Procurement Plan (Text Part) Nuton Jibon Livelihood Improvement Project (NJLIP) Agency: Social Development Foundation (SDF) I. General 1. Bank’s approval Date of the procurement Plan: December 28, 2017 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: The procurement period of project covered July 2016 to June 2021. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank: Procurement Prior Review Thresholds (US$ millions) (Procurement Activity) Type of Substantial High risk Moderate risk Low risk Procurement risk Works (including turnkey, supply & installation of plant 5 10 15 20 and equipment, and PPP) Goods, information technology and non- 1.5 2 4 6 consulting services Notes: 1. Use of Standard Procurement Documents: For all procurements under the project, the Bank’s Standard Procurement Documents (or other documents agreed with the Bank) shall be used; 2. Request for Bids (Open-National), if allowed in the Procurement Plan, will be carried out under the Bank’s Procurement Guidelines following procedures for Open Tendering Method (OTM) of the People’s Republic of Bangladesh (Public Procurement Act 2006 – PPA, 1st amendment to PPA (2009) and The Public Procurement Rules 2008, as amended in August 2009) using standard/model bidding documents satisfactory to the Bank. For the purpose of Request for Bids (Open-National) the following shall apply: a. Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; b. Bids should be submitted and opened in public in one location immediately after the deadline for submission; c. Lottery in award of contracts shall not be allowed; d. Bidders’ qualification/experience requirement shall be mandatory; e. Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost and contract award shall be based on the lowest evaluated bid price of compliant bid from eligible and qualified bidder; and f. Single-stage two-envelope procurement system shall not be allowed. .III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank: Procurement Prior Review Thresholds (US$ millions) (Procurement Activity) Type of Substantial High risk Moderate risk Low risk Procurement risk Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT Bangladesh : Nuton Jibon Livelihood Improvement Project PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2017-04-23 2021-03-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149605 GPN Date: Project Name: Nuton Jibon Livelihood Improvement Project Loan / Credit No: IDA / 55940 Social Development Foundation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BD-SDF-12729-GO-RFB G2 / Supply of Livelihood and Component B – Business Single Stage - One employment generation IDA / 55940 Development and Post Request for Bids Open - National 56,410.00 52,405.97 Signed 2017-05-01 2017-05-21 2017-05-06 2017-06-03 2017-06-22 2017-07-18 2017-11-07 2017-08-22 2017-12-12 2017-10-06 Envelope promotional materials phase- Institutional Strengthening 1 BD-SDF-12805-GO-RFB G-2- Component B – Business Pending 2 / Supply of promotional Single Stage - One IDA / 55940 Development and Post Request for Bids Open - National 25,640.00 0.00 Implementati 2018-04-01 2018-04-06 2018-05-04 2018-06-18 2018-07-23 2018-09-06 materials for livelihood and Envelope Institutional Strengthening on youth employment phase-II BD-SDF-12806-GO-RFB G-2- Component B – Business Pending 3 / supply of promotional Single Stage - One IDA / 55940 Development and Post Request for Bids Open - National 38,460.00 0.00 Implementati 2019-03-04 2019-03-09 2019-04-06 2019-05-21 2019-06-25 2019-08-09 materials for livelihood and Envelope Institutional Strengthening on youth employment phase-III BD-SDF-12809-GO-RFB-G-5- 0 / Information Education and Communication (IEC) Material for Information dessimination Component A – Community Pending at initial stage (e.g. poster, Single Stage - One IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 24,360.00 0.00 Implementati 2018-01-01 2018-01-06 2018-02-03 2018-03-20 2018-04-24 2018-06-08 leaflet, handouts, Festoon etc. Envelope Development on for around 2500 new villages, Ups, Upzs, districts and 3262 old villages on 2nd Generation activities) BD-SDF-12817-GO-RFB-G- Component C – Project Single Stage - One 10-2 / Supply and printing of IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 10,260.00 0.00 Canceled 2018-10-01 2018-10-06 2018-11-03 2018-11-17 2018-12-08 2019-01-07 Envelope annual diary 2019 Learning BD-SDF-12916-GO-RFB-G- Component C – Project Single Stage - One 10-4 / Supply and printing of IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 10,260.00 0.00 Canceled 2020-10-04 2020-10-09 2020-10-30 2020-11-04 2020-11-23 2020-12-23 Envelope diary 2021 Learning BD-SDF-12917-GO-RFB-G-7- Component C – Project Pending Single Stage - One 2 / Printing of News Letter( 8 IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 10,260.00 0.00 Implementati 2017-09-03 2017-09-08 2017-10-06 2017-10-16 2017-11-09 2017-12-09 Envelope Quarters) Learning on BD-SDF-12918-GO-RFB-G-8- Component C – Project Single Stage - One 1 / Printing of Annual Report IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 12,820.00 0.00 Canceled 2017-10-01 2017-10-06 2017-11-03 2017-11-13 2017-12-07 2018-01-06 Envelope 2017 Learning BD-SDF-12919-GO-RFB-G-8- Component C – Project Single Stage - One 2 / Printing of Annual Report IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 12,820.00 0.00 Canceled 2018-10-01 2018-10-06 2018-11-03 2018-11-13 2018-12-07 