PROCUREMENT PLAN (Textual Part) Country: Republic of Tajikistan Full Project Name: Tajikistan Socio-Economic Project Resilience Strengthening information Program Total Finance ($): US$ 37 million equivalent Project Number: P168052 Project Implementing Agencies NSIFT Date of the Procurement Plan April XXX, 2019 (initial) Period covered by this Procurement Project duration (5 years) Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Tendering with Unlimited Participation” method set forth in the Law of the Republic of Tajikistan “Оn Public Procurement of Goods, Works and Services”, # 168 dated March 3, 2006 (as amended by Law #815, the “Law of the Republic of Tajikistan on “Introduction of Amendments and Additions to the Law of the Republic of Tajikistan on ‘Public Procurement of Goods, Works and Services’” dated April 16, 2012), provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, World Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • The request for bids/request for proposals document, including contract forms, acceptable to the Bank shall be used. • The request for bids/request for proposals document and contract shall provide the right to the Bank to review procurement documentation and activities. • Borrower shall put in place an effective complaints review mechanism with procurement related complaints and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. • No preference shall be applied under competitive bidding following national market approach. Other national procurement arrangements such as tendering with limited participation, request for quotations, direct contracting, may be used on the above stated conditions. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): “Not Applicable” Other Relevant Procurement Information. The community-driven development (CDD) approach and procurement by the communities will follow Procurement Regulations paragraph 6.52 and Annex XII - Selection Methods, paragraphs 6.9 and 6.10. The procurement arrangements at the community level (including procurement responsibilities, procedures, disclosure requirements, sample documentation and oversight mechanisms) will be elaborated in the Project Operations Manual (POM) and Sub-Grant Manual (SGM) that shall be approved by the Bank and made publicly available by the Borrower. Community procurement will follow the Guidance Note for Design and Management of Procurement Responsibilities in Community Driven Development Projects (March 15, 2012). PROCUREMENT Tajikistan : Tajikistan Socio-Economic Resilience Strengthening Project PLAN General Information Country: Tajikistan 2020-03-17 Bank’s Approval Date of the Original Procurement Plan: 2025-01-08 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168052 GPN Date: 2020-05-22 Project Name: Tajikistan Socio-Economic Resilience Strengthening Project Loan / Credit No: IDA / D5000 National Social Investment Fund of Tajikistan Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NSIFT-SERSP-CW-1C-04 / Ro of restoration and overhaul o f 3 classrooms for the creatio Component 1: Inclusive Loca Request for Quota Single Stage - One E 2021-11-0 IDA / D5000 Post Open - National 65,000.00 57,793.93 Completed 2021-03-13 2021-05-18 2021-05-08 2021-05-12 n of a youth training center i l Development Initiatives tions nvelope 4 n a three-storey building of a vocational school in the Mosc ow village, Hamadoni district NSIFT-SERSP-CW-1C-07 / Ov erhaul of the Center for Addit ional Education for the creati Component 1: Inclusive Loca Request for Quota Single Stage - One E 2021-11-0 IDA / D5000 Post Open - National 80,000.00 77,373.62 Completed 2021-03-13 2021-05-18 2021-05-08 2021-05-12 on of a youth training center l Development Initiatives tions nvelope 4 in the Firuz village, jamoat 2 0 years of Independence of T ajikistan, Farkhor district NSIFT-SERSP-CW-1C-01 / Ov erhaul of 3 classrooms for th Component 1: Inclusive Loca Request for Quota Single Stage - One E 2021-11-0 e creation of a youth training IDA / D5000 Post Open - National 48,681.00 32,161.47 Completed 2021-03-13 2021-05-18 2021-05-08 2021-05-12 l Development Initiatives tions nvelope 4 center in the building of the Adult Education Center in Kul ob NSIFT-SERSP-CW-1C-02 / Ov erhaul of 3 classrooms for cr Component 1: Inclusive Loca Request for Quota Single Stage - One E 2021-11-0 eation of a youth training cen IDA / D5000 Post Open - National 34,218.00 30,443.80 Completed 2021-03-13 2021-05-18 2021-05-08 2021-05-12 l Development Initiatives tions nvelope 4 ter in the building of the Cent er of Additional Education in Kulob NSIFT-SERSP-CW-1C-14 / Re Request for Quota construction and major refur Component 1: Inclusive Loca Request for Quota Single Stage - One E tions - Small Work 2021-12-2 bishment of the building of M IDA / D5000 Post Open - National 65,000.00 84,260.76 Completed 2021-05-03 2021-05-17 2021-06-28 