PROCUREMENT PLAN (Textual Part) Project information: CONGO PROCLIMAT - P177786 Project Implementation agency: PIU within Ministry in charge of planning Date of the Procurement Plan: December 13, 2023 Period covered by this Procurement Plan: 18 first months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in “Décret n° 2009-156 du mai 2009”, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. the Procurement Documents include sufficient provisions, as agreed with the Bank, to adequately mitigate against environmental and social (including SEA/SH), risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). N/A Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. PROCUREMENT Congo, Republic of : Climate-Resilient and Inclusive Livelihoods Project (ProClimat Congo) PLAN General Information Country: Congo, Republic of 2023-12-13 Bank’s Approval Date of the Original Procurement Plan: 2025-01-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177786 GPN Date: 2024-12-13 Project Name: Climate-Resilient and Inclusive Livelihoods Project (ProClimat Congo) Loan / Credit No: IBRD / 94930, IDA / 74330 Ministry of Planning Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CG-PROCLIMAT-011-T-ED-24 / Contractualisation par Ente Responding to Immediate Fo Passation de marc Autre (avec cham 2025-01-2 nte directe avec le Program IDA / 74330 od and Nutrition Security Ne A priori Direct - National 7,000,000.00 0.00 Annulé 2024-06-15 2024-04-05 2024-06-20 2024-04-15 2024-07-25 hé de gré à gré p d'explication) 1 me Alimentaire Mondial (PAM eds ) pour les travaux à forte int ensité de main d'œuvre CG-PROCLIMAT-038-C-QC-24 Project Management, Monito Single Stage - One E Autre (avec cham 2025-07-2 / Aménagement des bureaux IBRD / 94930 A posteriori Demande de prix Limited - National 16,521.00 0.00 Annulé 2024-12-03 2025-01-28 ring, and Evaluation nvelope p d'explication) 7 de l'UGP-ProClimat CG-PROCLIMAT-040-T-AON-2 4 / TRAVAUX DE REALISATIO Demande d'offres N DES FORAGES MANUELS E Contingent Emergency Resp Single Stage - One E - DTPM Petits trav En cours d'e 2025-08-0 T MECANIQUES POSITIFS AVE IBRD / 94930 A posteriori Appel d'offres Open - National 1,000,000.00 0.00 2024-10-15 2024-08-06 2024-10-20 2024-08-08 2024-12-01 2024-12-31 2025-02-04 onse nvelope aux - (Processus à xécution 3 C SUPERSTRUCTURES EN D 1 enveloppe) OUZE (12) LOTS DANS LES L OCALITES EN PROIE AUX INO NDATIONS CG-PROCLIMAT-038-T-DC-24 Project Management, Monito Single Stage - One E Autre (avec cham 2025-07-1 / Aménagements des bureau IBRD / 94930 A posteriori Demande de prix Limited - National 16,521.00 0.00 Achevé 2024-11-20 2024-08-14 2025-01-15 2024-09-13 ring, and Evaluation nvelope p d'explication) 4 x du siège du ProClimat GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PROCLIMAT-001F-DC-23 / Acquisition du matériel infor Project Management, Monito Single Stage - One E IBRD / 94930 A posteriori Demande de prix Limited 231,294.00 0.00 Achevé 2024-02-19 2023-12-28 2024-04-15 2024-02-01 2024-10-12 2024-05-17 matique, réseau internet et t ring, and Evaluation nvelope éléphonique au profit de l'UG P-ProClimat CG-PROCLIMAT-002F-DC-23 Project Management, Monito Single Stage - One E / Acquisition de mobilier de b IBRD / 94930 A posteriori Demande de prix Limited 99,126.00 0.00 Achevé 2024-03-03 2024-04-11 2024-04-28 2024-02-01 2024-10-25 2024-05-08 ring, and Evaluation nvelope ureau au profit de l'UGP-ProC