PROCUREMENT PLAN Dar es Salaam Metropolitan Development Project - Phase 2 I. General Project Information 1. Country: Tanzania 2. Project Name: Dar es Salaam Metropolitan Development Project 3. Project ID: P180298 4. Project Implementation Agency: Presidents Office – Regional Administration and Local Government and and Participating Dar es Salaam Local Government Authorities (DLAs) 5. Date of the Procurement Plan: November 17, 2023 6. Period Covered by this procurement plan: First 18 Months I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Fifth Edition, September 2023) (“Procurement Regulations”) the Bank’ Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitutes the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement Act, 2011, The Public Procurement (Amendment) Act, 2016 and the Regulations, 2016, such arrangements shall be subject to complying in full with paragraphs 5.3 and 5.4 of the Procurement Regulations and the following conditions: o There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignment. o There should be no exclusive preference based on threshold prescribed in PPA and its Regulations. o Negotiations with the lowest evaluated bidder to reduce price in the case of goods, works and non-consulting services where competitive methods have been used shall not be allowed. o The fixed budget method shall not be used for goods, works and non- consulting services. o Established and approved procurement standards by the government may be used, provided that they are not restrictive. 1 When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification: Not Applicable V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not Applicable Domestic preference is not applicable for National Open Competitive Procurement VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is: Not Applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Prior Review, Procurement Approaches and Methods A. Goods, Works, and Non-Consulting Services Category Prior Review Procurement Approaches and Methods (US$ (US$ million) million) Open Open National Request for International Quotation (RfQ) Works ≥ 10 ≥ 20 < 20 ≤ 0.2 Goods, IT, and ≥2 non-consulting ≥5 <5 ≤ 0.1 services B. Consulting Services Category Prior Review Short List of National Consultants (US$ million) (US$ million) Consulting Services Engineering and Construction Supervision Consultants ≥1 ≤ 0.3 ≤ 0.3 (Firms) Individual ≥ 0.3 n.a. n.a. consultants Notes: Terms of Reference: Terms of Reference for all contracts shall be cleared by the Bank, regardless of whether the assignment is for prior or post review. 2 Advertisement: Consultancy Service for Contracts estimated to cost US$ 300,000 equivalent and above per contract shall be advertised in UNDB online in addition to advertising in National Newspaper(s) of wide circulation and/or Regional Newspaper(s). Beneficial Ownership Disclosure shall apply to all open or limited international competition. 3 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti- Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non- responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed 6Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 4 contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub- agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. 7For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 8A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 9Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 5 We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 6 PROCUREMENT Tanzania : DAR ES SALAAM METROPOLITAN DEVELOPMENT PROJECT PHASE 2 PLAN General Information Country: Tanzania 2024-03-15 Bank’s Approval Date of the Original Procurement Plan: 2025-01-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P180298 GPN Date: 2024-03-06 Project Name: DAR ES SALAAM METROPOLITAN DEVELOPMENT PROJECT PHASE 2 Loan / Credit No: IDA / 74780 President's Office - Regional Administration and Local Government Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-PO-RALG-420899-CW-RF Request for B B / Kinondoni Package 1: Upg ids - Small W Single Stage - One E Under Imple 2025-11-3 rading of Nakalekwa - Bwawa IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-04-15 2024-04-15 2024-04-20 2024-04-15 2024-06-09 2024-07-21 2024-08-30 nvelope mentation 0 ni, Mahakamani and Umoja R nvelope proc oads in Kinondoni Municipalit ess) y under the DMDP 