2021-05-31 l Development Initiatives tions nvelope s (Emergency) SP 5 . Shirinjonov rural jamoat for D -Competitive establishing the Youth Traini ng Center in Shughnon distri ct NSIFT-SERSP-CW-1C-13 / Maj or refurbishment of the Cent Request for Quota er for Additional Education fo Component 1: Inclusive Loca Request for Quota Single Stage - One E tions - Small Work 2021-12-2 IDA / D5000 Post Open - National 65,000.00 112,793.24 Completed 2021-05-03 2021-05-17 2021-06-28 2021-05-31 r establishing Youth Training l Development Initiatives tions nvelope s (Emergency) SP 5 Center in Kushk village, Pors D -Competitive hnev jamoat, Shughnon distri ct NSIFT-SERSP-CW-1C-12 / Maj Request for Quota or refurbishment of 3 classro Component 1: Inclusive Loca Request for Quota Single Stage - One E tions - Small Work 2021-12-2 oms for establishing Youth Tr IDA / D5000 Post Open - National 48,681.00 15,875.49 Completed 2021-05-03 2021-05-17 2021-06-28 2021-06-04 l Development Initiatives tions nvelope s (Emergency) SP 5 aining Center in the building D -Competitive of Adults Training Center in S h. Shotemur jamoat, Khorog NSIFT-SERSP-CW-1C-16 / Maj or refurbishment of the printi Request for Quota ng house "Zindagi" newspap Component 1: Inclusive Loca Request for Quota Single Stage - One E tions - Small Work 2021-12-2 IDA / D5000 Post Open - National 100,000.00 118,332.75 Completed 2021-05-03 2021-05-17 2021-06-28 2021-06-01 er for establishing Youth Trai l Development Initiatives tions nvelope s (Emergency) SP 5 ning Center in Ishkoshim villa D -Competitive ge, R. Yusufbekov jamoat, Is hkoshim district NSIFT-SERSP-CW-1C-17 / Maj Request for Quota or refurbishment of the buildi Component 1: Inclusive Loca Request for Quota Single Stage - One E tions - Small Work 2021-12-2 ng of A. Zamirov jamoat for e IDA / D5000 Post Open - National 80,000.00 111,168.42 Signed 2021-05-03 2021-05-17 2021-06-28 2021-06-01 l Development Initiatives tions nvelope s (Emergency) SP 5 stablishing Youth Training Ce D -Competitive nter in Ishkoshim district NSIFT-SERSP-CW-1C-10 / Co nstruction of a two-storey bui Request for Bids - lding for 8 classrooms for est Component 1: Inclusive Loca Single Stage - One E Works (without pr 2022-06-0 IDA / D5000 Post Request for Bids Open - National 250,000.00 273,873.60 Signed 2021-08-21 2021-08-02 2021-08-26 2021-10-07 2021-08-23 2021-11-06 2021-09-06 2021-12-11 2021-10-04 ablishing the Youth Training l Development Initiatives nvelope equalification) SP 9 Center in Roharv village of M. D Abdulloev rural jamoat in Va nj district NSIFT-SERSP-CW-1C-03 / Co nstruction of a building for 3 Request for Quota classrooms for establishing t Component 1: Inclusive Loca Request for Quota Single Stage - One E 2022-08-1 IDA / D5000 Post Open - National tions (Non Bank-S 60,000.00 71,746.41 Signed 2021-12-25 2022-02-19 2021-09-30 he Youth Training Center on t l Development Initiatives tions nvelope 8 PD) he territory of the vocational lyceum of the rural jamoat D ahana in Kulob city NSIFT-SERSP-CW-1C-05 / Co nstruction of a building for 3 Request for Quota Component 1: Inclusive Loca Request for Quota Single Stage - One E 2022-08-1 classes for establishing the Y IDA / D5000 Post Open - National tions (Non Bank-S 60,000.00 80,838.58 Signed 2021-12-25 2022-02-19 2021-09-30 l Development Initiatives tions nvelope 8 outh Training Center in Somo PD) niyon village of Turdiyev rura l jamoat, Hamadoni district NSIFT-SERSP-CW-1C-06 / Co nstruction of a building for 3 Request for Quota classrooms for establishing t Component 1: Inclusive Loca Request for Quota Single Stage - One E 2022-08-1 IDA / D5000 Post Open - National tions (Non Bank-S 60,000.00 84,148.79 Signed 2021-12-25 2022-02-19 2021-09-30 he youth training center on t l Development Initiatives tions nvelope 8 PD) he territory of a vocational ly ceum in Farkhor village, Fark hor district NSIFT-SERSP-CW-1C-08 / Co nstruction of a two-storey bui Component 1: Inclusive Loca Single Stage - One E Other (with field f 2022-10-1 lding for 8 classrooms for est IDA / D5000 Post Request for Bids Open - National 220,000.00 279,894.67 Signed 2021-12-22 2021-08-18 2021-12-27 2022-02-07 2021-09-08 2022-03-09 2021-09-13 2022-04-13 2021-10-20 l Development Initiatives nvelope or explanation) 0 ablishing the Youth Training Center in Panj township of Pa nj district NSIFT-SERSP-CW-1C-09 / Co nstruction of a building for 3 Request for Quota Component 1: Inclusive Loca Request for Quota Single Stage - One E 2022-08-1 classrooms for establishing t IDA / D5000 Post Open - National tions (Non Bank-S 60,000.00 77,452.09 Terminated 2021-12-25 2022-02-19 2021-10-04 l Development Initiatives tions nvelope 8 he Youth Training Center in N PD) amuna village of Namuna rur al jamoat in Panj district Page 1 NSIFT-SERSP-CW-1C-11 / Est Request for Quota ablishment of the Youth Trai Component 1: Inclusive Loca Request for Quota Single Stage - One E 2022-08-2 IDA / D5000 Post Open - National tions (Non Bank-S 5,000.00 624,451.64 Signed 2021-12-27 2022-02-21 2022-01-12 ning Center in two-storey bui l Development Initiatives tions nvelope 0 PD) lding in Yazgulom jamoat of Vanj district NSIFT-SERSP-CW-1C-15 / Est ablishment of the Youth Trai Request for Quota Component 1: Inclusive Loca Request for Quota Single Stage - One E 2022-08-2 ning Center in the two-storey IDA / D5000 Post Open - National tions (Non Bank-S 5,000.00 6,599.20 Signed 2021-12-27 2022-02-21 2022-01-17 l Development Initiatives tions nvelope 0 building of the Adult's Trainin PD) g Center in Vakhdat rural jam oat of Shugnon district NSIFT-SERSP-CW-1С-01/1 / C onstruction of a toilet in the Request for Quota Component 1: Inclusive Loca Request for Quota Single Stage - One E Pending Imp 2025-07-2 Youth Training Center at the IDA / D5000 Post Open - National tions (Non Bank-S 7,846.72 0.00 2024-11-26 2025-01-21 l Development Initiatives tions nvelope lementation 0 Adult Training Center’s buildi PD) ng on 12 1-May Str. in Kulob city NSIFT-SERSP-CW-1С-02/1 / C onstruction of a toilet in the Request for Quota Component 1: Inclusive Loca Request for Quota Single Stage - One E Pending Imp 2025-07-2 Youth Training Center at the IDA / D5000 Post Open - National tions (Non Bank-S 20,822.77 0.00 2024-11-26 2025-01-21 l Development Initiatives tions nvelope lementation 0 Center for Additional Educati PD) on on 12 I.Somoni Avenue in Kulob city NSIFT-SERSP-CW-1С-04/1 / C onstruction of a toilet in the Request for Quota Component 1: Inclusive Loca Request for Quota Single Stage - One E Pending Imp 2025-07-2 Youth Training Center in a th IDA / D5000 Post Open - National tions (Non Bank-S 17,544.28 0.00 2024-11-26 2025-01-21 l Development Initiatives tions nvelope lementation 0 ree-storey building of a vocat PD) ional lyceum in Moscow town ship of Hamadoni district NSIFT-SERSP-CW-1С-09-1 / C onstruction of a building for 3 Request for Quota Component 1: Inclusive Loca Request for Quota Single Stage - One E Pending Imp 2025-07-2 classrooms for establishing t IDA / D5000 Post Open - National tions (Non Bank-S 56,989.83 0.00 2024-11-26 2025-01-21 l Development Initiatives tions nvelope lementation 0 he Youth Training Center in N PD) amuna village of Namuna rur al jamoat, Panj district NSIFT-SERSP-1С-13/1 / Const ruction of a toilet in the Cent Request for Quota er for Additional Education fo Component 1: Inclusive Loca Request for Quota Single Stage - One E Pending Imp 2025-07-2 IDA / D5000 Post Open - National tions (Non Bank-S 7,895.35 0.00 2024-11-26 2025-01-21 r establishing the Youth Train l Development Initiatives tions nvelope lementation 0 PD) ing Center in Kushk village of Porshnev rural jamoat in Shu gnon district GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NSIFT-SERSP-G-4-1 / Procure Component 3: Project Manag Request for Quota Single Stage - One E ment of vehicles in the frame IDA / D5000 ement and Monitoring and E Post Open - National 100,000.00 87,956.21 Completed 2020-08-25 2020-10-20 2020-09-22 2021-04-18 2021-01-01 tions nvelope work of SERSP (package 1) valuation NSIFT-SERSP-G-4-2 / Procure Component 3: Project Manag Request for Quota Single Stage - One E ment of vehicles in the frame IDA / D5000 ement and Monitoring and E Post Open - National 40,000.00 35,130.54 Completed 2020-10-06 2020-12-01 2020-11-13 2021-05-30 2021-01-25 tions nvelope work of SERSP (package 2) valuation NSIFT-SERSP-G-3-1 / Comput Component 3: Project Manag Request for Quota Single Stage - One E IDA / D5000 Post Open - National 34,900.00 30,571.13 Completed 2020-10-24 2020-12-19 2020-08-29 2021-06-17 2020-12-06 er equipment for NSIFT ement and Monitoring and E tions nvelope valuation NSIFT-SERSP-G-3-2 / Procure Component 3: Project Manag ment ofoffice equipment for Request for Quota Single Stage - One E IDA / D5000 ement and Monitoring and E Post Open - National 8,000.00 10,570.43 Completed 2020-10-24 2020-12-19 2020-08-29 2021-06-17 2020-09-24 National Social Investment F tions nvelope valuation und of Tajikistan in the frame work of SERSP NSIFT-SERSP-G-12 / Procure Component 1: Inclusive Loca Request for Quota Single Stage - One E ment of furniture equipment IDA / D5000 Post Open - National 40,000.00 62,095.17 Signed 2021-12-29 2021-12-23 2022-02-23 2022-01-17 2022-08-22 l Development Initiatives tions nvelope for 44 SERSP Jamoat Project Commissions. NSIFT-SERSP-G-11 / Procure Component 1: Inclusive Loca Request for Quota Single Stage - One E ment of computer equipment IDA / D5000 Post Open - National 87,780.00 71,546.30 Signed 2021-12-29 2021-12-23 2022-02-23 2022-01-17 2022-08-22 l Development Initiatives tions nvelope for 44 SERSP Jamoat Project Commissions NSIFT-SERSP-G-1-3 / Procure Component 1: Inclusive Loca Request for Quota Single Stage - One E ment