limat CG-PROCLIMAT-003-F-DC-23 Project Management, Monito Single Stage - One E / Acquisition de cinq (05) véh IBRD / 94930 A posteriori Demande de prix Limited 660,840.00 0.00 Achevé 2024-03-10 2024-04-11 2024-05-05 2024-02-01 2024-11-01 2024-06-20 ring, and Evaluation nvelope icules 4X4 au profit de l'UGP CG-PROCLIMAT-004-F-DC-23 Project Management, Monito Single Stage - One E / Acquisition d'un groupe éle IBRD / 94930 A posteriori Demande de prix Limited 33,042.00 0.00 Achevé 2024-03-18 2024-06-09 2024-05-13 2024-02-14 2024-11-09 2024-05-15 ring, and Evaluation nvelope ctrogène de 40 KVA au profit de l'UGP CG-PROCLIMAT-005-F-DC-23 Project Management, Monito Single Stage - One E / Acquisition des fournitures IBRD / 94930 A posteriori Demande de prix Limited 24,782.00 0.00 Achevé 2024-04-03 2023-12-28 2024-05-29 2024-02-01 2024-11-25 2024-02-28 ring, and Evaluation nvelope de bureau au profit de l'UGP- ProClimat CG-PROCLIMAT-006-F-ED-24 Responding to Immediate Fo Passation de marc / Acquisition et formation du IBRD / 94930 od and Nutrition Security Ne A posteriori Direct - National 81,779.00 0.00 Achevé 2024-03-29 2024-01-10 2024-04-03 2024-02-15 2024-05-08 2024-02-22 2024-11-04 2024-07-16 hé de gré à gré personnel en logiciel TOMPR eds O CG-PROCLIMAT-007-F-DC-24 Project Management, Monito Single Stage - One E / Acquisition de trois (03) véh IBRD / 94930 A posteriori Demande de prix Limited - National 135,000.00 0.00 Achevé 2024-04-25 2024-04-11 2024-06-20 2024-05-22 2024-07-19 2024-07-15 ring, and Evaluation nvelope icules 4x4 au profit de trois ( 03) BSP CG-PROCLIMAT-010-F-ED-24 / Contractualisation par Ente Responding to Immediate Fo nte directe avec le Program Passation de marc IDA / 74330 od and Nutrition Security Ne A priori Direct - National 6,000,000.00 0.00 Annulé 2024-05-31 2024-04-05 2024-06-05 2024-04-15 2024-07-10 2025-01-06 me Alimentaire Mondial (PAM hé de gré à gré eds ) pour l'acquisition des fourni ture et distribution d'aliment s et des bons alimentaires 2- CG-PROCLIMAT-013-F-A Contingent Emergency Resp Single Stage - Two E ONR-24 / Acquisition et distri IBRD / 94930 A posteriori Appel d'offres Limited - National 800,000.00 0.00 Annulé 2024-07-29 2024-05-06 2024-07-29 2024-10-07 2024-12-20 2025-01-24 2026-07-18 onse nvelope bution des fours en futs méta llique 2- CG-PROCLIMAT-014-F-A Contingent Emergency Resp Single Stage - Two E ONR-24 / Acquisition et distri IBRD / 94930 A posteriori Appel d'offres Limited - National 700,000.00 0.00 Annulé 2024-08-14 2024-05-06 2024-08-14 2024-10-23 2025-01-05 2025-02-09 2026-08-03 onse nvelope bution des kits scolaires CG-PROCLIMAT-016-F-DC-24 Contingent Emergency Resp Single Stage - One E / Approvisionnement en eau IBRD / 94930 A posteriori Demande de prix Limited - National 20,000.00 0.00 Annulé 2024-05-30 2024-07-25 2024-08-23 onse nvelope potable disponible CG-PROCLIMAT-017-F-DC-24 Contingent Emergency Resp Single Stage - One E IBRD / 94930 A posteriori Demande de prix Limited - National 60,000.00 0.00 Achevé 2024-05-28 2024-04-25 2024-07-23 2024-05-15 2024-08-21 2024-06-04 / Acquisition du matériel dida onse nvelope ctique CG-PROCLIMAT-018-F-DC-24 Contingent Emergency Resp Single Stage - One E / Acquisition des supports de IBRD / 94930 A posteriori Demande de prix Limited - National 50,000.00 0.00 Achevé 2024-06-19 2024-04-25 2024-08-14 2024-05-15 2024-09-12 2024-06-04 onse nvelope sensibilisation CG-PROCLIMAT-019-F-24 / A cquisition des fournitures et Contingent Emergency Resp Single Stage - One E IBRD / 94930 A posteriori Demande de prix Limited - National 100,000.00 0.00 Annulé 2024-06-28 2024-08-23 2024-09-23 de matériels de travail pour l' onse nvelope opérationnalisation des MGP CG-PROCLIMAT-015-F-AONR- Contingent Emergency Resp Single Stage - One E 24 / Acquisition des produits IBRD / 94930 A posteriori Appel d'offres Open - National 300,000.00 0.00 Annulé 2024-06-27 2024-06-27 2024-09-05 2024-10-05 2024-11-09 2026-05-03 onse nvelope de désinfection des centres s colaires Page 1 CG-PROCLIMAT-014-F-AONR- Contingent Emergency Resp Single Stage - One E 24 / Acquisition et distributio IBRD / 94930 A posteriori Appel d'offres Limited - National 545,000.00 0.00 Annulé 2024-06-27 2024-06-27 2024-09-05 2024-10-05 2024-11-09 2026-05-03 onse nvelope n des kits de construction de s latrines CG-PROCLIMAT-021-F-ED-24 Contingent Emergency Resp Passation de marc / Acquisition et distribution d IBRD / 94930 A posteriori Direct - National 600,000.00 0.00 Achevé 2024-08-15 2024-04-16 2024-08-20 2024-05-21 2024-09-24 2024-06-07 2025-03-23 2024-07-18 onse hé de gré à gré es médicaments essentiels CG-PROCLIMAT-026-F-DC-24 Contingent Emergency Resp Single Stage - One E / Acquisition des médicament IBRD / 94930 A posteriori Demande de prix Limited - National 181,590.00 0.00 Signé 2024-10-05 2024-07-19 2024-11-30 2024-09-18 2025-05-29 onse nvelope s supplémentaires et spécifiq ues CG-PROCLIMAT-028-F-DC-24 / Acquisition et installation d Project Management, Monito Single Stage - One E IBRD / 94930 A posteriori Demande de prix Limited - National 99,950.00 0.00 Achevé 2024-11-20 2024-07-09 2025-01-15 2024-08-14 2025-07-14 2024-09-06 e trois (03) groupes électrog ring, and Evaluation nvelope ènes de 20 KVA au profit des BSP-ProClimat CG-PROCLIMAT-029-F-DC-24 / Acquisition du matériel infor Project Management, Monito Single Stage - One E matique au profit des stagiair IBRD / 94930 A posteriori Demande de prix Limited - National 10,000.00 0.00 Achevé 2024-11-25 2024-07-09 2025-01-20 2024-08-14 2025-07-19 2024-08-28 ring, and Evaluation nvelope es en passation des marchés et Assistants en sauvegarde CG-PROCLIMAT-030-F-DC-24 Project Management, Monito Single Stage - One E / Acquisition du mobilier de b IBRD / 94930 A posteriori Demande de prix Limited - National 33,042.00 0.00 Achevé 2024-12-03 2024-07-09 2025-01-28 2024-08-14 2025-07-27 2024-08-30 ring, and Evaluation nvelope ureau au profit des trois(03) BSP-ProClimat CG-PROCLIMAT-031-F-DC-24 / Acquisition des fournitures Project Management, Monito Single Stage - One E IBRD / 94930 A posteriori Demande de prix Limited - National 30,000.00 0.00 Achevé 2024-12-05 2024-07-16 2025-01-30 2024-08-14 2025-07-29 2024-09-05 de bureau au profit des trois( ring, and Evaluation nvelope 03) BSP-ProClimat CG-PROCLIMAT-013-F-AONR- Contingent Emergency Resp Single Stage - One E 24 / Acquisition et distributio IBRD / 94930 A posteriori Appel d'offres Open - National 800,000.00 0.00 Annulé 2024-05-06 2024-05-06 2024-05-11 2024-08-27 2024-06-22 2024-05-27 2024-07-22 2024-06-06 2024-08-26 2025-02-22 onse nvelope n des fours en futs métalliqu es CG-PROCLIMAT-0014-F-AON Contingent Emergency Resp Single Stage - One E En cours d'ex R-24 / Acquisition et distribut IBRD / 94930 A posteriori Appel d'offres Open - National 700,000.00 0.00 2024-05-06 2024-05-06 2024-05-11 