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 3,000.00 0.00 Signed 2022-11-20 2023-05-09 2022-12-22 2023-06-06 tions nvelope 0 al Infrastructure for Areka C Urban Environment PD) ity ET-SNNP ARBA MINCH -3240 Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E 2023-03-0 98-CW-RFQ / Semi skill for so IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 35,000.00 0.00 Completed 2022-11-26 2023-07-24 2023-01-02 2023-08-28 tions nvelope 3 cial infrastructures in Arba Mi Urban Environment PD) nch City ET-SNNP SODO UJCFSA-3477 Request for Quota Foster Urban Youth Employ Request for Quota Single Stage - One E 2023-07-1 18-CW-RFQ / Refurbishment IDA / D7320 Post Limited tions (Non Bank-S 62,000.00 0.00 Signed 2023-03-16 2023-04-11 2023-04-14 2023-05-11 ment tions nvelope 3 of arada OSSP in sodo by 2.2 PD) ET-SNNP DURAME -324065- Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E 2023-02-0 CW-RFQ / Semi Skill for social IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 2,000.00 0.00 Canceled 2022-11-15 2022-12-21 tions nvelope 4 infrastructure in Durame city Urban Environment PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-SNNP SODO-249201-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of safety IDA / D7320 e Safety Net to Improve the Post Limited 41,431.00 21,535.96 Completed 2021-08-29 2021-11-11 2021-09-29 2021-12-27 2021-10-29 2021-12-31 tions nvelope materials for Sodo city Urban Environment ET-SNNP SODO-249203-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Hand t IDA / D7320 e Safety Net to Improve the Post Limited 11,199.00 19,146.14 Completed 2021-08-29 2021-11-11 2021-09-29 2021-11-27 2021-10-29 2022-01-06 tions nvelope ools for Sodo city Urban Environment ET-SNNP ARBA MINCH-2492 Expand the Urban Productiv Request for Quota Single Stage - One E 06-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 44,587.00 265.89 Completed 2021-08-29 2021-10-05 2021-09-29 2021-11-25 2021-10-29 2021-12-12 tions nvelope safety materials for Arba min Urban Environment ch city ET-SNNP ARBA MINCH-2492 Expand the Urban Productiv Request for Quota Single Stage - One E 08-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 11,245.00 19,128.13 Completed 2021-08-29 2021-09-28 2021-09-29 2021-11-18 2021-10-29 2021-12-16 tions nvelope Hand tools for Arba minch cit Urban Environment y ET-SNNP HASAINA-249212-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 38,954.00 21,829.68 Completed 2021-08-29 2021-10-29 2021-09-29 2021-12-06 2021-10-29 2021-12-13 tions nvelope y Material for Hosaina city Urban Environment ET-SNNP HOSAINA-249213-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 9,853.00 18,279.83 Completed 2021-08-29 2021-10-29 2021-09-29 2021-12-06 2021-10-29 2021-12-13 tions nvelope tools for Hosaina City Urban Environment ET-SNNP DILLA-249215-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of safety IDA / D7320 e Safety Net to Improve the Post Limited 31,589.00 0.00 Completed 2021-08-29 2021-10-11 2021-09-29 2021-11-15 2021-10-29 2021-11-29 tions nvelope materials for Dilla city Urban Environment ET-SNNP DILLA-249217-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of hand t IDA / D7320 e Safety Net to Improve the Post Limited 8,597.00 0.00 Completed 2021-08-29 2021-10-11 2021-09-29 2021-11-12 2021-10-29 2021-12-11 tions nvelope ools for Dilla city Urban Environment ET-SNNP BUTAJIRA-249221- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Saf IDA / D7320 e Safety Net to Improve the Post Limited 17,709.00 1,241.35 Completed 2021-08-29 2021-11-16 2021-09-29 2021-12-07 2021-10-29 2021-12-13 tions nvelope ety materials for Butajira city Urban Environment ET-SNNP BUTAJIRA-249224- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of ha IDA / D7320 e Safety Net to Improve the Post Limited 5,242.00 0.00 Completed 2021-08-29 2021-10-22 2021-09-29 2021-11-23 2021-10-29 2021-12-02 tions nvelope nd tools for Butajira city Urban Environment ET-SNNP AREKA-249228-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Safety IDA / D7320 e Safety Net to Improve the Post Limited 34,336.00 0.00 Completed 2021-08-29 2021-11-01 2021-09-26 2021-11-30 2021-10-26 2021-12-09 tions nvelope materials for Areka city Urban Environment ET-SNNP AREKA-249232-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Hand t IDA / D7320 e Safety Net to Improve the Post Limited 8,968.00 0.00 Completed 2021-08-29 2022-03-10 2021-09-29 2022-04-08 2021-10-29 2022-04-17 tions nvelope olls for Areka city Urban Environment Page 1 ET-SNNP WOLKETE-249234- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of saf IDA / D7320 e Safety Net to Improve the Post Limited 31,121.00 0.00 Completed 2021-08-29 2021-11-27 2021-09-29 2021-12-24 2021-10-29 2022-01-22 tions nvelope ety material for wolkete city Urban Environment ET-SNNP WOLKETE-249236- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of ha IDA / D7320 e Safety Net to Improve the Post Limited 8,275.00 0.00 Completed 2021-08-29 2021-11-26 2021-09-29 2021-12-24 2021-10-29 2022-01-12 tions nvelope nd tools for wolkete city Urban Environment ET-SNNP HALABA-249239-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 28,065.00 0.00 Completed 2021-08-29 2021-10-26 2021-09-29 2021-11-22 2021-10-29 