PROCUREMENT PLAN (Textual Part) Country: Republic of Tajikistan Full Project Name: CASA-1000 Community Support Project Project information Total Finance ($): US$ 26 million equivalent Project Number: P165313 Project Implementing Agencies ESPMU and NSIFT Date of the Procurement Plan February 6, 2019 (initial) Period covered by this Procurement Project duration (5 years) Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Tendering with Unlimited Participation” method set forth in the Law of the Republic of Tajikistan “Оn Public Procurement of Goods, Works and Services”, # 168 dated March 3, 2006 (as amended by Law #815, the “Law of the Republic of Tajikistan on “Introduction of Amendments and Additions to the Law of the Republic of Tajikistan on ‘Public Procurement of Goods, Works and Services’” dated April 16, 2012), provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, World Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • The request for bids/request for proposals document, including contract forms, acceptable to the Bank shall be used. • The request for bids/request for proposals document and contract shall provide the right to the Bank to review procurement documentation and activities. • Borrower shall put in place an effective complaints review mechanism with procurement related complaints and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. • No preference shall be applied under competitive bidding following national market approach. Other national procurement arrangements such as tendering with limited participation, request for quotations, direct contracting, may be used on the above stated conditions. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): “Not Applicable” Other Relevant Procurement Information. The community-driven development (CDD) approach and procurement by the communities will follow Procurement Regulations paragraph 6.52 and Annex XII - Selection Methods, paragraphs 6.9 and 6.10. The procurement arrangements at the community level (including procurement responsibilities, procedures, disclosure requirements, sample documentation and oversight mechanisms) will be elaborated in the Project Operations Manual (POM) and Sub-Grant Manual (SGM) that shall be approved by the Bank and made publicly available by the Borrower. Community procurement will follow the Guidance Note for Design and Management of Procurement Responsibilities in Community Driven Development Projects (March 15, 2012). PROCUREMENT Central Asia : CASA1000 Community Support Project for Tajikistan PLAN General Information Country: Central Asia 2019-10-23 Bank’s Approval Date of the Original Procurement Plan: 2025-01-10 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165313 GPN Date: Project Name: CASA1000 Community Support Project for Tajikistan Loan / Credit No: IDA / D4400, TF / A9568, IDA / E2470 National Social Investment Fund of Tajikistan Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NSIFT-CW-CSP-2A-48/1 / Con Request for Bids - Component 2. Community-le struction of 2-storey educatio Single Stage - One E Small Works SPD 2023-03-0 IDA / D4400 d Investments in Socio-Econ Post Request for Bids Open - National 254,820.65 0.00 Signed 2022-05-18 2022-04-01 2022-05-23 2022-07-04 2022-04-01 2022-08-03 2022-04-28 2022-09-07 2022-05-10 nal building in school #12 in nvelope (1 envelope proce 6 omic Infrastructure Mehrobod village, jamoat Ma ss) shal, Vakhsh district NSIFT-CW-CSP-2A-09/1 / Con Request for Bids - Component 2. Community-le struction of kintergarten in T Single Stage - One E Small Works SPD 2023-03-2 IDA / D4400 d Investments in Socio-Econ Post Request for Bids Open - National 240,000.00 0.00 Completed 2022-06-02 2022-04-28 2022-06-07 2022-07-19 2022-04-28 2022-08-18 2022-05-25 2022-09-22 2022-06-16 oychi village, Jura Rahmonov nvelope (1 envelope proce 1 omic Infrastructure jamoat, tursunzoda city ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4. Project Manag NSIFT-CSP-G-2-1 / office equi Request for Quota Single Stage - One E IDA / D4400 ement, Monitoring and Evalu Post Open - National 8,000.00 6,237.82 Completed 2020-11-05 2020-12-31 2020-08-02 2021-06-29 2020-08-31 pment for NSIFT tions nvelope ation, and Communications Component 4. Project Manag NSIFT-CSP-G-2-2 / computer Request for Quota Single Stage - One E IDA / D4400 ement, Monitoring and Evalu