The World Bank                                                                                                                                               Report No: ISR15954


                                                                                                   Implementation Status & Results
                                                                                                            Haiti
                                                                        Cultural Heritage Preservation and Tourism Sector Support Project (P144614)
Public Disclosure Copy




                         Operation Name: Cultural Heritage Preservation and Tourism Sector Support          Project Stage:   Implementation         Seq.No: 1      Status: ARCHIVED     Archive Date:   27-Aug-2014
                                          Project (P144614)
                                                                              Country: Haiti                                         Approval FY:        2014
                         Product Line: IBRD/IDA                               Region: LATIN AMERICA AND CARIBBEAN                    Lending Instrument: Investment Project Financing
                         Implementing Agency(ies): UNITE TECHNIQUE D'EXECUTION

                         Key Dates
                         Board Approval Date      19-May-2014         Original Closing Date 31-Aug-2020            Planned Mid Term Review Date                            Last Archived ISR Date
                         Effectiveness Date                           Revised Closing Date 31-Aug-2020             Actual Mid Term Review Date

                         Project Development Objectives
                         Project Development Objective (from Project Appraisal Document)

                         The objectives of the Project are to: (a) increase the attractiveness of the cultural heritage sites in North of Haiti for tourists; (b) improve the living environment for the
                         residents living in North of Haiti; and (c) support the Recipient’s capacity to respond promptly and effectively to an Eligible Emergency, as needed.
                         Has the Project Development Objective been changed since Board Approval of the Project?

                            Yes           No

                         Component(s)
                         Component Name                                                                                                          Component Cost
                         Physical Cultural Heritages sites and Touristic Circuits in the PNH-CSSR and Cap-Haitien Historic                                 28.00
                         Center
                         Local Investments in Milot, Dondon and Cap-Haitien                                                                                 7.00
                         Inclusive Tourism Sector Development Support                                                                                       4.00
                         Contingency Emergency Response                                                                                                     1.00
Public Disclosure Copy




                         Project Implementation, Monitoring and Evaluation                                                                                  5.00

                         Overall Ratings
                                                                  Previous Rating                       Current Rating
                         Progress towards achievement of PDO                                            Satisfactory
                         Overall Implementation Progress (IP)                                           Satisfactory
                         Overall Risk Rating                                                            High

                         Implementation Status Overview


                                                                                                                                                                                                          Page 1 of 4
                             The World Bank                                                                                                                                      Report No: ISR15954



                         The project has been approved on May 19 and signed on July 7, 2004 with an estimated effectiveness date by October 7, 2014. In the mean time, under a Project Preparation
                         Advance, the Project teams including the dedicated ISPAN-PAST team are carrying preparatory activities to define the first set of rehabilitation works in the National History Park and
                         in the historic center of Cap Haitien. Communal Concertation Tables have been established to define investments programs in Dondon, Milot and Cap Haitien and bidding processes
                         for technical assistance activities for the tourism sector organizations will be launched end of August.
Public Disclosure Copy




                         Locations
                         No Location data has been entered

                         Results
                         Project Development Objective Indicators
                         Indicator Name                                      Core Unit of Measure                 Baseline                        Current                         End Target
                         Rehabilitated CH building resistant to a 8.5              Percentage         Value       0.00                                                            80.00
                         magnitude seismic event                                                      Date        01-Sep-2014                                                     31-Aug-2020
                                                                                                      Comments
                         An effective Park Management system is                    Text               Value       None                                                            Yes
                         contributing to sustainable development of the                               Date
                         park
                                                                                                      Comments
                         Population in project areas satisfied with the            Percentage         Value       0.00                                                            75.00
                         quality of infrastructure financed by the project                            Date        01-Sep-2014                                                     31-Aug-2020
                                                                                                      Comments
                         Tickets sold annually to the PNH-CSSR                     Number             Value       12500.00                                                        16750.00
                                                                                                      Date        01-Sep-2014                                                     31-Aug-2020
                                                                                                      Comments                                                                    Increase of 34%.
                         of which are sold to RCCL visitors                        Number             Value       0.00                                                            4400.00
                                                                                   Sub Type           Date        01-Sep-2014                                                     31-Aug-2020
                                                                                   Breakdown          Comments
                         Number of entities providing cultural and                 Number             Value       310.00                                                          340.00
Public Disclosure Copy




