THE WORLD BANK - ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) FOR COVID-19 EMERGENCY RESPONSE PROJECTS




                       REPUBLIC OF CABO VERDE


                 Cabo Verde COVID-19 Emergency
                        Response Project
      Additional Financing on Vaccines (P175807)



                   ENVIRONMENTAL and SOCIAL
                    COMMITMENT PLAN (ESCP)




                                      December 21, 2020




                                                                                                    1|Page
THE WORLD BANK - ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) FOR COVID-19 EMERGENCY RESPONSE PROJECTS




                             ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN

   1. The Republic of Cabo Verde (the Recipient) under the leadership of the Ministry of Health and Social
      Security (MHSS) is implementing a Cabo Verde Covid-19 Emergency Response Project (P173857) (the
      Parent Project), for which it has requested an Additional Financing (AF). The International Development
      Association (the Association) has agreed to provide financing for the Additional Financing.

   2. The Recipient shall implement material measures and actions so that the Project is implemented in
      accordance with the Environmental and Social Standards (ESSs). This Environmental and Social
      Commitment Plan (ESCP) sets out material measures and actions, any specific documents or plans, as well
      as the timing for each of these, including the timeframes of the actions and measures, institutional,
      staffing, training, monitoring and reporting arrangements, grievance management and the environmental
      and social assessments and instruments to be prepared or updated, disclosed, consulted, adopted and
      implemented under the ESCP and the ESSs, all in a manner acceptable to the Association.

   3. Implementation of the material measures and actions set out in this ESCP will be monitored and reported
      to the Association by the Recipient as required by the ESCP and the provisions of the Financing Agreement.

   4. As agreed by the Association and the Recipient, this ESCP may be revised from time to time during Project
      implementation, to reflect adaptive management of Project changes and unforeseen circumstances or in
      response to assessment of Project performance conducted under the ESCP itself. In such circumstances,
      the Recipient will agree to the changes with the Association and will update the ESCP to reflect such
      changes. Agreement on changes to the ESCP will be documented through the exchange of letters signed
      between the Association and the Recipient. The Recipient shall promptly disclose the updated ESCP.

   5. Where Project changes, unforeseen circumstances, or Project performance result in changes to the risks
      and impacts during Project implementation, the Recipient shall provide additional funds, if needed, to
      implement actions and measures to address such risks and impacts.




                                                                                                    2|Page
THE WORLD BANK - ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) FOR COVID-19 EMERGENCY RESPONSE PROJECTS

 MATERIAL MEASURES AND ACTIONS                                                                             TIMEFRAME                 RESPONSIBLE
                                                                                                                                     ENTITY/AUTHORITY
 MONITORING AND REPORTING
  A   REGULAR REPORTING:                                                                         Starting from the Effective date,   Cabo Verde Ministry of
      • Prepare and submit to the Association regular monitoring reports on the                  submit quarterly throughout the     Health and Social Security
            environmental, social, health and safety (ESHS) performance of the Project,          Project implementation period.      (MHSS) and Ministry of
            including but not limited to the implementation of the ESCP, status of preparation                                       Finance (MoF), through
            and implementation of E&S documents required under the ESCP, stakeholder                                                 the                 project
            engagement activities, and functioning of the grievance mechanism(s).                                                    implementation unit - the
                                                                                                                                     Unidade de Gestão de
                                                                                                                                     Projetos Especiais (UGPE).