Post Open - National 36,200.00 31,589.65 Completed 2020-10-19 2020-12-14 2020-08-12 2021-06-12 2020-12-05 equipment for NSIFT tions nvelope ation, and Communications Component 4. Project Manag NSIFT-CSP-G-3 / vehicles for Request for Quota Single Stage - One E IDA / D4400 ement, Monitoring and Evalu Post Open - National 70,000.00 61,465.56 Completed 2020-10-19 2020-12-14 2020-08-01 2021-06-12 2020-10-11 the NSIFT tions nvelope ation, and Communications Component 4. Project Manag Request for Quota Single Stage - One E NSIFT-CSP-G-4 / FM system IDA / D4400 ement, Monitoring and Evalu Post Open - National 10,000.00 7,441.86 Signed 2020-11-05 2020-12-31 2020-07-24 2021-06-29 tions nvelope ation, and Communications NSIFT-CSP-G-3-1 / Procurem Component 3. Community M Request for Quota Single Stage - One E ent of tablets for CSP CDA an TF / A9568 obilization, Capacity Building Post Open - National 14,760.00 12,714.91 Signed 2021-08-15 2021-08-13 2021-10-10 2021-09-24 2022-04-08 tions nvelope d project staff and Local Governance NSIFT-CSP/SERSP-G-1-3/3-1 / Component 3. Community M Request for Quota Single Stage - One E Procurement of additional co TF / A9568 obilization, Capacity Building Post Open - National 18,000.00 0.00 Completed 2022-06-08 2022-08-03 2022-04-04 2023-01-30 2022-06-24 tions nvelope mputer and furniture equipm and Local Governance ent for NSIFT NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NSIFT-CSP-CS-5 / Training an Component 1. Rural Electrici Quality And Cost- Open - Internationa d facilitating partners for wor IDA / D4400 Prior 1,317,343.00 1,284,341.02 Signed 2019-10-25 2019-11-11 2019-11-15 2019-11-26 2019-12-29 2020-02-19 2020-01-26 2020-03-20 2020-02-25 2020-07-27 2020-03-31 2020-10-01 2020-05-05 2020-11-14 2021-05-05 ty Supply Improvements Based Selection l king in jamoats NSIFT-CSP-CS-4 / Procureme nt of Management Informatio Component 4. Project Manag Consultant Qualifi n System and Village Mobile IDA / D4400 ement, Monitoring and Evalu Post Open - National 16,720.00 48,976.30 Signed 2020-07-28 2020-07-28 2020-08-18 2020-07-30 2020-10-01 2020-09-02 2020-10-31 2020-10-23 2020-12-05 2020-11-20 2021-06-03 cation Selection Application in the framework ation, and Communications of CSP and SERSP projects. NSIFT-CSP-CS-8-1 / Procure ment of the consulting servic Component 4. Project Manag Consultant Qualifi es of the communication firm IDA / D4400 ement, Monitoring and Evalu Post Open - National 35,000.00 34,753.60 Signed 2020-10-02 2020-10-08 2020-10-23 2020-10-14 2020-12-06 2020-11-25 2021-01-05 2020-12-12 2021-02-09 2021-01-07 2021-08-08 cation Selection in the framework of CASA100 ation, and Communications 0 Community Support Project . NSIFT-CSP-CS-2 / baseline re Component 2. Community-le Consultant Qualifi search within the CSP and SE IDA / D4400 d Investments in Socio-Econ Post Open - National 43,000.00 87,778.25 Signed 2020-11-02 2020-11-02 2020-11-07 2020-11-10 2020-12-21 2021-01-12 2021-01-20 2021-02-09 2021-02-24 2021-02-24 2021-08-23 cation Selection RSP omic Infrastructure NSIFT-CSP-CS-SG-1-1 / Desig Component 2. Community-le n-estimate documentation fo Consultant Qualifi IDA / D4400 d Investments in Socio-Econ Post Open - National 13,144.00 13,745.41 Signed 2021-11-22 2021-12-15 2021-12-13 2022-01-26 2021-12-22 2022-02-25 2022-01-10 2022-04-01 2022-01-15 2022-09-28 r CSP-2A-32/1, CSP-2A-34/1, cation Selection omic Infrastructure CSP-2A-41/1 and CSP-2A-53/ 1 subprojects NSIFT-CSP-CS-SG-1-2 / Desig Component 2. Community-le n-estimate documentation fo Consultant Qualifi IDA / D4400 d Investments in Socio-Econ Post Open - National 17,343.00 16,491.21 Signed 2021-11-22 2021-12-15 2021-12-13 2022-01-26 2021-12-22 2022-02-25 2022-01-10 2022-04-01 2022-01-15 2022-09-28 r CSP-2A-48/1, CSP-2A-58/1 a cation Selection omic Infrastructure nd CSP-2A-09/1 subprojects NSIFT-CSP-CS-SG-1-3 / Desig Component 2. Community-le Consultant Qualifi n-estimate documentation fo IDA / D4400 d Investments in Socio-Econ Post Open - National 6,466.00 6,830.10 Signed 2021-11-22 2021-12-15 2021-12-13 2022-01-26 2021-12-22 2022-02-25 2022-01-10 2022-04-01 2022-01-15 2022-09-28 cation Selection r CSP-2A-49/1 subproject omic Infrastructure Page 1 NSIFT-SERSP-CS-SG-1-4 / DE Component 2. Community-le D for subprojects CSP-2B-11, Consultant Qualifi IDA / D4400 d Investments in Socio-Econ Post Open - National 30,447.00 33,447.09 Signed 2022-01-17 2022-03-10 2022-02-07 2022-03-23 2022-02-17 2022-04-22 2022-02-14 2022-05-27 2022-03-10 2022-11-23 CSP-2B-22, CSP-2B-25, CSP-2 cation Selection omic Infrastructure B-32, CSP-2B-30, CSP-2B-27, CSP-2B-22. NSIFT-SERSP-CS-SG-1-5 / DE Component 2. Community-le Consultant Qualifi D for subprojects CSP-2B-03, IDA / D4400 d Investments in Socio-Econ Post Open - National 9,514.00 7,608.88 Signed 2022-01-17 2022-01-19 2022-02-07 2022-03-23 2022-02-28 2022-04-22 2022-03-05 2022-05-27 2022-03-10 2022-11-23 cation Selection CSP-2B-17, CSP-2B-14. omic Infrastructure NSIFT-CSP-CS-SG-1-6 / DED f or subprojects CSP-2А-31/1, Component 2. Community-le CSP-2А-43/1, CSP-2А-54/1, C Consultant Qualifi IDA / D4400 d Investments in Socio-Econ Post Open - National 39,577.00 44,092.49 Signed 2022-02-18 2022-03-04 2022-03-11 2022-04-24 2022-03-17 2022-05-24 2022-04-18 2022-06-28 2022-05-02 2022-12-25 SP-2А-59/1, CSP-2А-61/1, CS cation Selection omic Infrastructure P-2А-55/1, CSP-2А-42/1, CSP- 2А-56/1, CSP-2А-46/1, CSP-2 А-29/1, CSP-2А-27/1 NSIFT-CSP-CS-SG-1-7 / DED f Component 2. Community-le Consultant Qualifi or subprojects CSP-2A-28/1, IDA / D4400 d Investments in Socio-Econ Post Open - National 10,628.00 10,693.42 Signed 2022-02-18 2022-03-10 2022-03-11 2022-04-24 2022-03-17 2022-05-24 2022-04-18 2022-06-28 2022-05-02 2022-12-25 cation Selection CSP-2A-36/1, CSP-2A-62/1, C omic Infrastructure SP-2A-63/1 NSIFT-CSP-CS-SG-1-8 / DED f or subprojects CSP-2A-02/1, CSP-2A-03/1, CSP-2A-12/1, C Component 2. Community-le Consultant Qualifi SP-2A-07/1, CSP-2A-11/1, CS IDA / D4400 d Investments in Socio-Econ Post Open - National 42,754.00 47,989.41 Signed 2022-02-18 2022-03-10 2022-03-11 2022-04-24 2022-04-01 2022-05-24 2022-04-15 2022-06-28 2022-05-02 2022-12-25 cation Selection P-2A-13/1, CSP-2A-22/1, CSP- omic Infrastructure 2A-23/1, CSP-2A-20/1, CSP-2 A-25/1, CSP-2A-04/1, CSP-2A- 10/1, CSP-2A-17/1, CSP-2A-1 9/1 NSIFT-CSP-CS-SG-1-9 / DED f Component 2. Community-le Consultant Qualifi or subproject CSP-2B-01, CSP IDA / D4400 d Investments in Socio-Econ Post Open - National 5,480.00 8,586.45 Signed 2022-02-18 2022-03-10 2022-03-11 2022-04-24 2022-04-01 2022-05-24 2022-04-18 2022-06-28 2022-05-02 2022-12-25 cation Selection -2B-29 omic Infrastructure NSIFT-CSP-CS-SG-1-10 / DED Component 2. Community-le Consultant Qualifi for subprojects CSP-2A-38/1, IDA / D4400 d Investments in Socio-Econ Post Open - National 16,000.00 15,738.21 Signed 2022-02-18 2022-03-10 2022-03-11 2022-04-24 2022-04-01 2022-05-24 2022-04-18 2022-06-28 2022-04-22 2022-12-25 cation Selection CSP-2A-39/1 omic Infrastructure NSIFT-CSP-CS-SG-1-11 / DED Component 2. Community-le for subprojects CSP-2A-06/1, Consultant Qualifi IDA / D4400 d Investments in Socio-Econ Post Open - National 26,000.00 0.00 Signed 2022-09-21 2022-10-14 2022-10-12 2022-11-25 2022-08-10 2022-12-25 2022-08-23 2023-01-29 2022-08-25 2023-07-28 CSP-2A-18/1, CSP-2A-21/1, C cation Selection omic Infrastructure SP-2A-08/1, CSP-2A-05/1. NSIFT-CSP-CS-SG-1-12 / DED Component 2. Community-le Consultant Qualifi for subprojects CSP-2A-15/1, IDA / D4400 d Investments in Socio-Econ Post Open - National 6,000.00 0.00 Signed 2022-09-21 2022-10-14 2022-10-12 2022-11-25 2022-09-19 2022-12-25 2022-09-28 2023-01-29 2022-09-30 2023-07-28 cation Selection CSP-2A-16/1 omic Infrastructure NSIFT-CSP-CS-SG-1-13 / DED Component 2. Community-le Consultant Qualifi for subprojects CSP-2А-35/1, IDA / D4400 d Investments in Socio-Econ Post Open - National 19,570.00 0.00 Signed 2022-10-09 2022-10-14 2022-10-30 2022-12-13 2022-11-01 2023-01-12 2022-11-18 2023-02-16 2022-11-22 2023-08-15 cation Selection CSP-2А-45/1, CSP-2А-50/1, C omic Infrastructure SP-2А-51/1. NSIFT-CSP-CS-SG-1-14 / DED Component 2. Community-le Consultant Qualifi for subprojects CSP-2A-06, C IDA / D4400 d Investments in Socio-Econ Post Open - National 18,400.00 0.00 Signed 2022-10-09 2022-10-14 2022-10-30 2022-12-13 2022-11-01 2023-01-12 2022-11-18 2023-02-16 2022-11-22 2023-08-15 cation Selection SP-2A-02, CSP-2A-31, CSP-2A omic Infrastructure -37 NSIFT-CSP-CS-SG-1-15 / Geol Component 2. Community-le ogical referenсe of subprojec Consultant Qualifi IDA / D4400 d Investments in Socio-Econ Post Open - National 6,500.00 0.00 Signed 2023-01-30 2023-02-17 2023-02-20 2023-04-05 2023-02-09 