                         tourism services in the project areas                                        Date        01-Sep-2014                                                     31-Aug-2020
                                                                                                      Comments                                                                    tbd at effectiveness
                         Direct project beneficiaries                              Number             Value       0.00                                                            35000.00
                                                                                                      Date        01-Sep-2014                                                     31-Aug-2020
                                                                                                      Comments
                         Female beneficiaries                                      Percentage         Value       0.00                                                            40.00




                                                                                                                                                                                                     Page 2 of 4
                             The World Bank                                                                                                                           Report No: ISR15954



                                                                                  Sub Type
                                                                                  Supplemental
Public Disclosure Copy




                         Intermediate Results Indicators
                         Indicator Name                                    Core Unit of Measure                  Baseline               Current                       End Target
                         Heritage Sites restored enhanced and open to             Square Meter(m2)    Value      0.00                                                 29800.00
                         public                                                                       Date
                                                                                                      Comments
                         Streetscapes upgraded in project target areas            Meter(m)            Value      0.00                                                 300.00
                                                                                                      Date       01-Sep-2014                                          31-Aug-2020
                                                                                                      Comments
                         PNH Management Plan (i) finalized and (ii)               Yes/No              Value      No                                                   Yes
                         under implementation                                                         Date       01-Sep-2014                                          31-Aug-2020
                                                                                                      Comments
                         Infrastructure properly operated and                     Amount(USD)         Value      0.00                                                 5000000.00
                         maintained following project financing                                       Date       01-Sep-2014                                          31-Aug-2020
                                                                                                      Comments
                         Touristic routes developed and promoted                  Number              Value      0.00                                                 5.00
                         through project investments/activities                                       Date       01-Sep-2014                                          31-Aug-2020
                                                                                                      Comments
                         Activities supported by the Community Event &            Number              Value      0.00                                                 100.00
                         Tourism Development Grants                                                   Date       01-Sep-2014                                          31-Aug-2020
                                                                                                      Comments
                         Of which are women                                       Percentage          Value      0.00                                                 40.00
                                                                                  Sub Type
                                                                                  Supplemental
Public Disclosure Copy




                         Of which are youth                                       Percentage          Value      0.00                                                 25.00
                                                                                  Sub Type
                                                                                  Supplemental


                         Data on Financial Performance (as of 18-Jul-2014)
                         Financial Agreement(s) Key Dates
                         Project               Ln/Cr/Tf                  Status              Approval Date         Signing Date   Effectiveness Date   Original Closing Date   Revised Closing Date
                         P144614               IDA-H9440                 Not Effective       19-May-2014           09-Jul-2014                         31-Aug-2020             31-Aug-2020



                                                                                                                                                                                        Page 3 of 4
                             The World Bank                                                                                                                                          Report No: ISR15954


                         Disbursements (in Millions)
                         Project               Ln/Cr/Tf                Status              Currency       Original           Revised           Cancelled          Disbursed           Undisbursed      % Disbursed
                         P144614               IDA-H9440               Not Effective       XDR                       29.10             29.10               0.00               0.00             29.10          0.00
Public Disclosure Copy




                         Disbursement Graph




                         Key Decisions Regarding Implementation
                         The launching workshop of the project will be organized early October 2014 once the project is effective and the Project Steering Committee in place

                         Restructuring History
                         There has been no restructuring to date.
Public Disclosure Copy




                         Related Projects
                         There are no related projects.




                                                                                                                                                                                                       Page 4 of 4