                                                                                                                                                       3|Page
THE WORLD BANK - ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) FOR COVID-19 EMERGENCY RESPONSE PROJECTS

 MATERIAL MEASURES AND ACTIONS                                                                                 TIMEFRAME                 RESPONSIBLE
                                                                                                                                         ENTITY/AUTHORITY
  B     INCIDENTS AND ACCIDENTS NOTIFICATION
        • Notify the Association of any incident or accident related to the Project which has,      •   Notify the Association within    Contractor/ Supervising
            or is likely to have, a significant adverse impact on the environment, the affected         48 hours after learning of the   Entity notifies
            communities, the public, or the workers, including: contamination of water                  accident      or     incident.   MHSS/UGPE
            resources and soil with hazardous materials due to accident spillages;                      Throughout             project
            occupational accidents that may result in death or severe injury of workers (such           implementation.                  MHSS/UGPE notifies the
            as falls and vehicle accidents); incidents related to GBV, including sexual             •   Subsequently, a report would     Association
            exploitation and abuse and sexual harassment (SEA/SH), as well as child labor or            be provided within a
            any other forms of violence against children.                                               timeframe acceptable to the
                                                                                                                                         MHSS/UGPE shall provide
        • Provide the Association sufficient detail regarding the incident or accident,                 Association, as requested
                                                                                                                                         subsequent report on the
            indicating immediate measures taken, or that are planned to be taken, to address
                                                                                                                                         incident or accident within
            it, and any information provided by any contractor and supervising entity, as
                                                                                                                                         a timeframe acceptable to
            appropriate.
                                                                                                                                         the     Association,     as
        • Subsequently, as per Association’s request, prepare a report on the incident or
                                                                                                                                         requested.
            accident and propose any measures to prevent its recurrence and/or mitigate the
            risk of future such incidents. A report of the incident shall be submitted, detailing
            summary findings of the Root Cause Analysis (RCA).
        • An incident/accident register shall be maintained at all construction sites,
            throughout the works. Documentation of SEA/SH claims will be maintained
            separately and in a secure place that can be locked with very limited access.
        • For SEA/SH-related incidents, the survivor should be referred immediately to
            services following a survivor-centered protocol to be developed as part of the
            Grievance Mechanism (GM), which will be adapted to manage SEA/SH claims
            ethically and confidentially.
        • For SEA/SH incidents, reports to the Association regarding these claims must
            adhere to international norms and best practices regarding the management and
            sharing of survivor data (WHO Ethical and safety recommendations, 2007;
            GBVIMS Best Practices). As such, confidentiality should be ensured for the
            survivor as well as the accused, with no identifying information for either
            provided.




                                                                                                                                                           4|Page
THE WORLD BANK - ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) FOR COVID-19 EMERGENCY RESPONSE PROJECTS

 MATERIAL MEASURES AND ACTIONS                                                                             TIMEFRAME                RESPONSIBLE
                                                                                                                                    ENTITY/AUTHORITY
  C     CONTRACTORS MONTHLY REPORTS                                                             •   Contractors’ monthly reports
        • In case contractors are hired to undertake the works planned as part of the Project       to PIU throughout their         Contractors
           activities or sub-activities, the Recipient, through the PIU, will require such          Contracts.
           contactors to submit monthly monitoring reports to the PIU regarding the ESHS        •   PIU submits the monthly
           performance of the contracted works.                                                     monitoring reports to the
        • The Recipient will submit such monthly reports to the Association upon request.           Association       whenever      MoF/ UGPE
           Any reports by contractors to the Recipient (via the PIU) regarding individual           requested.
           SEA/SH incidents must follow the above guidance (see Part B). Any reports on the
           functioning of the contractors’ GM, if applicable, should report data on SEA/SH
           incidents in aggregate form only (type of GBV and age/sex of the survivor).
 ESS 1: ASSESSMENT AND MANAGEMENT OF ENVIRONMENTAL AND SOCIAL RISKS AND IMPACTS
  1.1    ORGANIZATIONAL STRUCTURE:                                                              The environmental and social        UGPE
        The Ministry of Health and Social Security (MHSS) has set up a PIU (the UGPE) for the   specialist is already assigned to
        Parent Project (PP) with qualified staff and resources to support management of         the Project and she/he will be
        environmental and social risks and impacts of the Project, including an environmental   maintained throughout Project
        and social specialist (E&S). The E&S will be responsible to manage and supervise the    implementation.
        environmental and social risks and impacts of the AF as well.