of furniture equipment IDA / D5000 Post Open - National 100,000.00 94,913.20 Signed 2021-12-21 2022-02-15 2021-08-15 2022-08-14 l Development Initiatives tions nvelope for 4 Khatlon and 7 GBAO yo uth center NSIFT-SERSP-G-1-1 / Comput er equipment for Khatlon (NS Component 1: Inclusive Loca Request for Quota Single Stage - One E IFT-SERSP-CW-1C-01, NSIFT- IDA / D5000 Post Open - National 65,000.00 62,451.90 Signed 2021-12-21 2022-02-15 2021-07-23 2022-08-14 l Development Initiatives tions nvelope SERSP-CW-1C-02, NSIFT-SER SP-CW-1C-04, NSIFT-SERSP-C W-1C-07) youth centers. NSIFT-SERSP-G-1-2 / Comput er equipment for GBAO (NSIF T-SERSP-CW-1C-11, NSIFT-SE RSP-CW-1C-12, NSIFT-SERSP- Component 1: Inclusive Loca Request for Quota Single Stage - One E IDA / D5000 Post Open - National 85,000.00 82,514.44 Signed 2021-12-21 2022-02-15 2021-07-23 2022-08-14 CW-1C-13, NSIFT-SERSP-CW- l Development Initiatives tions nvelope 1C-14, NSIFT-SERSP-CW-1C-1 5, NSIFT-SERSP-CW-1C-16, N SIFT-SERSP-CW-1C-17) youth centers. NSIFT-SERSP-G-2A-1 / Procur ement of communication mat Component 2: Youth Inclusio Request for Quota Single Stage - One E IDA / D5000 Post Open - National 95,000.00 0.00 Completed 2021-12-27 2022-02-21 2022-06-03 2022-08-20 2023-05-17 erials (T-shirts) for Compone n and Livelihoods tions nvelope nt 2 beneficiaries. NSIFT-SERSP-G-2A-2 / Procur Component 2: Youth Inclusio Request for Quota Single Stage - One E ement of communication mat IDA / D5000 Post Open - National 65,000.00 0.00 Completed 2021-12-27 2022-02-21 2022-06-03 2022-08-20 2023-01-17 n and Livelihoods tions nvelope erials (caps) for Component 2 beneficiaries. NSIFT-SERSP-G-1-5-1 / Procu rement of office equipment f or 4 Khatlon region youth ce Component 1: Inclusive Loca Request for Quota Single Stage - One E IDA / D5000 Post Open - National 60,000.00 0.00 Completed 2022-02-26 2022-02-25 2022-04-23 2022-03-04 2022-10-20 2022-05-05 nters (NSIFT-SERSP-CW-1C-0 l Development Initiatives tions nvelope 3, NSIFT-SERSP-CW-1C-05, N SIFT-SERSP-CW-1C-06, NSIFT -SERSP-CW-1C-09) NSIFT-CSP/SERSP-G-1-3/3-1 / Component 2: Youth Inclusio Request for Quota Single Stage - One E Procurement of additional co IDA / D5000 Post Open - National 22,000.00 0.00 Completed 2022-05-10 2022-07-05 2022-04-04 2023-01-01 2022-06-24 n and Livelihoods tions nvelope mputer and furniture equipm ent for NSIFT Page 2 NSIFT-SERSP-G-2A-3 / Equip ment for Subcomponent 2A I Component 2: Youth Inclusio Request for Quota Single Stage - One E IDA / D5000 Post Open - National 95,000.00 0.00 Completed 2022-08-22 2022-10-17 2022-09-20 2023-04-15 2022-12-20 mplementation Partner mobil n and Livelihoods tions nvelope e kits (laptops, projectors) NSIFT-SERSP-G-1C-04 / Whe Component 1: Inclusive Loca Request for Quota Single Stage - One E elchairs for subcomponent 1 IDA / D5000 Post Open - National 73,000.00 0.00 Completed 2022-10-04 2022-11-29 2022-12-06 2023-05-28 2023-03-15 l Development Initiatives tions nvelope C youth centers NSIFT-SERSP-G-1-5-2 / Procu rement of computer equipme nt for 4 Khatlon region youth Component 1: Inclusive Loca Request for Quota Single Stage - One E IDA / D5000 Post Open - National 82,000.00 0.00 Canceled 2022-02-26 2022-02-25 2022-04-23 2022-10-20 centers (NSIFT-SERSP-CW-1C l Development Initiatives tions nvelope -03, NSIFT-SERSP-CW-1C-05, NSIFT-SERSP-CW-1C-06, NSIF T-SERSP-CW-1C-09) NSIFT-SERSP-G-2B-01 / Proc urement, delivery and install Component 2: Youth Inclusio Request for Quota Single Stage - One E ation of furniture and equipm IDA / D5000 Post Open - National 98,664.00 0.00 Completed 2023-08-16 2023-10-11 2023-09-13 2024-04-08 2023-09-26 n and Livelihoods tions nvelope ent for the first batch of Subc omponent 2B beneficiaries in Khatlon region. NSIFT-SERSP-G-2B-02 / Proc urement and delivery of furni Component 2: Youth Inclusio Request for Quota Single Stage - One E ture and equipment for the s IDA / D5000 Post Open - National 99,600.00 0.00 Completed 2023-09-13 2023-11-08 2023-09-21 2024-05-06 2023-10-27 n and Livelihoods tions nvelope econd batch of Subcompone nt 2B beneficiaries in Khatlon region NSIFT-SERSP-G-2B-03 / Proc urement and delivery of furni Component 2: Youth Inclusio Request for Quota Single Stage - One E ture and equipment for the t IDA / D5000 Post Open - National 97,300.00 0.00 Completed 2023-09-13 2023-11-08 2023-09-21 2024-05-06 2024-05-22 n and Livelihoods tions nvelope hird batch of Subcomponent 2B beneficiaries in Khatlon re gion NSIFT-SERSP-G-2B-04 / Proc urement and delivery of furni Component 2: Youth Inclusio Request for Quota Single Stage - One E ture and equipment for the f IDA / D5000 Post Open - National 85,500.00 0.00 Signed 2023-09-13 2023-11-08 2023-09-21 2024-05-06 n and Livelihoods tions nvelope ourth batch of Subcomponen t 2B beneficiaries in Khatlon r egion NSIFT-SERSP-G-2B-05 / Proc urement and delivery of furni