2021-11-26 tions nvelope y materials for Halaba city Urban Environment ET-SNNP HALABA-249241-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of hand IDA / D7320 e Safety Net to Improve the Post Limited 7,730.00 0.00 Completed 2021-08-29 2021-10-26 2021-09-29 2021-11-22 2021-10-29 2021-11-26 tions nvelope tools for Halaba city Urban Environment ET-SNNP DURAME-249252-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 24,432.00 0.00 Completed 2021-08-29 2021-10-14 2021-09-29 2021-11-22 2021-10-29 2021-12-22 tions nvelope y materials for Durame city Urban Environment ET-SNNP DURAME-249254-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 6,786.00 0.00 Completed 2021-08-29 2021-10-14 2021-09-29 2021-11-22 2021-10-29 2021-12-22 tions nvelope tools for Durame city Urban Environment ET-SNNP BODITY-249267-GO Expand the Urban Productiv Request for Quota Single Stage - One E -RFQ / Procurement of safety IDA / D7320 e Safety Net to Improve the Post Limited 25,511.00 0.00 Completed 2021-08-29 2021-11-02 2021-09-29 2021-12-06 2021-10-29 2021-12-10 tions nvelope materials for Bidity city Urban Environment ET-SNNP BODITY-249269-GO Expand the Urban Productiv Request for Quota Single Stage - One E -RFQ / Procurement of hand t IDA / D7320 e Safety Net to Improve the Post Limited 6,716.00 0.00 Completed 2021-08-29 2021-11-02 2021-09-29 2021-12-06 2021-10-29 2021-12-10 tions nvelope ools for Bodity City Urban Environment ET-SNNP SAWULA-249271-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 20,193.00 17,587.87 Completed 2021-08-29 2021-11-01 2021-09-29 2021-12-06 2021-10-29 2022-01-29 tions nvelope y materials for Sawula city Urban Environment ET-SNNP SAWULA-249272-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of hand IDA / D7320 e Safety Net to Improve the Post Limited 6,490.00 3,432.53 Completed 2021-08-29 2021-11-01 2021-09-29 2021-12-06 2021-10-29 2022-04-18 tions nvelope tools for sawula city Urban Environment ET-SNNP UJCFSA-324018-GO -RFQ / Procurement of laptop Foster Urban Youth Employ Request for Quota Single Stage - One E computer, printer and Project IDA / D7320 Post Limited 9,230.00 0.00 Canceled 2022-11-09 2022-12-04 2023-01-03 ment tions nvelope or for wolayta sodo city in th e youth apprenticeship progr am ET-SNNP UJCFSA-324019-GO -RFQ / Procurement of office Foster Urban Youth Employ Request for Quota Single Stage - One E IDA / D7320 Post Limited 200.00 0.00 Completed 2022-11-13 2023-06-01 2022-12-12 2023-06-27 2023-01-12 2023-07-06 table and chair for Wolayta s ment tions nvelope odo city in the Youth Apprent iceship program ET-SNNP SODO-324021-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of hand t IDA / D7320 e Safety Net to Improve the Post Limited 49,500.00 0.00 Completed 2022-11-13 2023-02-21 2022-12-12 2023-03-09 2023-01-11 2023-03-21 tions nvelope ools for Sodo City Urban Environment ET-SNNP SODO-324023-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Safety IDA / D7320 e Safety Net to Improve the Post Limited 98,000.00 0.00 Completed 2022-11-13 2023-02-21 2022-12-12 2023-03-17 2023-01-11 2023-03-29 tions nvelope Material for Sodo city Urban Environment ET-SNNP SODO-324024-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Leathe IDA / D7320 e Safety Net to Improve the Post Limited 44,000.00 0.00 Completed 2022-11-13 2023-02-21 2022-12-12 2023-03-17 2023-01-11 2023-03-29 tions nvelope r Glove for Sodo city Urban Environment ET-SNNP WOLKETE-324032- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Ha IDA / D7320 e Safety Net to Improve the Post Limited 7,800.00 0.00 Completed 2022-11-13 2023-02-07 2022-12-12 2023-03-16 2023-01-11 2023-04-05 tions nvelope nd tools for wolkete city Urban Environment ET-SNNP WOLKETE-324034- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Saf IDA / D7320 e Safety Net to Improve the Post Limited 49,000.00 0.00 Completed 2022-11-13 2023-01-24 2022-12-25 2023-03-15 2023-01-24 2023-03-31 tions nvelope ety Materials for Wolkete City Urban Environment ET-SNNP WOLKETE-324036- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Ind IDA / D7320 e Safety Net to Improve the Post Limited 24,380.00 0.00 Completed 2022-11-13 2023-02-07 2022-12-12 2023-03-16 2023-01-11 2023-04-05 tions nvelope ustrial Construction materials Urban Environment ET-SNNP WOLKETE-324037- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Loc IDA / D7320 e Safety Net to Improve the Post Limited 41,000.00 0.00 Completed 2022-11-13 2023-02-13 2022-12-12 2023-04-15 2023-01-11 2023-05-26 tions nvelope al Construction Materials Urban Environment ET-SNNP SAWULA-324041-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 14,000.00 0.00 Completed 2022-11-13 2023-01-30 2022-12-12 2023-02-27 2023-01-11 2023-03-27 tions nvelope Tools for Sawula City Urban Environment ET-SNNP SAWULA-324043-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 52,000.00 0.00 Completed 2022-11-14 2023-01-30 2022-12-20 2023-02-27 2023-01-19 2023-03-22 tions nvelope y Materials for Sawula City Urban Environment ET-SNNPHOSANA 324047-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of hand IDA / D7320 e Safety Net to Improve the Post Limited 97,000.00 0.00 Completed 2022-11-15 2023-01-23 2022-12-14 2023-02-27 2023-01-26 2023-03-08 tions nvelope