2024-08-30 2024-06-22 2024-07-22 2024-08-26 2025-02-22 onse nvelope écution ion des kits scolaires CG-PROCLIMAT-047-F-ED-24 / Contractualisation par Ente nte Directe entre le ProClima Project Management, Monito Passation de marc En cours d'ex t et la société TOM@TE, pour IBRD / 94930 A posteriori Direct - National 49,563.00 0.00 2024-12-23 2024-11-13 2024-12-28 2024-11-22 2025-02-01 2025-07-31 ring, and Evaluation hé de gré à gré écution l’acquisition, l’installation et l ’opérationnalisation du logici el de Suivi-Evaluation (TOMM ONITORING, Version WEB). NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 3- CG-PROCLIMAT-015-F-A ONR-24 / Curage et désinfect Contingent Emergency Resp Single Stage - Two E IBRD / 94930 A posteriori Appel d'offres Limited - National 1,046,000.00 0.00 Annulé 2024-08-22 2024-08-22 2024-10-31 2025-01-13 2025-02-17 2026-08-11 ion des puits infectés, nettoy onse nvelope age des puits et des points d' eau inondés CG-PROCLIMAT-025-S-ED-24 / Recrutement d'une agence de paiement des primes des Contingent Emergency Resp Passation de marc enseignants en charges des t IBRD / 94930 A posteriori Direct - National 12,106.00 0.00 Signé 2024-09-27 2024-05-15 2024-10-02 2024-09-01 2024-11-06 2024-07-18 2025-05-05 onse hé de gré à gré ravaux dirigés des élèves de s classes d'examen des distri cts de Mossaka, Epena et Ma kotimpoko. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PROCLIMAT-008-C-SQC-2 Sélection fondée s 4 / Recrutement d'un cabinet Project Management, Monito Limited - Internatio IBRD / 94930 A posteriori ur les qualification 33,042.00 0.00 Annulé 2024-05-31 2024-03-18 2024-06-14 2024-07-14 2024-08-18 2025-02-14 d'audit interne exercices 202 ring, and Evaluation nal s des consultants 4-2025, pour le compte du P ROCLIMAT CG-PROCLIMAT-009-C-SQC-2 Sélection fondée s 4 / Recrutement d'un cabinet Project Management, Monito Open - Internationa En cours d'exécut IBRD / 94930 A posteriori ur la qualité et le 123,908.00 0.00 2024-07-26 2024-07-09 2024-08-16 2024-08-09 2024-09-29 2024-10-27 2024-11-26 2024-12-31 2025-02-04 2026-02-04 d'audit externe, exercices 20 ring, and Evaluation l ion coût 24-2026, pour le compte du PROCLIMAT. CG-PROCLIMAT-020-C-SFQC- Strengthening Capacity of In Sélection fondée s 24 / Recrutement d'un cabin Open - Internationa En cours d'exécut IBRD / 94930 stitutions and Promoting Soc A priori ur la qualité et le 6,300,000.00 0.00 2024-08-23 2024-04-16 2024-09-13 2024-05-30 2024-10-27 2024-09-09 2024-11-24 2024-10-22 2024-12-24 2025-01-28 2025-03-04 2026-03-04 et pour développer les plans l ion ial Cohesion coût d'investissement du projet (P IP) CG-PROCLIMAT-032-C-QC-24 / Recrutement d'un consultan t chargé de l'évaluation des c Strengthening Capacity of In Sélection fondée s En cours d'exécut apacités organisationnelles d IBRD / 94930 stitutions and Promoting Soc A posteriori ur les qualification Open - National 33,042.00 0.00 2024-12-20 2024-06-28 2025-01-10 2024-08-09 2025-02-23 2024-09-20 2025-03-25 2025-04-29 2025-10-26 ion es groupements de producte ial Cohesion s des consultants urs agricoles, des coopérativ es et des MPME opérant dans les zones du projet. CG-PROCLIMAT-039-C-QC-24 Sélection fondée s Project Management, Monito En cours d'exécut / Recrutement d'une Agence IBRD / 94930 A posteriori ur les qualification Open - National 99,500.00 0.00 2024-11-15 2024-07-30 2024-12-06 2024-09-02 2025-01-19 2025-02-18 