2019-01-06 Envelope 2018 Learning BD-SDF-12923-GO-RFB-G-8- Component C – Project Pending Single Stage - One 4 / Printing of Annual Report IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 12,820.00 0.00 Implementati 2020-10-01 2020-10-06 2020-11-03 2020-11-13 2020-12-07 2021-01-06 Envelope 2020 Learning on BD-SDF-12924-GO-RFB-G-9- Component C – Project Single Stage - One 0 / Printing of Project IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 7,690.00 2,941.98 Signed 2017-06-01 2017-11-12 2017-06-06 2017-07-04 2017-11-20 2017-07-14 2017-11-20 2017-08-07 2017-11-21 2017-09-06 Envelope Brochure-1 Learning BD-SDF-12925-GO-RFB-G-9- Component C – Project Pending Single Stage - One 1 / Printing of Project IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 7,690.00 0.00 Implementati 2019-06-02 2019-06-07 2019-07-05 2019-07-15 2019-08-08 2019-09-07 Envelope Brochure-2 Learning on BD-SDF-12926-GO-RFB-G-9- Component C – Project Pending Single Stage - One 2 / Printing of Project IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 7,690.00 0.00 Implementati 2021-05-02 2021-05-07 2021-06-04 2021-06-14 2021-07-08 2021-08-07 Envelope Brochure-3 Learning on BD-SDF-12927-GO-RFB-G- Component A – Community Pending 12 / Supply and procurement Single Stage - One IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 32,050.00 0.00 Implementati 2017-05-02 2017-05-07 2017-06-04 2017-06-18 2017-07-09 2017-08-23 of Training materials for Envelope Development on community and SDF field staff BD-SDF-12929-GO-RFB-G- Component C – Project Request for Single Stage - One 13-2 / Supply and printing of IDA / 55940 Management, Monitoring and Post Open - National 5,100.00 5,869.68 Signed 2018-10-06 2018-11-29 2018-11-29 2018-12-29 Quotations Envelope Wall Calendar 2019 Learning BD-SDF-12932-GO-RFQ-G- Component C – Project Request for Single Stage - One 13-4 / Supply and printing of IDA / 55940 Management, Monitoring and Post Open - National 5,100.00 4,905.37 Signed 2020-10-06 2020-11-29 2020-12-07 2020-12-29 Quotations Envelope Wall Calendar 2021 Learning BD-SDF-12944-GO-RFB-G- Component B – Business Pending Single Stage - One 14 / audio visual training IDA / 55940 Development and Post Request for Bids Open - National 32,051.00 0.00 Implementati 2018-01-01 2018-01-06 2018-01-27 2018-02-03 2018-02-24 2018-03-26 Envelope material for livelihood Institutional Strengthening on Page 1 BD-SDF-12958-GO-RFB-G-5- 3 / Information Education and Component A – Community Pending Communication (IEC) material Single Stage - One IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 64,103.00 0.00 Implementati 2018-01-01 2018-01-06 2018-02-03 2018-02-13 2018-03-09 2018-04-08 (i.e poster, leaflet, handouts, Envelope Development on festoon etc. for around 2500 villages) BD-SDF-12959-GO-RFB-G-5- 4 / Information Education & Component A – Community Pending Single Stage - One Communication Material IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 64,102.00 0.00 Implementati 2018-06-28 2018-07-03 2018-07-31 2018-08-10 2018-09-03 2018-10-03 Envelope (poster, leaflet, handouts, Development on Festoon etc.) for 2500 villages BD-SDF-12961-GO-RFB-G-5- Component A – Community Pending 5 / Information Education and Single Stage - One IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 64,102.00 0.00 Implementati 2018-12-02 2018-12-07 2019-01-04 2019-01-14 2019-02-07 2019-03-09 Communication Material for Envelope Development on 2500 villages BD-SDF-12545-GO-RFB-G 3- Component A – Community 1 / Supply of Laptop with Single Stage - One IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 544,600.00 498,799.95 Signed 2017-04-30 2017-05-21 2017-05-05 2017-06-16 2017-06-22 2017-07-16 2017-08-10 2017-08-20 2017-09-10 2018-02-16 modem for internet Envelope Development connection - Phase 1 BD-SDF-27665-GO-RFQ-13- Component A – Community Pending 5 / Preparation and supply of Request for Single Stage - One IDA / 55940 Institutions and Livelihood Post Open - National 1,800.00 0.00 Implementati 2017-09-07 2017-10-03 2017-11-17 short documentary on SDF Quotations Envelope Development on activities BD-SDF-12724-GO-RFB-3-2 Component A – Community / Supply of laptop with Single Stage - One IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 544,600.00 0.00 Canceled 2018-06-04 2018-06-14 2018-07-12 2018-08-26 2018-10-07 2019-01-05 Modem for the villages phase- Envelope Development 2 BD-SDF-12811-GO-RFB-G- Component C – Project Single Stage - One 10-1 / Supply and printing of IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 17,500.00 9,611.33 Signed 2017-09-17 2017-11-02 2017-09-22 2017-10-20 2017-11-23 2017-10-30 2017-12-12 2017-11-27 2018-01-04 2017-12-27 Envelope Annual Diary for the year Learning 2018 BD-SDF-32490-GO-RFQ-G- Component A – Community Request for Single Stage - One 14-0 / Procurement of PABX IDA / 55940 Institutions and Livelihood Post Limited 1,000.00 943.81 Signed 2017-10-22 2017-10-17 2017-10-26 2017-11-01 2017-11-02 Quotations Envelope System Development BD-SDF-12727-GO-RFB-3-3 Component A – Community / Supply and installation of Single Stage - One IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 1,225,000.00 1,192,627.90 Signed 2018-01-02 2018-01-18 2018-01-04 2018-02-15 2018-02-15 2018-03-02 2018-03-24 2018-03-23 2018-05-17 2018-06-21 1800 laptop and 1800 Envelope Development modem for the NJLIP villages phase-2 BD-SDF-44286-GO-RFQ-G- Component A – Community 16 / Purchase and