Component 2: Youth Inclusio Request for Quota Single Stage - One E IDA / D5000 Post Open - National 82,200.00 0.00 Completed 2023-09-13 2023-11-08 2023-09-21 2024-05-06 2024-05-22 ture and equipment for the fi n and Livelihoods tions nvelope rst batch of Subcomponent 2 B beneficiaries in GBAO NSIFT-SERSP-G-2В-04-1 / Pro curement and delivery of fur Component 2: Youth Inclusio Request for Quota Single Stage - One E niture and equipment for the IDA / D5000 Post Open - National 30,000.00 0.00 Completed 2023-09-18 2023-11-13 2023-09-22 2024-05-11 2023-09-22 n and Livelihoods tions nvelope fourth batch of Subcompone nt 2B beneficiaries in Khatlon region NSIFT-SERSP-G-2В-05-1 / Pro curement and delivery of fur Component 2: Youth Inclusio Request for Quota Single Stage - One E niture and equipment for the IDA / D5000 Post Open - National 31,500.00 0.00 Completed 2023-09-18 2023-11-13 2023-09-22 2024-05-11 2023-10-19 n and Livelihoods tions nvelope first batch of Subcomponent 2B beneficiaries in GBAO NSIFT-SERSP-G-2В-06 / Proc urement and delivery of equi Component 2: Youth Inclusio Request for Quota Single Stage - One E IDA / D5000 Post Open - National 91,500.00 0.00 Completed 2023-09-18 2023-11-13 2023-09-22 2024-05-11 2023-11-23 pment for the fifth batch of S n and Livelihoods tions nvelope ubcomponent 2B beneficiarie s in Khatlon region NSIFT-SERSP-G-2В-06-1 / Pro curement and delivery of equ Component 2: Youth Inclusio Request for Quota Single Stage - One E IDA / D5000 Post Open - National 30,000.00 0.00 Signed 2023-09-18 2023-11-13 2023-09-22 2024-05-11 ipment for the fifth batch of n and Livelihoods tions nvelope Subcomponent 2B beneficiari es in Khatlon region NSIFT-SERSP-G-2В-07 / Proc urement and delivery of equi Component 2: Youth Inclusio Request for Quota Single Stage - One E IDA / D5000 Post Open - National 78,000.00 0.00 Completed 2023-10-02 2023-11-27 2023-10-20 2024-05-25 2023-11-23 pment for the sixth batch of n and Livelihoods tions nvelope Subcomponent 2B beneficiari es in Khatlon region NSIFT-SERSP-G-2В-07-1 / Pro curement and delivery of fur Component 2: Youth Inclusio Request for Quota Single Stage - One E niture and equipment for the IDA / D5000 Post Open - National 33,000.00 0.00 Completed 2023-10-02 2023-11-27 2023-10-20 2024-05-25 2023-11-23 n and Livelihoods tions nvelope sixth batch of Subcomponent 2B beneficiaries in Khatlon re gion NSIFT-SERSP-G-2В-08 / Proc urement and delivery of equi Component 2: Youth Inclusio Request for Quota Single Stage - One E pment for the seventh batch IDA / D5000 Post Open - National 75,000.00 0.00 Completed 2023-10-02 2023-11-27 2023-10-20 2024-05-25 2023-11-23 n and Livelihoods tions nvelope of Subcomponent 2B benefici aries in Khatlon region NSIFT-SERSP-G-2В-08-1 / Pro curement and delivery of equ Component 2: Youth Inclusio Request for Quota Single Stage - One E ipment for the seventh batch IDA / D5000 Post Open - National 51,000.00 0.00 Completed 2023-10-02 2023-11-27 2023-10-20 2024-05-25 2023-11-15 n and Livelihoods tions nvelope of Subcomponent 2B benefici aries in Khatlon region NSIFT-SERSP-G-2В-09 / Proc urement and delivery of furni Component 2: Youth Inclusio Request for Quota Single Stage - One E ture and equipment for the ei IDA / D5000 Post Open - National 99,000.00 0.00 Completed 2023-11-22 2024-01-17 2023-12-04 2024-07-15 2023-12-20 n and Livelihoods tions nvelope ghth batch of Subcomponent 2B beneficiaries in Khatlon re gion NSIFT-SERSP-G-2В-09-1 / Pro curement and delivery of fur Component 2: Youth Inclusio Request for Quota Single Stage - One E niture and equipment for the IDA / D5000 Post Open - National 69,000.00 0.00 Completed 2023-11-22 2024-01-17 2023-12-04 2024-07-15 2023-12-21 n and Livelihoods tions nvelope eighth batch of Subcompone nt 2B beneficiaries in Khatlon region NSIFT-SERSP-G-2В-10 / Proc urement and delivery of furni Component 2: Youth Inclusio Request for Quota Single Stage - One E ture and equipment for the ni IDA / D5000 Post Open - National 70,500.00 0.00 Completed 2023-11-22 2024-01-17 2023-12-04 2024-07-15 2023-12-21 n and Livelihoods tions nvelope nth batch of Subcomponent 2B beneficiaries in Khatlon re gion NSIFT-SERSP-G-2В-10-1 / Pro curement and delivery of fur Component 2: Youth Inclusio Request for Quota Single Stage - One E niture and equipment for the IDA / D5000 Post Open - National 57,000.00 0.00 Completed 2023-11-22 2024-01-17 2023-12-04 2024-07-15 2024-05-22 n and Livelihoods tions nvelope ninth batch of Subcomponent 2B beneficiaries in Khatlon re gion Page 3 NSIFT-SERSP-G-2В-11 / Proc urement and delivery of equi Component 2: Youth Inclusio Request for Quota Single Stage - One E IDA / D5000 Post Open - National 42,000.00 0.00 Completed 2023-11-22 2024-01-17 2023-12-04 2024-07-15 2023-12-22 pment for the second batch o n and Livelihoods tions nvelope f Subcomponent 2B beneficia ries in GBAO