tools for HOSAENA City Urban Environment ET-SNNP HOSAENA -324048- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Saf IDA / D7320 e Safety Net to Improve the Post Limited 97,500.00 0.00 Completed 2022-11-15 2023-02-03 2022-12-14 2023-02-28 2023-01-13 2023-03-24 tions nvelope ety Materials Urban Environment ET-SNNP HOSAENA-324050- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Ind IDA / D7320 e Safety Net to Improve the Post Limited 33,000.00 0.00 Completed 2022-11-15 2023-04-27 2022-12-14 2023-06-19 2023-01-13 2023-07-06 tions nvelope ustrial Construction Materials Urban Environment ET-SNNP HOSAENA-324051- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Loc IDA / D7320 e Safety Net to Improve the Post Limited 58,000.00 0.00 Completed 2022-11-15 2023-05-29 2022-12-14 2023-06-26 2023-01-13 2023-07-05 tions nvelope al Construction materials Urban Environment ET-SNNP HALABA-324053-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 26,000.00 0.00 Completed 2022-11-15 2022-12-26 2022-12-14 2023-01-24 2023-01-13 2023-01-31 tions nvelope Tools for Halaba City Urban Environment Page 2 ET-SNNP HALABA -324055-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 48,000.00 0.00 Completed 2022-11-15 2022-12-26 2022-12-15 2023-01-24 2023-01-14 2023-01-31 tions nvelope y Materials for Halaba City Urban Environment ET-SNNP HALABA-324056-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Indu IDA / D7320 e Safety Net to Improve the Post Limited 35,000.00 0.00 Completed 2022-11-15 2023-05-09 2022-12-14 2023-06-01 2023-01-13 2023-06-10 tions nvelope strial Construction Materials f Urban Environment or Halaba City ET-SNNP HALABA-324059-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Local IDA / D7320 e Safety Net to Improve the Post Limited 2,000.00 0.00 Completed 2022-11-15 2023-04-21 2022-12-13 2023-05-18 2023-01-12 2023-06-05 tions nvelope Construction materials Urban Environment ET-SNNP DURAME-324061-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 60,500.00 0.00 Completed 2022-11-15 2023-01-30 2022-12-14 2023-02-22 2023-01-13 2023-02-24 tions nvelope Tools for Durame city Urban Environment ET-SNNP DURAME-324062-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 98,000.00 0.00 Completed 2022-11-15 2023-01-30 2022-12-15 2023-05-29 2023-01-14 2023-06-19 tions nvelope y Materials for Durame city Urban Environment ET-SNNP DURAME-324063-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Indu IDA / D7320 e Safety Net to Improve the Post Limited 18,000.00 0.00 Completed 2022-11-15 2023-03-24 2022-12-14 2023-04-21 2023-01-13 2023-04-28 tions nvelope strial Construction Materials Urban Environment ET-SNNP DURAME -324064- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Loc IDA / D7320 e Safety Net to Improve the Post Limited 3,000.00 0.00 Completed 2022-11-15 2023-06-05 2022-12-14 2023-06-24 2023-01-13 2023-07-08 tions nvelope al Construction Material for D Urban Environment urame city ET-SNNP DILLA-324066-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Hand T IDA / D7320 e Safety Net to Improve the Post Limited 65,000.00 0.00 Completed 2022-11-15 2022-12-21 2022-12-14 2023-01-30 2023-01-13 2023-02-17 tions nvelope ools for Dilla City Urban Environment ET-SNNP DILLA -324067-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Safety IDA / D7320 e Safety Net to Improve the Post Limited 96,000.00 0.00 Completed 2022-11-15 2022-12-21 2022-12-14 2023-01-30 2023-01-13 2023-02-17 tions nvelope Materials Urban Environment ET-SNNP DILLA -324068-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Industr IDA / D7320 e Safety Net to Improve the Post Limited 65,000.00 0.00 Completed 2022-11-15 2023-04-25 2022-12-14 2023-05-25 2023-01-13 2023-05-29 tions nvelope ial Construction Materials for Urban Environment Dill City ET-SNNP DILLA -324069-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Local C IDA / D7320 e Safety Net to Improve the Post Limited 40,000.00 0.00 Completed 2022-11-15 2023-04-27 2022-12-14 2023-05-24 2023-01-13 2023-06-12 tions nvelope onstruction Materials Urban Environment ET-SNNP BUTAJIRA-324071- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Ha IDA / D7320 e Safety Net to Improve the Post Limited 23,500.00 0.00 Completed 2022-11-12 2023-02-16 2022-12-11 2023-02-22 2023-01-10 2023-02-26 tions nvelope nd Tools for Butajira City Urban Environment ET-SNNP BUTAJIRA-324072- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Saf IDA / D7320 e Safety Net to Improve the Post Limited 72,000.00 0.00 Completed 2022-11-15 2023-01-16 2022-12-14 2023-03-03 2023-01-13 2023-03-24 tions nvelope ety Materials for Buta jira Cit Urban Environment y ET-SNNP BUTA JIRA -324073- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Ind IDA / D7320 e Safety Net to Improve the Post Limited 41,000.00 0.00 Completed 2022-11-15 2023-05-29 2022-12-14 2023-06-30 2023-01-13 2023-07-06 tions nvelope ustrial Construction Material f Urban Environment or Buta Jira City ET-SNNP BUTA JIRA-324074- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Loc IDA / D7320 e Safety Net to Improve the Post Limited 13,000.00 0.00 Completed 2022-11-15 2023-05-29 2022-12-14 2023-06-23 2023-01-13 2023-07-07 tions nvelope al Construction materials for Urban