MINISTRY OF AGRICULTURE, IRRIGATION AND WATER DEVELOPMENT MALAWI SHIRE RIVER BASIN MANAGEMENT PROJECT - P117617 1st STEP ANNUAL PROCUREMENT PLAN BASED ON THE FEBRUARY 2017 SUPERVISORY MISSION AND AVAILABLE BUDGET SIMPLIFIED (THRESHOLD) PROCUREMENT PLAN FOR THE SHIRE RIVER BASIN MANAGEMENT PROGRAM (PHSE 1) PROJECT (SRBMP) A. General Information 1 Project Information (i) Country Malawi (ii) Project Name Shire River Basin Management Project (iii) Credit No. 51250 (iv) Grant No H 775 (v) Project ID P117617 (vi) Implementation Agency Ministry of Agriculture, Irrigation and Water Development 2 Bank’s approval Date of the 5 Year Procurement June 2012 Plan 3 Bank’s approval Date of 1ST Revised 5 Year 19 March 2013 Procurement Plan 4 Date of General Procurement Notice 29th February 2012 5 Date of General Procurement Notice 1st Revision 24 March 2013 6 Period Covered by this Procurement Plan April 2017 – March 2018 7 Versions of Applicable Procurement Guidelines For Goods and Works Governed by IDA’s Guidelines for Procurement of Goods, Works, and Non- Consulting Services Under IBRD Loans and IDA Credits & Grants by World Bank Borrowers published January 2011 Governed by IDA’s Guidelines for Selection and For Consultant’s Services Employment of Consultant Under IBRD Loans and IDA Credits & Grants by World Bank Borrowers published January 2011 Community Participation Procurement will be Community Driven Procurement Activities carried out as defined in the Project Appraisal Document (PAD), Project Implementation Plan (PIP) and the SRBMP CPP Guidelines B. Works, Goods and Consultant’s Services with Thresholds for Prior Review 1. Prior Review threshold: Procurement Decisions subject to Prior Review by the Bank will be as follows: No Procurement Method Prior Review Threshold Comments (USD) (i). ICB and LIB (Goods) 1,000,000.00 and above All Contracts (ii) NCB (Goods and Non-Consulting 200,000.00 and below First Contract only Services) 1,000,000.00 Page 1 of 9 No Procurement Method Prior Review Threshold Comments (USD) (iii) ICB (Works) 5,000,000.00 and above All Contracts (iv) NCB (Works) 200,000 00.00and below First Contract only 5, 000,000.00 (v) Direct Contracting All Values All Contracts (vi) Force Account All Values All Contracts (vii) Shopping (Goods and Non- Below 200,000.00 None Consulting Services) (viii) Shopping (Works) Below 200,000.00 None (ix) Community Participation (a) Local Bidding Below 10,000.00 None (b) Local Shopping Below 3,000.00 None (c ) Direct contracting All Values All Contracts 2. Prequalification None 3. Proposed Procedures for CDD Components. As per paragraph. 3.17 of the Guidelines and supported project procurement guidelines and project implementation plans. 4. Training and Workshop programmes and plans will be submitted separately for prior review and no objection by the Bank. 5. Reference to (if any) Project Operational/Procurement Manual Project Implementation Plan and Fiduciary Management manual for CPP 6. Any Other Special Procurement Arrangements: None C: Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: No Selection Method Prior Review Threshold Comment (i) Competitive Methods Above USD200,000.00 All Contracts (Firms) (ii) Single Source All Values All Contracts (iii) Individual Consultants Above USD100,000.00 All Contracts 2. Short list comprising entirely of national consultants Short list of consultants for services, estimated to cost less than $200,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements Page 2 of 9 Not applicable D.Procurement Packages with Methods and Time Schedule Page 3 of 9 1. GOODS: – SHIRE RIVER PLANNING Page 4 of 9 1 2 3 4 5 6 7 8 9 10 11 Package Contract Description Source Proc. Estimated Procurement Prequalifi Domestic Review by Expected Bid Comments No. of Funds Unit Cost in US$ Method cation Preference Bank Opening Date (Yes/No) (Yes/No) (Prior/Post) 1 Supply and delivery of IDA SRBMP 100,000.00 NCB No No Post 7 February 2017 Bids Evaluated and BER Field Equipment including Secretaria awaiting next IPC early flood warning t meeting to get approval. Equipment like Delivery expected before megaphones, bicycles, end of April 2017 dinghy boats, etc for use in the Flood areas of Chikwawa and Nsanje 2 Framework Arrangement IDA SRBMP 250,000.00 NCB No No Post March 2017 Bids Evaluated and BER for motor vehicle and Secretaria awaiting next IPC motor cycle tyres and t meeting to get approval. tubes for the SRBMP Contract signing Fleet expected before end of April 2017 HOWEVER delivery of items will be within one week BASED UPON ACTUAL REQUEST/ NEED and budget 3 Framework Arrangement IDA SRBMP 100,000.00 NCB No No Post March 2017 Bids Evaluated and BER for common stationery Secretaria awaiting next IPC and toners used by project t meeting to get approval. during implementation Contract signing expected before end of April 2017 HOWEVER delivery of items will be within one week BASED UPON ACTUAL REQUEST/ NEED and budget Sub-Total Goods 450,000.00 Page 5 of 9 2. WORKS 1 2 3 4 5 6 7 8 9 10 11 Package Contract Description Source of Proc. Unit Estimated Cost Procure Prequalifica Domestic Review by Expected Bid Comments No. Funds in USD $ ment tion Preferenc Bank Opening Method (Yes/No) e (Yes/No) (Prior/Post) Date 1 Construction Works IDA SRBMP NCB No No Post 10 February Bids opened and Package 1 under Flood Secretariat 2017 evaluated; BER awaiting Risk Management next IPC meeting for Package 1 review and approval. Contracts expected to be signed before end of April 1,300,000.00 2017 2 Contraction of Lengwe IDA SRBMP NCB No No Post 10 March Bids opened; evaluation Nation Parks Secretariat 2017 scheduled for week Infrastructure beginning 10 April 2017. Because of financial constraint, only the conference room and ranger camps will be 500,000.00 considered for award Sub-Total ALL Works 1,800,000.00 Page 6 of 9 3. CONSULTANCY SERVICES - SHIRE RIVER PLANNING Page 7 of 9 1 2 3 4 5 6 7 8 9 Consultancy Description of Source Procuring Unit Estimated Selection Review by Expected Proposal Comments No. Assignment of Funds Cost in US $ Method Bank Submission Date (Prior/Post) 1 Engage Chief IDA SRBMP Secretariat 144,000 IC Post March 2017 Executive Officer for NWRA 2 Contract renewal for IDA SRBMP Secretariat 232,000.00 IC Post June-Oct 2017 From June next 12 months for 2017 SRBMP Secretariat staff (3 Procurement Specialists, 2 Financial Management Specialists, 1 Communication Specialist, 1 Liaison Officer and 1 Assistant Accountant based at Lengwe National Parks) 3 Phase 2 Feasibility IDA SRBMP Secretariat 500,000.00 SSS Prior May 2017 ToRs being Study: Rehabilitation developed/ of Mpira Balaka for refined for water supply and submission to various smaller WB for no multipurpose dams objection to be identified later Sub-Total Consultancy Services 966,000.00 Page 8 of 9 4. TRAINING AND WORKSHOPS The strategic Training Plan will be submitted separately