supply of Request for Single Stage - One IDA / 55940 Institutions and Livelihood Post Limited 2,450.00 2,499.26 Signed 2018-01-22 2018-01-29 2018-02-04 2018-02-25 2018-03-04 Online UPS for Loan Quotations Envelope Development Management System Server BD-SDF-46519-GO-RFQ G Component A – Community Pending Request for Single Stage - One 17 / Supply and installation of IDA / 55940 Institutions and Livelihood Post Limited 3,200.00 0.00 Implementati 2018-02-04 2018-03-07 2018-04-04 Quotations Envelope Printers and Scanner Development on BD-SDF-56753-GO-RFQ-G- 18 / Photography and supply Component C – Project Pending Request for Single Stage - One of photograph for annual IDA / 55940 Management, Monitoring and Post Limited 2,500.00 0.00 Implementati 2018-04-06 2018-04-25 2018-05-05 Quotations Envelope report and other Learning on documentation. BD-SDF-56988-GO-RFQ-G- Component C – Project 19 / Server based antivirus for Request for Single Stage - One IDA / 55940 Management, Monitoring and Post Limited 2,200.00 1,628.98 Signed 2018-04-05 2018-04-04 2018-04-19 2018-04-11 2019-04-19 the computers/laptops of Quotations Envelope Learning SDF. BD-SDF-57109-GO-RFQ-G- Component A – Community 20 / Purchase of 16 pcs high Request for Single Stage - One IDA / 55940 Institutions and Livelihood Post Limited 2,800.00 2,571.27 Signed 2018-04-09 2018-04-18 2018-05-07 2018-05-14 2018-06-04 power online UPS battery for Quotations Envelope Development the server BD-SDF-59380-GO-RFQ-G- Component B – Business Request for Single Stage - One 21-0 NJLIP / Brochure for IDA / 55940 Development and Post Limited 2,500.00 1,606.66 Signed 2018-07-24 2018-07-19 2018-08-23 2018-07-24 2018-09-20 Quotations Envelope Nutrition of NJLIP Institutional Strengthening BD-SDF-59383-GO-RFQ-G- Component B – Business Request for Single Stage - One 22-0-NJLIP / Brochure on IDA / 55940 Development and Post Limited 2,500.00 4,707.57 Signed 2018-11-20 2019-07-07 2018-12-23 2019-07-17 2019-01-20 Quotations Envelope livelihood activities of NJLIP Institutional Strengthening BD-SDF-59394-GO-RFQG- Component B – Business Pending 23-0-NJLIP / Brochure on Request for Single Stage - One IDA / 55940 Development and Post Limited 2,500.00 0.00 Implementati 2018-06-30 2018-07-30 2018-08-27 Youth and Employment of Quotations Envelope Institutional Strengthening on NJLIP BD-SDF-59401-GO-RFQ-G- Component B – Business 24-0-NJLIP / preparation and Request for Single Stage - One IDA / 55940 Development and Post Limited 4,000.00 2,517.11 Signed 2018-04-21 2018-04-03 2018-05-23 2018-04-15 2018-06-20 supply of short film on Quotations Envelope Institutional Strengthening success story / case study BD-SDF-59402-GO-RFQ-G- 25-0-NJLLIP / preparation Component B – Business Pending Request for Single Stage - One and supply of short film on IDA / 55940 Development and Post Limited 5,000.00 0.00 Implementati 2018-06-01 2018-07-04 2018-08-01 Quotations Envelope success story / case study of Institutional Strengthening on IGA (Agriculture) BD-SDF-12928-GO-RFB-G- Component A – Community 13-1 / Printing and supply of Single Stage - One IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 15,000.00 11,085.15 Signed 2018-07-24 2017-11-02 2018-08-07 2018-08-08 2017-11-23 2018-08-15 2017-12-14 2018-08-31 2018-01-04 2018-09-28 Wall Calendar -2018 and Desk Envelope Development Calendar-2018 BD-SDF-36594-GO-RFQ- G- 15-0 / Supply installation and Component A – Community Request for Single Stage - One commissioning of Database IDA / 55940 Institutions and Livelihood Post Limited 6,400.00 5,542.82 Signed 2018-07-31 2017-11-22 2018-08-22 2018-01-01 2018-09-12 Quotations Envelope Server for Loan Management Development Systems under NJLIP BD-SDF-71230-GO-RFQ-G- Component C – Project 27-0 / Procurement, supply Request for Single Stage - One IDA / 55940 Management, Monitoring and Post Limited 6,000.00 5,786.85 Signed 2018-08-04 2018-07-25 2018-09-10 2018-08-16 2018-10-08 and installation of server for Quotations Envelope Learning MIS of NJLIP Page 2 BD-SDF-78302-GO-RFQ-8- Component C – Project Request for Single Stage - One 06 / Printing and supply of IDA / 55940 Management, Monitoring and Post Limited 6,250.00 5,891.10 Signed 2018-09-19 2018-10-02 2018-10-10 2018-10-18 2018-10-24 Quotations Envelope Annual Report-2017 of SDF Learning BD-SDF-12933-GO-RFB-G-1- Component A – Community 1 / Furniture and fixtures for Single Stage - One IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 200,000.00 10,879.08 Signed 2018-10-30 2016-08-02 2018-11-04 2018-12-02 2016-08-28 2018-12-23 2016-09-06 2019-01-13 2016-09-18 2019-03-14 project office at field level of Envelope Development NJLIP project BD-SDF-79304-GO-RFB-G- 28 / Procurement, supply and Component A – Community Single Stage - One Installation of 25 Air Cooler IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 37,500.00 27,403.99 Signed 2018-11-01 2019-05-22 2018-11-06 2019-10-02 2018-12-04 2019-06-13 2018-12-11 2019-07-15 2018-12-26 2019-09-01 2019-02-09 Envelope for HQ and Regional Office of Development SDF BD-SDF-81093-GO-RFB-G- 30 / Procurement and supply Component A – Community of 2500 BMI (weight & height Single Stage - One IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 115,000.00 94,559.48 Signed 2019-01-28 2019-05-19 2019-02-02 2019-09-30 2019-03-02 2019-06-11 2019-03-09 2019-07-21 2019-03-25 2019-09-15 2019-04-22 measurement machines) to Envelope Development distribute to 2500 villages of NJLIP