Document of The World Bank REPORT NO: 62262-AL Restructuring PAPER ON A PROPOSED Project restructuring of Power Sector Generation AnD Restructuring Project Credit 3872 ALB March 16, 2004 TO ALBANIA June 16, 2011 REGIONAL VICE PRESIDENT: PHILIPPE LE HOUEROU COUNTRY DIRECTOR: JANE ARMITAGE SECTOR MANAGER / DIRECTOR: RANJIT LAMECH TASK TEAM LEADER: ARTURO S. RIVERA Extension of Closing Date ALBANIA - POWER SECTOR GENERATION AND RESTRUCTURING PROJECT PROJECT NO. P077526 cREDIT 3872 ALB 1. The closing date for the Albania Power Sector Generation and Restructuring Project, Credit 3872-ALB (P077526) will be extended from June 30, 2011, until December 30, 2011. 2. The project is nearing completion with disbursements at 90%. The project has achieved substantial progress in facilitating sector reforms, thus paving the way for the privatization of the distribution sector in 2009. Technical problems experienced during the installation of the offshore water intake/outflow and fuel line pipes caused a delay in the commissioning of the Vlore Power Plant – the project’s investment component. Given the severity of the issues, a new management team was put in place at KESH, the project beneficiary, and the Contractor, the latter including the involvement of senior management from HQs in Italy. Furthermore, periodic monitoring meetings, involving KESH, the Contractor, EBRD and EIB, have been taking place, the latest on May 2-3, 2011. 3. As a result of these actions, substantial progress has taken place, including safe restoration of the fuel line and ongoing replacement of the water intake/outflow pipes. 4. The proposed extension will enable completion of the following critical tasks: (i) Completion of water intake/outflow pipes installation, including testing. Based on 40 % progress achieved so far, this process is scheduled to be completed by the end of July; (ii) Testing/trial running and commissioning of the Vlore Power Plant immediately after acceptance of offshore works. According to the Action Plan submitted by the borrower, commissioning is likely to take place in July 2011. The contractor introduced the head of the commissioning team during the last meeting at Vlore on May 30; and (iii) Contract award to the Operating and Maintenance (O&M) firm which will operate the Vlore Power Plant, and which has to be on site during the commissioning process. The selection process has been completed and contract award will be completed this month. 5. The requirements of OP13.30 have been met, namely, (a) the project objectives continue to be achievable; (b) the performance of the Borrower and other project implementing agencies is satisfactory; and (c) the borrower has prepared a specific Action Plan acceptable to the Bank to complete the project within the proposed extended timeframe. There are no outstanding audits. No new safeguards policies will be triggered and there are no changes proposed to the environmental assessment category. Disbursement is currently at 90%. 6. This will be the second extension of the Closing Date and the proposed extension will result in a cumulative extension of over two years.