Page 1 i Restructuring Status: Archived Restructuring Type: Level two Last modified on date : 12/23/2010 1. Basic Information Project ID & Name P071157: GH Land Administration (FY04) Country Ghana Task Team Leader Charles Annor-Frempong Sector Manager/Director Karen Mcconnell Brooks Country Director Ishac Diwan Original Board Approval Date 07/31/2003 Original Closing Date: 12/31/2008 Current Closing Date 12/31/2010 Proposed Closing Date [if applicable] 06/30/2011 EA Category B-Partial Assessment Revised EA Category B-Partial Assessment-Partial Assessment EA Completion Date 09/27/2002 Revised EA Completion Date 2. Revised Financing Plan (US$m) Source Original Revised BORR 7.56 7.56 CIDA 1.03 1.03 DFID 9.02 9.02 GTZ 3.98 3.98 IDA 20.51 20.51 KFW 6.03 6.03 NDF 6.92 6.92 Total 55.05 55.05 3. Borrower Organization Department Location Republic of Ghana Ghana 4. Implementing Agency Organization Department Location Ministry of Lands and Natural Resources Ghana 58683 v2 Page 2 ii 5. Disbursement Estimates (US$m) Actual amount disbursed as of 12/27/2010 20.84 Fiscal Year Annual Cumulative 2010 0.00 20.84 2011 0.00 20.84 Total 20.84 6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N Does the restructured projects trigger any new safeguard policies? If yes, please select from the checklist below and update ISDS accordingly before submitting the package. N 7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes To undertake land policy and institutional reforms and key land administration pilots for laying the foundation for sustainable decentralized land administration system that is fair, efficient, cost effective and ensures land tenure security 7b. Revised Project Development Objectives/Outcomes [if applicable]