2 Project TZ-PO-RALG-420900-CW-RF Request for B B / Kinondoni Package 2: Upg ids - Small W rading of Tegeta - Silver, Miv Single Stage - One E Under Imple 2025-11-3 IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-04-15 2024-04-15 2024-04-20 2024-04-15 2024-06-09 2024-05-31 2024-07-21 2024-09-04 2024-08-30 umoni, Binti Matola, Amiri Le nvelope mentation 0 nvelope proc ni 3 (DAWASA) and Togo Roa ess) ds in Kinondoni Municipality under the DMDP 2 Project Request for B TZ-PO-RALG-420901-CW-RF ids - Small W B / Ubungo Package 1: Upgra Single Stage - One E Under Imple 2025-11-3 IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-04-15 2024-04-15 2024-04-20 2024-04-15 2024-06-09 2024-05-31 2024-07-21 2024-09-04 2024-08-30 ding of Msumi Road in Ubung nvelope mentation 0 nvelope proc o Municipality under the DM ess) DP 2 Project TZ-PO-RALG-420902-CW-RF B / Ubungo Package 3: Upgra Request for B ding of Posta Matembe, Shei ids - Small W Single Stage - One E Under Imple 2025-11-3 kh Bofu, Msikitini, Sinza KKKT IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-04-15 2024-04-15 2024-04-20 2024-04-15 2024-06-09 2024-05-31 2024-07-21 2024-09-04 2024-08-30 nvelope mentation 0 , Segesera, Juma Ikangaa an nvelope proc d Ubungo NHC Roads in Ubu ess) ngo Municipality under the D MDP 2 Project TZ-PO-RALG-420903-CW-RF Request for B B / Dar es Salaam CC Packag ids - Small W Single Stage - One E Under Imple 2025-11-3 e 1: Upgrading of Kitunda – K IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-04-15 2024-04-15 2024-04-20 2024-04-15 2024-06-09 2024-05-31 2024-07-21 2024-09-30 2024-08-30 nvelope mentation 0 ivule – Msongola Road and K nvelope proc ivule – Majohe Junction Road ess) in Dar es Salaam City TZ-PO-RALG-420904-CW-RF B / Dar CC Package 2: Upgra ding of Kiwalani Community Request for B Roads (Park 1 - Roads 1 & 2, ids - Small W Single Stage - One E Under Imple 2025-11-3 Park 2 - Roads 1–4, Kigilagila IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-04-15 2024-04-15 2024-04-20 2024-04-15 2024-06-09 2024-07-21 2024-08-30 nvelope mentation 0 Market - Roads 1-3 and Bom nvelope proc bom Market Road), Banana – ess) Kitunda Road and Migombani Road in Dar es Salaam City u nder the DMDP 2 Project TZ-PO-RALG-420905-CW-RF Request for B B / Temeke Package 1: Upgra ids - Small W ding of Mbagala Roads (Ndun Single Stage - One E Under Imple 2025-11-3 IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-04-15 2024-04-15 2024-04-20 2024-04-15 2024-06-09 2024-05-31 2024-07-21 2024-09-04 2024-08-30 guru, Masaki, Maandazi and nvelope mentation 0 nvelope proc Kipati Roads) in Temeke Mun ess) icipality under the DMDP 2 Pr oject TZ-PO-RALG-420906-CW-RF B / Temeke Package 3: Upgra ding of Yombo Vituka Roads ( Request for B Msikitini, Mwembeni & Malaw ids - Small W Single Stage - One E Under Imple 2025-11-3 i West), Keko Taifa Roads (So IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-04-15 2024-04-15 2024-04-20 2024-04-15 2024-06-09 2024-05-31 2024-07-21 2024-09-04 2024-08-30 nvelope mentation 0 ngambele, Mwakalinga, Mark nvelope proc as, Majimaji, Magorofani, Igo ess) me, Diwani, Keko Machungw a & Basri) and Footbridges (C haurembo 1 & 2) in Temeke Municipality TZ-PO-RALG-420907-CW-RF B / Kigamboni Package 1: Up Request for B grading of Full Shangwe, Gofi ids - Small W Single Stage - One E Under Imple 2025-11-3 ngo - Shangwe, Kibada – Plot, IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-04-15 2024-04-15 2024-04-20 2024-04-15 2024-06-09 2024-05-31 2024-07-21 2024-09-04 2024-08-30 nvelope mentation 0 Lingia – Nyakwale & Mzimbini nvelope proc P/S Roads in Kigamboni Muni ess) cipality under the DMDP 2 Pr oject TZ-PO-RALG-420908-CW-RF B / Kigamboni Package 3: Up Request for B grading of Dege Mbutu, Atani ids - Small W Single Stage - One E Under Imple 2025-11-3 Dege, Machava Njama, Mtaa IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-04-15 2024-04-15 2024-04-20 2024-04-15 2024-06-09 2024-05-31 2024-07-21 2024-09-04 2024-08-30 nvelope mentation 0 wa Maji – Posta, Orassa, Mze nvelope proc e Msomi & Polisi Pikorii Road ess) s in Kigamboni Municipality u nder the DMDP 2 Project TZ-PO-RALG-436234-CW-RF Request for B B / Ubungo Package 2: Upgra ids - Small W Single Stage - One E Under Imple 2026-02-2 ding of Goba Wakorea and H IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-07-10 2024-06-28 2024-07-15 2024-06-28 2024-09-02 