BD-SDF-70178-GO-RFB- G- Component A – Community 26 / Procurement and supply Single Stage - One IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 15,000.00 11,489.06 Signed 2018-11-29 2018-11-19 2018-12-09 2019-01-06 2018-12-12 2019-01-20 2018-12-26 2019-02-10 2019-03-05 2019-03-27 of nutrition plate to the NJLIP Envelope Development villages to BD-SDF-12922-GO-RFB-G-8- Component C – Project Single Stage - One 3 / Printing of Annual Report IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 12,820.00 0.00 Canceled 2020-05-21 2020-05-26 2020-06-23 2020-07-03 2020-07-27 2020-08-26 Envelope 2019 Learning BD-SDF-87265-GO-RFQ-G- Component C – Project Request for Single Stage - One 10-0 / Printing and supply of IDA / 55940 Management, Monitoring and Post Limited 6,000.00 5,891.10 Signed 2018-11-16 2018-11-15 2018-12-03 2018-11-26 2018-12-24 Quotations Envelope Annual Diary-2019 Learning BD-SDF-92056-GO-RFQ-G- Component A – Community 31 / Printing and supply of Request for Single Stage - One IDA / 55940 Institutions and Livelihood Post Limited 6,000.00 5,876.82 Signed 2018-12-21 2018-12-19 2019-01-05 2018-12-27 2019-01-26 Desk Calendar of SDF for the Quotations Envelope Development calendar year 2019 BD-SDF-94882-GO-RFB-G- Component A – Community 32 / Procurement and supply Request for Single Stage - One IDA / 55940 Institutions and Livelihood Post Limited 5,000.00 3,590.60 Signed 2019-01-25 2019-01-10 2019-02-20 2019-02-04 2019-03-13 of printer and scanner for Quotations Envelope Development NJLIP project BD-SDF-96922-GO-RFQ-G- Component C – Project 34 / Printing and supply of Request for Single Stage - One IDA / 55940 Management, Monitoring and Post Limited 1,250.00 1,868.72 Signed 2019-01-29 2019-01-28 2019-02-11 2019-02-13 2019-03-04 semiannual news letter of Quotations Envelope Learning NJLIP BD-SDF-107588-GO-RFQ-G- 35 / Printing and supply of Component B – Business questionnaire for Request for Single Stage - One IDA / 55940 Development and Post Limited 6,000.00 5,059.47 Signed 2019-03-29 2019-02-06 2019-04-14 2019-02-17 2019-05-05 identification of migration Quotations Envelope Institutional Strengthening status of poor and hardcore poor BD-SDF-78303-GO-RFQ-8-7 Component C – Project Request for Single Stage - One / Annual report 2018 printing IDA / 55940 Management, Monitoring and Post Limited 6,250.00 3,358.96 Signed 2019-06-17 2019-04-03 2019-07-26 2019-04-18 2019-08-23 Quotations Envelope and supply Learning BD-SDF-113894-GO-RFB-G- Component A – Community 36 / Procurement and supply Single Stage - One IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 160,000.00 65,090.25 Signed 2019-05-07 2019-06-23 2019-05-12 2019-10-01 2019-06-02 2019-07-21 2019-06-17 2019-08-06 2019-07-03 2019-09-18 2019-08-13 of furniture for SDF HQ and Envelope Development filed office staff of NJCS BD-SDF-12940-GO-RFQ-G- Component C – Project Request for Single Stage - One 13-3 / Supply and printing of IDA / 55940 Management, Monitoring and Post Open - National 6,000.00 5,014.70 Signed 2019-10-06 2019-11-29 2019-11-26 2019-12-29 Quotations Envelope Diary 2020 Learning BD-SDF-12906-GO-RFB-G- Component C – Project 10-3 / Supply of SDF desk Single Stage - One IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 15,300.00 8,136.48 Signed 2019-11-12 2019-11-17 2019-11-14 2019-11-29 2019-12-04 2019-12-02 2019-12-24 2019-12-08 2019-12-31 2020-01-07 Calendar and Wall Calendar Envelope Learning 2020 BD-SDF-79161-GO-RFB-G- 29 / 12 motor cycles for the Component A – Community Single Stage - One District Level MIS officer of IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 25,500.00 0.00 Canceled 2018-10-31 2018-11-05 2018-12-03 2018-12-18 2019-01-05 2019-03-06 Envelope NJLIP to support Development implementation of LMS . BD-SDF-95009-GO-RFB-G- 33 / Procurement and supply Component A – Community of Desktop, laptop and printer Single Stage - One IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 300,000.00 0.00 Canceled 2019-04-30 2019-05-26 2019-05-28 2019-06-01 2019-06-24 2019-06-08 2019-10-23 2019-06-24 2019-08-08 for NJLIP project staff (SDF Envelope Development HQ, Regional, district and cluster level staff BD-SDF-149429-GO-RFQ-G- 51 / procurement and supply Component A – Community Under Request for Single Stage - One of conference table and other IDA / 55940 Institutions and Livelihood Post Limited 6,000.00 0.00 Implementati 2020-01-10 2020-02-16 2020-04-16 Quotations Envelope small furniture for H.O and Development on Field office BD-SDF-149453-GO-RFQ-G- Component A – Community Pending Request for Single Stage - One 39 / Printing of Brochure on IDA / 55940 Institutions and Livelihood Post Limited 5,000.00 0.00 Implementati 2020-02-11 2020-03-19 2020-04-09 Quotations Envelope various activities of NJLIP Development on Component A – Community BD-SDF-149459-GO-RFQ-43 Request for Single Stage - One IDA / 55940 Institutions and Livelihood Post Limited 2,500.00 907.22 Signed 2020-02-21 2020-01-08 2020-03-21 2020-01-15 2020-04-10 / Printing and supply of folder Quotations Envelope Development BD-SDF-149460-GO-RFQ-G- Component A – Community Request for Single Stage - One 44 / Printing and supply of IDA / 55940 Institutions and Livelihood Post Limited 5,000.00 4,918.41 Signed 2020-01-13 2020-02-20 2020-02-01 2020-02-27 2020-02-22 Quotations Envelope digital pictorial Development Component A – Community BD-SDF-149462-GO-RFQ-G- Request for Single Stage - One IDA / 55940 Institutions