2023-05-05 2023-02-23 2023-06-09 2023-02-27 2023-12-06 t CSP-2A-58/1 to CSP-2A-52/ cation Selection omic Infrastructure 1, of CSP-2A-41/1 to CSP-2A- 33/1/ NSIFT-CSP-CS-SG-1-16 / DED Component 2. Community-le Consultant Qualifi for subprojects CSP-2B-12, C IDA / D4400 d Investments in Socio-Econ Post Open - National 12,000.00 0.00 Signed 2023-01-30 2023-02-17 2023-02-20 2023-04-05 2023-02-09 2023-05-05 2023-02-23 2023-06-09 2022-02-27 2023-12-06 cation Selection SP-2B-28. omic Infrastructure NSIFT-CSP-CS-SG-1-17 / Con sultancy services for the desi gn-estimate documentation f Component 2. Community-le Consultant Qualifi or 7 subprojects - DED for su IDA / D4400 d Investments in Socio-Econ Post Open - National 35,000.00 0.00 Signed 2024-03-07 2024-03-19 2024-03-28 2024-05-11 2024-04-15 2024-06-10 2024-04-24 2024-07-15 2024-04-26 2025-01-11 cation Selection bprojects CSP-2A-58/2, CSP-2 omic Infrastructure A-41/2, CSP-2A-48/2, CSP-2A- 53/2, CSP-2A-32/2, CSP-2A-3 4/2, CSP-2A-57/2. NSIFT-CSP-CS-8-2 / Commun Component 4. Project Manag ication support to Communit Consultant Qualifi Under Implement IDA / E2470 ement, Monitoring and Evalu Post Open - National 68,000.00 0.00 2024-06-24 2024-07-12 2024-08-09 2024-08-26 2024-08-28 2025-08-28 y Support Project under CAS cation Selection ation ation, and Communications A-1000 project framework NSIFT-CSP-CS-3 / Final proje Component 4. Project Manag Consultant Qualifi Pending Impleme ct study within the CASA 100 IDA / E2470 ement, Monitoring and Evalu Post Open - National 50,000.00 0.00 2025-01-08 2025-01-29 2025-03-14 2025-04-13 2025-05-18 2025-11-14 cation Selection ntation 0 Community Support Project ation, and Communications INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3. Community M NSIFT-CSP-CS-IC-1-1 / Comm Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 unity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-2 / Comm Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 unity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-3 / Comm Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 unity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-4 / Comm Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 unity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-5 / Comm Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 unity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-6 / Comm Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 unity Development Advisor ant Selection and Local Governance Page 2 Component 3. Community M NSIFT-CSP-CS-IC-1-7 / Comm Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 unity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-8 / Comm Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 unity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-9 / Comm Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 unity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-10 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-11 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-07-24 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-12 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-13 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-14 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-15 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-16 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-17 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-18 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-19 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-20 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-21 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-22 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-23 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-24 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-05 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-25 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-26 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-05 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-27 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-28 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-29 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-07-24 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-30 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-31 