The World Bank                                                                                                                                                  Report No: ISR15973


                                                                                                    Implementation Status & Results
                                                                                                                Africa
                                                                                     East Africa Trade and Transport Facilitation Project (P079734)
Public Disclosure Copy




                         Operation Name: East Africa Trade and Transport Facilitation Project                 Project Stage:   Implementation         Seq.No: 18      Status: ARCHIVED      Archive Date:    04-Oct-2014
                                           (P079734)
                                                                               Country: Africa                                         Approval FY:        2006
                         Product Line: IBRD/IDA                                Region: AFRICA                                          Lending Instrument: Specific Investment Loan
                         Implementing Agency(ies): Ministry of Infrastructure Development, Ministry of Transport and Infrastructure, Ministry of Works and Transport, SUMATRA

                         Key Dates
                         Board Approval Date      24-Jan-2006            Original Closing Date 30-Sep-2011            Planned Mid Term Review Date 08-Dec-2008                  Last Archived ISR Date 06-Mar-2014
                         Effectiveness Date       05-Jun-2006            Revised Closing Date 30-Sep-2014             Actual Mid Term Review Date      08-Dec-2008

                         Project Development Objectives
                         Project Development Objective (from Project Appraisal Document)

                         Project Development Objective (PDO): is to (i) enhance efficiency of customs agencies' clearance processes, for the EAC Partner States participating in the East Africa
                         Customs Union, to facilitate trade; (ii) improve efficiency and reliability of transport and logistics services along the key corridors; and (iii) enhance safety in identified
                         areas and reduce the Recipient#s fiscal transfers to railway institutions by rationalizing the work force on the Kenya-Uganda railway.
                         Has the Project Development Objective been changed since Board Approval of the Project?

                            Yes           No

                         Component(s)
                         Component Name                                                                                                             Component Cost
                         Support to implement EAC Custom Union                                                                                                15.80
                         Institutional support for transport facilitation                                                                                     10.40
                         Investment support for transport facilitation                                                                                        98.60
                         Support to the Concession of the Railways                                                                                            74.20
Public Disclosure Copy




                         Support to implement EAC Custom Union                                                                                                15.80
                         Institutional support for transport facilitation                                                                                     10.40
                         Investment support for transport facilitation                                                                                        98.60
                         Support to the Concession of the Railways                                                                                            74.20

                         Overall Ratings
                                                                   Previous Rating                        Current Rating
                         Progress towards achievement of PDO       Moderately Satisfactory                Moderately Satisfactory
                         Overall Implementation Progress (IP)      Moderately Unsatisfactory              Moderately Unsatisfactory


                                                                                                                                                                                                               Page 1 of 7
                             The World Bank                                                                                                                                        Report No: ISR15973



                                                               Previous Rating                           Current Rating
                         Overall Risk Rating                   Substantial                               Moderate
Public Disclosure Copy




                         Implementation Status Overview
                         1. This ISR focuses on the project's implementation progress in the period Jan to June 2014. The main objective has been to complete the implementation of key activities and to
                         monitor key indicators of trade facilitation. The team has worked closely with Implementing Agencies in all four participating countries with good results. Though substantial progress
                         has been made with outstanding operational issues resolved, it has been found necessary to extend the closing date of the project by one year to September 2015 to provide time to
                         finalize some delayed activities and operationalize common facilities such as border posts through ICT.

                         2. Training and installation of the Integrated Border Management system (IBM) for the One Stop Border Posts (OSBP) has commenced and will be rolled out progressively in the
                         coming 6 months. Installation of weighbridges in Tanzania and Uganda has progressed well and is planned for completion by November 2014. Rehabilitation of the Kenya-Uganda
                         railway line and provision of rolling stock, started in 2012, continues with first batch of 20 reconditioned wagons due for delivery and track monitoring equipment received and
                         deployed. The equipment should help in rail maintenance and consequent reduction of accidents leading to cut down on downtime which should result in increased freight volumes.
                         RVR is up to date in remitting concession fee to the governments of Uganda and Kenya. On the security front, training for the port of Dar es Salaam is finalized but the Integrated
                         Security System (ISS) will be implemented through another Development Partner (DP) while the Mombasa ISS is fully operational. The implementation of the railway Relocation
                         Action Plan (RAP) in Kenya has progressed well with first relocation planned for September 2014. The construction of the Katuna OSBP on the Uganda side of Uganda/Rwanda
                         border has commenced while the construction of Gatuna OSBP on the Rwanda side is likely to start soon, with scaled down infrastructure, which takes into account likely diversion of
                         traffic to Kagitumba border once the ongoing OSBP developments there are completed. Finally, the task team and Implementing Agencies (IA) are actively working with concerned
                         authorities to expedite progress where possible.


