Procurement Plan (Textual Part) I. General 1. Project Information Country: Senegal Project Name: Saint-Louis Emergency Recovery and Resilience Project Project Id: P166538 Project Implementation Agency: Municipal Development Agency Date of the Procurement Plan: Septembre 2018 2. Period Covered by this procurement plan: Septembre 2018 to March 31,2020 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in decree n° 2014-1212 of 22 September 2014 of The Senegal Public Procurement Regulations, such 1 arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: (the “Procurement Guidelines”), and the additional provisions in the following paragraphs: (a) Eligibility: Eligibility to participate in a procurement process and to be awarded an Association-financed contract shall be as defined under Section I of the Procurement Guidelines; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Association for reasons other than those provided in Section I of the Procurement Guidelines. No restriction based on nationality of bidders and/or origin of goods shall apply, and foreign bidders shall be allowed to participate in NCB without application of restrictive conditions, such as, but not limited to, mandatory partnering or subcontracting with national entities. (b) Domestic Preference: No margins of preference of any sort shall be applied in the bid evaluation. (c) Bidding Documents: Procuring entities shall use bidding documents acceptable to the Association. (d) Bid validity: An extension of bid validity, if justified by exceptional circumstances, may be requested in accordance with Appendix 1 of the Procurement Guidelines. A corresponding extension of any bid guarantee shall be required in all cases of extension of bid validity. A bidder may refuse a request for extension of bid validity without forfeiting its bid guarantee. (e) Qualification: Qualification criteria shall be clearly specified in the bidding documents. All criteria so specified, and only such specified criteria, shall be used to determine whether a bidder is qualified. Qualification shall be assessed on a “pass or fail” basis, and merit points shall not be used. Such assessment shall be based entirely upon the bidder’s or prospective bidder’s capability and resources to effectively perform the contract, taking into account objective and measurable factors, including: (i) relevant general and specific experience, and satisfactory past performance and successful completion of similar contracts over a given period; (ii) financial position; and where relevant (ii) capability of construction and/or manufacturing facilities (f) Prequalification procedures and documents acceptable to the Association shall be used for large, complex and/or specialized works. Verification of the information upon which a bidder was prequalified, including current commitments, shall be carried out at the time of contract award, along with the bidder’s capability with respect to personnel and equipment. Where pre- qualification is not used, the qualification of the bidder who is recommended for award of contract shall be assessed by post-qualification, applying the qualification criteria stated in the bidding documents. (g) Bid Evaluation: All bid evaluation criteria other than price shall be quantifiable in monetary terms. Merit points shall not be used, and no minimum point or percentage value shall be assigned to the evaluation 2 criteria or significance of price in bid evaluation. No negotiations shall be permitted. (h) Guarantees: Guarantees shall be in the format, shall have the period of validity and shall be submitted when and as specified in the bidding documents. (i) Cost Estimates: Detailed cost estimates shall be confidential and shall not be disclosed to prospective bidders. No bids shall be rejected on the basis of comparison with the cost estimates without the Association’s prior written concurrence. (j) Rejection of bids and re-bidding: No bid shall be rejected solely because it falls outside of a predetermined price range or exceeds the estimated cost. All bids (or the sole bid if only one bid is received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Association’s prior written concurrence. (k) Fraud and corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the Association’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines. (l) Inspection and audit rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the submission of bids and contract performance. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification: Not applicable VI. Leased Assets: Not applicable VII. Procurement of Second Hand Goods: Not applicable 3 VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). (a) Goods: Non- identified for now (b) Works: Non- identified for now Domestic preference is not applicable for National Open Competitive Procurement IX. Other Relevant Procurement Information 4 X. Procurement Prior Review Thresholds (US$) Valeur seuil Contrats soumis à examen Nature des dépenses Méthode de passation de marchés du préalable de l’IDA march é $EU AOI ≥ Tous les contrats de plus 15.000. $10,000,000 USD 000 AON < Tous les contrats de plus 15.000. $10,000,000 USD 1. Travaux 000 Demande de cotation – au moins 3 offres < Aucun 200.00 0 Entente Directe Pas de Tous les contrats de plus seuil $10,000,000 USD AOI ≥1 Tous les contrats de $2,000,000 000.00 et plus 0 AON < Aucun 1000.0 00 2. Fournitures et Consultation de Fournisseurs locaux au < Aucun services assimilés moins 3 offres 100.00 0 Consultation de Fournisseurs locaux < Aucun (véhicules et carburant) 500.00 0 Entente directe Pas de Tous les contrats de $2,000,000 seuil et plus 5 Post Review: All contracts not subject to prior review shall be subject to post review. 6 XI. Thresholds for Procurement Approaches and Method (US$) Nature de Méthode de passation de Valeur seuil du Contrats soumis à examen dépenses marchés contrat $EU préalable Tous contrats de $1,000,000 EU SBQC1; SBQ2; SCM3; SBF4 ou plus Consultants SQC5 < 300 000 Aucun Firmes Tous contrats de $1,000,000 EU Entente directe Pas de seuil ou plus Consultant individuel (CI) 6 ≥ 100.000 (AMI)7 Tous contrats de 300.000 $ EU ou plus Consultants Consultant individuel (CI) (3CV) < 100.000 Individuels Tous contrats de 300.000 $ EU Entente directe Pas de seuil ou plus Tous les TDRs, quel que soit la valeur du contrat, sont soumis à examen préalable. 1 Sélection Basée sur la Qualité et le Coût 2 Sélection Basée sur la qualité du Consultant 3 Sélection au coût minimum 4 Sélection à Budget fixe 5 Sélection basée sur les qualifications des consultants 6 Consultant Individuel 7 Avis à Manifestation d’Intérêt 7 8 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines8 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed 8Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 9 contract, financially or in any other manner;9 (ii) to be a nominated10 sub- contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension about an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect11 all accounts, records, and other 9 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 10 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 11 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 10 documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 11 PROCUREMENT Senegal : Senegal - Saint-Louis Emergency Recovery and Resilience Project PLAN General Information Country: Senegal 2018-09-04 Bank’s Approval Date of the Original Procurement Plan: 2025-01-15 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166538 GPN Date: Project Name: Senegal - Saint-Louis Emergency Recovery and Resilience Project Loan / Credit No: IDA / 62730, IDA / 67600 MUNICIPAL DEVELOPMENT AGENCY Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-ADM-02-T-AONR / Travau Component 1: Meeting Imm Single Stage - One E 2019-02-2 x d'aménagement du site de IDA / 62730 ediate Needs of the Disaster A posteriori Appel d'offres Limited 457,123.94 Signé 2018-08-31 2018-12-07 2018-09-05 2018-04-10 2018-09-19 2018-12-17 2018-10-03 2018-12-26 2018-10-31 2019-02-12 nvelope 8 relogement provisoire Affected Population SN-ADM-04-CS-ED / Sélectio n par entente directe d’une e Component 2: Planned Reloc ntreprise pour la réalisation d ation of Populations Living in Passation de marc 2020-02-2 e travaux complémentaires p IDA / 62730 A posteriori Direct 605,481.76 Signé 2019-11-12 2019-10-25 2019-11-15 2020-01-08 2019-11-29 2020-04-07 the Highest Risk Zones in th hé de gré à gré 7 our l’aménagement du site d e Langue de Barbarie e relogement provisoire de D jougob - Avec l’entreprise CS TP SN-ADM-191231-CW-RFQ / T Component 2: Planned Reloc ravaux complémentaires de l ation of Populations Living in Single Stage - One E 2020-12-1 IDA / 62730 A posteriori Demande de prix Limited 217,305.90 Signé 2020-09-03 2020-09-17 2020-09-18 2020-11-25 a phase 2 de l'aménagement the Highest Risk Zones in th nvelope 7 provisoire de Diougop e Langue de Barbarie SN-ADM-196346-CW-RFB / R Component 2: Planned Reloc éalisation des travaux de terr ation of Populations Living in Open - Internationa Single Stage - One E 11,400,915. 