2024-10-15 2024-11-30 nvelope mentation 8 ondogo Shija Roads in Ubung nvelope proc o Municipality under the DM ess) DP 2 Project TZ-PO-RALG-436235-CW-RF B / Ubungo Package 4: Upgra Request for B ding of Tip Top, Midizini, Binti ids - Small W Single Stage - One E Under Imple 2026-02-2 Kayenga, Namnani, Mikindan IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-07-10 2024-06-28 2024-07-15 2024-06-28 2024-09-02 2024-10-15 2024-11-30 nvelope mentation 8 i, Chimwaga, Mbegani, Shule nvelope proc and Lion Roads in Ubungo M ess) unicipality under the DMDP 2 Project TZ-PO-RALG-436236-CW-RF B / Dar es Salaam CC Packag Request for B e 3: Upgrading of Tabata Roa ids - Small W ds (Barakuda - Changombe – Single Stage - One E Under Imple 2026-02-2 IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-07-10 2024-06-28 2024-07-15 2024-06-28 2024-09-02 2024-10-15 2024-11-30 Majichumvi, Majumba Sita – nvelope mentation 8 nvelope proc Segerea and Tabata Mawenzi ess) – Kisiwani Roads) in Dar es S alaam City under the DMDP 2 Project Page 1 TZ-PO-RALG-436237-CW-RF Request for B B / Dar es Salaam CC Packag ids - Small W Single Stage - One E Under Imple 2026-02-2 e 4: Rehabilitation of Upanga IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-07-10 2024-06-28 2024-07-15 2024-06-28 2024-09-02 2024-10-15 2024-11-30 nvelope mentation 8 CBD Roads in Dar es Salaam nvelope proc City under the DMDP 2 Projec ess) t TZ-PO-RALG-436238-CW-RF Request for B B / Dar es Salaam CC Packag ids - Small W Single Stage - One E Under Imple 2026-02-2 e 5: Rehabilitation of Ilala CB IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-07-10 2024-06-28 2024-07-15 2024-06-28 2024-09-02 2024-10-15 2024-11-30 nvelope mentation 8 D Roads in Dar es Salaam Cit nvelope proc y under the DMDP 2 Project ess) TZ-PO-RALG-436239-CW-RF Request for B B / Temeke Package 2: Upgra ids - Small W Single Stage - One E Under Imple 2026-02-2 ding of Masuliza and Kilimah IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-07-10 2024-06-28 2024-07-15 2024-06-28 2024-09-02 2024-10-15 2024-11-30 nvelope mentation 8 ewa - Tuangoma Roads in Te nvelope proc meke Municipality under the ess) DMDP 2 Project TZ-PO-RALG-436240-CW-RF B / Temeke Package 4: Upgra ding of Kurasini Roads (Konis Request for B aga 1, Konisaga 3, Kurasini, T ids - Small W Single Stage - One E Under Imple 2026-02-2 aningra & Uhasibu), Temeke IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-07-10 2024-06-28 2024-07-15 2024-06-28 2024-09-02 2024-10-15 2024-11-30 nvelope mentation 8 Roads (Temeke, Lushoto, Pe nvelope proc ndamoyo, Pendamoyo 1, Ma ess) ndera & Mkumba Miburani) a nd Footbridges in Temeke M unicipality under DMDP 2 Pro ject TZ-PO-RALG-436241-CW-RF Request for B B / Kigamboni Package 2: Up ids - Small W grading of Geza Ulole/Mivum Single Stage - One E Under Imple 2026-02-2 IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-07-10 2024-06-28 2024-07-15 2024-06-28 2024-09-02 2024-10-15 2024-11-30 oni, Geza Juu – Eddah Avenu nvelope mentation 8 nvelope proc e & Mwongozo P/S Roads in K ess) igamboni Municipality under the DMDP 2 Project TZ-PO-RALG-436242-CW-RF B / Kigamboni Package 4: Up Request for B grading of Upendo Vijibweni ids - Small W Single Stage - One E Under Imple 2026-02-2 Centre, Daraja la Meya – Vijib IDA / 74780 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-07-10 2024-06-28 2024-07-15 2024-06-28 2024-09-02 2024-10-15 2024-11-30 nvelope mentation 8 weni Hospital, Kibugumo Dar nvelope proc ajani & Mloka/Wakorea Road ess) s in Kigamboni Municipality u nder the DMDP 2 Project National Proc TZ-PO-RALG-460397-CW-DIR urement Doc / Emergency Interventions al ument - 1 En Under Imple 2025-07-1 ong Monduli - Lendikinya - Mt IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-06 2024-12-02 2024-12-16 2024-12-23 2025-01-17 velope proce mentation 6 i Mmoja Road (23 km) in Mon ss (Non Bank duli DC- Arusha Region -SPD) National Proc TZ-PO-RALG-460417-CW-DIR urement Doc / Emergency Interventions al ument - 2 En Under Imple 2025-07-1 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-06 2024-12-02 2024-12-16 2024-12-23 2025-01-17 ong Zajilwa-Izava road (28.4 velope proce mentation 6 km) in Chamwino DC - Dodo ss (Non Bank ma -SPD) National Proc TZ-PO-RALG-460375-CW-DIR urement Doc / Emergency Interventions al ument - 1 En Under Imple 2025-07-1 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-06 2024-12-02 