                         Locations
                         Country                                                 First Administrative Division               Location                                    Planned              Actual
                         Rwanda                                                  Not Entered                                 Republic of Rwanda

                         Tanzania                                                Not Entered                                 United Republic of Tanzania

                         Tanzania                                                Pwani                                       Kibaha

                         Tanzania                                                Shinyanga Region                            Isaka

                         Tanzania                                                Dar es Salaam Region                        Dar es Salaam

                         Kenya                                                   Coast Province                              Taveta
Public Disclosure Copy




                         Kenya                                                   Rift Valley Province                        Namanga

                         Kenya                                                   Coast Province                              Mombasa

                         Kenya                                                   Coast Province                              Mariakani

                         Kenya                                                   Western Province                            Malaba

                         Kenya                                                   Coast Province                              Lunga-Lunga

                         Kenya                                                   Nairobi Area                                Kibera



                                                                                                                                                                                                       Page 2 of 7
                             The World Bank                                                                                                                                        Report No: ISR15973



                         Country                                              First Administrative Division                    Location                                  Planned                Actual
                         Kenya                                                Not Entered                                      Republic of Kenya
Public Disclosure Copy




                         Kenya                                                Nyanza Province                                  Isebania Sub-Location

                         Kenya                                                Western Province                                 Busia

                         Kenya                                                Eastern                                          Athi River

                         Rwanda                                               Not Entered                                      Rusumo Falls

                         Rwanda                                               Kigali City                                      Kigali

                         Uganda                                               Not Entered                                      Republic of Uganda

                         Uganda                                               Rakai District                                   Mutukula

                         Uganda                                               Kampala District                                 Kampala

                         Uganda                                               Busia District                                   Busia

                         Uganda                                               Kabale                                           Kabale District

                         Kenya                                                Nairobi Area                                     Mukuru


                         Results
                         Project Development Objective Indicators
                         Indicator Name                                   Core Unit of Measure                      Baseline                        Current                        End Target
                         Variance of transit time through the Northern          Text                     Value      14 days (NC).                   3 days                         2 days (NC).
                         and Central Corridor is significantly reduced.                                  Date       27-Dec-2005                     04-Sep-2014                    30-Sep-2014
                                                                                                         Comments                                   Data to be reconfirmed         Retained from original project.
                                                                                                                                                    through the proposed time
                                                                                                                                                    release study.
Public Disclosure Copy




                         Rwanda meets the technical requirements to             Text                     Value      Application made                Full member                    Full member
                         become a member of the EAC CU by end of                                         Date       01-Dec-2005                     04-Sep-2014                    30-Sep-2014
                         project
                                                                                                         Comments                                   Project supports the RRA       Project supports the RRA
                         Seamless Cargo tracking is operatinal on the           Text                     Value      No Cargo tracking               Achieved. Operational in KE    Cargo tracking operational in
                         Northern Corridor                                                                                                          and UG                         at least 2 countries on the NC.
                                                                                                         Date       01-Dec-2005                     04-Sep-2014                    30-Sep-2014
                                                                                                         Comments                                   Uganda has installed the ECT
                                                                                                                                                    and Rwanda has awarded the




                                                                                                                                                                                                         Page 3 of 7
                             The World Bank                                                                                                                   Report No: ISR15973



                                                                                                                            installation contract. KE's has
                                                                                                                            resumed.
                         Kenya Railways Pension Scheme (KRPS) set          Text     Value      Non existent                 KRPS already set up and        Fully operatinal and
                         up and is financially sustainable                                                                  operational with challenges in Sustainable with known
Public Disclosure Copy