and Livelihood Post Limited 4,000.00 1,060.38 Signed 2020-03-21 2019-08-18 2020-04-18 2019-09-04 2020-05-13 47 / Printing of News letter Quotations Envelope Development Page 3 BD-SDF-149463-GO-RFQ-G- Component A – Community Request for Single Stage - One 48 / Printing and supply of IDA / 55940 Institutions and Livelihood Post Limited 2,000.00 1,563.48 Signed 2020-03-06 2020-02-19 2020-04-12 2020-02-26 2020-05-10 Quotations Envelope still photography Development BD-SDF-59403-GO-RFQ-G- 25-0-NJLIP / preparation and Component B – Business Pending Request for Single Stage - One supply of short film on IDA / 55940 Development and Post Limited 5,000.00 0.00 Implementati 2018-07-03 2018-08-07 2018-09-04 Quotations Envelope success story / case study Institutional Strengthening on phase-II BD-SDF-149464-GO-RFQ-G- Component A – Community Request for Single Stage - One 49 / Prepare and supply of IDA / 55940 Institutions and Livelihood Post Limited 6,000.00 3,882.96 Signed 2020-04-13 2019-09-16 2020-05-23 2019-10-09 2020-05-29 Quotations Envelope Video documentary Development BD-SDF-149466-GO-RFQ-G- Component A – Community Request for Single Stage - One 51 / Procurement and supply IDA / 55940 Institutions and Livelihood Post Limited 5,500.00 3,593.52 Signed 2020-01-20 2020-02-18 2020-02-24 2020-03-01 2020-03-23 Quotations Envelope of PABX systems Development BD-SDF-149412-GO-RFB- G- Component C – Project Pending 42 / Procurement and supply Single Stage - One IDA / 55940 Management, Monitoring and Post Request for Bids Open - National 14,500.00 0.00 Implementati 2020-10-13 2020-10-18 2020-11-15 2020-11-29 2020-12-15 2021-01-12 of equipment for video Envelope Learning on conference BD-SDF-149423-GO-RFB-G- 33 / Procurement and supply Component A – Community Under Single Stage - One of Laptop, Desktop, Printer, IDA / 55940 Institutions and Livelihood Post Request for Bids Open - National 300,000.00 0.00 Implementati 2019-12-18 2019-12-23 2019-12-23 2021-01-04 2020-01-20 2020-02-03 2020-02-21 2020-04-01 Envelope scanner and UPS for SDF field Development on and Head office BD-SDF-204044-GO-RFQ-G- Component C – Project 53 / Printing and Supply of Request for Single Stage - One IDA / 55940 Management, Monitoring and Post Limited 6,000.00 5,897.00 Signed 2020-11-25 2020-11-29 2020-12-03 2020-12-07 2020-12-24 Desk calendar for 2021 of SDF Quotations Envelope Learning under NJLIP BD-SDF-204050-GO-RFQ-G- Component C – Project Request for Single Stage - One 54 / Printing and supply of IDA / 55940 Management, Monitoring and Post Limited 6,000.00 5,895.82 Signed 2020-11-25 2020-11-29 2020-12-02 2020-12-07 2020-12-30 Quotations Envelope SDF diary for 2021 under Learning NJLIP BD-SDF-204051-GO-RFQ-G- Component C – Project Request for Single Stage - One 55 / SDF Annual Report 2019 IDA / 55940 Management, Monitoring and Post Limited 6,000.00 4,610.58 Signed 2020-11-20 2020-10-11 2020-11-28 2020-10-22 2020-12-19 Quotations Envelope under NJLIP Learning BD-SDF-204052-GO-RFQ-G- Component C – Project Pending Request for Single Stage - One 56 / SDF Annual report 2020 IDA / 55940 Management, Monitoring and Post Limited 6,000.00 0.00 Implementati 2021-02-15 2021-02-28 2021-03-28 Quotations Envelope under NJLIP Learning on BD-SDF-204053-GO-RFQ-G- 57 / Supply and installation of Component A – Community Request for Single Stage - One conference system (Sound IDA / 55940 Institutions and Livelihood Post Limited 6,000.00 5,629.44 Signed 2020-11-17 2020-10-21 2020-11-24 2020-11-03 2020-12-08 Quotations Envelope system) for SDF conference Development room at SDF HQ NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BD-SDF-13027-CS-QCBS-S- Component A – Community 1-0 / NGO Hiring for Quality And Cost- IDA / 55940 Institutions and Livelihood Post Open - International 987,307.00 1,045,792.95 Signed 2017-04-24 2016-05-12 2017-04-24 2017-04-24 2016-12-29 2017-04-24 2017-01-29 2017-04-24 2017-02-15 2017-05-01 2017-05-16 2017-06-05 2017-06-13 2020-06-04 nutrition, awareness and Based Selection Development support services BD-SDF-13029-CS-QCBS-S- Component A – Community 1-1 / NGO Hiring for Quality And Cost- IDA / 55940 Institutions and Livelihood Post Open - International 857,615.00 679,499.97 Signed 2017-04-24 2016-05-11 2017-04-24 2017-04-24 2016-12-29 2017-04-24 2017-01-29 2017-04-24 2017-02-15 2017-05-01 2017-05-16 2017-06-05 2017-06-13 2020-06-04 Nutrition, Awareness and Based Selection Development Support Services BD-SDF-13031-CS-QCBS-S- Component A – Community 1-3 / NGO Hiring for Quality And Cost- IDA / 55940 Institutions and Livelihood Post Open - International 982,000.00 775,356.84 Signed 2017-04-24 2016-05-11 2017-04-24 2017-04-24 2016-12-29 2017-04-24 2017-01-29 2017-04-24 2017-02-15 2017-05-01 2017-05-16 2017-06-05 2017-06-13 2020-06-04 Nutrition, Awareness and Based Selection Development Support Services BD-SDF-13033-CS-QCBS-S- Component A – Community 1-4 / NGO Hiring for Quality And Cost- IDA / 55940 Institutions and Livelihood Post Open - International 288,461.00 107,626.33 Signed 2017-04-25 2016-05-11 2017-05-16 2017-05-16 2016-12-29 2017-05-16 2017-01-29 2017-05-16 2017-02-15 2017-05-23 2017-05-16 2017-06-27 2017-06-13 2020-06-26 Nutrition, Awareness and Based Selection Development Support Services BD-SDF-13034-CS-QCBS-S- Component A – Community Quality And Cost- 2-2 / Firm Hiring for Process IDA / 55940 Institutions and Livelihood Prior Open - International 1,230,769.00 779,793.77 Signed 2017-04-24 