NSIFT-SERSP-G-2В-11-1 / Pro curement and delivery of equ Component 2: Youth Inclusio Request for Quota Single Stage - One E IDA / D5000 Post Open - National 87,000.00 0.00 Completed 2023-11-22 2024-01-17 2023-12-04 2024-07-15 2023-12-26 ipment for the second batch n and Livelihoods tions nvelope of Subcomponent 2B benefici aries in GBAO NSIFT-SERSP-G-2В-12 / Proc urement and delivery of furni Component 2: Youth Inclusio Request for Quota Single Stage - One E ture and equipment for the t IDA / D5000 Post Open - National 76,500.00 0.00 Completed 2023-11-22 2024-01-17 2023-12-04 2024-07-15 2023-12-22 n and Livelihoods tions nvelope hird batch of Subcomponent 2B beneficiaries in GBAO NSIFT-SERSP-G-2В-12-1 / Pro curement and delivery of fur Component 2: Youth Inclusio Request for Quota Single Stage - One E niture and equipment for the IDA / D5000 Post Open - National 64,500.00 0.00 Completed 2023-11-22 2024-01-17 2023-12-04 2024-07-15 2023-12-26 n and Livelihoods tions nvelope third batch of Subcomponent 2B beneficiaries in GBAO NSIFT-SERSP-G-2В-13 / Proc urement and delivery of furni Component 2: Youth Inclusio Request for Quota Single Stage - One E Under Imple ture and equipment for the f IDA / D5000 Post Open - National 61,500.00 0.00 2023-11-22 2024-01-17 2024-07-15 n and Livelihoods tions nvelope mentation ourth batch of Subcomponen t 2B beneficiaries in GBAO NSIFT-SERSP-G-2В-13-1 / Pro curement and delivery of fur Component 2: Youth Inclusio Request for Quota Single Stage - One E niture and equipment for the IDA / D5000 Post Open - National 69,000.00 0.00 Signed 2023-11-22 2024-01-17 2023-12-04 2024-07-15 n and Livelihoods tions nvelope fourth batch of Subcompone nt 2B beneficiaries in GBAO NSIFT-SERSP-G-2В-14 / Proc urement and delivery of furni Component 2: Youth Inclusio Request for Quota Single Stage - One E IDA / D5000 Post Open - National 46,500.00 0.00 Completed 2023-11-22 2024-01-17 2023-12-04 2024-07-15 2024-05-22 ture and equipment for the fi n and Livelihoods tions nvelope fth batch of Subcomponent 2 B beneficiaries in GBAO NSIFT-SERSP-G-2В-14-1 / Pro curement and delivery of fur Component 2: Youth Inclusio Request for Quota Single Stage - One E niture and equipment for the IDA / D5000 Post Open - National 82,500.00 0.00 Signed 2023-11-22 2024-01-17 2023-09-22 2024-07-15 n and Livelihoods tions nvelope fifth batch of Subcomponent 2B beneficiaries in GBAO NSIFT-SERSP-G-2В-15 / Proc urement and delivery of equi Component 2: Youth Inclusio Request for Quota Single Stage - One E IDA / D5000 Post Open - National 82,500.00 0.00 Completed 2024-02-18 2024-04-14 2024-02-29 2024-10-11 2024-03-04 pment for the tenth batch of n and Livelihoods tions nvelope Subcomponent 2B beneficiari es in Khatlon region NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NSIFT-SERSP-CS-3-2 / Procur ement of consulting services of Training and Facilitating P Component 1: Inclusive Loca Quality And Cost- Open - Internationa artner in Gorno-Badakhshan IDA / D5000 Prior 1,253,292.00 1,042,118.00 Signed 2020-06-19 2020-06-24 2020-08-05 2020-08-03 2020-09-18 2020-10-26 2020-10-16 2020-11-19 2020-11-15 2021-04-07 2020-12-20 2021-09-21 2021-01-24 2021-10-19 2022-01-24 l Development Initiatives Based Selection l Autonomous Oblast (GBAO) u nder the framework of the So cio-Economic Resilience Stre ngthening Project NSIFT-SERSP-CS-3-1 / Procur ement of consulting services of Training and Facilitating P Component 1: Inclusive Loca Quality And Cost- Open - Internationa IDA / D5000 Prior 1,333,552.00 1,124,997.00 Signed 2020-06-25 2020-06-24 2020-08-05 2020-08-03 2020-09-18 2020-10-26 2020-10-16 2020-11-19 2020-11-15 2021-04-07 2020-12-20 2021-07-13 2021-01-24 2021-08-16 2022-01-24 artner in Khatlon region unde l Development Initiatives Based Selection l r the framework of the Socio- Economic Resilience Strengt hening Project NSIFT-SERSP-CS-7 / Procure ment of Management Inform Component 3: Project Manag Consultant Qualifi ation System and Village Mo IDA / D5000 ement and Monitoring and E Post Open - National 30,000.00 48,976.30 Signed 2020-07-28 2020-07-28 2020-08-18 2020-07-30 2020-10-01 2020-09-02 2020-10-31 2020-10-23 2020-12-05 2020-11-20 2021-06-03 cation Selection bile Application in the frame valuation work of SERSP and CSP proje cts. NSIFT-SERSP-CS-2 / Procure ment of the consulting servic es for IT application develop Component 1: Inclusive Loca Consultant Qualifi ment for broader beneficiary IDA / D5000 Post Open - National 10,000.00 0.00 Canceled 2020-08-01 2020-08-22 2020-10-05 2020-11-04 2020-12-09 2021-06-07 l Development Initiatives cation Selection feedback mechanism under t he framework of Socio-Econo mic Resilience Strengthening Project NSIFT-SERSP-CS-9 / Market r Component 2: Youth Inclusio Consultant Qualifi IDA / D5000 Prior Open - National 143,846.00 0.00 Canceled 2020-10-26 2020-12-17 2020-11-16 2020-12-30 