                                                                                                                                                   5|Page
THE WORLD BANK - ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) FOR COVID-19 EMERGENCY RESPONSE PROJECTS

 MATERIAL MEASURES AND ACTIONS                                                                                    TIMEFRAME                 RESPONSIBLE
                                                                                                                                            ENTITY/AUTHORITY
  1.2   ENVIRONMENTAL AND SOCIAL ASSESSMENT/MANAGEMENT PLANS AND INSTRUMENTS                           a. The PP ESMF, LMP and GBV          UGPE
           a. Assess the environmental and social risks and impacts of proposed Project                   AP shall be updated and
           activities in accordance with the ESSs, the Environmental, Health and Safety                   disclosed by Effectiveness
           Guidelines (EHSGs), the Parent Project (PP) ESMF, LMP and GBV/SEA/SH Action                    and implemented throughout
           Plan (GBV AP) to be updated, disclosed, adopted, and implemented, and other                    Project implementation.
           relevant Good International Industry Practice (GIIP), including relevant WHO                b. Plans/instruments shall be
           guidelines.                                                                                    prepared,            disclosed,
           b. Prepare, disclose, consult, adopt and implement any environmental and social                consulted      and      adopted
           management plans, e.g. Medical Waste Management Plans (MWMPs),                                 before the carrying out of the
           instruments or other measures required for the respective Project activities based             relevant Project activities,
           on the assessment process, in accordance with the ESSs, the ESMF, the EHSGs, and               and thereafter implemented
           other relevant Good International Industry Practice (GIIP), including relevant WHO             throughout the carrying out
           guidelines to, inter alia, ensure access to and allocation of Project benefits in a fair,      of such activities.
           equitable and inclusive manner, taking into account the needs of individuals or             c. The relevant ESHS measures
           groups who, because of their particular circumstances, may be disadvantaged or                 shall be incorporated into the
           vulnerable , including, as relevant, with regards to COVID-19 Vaccines.                        procurement         documents
           c. Incorporate the relevant aspects of this ESCP, including, inter alia, the ESMF,             before      launching       the
           any environmental and social management plans, MWMPs and/or other                              procurement process for the
           instruments, ESS2 requirements, and any other required ESHS measures, into the                 relevant Project activities and
           ESHS specifications of the procurement documents and contracts with contractors                shall thereafter complied
           and supervising firms. Thereafter, ensure that the contractors and supervising                 with throughout the carrying
           firms comply with the ESHS specifications of their respective contracts.                       out of such activities.
           d. Adopt procedures, protocols and/or other measures to ensure voluntary                    d. Before the carrying out of the
           consent of Project beneficiaries receiving COVID-19 Vaccines under the Project.                relevant Project activities,
                                                                                                          and thereafter implemented
                                                                                                          throughout the carrying out
                                                                                                          of such activities.




                                                                                                                                                           6|Page
THE WORLD BANK - ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) FOR COVID-19 EMERGENCY RESPONSE PROJECTS

 MATERIAL MEASURES AND ACTIONS                                                                             TIMEFRAME                  RESPONSIBLE
                                                                                                                                      ENTITY/AUTHORITY
  1.3   CONTRACTORS:                                                                            •   The relevant ESHS measures        Contractors and UGPE for
        •   Construction-Environmental and Social Management Plans (C-ESMP) and                     shall be incorporated into the    the monitoring part
            Occupational Health and Safety Management Plans (OHSMP) must include                    procurement         documents
            provisions to address COVID-19 risk as well as to address the Project SEA/SH-           before      launching       the
            related risks ethically and adequately. These plans need to include Code of             procurement process for the
            Conduct (CoC) that specifically prohibit SEA/SH and include applicable sanctions.       relevant Project activities and
        •   Incorporate the relevant aspects of this ESCP, including, inter alia, any               shall thereafter complied
            environmental and social management plans or other instruments, ESS2                    with throughout the carrying
            requirements, and any other required ESHS measures, into the ESHS                       out of such activities.
            specifications of the procurement documents and contracts with contractors and      •   Before the carrying out of the
            supervising firms. Thereafter, ensure that the contractors and supervising firms        relevant Project activities,
            comply with the ESHS specifications of their respective contracts.                      and thereafter implemented
        •   Contractors shall reflect the requirements stated in the GBV AP in their C-ESMP.        throughout the carrying out
            The procurement documents shall set out clearly how adequate SEA/SH related             of such activities.
            costs will be paid for in the Contract.