2021-07-2 assements généraux et de V IDA / 62730 A priori Appel d'offres Signé 2020-10-05 2020-12-03 2020-10-10 2020-12-09 2020-11-21 2021-01-26 2020-12-21 2021-02-26 2021-01-25 2021-04-29 the Highest Risk Zones in th l nvelope 30 4 RD primaires dans le cadre d e Langue de Barbarie e l’aménagement du site de r elogement définitif SN-ADM-202773-CW-RFQ / T RAVAUX D’AMENAGEMENT D’ Component 2: Planned Reloc ABRI POUR LE PROSE CENTR ation of Populations Living in Single Stage - One E 2021-02-1 ALE D’ACHAT COMMUNAUTAI IDA / 62730 A posteriori Demande de prix Limited 18,882.97 Signé 2020-11-11 2020-11-05 2021-01-06 2020-12-09 the Highest Risk Zones in th nvelope 5 RE, ET DE REALISATION D’UN e Langue de Barbarie E CLOTURE EN GRILLAGE PO UR LE MICRO- JARDINAGE A DIOUGOP SN-ADM-195764-CW-RFQ / T ravaux dans le cadre de la ré Component 2: Planned Reloc alisation d'un PROSE de pre ation of Populations Living in Single Stage - One E 2021-06-2 IDA / 62730 A posteriori Demande de prix Limited 0.00 Annulé 2020-10-27 2020-12-22 mière génération sur le site d the Highest Risk Zones in th nvelope 0 e relogement provisoire (Tra e Langue de Barbarie vaux aménagement parking arrêt bus) Edital de Licit Component 2: Planned Reloc SN-ADM-280022-CW-RFB / C ação - Obras ation of Populations Living in Open - Internationa Single Stage - One E 2024-12-0 onstruction de logements déf IDA / 62730 A priori Appel d'offres Direito Civil F 0.00 Signé 2022-02-23 2022-02-24 2022-02-28 2022-02-25 2022-04-11 2022-04-19 2022-05-11 2022-06-30 2022-06-15 2022-08-03 the Highest Risk Zones in th l nvelope 1 initifs à Diougop rancês (Fran e Langue de Barbarie cês) SPD Edital de Licit Component 2: Planned Reloc SN-ADM-180401-CW-RFB / T ação - Obras ation of Populations Living in Open - Internationa Single Stage - One E 2024-09-1 ravaux de construction des lo IDA / 62730 A priori Appel d'offres Direito Civil F 0.00 Annulé 2021-12-06 2021-12-11 2022-01-22 2022-02-21 2022-03-28 the Highest Risk Zones in th l nvelope 3 gements définitifs en 4 lots rancês (Fran e Langue de Barbarie cês) SPD Demande d'o SN-ADM-325018-CW-RFB / T Component 2: Planned Reloc ffres - DTPM ravaux de construction d’infr ation of Populations Living in Single Stage - One E Petits travau 2024-01-0 IDA / 62730 A posteriori Appel d'offres Open - National 0.00 Signé 2023-03-15 2023-07-19 2023-03-20 2023-09-12 2023-05-01 2023-08-22 2023-05-31 2023-10-13 2023-07-05 2024-02-22 astructures collectives (poste the Highest Risk Zones in th nvelope x - (Processu 1 de santé et marché) e Langue de Barbarie s à 1 envelop pe) Edital de Licit SN-ADM-325024-CW-RFB / T Component 2: Planned Reloc ação - Obras ravaux de construction des lo ation of Populations Living in Single Stage - One E 2025-11-0 IDA / 62730 A posteriori Appel d'offres Open - National Direito Civil F 0.00 Signé 2023-01-31 2023-05-15 2023-02-05 2023-05-16 2023-03-19 2023-06-19 2023-04-18 2023-07-07 2023-05-23 2023-12-11 gements définitifs et des PIC the Highest Risk Zones in th nvelope 8 rancês (Fran et PROSE (phase 3) e Langue de Barbarie cês) SPD SN-ADM-195740-CW-RFB / T Edital de Licit ravaux complémentaires de Component 2: Planned Reloc ação - Obras voiries et réseaux secondaire ation of Populations Living in Single Stage - One E 2024-07-1 IDA / 62730 A posteriori Appel d'offres Open - National Direito Civil F 0.00 Signé 2023-03-20 2023-05-22 2023-03-25 2023-11-15 2023-05-08 2023-06-27 2023-06-07 2023-08-10 2023-07-12 2023-11-30 s et démolition du site de rel the Highest Risk Zones in th nvelope 1 rancês (Fran ogement provisoire dans le c e Langue de Barbarie cês) SPD adre de l’aménagement du si te de relogement définitif Document na SN-ADM-375512-CW-DIR / Tr tional de pas avaux de contruction des log Component 2: Planned Reloc sation des m ements définitifs des tranche ation of Populations Living in Passation de marc archés - Proc 2024-03-2 IDA / 62730 A posteriori Direct - National 0.00 Signé 2023-08-21 2023-08-24 2023-08-26 2023-09-15 2023-09-30 2023-12-19 s conditionnelles non affermi the Highest Risk Zones in th hé de gré à gré essus à une 8 es, des lots 4 et 5 du marché e Langue de Barbarie enveloppe (D N° T 05-2022-ADM TPM ne prov enant pas de la Banque) Demande d'o SN-ADM-02-T-AON / Réalisati Component 3: Strengthening ffres - DTPM on des travaux de démolition Single Stage - One E En cours d'e 2026-10-2 IDA / 62730 Urban and Coastal Resilienc A posteriori Appel d'offres Open - National Travaux (san 0.00 2024-07-16 2024-10-31 2024-07-21 2024-10-31 2024-08-20 2024-09-19 2024-10-24 , de nettoyage et de sécurisa nvelope xécution 4 e Planning s préqualifica tion de la bande des 20 m tion) Edital de Licit Component 2: Planned Reloc SN-ADM-234573-CW-RFB / T ação - Obras ation of Populations Living in Single Stage - One E 2024-02-2 ravaux de réalisation des équ IDA / 62730 A posteriori Appel d'offres Open - National Direito Civil F 0.00 Annulé 2021-11-15 2021-11-20 2021-12-20 2022-01-19 2022-02-23 the Highest Risk Zones in th nvelope 3 ipements socio-collectifs rancês (Fran e Langue de Barbarie cês) SPD Demande d'o SN-ADM-331528-CW-RFB / T Component 2: Planned Reloc ffres - DTPM ravaux de construction d’équ ation of Populations Living in Single Stage - One E Petits travau 2024-12-0 IDA / 62730 A posteriori Appel d'offres Open - National 0.00 Annulé 2024-02-19 2024-02-24 2024-04-06 2024-05-06 2024-06-10 ipements collectifs (école pré the Highest Risk Zones in th nvelope x - (Processu 7 scolaire et primaire et mosqu e Langue de Barbarie s à 1 envelop ée) pe) SN-ADM-413052-CW-RFQ / C Demande de Component 2: Planned Reloc onstruction d’une aire de tra cotations (DT ation of Populations Living in Single Stage - One E 2025-02-1 nsit avec clôture, plateforme, IDA / 62730 A posteriori Demande de prix Limited - National PM ne prove 0.00 Signé 2024-06-22 2024-04-16 2024-08-17 2024-06-28 the Highest Risk Zones in th nvelope 3 magasin de stockage + abris nant pas de l e Langue de Barbarie de gardien pour le PROSE GO a Banque) M Page 1 Demande d'o Component 2: Planned Reloc ffres - DTPM SN-ADM-413078-CW-RFB / T ation of Populations Living in Single Stage - One E Petits travau En attente d 2026-10-2 ravaux d'aménagement pays IDA / 62730 A posteriori Appel d'offres Open - National 0.00 2024-12-16 2024-12-16 2025-02-24 2025-03-26 2025-04-30 the Highest Risk Zones in th nvelope x - (Processu 'exécution 2 ager du site de Djougop e Langue de Barbarie s à 1 envelop pe) Demande de SN-ADM-325033-CW-RFQ / T Component 2: Planned Reloc cotations (DT ravaux de construction des PI ation of Populations Living in Single Stage - One E 2025-03-1 IDA / 62730 A posteriori Demande de prix Limited - National PM ne prove 0.00 Annulé 2024-07-23 2024-09-17 C et PROSE prioritaires de la the Highest Risk Zones in th nvelope 6 nant pas de l phase 1 et 2 sur le site relog e Langue de Barbarie a Banque) ement définitif Demande d'o SN-ADM-413027-CW-RFB / T Component 2: Planned Reloc ffres - DTPM ravaux de construction des lo ation of Populations Living in Single Stage - One E En attente d 2025-06-3 IDA / 62730 A posteriori Appel d'offres Limited - National Travaux (san 0.00 2024-09-02 2024-09-02 2024-11-11 2024-12-11 2025-01-15 gements définitifs (Reprise lo the Highest Risk Zones in th nvelope 'exécution 0 s préqualifica ts 4 et 5) e Langue de Barbarie tion) Demande d'o SN-ADM-325008-CW-RFB / T Component 2: Planned Reloc ffres - DTPM ravaux de construction d’équ ation of Populations Living in Single Stage - One E Petits travau 2025-05-3 IDA / 62730 A posteriori Appel d'offres Open - National 0.00 Annulé 2024-08-12 2024-08-17 2024-09-28 2024-10-28 2024-12-02 ipements collectifs (mosquée the Highest Risk Zones in th nvelope x - (Processu 1 , collège et centre socio-éduc e Langue de Barbarie s à 1 envelop atif) pe) Demande d'o SN-ADM-436153-CW-RFB / T Component 2: Planned Reloc ffres - DTPM ravaux de construction d’équ ation of Populations Living in Single Stage - One E Petits travau 2025-05-3 IDA / 62730 A posteriori Appel d'offres Open - National 0.00 Annulé 2024-08-12 2024-08-17 2024-09-28 2024-10-28 2024-12-02 ipements collectifs (école pré the Highest Risk Zones in th nvelope x - (Processu 1 scolaire et primaire) e Langue de Barbarie s à 1 envelop pe) SN-ADM-450037-CW-DIR / Tr Demande d'o Component 2: Planned Reloc avaux de construction d’équi ffres - DTPM ation of Populations Living in Single Stage - One E En cours d'e 2025-08-0 pements collectifs (mosquée IDA / 62730 A posteriori Appel d'offres Open - National Travaux (san 0.00 2024-10-14 2024-11-04 2024-10-19 2024-11-11 2024-11-30 2024-12-30 2025-02-03 the Highest Risk Zones in th nvelope xécution 2 , collège, centre socio-éducat s préqualifica e Langue de Barbarie if, école préscolaire et primai tion) re) Demande d'o SN-ADM-01-T-AON / Travaux Component 3: Strengthening ffres - DTPM Single Stage - One E En attente d 2026-01-1 d’aménagement pour la requ IDA / 62730 Urban and Coastal Resilienc A posteriori Appel d'offres Open - National Travaux (san 0.00 2025-06-23 2025-06-28 2025-08-09 2025-09-08 2025-10-13 nvelope 'exécution 1 alification de la zone