2017-05-07 2017-04-24 2017-05-09 2017-05-09 2017-08-13 2017-06-06 2017-09-14 2017-07-06 2017-11-13 2017-08-10 2018-01-18 2017-09-14 2018-01-19 2020-09-13 Based Selection Monitoring Development BD-SDF-19446-CS-FBS-S-15- Component C – Project 0 / Hiring of independent Fixed Budget IDA / 55940 Management, Monitoring and Post Open - National 57,000.00 23,127.45 Signed 2017-06-29 2017-06-29 2017-07-20 2017-08-31 2017-12-28 2017-09-07 2018-01-28 2017-09-14 2018-02-27 2017-09-28 2018-05-14 2017-10-12 2018-05-17 2018-01-10 Operational audit (Internal Selection Learning Audit) (Phase-1) BD-SDF-19462-CS-FBS / Component C – Project Hiring of Independent Fixed Budget Pending IDA / 55940 Management, Monitoring and Post Open - National 58,000.00 0.00 2021-03-01 2021-03-22 2021-05-03 2021-05-10 2021-05-24 2021-06-14 2021-07-12 2021-10-10 Operational Auditor (Internal Selection Implementation Learning Auditor) Phase-5 BD-SDF-19458-CS-FBS-S-15- Component C – Project 3 / Hiring of Independent Fixed Budget Pending IDA / 55940 Management, Monitoring and Post Open - National 56,000.00 0.00 2019-05-01 2019-05-22 2019-07-03 2019-07-10 2019-07-24 2019-08-14 2019-09-11 2019-12-10 Operational Auditor (Internal Selection Implementation Learning Auditor) Phase-4 Page 4 BD-SDF-26656-CS-QCBS- S16-0 / Hiring of consulting Component B – Business firm for developing audio Quality And Cost- Pending IDA / 55940 Development and Post Open - National 51,300.00 0.00 2017-09-10 2017-10-08 2017-11-21 2017-12-19 2018-01-03 2018-01-17 2018-02-07 2018-06-07 visual training materials for Based Selection Implementation Institutional Strengthening income generating activities (IGA) BD-SDF-29082-CS-QCBS-S- 1-5 / Hiring Consulting firm for conducting Behavior Component A – Community Change Communication (BCC) Quality And Cost- IDA / 55940 Institutions and Livelihood Post Open - National 51,300.00 29,472.35 Signed 2017-09-21 2017-10-02 2017-10-12 2017-11-09 2018-01-07 2017-12-07 2017-12-19 2017-12-14 2018-02-07 2017-12-28 2018-02-15 2018-01-11 2018-02-22 2018-05-11 assessment for 'Nutrition Based Selection Development Awareness & Support Services" in 3 Regions of SDF under NJLIP BD-SDF-13318-CS-QCBS-S- Component C – Project Quality And Cost- 5-0 / Impact evaluation after IDA / 55940 Management, Monitoring and Post Open - National 128,205.00 0.00 Canceled 2018-03-01 2018-03-01 2018-03-29 2018-04-12 2018-04-18 2018-05-10 2018-04-23 2018-05-25 2018-04-23 2018-06-01 2018-04-24 2018-06-10 2018-10-08 Based Selection 3 years of the proejct Learning BD-SDF-13316-CS-QCBS-S- Component C – Project Quality And Cost- Pending 5-1 / Impact evaluation of the IDA / 55940 Management, Monitoring and Post Open - National 141,025.00 0.00 2021-02-01 2021-03-01 2021-04-14 2021-05-12 2021-05-19 2021-06-16 2021-07-05 2021-12-02 Based Selection Implementation project at the end Learning BD-SDF-13296-CS-QCBS-S- Component B – Business Quality And Cost- 4-0 / Mid term review of the IDA / 55940 Development and Post Open - National 76,900.00 0.00 Canceled 2018-01-15 2018-02-12 2018-03-28 2018-04-25 2018-05-10 2018-06-14 2018-07-08 2019-01-04 Based Selection project-NJLIP Institutional Strengthening BD-SDF-58780-CS-CQS-S-4- Component B – Business Consultant 0 / Mid term review (MTR) of IDA / 55940 Development and Post Qualification Open - National 58,000.00 53,501.36 Signed 2018-04-12 2018-05-08 2018-05-03 2018-05-20 2018-06-06 2018-05-25 2018-06-28 2018-06-02 2018-07-01 2018-08-31 the project NJLIP Institutional Strengthening Selection BD-SDF-19457-CS-FBS-S-15- Component C – Project 2 / Hiring of Independent Fixed Budget Pending IDA / 55940 Management, Monitoring and Post Open - National 56,000.00 0.00 2018-10-21 2018-11-11 2018-12-19 2018-12-20 2018-12-30 2019-01-07 2019-01-18 2019-04-18 Operational Auditor (Internal Selection Implementation Learning Auditor) Phase-3 BD-SDF-19455-CS-FBS-S-15- Component C – Project 1 / Hiring of Independent Fixed Budget Under IDA / 55940 Management, Monitoring and Post Open - National 55,000.00 0.00 2017-10-01 2019-11-03 2017-10-22 2019-11-04 2017-12-03 2017-12-10 2017-12-24 2018-01-14 2018-02-11 2018-05-12 Operational Audit (Internal Selection Implementation Learning Audit) Phase-2 BD-SDF-59420-CS-CQS-S-5- Component C – Project Consultant 0-NJLIP / Conducting Midterm IDA / 55940 Management, Monitoring and Post Qualification Open - National 100,000.00 89,848.49 Signed 2018-07-24 2018-03-04 2018-08-07 2018-08-24 2018-04-11 2018-08-31 2018-04-23 2018-09-16 2018-04-25 2018-12-15 Impact Assessment of the Learning Selection Project (NJLIP) BD-SDF-13118-CS-QCBS-S- Component C – Project 11-0 / Hiring of Agency for Quality And Cost- IDA / 55940 Management, Monitoring and Post Open - National 51,282.00 0.00 Canceled 2017-07-02 2017-07-30 2017-09-12 2017-10-10 2017-10-25 2017-11-29 2017-12-23 2018-06-21 development of counselling Based Selection Learning skill to SDF staff INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BD-SDF-12941-CS-INDV-S- Component B – Business Individual Under 9-1 / Sectoral Study and IDA / 55940 Development and Post Consultant Open 19,500.00 0.00 2018-04-01 2017-07-31 2018-05-20 2018-06-10 2018-07-01 2018-09-29 Implementation Market Scan on IGAs- 2 Institutional Strengthening Selection BD-SDF-12971-CS-INDV-S- 12-5 / specialized Component B – Business Individual Employment Support for Pending IDA / 55940 Development and Post Consultant Open 25,641.00 0.00 2019-06-05 2019-07-24 2019-08-14 