2021-01-29 2021-03-05 2021-09-01 esearch n and Livelihoods cation Selection NSIFT-SERSP-CS-18-1 / basel Component 3: Project Manag Consultant Qualifi IDA / D5000 Post Open - National 47,000.00 87,778.25 Signed 2020-11-02 2020-11-02 2020-11-07 2020-11-10 2020-12-21 2021-01-12 2021-01-20 2021-02-09 2021-02-24 2021-02-17 2021-08-23 ine research within the CSP a ement and Monitoring and E cation Selection nd SERSP valuation NSIFT-SERSP-CS-5 / Commu Component 3: Project Manag Consultant Qualifi IDA / D5000 Post Open - National 100,000.00 94,587.72 Signed 2020-12-06 2021-01-18 2020-12-27 2021-01-27 2021-02-09 2021-03-12 2021-03-11 2021-04-22 2021-04-15 2021-05-07 2021-10-12 nication services for SERSP ement and Monitoring and E cation Selection valuation NSIFT-SERSP-CS-09 / Market Component 2: Youth Inclusio Consultant Qualifi IDA / D5000 Post Open - National 140,000.00 136,273.98 Signed 2021-01-07 2021-01-11 2021-01-28 2021-01-14 2021-03-13 2021-02-19 2021-04-12 2021-03-26 2021-05-17 2021-04-10 2021-11-13 research n and Livelihoods cation Selection NSIFT-SERSP-CS-1-1 / Procur Component 1: Inclusive Loca Consultant Qualifi ement of consulting services IDA / D5000 Post Open - National 30,000.00 29,208.50 Signed 2021-02-21 2021-02-12 2021-03-14 2021-02-16 2021-04-27 2021-03-05 2021-05-27 2021-03-29 2021-07-01 2021-04-03 2021-12-28 l Development Initiatives cation Selection for Component 1C design de velopment NSIFT-SERSP-CS-4-1 / Imple Component 2: Youth Inclusio Quality And Cost- Open - Internationa IDA / D5000 Prior 2,875,420.00 2,011,750.00 Signed 2021-02-14 2021-02-11 2021-03-07 2021-02-16 2021-04-20 2021-05-06 2021-05-18 2021-06-08 2021-06-17 2021-09-05 2021-07-22 2021-12-13 2021-08-26 2021-12-28 2022-08-26 menting partner for Subcomp n and Livelihoods Based Selection l onent 2a Page 4 NSIFT-SERSP-CS-4-2 / Imple Component 2: Youth Inclusio Quality And Cost- Open - Internationa mentaiton partner for Subco IDA / D5000 Post 1,788,850.00 0.00 Canceled 2021-02-14 2021-03-31 2021-03-07 2021-04-05 2021-04-20 2021-05-18 2021-06-17 2021-07-22 2021-08-26 2022-08-26 n and Livelihoods Based Selection l mponent 2B NSIFT-SERSP-CS-04-2 / Imple Component 2: Youth Inclusio Quality And Cost- Open - Internationa mentation Partner within Sub IDA / D5000 Prior 1,788,850.00 0.00 Canceled 2021-05-28 2021-06-23 2021-06-18 2021-08-01 2022-01-14 2021-08-29 2022-02-25 2021-09-28 2022-06-15 2021-11-02 2021-12-07 2022-12-07 n and Livelihoods Based Selection l component 2B: Youth Livelih oods NSIFT-SERSP-CS-5-1 / Comm Component 3: Project Manag Consultant Qualifi IDA / D5000 Post Open - National 100,000.00 99,285.21 Signed 2021-08-09 2021-08-25 2021-08-30 2021-10-13 2021-08-25 2021-11-12 2021-09-07 2021-12-17 2021-09-27 2022-06-15 unication services for SERSP ement and Monitoring and E cation Selection valuation NSIFT-SERSP-CS-1A-01 / DE D for subproject SERSP-1B-0 3/1 "Repair and reconstrucito Component 1: Inclusive Loca Consultant Qualifi n of unfinished bridge betwe IDA / D5000 Post Open - National 7,500.00 0.00 Signed 2022-05-04 2022-05-11 2022-05-11 2022-05-25 2022-06-02 2022-06-10 2022-06-17 2022-06-15 2022-06-20 2022-09-16 l Development Initiatives cation Selection en Faizobod village and nam ed after Izatullo Sharipov, Da shtigulo jamoat, Mir Said Ali Hamadoni district". NSIFT-SERSP-CS-1A-02 / Geo logical reference of subprojec Component 1: Inclusive Loca Consultant Qualifi IDA / D5000 Post Open - National 17,000.00 0.00 Signed 2022-05-04 2022-05-11 2022-05-11 2022-05-25 2022-06-02 2022-06-10 2022-06-17 2022-06-15 2022-06-20 2022-08-31 t SERSP-1B-01/1, SERSP-1B-0 l Development Initiatives cation Selection 5/1, SERSP-1B-04/1 NSIFT-SERSP-CS-1A-03 / Geo Component 1: Inclusive Loca Consultant Qualifi logical reference of subprojec IDA / D5000 Post Open - National 5,000.00 0.00 Signed 2022-05-04 2022-05-11 2022-05-11 2022-05-25 2022-06-02 2022-06-10 2022-06-17 2022-06-15 2022-06-22 2022-08-31 l Development Initiatives cation Selection t SERSP-1B-02/1 NSIFT-SERSP-CS-1A-04 / DE Component 1: Inclusive Loca Consultant Qualifi D for subprojects SERSP-1A-2 IDA / D5000 Post Open - National 12,000.00 0.00 Signed 2022-05-27 2022-06-02 2022-06-03 2022-06-17 2022-06-24 2022-07-03 2022-07-13 2022-07-08 2022-07-15 2022-10-09 l Development Initiatives cation Selection 1, SERSP-1A-22, SERSP-1A-2 3 NSIFT-SERSP-CS-2B-01 / Sub Component 2: Youth Inclusio Consultant Qualifi component 2B Implementati IDA / D5000 Post Open - National 278,180.00 0.00 Signed 2022-10-05 2022-10-05 2022-10-12 2022-10-09 2022-11-16 2022-11-08 2022-12-15 2022-12-07 2022-12-19 2022-12-09 2024-06-30 n and Livelihoods cation Selection on Partner for Khatlon region NSIFT-SERSP-CS-2B-02 / Sub Component 2: Youth Inclusio Consultant Qualifi component 2B Implementati IDA / D5000 Post Open - National 220,000.00 0.00 Signed 2022-10-05 2022-10-05 2022-10-12 2022-10-09 2022-11-16 2022-11-08 