Environment Buta Jira City ET-SNNP BODETE -324078-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 12,000.00 0.00 Completed 2022-11-15 2022-12-06 2022-12-14 2023-01-25 2023-01-13 2023-02-03 tions nvelope tools for Bodete Urban Environment ET-SNNP BODETE 324079-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 42,000.00 0.00 Completed 2022-11-15 2022-12-06 2022-12-14 2023-01-25 2023-01-13 2023-02-03 tions nvelope y Materials for Bodete City Urban Environment ET-SNNP BODETE -324080-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Indu IDA / D7320 e Safety Net to Improve the Post Limited 13,000.00 0.00 Completed 2022-11-15 2023-05-11 2022-12-14 2023-06-06 2023-01-13 2023-06-15 tions nvelope strial Construction Materials Urban Environment ET-SNNP BODETE-324082-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Local IDA / D7320 e Safety Net to Improve the Post Limited 7,000.00 0.00 Completed 2022-11-15 2023-05-01 2022-12-14 2023-05-26 2023-01-13 2023-06-04 tions nvelope Construction Materials for Bo Urban Environment dity City ET-SNNP AREKA -324083-GO Expand the Urban Productiv Request for Quota Single Stage - One E -RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 12,000.00 0.00 Completed 2022-11-15 2023-01-13 2022-12-15 2023-02-27 2023-01-14 2023-04-04 tions nvelope Tools for Areka City Urban Environment ET-SNNP AREKA -324085-GO Expand the Urban Productiv Request for Quota Single Stage - One E -RFQ / Procurement of Safety IDA / D7320 e Safety Net to Improve the Post Limited 63,000.00 0.00 Completed 2022-11-15 2023-02-08 2022-12-17 2023-02-27 2023-01-16 2023-03-24 tions nvelope Materials for Areka City Urban Environment ET-SNNPAREKA -324087-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Industr IDA / D7320 e Safety Net to Improve the Post Limited 31,000.00 0.00 Completed 2022-11-15 2023-01-13 2022-12-17 2023-02-27 2023-01-16 2023-04-04 tions nvelope ial Construction Materials Urban Environment ET-SNNP AREKA -324088-GO Expand the Urban Productiv Request for Quota Single Stage - One E -RFQ / Procurement of Local IDA / D7320 e Safety Net to Improve the Post Limited 7,000.00 0.00 Completed 2022-11-16 2023-01-20 2022-12-18 2023-02-15 2023-01-17 2023-03-27 tions nvelope Construction Materials for Ar Urban Environment eka City ET-SNNP ARBA MINCH -3240 Expand the Urban Productiv Request for Quota Single Stage - One E 91-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 38,000.00 0.00 Completed 2022-11-19 2023-04-26 2022-12-18 2023-05-21 2023-01-17 2023-07-05 tions nvelope Hand tools for Arba Minch Cit Urban Environment y ET-SNNP ARBA MINCH -3240 Expand the Urban Productiv Request for Quota Single Stage - One E 92-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 96,000.00 0.00 Completed 2022-11-19 2022-12-14 2022-12-18 2023-03-08 2023-01-17 2023-04-18 tions nvelope Safety Clothes, hats and Mas Urban Environment ks ET-SNNP ARBA MINCH -3240 Expand the Urban Productiv Request for Quota Single Stage - One E 94-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 52,000.00 0.00 Completed 2022-11-19 2023-04-27 2022-12-19 2023-05-23 2023-01-18 2023-06-11 tions nvelope Safety Shoos and Protective Urban Environment gloves ET-SNNP ARBA MINCH -3240 Expand the Urban Productiv Request for Quota Single Stage - One E 95-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 22,000.00 0.00 Completed 2022-11-19 2023-04-26 2022-12-18 2023-07-13 2023-01-18 2023-07-22 tions nvelope Industrial Construction Materi Urban Environment als Page 3 ET-SNNP ARBA MINCH -3240 Expand the Urban Productiv Request for Quota Single Stage - One E 96-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 39,000.00 0.00 Completed 2022-11-19 2023-04-26 2022-12-21 2023-07-12 2023-01-30 2023-08-25 tions nvelope local construction Materials Urban Environment ET-SNNP UJCFSA-334510-GO -RFQ / Procurement of Desk t op computers, laptop comput Foster Urban Youth Employ Request for Quota Single Stage - One E IDA / D7320 Post Limited 76,425.00 0.00 Completed 2023-01-18 2023-05-12 2023-02-16 2023-06-24 2023-03-18 2023-07-03 er, printer, and LCD Projector ment tions nvelope for SNNPR Regional Hub and for Sodo city in youth employ ment ET-SNNP- BODETE--355120- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of ind IDA / D7320 e Safety Net to Improve the Post Limited 25,500.00 0.00 Completed 2023-06-29 2023-05-11 2023-07-28 2023-06-07 2023-08-27 2023-06-16 tions nvelope ustrial Construction Materials Urban Environment for bodete city ET-SNNP-WOLKETE-367596- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of See IDA / D7320 e Safety Net to Improve the Post Limited 9,000.00 0.00 Completed 2023-06-29 2023-06-26 2023-07-26 2023-07-19 2023-08-15 2023-08-07 tions nvelope dling for Wolkete city Urban Environment ET-SNNP- ARBA MINCH-3676 Expand the Urban Productiv Request for Quota Single Stage - One E 08-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 25,000.00 0.00 Completed 2023-06-29 2023-06-07 2023-07-26 2023-08-01 2023-08-15 2023-08-21 tions nvelope seedling for Arba Minch city Urban Environment ET-SNNP ARBA MINCH-3240 25-GO-RFQ / Procurement of Expand the Urban Productiv Request for Quota Single Stage - One E Industrial Construction mater IDA / D7320 e Safety Net