2019-09-04 2019-12-03 providing skill development Implementation Institutional Strengthening Selection training and employment support through outsourcing BD-SDF-12973-CS-INDV-S- Component B – Business Individual 14 / Consultancy hiring for Pending IDA / 55940 Development and Post Consultant Open 3,846.00 0.00 2017-07-02 2017-08-20 2017-09-10 2017-10-01 2017-12-30 capacity building of producer Implementation Institutional Strengthening Selection group BD-SDF-13060-CS-INDV-S- Component B – Business Individual Pending 6-4 / Thematic Studies, Phase- IDA / 55940 Development and Post Consultant Open 19,230.00 0.00 2019-01-01 2019-02-19 2019-03-12 2019-04-02 2019-07-01 Implementation 4 Institutional Strengthening Selection BD-SDF-13114-CS-INDV-S- Component B – Business Individual Pending 6-5 / Thematic Short Studies, IDA / 55940 Development and Post Consultant Open 19,230.00 0.00 2019-07-01 2019-08-19 2019-09-09 2019-09-30 2019-12-29 Implementation Phase-5 Institutional Strengthening Selection BD-SDF-13115-CS-INDV-S- Component B – Business Individual Pending 6-6 / Thematic Short Studies, IDA / 55940 Development and Post Consultant Open 19,230.00 0.00 2020-01-01 2020-02-19 2020-03-11 2020-04-01 2020-06-30 Implementation Phase-6 Institutional Strengthening Selection BD-SDF-12543-CS-INDV-S Component C – Project Individual 10 / Hiring of Procurement IDA / 55940 Management, Monitoring and Prior Consultant Limited 32,050.00 27,828.06 Signed 2017-04-27 2017-04-30 2017-05-02 2017-05-28 2017-05-16 2017-06-13 2017-06-09 2017-06-14 2017-12-06 Consultant Learning Selection BD-SDF-13329-CS-INDV-S- Component C – Project Individual 15-0 / Hiring of Independent IDA / 55940 Management, Monitoring and Post Consultant Open 57,692.00 0.00 Canceled 2017-05-15 2017-07-03 2017-07-24 2017-08-14 2017-11-12 Operational Audit (Internal Learning Selection Audit), Phase-1 BD-SDF-13332-CS-INDV-S- Component C – Project Individual 15-1 / Hiring of Independent IDA / 55940 Management, Monitoring and Post Consultant Open 57,692.00 0.00 Canceled 2018-05-15 2018-07-03 2018-07-24 2018-08-14 2018-11-12 Audit ( Internal Audit), Phase- Learning Selection 2 BD-SDF-13334-CS-INDV-S- Component C – Project Individual 15-2 / Hiring of Independent IDA / 55940 Management, Monitoring and Post Consultant Open 57,692.00 0.00 Canceled 2019-05-02 2019-06-20 2019-07-11 2019-08-01 2019-10-30 Operational Audit (Internal Learning Selection Audit), Phase-3 BD-SDF-13338-CS-INDV-S- Component C – Project Individual 15-4 / Hiring of Independent IDA / 55940 Management, Monitoring and Post Consultant Open 57,692.00 0.00 Canceled 2021-05-16 2021-07-04 2021-07-25 2021-08-15 2021-11-13 Operational Audit (Internal Learning Selection Audit), Phase-4 Page 5 BD-SDF-13336-CS-INDV-15- Component C – Project Individual 3 / Hiring of Independent IDA / 55940 Management, Monitoring and Post Consultant Open 57,692.00 0.00 Canceled 2020-05-17 2020-07-05 2020-07-26 2020-08-16 2020-11-14 Operational Audit (Internal Learning Selection Audit), Phase-4 BD-SDF-12967-CS-INDV- S12-1 / Specialized Component B – Business Individual Employment Support (for IDA / 55940 Development and Post Consultant Open 25,641.00 0.00 Canceled 2017-07-02 2017-08-20 2017-09-10 2017-10-01 2017-12-30 providing skill development Institutional Strengthening Selection training and employment support through outsourcing. BD-SDF-12968-CS-INDV-S- 12-2 / specialized Component B – Business Individual Employment Support for IDA / 55940 Development and Post Consultant Open 25,641.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-03-28 2018-06-26 providing skill development Institutional Strengthening Selection training and employment support through outsourcing. BD-SDF-59306-CS-INDV-S- Component B – Business Individual Pending 17-0-NJLIP / Thematic Short IDA / 55940 Development and Post Consultant Limited 22,000.00 0.00 2018-07-01 2018-07-06 2018-07-20 2018-07-29 2018-10-27 Implementation studies for CISF under NJLIP Institutional Strengthening Selection BD-SDF-12969-CS-INDV-S- 12-3 / specialized Component B – Business Individual Employment Support for IDA / 55940 Development and Post Consultant Open 25,641.00 0.00 Canceled 2018-06-03 2018-07-22 2018-08-12 2018-09-02 2018-12-01 providing skill development Institutional Strengthening Selection training and employment support through outsourcing BD-SDF-12970-CS-INDV-S- 12-4 / specialized Component B – Business Individual Employment Support for IDA / 55940 Development and Post Consultant Open 25,641.00 0.00 Canceled 2018-12-27 2019-02-14 2019-03-07 2019-03-28 2019-06-26 providing skill development Institutional Strengthening Selection training and employment support through outsourcing BD-SDF-70165-CS-INDV-S- 19-0 / Hiring consultant for Component B – Business Individual facilitating accomplishment of IDA / 55940 Development and Post Consultant Limited 5,000.00 4,438.13 Signed 2018-07-24 2019-01-06 2018-08-03 2019-01-06 2018-08-10 2019-02-07 2018-08-24 2019-02-27 2018-12-22 producer group registration at Institutional Strengthening Selection village level of NJLIP villages for 4 months BD-SDF-59307-CS-INDV-S- Component B – Business Individual Pending 18-0-NJLIP / Thematic Short IDA / 55940 Development and Post Consultant Limited 22,000.00 0.00 2018-10-30 2018-11-04 2018-11-18 2018-11-27 2019-02-25 Implementation Studies Nutrition of NJLIP Institutional Strengthening Selection BD-SDF-13057-CS-INDV-S- Component B – Business Individual Pending 