                                                                                                                                                      7|Page
THE WORLD BANK - ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) FOR COVID-19 EMERGENCY RESPONSE PROJECTS

 MATERIAL MEASURES AND ACTIONS                                                                   TIMEFRAME                       RESPONSIBLE ENTITY/AUTHORITY
  1.3  EXCLUSIONS:                                                              These exclusions shall be applied as part of     UGPE
         Exclude the following type of activities as ineligible for financing   the assessment process conducted under
         under the Project:                                                     action 1.2.a. above.
         • Activities that may cause long term, permanent and/or
             irreversible (e.g., loss of major natural habitat) adverse
             impacts
         • Activities that have high probability of causing serious adverse
             effects to human health and/or the environment
         • Activities that may have significant adverse social impacts and
             may give rise to significant social conflict
         • Activities that may affect lands or rights of any vulnerable
             communities,
         • Activities that may involve permanent involuntary
             resettlement, including physical and/or economical
             displacement, and/or land acquisition, and/or adverse impacts
             on cultural heritage
         • All other excluded activities set out in the ESMF of the Project.
 ESS 2: LABOR AND WORKING CONDITIONS
  2.1     LABOR MANAGEMENT:                                                     •   The Project shall be carried out in          UGPE
          • The Project shall be carried out in accordance with the                 accordance      with    the     applicable
             applicable requirements of ESS2, in a manner acceptable to             requirements of ESS2 throughout Project
             the Association, including through, inter alia, implementing           implementation.
             adequate occupational health and safety measures (including        •   The PP LMP shall be updated and
             emergency preparedness and response measures), setting out             disclosed by Effectiveness . The LMP shall
             grievance mechanisms (GM) for Project workers, and                     be implemented throughout Project
             incorporating labor requirements into the ESHS specifications          implementation.
             of the procurement documents and contracts with contractors        •   The GM for Project workers shall be
             and supervising firms.                                                 operational by the Effective Date and
         •   Update, disclose, adopt, and implement the Parent Project              prior to engaging Project workers and
             (PP) Labor Management Procedures (LMP) in a manner                     start of any activities. GM maintained
             acceptable to the Association.                                         throughout Project implementation.
 ESS 3: RESOURCE EFFICIENCY AND POLLUTION PREVENTION AND MANAGEMENT



                                                                                                                                                      8|Page
THE WORLD BANK - ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) FOR COVID-19 EMERGENCY RESPONSE PROJECTS