libérée e Planning s préqualifica tion) Demande de SN-ADM-413082-CW-RFQ / R Component 2: Planned Reloc cotations (DT éalisation d’abris provisoires ation of Populations Living in Single Stage - One E En attente d 2025-08-2 IDA / 62730 A posteriori Demande de prix Limited - National PM ne prove 0.00 2025-01-05 2025-03-02 sur le site de Djougop et envi the Highest Risk Zones in th nvelope 'exécution 9 nant pas de l rons (PIC éducation) e Langue de Barbarie a Banque) Demande d'o SN-ADM-464955-CW-RFB / T Component 2: Planned Reloc ffres - DTPM ravaux de construction des PI ation of Populations Living in Single Stage - One E En attente d 2025-10-1 IDA / 62730 A posteriori Appel d'offres Open - National Travaux (san 0.00 2024-12-31 2025-01-05 2025-02-16 2025-03-18 2025-04-22 C et PROSE des phases 1, 2 e the Highest Risk Zones in th nvelope 'exécution 9 s préqualifica t 3 sur le site de relogement e Langue de Barbarie tion) définitif SN-ADM-413046-CW-RFQ / C onstruction d’une ferme inté Demande de grée (installation d’unités de Component 2: Planned Reloc cotations (DT production piscicole, maraich ation of Populations Living in Single Stage - One E En attente d 2025-08-2 IDA / 62730 A posteriori Demande de prix Limited - National PM ne prove 0.00 2025-01-04 2025-03-01 ère, avicole, fourragère / con the Highest Risk Zones in th nvelope 'exécution 8 nant pas de l struction de clôture de la fer e Langue de Barbarie a Banque) me, clôture de l'exploitation avicole, loge gardien, toilette et bloc administratif) pour le PROSE ZAED Demande de SN-ADM-413048-CW-RFQ / T Component 2: Planned Reloc cotations (DT ravaux d’aménagement et d’ ation of Populations Living in Single Stage - One E En attente d 2025-09-2 IDA / 62730 A posteriori Demande de prix Limited - National PM ne prove 0.00 2025-02-01 2025-03-29 installation de réseaux hydra the Highest Risk Zones in th nvelope 'exécution 5 nant pas de l ulique et d’irrigation pour le e Langue de Barbarie a Banque) PROSE ZAED SN-ADM-413083-CW-RFQ / C Demande de Component 2: Planned Reloc onstruction d'un laboratoire cotations (DT ation of Populations Living in Single Stage - One E En attente d 2026-02-2 à l'UGB pour accompagner le IDA / 62730 A posteriori Demande de prix Limited - National PM ne prove 0.00 2025-07-05 2025-08-30 the Highest Risk Zones in th nvelope 'exécution 6 dispositif provisoire de gestio nant pas de l e Langue de Barbarie n des eaux usées du site de a Banque) Djougop SN-ADM-467643-CW-RFQ / C Demande de Component 2: Planned Reloc onstruction d’une aire de tra cotations (DT ation of Populations Living in Single Stage - One E En attente d 2025-08-2 nsit avec clôture, plateforme, IDA / 62730 A posteriori Demande de prix Limited - National PM ne prove 0.00 2025-01-04 2025-03-01 the Highest Risk Zones in th nvelope 'exécution 8 magasin de stockage + abris nant pas de l e Langue de Barbarie de gardien pour le PROSE GO a Banque) M (Relance) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-ADM-O1-F-UN / Acquisitio n et installation de matériels Component 1: Meeting Imm Passation de marc et équipements (unités mobil IDA / 62730 ediate Needs of the Disaster A priori hés auprès des ag Direct 2,313,214.00 Signé 2018-08-14 2018-08-19 2018-09-02 2018-09-28 2019-06-29 es etc. pour le relogement t Affected Population ences de l'ONU emporaire - Avec UNOPS SN-ADM-02-F-DC / Fournitur e d'équipements pour les ex Component 5: Project Manag perts du SERRP basés à l'AR Single Stage - One E IDA / 62730 ement, Monitoring and Evalu A posteriori Demande de prix Limited 4,310.49 Signé 2019-03-13 2019-03-28 2019-04-17 2019-05-29 2019-05-17 D de Saint-Louis - Lot unique nvelope ation comportant une imprimante, du mobilier de bureau, un spl it et une Fontaine à eau SN-ADM-03-F-DC / Fournitur e de matériels informatiques Component 5: Project Manag et de mobiliers de bureau da Single Stage - One E IDA / 62730 ement, Monitoring and Evalu A posteriori Demande de prix Limited 25,471.05 Signé 2019-03-13 2018-12-24 2019-04-10 2019-03-30 2019-05-10 ns le cadre de l' appui à la c nvelope ation ommune et à l'ARD de saint-l ouis en deux (02) lots separe s SN-ADM-05-F-DC / Acquisitio Component 2: Planned Reloc n d'équipements ménagers p ation of Populations Living in Single Stage - One E our les mesures d'aide au rel IDA / 62730 A posteriori Demande de prix Limited 50,087.21 Signé 2019-06-15 2019-07-02 2019-07-20 2019-08-23 2019-08-19 the Highest Risk Zones in th nvelope ogement provisoire des famil e Langue de Barbarie les sinistrées de la langue de barbarie. SN-ADM-12-CS-CI / Fournitur Component 5: Project Manag Single Stage - One E e de matériels informatiques IDA / 62730 ement, Monitoring and Evalu A posteriori Demande de prix Limited 36,992.91 Signé 2019-08-27 2019-07-15 2019-10-22 2019-09-20 2019-11-21 nvelope pour la commune de Gandon ation SN-ADM-161657-GO-RFQ / A Component 5: Project Manag cquisition de mobilier de sall Single Stage - One E IDA / 62730 ement, Monitoring and Evalu A posteriori Demande de prix Limited 3,671.40 Signé 2019-08-20 2019-08-21 2019-10-15 2019-11-05 2020-04-12 e de réunion dans le cadre d nvelope ation e l'appui logistique à la préfe cture de Saint-Louis Page 2 SN-ADM-168570-GO-RFQ / Pl an de renforcement de la rési Component 1: Meeting Imm lience des populations sinistr Single Stage - One E IDA / 62730 ediate Needs of the Disaster A posteriori Demande de prix Limited 15,095.20 Signé 2020-04-26 2020-04-22 2020-06-21 2020-06-02 2020-12-18 ées installées sur le site de r nvelope Affected Population elogement de Djougop face à la maladie à coronavirus (CO VID-19) SN-ADM-181858-GO-RFQ / R éalisation du PROSE micro jar Component 2: Planned Reloc dinage : Fournitures de maté ation of Populations Living in Single Stage - One E riels de confection de tables IDA / 62730 A posteriori Demande de prix Limited 22,389.75 Signé 2020-07-20 2020-08-06 2020-09-14 2020-10-12 2021-03-13 the Highest Risk Zones in th nvelope pour le jardinage ; Fourniture e Langue de Barbarie s d’intrants de production po ur le micro- jardinage ; Acqui sition de plants pour reboise ment SN-ADM-186084-GO-RFQ / A cquisition de kits domestique Component 1: Meeting Imm Single Stage - One E s (literie, ustensiles, produits IDA / 62730 ediate Needs of the Disaster A posteriori Demande de prix Limited 59,746.73 Signé 2020-08-03 2020-08-20 2020-09-28 2020-10-08 2021-03-27 nvelope d'entretien, etc.) en appui au Affected Population x populations relogées (phas e 2) SN-ADM-04-F-DC / Acquisitio n de véhicules dans le cadre du renforcement de capacité Component 5: Project Manag s au niveaux institutionnel et Single Stage - One E IDA / 62730 ement, Monitoring and Evalu A posteriori Demande de prix Limited 99,933.81 Signé 2019-04-06 2020-09-08 2019-06-17 2020-11-23 2019-07-17 technique (1Véhicule 4x4 po nvelope ation ur ARD de Saint Louis, 1Pick up pour commune de St Loui s et 1Pick up pour commune de GANDON) SN-ADM-181841-GO-RFQ / r éalisation du PROSE centrale Component 2: Planned Reloc d’achat : Acquisition de maté ation of Populations Living in Single Stage - One E riels de production (congélat IDA / 62730 A posteriori Demande de prix Limited 0.00 Annulé 2020-07-20 2020-09-14 2021-03-13 the Highest Risk Zones in th nvelope eurs, frigos, kits solaires, etc. e Langue de Barbarie ) ; Fournitures de denrées ali mentaires, de produits ména gers et produits cosmétiques SN-ADM-186122-GO-RFQ / r Component 2: Planned Reloc éalisation du PROSE coiffure : ation of Populations Living in Acquisition de matériels de c IDA / 62730 A posteriori Demande de prix 0.00 Annulé 2020-12-26 2021-02-20 2021-08-19 the Highest Risk Zones in th oiffure ; Acquisition de produi e Langue de Barbarie ts cosmétiques pour la coiffu re SN-ADM-186111-GO-RFQ / r Component 2: Planned Reloc éalisation du PROSE couture ation of Populations Living in Single Stage - One E IDA / 62730 A posteriori Demande de prix Limited 0.00 Annulé 2020-12-26 2021-02-20 2021-08-19 : Acquisition de matériels de the Highest Risk Zones in th nvelope couture ; Acquisition de fourn e Langue de Barbarie itures pour la couture SN-ADM-287047-GO-RFQ / A Component 2: Planned Reloc cquisition d'un camion frigori ation of Populations Living in Single Stage - One E fique pour le GIE And Bokk Li IDA / 62730 A posteriori Demande de prix Limited 74,775.25 Signé 2022-04-10 2022-04-06 2022-06-21 2022-07-08 2022-07-21 the Highest Risk Zones in th nvelope gguey de Diougop porteur du e Langue de Barbarie PROSE Renforcement Filière Halieutique (FI) SN-ADM-287053-GO-RFQ / A Component 2: Planned Reloc cquisition de petits matériels ation of Populations Living in Single Stage - One E IDA / 62730 A posteriori Demande de prix Limited 6,475.00 Achevé 2022-04-10 2022-04-06 2022-06-21 2022-05-13 2022-07-21 2022-06-20 de mareyage pour le GIE And the Highest Risk Zones in th nvelope Bokk Ligguey de Diougop e Langue de Barbarie SN-ADM-302606-GO-RFQ / A Component 5: Project Manag Single Stage - One E cquisition d'un véhicule Pick IDA / 62730 ement, Monitoring and Evalu A posteriori Demande de prix Limited 0.00 Signé 2022-07-30 2023-01-05 2022-10-10 2023-05-26 