6-3 / Thematic Short Studies, IDA / 55940 Development and Post Consultant Open 19,230.00 0.00 2018-12-02 2019-01-20 2019-02-10 2019-03-03 2019-06-01 Implementation Phase-3 Institutional Strengthening Selection BD-SDF-13056-CS-INDV-S- Component B – Business Individual Pending 6-2 / Thematic Short Studies- IDA / 55940 Development and Post Consultant Open 19,230.00 0.00 2018-11-08 2018-12-27 2019-01-17 2019-02-07 2019-05-08 Implementation Phase 2 Institutional Strengthening Selection BD-SDF-13055-CS-INDV-S- Component B – Business Individual Pending 6-0 / Thematic Short Studies, IDA / 55940 Development and Post Consultant Open 19,230.00 0.00 2017-07-02 2017-08-20 2017-09-10 2017-10-01 2017-12-30 Implementation Phase-1 Institutional Strengthening Selection BD-SDF-12975-CS-INDV-S- 13 / Consultancy hiring for Component B – Business Individual Pending value chain development of IDA / 55940 Development and Post Consultant Open 25,641.00 0.00 2018-10-25 2018-12-13 2018-12-18 2019-01-08 2019-04-08 Implementation livestock Income Generating Institutional Strengthening Selection Activities BD-SDF-95018-CS-INDV-S- 37 / Hiring of consultant for conducting Technical Audit Component B – Business Individual including environmental IDA / 55940 Development and Post Consultant Limited 31,000.00 24,853.54 Signed 2019-01-22 2019-03-05 2019-02-12 2019-03-05 2019-02-19 2019-04-24 2019-02-28 2019-05-06 2019-06-28 impact assessment of Institutional Strengthening Selection completed community sub- projects of NJLIP. BD-SDF-149570-CS-INDV-S- Component A – Community Individual 38 / Hiring consultant for IDA / 55940 Institutions and Livelihood Post Consultant Limited 10,800.00 9,046.22 Signed 2019-12-17 2020-01-09 2019-12-31 2020-01-12 2020-01-04 2020-01-29 2020-01-11 2020-01-30 2020-07-09 documentation of NJLIP Development Selection achievement Component A – Community Individual BD-SDF-149465-GO-RFQ-S- IDA / 55940 Institutions and Livelihood Post Consultant Limited 5,600.00 4,333.47 Signed 2019-12-22 2019-12-01 2019-12-29 2020-01-20 2020-01-03 2020-01-20 2020-01-12 2020-01-21 2020-04-11 39 / SDF website development Development Selection BD-SDF-193708-CS-CDS-S- 41 / Hiring consultant to review and recast the existing Environment and Social Management Framework Component C – Project (ESMF) of Nuton Jibon IDA / 55940 Management, Monitoring and Post Direct Selection Direct 6,000.00 5,748.48 Signed 2020-09-12 2020-09-03 2020-09-14 2020-09-07 2020-09-19 2020-09-17 2020-10-04 Livelihood Improvement Learning Project (NJLIP) to make it functional for the upcoming buffer project: NJLIP- Additional Financing (AF) BD-SDF-193709-CS-CDS-S- 42 / Impact assessment Component C – Project survey of COVID-19 on NJLIP Under IDA / 55940 Management, Monitoring and Post Direct Selection Direct 26,000.00 0.00 2020-09-13 2020-09-03 2020-09-16 2020-09-22 2020-11-06 beneficiaries to draw a Implementation Learning baseline for the NJLIP-AF’ using Mobile Phone and Tab. BD-SDF-185849-CS-INDV-S- 40 / Hiring consultant for Component A – Community Individual preparation of ToT on Under IDA / 55940 Institutions and Livelihood Post Consultant Limited 7,150.00 0.00 2020-09-16 2020-08-04 2020-09-21 2020-09-23 2020-09-27 2020-11-26 installation and maintenance Implementation Development Selection of water treatment plant in NJLIP villages BD-SDF-203687-CS-INDV-S- 43 / Hiring Media Consultant Component C – Project Individual Pending (Junior) for dissemination of IDA / 55940 Management, Monitoring and Post Consultant Limited 3,600.00 0.00 2020-11-15 2020-11-22 2020-11-24 2020-12-02 2021-05-31 Implementation NJLIP activities in Electronic, Learning Selection Print & Social media Page 6 BD-SDF-203689-CS-INDV-S- 44 / Hiring consultant for preparation of Labor Component C – Project Individual Under Management Procedures (LMP) IDA / 55940 Management, Monitoring and Post Consultant Limited 8,400.00 0.00 2020-11-10 2020-11-17 2020-11-15 2020-11-16 2020-11-19 2020-12-19 Implementation and Environment & Social Learning Selection Commitment Plan (ESCP) for NJLIP-2 project BD-SDF-203691-CS-INDV-S- 45 / Hiring consultant for Component C – Project Individual preparation of Environment & Under IDA / 55940 Management, Monitoring and Post Consultant Limited 8,400.00 0.00 2020-11-12 2020-11-18 2020-11-19 2020-11-21 2020-11-23 2020-11-26 Social Management Implementation Learning Selection Framework (ESNF) for NJLIP-2 Project BD-SDF-203817-CS-INDV-S- 46 / Hiring consultant for preparation of Small Ethnic Component C – Project Individual Community and Vulnerable Pending IDA / 55940 Management, Monitoring and Post Consultant Limited 8,400.00 0.00 2020-11-15 2020-11-20 2020-11-22 2020-11-25 2020-12-25 Peoples' Development Implementation Learning Selection Framework (SECVPDF) including Stakeholder Engagement Plan BD-SDF-222532-CS-INDV-S- 47 / Hiring consultant for Component C – Project Individual Pending conducting and submission of IDA / 55940 Management, Monitoring and Post Consultant Limited 42,000.00 0.00 2021-03-04 2021-03-18 2021-03-22 2021-03-31 2021-06-29 Implementation Borrowers Completion Report Learning Selection of NJLIP BD-SDF-222537-CS-INDV-S- 48 / Hiring Consultant to Component C – Project Individual Pending update Financial Management IDA / 55940 Management, Monitoring and Post Consultant Limited 5,000.00 0.00 2021-03-08 2021-03-22 2021-03-27 2021-04-05 2021-05-05 Implementation Guidelines of SDF for RELI Learning Selection Project Page 7