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-07-24 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-32 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-33 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-34 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Page 3 Component 3. Community M NSIFT-CSP-CS-IC-1-35 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-36 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-05 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-37 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-38 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-39 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-40 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-41 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-07 2019-11-21 2020-10-02 2019-12-26 2020-10-05 2020-06-23 munity Development Advisor ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-2-1-1 / Man Individual Consult IDA / D4400 obilization, Capacity Building Post Open 33,000.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-10 2019-11-21 2020-04-09 2019-12-26 2020-08-01 2020-06-23 ager of regional office ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-2-1-2 / Man Individual Consult IDA / D4400 obilization, Capacity Building Post Open 33,000.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-10 2019-11-21 2020-04-09 2019-12-26 2020-08-10 2020-06-23 ager of regional office ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-2-1-3 / Man Individual Consult IDA / D4400 obilization, Capacity Building Post Open 33,000.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-10 2019-11-21 2020-04-09 2019-12-26 2020-08-01 2020-06-23 ager of regional office ant Selection and Local Governance NSIFT-CSP-CS-IC-2-2-1 / Regi Component 3. Community M Individual Consult onal Community Developme IDA / D4400 obilization, Capacity Building Post Open 33,000.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-10 2019-11-21 2020-04-09 2019-12-26 2020-08-10 2020-06-23 ant Selection nt Advisor and Local Governance NSIFT-CSP-CS-IC-2-2-2 / Regi Component 3. Community M Individual Consult onal Community Developme IDA / D4400 obilization, Capacity Building Post Open 33,000.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-07-24 2019-11-21 2020-09-04 2019-12-26 2020-09-22 2020-06-23 ant Selection nt Advisor and Local Governance NSIFT-CSP-CS-IC-2-2-3 / Regi Component 3. Community M Individual Consult onal Community Developme IDA / D4400 obilization, Capacity Building Post Open 33,000.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-10 2019-11-21 2020-04-09 2019-12-26 2020-08-01 2020-06-23 ant Selection nt Advisor and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-3 / Chief So Individual Consult IDA / D4400 obilization, Capacity Building Post Open 33,000.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-01-10 2019-11-21 2020-03-02 2019-12-26 2020-08-10 2020-06-23 cial Accountability Specialist ant Selection and Local Governance NSIFT-CSP-CS-IC-4 / Chief Lo Component 3. Community M Individual Consult cal Governance Capacity Buil IDA / D4400 obilization, Capacity Building Post Open 33,000.00 0.00 Signed 2019-09-12 2019-12-27 2019-10-31 2020-07-24 2019-11-21 2020-09-04 2019-12-26 2020-09-21 2020-06-23 ant Selection ding Specialist and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-42 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2020-09-21 2020-10-01 2020-11-09 2020-07-24 2020-11-30 2020-10-02 2021-01-04 2020-10-05 2021-07-03 munity Development Adviser ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-43 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2020-09-21 2020-10-01 2020-11-09 2020-01-07 2020-11-30 2020-10-02 2021-01-04 2020-10-05 2021-07-03 munity Development Adviser ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-44 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2020-09-21 2020-10-01 2020-11-09 2020-01-07 2020-11-30 2020-10-02 2021-01-04 2020-10-05 2021-07-03 munity Development Adviser ant Selection and Local Governance Component 3. Community M NSIFT-CSP-CS-IC-1-45 / Com Individual Consult IDA / D4400 obilization, Capacity Building Post Open 11,610.00 0.00 Signed 2020-09-21 2020-10-01 2020-11-09 2020-01-07 2020-11-30 2020-10-02 2021-01-04 2020-10-05 2021-07-03 munity Development Adviser ant Selection and Local Governance Page 4