PROCUREMENT PLAN (Textual Part) Project information: Republic of Croatia, Integrated Land Administration System Project (P122219) – Additional Financing Project Implementation agency: Ministry of Justice(MoJ) and State Geodetic Administration (SGA) Date of the Procurement Plan: September 2019 Period covered by this Procurement Plan: The life of the Project Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: “Not Applicable” The Procurement and Review Thresholds, applicable to the Project are as indicated in the table below: Thresholds for Procurement Approaches and Methods (€ thousands) Works Goods, IT and non-consulting Shortlist of national services consultants Open Open RfQ Open Open RfQ Consultin Engineering internation national internation national g services and al al construction supervision < < ≤ ≤ ≤ ≤ ≥ ≥ 20,000 20,000 200 2 000 2 000 100 500 N/A Review Arrangements First contract for each approach First contract for each approach First contract for each and method and all > 15 000 and method and all > 3 000 approach and method, all TORs and all contracts > 1 000 Direct Selection all > 80 000 Direct Selection all > 80 000 Individual consultants all TORs and all contracts > 300 Direct Selection all >10 000 PROCUREMENT Croatia : Integrated Land Administration System Project PLAN General Information Country: Croatia Bank’s Approval Date of the Original Procurement Plan: 2019-09-09 2020-02-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P122219 GPN Date: 2019-05-29 Project Name: Integrated Land Administration System Project Loan / Credit No: IBRD / 89000 Executing Agency(ies): Ministry of Justice WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual A1.5 / MOJ - Works on Pending A: Land Registration Single Stage - One adaptation of premises for IBRD / 89000 Post Request for Bids Open - National 0.00 Implementati 2019-12-01 2019-12-06 2020-01-17 2020-02-16 2020-03-22 2021-03-22 System Development Envelope Archive Center (Works) on A5.3 / MOJ - Works on Pending A: Land Registration Single Stage - One adaptation of LRO premises IBRD / 89000 Post Request for Bids Open - National 0.00 Implementati 2019-10-01 2019-10-06 2019-11-05 2019-11-25 2019-12-30 2020-12-29 System Development Envelope in Zagreb (Works) on B2.1 / SGA-Renovation of B: Spatial Information and Pending the Sisak Regional CO Single Stage - One IBRD / 89000 Cadastre System Post Request for Bids Open - National 0.00 Implementati 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2019-09-17 building (Continued works/ Envelope Modernization on Services) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual A1.2 / MOJ - Procurement of HW (mainly large Under A: Land Registration Single Stage - One capacity storage and server) IBRD / 89000 Post Request for Bids Open - National 0.00 Implementati 2019-09-02 2019-09-07 2019-10-19 2019-11-18 2019-12-23 2020-05-31 System Development Envelope and SW for upgrading the on LROs digital archive (Goods) A1.6 / MOJ - Supply of Pending A: Land Registration Single Stage - One furniture and equipment for IBRD / 89000 Post Request for Bids Open - National 0.00 Implementati 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 2021-06-20 System Development Envelope Archive Center (Goods) on A5.4 / MOJ - Supply of Pending furniture and equipment for A: Land Registration Single Stage - One IBRD / 89000 Post Request for Bids Open - National 0.00 Implementati 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 2021-06-20 LRO premises in Zagreb System Development Envelope on (Goods) A6.2 / MOJ - Binding of A: Land Registration Request for Single Stage - One documents and/or Land IBRD / 89000 Post Limited 130,977.23 Signed 2019-09-27 2019-11-22 2021-05-17 System Development Quotations Envelope Books B1.1.1 / SGA-Supply of B: Spatial Information and Request for Single Stage - One furniture SGA Archive IBRD / 89000 Cadastre System Post Limited 74,796.34 Signed 2019-09-07 2019-11-02 2020-01-02 Quotations Envelope System (Goods) Modernization B1.1.2 / SGA-IT equipment B: Spatial Information and Single Stage - One for upgrade of SGA Archive IBRD / 89000 Cadastre System Post Request for Bids Open - National 0.00 Canceled 2019-10-06 2019-10-11 2019-11-22 2019-12-08 2020-01-12 2020-07-10 Envelope System (Goods) Modernization Page 1 B2.4 / SGA-Acquisition and B: Spatial Information and Pending installation of additional Single Stage - One IBRD / 89000 Cadastre System Post