2022-12-15 2022-12-07 2022-12-19 2022-12-09 2024-06-30 n and Livelihoods cation Selection on Partner for GBAO NSIFT-SERSP-CS-1A-05 / DE D for subprojects SERSP-1A-1 27, SERSP-1A-119, geo refer Component 1: Inclusive Loca Consultant Qualifi IDA / D5000 Post Open - National 45,000.00 0.00 Signed 2022-12-08 2022-12-12 2022-12-29 2023-02-11 2022-12-26 2023-03-13 2023-01-10 2023-04-17 2023-01-12 2023-10-14 ence of SERSP-1A-121, SERS l Development Initiatives cation Selection P-1A-122, SERSP-1A-123, SE RSP-1A-130, SERSP-1A-128, SERSP-1A-129 subprojects NSIFT-SERSP-CS-1A-06 / Geo logical reference of subprojec t CSP-2A-05 to SERSP-1A-43, SERSP-1A-44. SERSP-1A-49. Component 1: Inclusive Loca Consultant Qualifi IDA / D5000 Post Open - National 40,000.00 0.00 Signed 2023-02-27 2023-03-02 2023-03-20 2023-05-03 2023-02-01 2023-06-02 2023-02-15 2023-07-07 2023-02-20 2024-01-03 SERSP-1A-58, of SERSP-1A-0 l Development Initiatives cation Selection 1 to SERSP-1A-48, of SERSP- 1A-07 to SERSP-1A-50, of CS P-2B-17 to SERSP-1A-46, of S ERSP-1A-106 to SERSP-1A-45 . NSIFT-SERSP-CS-1A-07 / DE Component 1: Inclusive Loca Consultant Qualifi D for subprojects SERSP-1A-1 IDA / D5000 Post Open - National 19,000.00 0.00 Signed 2023-02-27 2023-03-02 2023-03-20 2023-05-03 2023-03-13 2023-06-02 2023-03-17 2023-07-07 2023-03-18 2024-01-03 l Development Initiatives cation Selection 18, SERSP-1A-118 NSIFT-SERSP-CS-1A-08 / Geo logical reference of subprojec t SERSP-1A-103 to SERSP-1A- Component 1: Inclusive Loca Consultant Qualifi 133, SERSP-1A-131, of SERS IDA / D5000 Post Open - National 24,000.00 0.00 Signed 2023-02-27 2023-03-02 2023-03-20 2023-05-03 2023-03-13 2023-06-02 2023-03-17 2023-07-07 2023-03-18 2024-01-03 l Development Initiatives cation Selection P-1A-105 to SERSP-1A-143, o f SERSP-1A-101 to SERSP-1A- 139, SERSP-1A-142, of SERSP -1A-111 to SERSP-1A-145. NSIFT-SERSP-CS-1A-09 / Geo logical reference of subprojec t СSP-2A-05 to SERSP-1А-82, Component 1: Inclusive Loca Consultant Qualifi IDA / D5000 Post Open - National 20,000.00 0.00 Signed 2023-04-06 2023-07-14 2023-04-27 2023-06-10 2023-04-14 2023-07-10 2023-04-28 2023-08-14 2024-05-01 2024-02-10 SERSP-1А-83, SERSP-1А-85, l Development Initiatives cation Selection SERSP-1А-88, SERSP-1А-94, of SERSP-1А-07 to SERSP-1А- 61. NSIFT-SERSP-CS-1A-10 / Geo logical reference of subprojec Component 1: Inclusive Loca Consultant Qualifi t СSP-2A-05 to SERSP-1А-72, IDA / D5000 Post Open - National 18,500.00 0.00 Signed 2023-04-06 2023-07-14 2023-04-27 2023-06-10 2023-04-14 2023-07-10 2023-04-28 2023-08-14 2023-05-01 2024-02-10 l Development Initiatives cation Selection SERSP-1А-74, SERSP-1А-75, SERSP-1А-76, of SERSP-1А-0 7 to SERSP-1А-71. NSIFT-SERSP-CS-1A-11 / Geo logical reference of subprojec t СSP-2A-05 to SERSP-1А-59, SERSP-1А-79, SERSP-1А-100, Component 1: Inclusive Loca Consultant Qualifi SERSP-1А-228, of SERSP-1А- IDA / D5000 Post Open - National 50,000.00 0.00 Signed 2023-06-12 2023-07-14 2023-07-03 2023-08-16 2023-06-23 2023-09-15 2023-07-12 2023-10-20 2023-07-13 2024-04-17 l Development Initiatives cation Selection 07 to SERSP-1А-70, SERSP-1 А-95, SERSP-1А-204, SERSP- 1А-206, SERSP-1А-209, of S ERSP-1А-01 to SERSP-1А-68, SERSP-1А-78. NSIFT-SERSP-CS-5-2 / Comm Component 3: Project Manag Consultant Qualifi IDA / D5000 Post Open - National 125,000.00 0.00 Signed 2023-06-12 2023-06-20 2023-07-03 2023-06-24 2023-08-16 2023-07-14 2023-09-15 2023-07-31 2023-10-20 2023-08-01 2024-04-17 unication services for SERSP ement and Monitoring and E cation Selection (2) valuation NSIFT-SERSP-CS-1A-12 / DE D for subproject SERSP-1A-2 Component 1: Inclusive Loca Consultant Qualifi 22 "“Construction of a pedes IDA / D5000 Post Open - National 8,000.00 0.00 Signed 2023-10-23 2024-03-05 2023-11-13 2023-12-27 2023-10-24 2024-01-26 2023-11-03 2024-03-01 2023-11-08 2024-08-28 l Development Initiatives cation Selection trian bridge in the village of Kodara 1, Panjrud jamoat, Ha madoni district” INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NSIFT-SERSP-CS-8 / Develop Component 3: Project Manag ment of module of automate IDA / D5000 ement and Monitoring and E Post Direct Selection Direct 5,000.00 0.00 Canceled 2020-10-19 2020-09-10 2020-10-29 2021-01-02 2021-07-01 d FM system valuation Page 5 NSIFT-SERSP-CS-3-1-DS-1 / A dditional TFP for Khatlon (NSI Component 1: Inclusive Loca IDA / D5000 Post Direct Selection Direct - National 200,000.00 0.00 Canceled 2023-04-14 2023-04-24 2023-06-28 2026-12-31 FT-SERSP-CS-3-1) services in l Development Initiatives accordance with additional fi nancing. NSIFT-SERSP-CS-3-2-DS-1 / A dditional TFP for GBAO (NSIF Component 1: Inclusive Loca IDA / D5000 Post Direct Selection Direct - National 200,000.00 0.00 Canceled 2023-04-14 2023-04-24 2023-06-28 2026-12-31 T-SERSP-CS-3-2) services in a l Development Initiatives ccordance with additional fin ancing. Page 6