2024-12-16 2024-12-23 2025-01-17 ong Kidabaga - Boma la Ng'o velope proce mentation 6 mbe road (18.3 km) in Kilolo ss (Non Bank DC - Iringa -SPD) National Proc TZ-PO-RALG-460343-CW-DIR urement Doc / Emergency Interventions al ument - 1 En Under Imple 2025-07-1 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-06 2024-12-02 2024-12-16 2024-12-23 2025-01-17 ong Kasanga - Ihomasa - Mag velope proce mentation 6 unguli road (16.6 km) in Mufi ss (Non Bank ndi DC - Iringa -SPD) National Proc TZ-PO-RALG-460377-CW-DIR urement Doc / Emergency Interventions al ument - 1 En Under Imple 2025-08-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-06 2024-12-02 2024-12-16 2024-12-23 2025-01-17 ong Sawala - Mkonge - Iyege velope proce mentation 5 ya- lulanda road (41 km) in M ss (Non Bank ufindi DC - Iringa -SPD) National Proc TZ-PO-RALG-460279-CW-DIR urement Doc / Emergency Interventions al ument - 1 En Under Imple 2025-07-0 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-06 2024-12-02 2024-12-16 2024-12-23 2025-01-07 ong Shore road (0.972 km) in velope proce mentation 6 Bukoba MC - Kagera ss (Non Bank -SPD) National Proc TZ-PO-RALG-460323-CW-DIR urement Doc / Emergency Interventions al ument - 1 En Under Imple 2025-07-1 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-06 2024-12-02 2024-12-16 2024-12-23 2025-01-17 ong Engusero - Ngipa - Orkin velope proce mentation 6 e road (19.8 km) in Kiteto D ss (Non Bank C - Manyara -SPD) National Proc TZ-PO-RALG-460329-CW-DIR urement Doc / Emergency Interventions al ument - 1 En Under Imple 2025-07-1 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-06 2024-12-02 2024-12-16 2024-12-23 2025-01-17 ong Dosidosi - Chapakazi ro velope proce mentation 6 ad (18.45 km) in Kiteto DC - ss (Non Bank Manyara -SPD) National Proc TZ-PO-RALG-460393-CW-DIR urement Doc / Emergency Interventions al ument - 1 En Under Imple 2025-07-1 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-06 2024-12-02 2024-12-16 2024-12-23 2025-01-17 ong Kwitete Mosongo Wafet velope proce mentation 6 e road (25 km) in Serengeti ss (Non Bank DC - Mara -SPD) National Proc TZ-PO-RALG-460328-CW-DIR urement Doc / Emergency Interventions al ument - 1 En Under Imple 2025-07-1 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-06 2024-12-02 2024-12-16 2025-01-17 ong Lugala - Biro road (8.1 k velope proce mentation 6 m) in Malinyi DC - Morogoro ss (Non Bank -SPD) National Proc TZ-PO-RALG-467141-CW-DIR urement Doc / Construction of Side Drains ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Along Sokoine - Muriet – Meid velope proce lementation 8 imu in Arusha CC - Arusha R ss (Non Bank egion -SPD) TZ-PO-RALG-467262-CW-DIR National Proc / Emergency Interventions al urement Doc ong Sokoine Road (2.22km), ument - 1 En Pending Imp 2025-09-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Nyerere Road (1.07km), Col velope proce lementation 6 middleton Road (0.93km) an ss (Non Bank d Simeoni Road (1.38km) In -SPD) Arusha CC - Arusha Region TZ-PO-RALG-467226-CW-DIR National Proc / Construction of Stone Maso urement Doc nry Single Lane Bridge, Five ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Cell Stone Masonry Arch Brid velope proce lementation 8 ge and Side Drainage Along ss (Non Bank Mti Mmoja - Enjoro Road (2.9 -SPD) Km) In Arusha DC- Arusha Re gion Page 2 National Proc TZ-PO-RALG-467223-CW-DIR urement Doc / Construction of Masonry Bri ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 dge Along Manyara - Lositete velope proce lementation 8 Road (37.7 Km) In Karatu DC- ss (Non Bank Arusha Region -SPD) National Proc TZ-PO-RALG-467159-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Along Sale- Malambo Road (3 velope proce lementation 8 2.25km) In Ngorongoro DC- A ss (Non Bank rusha Region -SPD) National Proc TZ-PO-RALG-467040-CW-DIR urement Doc / Construction of Solid Drifts ument - 1 En Pending Imp 2025-07-2 and Access Structure Along N IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 amanga - Sinya Jct Road (34. ss (Non Bank 5 Km) in Longido DC- Arusha -SPD) Region National Proc TZ-PO-RALG-467235-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Along Mayamaya - Mkondai R velope proce lementation 8 oad (16 Km) In Bahi DC - Dod ss (Non Bank oma -SPD) National Proc TZ-PO-RALG-467260-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Along Nghambala - Chigongw velope proce lementation 8 e Road (5.28 