                                                                                                                            respect of the management of sources of revenue.
                                                                                                                            assets.
                                                                                    Date       01-Dec-2005                  04-Sep-2014                       30-Sep-2014
                                                                                    Comments                                Some members have
                                                                                                                            challenged the rationale of
                                                                                                                            sale of prime assets.
                         Safety railway operation zones established in     Text     Value      Non existant                 Good progress made in         Safety zone established. Mv
                         Kibera and Mukuru areas, Wagon Ferry                                                               establishing safety railway   Kaawa operational
                         services resume in Uganda                                                                          operation zones in Kibera and
                                                                                                                            Mukuru areas. MV Kaawa
                                                                                                                            operational
                                                                                    Date       01-Dec-2005                  04-Sep-2014                       30-Sep-2014
                                                                                    Comments   RAP works contracts that will MV Kaawa operational             MV Kaawa operational
                                                                                               help establish the safety zone
                                                                                               likely to commence by Jan
                                                                                               2012.
                         Transit time along the NC (Mombas to Kigali) is   Number   Value      19.00                        6.00                              5.00
                         reduced.                                                   Date       01-Dec-2005                  04-Sep-2014                       30-Sep-2014
                                                                                    Comments   Core indicator of transit    There is good progress on
                                                                                               facilitation                 this target.
                         Dwell time for standard 2 TEU container           Text     Value      Mombasa 13 days; Dar 18      Mombasa 5 days. Dar 9 days Mombasa 4days; Dar 8 days
                         domestic cargo reduced                                                days
                                                                                    Date       01-Dec-2005                  04-Sep-2014                       30-Sep-2014
                                                                                    Comments   Original 2005 data           Currently-- Mombasa 5 days.
                                                                                                                            Dar 9 days

                         Intermediate Results Indicators
Public Disclosure Copy




                                                                                                                                                                              Page 4 of 7
                             The World Bank                                                                                                                             Report No: ISR15973



                         Indicator Name                                 Core Unit of Measure              Baseline                    Current                           End Target
                         Regional Customs Systems Interconnection             Text             Value      Interconnection not         The IBM is being tested          Substantial regional
                         functions in all 4 participating countries                                       operational                 waiting progressive rolling out. interconnection amongst
Public Disclosure Copy




                                                                                                                                                                       participating EAC countries
                                                                                               Date       01-Dec-2005                 04-Sep-2014                       30-Sep-2014
                                                                                               Comments   Rudimentary connections     The EATTF project provides
                                                                                                                                      equipment to facilitate
                                                                                                                                      interconnection however with
                                                                                                                                      KE and TZ installing new
                                                                                                                                      Customs systems progress
                                                                                                                                      may be interrupted.
                         Customs procedures and documents are                 Text             Value      Complex documentation       Ongoing simplification to be      Simplified documents as
                         simplified in accordance with WCO standards.                                                                 assessed as part of the time      adjudged by WCO consultant
                                                                                                                                      release study
                                                                                               Date       02-Jan-2006                 04-Sep-2014                       30-Sep-2014
                                                                                               Comments                               HOS Initiative has helped the
                                                                                                                                      simplification process.
                         Corridor Authorities (NCTTCA and CCTTFA)             Text             Value      None                        Transit traffic monitoring data   Fully operational Data base
                         set a transit traffic monitoring data base                                                                   base set up for both CC and
                                                                                                                                      NC
                                                                                               Date       23-Jun-2011                 04-Sep-2014                       30-Sep-2014
                                                                                               Comments   Non                         Review of data to be carried
                                                                                                                                      out. MOT in Kenya is also
                                                                                                                                      setting up a transport Data
                                                                                                                                      Center
                         NSW establised in Kenya and CBS ESW at the           Text             Value      None existant               Kenya's eSW was               Established systems
                         Dar port                                                                                                     commissioned in Nov 2013.
                                                                                                                                      Tanzania's will be
                                                                                                                                      implemented through another
                                                                                                                                      DP support. Indicator dropeed
                                                                                                                                      in proj restructuring.
Public Disclosure Copy




                                                                                               Date       01-Dec-2005                 04-Sep-2014                       30-Sep-2014
                                                                                               Comments   Rwanda has implemented the Kenya'S ESW was                    Likely to be met but for KE
                                                                                                          ESW                        commissioned in Nov 2013           and RW.
                                                                                                                                     while Tanzania's is at
                                                                                                                                     procurement stage.
                         Decrease in border crossing time (in hours)          Text             Value      Malaba - KE 15; UG 30 hrs   Malaba, Kenya 5hours;             Serare - 5 hours
                                                                                                          Serare/Isebania - No data   Uganda, 6hours                    Gatuna - 2 hours
                                                                                                          Gatuna/Katuna - RW13 hrs
                                                                                                          UG no data
                                                                                               Date       01-Dec-2005                 04-Sep-2014                       30-Sep-2014



                                                                                                                                                                                           Page 5 of 7
                             The World Bank                                                                                                                                               Report No: ISR15973