to Improve the Post Limited 72,000.00 0.00 Canceled 2023-01-18 2023-02-16 2023-03-18 tions nvelope ials y for construction of publ Urban Environment ic toilets in Arba Minch city ET-SNNP SODO-324027-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Local C IDA / D7320 e Safety Net to Improve the Post Limited 35,000.00 0.00 Canceled 2022-11-13 2022-12-12 2023-01-11 tions nvelope onstruction Materials for Sod Urban Environment o city ET-SNNP SODO-367412-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of seedlin IDA / D7320 e Safety Net to Improve the Post Limited 30,000.00 0.00 Canceled 2023-06-29 2023-07-21 2023-08-10 tions nvelope g for Wolayta Sodo City Urban Environment ET-SNNP - BODETE-367606- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of see IDA / D7320 e Safety Net to Improve the Post Limited 2,500.00 0.00 Canceled 2023-06-29 2023-07-26 2023-08-15 tions nvelope dling for Bodete City Urban Environment ET-SNNP -DILLA-367603-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of seedlin IDA / D7320 e Safety Net to Improve the Post Limited 8,000.00 0.00 Canceled 2023-06-29 2023-07-26 2023-08-15 tions nvelope gs for Dilla city Urban Environment ET-SNNP-AREKA-367613-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Seedlin IDA / D7320 e Safety Net to Improve the Post Limited 2,500.00 0.00 Canceled 2023-06-29 2023-07-26 2023-08-15 tions nvelope g for Areka city Urban Environment ET-SNNP SAWULA-367597-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of seed IDA / D7320 e Safety Net to Improve the Post Limited 8,000.00 0.00 Canceled 2023-06-29 2023-07-28 2023-08-17 tions nvelope lings for sawula city Urban Environment ET-SNNPSAWULA-324044-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Indu IDA / D7320 e Safety Net to Improve the Post Limited 22,000.00 0.00 Canceled 2022-11-15 2022-12-14 2023-01-13 tions nvelope strial Construction Materials Urban Environment ET-SNNP- DURAME-367602- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of see IDA / D7320 e Safety Net to Improve the Post Limited 7,500.00 0.00 Canceled 2023-06-29 2023-07-26 2023-08-15 tions nvelope dling for Durame city Urban Environment ET-SNNP SODO-324029-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of hollow IDA / D7320 e Safety Net to Improve the Post Limited 8,500.00 0.00 Canceled 2022-11-13 2022-12-12 2023-01-11 tions nvelope concrete Block and terrazzo Urban Environment ET-SNNP SODO-324028-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Cerami IDA / D7320 e Safety Net to Improve the Post Limited 49,000.00 0.00 Canceled 2022-11-13 2022-12-12 2023-01-11 tions nvelope c Tails for sodo city Urban Environment ET-SNNP HALABA KOLITO-36 Expand the Urban Productiv Request for Quota Single Stage - One E 7600-GO-RFQ / Procurement IDA / D7320 e Safety Net to Improve the Post Limited 9,500.00 0.00 Canceled 2023-06-28 2023-07-25 2023-08-14 tions nvelope of seedling for Halaba Kolito Urban Environment city ET-SNNP SAWULA -324045- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Loc IDA / D7320 e Safety Net to Improve the Post Limited 9,000.00 0.00 Canceled 2022-11-14 2022-12-13 2023-01-12 tions nvelope al Construction Materials Urban Environment ET-SNNP SODO-324030-GO- Expand the Urban Productiv DIR / Procurement of cement IDA / D7320 e Safety Net to Improve the Post Direct Selection Direct - National 87,000.00 0.00 Canceled 2022-11-21 2022-11-26 2022-12-11 2023-02-09 for Sodo City Urban Environment ET-SNNP HOSAENA-367598- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of see IDA / D7320 e Safety Net to Improve the Post Limited 8,000.00 0.00 Canceled 2023-06-29 2023-08-24 2024-02-20 tions nvelope dling for Hosaena city Urban Environment ET-SNNP- BUTAJIRA-367604- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of see IDA / D7320 e Safety Net to Improve the Post Limited 9,000.00 0.00 Canceled 2023-06-29 2023-07-26 2023-08-15 tions nvelope dlingd for butajira Urban Environment ET-SNNP SODO-324031-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Tents f IDA / D7320 e Safety Net to Improve the Post Limited 49,000.00 0.00 Canceled 2022-11-14 2022-12-13 2023-01-12 tions nvelope or child protection for SODO Urban Environment City ET-SNNP MIZAN-249262-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of hand t IDA / D7320 e Safety Net to Improve the Post Limited 6,406.00 0.00 Canceled 2021-08-29 2021-09-29 2021-10-29 tions nvelope ools for Mizan Aman city Urban Environment ET-SNNP MIZAN-249260-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Safety IDA / D7320 e Safety Net to Improve the Post Limited 24,883.00 0.00 Canceled 2021-08-29 2021-09-29 2021-10-29 tions nvelope materials for mizan aman cit Urban Environment y ET-SNNP TEPI-249245-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Q / Procurement of safety ma IDA / D7320 e Safety Net to Improve the Post Limited 26,687.00 0.00 Canceled 2021-08-29 2021-09-29 2021-10-29 tions nvelope terials for Tepi city Urban Environment ET-SNNP TEPI-249247-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Q / Procurement of hand tool IDA / D7320 e Safety Net to Improve the Post Limited 6,842.00 0.00 Canceled 2021-08-25 2021-09-25 2021-10-25 tions nvelope s for Tepi city Urban Environment Page 