2025-03-25 2025-09-21 ring, and Evaluation ion de Vérification Indépendante s des consultants du Projet CG-PROCLIMAT-035-C-QC-24 Strengthening Investments i Sélection fondée s / Recrutement d'un cabinet n Sustainable and Resilient En cours d'exécut IBRD / 94930 A priori ur la qualité et le Open - National 761,841.00 0.00 2024-11-29 2024-08-06 2024-12-20 2024-08-22 2025-02-02 2024-12-07 2025-03-02 2025-04-01 2025-05-06 2025-06-10 2026-06-10 pour la mise en œuvre de la Agriculture and Natural Capi ion coût composante 3 dans le BSP de tal Management Ouesso CG-PROCLIMAT-036-C-QC-24 Strengthening Investments i Sélection fondée s / Recrutement d'un cabinet p n Sustainable and Resilient En cours d'exame IBRD / 94930 A priori ur la qualité et le Open - National 1,251,631.00 0.00 2024-11-28 2024-08-06 2024-12-19 2024-08-27 2025-02-01 2025-03-01 2025-03-31 2025-05-05 2025-06-09 2026-06-09 our la mise en œuvre de la c Agriculture and Natural Capi n coût omposante 3 dans le BSP de tal Management Ignié Page 2 CG-PROCLIMAT-037-C-QC-24 Strengthening Investments i Sélection fondée s / Recrutement d'un cabinet p n Sustainable and Resilient En cours d'exécut IBRD / 94930 A priori ur la qualité et le Open - National 812,074.00 0.00 2024-11-25 2024-08-06 2024-12-16 2024-09-04 2025-01-29 2024-12-19 2025-02-26 2025-03-28 2025-05-02 2025-06-06 2026-06-06 our la mise en œuvre de la c Agriculture and Natural Capi ion coût omposante 3 dans le BSP de tal Management Pointe-Noire CG-PROCLIMAT-041-C-QC-24 / Recrutement d'un bureau d' études pour le contrôle techn Sélection fondée s Contingent Emergency Resp En cours d'exécut ique des travaux de construc IBRD / 94930 A posteriori ur les qualification Open - National 300,000.00 0.00 2024-11-25 2024-08-06 2024-12-16 2024-09-02 2025-01-29 2024-10-18 2025-02-28 2025-04-04 2025-10-01 onse ion tion de 34 Forages (soit 12 lo s des consultants ts) dans les localités des dép artements affectés par les in ondations en République du Congo. CG-PROCLIMAT-044-C-QC-24 Strengthening Investments i / Recrutement d'un consultan Sélection fondée s n Sustainable and Resilient En cours d'exécut t pour l'identification des peti IDA / 74330 A posteriori ur les qualification Open - National 289,118.00 0.00 2024-12-10 2024-09-11 2024-12-31 2024-10-09 2025-02-13 2024-10-18 2025-03-15 2025-04-19 2025-10-16 Agriculture and Natural Capi ion ts exploitants agricoles vulné s des consultants tal Management rables à l'insécurité alimentai re et nutritionnelle. CG-PROCLIMAT-045-C-QC-24 / Recrutement d'un cabinet o Strengthening Capacity of In Sélection fondée s u ONG en charge de l'analys En cours d'exécut IBRD / 94930 stitutions and Promoting Soc A posteriori ur les qualification Open - National 34,000.00 0.00 2024-12-30 2024-10-02 2025-01-20 2024-10-25 2025-03-05 2024-12-06 2025-04-04 2025-05-09 2025-11-05 e des dimensions sociales de ion ial Cohesion s des consultants changement climatique dans les zones d'intervention du p rojet ProClimat. CG-PROCLIMAT-0046-C-QC-2 4 / Recrutement d'un consult ant en charge de l'analyse de Strengthening Capacity of In Sélection fondée s s dimensions du genre face a En attente d'exéc IBRD / 94930 stitutions and Promoting Soc A posteriori ur les qualification Open - National 132,168.00 0.00 2025-03-07 2025-03-28 2025-05-11 2025-06-10 2025-07-15 2026-01-11 u changement climatique en ution ial Cohesion s des consultants Rép. du Congo et la promotio n de l'inclusion des femmes dans les activités du projet e n appliquant une optique cli matique. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PROCLIMAT-012-C-CI-24 Promoting Inclusive, Climate / Recrutement d'un consultan IBRD / 94930 -resilient Livelihoods and Val A posteriori Individuel Limited - National 30,000.00 0.00 Signé 2024-07-25 2024-04-16 2024-07-30 2024-05-10 2024-08-20 2024-08-16 2024-09-24 2024-08-20 2025-03-23 t individuel pour la rédaction ue Chains d'un manuel de subventions CG-PROCLIMAT-022-C-ED-24 Sélection de cons Contingent Emergency Resp / Mission de l'INS pour la coll IBRD / 94930 A posteriori ultants par entent Direct - National 434,007.00 0.00 Signé 2024-08-20 2024-04-17 2024-08-30 2024-04-18 2024-11-03 2024-05-17 2025-05-02 onse ecte de données de la compo e directe sante CERC CG-PROCLIMAT-023-C-ED-24 Sélection de cons / Mission d’un consultant spé Contingent Emergency Resp IBRD / 94930 A posteriori ultants par entent Direct - National 18,206.00 0.00 Achevé 2024-05-31 2024-05-11 2024-06-10 2024-06-06 2024-08-14 2024-06-21 2025-02-10 2024-11-25 cialiste en passation de marc onse e directe hé pour le ProClimat CG-PROCLIMAT-024-C-ED-24 / Contractualisation par ente Responding to Immediate Fo Sélection de cons nte directe entre le ProClimat Direct - Internation IDA / 74330 od and Nutrition Security Ne A priori ultants par entent 13,000,000.00 0.00 Signé 2024-09-13 2024-05-23 2024-09-23 2024-05-28 2024-11-27 2024-06-18 2025-05-26 et le PAM pour répondre aux al eds e directe besoins immédiats en matièr e de sécurité alimentaire et n utritionnelle. CG-PROCLIMAT-027-C-CI-24 / Recrutement d'un consultan Project Management, Monito IBRD / 94930 A posteriori Individuel Limited - National 39,350.00 0.00 Annulé 2024-09-28 2024-06-25 2024-10-03 2024-10-24 2024-11-28 2025-05-27 t individuel pour l'élaboration ring, and Evaluation d'un plan en faveur des popu lations autochtones CG-PROCLIMAT-033-C-CI-24 / Recrutement d'un Consulta nt Individuel pour la réalisati Contingent Emergency Resp on d'une enquête relative à l' IBRD / 94930 A posteriori Individuel Limited - National 8,261.00 0.00 Achevé 2024-10-25 2024-07-12 2024-10-30 2024-07-12 2024-11-20 2024-08-12 2024-12-25 2024-08-12 2025-06-23 2024-10-10 onse incident survenu lors de la mi ssion de collecte des donnée s par l'INS dans le départeme nt de la Likouala CG-PROCLIMAT-034-C-CI-24 / Recrutement d'un Consulta Strengthening Capacity of In nt Individuel pour l'élaboratio En cours d'exécut IBRD / 94930 stitutions and Promoting Soc A posteriori Individuel Limited - National 33,042.00 0.00 2024-11-15 2024-07-12 2024-11-20 2024-08-16 2024-12-11 2025-01-15 2025-07-14 n du Plan National de Prépar ion ial Cohesion ation et Réponse aux Crise d e Sécurité Alimentaire (PNPR CSA) du Congo CG-PROCLIMAT-042-C-ED-24 / Recrutement d’un Consulta nt pour la réalisation d’une e Sélection de cons Contingent Emergency Resp nquête suite à l’incident surv IBRD / 94930 A posteriori ultants par entent Direct - National 8,260.00 0.00 Achevé 2024-11-29 2024-08-29 2024-12-09 2024-09-05 2025-02-12 2024-09-17 2025-08-11 2024-10-30 onse enu dans le cadre de la missi e directe on de collecte des données d ans le district de Bouaniela ( département de la Likouala) CG-PROCLIMAT-043-C-CI-24 Project Management, Monito En cours d'exécut / Recrutement d'un consultan IBRD / 94930 A posteriori Individuel Open - National 29,738.00 0.00 