later Page 9 of 9 PROCUREMENT Malawi : Malawi: Shire River Basin Management Program (Phase-I) Project PLAN General Information Country: Malawi Banks Approval Date of the Original Procurement Plan: 2017-04-05 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-08-08 Project ID: P117617 GPN Date: Project Name: Malawi: Shire River Basin Management Program (Phase-I) Project Loan / Credit No: IDA / 51250, IDA / Q7630, IDA / H7750 Executing Agency(ies): Shire River Basin Management Program WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-SRBMP-44855-CW-RFQ / Civil Works for the Construction Request for Single Stage - One Under IDA / 51250 SHIRE BASIN PLANNING Post Limited 0.00 2018-01-27 2018-02-14 2018-03-24 2018-05-23 of an Access Road to the Shire Quotations Envelope Implementation River Basin Agency Offices MW-SRBMP-18373-CW-RFB / WATER-RELATED Single Stage - One Civil Works for the Upgraded IDA / 51250 Prior Request for Bids Open - International 0.00 Canceled 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-10-31 INFRASTRUCTURE Envelope Kamuzu Barrage at Liwonde MW-SRBMP-18263-CW-RFB / IDA / 51250 Single Stage - One Construction of Infrastructures in IDA / Q7630 CATCHMENT MANAGEMENT Post Request for Bids Open - National 0.00 Canceled 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2017-06-30 2017-12-27 Envelope Lengwe National Park IDA / H7750 MW-SRBMP-45013-CW-RFB / WATER-RELATED Single Stage - One Pending Civil Works for the Upgraded IDA / 51250 Prior Request for Bids Open - International 0.00 2018-01-22 2018-01-22 2018-01-22 2018-01-25 2018-02-08 2018-05-31 INFRASTRUCTURE Envelope Implementation Kamuzu Barrage at Liwonde MW-SRBMP-45056-CW-RFB / Single Stage - One Pending Construction of Infrastructures in IDA / 51250 CATCHMENT MANAGEMENT Post Request for Bids Open - National 0.00 2018-02-04 2018-02-07 2018-03-09 2018-03-19 2018-04-02 2018-05-13 Envelope Implementation Lengwe National Park MW-SRBMP-67744-CW-RFQ / Construction of a Water Tank at Request for Single Stage - One Pending the National Water Resources IDA / 51250 SHIRE BASIN PLANNING Post Limited 0.00 2018-06-28 2018-07-26 2018-08-25 Quotations Envelope Implementation Authority Offices in Area 47 Lilongwe GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 021/IPC/SRB/16/07F/06G / IDA / 51250 Supply and Delivery of 27 Push Request for Single Stage - One Pending IDA / Q7630 CATCHMENT MANAGEMENT Post Limited 0.00 2017-04-12 2017-05-12 2017-06-02 Bicycles for PICs in Chingale and Quotations Envelope Implementation IDA / H7750 Kapichila Catchments 021/IPC/SB/17/04/01 / Supply, Delivery and Installation of IDA / 51250 Request for Single Stage - One Pending Fridges (2) and Air Conditioners IDA / Q7630 SHIRE BASIN PLANNING Post Limited 0.00 2017-04-21 2017-05-25 2017-06-24 Quotations Envelope Implementation (10) to the SRBA Offices in Area IDA / H7750 47 021/IPC/SB/17/04/02 / Supply, IDA / 51250 Delivery and Installation of 1 Request for Single Stage - One Pending IDA / Q7630 SHIRE BASIN PLANNING Post Limited 0.00 2017-04-21 2017-05-25 2017-06-24 Projector to the SRBA Offices in Quotations Envelope Implementation IDA / H7750 Area 47 IDA / 51250 021/IPC/SB/17/04/03 / Supply Request for Single Stage - One Pending IDA / Q7630 SHIRE BASIN PLANNING Post Limited 0.00 2017-04-21 2017-05-25 2017-06-24 and Delivery of Hardware Items Quotations Envelope Implementation IDA / H7750 021/IPC/SB/17/04/04 / Supply and Delivery of