4 ET-SOUTH ETH - DILLA-3954 Expand the Urban Productiv Request for Quota Single Stage - One E 82-GO-RFQ / procurement of IDA / D7320 e Safety Net to Improve the Post Limited - National 94,044.00 0.00 Completed 2024-04-05 2024-05-16 2024-05-04 2024-06-11 2024-06-03 2024-07-01 tions nvelope safety material dilla. Urban Environment ET-SOUTH ETH - DILLA -3954 Expand the Urban Productiv 93-GO-RFQ / procurement of Request for Quota Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Limited - National 91,950.00 0.00 Completed 2024-04-05 2024-05-16 2024-05-04 2024-06-04 2024-05-24 2024-06-22 industrial construction materi tions nvelope Urban Environment al and hand tools for dilla cit y. ET-SOUTH ETH - DILLA-3954 Expand the Urban Productiv Request for Quota Single Stage - One E 96-GO-RFQ / procurement of IDA / D7320 e Safety Net to Improve the Post Limited - National 39,779.00 0.00 Completed 2024-04-05 2024-05-16 2024-05-04 2024-06-04 2024-06-03 2024-07-03 tions nvelope local construction material, d Urban Environment iila city. ET-SOUTH ETH - DILLA-3955 Expand the Urban Productiv Request for Quota Single Stage - One E 00-GO-RFQ / procurement of IDA / D7320 e Safety Net to Improve the Post Limited - National 8,378.00 0.00 Completed 2024-04-13 2024-05-17 2024-05-21 2024-06-14 2024-06-06 2024-07-05 tions nvelope seedling, dilla city Urban Environment ET-SOUTH ETH - AREKA-396 Expand the Urban Productiv 078-GO-RFQ / procurement o Request for Quota Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Limited - National 91,200.00 0.00 Completed 2024-04-05 2024-04-18 2024-05-04 2024-05-04 2024-06-05 2024-07-03 f industrial construction mate tions nvelope Urban Environment rial, safety materials and han d tools for Areka city ET-SOUTH ETH - BODITI-396 Expand the Urban Productiv Request for Quota Single Stage - One E 162-GO-RFQ / procurement o IDA / D7320 e Safety Net to Improve the Post Limited - National 19,464.00 0.00 Completed 2024-04-05 2024-05-13 2024-05-04 2024-05-28 2024-06-03 2024-05-31 tions nvelope f safety material, bodity city Urban Environment . ET-SOUTH ETH - BODITY-396 Expand the Urban Productiv 166-GO-RFQ / Procurement o Request for Quota Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Limited - National 66,400.00 0.00 Completed 2024-04-05 2024-04-19 2024-05-04 2024-05-18 2024-05-24 2024-06-02 f industrial Construction mat tions nvelope Urban Environment erial and hand tools for Bodit y city ET-SOUTH ETH - BODITY-396 Expand the Urban Productiv Request for Quota Single Stage - One E 169-GO-RFQ / Procurement o IDA / D7320 e Safety Net to Improve the Post Limited - National 26,190.00 0.00 Completed 2024-04-20 2024-04-19 2024-05-19 2024-05-18 2024-06-09 2024-05-30 tions nvelope f seedling for Bodity city. Urban Environment ET- SOUTH ETH - AREKA-396 Expand the Urban Productiv Request for Quota Single Stage - One E 171-GO-RFQ / procurement o IDA / D7320 e Safety Net to Improve the Post Limited - National 19,675.00 0.00 Completed 2024-04-05 2024-04-17 2024-05-04 2024-05-16 2024-05-25 2024-07-05 tions nvelope f local construction material, Urban Environment Areka city ET-SOUTH ETH - SODO-396 Expand the Urban Productiv Request for Quota Single Stage - One E 173-GO-RFQ / procurement o IDA / D7320 e Safety Net to Improve the Post Limited - National 97,800.00 0.00 Completed 2024-03-24 2024-04-12 2024-04-22 2024-04-26 2024-05-12 2024-05-22 tions nvelope f industrial construction mate Urban Environment rial, Sodo city ET- SOUTH ETH - SODO-396 Expand the Urban Productiv Request for Quota Single Stage - One E 174-GO-RFQ / procurement o IDA / D7320 e Safety Net to Improve the Post Limited - National 99,115.00 0.00 Completed 2024-04-05 2024-04-12 2024-05-04 2024-04-26 2024-06-03 2024-05-22 tions nvelope f local construction material f Urban Environment or Sodo city ET-SOUTH ETH - SODO - 396 Expand the Urban Productiv 175-GO-RFQ / procurement o Request for Quota Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Limited - National 59,500.00 0.00 Completed 2024-03-23 2024-04-26 2024-04-21 2024-05-15 2024-05-21 2024-07-05 f safety material and hand to tions nvelope Urban Environment ols for Sodo city ET- SOUTH ETH - SODO - 39 Expand the Urban Productiv Request for Quota Single Stage - One E 6180-GO-RFQ / procurement IDA / D7320 e Safety Net to Improve the Post Limited - National 17,506.00 0.00 Canceled 2024-04-15 2024-05-14 2024-06-13 tions nvelope of seedling, sodo city. Urban Environment ET-SE-ARBA MINCH-415274- Expand the Urban Productiv GO-RFQ / Procurement of Loc Request for Quota Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Limited - National 44,020.00 0.00 Completed 2024-04-05 2024-04-01 2024-05-04 2024-05-04 2024-05-23 2024-06-03 al Construction Materials FOR tions nvelope Urban Environment Arba minch city. ET-SOUTH ETH - ARBA MINC Expand the Urban Productiv H-396193-GO-RFQ / Procure Request for Quota Single Stage - One E Under Imple IDA / D7320 e Safety Net to Improve the Post Limited - National 97,000.00 0.00 2024-04-05 2024-05-04 2024-06-03 ment of reinforced bar, hand tions nvelope mentation Urban Environment tools and cement for Arba mi nch city. ET-SOUTH ETH - ARBA MINC Expand the Urban Productiv Request for Quota Single Stage - One E