2022-11-09 nvelope up pour la commune de GAN ation DON SN-ADM-319608-GO-RFQ / A cquisition de moustiquaires i mprégnés et produits d’hygiè Component 1: Meeting Imm Single Stage - One E ne et d’entretien pour la 2èm IDA / 62730 ediate Needs of the Disaster A posteriori Demande de prix Limited 0.00 Achevé 2022-10-22 2023-03-10 2022-12-17 2023-04-24 2023-06-15 2023-05-25 nvelope e vague de populations sinist Affected Population rées installées sur le site de r elogement provisoire de Djou gop SN-ADM-354526-GO-RFQ / A Component 5: Project Manag cquisition de licences Micros Single Stage - One E IDA / 62730 ement, Monitoring and Evalu A posteriori Demande de prix Limited 0.00 Achevé 2023-04-22 2023-05-05 2023-06-17 2023-07-06 2023-07-17 2023-07-07 oft 365 pour un abonnement nvelope ation de 2 ans, pour quarante-cinq (45) agents SN-ADM-375500-GO-RFQ / A Component 2: Planned Reloc cquisition d’équipements et ation of Populations Living in Single Stage - One E IDA / 62730 A posteriori Demande de prix Open - National 0.00 Signé 2023-08-22 2023-10-17 2023-10-16 2024-04-14 2024-02-02 de fournitures destinés aux é the Highest Risk Zones in th nvelope tablissements scolaires de Di e Langue de Barbarie ougop et environs SN-ADM-382956-GO-RFQ / A Component 5: Project Manag cquisition véhicules pour les Single Stage - One E IDA / 62730 ement, Monitoring and Evalu A posteriori Demande de prix Limited 0.00 Signé 2023-10-02 2023-08-22 2023-12-13 2023-10-03 2024-01-12 déplacements professionnels nvelope ation des équipes techniques et fi duciaires du SERRP SN-ADM-181829-GO-RFQ / A cquisition de fournitures et s ervices dans le cadre de la ré Component 2: Planned Reloc alisation du PIC SANTE Equip ation of Populations Living in Single Stage - One E IDA / 62730 A posteriori Demande de prix Limited 0.00 Annulé 2024-10-21 2024-12-16 2025-06-14 ement Unité provisoire de sa the Highest Risk Zones in th nvelope nté : Fournitures d’équipeme e Langue de Barbarie nts et de matériels médicaux ; Fournitures de médicament s et produits phytosanitaires SN-ADM-01-F-AON / Acquisiti on matériels et équipements Component 3: Strengthening Single Stage - One E (pluviomètres, limnimètres, b IDA / 62730 Urban and Coastal Resilienc A posteriori Appel d'offres Open - National 0.00 Annulé 2022-02-03 2022-02-08 2022-03-10 2022-03-31 2022-05-05 2022-11-01 nvelope alises etc...) pour le système e Planning d'Alerte Précoce (SAP etc.) SN-ADM-302615-GO-RFQ / A cquisition de matériels et éq Component 5: Project Manag uipements informatique pou Single Stage - One E IDA / 62730 ement, Monitoring and Evalu A posteriori Demande de prix Limited - National 0.00 Signé 2024-05-25 2024-04-09 2024-07-20 2024-08-20 2025-01-16 r le Système d’information te nvelope ation rritoriale (SIT) et le système d'Alerte Précoce de Saint-Lou is SN-ADM-234819-GO-RFQ / A Component 3: Strengthening cquisition d'équipements dan Single Stage - One E IDA / 62730 Urban and Coastal Resilienc A posteriori Demande de prix Limited 0.00 Annulé 2024-02-24 2024-04-20 2024-10-17 s le cadre de la mise en pace nvelope e Planning d'un dispositif provisoire d'al erte précoce Page 3 SN-ADM-413080-GO-RFQ / A Component 2: Planned Reloc cquisition d'un véhicule pick- ation of Populations Living in Single Stage - One E IDA / 62730 A posteriori Demande de prix Limited - National 0.00 Signé 2024-06-15 2024-03-28 2024-08-10 2024-06-12 2025-02-06 up pour le suivi des travaux the Highest Risk Zones in th nvelope à Saint-Louis e Langue de Barbarie SN-ADM-186126-GO-RFQ / r Component 2: Planned Reloc éalisation du PROSE transpor ation of Populations Living in Single Stage - One E IDA / 62730 A posteriori Demande de prix Limited - National 0.00 Annulé 2025-03-22 2025-05-17 2025-11-13 t : acquisition de 02 bus pour the Highest Risk Zones in th nvelope le transport des résidents de e Langue de Barbarie Diougop SN-ADM-302616-GO-RFQ / A Component 2: Planned Reloc cquisition de matériels, biens ation of Populations Living in Single Stage - One E et services pour l’équipemen IDA / 62730 A posteriori Demande de prix Limited - National 0.00 Annulé 2024-07-27 2024-09-21 2025-03-20 the Highest Risk Zones in th nvelope t de l’école primaire, le présc e Langue de Barbarie olaire et la mosquée (FA) SN-ADM-302612-GO-RFQ / A Component 2: Planned Reloc cquisition d’équipements pou ation of Populations Living in Single Stage - One E r le PROSE mise en place d’u IDA / 62730 A posteriori Demande de prix Limited - National 0.00 Annulé 2024-09-07 2024-11-02 2025-05-01 the Highest Risk Zones in th nvelope ne unité de restauration avec e Langue de Barbarie les femmes de Diougop (FI) SN-ADM-186125-GO-RFQ / r éalisation du PROSE petite e Component 2: Planned Reloc nfance : Acquisition d’équipe ation of Populations Living in Single Stage - One E ment pour les enseignement IDA / 62730 A posteriori Demande de prix Limited - National 0.00 Annulé 2024-10-06 2024-12-01 2025-05-30 the Highest Risk Zones in th nvelope s de la Petite- enfance ; Four e Langue de Barbarie niture de matériels didactiqu es pour les enseignements d e la Petite- enfance SN-ADM-413065-GO-RFQ / A cquisition d’équipements de Component 2: Planned Reloc matériel de pré collecte, de c ation of Populations Living in Single Stage - One E IDA / 62730 A posteriori Demande de prix Limited - National 0.00 Signé 2024-10-12 2024-04-02 2024-12-07 2024-05-08 2025-06-05 ollecte, d’évacuation de nett the Highest Risk Zones in th nvelope oiement et de protection pou e Langue de Barbarie r le PROSE Gestion des Ordur es Ménagères (GOM) SN-ADM-371324-GO-RFQ / A cquisition de matériels destin és aux exercices de simulatio n et aux interventions en situ Component 1: Meeting Imm Single Stage - One E En attente d' ation de catastrophe et de kit IDA / 62730 ediate Needs of the Disaster A posteriori Demande de prix Limited - National 0.00 2024-12-28 2025-02-22 2025-08-21 nvelope exécution s de réinstallation (pour les Affected Population ménages sinistrés) dans le c adre de la mise en œuvre du plan d'intervention d'urgence du SERRP (en 2lots) Component 2: Planned Reloc SN-ADM-434322-GO-RFQ / A ation of Populations Living in Single Stage - One E En attente d' cquisition d’équipements mé IDA / 62730 A posteriori Demande de prix Limited - National 0.00 2025-02-05 2025-04-02 2025-09-29 the Highest Risk Zones in th nvelope exécution dicaux pour le poste de santé e Langue de Barbarie SN-ADM-321050-GO-RFB / A Component 2: Planned Reloc cquisition de matériels, biens ation of Populations Living in Single Stage - One E En attente d' et services pour le collège, le IDA / 62730 A posteriori Appel d'offres Open - National 0.00 2025-04-14 2025-04-19 2025-05-31 2025-06-30 2025-08-04 2026-01-31 the Highest Risk Zones in th nvelope exécution centre socio-éducatif, la mos e Langue de Barbarie quée et l'école préscolaires et élémentaire Component 2: Planned Reloc SN-ADM-465021-GO-RFQ / A ation of Populations Living in Single Stage - One E En attente d' cquisition de matériels, biens IDA / 67600 A posteriori Demande de prix Limited - National 0.00 2025-03-05 2025-04-30 2025-10-27 the Highest Risk Zones in th nvelope exécution et services pour le marché e Langue de Barbarie SN-ADM-302613-GO-RFQ / A Component 2: Planned Reloc cquisition d’équipements pou ation of Populations Living in Single Stage - One E En attente d' r le PROSE mise en place d’u IDA / 62730 A posteriori Demande de prix Limited - National 0.00 2025-03-22 2025-05-17 2025-11-13 the Highest Risk Zones in th nvelope exécution ne unité de transformations e Langue de Barbarie de produits céréaliers SN-ADM-180403-GO-RFB / A cquisition de matériels, biens Component 3: Strengthening Single Stage - One E En attente d' et services dans le cadre du r IDA / 62730 Urban and Coastal Resilienc A posteriori Appel d'offres Open - National 0.00 2025-01-31 2025-01-31 2025-04-11 2025-05-11 2025-06-15 2026-12-07 nvelope exécution enforcement des capacités a e Planning u niveau institutionnel et tec hnique SN-ADM-413060-GO-RFQ / A cquisition d’équipements d’u Component 2: Planned Reloc ne ferme intégrée (Fournitur ation of Populations Living in Single Stage - One E En attente d' es de Matériels d’installation IDA / 62730 A posteriori Demande de prix Limited - National 0.00 2025-01-25 2025-03-22 2025-09-18 the Highest Risk Zones in th nvelope exécution pour la mise en place d’unité e Langue de Barbarie s de production piscicole, ma raichère, avicole et fourragèr e) pour le PROSE ZAED SN-ADM-413063-GO-RFQ / A Component 2: Planned Reloc cquisition d’équipements pou ation of Populations Living in Single Stage - One E En attente d' IDA / 62730 A posteriori Demande de prix Limited - National 0.00 2025-02-08 2025-04-05 2025-10-02 r le bloc administratif du PRO the Highest Risk Zones in th nvelope exécution SE ZAED e Langue de Barbarie NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-ADM-161586-NC-RFQ / E NTRETIEN DU SYSTEME D’AS Component 1: Meeting Imm Single Stage - One E SAINISSEMENT ET LA VIDANG IDA / 62730 ediate Needs of the Disaster A posteriori Demande de prix Limited 14,393.55 Signé 2020-03-10 2020-03-27 2020-05-05 