Km) In Dodoma ss (Non Bank CC - Dodoma -SPD) National Proc TZ-PO-RALG-467038-CW-DIR urement Doc / Construction Of Masonry Ar ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2024-12-30 2025-01-22 ch Bridge Along Mpera - Jeshi velope proce lementation 1 ni Road (0.9 Km) In Chamwin ss (Non Bank o DC - Dodoma -SPD) National Proc TZ-PO-RALG-467132-CW-DIR urement Doc / Construction of Masonry Arc ument - 1 En Pending Imp 2025-07-3 h Bridge Along Ovada – Baab IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2024-12-28 2025-02-01 velope proce lementation 1 a - Jogolo Road (36.4 Km) In ss (Non Bank Chemba DC - Dodoma -SPD) National Proc TZ-PO-RALG-467258-CW-DIR urement Doc / Spot Improvement Works al ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 ong Mnenia – Itololo – Disa – velope proce lementation 8 Kisese 36.4 Km Road in Kond ss (Non Bank oa DC- Dodoma -SPD) National Proc TZ-PO-RALG-467130-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 s along Kamhanga- Igaka-Ibi velope proce lementation 8 sabageni in Geita DC - Geita ss (Non Bank Region -SPD) National Proc TZ-PO-RALG-467261-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 s and Access Structures alon IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 g Kasamwa - Mkoba Bridge- L ss (Non Bank ubanga Road (13.1 Km) In Ge -SPD) ita DC - Geita National Proc TZ-PO-RALG-467254-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Along Bugalama - Nyakaduha velope proce lementation 8 Road (17.2 Km) in Geita DC - ss (Non Bank Geita -SPD) National Proc TZ-PO-RALG-467148-CW-DIR urement Doc / Construction Of Box Culvert ument - 1 En Pending Imp 2025-07-2 s Along Wavu- Lwamizo Road IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 (3.35 Km) And Buyagu - Nyar ss (Non Bank ugusu Road (14.5 Km) In Geit -SPD) a DC - Geita National Proc TZ-PO-RALG-467128-CW-DIR urement Doc / Spot Improvement Along Ho ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 spitali ya Rufaa Road (0.2 Km velope proce lementation 8 ) In Chato DC - Geita ss (Non Bank -SPD) National Proc TZ-PO-RALG-467155-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Along Kasamwa-Gamashi-Bu velope proce lementation 8 solwa Road (18.7 Km) In Geit ss (Non Bank a TC- Geita -SPD) TZ-PO-RALG-467253-CW-DIR National Proc / Construction of Storm Drain urement Doc s in Katoro Town and Spot Im ument - 1 En Pending Imp 2025-07-2 provement Along CCM - Kadu IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 da, Sheli Ya Nasoro - Hospital ss (Non Bank , Stendi - Kilimahewa, Mtund -SPD) uni No. 7 Roads (8 Km) In Gei ta DC - Geita National Proc TZ-PO-RALG-467047-CW-DIR urement Doc / Constructions of Box Culver ument - 1 En Pending Imp 2025-07-2 t Along Mzambarauni – Budo IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 da - Kanegere Prison Road (2 ss (Non Bank 2.06 Km) In Mbogwe DC - Gei -SPD) ta National Proc TZ-PO-RALG-467240-CW-DIR urement Doc / Construction of Stone Pitchi ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 ng Along Nyakafuru Town Ro velope proce lementation 8 ad No. 73 Road (1.58 Km) in ss (Non Bank Mbogwe DC - Geita -SPD) National Proc TZ-PO-RALG-467252-CW-DIR urement Doc / Construction of Stone Pitchi ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 ng Along Masumbwe Town R velope proce lementation 8 oad No. 39 Road (1.04 Km) in ss (Non Bank Mbogwe DC - Geita -SPD) National Proc TZ-PO-RALG-467239-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Along Bomangombe - Kikavu velope proce lementation 8 chini Road (24.18 Km) in Hai ss (Non Bank DC - Kilimanjaro -SPD) National Proc TZ-PO-RALG-467242-CW-DIR urement Doc / Spot Improvement Works Al ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 ong Mwenge road (2.23 Km) I velope proce lementation 8 n Moshi Mc- Kilimanjaro ss (Non Bank -SPD) National Proc TZ-PO-RALG-467241-CW-DIR urement Doc / Extension of Reha Bridge Al ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 ong Mungushi - Sikirari Road velope proce lementation 8 (1.37 Km) in Siha DC - Kilima ss (Non Bank njaro -SPD) Page 3 National Proc TZ-PO-RALG-467127-CW-DIR urement Doc / Construction of Storm Wate ument - 1 En Pending Imp 2025-07-1 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2024-12-24 2025-01-16 r Drains Along Mwanga Road velope proce lementation 5 s (5.65 Km) In Mwanga DC - ss (Non Bank Kilimanjaro -SPD) National Proc