Protective Wear IDA / 51250 Request for Single Stage - One Pending (Working Suits, Leather Gloves IDA / Q7630 SHIRE BASIN PLANNING Post Limited 0.00 2017-04-21 2017-05-25 2017-06-24 Quotations Envelope Implementation and Gum Boots (37 per set) for IDA / H7750 Gauge Readers MW-SRBMP-18243-GO-RFQ / IDA / 51250 Procurement of stationery and Request for Single Stage - One Pending IDA / Q7630 SHIRE BASIN PLANNING Post Limited 0.00 2017-06-16 2017-07-05 2017-07-19 toner (item types not included in Quotations Envelope Implementation IDA / H7750 current framework agreement) MW-SRBMP-18374-GO-RFB / IDA / 51250 Supply and Installation of Single Stage - One IDA / Q7630 SHIRE BASIN PLANNING Prior Request for Bids Limited 1,785,813.86 Signed 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-11-04 2017-06-17 2016-05-25 2017-07-31 Hydromet Equipment and Envelope IDA / H7750 Ancillary Works MW-SRBMP-19674-GO-RFQ / Supply and delivery of IT IDA / 51250 Request for Single Stage - One Pending equipment for SRBMP (2nd IDA / Q7630 SHIRE BASIN PLANNING Post Limited 0.00 2017-07-24 2017-09-18 2017-10-18 Quotations Envelope Implementation Batch), National Spatial Data IDA / H7750 Centre, ODSS and Hydromet MW-SRBMP-19677-GO-RFQ / IDA / 51250 Request for Single Stage - One Pending Supply and Delivery of 2018 IDA / Q7630 SHIRE BASIN PLANNING Post Limited 0.00 2017-09-11 2017-11-06 2017-12-21 Quotations Envelope Implementation Diaries and Calendars IDA / H7750 MW-SRBMP-27202-GO-RFQ / IDA / 51250 Request for Single Stage - One Pending Supply and Delivery of a Server IDA / Q7630 SHIRE BASIN PLANNING Post Limited 0.00 2017-09-22 2017-10-16 2017-10-30 Quotations Envelope Implementation to the Department of Surveys IDA / H7750 MW-SRBMP-19682-GO-RFB / IDA / 51250 Framework Agreement Supply Single Stage - One IDA / Q7630 SHIRE BASIN PLANNING Post Request for Bids Open - National 0.00 Canceled 2017-10-06 2017-10-11 2017-11-22 2017-12-22 2018-01-26 2018-07-25 and Delivery of Common Envelope IDA / H7750 Stationery and Toners Page 1 MW-SRBMP-36324-GO-RFQ / IDA / 51250 Request for Single Stage - One Pending Supply and Delivery of Laptop IDA / Q7630 SHIRE BASIN PLANNING Post Limited 0.00 2017-11-15 2017-12-23 2018-01-22 Quotations Envelope Implementation Computers IDA / H7750 MW-SRBMP-36335-GO-RFQ / IDA / 51250 Request for Single Stage - One Pending Supply and Delivery of a Heavy IDA / Q7630 SHIRE BASIN PLANNING Post Limited 0.00 2017-11-18 2017-12-16 2018-01-15 Quotations Envelope Implementation Duty UPS IDA / H7750 MW-SRBMP-44854-GO-RFQ / Request for Single Stage - One Pending Printing and Delivery of Shire IDA / 51250 SHIRE BASIN PLANNING Post Limited 0.00 2018-01-23 2018-02-20 2018-03-22 Quotations Envelope Implementation River Basin Plans MW-SRBMP-44856-GO-RFB / Framework Agreement Supply Single Stage - One Pending IDA / 51250 SHIRE BASIN PLANNING Post Request for Bids Open - National 0.00 2018-01-23 2018-01-28 2018-03-11 2018-04-10 2018-05-15 2018-10-12 and Delivery of Common Envelope Implementation Stationery and Toners MW-SRBMP-19678-GO-RFB / Framework Agreement for Supply IDA / 51250 Single Stage - One and Fitting of Motor Vehicle IDA / Q7630 SHIRE BASIN PLANNING Post Request for Bids Open - National 0.00 Canceled 2017-10-06 2017-10-11 2017-11-22 2017-12-22 2018-01-26 2018-07-25 Envelope Tyres and Tubes for SRBMP IDA / H7750 Fleet MW-SRBMP-19680-GO-RFB / Framework Agreement for Supply IDA / 51250 Single Stage - One and Fitting