2024-11-29 2024-11-07 2025-01-17 2024-11-07 2025-02-07 2025-03-14 2025-09-10 ring, and Evaluation ion t individuel pour l'audit inter ne du ProClimat CG-PROCLIMAT-0027-C-CI-2 4 / Recrutement d'un consult Project Management, Monito IBRD / 94930 A posteriori Individuel Open - National 100,000.00 0.00 Signé 2024-06-25 2024-09-02 2024-08-13 2024-09-20 2024-09-03 2024-10-29 2024-10-08 2024-10-30 2025-04-06 ant individuel pour l'élaborati ring, and Evaluation on d'un plan en faveur des p euples autochtones CG-PROCLIMAT-046-C-CI-24 / Recrutement d'un consultan t individuel en charge de l'an Strengthening Capacity of In alyse des dimensions du gen IBRD / 94930 stitutions and Promoting Soc A posteriori Individuel Open - National 34,000.00 0.00 Annulé 2024-12-27 2024-10-01 2025-02-14 2024-11-22 2025-03-07 2025-04-11 2025-10-08 re face au changement clima ial Cohesion tique en Rép. du Congo et la promotion de l'inclusion des f emmes dans les activités du projet en appliquant une opti que climatique. CG-PROCLIMAT-048-C-ED-24 / Contractualisation par ente Strengthening Investments i Sélection de cons nte directe entre le ProClimat n Sustainable and Resilient En cours d'exécut IBRD / 94930 A priori ultants par entent Direct - National 3,400,000.00 0.00 2024-12-20 2024-11-12 2024-12-30 2024-11-12 2025-03-05 2025-09-01 et le consultant World Wide F Agriculture and Natural Capi ion e directe und for Nature (WWF) pour la tal Management gestion du Parc National Nto kou-Pikounda. Page 3 CG-PROCLIMAT-049-C-ED-24 / Contractualisation par ente Strengthening Investments i Sélection de cons nte directe entre le ProClimat n Sustainable and Resilient En cours d'exécut IBRD / 94930 A priori ultants par entent Direct - National 4,296,516.00 0.00 2024-11-27 2024-11-26 2024-12-07 2024-12-04 2025-02-10 2025-08-09 et le consultant ONG Noé Agriculture and Natural Capi ion e directe pour la gestion du Parc Natio tal Management nal de Conkouati Douli CG-PROCLIMAT-050-C-ED-24 / Contractualisation par ente Strengthening Investments i Sélection de cons nte directe entre le ProClimat n Sustainable and Resilient En cours d'exécut IBRD / 94930 A priori ultants par entent Direct - National 2,643,361.00 0.00 2024-11-28 2024-11-26 2024-12-08 2024-12-04 2025-02-11 2025-08-10 et la Fondation Aspinall pour Agriculture and Natural Capi ion e directe la gestion de la Reserve Natu tal Management relle de Gorille de Lossi CG-PROCLIMAT-051-C-ED-24 / Contractualisation par ente nte directe entre le ProClimat Promoting Inclusive, Climate Sélection de cons et le Centre d’Investissement Direct - Internation En cours d'exécut IBRD / 94930 -resilient Livelihoods and Val A priori ultants par entent 282,000.00 0.00 2024-12-10 2024-12-20 2025-02-23 2025-08-22 de la FAO pour la formation d al ion ue Chains e directe es prestataires de la mise en œuvre de la composante 3 s ur le montage des plans d’aff aires avec le logiciel RuralInv est CG-PROCLIMAT-052-C-ED-24 / Contractualisation par Ente nte Directe entre le Projet de Création des Activités écono Sélection de cons Project Management, Monito En attente d'exéc miques Inclusives et Résilient IBRD / 94930 A posteriori ultants par entent Direct - National 19,825.00 0.00 2025-02-20 2025-03-02 2025-05-06 2025-11-02 ring, and Evaluation ution es au Changement Climatiqu e directe e (ProClimat – Congo) et la C onsultante RADJIMTA NDILEN GAR Grace, Spécialiste en Pa ssation des Marchés Page 4