 MATERIAL MEASURES AND ACTIONS                                                                    TIMEFRAME                        RESPONSIBLE ENTITY/AUTHORITY
         Relevant aspects of this standard shall be considered, as needed,       •   Plans/instruments shall be prepared,          UGPE
         under action 1.2 above, including, inter alia, measures to: carry out       disclosed, consulted and adopted before
         the purchase, storage, transportation and handling of vaccines              the carrying out of the relevant Project
         (including, ultra-cold chain management) in a safe manner and in            activities, and thereafter implemented
         accordance with the EHSGs, and other relevant GIIP including                throughout the carrying out of such
         relevant WHO guidelines; and adequately manage and dispose of               activities.
         health care wastes (including, vaccines) in the MWMPs, , and other      •   The relevant ESHS measures shall be
         types of hazardous and non-hazardous wastes.                                incorporated into the procurement
                                                                                     documents before launching the
                                                                                     procurement process for the relevant
                                                                                     Project activities and shall thereafter
                                                                                     complied with throughout the carrying
                                                                                     out of such activities.
 ESS 4: COMMUNITY HEALTH AND SAFETY
         •   Relevant aspects of this standard shall be considered, as           •   All measures shall be included in the ESMF    UGPE
             needed, under action 1.2 above including, inter alia, measures          and adopted before the commencement
             to: minimize the potential for community exposure to                    of any Project activities and shall remain
             communicable diseases; ensure that individuals or groups                operational      throughout         Project
             who, because of their particular circumstances, may be                  implementation.
             disadvantaged or vulnerable, have access to the development
             benefits resulting from the Project; manage the risks of the
             potential use of security personnel; manage the risks of labor
             influx; and prevent and respond to sexual exploitation and
             abuse, and sexual harassment.
         •   GBV/SEA/SH mitigation measures shall be implemented to
             address identified SEA/SH risks per the GBV AP/s. The
             Recipient shall recruit GBV services providers to facilitate
             access to timely, safe and confidential services for survivors
             (including       providing funding for transportation,
             documentation fees, and lodging if needed).




                                                                                                                                                        9|Page
THE WORLD BANK - ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) FOR COVID-19 EMERGENCY RESPONSE PROJECTS

  4.2    USE OF MILITARY OR SECURITY FORCES: The following measures               a) Assessment carried out in the same          UGPE
         shall be adopted, to ensure that the engagement of [security or          timeframe than action 1.2 (a) above and [any
         military] personnel [in the implementation of Project activities]        required measures shall be adopted before
         [for provision of security to Project workers, sites and/or assets],     deploying [security or military] personnel
         is carried out in accordance with the ESSs:                              under the Project and thereafter
         • Assess the risks and impacts of engagement of the [security or         implemented throughout Project
              military] personnel, as part of the assessment referred to in       implementation] or [a stand-alone Security
              action 1.2 (a) above, and implement measures to manage such         Management Plan shall be prepared and
              risks and impacts, [including a stand-alone Security                adopted before deploying [security or
              Management Plan], guided by the principles of proportionality       military] personnel under the Project and
              and GIIP, and by applicable law, in relation to hiring, rules of    thereafter implemented throughout Project
              conduct, training, equipping, and monitoring of such [security      implementation].
              or military] personnel;
         • Adopt and enforce standards, protocols and codes of conduct            b), c) and d) before deploying [security or
              for the selection and use of [security or military] personnel,      military] personnel under the Project and
              and screen such personnel to verify that they have not              thereafter throughout Project
              engaged in past unlawful or abusive behavior, including sexual      implementation.
              exploitation and abuse (SEA), sexual harassment (SH) or
              excessive use of force;                                             e) and f) as set out under actions 10.1 and
         • Ensure that [indicate the responsible entity, e.g. Project             10.2, respectively.
              implementing entity] enters into a memorandum of
              understanding (MoU), with the [line ministry in control of
              military or security forces] [and] [relevant Security or Military
              Unit], setting out the arrangements for the engagement of the
              [military or security personnel] under the Project, including
              compliance with the relevant requirements of this ESCP;]
         • Ensure that such personnel is adequately instructed and
              trained, prior to deployment and on a regular basis, on the use
              of force and appropriate conduct (including in relation to
              civilian-military engagement, SEA and SH, and other relevant
              areas), as set out in the [Project Implementation Manual],
              [ESMF], [Security Management Plan], [MoU];
         • Ensure that the stakeholder engagement activities under the
              Stakeholder Engagement Plan (SEP) include a communication
              strategy on the involvement of [security or military] personnel
              under the Project;
                                                                                                                                        10 | P a g e
THE WORLD BANK - ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) FOR COVID-19 EMERGENCY RESPONSE PROJECTS

 MATERIAL MEASURES AND ACTIONS                                                                  TIMEFRAME                       RESPONSIBLE ENTITY/AUTHORITY
         •   Ensure that any concerns or grievances regarding the conduct
             of [security or military] personnel are received, monitored,
             documented (taking into account the need to protect
             confidentiality),resolved through the Project’s grievance
             mechanism (see action 10.2 below) and reported to the
             [Bank/Association] no later than 48 hours after being received.