Request for Bids Open - National 0.00 Implementati 2020-01-01 2020-01-06 2020-02-17 2020-02-27 2020-04-02 2020-09-29 power supply source for the Envelope Modernization on SGA Data Centre (Goods) B3.1 / SGA-Procurement of B: Spatial Information and Pending hardware and software for Single Stage - One IBRD / 89000 Cadastre System Post Request for Bids Open - National 0.00 Implementati 2019-09-15 2019-09-20 2019-11-01 2019-12-01 2020-01-05 2020-07-03 the CROPOS Control Center Envelope Modernization on at the SGA (Goods) Under A1.1 / MOJ - Procurement A: Land Registration Single Stage - One IBRD / 89000 Post Request for Bids Open - National 0.00 Implementati 2019-09-02 2019-09-17 2019-10-29 2019-12-28 2020-02-01 2020-07-30 of scanner for LRO Offices System Development Envelope on A6.2B / MOJ - Binding of Pending A: Land Registration Request for Single Stage - One documents and/or Land IBRD / 89000 Post Limited 0.00 Implementati 2019-12-20 2020-02-14 2020-08-12 System Development Quotations Envelope Books on B1.1.2. / SGA-IT equipment B: Spatial Information and Pending Request for Single Stage - One for upgrade of SGA Archive IBRD / 89000 Cadastre System Post Limited 0.00 Implementati 2020-02-08 2020-03-18 2020-06-16 Quotations Envelope System (Goods) Modernization on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual A6.1 / MOJ-Additional staff Pending A: Land Registration Single Stage - One for six most underperforming IBRD / 89000 Post Request for Bids Open - National 0.00 Implementati 2019-10-01 2019-10-06 2019-11-17 2019-12-17 2020-01-21 2021-06-30 System Development Envelope LROs on B: Spatial Information and Under B1.2 / SGA-Services of Single Stage - One IBRD / 89000 Cadastre System Post Request for Bids Open - National 0.00 Implementati 2019-09-16 2021-06-30 scanning operators (Services) Envelope Modernization on B2.2 / SGA-Development and implementation of new B: Spatial Information and functionalities of the SGA IBRD / 89000 Cadastre System Post Direct Selection Direct 110,870.43 Signed 2019-09-15 2019-09-15 2019-09-15 2021-06-30 HR-net application with Modernization procurement of necessary licenses (Services) B: Spatial Information and B2.5 / SGA-Consultants to Single Stage - One IBRD / 89000 Cadastre System Post Request for Bids Open - National 519,461.79 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2020-11-05 support cadastral offices Envelope Modernization C1.2 / SGA - Services for conducting pre-public Pending C: Improving Digital Single Stage - One displays in 50 cadastral IBRD / 89000 Prior Request for Bids Open - National 0.00 Implementati 2019-08-31 2019-09-05 2019-10-05 2019-10-20 2019-11-24 2020-11-23 Services Envelope municipalities (Non- on Consultancy Services) C1.1-1 / SGA - Services for conducting cadastral field surveys in 13 cadastral C: Improving Digital Single Stage - One IBRD / 89000 Post Request for Bids Open - National 354,184.96 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-06-15 municipalities (Non- Services Envelope Consultancy) - Lot 1 Garešnica C1.1-2 / SGA - Services for conducting cadastral field surveys in 13 cadastral C: Improving Digital Single Stage - One IBRD / 89000 Post Request for Bids Open - National 896,878.68 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-06-15 municipalities (Non- Services Envelope Consultancy) - Lot 2 - Draganić Page 2 C1.1-3 / SGA - Services for conducting cadastral field surveys in 13 cadastral C: Improving Digital Single Stage - One IBRD / 89000 Post Request for Bids Open - National 276,296.65 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-06-15 municipalities (Non- Services Envelope Consultancy) - Lot 3 - Mala Švarča C1.1-4 / SGA - Services for conducting cadastral field surveys in 13 cadastral C: Improving Digital Single Stage - One IBRD / 89000 Post Request for Bids Open - National 87,016.99 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-06-15 municipalities (Non- Services Envelope Consultancy) - Lot 4 Donja Motičina C1.1-5 / SGA - Services for conducting cadastral field surveys in 13 cadastral C: Improving Digital Single Stage - One IBRD / 89000 Post Request for Bids Open - National 330,552.37 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-06-15 municipalities (Non- Services Envelope Consultancy) - Lot 4 - Mrzović C1.1-6 / SGA - Services for conducting cadastral field surveys in 13 cadastral C: Improving Digital Single Stage - One IBRD / 89000 Post Request