of Motor Vehicle and IDA / Q7630 SHIRE BASIN PLANNING Post Request for Bids Open - National 0.00 Canceled 2017-10-06 2017-10-11 2017-11-22 2017-12-22 2018-01-26 2018-07-25 Envelope Motorcycle Tyres and Tubes for IDA / H7750 the SRBMP Fleet MW-SRBMP-18331-GO-RFB / Supply and Installation of Jib WATER-RELATED Single Stage - One IDA / 51250 Prior Request for Bids Open - International 0.00 Canceled 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-11-20 Crane for the Upgraded Kamuzu INFRASTRUCTURE Envelope Barrage MW-SRBMP-18332-GO-RFB / Supply and Installation of Gates WATER-RELATED Single Stage - One IDA / 51250 Prior Request for Bids Open - International 0.00 Canceled 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-08-15 and Weed Boom for the INFRASTRUCTURE Envelope Upgraded Kamuzu Barrage MW-SRBMP-45052-GO-RFB / Framework Agreement for Supply Single Stage - One Pending and Fitting of Motor Vehicle IDA / 51250 SHIRE BASIN PLANNING Post Request for Bids Open - National 0.00 2018-01-22 2018-01-25 2018-02-08 2018-02-22 2018-03-08 2018-08-05 Envelope Implementation Tyres and Tubes for SRBMP Fleet MW-SRBMP-45011-GO-RFB / Framework Agreement for Supply Single Stage - One Pending and Fitting of Motor Vehicle and IDA / 51250 SHIRE BASIN PLANNING Post Request for Bids Open - National 0.00 2018-01-22 2018-01-27 2018-02-26 2018-03-13 2018-04-17 2018-10-14 Envelope Implementation Motorcycle Tyres and Tubes for the SRBMP Fleet MW-SRBMP-53336-GO-RFQ / Request for Single Stage - One Pending IDA / 51250 SHIRE BASIN PLANNING Post Limited 0.00 2018-03-13 2018-04-10 2018-05-01 Supply and Delivery of Stationery Quotations Envelope Implementation MW-SRBMP-53337-GO-RFQ / Request for Single Stage - One Pending Supply and delivery of a Lawn IDA / 51250 SHIRE BASIN PLANNING Post Limited 0.00 2018-03-13 2018-04-13 2018-05-13 Quotations Envelope Implementation Mower MW-SRBMP-53339-GO-RFQ / Request for Single Stage - One Pending Supply and Delivery of Antivirus IDA / 51250 SHIRE BASIN PLANNING Post Limited 0.00 2018-03-13 2018-04-10 2018-05-10 Quotations Envelope Implementation Licences for 2018 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-SRBMP-53491-NC-RFQ / Request for Single Stage - One Pending Web hosting for the Domain IDA / 51250 CATCHMENT MANAGEMENT Post Limited 0.00 2018-03-17 2018-04-21 2018-10-18 Quotations Envelope Implementation Forestry.shirebasin.mw MW-SRBMP-53641-NC-RFQ / Request for Single Stage - One Pending Local Broker for ODSS Cloud IDA / 51250 SHIRE BASIN PLANNING Post Limited 0.00 2018-03-17 2018-04-21 2018-10-18 Quotations Envelope Implementation Service Provider MW-SRBMP-57432-NC-DIR / Non Consulting Services for Under Provision of the Tom2Pro IDA / 51250 SHIRE BASIN PLANNING Prior Direct Selection Direct 0.00 2018-04-10 2018-05-15 2018-04-15 2018-05-16 2018-05-09 2018-11-05 Implementation Software Maintenance and Technical Support MW-SRBMP-68132-NC-DIR / Non Consultancy Services for Hydrological Data Management Pending IDA / 51250 SHIRE BASIN PLANNING Prior Direct Selection Direct 0.00 2018-08-10 2018-08-14 2018-09-02 2019-01-31 Information System (HYDSTRA) Implementation Software Maintenance and Technical Support CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-SRBMP-18293-CS-QCBS / IDA / 51250 Consultancy Services for Quality And Cost- IDA / Q7630 SHIRE BASIN PLANNING Prior Open - International 3,859,835.00 Signed 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2017-09-25 