 ESS 5: LAND ACQUISITION, RESTRICTIONS ON LAND USE AND INVOLUNTARY RESETTLEMENT
 5.1      Not currently relevant. No land acquisition, restrictions on land use or involuntary resettlement in the proposed project. Small rehabilitation works of
         existing health facilities will be conducted within existing government facilities/grounds and no new land will be acquired or accessed.
 ESS 6: BIODIVERSITY CONSERVATION AND SUSTAINABLE MANAGEMENT OF LIVING NATURAL RESOURCES
         Not currently relevant.

 ESS 7: INDIGENOUS PEOPLES/SUB-SAHARAN AFRICAN HISTORICALLY UNDERSERVED TRADITIONAL LOCAL COMMUNITIES
         Not relevant, as there are no IP/SSAHUTLCs in Cabo Verde.

 ESS 8: CULTURAL HERITAGE
         Not currently relevant.

 ESS 9: FINANCIAL INTERMEDIARIES
         Not relevant.

 ESS 10: STAKEHOLDER ENGAGEMENT AND INFORMATION DISCLOSURE
 10.1     STAKEHOLDER ENGAGEMENT PLAN:                                         The PP SEP shall be updated and disclosed        UGPE
         Update, disclose, adopt, and implement the parent project (PP)        before Appraisal. The SEP shall be
         Stakeholder Engagement Plan (SEP) consistent with ESS10, which        implemented       throughout      Project
         shall include measures to, inter alia, provide stakeholders with      implementation.
         timely, relevant, understandable and accessible information, and
         consult with them in a culturally appropriate manner, which is
         free of manipulation, interference, coercion, discrimination and
         intimidation.

                                                                                                                                                       11 | P a g e
THE WORLD BANK - ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) FOR COVID-19 EMERGENCY RESPONSE PROJECTS

 MATERIAL MEASURES AND ACTIONS                                                               TIMEFRAME                       RESPONSIBLE ENTITY/AUTHORITY
 10.2  GRIEVANCE MECHANISM:                                                                                                  UGPE
         •   Ensure that the PP’s grievance mechanism (GM) is maintained,    The grievance arrangements of the PP shall be
             equipped and adapted to address SEA/SH-allegations ethically    equipped and adapted to address
             and confidentially and integrate an appropriate response        GBV/SEA/SH-allegations       before      the
             protocol for such claims.                                       commencement of any Project activities and
         •   Accessible GBV/SEA/SH-sensitive grievance arrangements          shall remain operational throughout Project
             shall be made publicly available to receive and facilitate      implementation.
             resolution of concerns and grievances in relation to the
             Project, consistent with ESS10 .
 CAPACITY SUPPORT (TRAINING)
         Training topics for personnel involved in Project implementation    Throughout Project implementation.              UGPE
         will among others include:
              • COVID-19        Infection    Prevention      and   Control
                 Recommendations
              • Laboratory biosafety guidance related to COVID-19
              • Specimen collection and shipment
              • Standard precautions for COVID-19 patients
              • Risk communication and community engagement
              • Management and supervision of the GBV/SEA/SH-
                 sensitive GM
              • Risk of gender-based violence, including the mechanism
                 for submitting GBV/SEA complaints
              • WHO and Africa CDC guidelines on quarantine including
                 case management




                                                                                                                                                 12 | P a g e