                                                                                                    Comments       Challenge has been             Data to be updated after time           Achievable once
                                                                                                                   sustainability which should be release study under TMEA.               infrastructure is completed in
                                                                                                                   possible once the concept of                                           November 2014
                                                                                                                   OSBP is fully operational.
Public Disclosure Copy




                         Railway ICD in Uganda built and functional               Text              Value          Non existant                       Due to be completed in Sep/         Operational ICD
                                                                                                                                                      October 2014
                                                                                                    Date           01-Dec-2005                        04-Sep-2014                         30-Sep-2014
                                                                                                    Comments       originally planned to be       Completion and handover of              Important facility for the
                                                                                                                   located in Kamplala station an ICD planned around                      restructured K-U railway.
                                                                                                                   area later found unsuitable    September 2014.
                         Updated RAP is implemented in Kibera and                 Text              Value          Chaotic                            Ongoing with construction of        3km safety zone established
                         Mukuru areas and safety zone created                                                                                         safety and resettlement at          in both Kibera and Mukuru
                                                                                                                                                      halfway complete.
                                                                                                    Date           01-Dec-2005                        04-Sep-2014                         30-Sep-2014
                                                                                                    Comments       Original RAP prepared.             The RAP civil works are 41%         Objective to resettle 9,005
                                                                                                                                                      complete and 1st batch of           households and provide a
                                                                                                                                                      PAPS relocation planned for         safety operating zone for
                                                                                                                                                      September2014.                      railway.


                         Data on Financial Performance (as of 05-Sep-2014)
                         Financial Agreement(s) Key Dates
                         Project              Ln/Cr/Tf                Status             Approval Date                 Signing Date           Effectiveness Date        Original Closing Date      Revised Closing Date
                         P079734              IDA-41470               Effective          24-Jan-2006                   07-Apr-2006            02-Apr-2007               30-Sep-2011                30-Sep-2014
                         P079734              IDA-41480               Effective          24-Jan-2006                   05-Apr-2006            05-Jul-2006               30-Sep-2011                30-Sep-2014
                         P079734              IDA-41490               Effective          24-Jan-2006                   09-Mar-2006            09-Jun-2006               30-Sep-2011                30-Sep-2014
                         P079734              IDA-49770               Effective          23-Jun-2011                   03-Aug-2011            07-Feb-2012               30-Sep-2014                30-Sep-2014
                         P079734              IDA-H2020               Effective          24-Jan-2006                   06-Mar-2006            05-Jun-2006               31-Mar-2011                30-Sep-2014

                         Disbursements (in Millions)
Public Disclosure Copy




                         Project              Ln/Cr/Tf                Status             Currency           Original             Revised           Cancelled          Disbursed            Undisbursed          % Disbursed
                         P079734              IDA-41470               Effective          XDR                             18.20             18.20               0.00               12.09                  6.11         66.00
                         P079734              IDA-41480               Effective          XDR                             83.30             83.30               0.00               67.97              15.33            82.00
                         P079734              IDA-41490               Effective          XDR                             25.50             25.50               0.00               16.49                  9.01         65.00
                         P079734              IDA-49770               Effective          XDR                             18.60             18.60               0.00                8.45              10.15            45.00
                         P079734              IDA-H2020               Effective          XDR                             10.40             10.40               0.00                6.32                  4.08         61.00


                         Disbursement Graph


                                                                                                                                                                                                                Page 6 of 7
                             The World Bank                                                                                                                                     Report No: ISR15973
Public Disclosure Copy




                         Key Decisions Regarding Implementation
                         3. Key developments noted in the past 6 months are; (i) substantial progress in the implementation of the railway RAP in Kenya, ii) acceleration of construction of OSBP (with those
                         for TZ substantially completed and those for KE and UG nearing completion) and commencement of the installation of Integrated Border Management (IBM) systems, (ii)
                         independent overall review of the project's impact and progress towards achieving its PDO and iv) restructuring of the project involving extension of the closing date to provide
                         sufficient time to complete key activities and modification of the Results Framework (captured in this ISR).

                         4. The project continues to make good overall progress with over 90 percent commitments made, over 67 percent disbursement achieved and several development objective targets
                         met and is thus on track to achieve its PDO.

                         Restructuring History
                         There has been no restructuring to date.
Public Disclosure Copy




                         Related Projects
                         P098770-East Africa Trade and Transport Facilitation Project, P121354-East Africa Trade and Transport Facilitation Program (EATTFP) - Additional Financing




                                                                                                                                                                                                   Page 7 of 7