Restructuring Status: Archived Restructuring Type: Level two Last modified on date : 12/21/2012 1. Basic Information Project ID & Name P096801: ELECT DISTRIB REHAB Country Turkey Task Team Leader Yesim Akcollu Sector Manager/Director Ranjit J. Lamech Country Director Martin Raiser Original Board Approval Date 04/19/2007 Original Closing Date: 12/31/2012 Current Closing Date 12/31/2012 Proposed Closing Date [if applicable] EA Category B-Partial Assessment Revised EA Category B-Partial Assessment-Partial Assessment EA Completion Date 07/13/2006 Revised EA Completion Date 2. Revised Financing Plan (US$m) Source Original Revised BORR 75.00 75.00 IBRD 269.40 269.40 Total 344.40 344.40 3. Borrower Organization Department Location TURKIYE ELEKTRIK Turkey DAGITIM AS (TEDAS) 4. Implementing Agency Organization Department Location TURKIYE ELEKTRIK DAGITIM Turkey AS (TEDAS) i 5. Disbursement Estimates (US$m) Actual amount disbursed as of 12/26/2012 115.30 Fiscal Year Annual Cumulative 2012 12.00 127.30 2013 10.00 137.30 Total 137.30 6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N Does the restructured projects trigger any new safeguard policies? If yes, please select N from the checklist below and update ISDS accordingly before submitting the package. 7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes To help improve the reliability of power supply to consumers in Turkey by supporting the implementation of the electricity distribution network rehabilitation and expansion program. 7b. Revised Project Development Objectives/Outcomes [if applicable] ii