2017-06-16 2017-09-26 2018-01-31 Consolidated Monitoring and Based Selection IDA / H7750 Evaluation IDA / 51250 MW-SRBMP-18298-CS-QCBS / Quality And Cost- Pending IDA / Q7630 SHIRE BASIN PLANNING Prior Open - International 0.00 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2018-01-31 Hydromet Consultancy Based Selection Implementation IDA / H7750 Page 2 MW-SRBMP-18300-CS-QCBS / Implementation Service Provider IDA / 51250 Quality And Cost- Pending Catchment Management Upper IDA / Q7630 CATCHMENT MANAGEMENT Prior Open - International 0.00 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2018-01-31 Based Selection Implementation Lisungwi and Upper IDA / H7750 Wamkulumadzi MW-SRBMP-18303-CS-QCBS / IDA / 51250 Implementation Service Provider Quality And Cost- Pending IDA / Q7630 CATCHMENT MANAGEMENT Prior Open - International 0.00 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2017-06-16 2018-01-31 Catchment Management in Based Selection Implementation IDA / H7750 Kapichira and Chingale IDA / 51250 MW-SRBMP-18305-CS-QCBS / Quality And Cost- IDA / Q7630 SHIRE BASIN PLANNING Prior Open - International 4,049,753.50 Signed 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-12-29 2017-06-17 2014-04-11 2018-01-31 ODSS Consultancy Based Selection IDA / H7750 MW-SRBMP-18306-CS-QCBS / Architectural Design and IDA / 51250 Quality And Cost- Construction Supervision for the IDA / Q7630 SHIRE BASIN PLANNING Prior Open - International 367,504.57 Signed 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-11-24 2017-06-17 2015-03-20 2017-12-31 Based Selection Shire River Basin Agency Offices IDA / H7750 in Blantyre MW-SRBMP-18309-CS-QCBS / IDA / 51250 WATER-RELATED Quality And Cost- Implementation Service Provider IDA / Q7630 Prior Open - International 3,884,914.91 Signed 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2018-01-23 2017-06-17 2014-05-12 2018-01-31 INFRASTRUCTURE Based Selection Flood Risk Management IDA / H7750 MW-SRBMP-18318-CS-QCBS / Consultancy Services to IDA / 51250 Strengthen Information Base of Quality And Cost- Pending IDA / Q7630 CATCHMENT MANAGEMENT Prior Open - International 0.00 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2018-01-31 Natural Habitats, Biodiversity and Based Selection Implementation IDA / H7750 Environmental Services in the Shire Basin MW-SRBMP-18320-CS-QCBS / IDA / 51250 Consultancy Services to Conduct Quality And Cost- IDA / Q7630 CATCHMENT MANAGEMENT Prior Open - International 219,660.75 Signed 2017-06-17 2017-07-14 2017-06-17 2017-07-24 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-07-28 2017-06-17 2017-07-28 2017-07-31 Study to Enhance the Potential Based Selection IDA / H7750 of Nature Based Tourism MW-SRBMP-18322-CS-QCBS / Construction Supervision for the WATER-RELATED Quality And Cost- IDA / 51250 Prior Open - International 10,622,106.27 Signed 2017-06-17 2017-07-14 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-09-03 2017-06-17 2017-09-18 2018-01-31 Upgraded Kamuzu Barrage at INFRASTRUCTURE Based Selection Liwonde MW-SRBMP-18326-CS-QCBS / Consultancy Services for Climate IDA / 51250 Resilience, Livelihoods and Quality And Cost- Pending IDA / Q7630 CATCHMENT MANAGEMENT Prior Open - International 0.00 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-06-17 2017-12-31 Sustainable Natural Resources Based Selection Implementation IDA / H7750 Management in the Elephant Marshes INDIVIDUAL CONSULTANTS Page 3