TZ-PO-RALG-467229-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Along Mogabiri - Nyarwana R velope proce lementation 8 oad (6.5 Km) In Tarime TC - ss (Non Bank Mara -SPD) National Proc TZ-PO-RALG-467126-CW-DIR urement Doc / Construction Masonry Arc B ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 ridge Along Matongo-Nyarwa velope proce lementation 8 na Road (2.6 Km) In Tarime ss (Non Bank DC - Mara -SPD) National Proc TZ-PO-RALG-467037-CW-DIR urement Doc / Construction Masonry Arc B ument - 1 En Pending Imp 2025-07-1 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2024-12-30 2025-01-15 ridge Along Kumbini - Ahero velope proce lementation 4 Road (7.8km) Rorya DC - Mar ss (Non Bank a -SPD) National Proc TZ-PO-RALG-467233-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 and Rigid Pavement Along N IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 amdimba - Chiwata Road (2 ss (Non Bank Km) Newala DC - Mtwara -SPD) National Proc TZ-PO-RALG-467150-CW-DIR urement Doc / Construction of Rigid Pavem ument - 1 En Pending Imp 2025-09-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 ent along Kiduni-Mkunya-Chi velope proce lementation 6 hanga Road (15.5 Km) Newal ss (Non Bank a TC - Mtwara -SPD) National Proc TZ-PO-RALG-467224-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 s Along Tandahimba - Mivang velope proce lementation 8 a Road (8.7 Km) Tandahimba ss (Non Bank DC - Mtwara -SPD) National Proc TZ-PO-RALG-467222-CW-DIR urement Doc / Spot Improvement Works Al ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 ong Mahuta - Lipalwe Road ( velope proce lementation 8 10.45 Km) Tandahimba DC - ss (Non Bank Mtwara -SPD) National Proc TZ-PO-RALG-467225-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 Along Malamba - Kwanyama IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 - Mchichira Road (13.6 Km) T ss (Non Bank andahimba DC - Mtwara -SPD) National Proc TZ-PO-RALG-467221-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Along Ghalani - Malopokelo P velope proce lementation 8 /S Road (0.95 Km) Tandahim ss (Non Bank ba DC - Mtwara -SPD) National Proc TZ-PO-RALG-467039-CW-DIR urement Doc / Construction Of Masonry Ar ument - 1 En Pending Imp 2025-07-2 c Bridge Along Bilulumo-Luho IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2024-12-30 2025-01-22 velope proce lementation 1 rongoma-Kafunzo Road (4.93 ss (Non Bank Km) In Buchosa DC - Mwanza -SPD) National Proc TZ-PO-RALG-467218-CW-DIR urement Doc / Construction of Uhuru Bridg ument - 1 En Pending Imp 2025-07-2 e (1.72 Km) and Mlango Mmo IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 ja Dranage System (0.16km) ss (Non Bank In Nyamagana Mc - Mwanza -SPD) National Proc TZ-PO-RALG-467152-CW-DIR urement Doc / Construction of Side Drains ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Along Rufiji Road (1.28 Km) I velope proce lementation 8 n Nyamagana MC - Mwanza ss (Non Bank -SPD) National Proc TZ-PO-RALG-467139-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 and Side Drains Along Kishiri IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 - Fumagila Road (7.4 Km) in ss (Non Bank Nyamagana MC - Mwanza -SPD) National Proc TZ-PO-RALG-467230-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Along Magu Ginery - Busulwa velope proce lementation 8 Road (7.8 Km) In Magu DC - ss (Non Bank Mwanza -SPD) National Proc TZ-PO-RALG-467227-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Along Sagani - Mwatelesha R velope proce lementation 8 oad (7.8 Km) In Magu DC - M ss (Non Bank wanza -SPD) TZ-PO-RALG-467245-CW-DIR National Proc / Construction of Box Culvert urement Doc and raise embankment for a ument - 1 En Pending Imp 2025-07-2 pproach at ch 3+100 and co IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 nstruction of relief culvert at ss (Non Bank Ch 6+000 along Vigwaza -Bu -SPD) yuni road (9.24 km) in Chalin ze DC - Pwani National Proc TZ-PO-RALG-467048-CW-DIR urement Doc / Construction of Ruiche Brid ument - 1 En Pending Imp 2025-09-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 ge along Kigogwe - Murungu velope proce lementation 6 road (10.5 km) in Buhigwe D ss (Non Bank C - Kigoma -SPD) National Proc TZ-PO-RALG-467216-CW-DIR urement Doc / Bridge Protection works and ument - 1 En Pending Imp 2025-07-2 Construction of lined ditch al IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 ong Luvulunge - Unyangogo - ss (Non Bank Mwakavuta road (22.4 km) in -SPD) Makete DC - Njombe TZ-PO-RALG-467232-CW-DIR National Proc / Construction of Box Culvert, urement Doc Storm water side drains and ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Concrete Strips along Kasaga velope proce lementation 8 la - Image road (5.5 km) in ss (Non Bank Wanging'ombe DC - Njombe -SPD) Page 4 National Proc TRR-REF-45 / Construction of urement Doc Box Culvert, Storm water sid ument - 1 En Pending Imp 2025-07-2 e drains and Concrete Strips IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 along Malangali - Wangama r ss (Non Bank oad (15.4 km) in Wanging'o -SPD) mbe DC - Njombe TZ-PO-RALG-467231-CW-DIR National Proc / Construction of Box Culvert, urement Doc Storm water side drains and ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Concrete Strips along Wangi velope proce lementation 8 ng'ombe - Wangutwa road (7 ss (Non Bank .85 km) in Wanging'ombe DC -SPD) - Njombe TZ-PO-RALG-467138-CW-DIR National Proc / Construction of Box Culvert, urement Doc Storm water side drains and ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Concrete Strips along Mapog velope proce lementation 8 olo - Ipwani road (8.98 km) in ss (Non Bank Wanging'ombe DC - Njombe -SPD) National Proc TZ-PO-RALG-467249-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 along Kwala -Mperamumbi ro velope proce lementation 8 ad (10.82 km) in Kibaha DC - ss (Non Bank Pwani -SPD) National Proc TZ-PO-RALG-467246-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 along Kilangalanga -Mwanabi velope proce lementation 8 to road (10.71 km) in Kibaha ss (Non Bank DC - Pwani -SPD) National Proc TZ-PO-RALG-467247-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 along Mzenga-Gwata road (4 velope proce lementation 8 2 km) in Kisarawe DC - Pwani ss (Non Bank -SPD) National Proc TZ-PO-RALG-467051-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 along Kisarawe - Kwembe ro velope proce lementation 8 ad (4.8 km) in Kisarawe DC - ss (Non Bank Pwani -SPD) National Proc TZ-PO-RALG-467257-CW-DIR urement Doc / Spot Improvement works al ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 ong Chole - Kihare road (25.2 velope proce lementation 8 km) in Kisarawe DC - Pwani ss (Non Bank -SPD) National Proc TZ-PO-RALG-467243-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 and rise of embarkment alon IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 g Sotele - Nasibugani - Mavu ss (Non Bank nja road (18.4 km) in Mkuran -SPD) ga DC - Pwani National Proc TZ-PO-RALG-467236-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 along Pachani – Luwawasi se IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 velope proce lementation 8 c – Ruhuwiko road (3.12 km) ss (Non Bank in Songea DC - Ruvuma -SPD) National Proc TZ-PO-RALG-467220-CW-DIR urement Doc / Construction of Slab culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 along Mbinga-Liparamba roa velope proce lementation 8 d (41.87 km) in Mbinga DC - ss (Non Bank Ruvuma -SPD) National Proc TZ-PO-RALG-467050-CW-DIR urement Doc / Construction of Slab along K ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 itanda-Lupilo road (15.4 km) velope proce lementation 8 in Mbinga DC - Ruvuma ss (Non Bank -SPD) National Proc TZ-PO-RALG-467215-CW-DIR urement Doc / Construction of Muungano ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 Bridge along Minazini-Ukomb velope proce lementation 8 ozi road (10.1 km) in Namtu ss (Non Bank mbo DC - Ruvuma -SPD) National Proc TZ-PO-RALG-467125-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 along Kiomboi-Tutu-Kisana ro velope proce lementation 8 ad (13.51 km) in Iramba DC- ss (Non Bank Singida -SPD) National Proc TZ-PO-RALG-467043-CW-DIR urement Doc / Construction Box Culvert al ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 ong Urughu -Kisonga road (1 velope proce lementation 8 7.19 km) in Iramba DC- Singi ss (Non Bank da -SPD) National Proc TRR-REF-62 / Construction of urement Doc Box Culvert along Mtinko-Ma ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 kuro-Diagwa road (19.85 km) velope proce lementation 8 in Singida DC - Singida ss (Non Bank -SPD) National Proc TZ-PO-RALG-467219-CW-DIR urement Doc / Construction of Box Culvert ument - 1 En Pending Imp 2025-07-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 along Ikenga road (9.427 km velope proce lementation 8 ) in Singida MC- Singida ss (Non Bank -SPD) National Proc TZ-PO-RALG-467234-CW-DIR urement Doc / Construction of Fulua Bridg ument - 1 En Pending Imp 2025-09-2 IDA / 74780 Post Direct Selection Direct - National 0.00 2024-12-23 2025-01-06 2025-01-29 e along Lugala - Biro road (8. velope proce lementation 6 1Km) in Malinyi DC in Morogo ss (Non Bank ro -SPD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-PO-RALG-464671-GO-DIR / Supply of Mabey Bridges for Emergency Interventions at L uhombero Bridge (61.542 m) Direct - Internation Pending Impl in Ulanga DC, Mbasa Bridge ( IDA / 74780 Prior Direct Selection 0.00 2024-12-23 2025-01-06 2025-03-02 2025-08-29 al ementation 42.672m) in Kilombero DC, M basa Bridge (42.672m) in Mli mba DC , Ng’uni bridge (30.4 8m) in Ruangwa DC, Msanga Bridge (39.624m) in Busokel oD Page 5 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-PO-RALG-414782-CS-QCB S / Construction Supervision Consultancy Services for Urb Quality And Cost- Open - Internationa Under Implement IDA / 74780 Prior 0.00 2024-03-15 2024-03-21 2024-04-05 2024-03-28 2024-05-19 2024-07-23 2024-06-30 2024-09-04 2024-07-30 2024-12-01 2024-09-03 2024-10-08 2027-10-08 an Infrastructure Developme Based Selection l ation nt in Kinondoni and Ubungo Municipalities under the DMD P 2 Project TZ-PO-RALG-414802-CS-QCB S / Construction Supervision Quality And Cost- Open - Internationa Under Implement Consultancy Services for Urb IDA / 74780 Prior 0.00 2024-03-15 2024-03-26 2024-04-05 2024-03-28 2024-05-19 2024-07-23 2024-06-30 2024-09-04 2024-07-30 2024-12-01 2024-09-03 2024-10-08 2027-10-08 Based Selection l ation an Infrastructure Developme nt in Dar es Salaam City und er the DMDP 2 Project TZ-PO-RALG-414804-CS-QCB S / Construction Supervision Consultancy Services for Urb Quality And Cost- Open - Internationa Under Implement IDA / 74780 Prior 0.00 2024-03-15 2024-03-21 2024-04-05 2024-03-28 2024-05-19 2024-07-23 2024-06-30 2024-09-04 2024-07-30 2024-12-01 2024-09-03 2024-10-08 2027-10-08 an Infrastructure Developme Based Selection l ation nt in Temeke and Kigamboni Municipalities under the DMD P 2 Project TZ-PO-RALG-414811-CS-CQS / Consultancy Services for Tr affic Management and Parkin Consultant Qualifi Open - Internationa Under Implement IDA / 74780 Post 0.00 2024-03-15 2024-03-17 2024-04-05 2024-03-28 2024-05-19 2024-06-30 2024-08-04 2025-01-04 g Study in the Central Busine cation Selection l ation ss District Areas of Dar es Sal aam City under the DMDP 2 Project TZ-PO-RALG-462872-CS-QCB S / Consultancy Services for t he Design, Implementation, a Quality And Cost- Open - Internationa Pending Impleme nd Updating Local Governme IDA / 74780 Prior 0.00 2024-11-25 2024-12-16 2025-01-29 2025-03-15 2025-04-14 2025-05-28 2025-07-15 2027-03-15 Based Selection l ntation nt Solid Waste Management Service Framework and Deliv ery System in Dar es Salaam under the DMDP 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-PO-RALG-462865-CS-CDS / Consultancy Services - Desi gn Review and Advice for Flo od Resilient Bridges and Rela Direct - Internation Pending Impleme IDA / 74780 Post Direct Selection 0.00 2024-11-22 2024-12-07 2025-02-15 2025-04-30 ted Works proposed for the D al ntation ar es Salaam Region under C ontingent Emergency Respon se Component (CERC) under the DMDP 2 Project TZ-PO-RALG-463934-CS-CDS / Provision of Design Review and Construction Supervision Consultancy Services for Vari ous Roads Under Emergency IDA / 74780 Prior Direct Selection Direct - National 0.00 Under Review 2024-12-06 2024-12-16 2025-02-19 2026-05-30 Works in Tanzania Mainland: Arusha, Tanga, Kilimanjaro, Dodoma, Manyara, Morogoro , Dar es Salaam, Lindi, Pwani and Mtwara Regions TZ-PO-RALG-463935-CS-CDS / Provision of Design Review and Construction Supervision Consultancy Services for Vari IDA / 74780 Prior Direct Selection Direct - National 0.00 Under Review 2024-12-06 2024-12-16 2025-02-19 2026-05-30 ous Roads Under Emergency Works in Tanzania Mainland: Ruvuma, Njombe, Songwe, Iri nga, Rukwa, Mbeya, Tabora, Kigoma and Katavi Regions TZ-PO-RALG-463936-CS-CDS / Provision of Design Review and Construction Supervision Consultancy Services for Vari Under Implement IDA / 74780 Prior Direct Selection Direct - National 0.00 2024-12-06 2024-12-04 2024-12-16 2025-02-19 2026-05-30 ous Roads Under Emergency ation Works in Tanzania Mainland: Simiyu, Singida, Mara, Shiny anga, Mwanza, Geita, and Ka gera Regions Page 6