2020-06-08 2021-05-05 nvelope E DE FOSSES SEPTIQUES, DU Affected Population SITE DE RECASEMENT PROVI SOIRE DE DIOUGOP SN-ADM-413059-NC-RFQ / In Component 3: Strengthening Single Stage - One E vestigations géotechniques à IDA / 62730 Urban and Coastal Resilienc A posteriori Demande de prix Limited - National 0.00 Signé 2024-05-06 2024-04-18 2024-07-01 2024-06-13 2024-07-30 nvelope Potou e Planning SN-ADM-450274-CS-INDV / R ecrutement d’un prestataire Component 3: Strengthening Single Stage - One E pour la réalisation d’un film i IDA / 62730 Urban and Coastal Resilienc A posteriori Demande de prix Limited - National 0.00 Signé 2024-10-20 2024-10-25 2024-12-15 2024-12-03 2025-06-13 nvelope nstitutionnel sur le SERRP et e Planning la prise de vues par drone CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Page 4 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-ADM-02-CS-SQC / Sélecti Component 2: Planned Reloc on d'un Cabinet pour la Facili Sélection fondée s ation of Populations Living in tation sociale du programme IDA / 62730 A posteriori ur les qualification Open - National 424,512.59 Signé 2018-08-14 2018-03-19 2018-08-28 2018-09-25 2018-09-28 2018-10-09 2018-10-09 2018-11-13 2018-12-23 2021-10-28 the Highest Risk Zones in th de récasement définitif des f s des consultants e Langue de Barbarie amilles déplacées de la langu e de barbarie SN-ADM-02-CS-SFQC / Sélect Component 3: Strengthening Sélection fondée s ion d'un Cabinet pour la prép IDA / 62730 Urban and Coastal Resilienc A posteriori ur la qualité et le Open - National 0.00 Signé 2021-12-01 2023-02-07 2021-12-22 2022-02-04 2023-08-18 2022-03-04 2023-10-16 2022-04-03 2024-02-07 2022-05-08 2024-03-21 2022-06-12 2024-07-05 2023-01-08 aration du Plan de résilience e Planning coût de l'agglomération de Saint-L ouis SN-ADM-180398-CS-QCBS / Component 2: Planned Reloc Firme pour la supervision des Sélection fondée s ation of Populations Living in Open - Internationa travaux d'aménagement du s IDA / 62730 A priori ur la qualité et le 319,188.15 Signé 2021-01-23 2020-11-18 2021-02-13 2020-12-03 2021-03-29 2021-05-29 2021-04-26 2021-04-30 2021-05-26 2021-09-24 2021-06-30 2021-12-06 2021-08-04 2021-12-24 2024-01-21 the Highest Risk Zones in th l ite définitif et de construction coût e Langue de Barbarie de logement et d'équipemen t collectifs SN-ADM-05-CS-SFQC / Sélect ion d'un Cabinet pour l'élabor Component 3: Strengthening Sélection fondée s ation et la mise œuvre du pla IDA / 62730 Urban and Coastal Resilienc A posteriori ur la qualité et le Open - National 0.00 Annulé 2020-08-03 2020-08-24 2020-10-07 2020-11-04 2020-12-04 2021-01-08 2021-02-12 2024-01-28 n de renforcement de capacit e Planning coût és des structures parties pre nantes du projet SN-ADM-234597-CS-QCBS / Component 3: Strengthening Sélection fondée s Elaboration des PUD des com Open - Internationa IDA / 67600 Urban and Coastal Resilienc A priori ur la qualité et le 0.00 Signé 2021-07-19 2022-02-04 2021-08-09 2022-02-17 2021-09-22 2022-08-12 2021-10-20 2022-10-03 2021-11-19 2023-04-12 2021-12-24 2024-06-13 2022-01-28 2024-06-14 2023-01-28 munes de Saint-Louis, Ndiéb l e Planning coût ène-Gandiol et Gandon (en 3 lots) SN-ADM-01-CS-SFQC / Sélect Component 3: Strengthening Sélection fondée s ion d'un Cabinet pour la conc IDA / 62730 Urban and Coastal Resilienc A posteriori ur la qualité et le Open - National 0.00 Annulé 2018-11-07 2019-12-18 2018-11-21 2019-01-04 2019-02-01 2019-03-03 2019-04-07 2019-05-12 2020-05-06 eption , opérationnalisation d e Planning coût u Système d'alerte précoce l ocal (SAPL) SN-ADM-204356-CS-QCBS / Component 2: Planned Reloc Sélection fondée s Sélection d’un Cabinet pour l ation of Populations Living in Open - Internationa IDA / 62730 A priori ur la qualité et le 0.00 Annulé 2022-03-14 2022-04-04 2022-05-18 2022-06-15 2022-07-15 2022-08-19 2022-09-23 2024-08-23 a supervision des travaux de the Highest Risk Zones in th l coût construction des logements d e Langue de Barbarie éfinitifs SN-ADM-283023-CS-CQS / S Component 2: Planned Reloc Sélection fondée s élection d’un Cabinet pour la ation of Populations Living in Open - Internationa IDA / 62730 A priori ur les qualification 0.00 Signé 2022-04-11 2022-04-25 2022-05-02 2022-05-16 2022-06-15 2022-09-05 2022-07-15 2022-10-17 2022-08-19 2022-12-08 2023-02-15 supervision des travaux de c the Highest Risk Zones in th l s des consultants onstruction des logements d e Langue de Barbarie éfinitifs SN-ADM-303085-CS-CQS / S élection d’un Cabinet chargé Component 3: Strengthening Sélection fondée s Open - Internationa de la mise œuvre du plan de IDA / 62730 Urban and Coastal Resilienc A posteriori ur la qualité et le 0.00 Signé 2022-07-29 2022-07-26 2022-08-19 2022-07-28 2022-10-02 2022-12-29 2022-10-30 2023-01-31 2022-11-29 2023-04-11 2023-01-03 2023-06-06 2023-02-07 2023-12-20 2024-02-07 l renforcement de capacités d e Planning coût es structures parties prenant es du projet SN-ADM-180399-CS-CQS / S Component 5: Project Manag Sélection fondée s En attente d'exéc élection d'un Cabinet d'audit IDA / 62730 ement, Monitoring and Evalu A posteriori ur les qualification Open - National 0.00 2025-02-17 2025-03-10 2025-04-23 2025-05-23 2025-06-27 2025-12-24 ution technique du projet ation s des consultants SN-ADM-06-CS-SFQC / Etude des modalites de financemen Component 3: Strengthening Sélection fondée s t de la reinstallation de com En attente d'exéc IDA / 62730 Urban and Coastal Resilienc A posteriori ur les qualification Open - National 0.00 2025-02-17 2025-03-10 2025-03-31 2025-04-14 2025-05-05 2025-11-01 munautes/personnes ayant p ution e Planning s des consultants erdues leurs biens et/ou etab lies sur des zones a risque SN-ADM-331738-CS-QCBS / Sélection d’un Cabinet pour l Component 2: Planned Reloc a supervision des travaux de Sélection fondée s ation of Populations Living in construction des logements d IDA / 62730 A posteriori ur la qualité et le Open - National 0.00 Annulé 2024-03-04 2024-03-25 2024-05-08 2024-06-05 2024-07-05 2024-08-09 2024-09-13 2025-09-13 the Highest Risk Zones in th éfinitifs restant + école présc coût e Langue de Barbarie olaire et élémentaire et mosq uée + PIC et PROSE (phase 3 ) SN-ADM-413076-CS-CQS / R Component 2: Planned Reloc Sélection fondée s ecrutement d'un Cabinet pou ation of Populations Living in En cours d'exécut IDA / 62730 A posteriori ur les qualification Limited - National 0.00 2024-07-08 2024-01-18 2024-07-22 2024-08-21 2024-09-25 2025-03-24 r la réalisation de l'étude am the Highest Risk Zones in th ion s des consultants énagement paysager du site e Langue de Barbarie de Djougop SN-ADM-180402-CS-LCS / Sé Component 5: Project Manag Sélection au moin En attente d'exéc lection d'un Cabinet d'audit fi IDA / 62730 ement, Monitoring and Evalu A posteriori Open - National 0.00 2024-10-03 2024-10-18 2024-11-16 2024-12-14 2024-12-29 2025-02-02 2025-03-09 2025-06-07 dre coût ution nancier du projet (Par la DCF ation E) SN-ADM-455084-CS-CQS / S élection d'un Cabinet pour le s Etudes Techniques d'APD e Component 3: Strengthening Sélection fondée s Open - Internationa En cours d'exécut t DAO pour la proposition d'u IDA / 62730 Urban and Coastal Resilienc A priori ur la qualité et le 0.00 2024-10-28 2024-10-30 2024-11-18 2024-12-09 2025-01-01 2025-01-29 2025-02-28 2025-04-04 2025-05-09 2026-05-09 l ion ne solution de protection dur e Planning coût able du littoral au niveau de l a langue de Barbarie et le Pla n Directeur de Drainage. SN-ADM-413069-CS-CQS / S élection d’un Cabinet pour l’é Component 3: Strengthening Sélection fondée s laboration de l’étude d’impac En attente d'exéc IDA / 62730 Urban and Coastal Resilienc A posteriori ur les qualification Limited - National 0.00 2025-04-14 2025-04-28 2025-05-28 2025-07-02 2025-12-29 t environnemental et social ( ution e Planning s des consultants EIES) de la solution de protec tion durable de la langue de barbarie INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-ADM-04-CS-CI / Recrute Component 2: Planned Reloc ment d'un expert social pour ation of Populations Living in IDA / 62730 A posteriori Individuel Open 0.00 Annulé 2018-08-16 2018-04-10 2018-10-04 2018-10-25 2018-11-29 2022-11-08 assister l'équipe du projet ba the Highest Risk Zones in th sée à St Louis e Langue de Barbarie SN-ADM-05-CS-CI / Recrute ment d'un spécialiste en sau Component 5: Project Manag vegarde environnementale e IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open 0.00 Annulé 2018-08-20 2018-03-30 2018-10-08 2018-10-29 2018-12-03 2022-11-12 t sociale pour assister l'équip ation e du projet basée à St Louis SN-ADM-06-CS-CI / Recrute Component 5: Project Manag ment d'un assistant en suivi IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open 0.00 Annulé 2018-09-12 2018-04-25 2018-10-31 2018-11-21 2018-12-26 2022-12-05 et évaluation pour assister l' ation ADM Page 5 SN-ADM-07-CS-CI / Recrute Component 5: Project Manag ment d'un expert en génie ci IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open 0.00 Signé 2018-08-29 2019-05-06 2018-10-17 2019-06-20 2018-11-07 2019-07-09 2018-12-12 2020-04-01 2022-11-21 