H-396196-GO-RFQ / Procure IDA / D7320 e Safety Net to Improve the Post Limited - National 2,800.00 0.00 Completed 2024-04-15 2024-03-12 2024-05-14 2024-04-14 2024-06-05 2024-05-13 tions nvelope ment of seedling for Arba mi Urban Environment nch city. ET-SOUTH ETH - SAWELA-39 6200-GO-RFQ / Procurement Expand the Urban Productiv Request for Quota Single Stage - One E Under Imple of Industrial Construction Mat IDA / D7320 e Safety Net to Improve the Post Limited - National 92,608.00 0.00 2024-04-05 2024-05-04 2024-06-03 tions nvelope mentation erials in lot one and Local Co Urban Environment nstruction materials for sawe la city ET-SOUTH ETH - SAWELA-39 Expand the Urban Productiv Request for Quota Single Stage - One E Under Imple 6206-GO-RFQ / Procurement IDA / D7320 e Safety Net to Improve the Post Limited - National 3,392.00 0.00 2024-04-24 2024-05-23 2024-06-12 tions nvelope mentation of seedling for sawela city Urban Environment ET-SOUTH ETH - BODITY-396 Expand the Urban Productiv Request for Quota Single Stage - One E 260-GO-RFQ / procurement o IDA / D7320 e Safety Net to Improve the Post Limited - National 37,400.00 0.00 Completed 2024-04-05 2024-04-19 2024-05-04 2024-05-17 2024-06-03 2024-06-02 tions nvelope f Local construction Materials Urban Environment for bodity city. ET- SOUTH ETH- AREKA -411 Expand the Urban Productiv Request for Quota Single Stage - One E 037-GO-RFQ / procurement o IDA / D7320 e Safety Net to Improve the Post Limited - National 1,330.00 0.00 Canceled 2024-04-21 2024-05-20 2024-06-11 tions nvelope f seedling for Areka city. Urban Environment ET-SNNP UJCFSA-419401-GO Institutional Strengthening, -RFQ / Procurement of laptop Request for Quota Single Stage - One E Pending Impl IDA / D7320 Project Management and Mo Post Limited - National 10,277.00 0.00 2024-04-09 2024-05-17 2024-06-16 computer and printer for sou tions nvelope ementation nitoring and Evaluation thern Ethiopia Regional hub and cities ET-SOUTH ETH- ARBA MINCH Expand the Urban Productiv Request for Quota Single Stage - One E -411876-GO-RFQ / procurem IDA / D7320 e Safety Net to Improve the Post Limited - National 97,746.00 0.00 Completed 2024-04-05 2024-04-11 2024-05-04 2024-05-04 2024-06-03 2024-06-03 tions nvelope ent of safety material for arb Urban Environment a minch city ET-SOUTH ETH- ARBA MINCH Expand the Urban Productiv - 411879-GO-RFQ / Procurem Request for Quota Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Limited - National 99,500.00 0.00 Completed 2024-04-05 2024-04-01 2024-05-04 2024-05-04 2024-06-03 2024-06-03 ent of Industrial Construction tions nvelope Urban Environment Materials for arba minch city. ET-SOUTHETH-BODITI-46791 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 5-GO-RFQ / procurement of s IDA / D7320 e Safety Net to Improve the Post Limited - National 50,200.00 0.00 2025-01-15 2025-02-07 2025-02-12 tions nvelope ementation afety material for boditi city. Urban Environment ET-SOUTHETH- DILLA-46797 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 7-GO-RFQ / procurement of s IDA / D7320 e Safety Net to Improve the Post Limited - National 66,800.00 0.00 2025-01-15 2025-02-07 2025-02-12 tions nvelope ementation afety material for DILLA city Urban Environment Page 5 ET-SOUTHETH- ARBAMINCH- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 467979-GO-RFQ / procureme IDA / D7320 e Safety Net to Improve the Post Limited - National 86,100.00 0.00 2025-01-15 2025-02-07 2025-02-12 tions nvelope ementation nt of safety material for Arba Urban Environment Minch city. ET-SOUTHETH- SAWELA-467 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 980-GO-RFQ / procurement o IDA / D7320 e Safety Net to Improve the Post Limited - National 26,800.00 0.00 2025-01-15 2025-02-07 2025-02-12 tions nvelope ementation f safety material for sawela ci Urban Environment ty. ET-SOUTHETH-SODO-46798 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 3-GO-RFQ / procurement of p IDA / D7320 e Safety Net to Improve the Post Limited - National 83,600.00 0.00 2025-01-15 2025-02-07 2025-02-12 tions nvelope ementation rotective cloth and gloves for Urban Environment sodo city. ET-SOUTHETH-SODO-46798 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 5-GO-RFQ / procurement of s IDA / D7320 e Safety Net to Improve the Post Limited - National 94,000.00 0.00 2025-01-15 2025-02-07 2025-02-12 tions nvelope ementation afety material for sodo city. Urban Environment ET-SOUTH ETH- AREKA-4681 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 13-GO-RFQ / procurement of IDA / D7320 e Safety Net to Improve the Post Limited - National 30,200.00 0.00 2025-01-15 2025-02-07 2025-02-12 tions nvelope ementation safety material for Areka city Urban Environment ET-SOUTHETH- BUID-468115 -GO-RFQ / procurement of la Institutional Strengthening, Request for Quota Single Stage - One E Pending Impl ptop computers and Portable IDA / D7320 Project Management and Mo Post Limited - National 6,000.00 0.00 2025-01-18 2025-02-13 2025-02-28 tions nvelope ementation hard disk storage device for s nitoring and Evaluation outh Ethiopia UPSNJP regiona l hub NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-SOUTH ETH - DILLA-3954 Expand the Urban Productiv Request for Quota