vil avec une expertise en gén ation ie côtier pour assister l'ADM SN-ADM-01-CS-ED / Sélectio n d'un Cabinet pour les Étud es Techniques (APS) environ nementale et sociale pour la Component 3: Strengthening Sélection de cons proposition d'une solution de IDA / 62730 Urban and Coastal Resilienc A priori ultants par entent Direct 2,018,523.72 Signé 2018-09-07 2019-03-08 2018-09-17 2019-03-05 2018-11-05 2020-02-01 2020-04-28 protection durable du littoral e Planning e directe au niveau de la langue de Ba rbarie et le Plan Directeur de Drainage. Avec le Groupeme nt EGIS/DELTARES SN-ADM-03-CS-ED / Sélectio Component 5: Project Manag Sélection de cons n d'un Cabinet assistant tech IDA / 62730 ement, Monitoring and Evalu A priori ultants par entent Direct 537,399.86 Signé 2019-03-04 2020-07-08 2019-03-14 2020-07-10 2019-05-18 2021-05-18 2020-05-12 nique international au projet ation e directe avec Cabinet CREOCEAN SN-ADM-04-CS-CIB / Recrute Component 2: Planned Reloc ment d'un expert social pour ation of Populations Living in IDA / 62730 A posteriori Individuel Open 2,818.16 Signé 2018-04-10 2019-05-05 2019-06-14 2019-08-15 2019-07-14 2019-09-12 2019-09-16 2019-09-29 2020-09-15 assister l'équipe du projet ba the Highest Risk Zones in th sée à Saint Louis e Langue de Barbarie SN-ADM-06-CS-CIB / Recrute Component 5: Project Manag ment d'un assistant en suivi IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open 113,790.19 Signé 2018-04-25 2018-10-01 2018-11-01 2019-01-02 2018-12-16 2019-02-16 2019-02-20 2019-02-17 2022-12-31 et évaluation pour assister l' ation ADM SN-ADM-13-CS-CI / Sélection Component 5: Project Manag d'un Spécialiste en Passation IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open 295,691.28 Signé 2019-12-13 2020-01-14 2020-01-06 2020-05-26 2020-01-11 2020-05-29 2020-01-19 2020-06-19 2023-07-02 de Marchés ation SN-ADM-01-CI-ED / Sélection Directe d'un consultant Indivi Component 5: Project Manag duel Assistant Technique Nat IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Direct 191,233.79 Signé 2019-12-16 2020-02-14 2019-12-24 2020-02-24 2019-12-26 2020-02-28 2019-12-30 2020-04-14 2023-06-30 ional en Ingénierie Sociale. A ation vec Mouhamadou BA SN-ADM-06-CI-ED / Sélection Component 5: Project Manag Directe d'un consultant Indivi IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Direct 0.00 Signé 2019-12-16 2018-08-03 2019-12-24 2018-08-20 2019-12-26 2018-08-31 2019-12-30 2018-10-01 2023-06-30 duel Expert Environnemental ation iste. Avec Insa FALL SN-ADM-05-CI-ED / Sélection Component 5: Project Manag Directe d'un consultant Indivi IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Direct 188,599.45 Signé 2019-12-16 2020-02-14 2019-12-24 2020-02-24 2019-12-26 2020-02-28 2019-12-30 2020-04-14 2023-06-30 duel Spécialiste en sauvegar ation de sociale. Avec Marie Solan ge NDIONE SN-ADM-03-CI-ED / Sélection Directe d'un consultant Indivi Component 5: Project Manag duel Spécialiste en Hygiène, IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Direct 59,560.23 Signé 2019-12-16 2018-10-02 2019-12-24 2018-08-14 2019-12-26 2019-03-08 2019-12-30 2019-05-05 2023-06-30 Santé, Sécurité Environnem ation ent & Social (HESSS). Avec L ala Youssou NDIAYE SN-ADM-04-CI-ED / Sélection Component 5: Project Manag Directe d'un consultant Indivi IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Direct 90,839.21 Signé 2019-12-16 2020-02-13 2019-12-24 2020-02-24 2019-12-26 2020-02-28 2019-12-30 2020-04-14 2023-06-30 duel Assistant de Projet. Ave ation c Khady Manel FALL SN-ADM-07-CI-ED / Sélection Component 5: Project Manag Sélection de cons Directe d'un consultant Indivi IDA / 62730 ement, Monitoring and Evalu A posteriori ultants par entent Direct 0.00 Signé 2019-12-19 2018-08-03 2019-12-23 2019-12-26 2019-12-29 2020-07-01 2023-06-30 duel Expert en Développeme ation e directe nt urbain. Avec Amadou Diou ldé DIALLO SN-ADM-12-CONS-CI / Sélect ion d’un consultant pour la ré alisation de l’Étude d’Impact Component 3: Strengthening Environnemental et Social (EI IDA / 62730 Urban and Coastal Resilienc A posteriori Individuel Limited 46,126.08 Signé 2020-01-17 2019-11-05 2020-01-20 2019-11-11 2020-01-23 2019-12-23 2020-01-28 2020-01-28 2020-02-27 ES) de l’aménagement défini e Planning tif du site de relogement de Djougop et de la libération d e la bande des 20m sur la lan gue de Barbarie. SN-ADM-160320-CS-INDV / R Component 5: Project Manag ecrutement d’un comptable IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open 121,394.45 Signé 2020-02-24 2020-02-20 2020-04-13 2021-02-12 2020-05-04 2021-03-24 2020-06-08 2021-04-18 2023-06-30 dans le cadre du SERRP ation SN-ADM-160526-CS-INDV / R ecrutement d’un Géomètre a Component 2: Planned Reloc gréé pour la délimitation de l’ ation of Populations Living in IDA / 62730 A posteriori Individuel Limited 2,208.10 Signé 2020-03-02 2020-03-12 2020-03-07 2020-04-23 2020-03-28 2020-05-22 2020-05-02 2020-07-16 2020-05-08 assiette foncière de la bande the Highest Risk Zones in th des 20 mètres de la Langue e Langue de Barbarie de Barbarie à Saint Louis. SN-ADM-161658-CS-INDV / C onception et opérationnalisat Component 4: Contingent E ion d'un système d'alerte pré IDA / 62730 mergency Response Compo A posteriori Individuel Open 37,384.88 Signé 2019-11-21 2019-10-17 2020-01-09 2020-01-10 2020-01-30 2020-02-07 2020-03-05 2020-03-02 2020-09-01 coce (SAP) provisoire pour fai nent re face aux impacts du chan gement climatique sur la LAN GUE DE BARBARIE SN-ADM-161660-CS-INDV / S Component 5: Project Manag élection Directe d'un consult IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Direct 182,547.87 Signé 2020-02-14 2020-02-14 2020-02-24 2020-02-26 2020-03-16 2020-02-28 2020-04-20 2020-04-14 2023-06-30 ant Individuel Ingénieur Géni ation e Civil spécialisé en Hydrauli que SN-ADM-165141-CS-INDV / S Component 1: Meeting Imm upervision des travaux d'am IDA / 62730 ediate Needs of the Disaster A posteriori Individuel Open 55,621.04 Signé 2020-03-20 2020-03-19 2020-05-08 2020-05-05 2020-05-29 2020-05-11 2020-07-03 2020-06-17 2020-12-30 énagement du site de reloge Affected Population ment provisoire (2e phase) SN-ADM-165134-CS-INDV / S ÉLECTION DIRECTE D’UN CO NSULTANT EN CHARGE DE P RÉPARER UNE ANNEXE DU M Component 5: Project Manag ANUEL DE PROCEDURES EXIS IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Direct 34,000.00 Signé 2020-03-19 2020-03-15 2020-03-23 2020-03-18 2020-03-25 2020-03-23 2020-03-27 2020-04-22 2020-05-11 TANT, PORTANT SUR LE CYCL ation E DE GESTION ET DE SUIVI D ES PROCESSUS DE PASSATIO N ET D’EXECUTION DES MAR CHES DE L’ADM Page 6 SN-ADM-168569-CS-INDV / R ECRUTEMENT D’UN(E) CONS Component 3: Strengthening ULTANT(E) INDIVIDUEL(LE) P IDA / 62730 Urban and Coastal Resilienc A posteriori Individuel Open 88,265.18 Signé 2020-04-20 2020-04-08 2020-06-08 2020-06-09 2020-06-29 2020-06-15 2020-08-03 2020-08-05 2021-01-30 OUR L’ÉLABORATION ET L’AP e Planning PUI A LA MISE EN ŒUVRE DU PLAN DE FORMATION DES AC TEURS DU SERRP SN-ADM-01-CS-CI / Sélection Component 2: Planned Reloc d'un Consultant individuel po ation of Populations Living in ur l'étude et le suivi architect IDA / 62730 A posteriori Individuel Open 69,335.05 Signé 2020-06-17 2019-11-22 2020-08-05 2020-01-16 2020-08-26 2020-07-08 2020-09-30 2020-08-21 2022-12-19 the Highest Risk Zones in th ural des travaux de construct e Langue de Barbarie ion de logements et d'équipe ment sociaux SN-ADM-183283-CS-INDV / S ELECTION D’UN ASSISTANT T Component 5: Project Manag ECHNIQUE SPECIALISTE DES IDA / 62730 ement, Monitoring and Evalu A priori Individuel Open 296,489.78 Signé 2020-07-15 2020-07-21 2020-09-02 2021-02-19 2020-09-23 2021-04-05 2020-10-28 2021-05-02 2021-04-26 VILLES DURABLES ET RESILIE ation NTES POUR APPUYER LA MIS E EN ŒUVRE DES ACTIVITES PREVUES DANS LE SERRP SN-ADM-191242-CS-INDV / E LABORATION DE L’AUDIT DE LA MISE EN ŒUVRE DU PLAN Component 2: Planned Reloc D’ACTIONS DE REINSTALLATI ation of Populations Living in IDA / 62730 A posteriori Individuel Open 29,464.45 Signé 2020-09-03 2020-09-07 2020-10-22 2020-03-19 2020-11-12 2020-03-19 2020-12-17 2020-04-14 2021-06-15 ON DE L’AMENAGEMENT PRO the Highest Risk Zones in th VISOIRE DU SITE DE DJOUGO e Langue de Barbarie P ET DU DEPLACEMENT DES PERSONNES AFFECTEES PAR LE PROJET SN-ADM-11-CS-CI / Élaborati Component 5: Project Manag on d'une stratégie visant les IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open 0.00 Annulé 2020-11-02 2020-12-21 2021-01-11 2021-02-15 2025-01-25 modalités d'allocation de log ation ements en complément du P AR SN-ADM-205155-CS-INDV / R ECRUTEMENT D’UN CONSULT Component 2: Planned Reloc ANT CHARGE DE L’ELABORAT ation of Populations Living in ION DU PLAN DE RESTAURATI IDA / 62730 A posteriori Individuel Open 20,575.85 Signé 2020-11-20 2020-11-16 2021-01-08 2021-01-08 2021-01-29 2021-01-18 2021-03-05 2021-02-15 2021-09-01 the Highest Risk Zones in th ON DES MOYENS DE SUBSIST e Langue de Barbarie ANCE (PRMS) DES PERSONNE S AFFECTEES DE LA LANGUE DE BARBARIE SN-ADM-234572-CS-INDV / R Component 5: Project Manag ecrutement d’un (e) Expert(e IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open 288,515.65 Signé 2021-05-24 2021-05-21 2021-07-12 2021-07-12 2021-08-02 2021-07-15 2021-09-06 2021-08-15 2022-03-05 ) en intermédiation sociale d ation ans le cadre du SERRP SN-ADM-09-CS-CI / Recrute Component 5: Project Manag IDA / 62730 A posteriori Individuel Open 0.00 Annulé 2019-04-01 2020-02-20 2019-05-20 2019-06-10 2019-07-15 2023-06-24 ment d'un comptable basé à ement, Monitoring and Evalu St Louis ation SN-ADM-08-CS-CI / Recrute Component 5: Project Manag ment d'un assistant à la coor IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open 0.00 Annulé 2018-11-07 2019-12-31 2018-12-26 2019-01-16 2019-02-20 2023-01-30 dination du projet ation SN-ADM-02-CI-ED / Sélection Directe d'un consultant Indivi Component 5: Project Manag duel Ingénieur Génie Civil sp IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open 0.00 Annulé 2019-12-16 2020-02-14 2019-12-25 2019-12-27 2019-12-31 2023-06-30 écialisé en Hydraulique. Avec ation Lamine Doumbouya SN-ADM-234880-CS-INDV / R Component 2: Planned Reloc ecrutement d'un expert socia ation of Populations Living in IDA / 62730 A posteriori Individuel Open 190,951.02 Signé 2021-05-24 2021-06-01 2021-07-12 2021-10-22 2021-08-02 2021-09-08 2021-09-06 2021-12-18 2022-03-05 l pour assister l'équipe du pr the Highest Risk Zones in th ojet basée à St Louis (rempla e Langue de Barbarie cement/démission) SN-ADM-206510-CS-INDV / R ecrutement d’un (e) Expert(e Component 5: Project Manag ) en médiation sociale et lutt IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open 0.00 Annulé 2020-12-03 2020-11-25 2021-01-21 2021-02-11 2021-03-18 2021-09-14 e contre les violences basées ation sur le genre dans le cadre du SERRP SN-ADM-10-CS-CI / Recrute Component 5: Project Manag ment d'un expert de la résilie IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open 0.00 Annulé 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2023-06-24 nce urbaine ation SN-ADM-05-CS-CIB / Recrute ment d'un spécialiste en sau Component 3: Strengthening vegarde environnementale e IDA / 62730 Urban and Coastal Resilienc A posteriori Individuel Open 0.00 Annulé 2018-03-30 2018-05-02 2018-06-20 2018-08-04 2018-10-01 2023-12-31 t sociale pour assister l'équip e Planning e du projet basée à St Louis SN-ADM-02-CS-CI / Sélection Component 2: Planned Reloc d'un Consultant individuel po ation of Populations Living in IDA / 62730 A posteriori Individuel Limited 49,774.27 Signé 2021-08-09 2021-06-22 2021-08-14 2021-07-15 2021-08-28 2021-08-24 2021-09-18 2021-11-15 2021-12-17 ur l'étude de plan béton arm the Highest Risk Zones in th é des logements e Langue de Barbarie SN-ADM-03-CS-CI / Sélection Component 2: Planned Reloc d'un Consultant individuel po ation of Populations Living in IDA / 62730 A posteriori Individuel Limited 20,595.24 Signé 2021-08-09 2021-06-30 2021-08-14 2021-07-13 2021-09-04 2021-08-16 2021-10-09 2021-10-16 2022-01-07 ur l'étude des lots techniques the Highest Risk Zones in th des logements e Langue de Barbarie SN-ADM-247450-CS-INDV / S ELECTION D’UN CONSULTAN Component 2: Planned Reloc T INDIVIDUEL POUR LES ETU ation of Populations Living in DES ARCHITECTURALES DU IDA / 67600 A posteriori Individuel Limited 32,457.93 Signé 2021-08-16 2021-08-10 2021-08-21 2021-08-24 2021-09-11 2021-10-11 2021-10-16 2021-11-14 2022-04-14 the Highest Risk Zones in th MARCHE, DU POSTE DE SANT e Langue de Barbarie E, DU COLLEGE DU PROJET D E RELOGEMENT DES POPULA TIONS SUR LE SITE DE DIOUG OP SN-ADM-02-CS-ED / Sélectio n d'un Cabinet pour les Etud es Techniques d'APD et DAO Component 3: Strengthening Sélection de cons pour la proposition d'une sol IDA / 62730 Urban and Coastal Resilienc A posteriori ultants par entent Direct 0.00 Annulé 2020-03-05 2020-06-17 2020-03-15 2018-10-22 2020-05-10 2021-05-05 ution de protection durable d e Planning e directe u littoral au niveau de la lang ue de Barbarie et le Plan Dire cteur de Drainage. Avec le Gr oupement EGIS/DELTARES SN-ADM-314734-CS-INDV / S Component 5: Project Manag élection d’un Consultant indi IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open - National 0.00 Signé 2022-09-14 2022-09-08 2022-11-02 2022-11-03 2022-11-23 2022-11-28 2022-12-28 2022-12-22 2023-06-26 viduel spécialiste en passatio ation n des marchés en appui à l'A DM Page 7 SN-ADM-321097-CS-INDV / R Component 5: Project Manag ecrutement d’un Spécialiste IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Limited 0.00 Signé 2023-01-16 2021-05-07 2023-01-21 2021-06-02 2023-02-11 2021-09-08 2023-03-18 2021-12-01 2023-09-14 en Ingénierie Sociale et Genr ation e basé à Saint-Louis SN-ADM-321110-CS-INDV / S Component 5: Project Manag IDA / 62730 A posteriori Individuel Open - National 0.00 Signé 2023-03-20 2023-01-25 2023-05-08 2024-04-17 2023-05-29 2023-04-20 2023-07-03 2023-05-11 2023-12-30 élection d’un auditeur intern ement, Monitoring and Evalu e du projet ation SN-ADM-321149-CS-INDV / S Component 5: Project Manag élection d’un Consultant indi IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Limited 0.00 Signé 2024-03-18 2022-01-26 2024-03-23 2022-01-29 2024-04-13 2022-02-28 2024-05-18 2022-03-16 2024-11-14 viduel pour l’élaboration du r ation apport de revue à mi-parcour s du SERRP SN-ADM-321153-CS-INDV / S Component 2: Planned Reloc élection d’un Consultant indi ation of Populations Living in viduel pour l’étude pour la ge IDA / 62730 A posteriori Individuel Limited 0.00 Signé 2024-02-19 2024-03-28 2024-02-24 2024-04-25 2024-03-16 2024-07-02 2024-04-20 2024-07-12 2024-10-17 the Highest Risk Zones in th stion des déchets de démoliti e Langue de Barbarie on des maisons sur la bande des 20 m SN-ADM-324991-CS-INDV / S élection d’un Consultant indi Component 2: Planned Reloc viduel pour les études archit ation of Populations Living in IDA / 67600 A posteriori Individuel Limited 0.00 Signé 2022-12-28 2022-10-14 2023-01-02 2022-12-22 2023-01-23 2023-01-23 2023-02-27 2023-02-20 2023-08-26 ecturales des équipements c the Highest Risk Zones in th ollectifs (centre socio- éducat e Langue de Barbarie if, école primaire et préscolai re et mosquée) SN-ADM-324992-CS-INDV / S Component 2: Planned Reloc élection d’un Consultant indi ation of Populations Living in IDA / 67600 A posteriori Individuel Limited 0.00 Signé 2023-01-30 2022-10-13 2023-02-04 2022-10-17 2023-02-25 2023-02-28 2023-04-01 2023-04-13 2023-09-28 viduel pour les études archit the Highest Risk Zones in th ecturales des PIC et PROSE ( e Langue de Barbarie phases 1, 2 et 3) SN-ADM-324995-CS-INDV / S élection d’un Consultant indi Component 2: Planned Reloc viduel pour les études béton ation of Populations Living in armé du centre socio- éducat IDA / 62730 A posteriori Individuel Limited 0.00 Signé 2023-01-23 2023-02-27 2023-01-28 2024-06-11 2023-02-11 2024-07-16 2023-03-04 2024-09-12 2023-06-02 the Highest Risk Zones in th if, de l'école primaire et prés e Langue de Barbarie colaire et de la mosquée, PIC et PROSE, y compris étude g éotechnique SN-ADM-324997-CS-INDV / S élection d’un Consultant indi Component 2: Planned Reloc viduel pour les études lots te ation of Populations Living in IDA / 62730 A posteriori Individuel Limited 0.00 Signé 2023-02-22 2023-02-27 2023-02-27 2023-03-08 2023-03-20 2023-04-20 2023-04-24 2023-06-07 2023-07-23 chniques du centre socio- éd the Highest Risk Zones in th ucatif, de l'école primaire et e Langue de Barbarie préscolaire et de la mosquée + PIC et PROSE (3 phases) SN-ADM-234596-CS-INDV / S Component 2: Planned Reloc élection d'un Consultant pour ation of Populations Living in IDA / 62730 A posteriori Individuel Limited 0.00 Signé 2023-03-14 2023-03-01 2023-03-17 2023-03-10 2023-03-20 2023-05-04 2023-03-25 2023-06-14 2023-04-24 l'étude de démolition des ma the Highest Risk Zones in th isons au niveau de la LB e Langue de Barbarie SN-ADM-326128-CS-INDV / S Component 5: Project Manag élection d'un consultant Indiv IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Limited 0.00 Signé 2023-03-20 2023-01-04 2023-03-25 2023-01-06 2023-04-15 2023-04-06 2023-05-20 2023-05-01 2023-11-16 iduel Ingénieur Génie Civil (b ation asé à St Louis) SN-ADM-347695-CS-INDV / S élection d’un Consultant indi viduel pour proposer et acco Component 2: Planned Reloc mpagner la mise en place de ation of Populations Living in modes de gouvernance, de g IDA / 62730 A posteriori Individuel Limited 0.00 Signé 2023-03-27 2023-02-21 2023-04-01 2023-03-29 2023-04-15 2023-06-08 2023-05-06 2023-06-20 2023-08-04 the Highest Risk Zones in th estion et d’exploitation des P e Langue de Barbarie rojets socio-économiques (PR OSE), Projets d’investisseme nts communautaires (PIC) et équipements collectifs SN-ADM-368129-CS-INDV / R ecrutement d’un (e) Expert(e ), Assistant Technique nation Component 5: Project Manag al en charge de la facilitation IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open - National 0.00 Signé 2023-06-28 2023-06-15 2023-08-16 2023-08-08 2023-09-06 2023-08-10 2023-10-11 2023-11-01 2024-04-08 sociale, des projets commun ation autaires et des aspects de ch angements climatiques (rem placement/démission) SN-ADM-371329-CS-INDV / S élection d’un consultant indiv iduel pour la réalisation de l’ Component 3: Strengthening En attente d'exéc Étude d’Impact Environneme IDA / 62730 Urban and Coastal Resilienc A posteriori Individuel Limited 0.00 2024-12-16 2024-12-19 2024-12-22 2024-12-27 2025-01-26 ution ntal et Social (EIES) de l’APD e Planning de la solution durable de prot ection côtière de la langue d e Barbarie. SN-ADM-375721-CS-INDV / S élection d'un consultant indiv Component 3: Strengthening iduel Expert en végétalisatio IDA / 62730 Urban and Coastal Resilienc A posteriori Individuel Open - National 0.00 Signé 2023-09-25 2023-10-09 2023-11-13 2024-09-26 2023-12-04 2024-10-10 2024-01-08 2024-11-25 2024-07-06 n pour réaliser un aménage e Planning ment paysager à l’échelle du lotissement du site de Dioug op (St Louis) SN-ADM-324989-CS-INDV / S Component 2: Planned Reloc élection d’un Consultant indi ation of Populations Living in viduel pour la supervision de IDA / 62730 A posteriori Individuel Limited 0.00 Annulé 2023-01-31 2023-02-05 2023-02-26 2023-04-02 2023-09-29 the Highest Risk Zones in th s travaux de construction d’é e Langue de Barbarie quipements collectifs (poste de santé et marché) SN-ADM-413073-CS-INDV / S élection d’un Consultant indi Component 3: Strengthening En attente d'exéc viduel pour l’élaboration du p IDA / 62730 Urban and Coastal Resilienc A posteriori Individuel Limited - National 0.00 2024-06-17 2024-06-17 2024-06-24 2024-08-12 2024-09-10 ution lan de contingence de la Lan e Planning gue de Barbarie (en complé ment du SAP) SN-ADM-413085-CS-INDV / S Component 2: Planned Reloc élection d’un Consultant indi ation of Populations Living in IDA / 62730 A posteriori Individuel Limited - National 0.00 Signé 2024-03-20 2023-02-27 2024-03-25 2024-03-20 2024-04-15 2024-03-27 2024-05-20 2023-06-07 2024-08-18 viduel pour les études lots te the Highest Risk Zones in th chniques de l'école primaire e Langue de Barbarie et préscolaire SN-ADM-414305-CS-INDV / R ecrutement d’un (e) Expert(e ), Assistant Technique nation Component 5: Project Manag al en charge de la facilitation IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open - National 0.00 Signé 2024-04-08 2024-03-07 2024-05-27 2024-05-16 2024-06-17 2024-05-21 2024-07-22 2024-06-10 2025-01-18 sociale, des projets commun ation autaires et des aspects de ch angements climatiques (2e r emplacement/démission) Page 8 SN-ADM-325003-CS-INDV / S élection d'un Consultant indi Component 3: Strengthening viduel pour l’élaboration de l’ IDA / 67600 Urban and Coastal Resilienc A posteriori Individuel Open - National 0.00 Signé 2024-07-08 2024-07-30 2024-08-26 2024-09-26 2024-09-16 2024-10-14 2024-10-21 2024-11-19 2025-04-19 étude pour la requalification e Planning de la bande des 20 m libérée sur la Langue de Barbarie SN-ADM-260531-CS-CDS / S élection d'un Cabinet pour le s Etudes Techniques d'APD e Component 3: Strengthening Sélection de cons t DAO pour la proposition d'u Direct - Internation IDA / 62730 Urban and Coastal Resilienc A posteriori ultants par entent 0.00 Annulé 2024-07-17 2024-07-27 2024-09-30 2025-03-29 ne solution de protection dur al e Planning e directe able du littoral au niveau de l a langue de Barbarie et le Pla n Directeur de Drainage. Ave c le Groupement EGIS/DELTA RES SN-ADM-423023-CS-INDV / S élection d’un Consultant indi Component 2: Planned Reloc viduel pour les études lots te ation of Populations Living in En cours d'exame IDA / 62730 A posteriori Individuel Limited - National 0.00 2024-05-06 2024-06-10 2024-05-11 2024-06-01 2024-07-06 2024-10-04 chniques des PIC et PROSE (3 the Highest Risk Zones in th n phases) + l'extension de l'éc e Langue de Barbarie ole primaire et préscolaire SN-ADM-423043-CS-INDV / S Component 3: Strengthening élection d’un Consultant indi IDA / 62730 Urban and Coastal Resilienc A posteriori Individuel Limited - National 0.00 Signé 2024-06-17 2024-05-16 2024-06-20 2024-05-28 2024-06-23 2024-07-01 2024-06-28 2024-07-18 2024-07-28 viduel pour l’analyse environ e Planning nementale initiale de la PROS E ZAED SN-ADM-423009-CS-INDV / S Component 2: Planned Reloc élection d’un Consultant indi ation of Populations Living in En cours d'exame viduel pour les études archit IDA / 67600 A posteriori Individuel Limited - National 0.00 2024-06-28 2024-02-14 2024-07-03 2024-07-24 2024-08-28 2024-11-26 the Highest Risk Zones in th n ecturales pour l'extension de e Langue de Barbarie l'école primaire et préscolair e SN-ADM-434327-CS-INDV / S Component 2: Planned Reloc élection d’un Consultant indi ation of Populations Living in viduel pour les études de ré IDA / 67600 A posteriori Individuel Limited - National 0.00 Annulé 2024-09-23 2024-09-28 2024-10-19 2024-11-23 2025-05-22 the Highest Risk Zones in th novation des équipements so e Langue de Barbarie ciaux sur la Langue de barba rie SN-ADM-434332-CS-INDV / S élection d’un Consultant indi Component 2: Planned Reloc viduel pour les études de cal ation of Populations Living in En attente d'exéc cul de structure (BA et charp IDA / 62730 A posteriori Individuel Limited - National 0.00 2024-09-30 2024-10-05 2024-10-19 2024-11-09 2025-02-07 the Highest Risk Zones in th ution ente métallique) des PIC et P e Langue de Barbarie ROSE (3 phases) + l'extensio n de l'école primaire et présc olaire SN-ADM-413072-CS-INDV / S élection d’un Consultant indi Component 3: Strengthening viduel Urbaniste pour appuye IDA / 62730 Urban and Coastal Resilienc A posteriori Individuel Limited - National 0.00 Annulé 2024-10-09 2024-10-14 2024-11-04 2024-12-09 2025-06-07 r l’élaboration de plans com e Planning munaux d’urbanisme dans l’ agglomération de Saint-Louis SN-ADM-459964-CS-INDV / S CI POUR LA RÉALISATION D’U NE ÉTUDE D’ACCEPTABILITE SOCIALE ET ENVIRONNEMEN Component 3: Strengthening En attente d'exéc TALE DU PROJET D’EXPLOITA IDA / 62730 Urban and Coastal Resilienc A posteriori Individuel Open - National 0.00 2024-11-18 2025-01-06 2025-01-27 2025-03-03 2025-08-30 ution TION DE SABLE DANS LA ZO e Planning NE DE POTOU POUR LA MISE EN ŒUVRE DES MESURES DE PROTECTION DURABLE DE LA LANGUE DE BARBARIE / SAIN T-LOUIS SN-ADM-321142-CS-INDV / S Component 5: Project Manag élection d’un Consultant indi En attente d'exéc IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Limited - National 0.00 2025-12-31 2026-01-05 2026-01-26 2026-03-02 2026-08-29 viduel pour l’élaboration du r ution ation apport d’achèvement du SER RP SN-ADM-324987-CS-INDV / S élection d’un Consultant indi Component 5: Project Manag viduel pour la mise à niveau En attente d'exéc IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Limited - National 0.00 2025-02-10 2025-02-15 2025-03-08 2025-04-12 2025-05-13 du personnel de l’ADM dans l ution ation es nouvelles procédures de p assation de marchés de la Ba nque Mondiale SN-ADM-423046-CS-INDV / S Component 5: Project Manag élection d’un Consultant indi En attente d'exéc IDA / 62730 ement, Monitoring and Evalu A posteriori Individuel Open - National 0.00 2025-01-31 2025-03-21 2025-04-11 2025-05-16 2025-11-12 viduel spécialiste en passatio ution ation n des marchés en appui à l'A DM SN-ADM-450275-CS-INDV / R Component 3: Strengthening ecrutement d’un consultant En attente d'exéc IDA / 62730 Urban and Coastal Resilienc A posteriori Individuel Limited - National 0.00 2025-01-31 2025-02-05 2025-02-26 2025-04-02 2025-09-29 pour la mise en œuvre de la ution e Planning campagne digitale du SERRP SN-ADM-423050-CS-INDV / S élection d'un Consultant indi Component 2: Planned Reloc viduel pour la supervision de ation of Populations Living in En attente d'exéc IDA / 67600 A posteriori Individuel Limited - National 0.00 2024-12-31 2025-01-05 2025-01-26 2025-03-02 2025-08-29 s travaux de démolition du b the Highest Risk Zones in th ution âti sur la bande des 20 m lib e Langue de Barbarie érée sur la Langue de Barbar ie SN-ADM-325005-CS-INDV / S élection d'un Consultant indi Component 2: Planned Reloc viduel pour la supervision de ation of Populations Living in En attente d'exéc IDA / 62730 A posteriori Individuel Limited - National 0.00 2025-01-20 2025-01-25 2025-02-15 2025-03-22 2025-09-18 s travaux de construction d'é the Highest Risk Zones in th ution quipements collectifs (école e Langue de Barbarie élémentaire et préscolaire, m osquée et centre socio-éduca tif) SN-ADM-324983-CS-INDV / S Component 2: Planned Reloc élection d’un Consultant indi ation of Populations Living in Open - Internationa En attente d'exéc IDA / 62730 A posteriori Individuel 0.00 2025-12-15 2026-02-02 2026-02-23 2026-03-30 2026-09-26 viduel pour l’étude relative à the Highest Risk Zones in th l ution la capitalisation des acquis d e Langue de Barbarie u SERRP SN-ADM-423058-CS-INDV / S Component 2: Planned Reloc élection d'un Consultant indi ation of Populations Living in En attente d'exéc viduel pour la supervision de IDA / 62730 A posteriori Individuel Limited - National 0.00 2025-09-15 2025-09-20 2025-10-11 2025-11-15 2026-05-14 the Highest Risk Zones in th ution s travaux de requalification d e Langue de Barbarie e la bande des 20 m libérée s ur la Langue de Barbarie Page 9