Single Stage - One E 97-CW-RFQ / semi skill to con IDA / D7320 e Safety Net to Improve the Post Limited - National 51,235.00 0.00 Completed 2024-04-07 2024-05-27 2024-05-06 2024-06-17 2024-07-05 2024-09-08 tions nvelope struct social infrastructure in Urban Environment dilla city ET-SOUTH ETH - ARKA - 411 Expand the Urban Productiv 030-NC-RFQ / procurement of Request for Quota Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Limited - National 24,224.00 0.00 Signed 2024-04-12 2024-04-19 2024-05-11 2024-05-11 2024-06-25 Semi skill to construct small tions nvelope Urban Environment social infrastructure in areka city. ET-SOUTH ETH - BODITY - 39 Expand the Urban Productiv 6212-NC-RFQ / procurement Request for Quota Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Limited - National 3,267.00 0.00 Canceled 2024-04-13 2024-05-12 2024-07-11 of semi skill to construct soci tions nvelope Urban Environment al infrastructure in bodity cit y ET-SOUTH ETH - SODO-396 Expand the Urban Productiv 183-NC-RFQ / procurement of Request for Quota Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Limited - National 94,000.00 0.00 Completed 2024-04-03 2024-04-12 2024-04-30 2024-04-28 2024-07-14 2024-09-07 semi skill to construct Condo tions nvelope Urban Environment minium area greenery areas i n Sodo city. ET- SOUTH ETH ARBA MINC H-396194-NC-RFQ / Procure Expand the Urban Productiv Request for Quota Single Stage - One E ment of semi skill for two blo IDA / D7320 e Safety Net to Improve the Post Limited - National 98,197.00 0.00 Signed 2024-04-13 2024-04-11 2024-05-12 2024-05-17 2024-07-11 tions nvelope ck maintenance for sikila pri Urban Environment mary school in Arba Minch cit y. ET-SOUTH ETH - SAWELA-39 Expand the Urban Productiv 6207-NC-RFQ / Procurement Request for Quota Single Stage - One E Under Imple IDA / D7320 e Safety Net to Improve the Post Limited - National 36,524.00 0.00 2024-04-10 2024-05-09 2024-07-08 of semi skill to construct soci tions nvelope mentation Urban Environment al infrastructure in bodity cit y ET-SOUTH ETH -SODO-4118 Expand the Urban Productiv 70-NC-RFQ / procurement of Request for Quota Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Limited - National 23,819.00 0.00 Completed 2024-04-05 2024-04-12 2024-05-03 2024-04-27 2024-07-17 2024-09-07 semi skill for NOC area Green tions nvelope Urban Environment area development in Sodo cit y. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-SNNP UJCFSA-324014-CS- Institutional Strengthening, Individual Consult INDV / Recruitment of procur IDA / D7320 Project Management and Mo Post Limited 5,000.00 0.00 Signed 2022-11-07 2023-01-04 2022-11-12 2023-02-10 2022-12-03 2023-03-03 2022-12-28 2023-05-15 2023-12-28 ant Selection ement Specialist for SNNP Re nitoring and Evaluation gional Hub ET-SNNP UJCFSA-324015-CS- Institutional Strengthening, Individual Consult INDV / Recruitment of Gende IDA / D7320 Project Management and Mo Post Open - National 5,000.00 0.00 Signed 2022-11-07 2023-01-04 2022-12-12 2023-03-07 2022-12-22 2023-03-17 2023-01-23 2023-06-15 2024-01-23 ant Selection r Specialist for SNNP regional nitoring and Evaluation Hub ET-SNNP UJCFSA-324016-CS- Institutional Strengthening, Individual Consult INDV / Recruitment of safegu IDA / D7320 Project Management and Mo Post Open - National 5,000.00 0.00 Signed 2022-11-07 2023-01-04 2022-12-12 2023-03-07 2022-12-27 2023-03-17 2023-01-27 2023-06-15 2024-01-27 ant Selection ard Specialist for SNNP Regio nitoring and Evaluation nal Hub ET-SNNP UJCFSA-324017-CS- INDV / Recruitment of Youth Foster Urban Youth Employ Individual Consult IDA / D7320 Post Open - National 4,000.00 0.00 Signed 2022-11-07 2023-01-04 2022-12-12 2023-03-07 2022-12-27 2023-03-17 2023-01-27 2023-05-15 2024-01-27 Employment apprenticeship ment ant Selection specialist for Wolayta Sodo C ity ET-SNNP UJCFSA-324020-CS- INDV / Recruitment of Public Institutional Strengthening, Individual Consult Work Specialist with assignm IDA / D7320 Project Management and Mo Post Open - National 5,000.00 0.00 Signed 2022-11-07 2023-01-04 2022-12-27 2023-03-07 2023-01-11 2023-03-17 2023-02-11 2023-06-15 2024-02-11 ant Selection ent to handle the Livelihood nitoring and Evaluation component for SNNP Regiona l hub ET-SNNP UJCFSA-248275-CS- Institutional Strengthening, INDV / Recruitment of Public Individual Consult IDA / D7320 Project Management and Mo Post Open 5,600.00 0.00 Canceled 2021-08-20 2021-09-23 2021-10-08 2021-11-02 2022-11-02 work specialist with ability to ant Selection nitoring and Evaluation handle Lively hood Page 6 ET-SNNP UJCFSA-248272-CS- Institutional Strengthening, INDV / Recruitment of individ Individual Consult IDA / D7320 Project Management and Mo Post Open 5,600.00 0.00 Canceled 2021-09-06 2021-10-10 2021-10-20 2021-11-14 2022-11-14 ual consultant/ Safeguard sp ant Selection nitoring and Evaluation ecialist for SNNPRS Regional hub ET-SOUTH ETH- BOUID-4681 Institutional Strengthening, 67-CS-INDV / Recruitment of Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Prior Open - National 3,100.00 0.00 2025-01-13 2025-02-17 2025-03-04 2025-04-08 2026-04-08 Procurement specialist for so ant Selection ntation nitoring and Evaluation uthern Ethiopia Regional Hub Page 7