for Bids Open - National 259,619.25 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-06-15 municipalities (Non- Services Envelope Consultancy) - Lot 6 - Ivanovci Đakovački C1.1-7 / SGA - Services for conducting cadastral field surveys in 13 cadastral C: Improving Digital Single Stage - One IBRD / 89000 Post Request for Bids Open - National 558,154.60 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-06-15 municipalities (Non- Services Envelope Consultancy) - Lot 7 - Subotica Podravska C1.1-8 / SGA - Services for conducting cadastral field surveys in 13 cadastral C: Improving Digital Single Stage - One IBRD / 89000 Post Request for Bids Open - National 260,483.74 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-06-15 municipalities (Non- Services Envelope Consultancy) - Lot 8 - Gorica C1.1-9 / SGA - Services for conducting cadastral field surveys in 13 cadastral C: Improving Digital Single Stage - One IBRD / 89000 Post Request for Bids Open - National 365,427.59 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-06-15 municipalities (Non- Services Envelope Consultancy) - Lot 9 - Velika Ves C1.1-10 / SGA - Services for conducting cadastral field surveys in 13 cadastral C: Improving Digital Single Stage - One IBRD / 89000 Post Request for Bids Open - National 148,359.33 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-06-15 municipalities (Non- Services Envelope Consultancy) - Lot 10 - Donja i Gornja Pačetina C1.1-11 / SGA - Services for conducting cadastral field surveys in 13 cadastral C: Improving Digital Single Stage - One IBRD / 89000 Post Request for Bids Open - National 167,327.12 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-06-15 municipalities (Non- Services Envelope Consultancy) - Lot 11 - Forkuševci C1.1-12 / SGA - Services for conducting cadastral field surveys in 13 cadastral C: Improving Digital Single Stage - One IBRD / 89000 Post Request for Bids Open - National 539,236.12 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-06-15 municipalities (Non- Services Envelope Consultancy) - Lot 12 - Viduševac Page 3 C1.1-13 / SGA - Services for conducting cadastral field surveys in 13 cadastral C: Improving Digital Single Stage - One IBRD / 89000 Post Request for Bids Open - National 186,848.05 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-06-15 municipalities (Non- Services Envelope Consultancy) - Lot 13 - Dvorišće CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual A1.3 / MOJ - Design of the renovation and equipping of Consultant A: Land Registration the central archive in Gospić IBRD / 89000 Post Qualification Open - National 91,777.23 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2020-03-14 System Development and design supervision Selection (Services) A1.4 / MOJ - Supervision and safety at work services Consultant A: Land Registration Pending for the renovation and IBRD / 89000 Post Qualification Open - National 0.00 2019-10-01 2019-10-22 2019-12-05 2020-01-04 2020-03-23 2021-03-23 System Development Implementation equipping of the central Selection archive (Services) A5.2 / MOJ - Supervision and safety at work services Consultant A: Land Registration Pending services for adaptation and IBRD / 89000 Post Qualification Open - National 0.00 2019-10-01 2019-10-16 2019-11-14 2019-11-29 2019-12-30 2020-12-29 System Development Implementation equipping of LRO premises Selection in Zagreb (Services) B1.3 / SGA-Optimization of B: Spatial Information and Consultant Pending SGA archive system IBRD / 89000 Cadastre System Post Qualification Open - National 0.00 2019-10-20 2019-11-04 2019-12-05 2019-12-27 2020-01-31 2020-04-30 Implementation (Consultancy services) Modernization Selection B2.3 / SGA-Preparation of updated design, Bill of Quantities & Technical B: Spatial Information and Consultant Specifications and Under IBRD / 89000 Cadastre System Post Qualification Open - National 0.00 2019-09-15 2019-09-25 2019-10-21 2019-10-26 2019-11-30 2020-07-27 supervision services for Implementation Modernization Selection additional power supply source for the SGA Data Centre (Services) B4.1 / SGA-Preparation of B: Spatial Information and initial dataset on buildings Least Cost Pending IBRD / 89000 Cadastre System Prior Open - National 0.00 2019-12-02 2019-12-23 2020-02-05 2020-03-04 2020-04-03 2020-05-08 2020-06-12 2021-06-12 from available originals Selection Implementation Modernization (DOP, photos) (Services) B4.2 / SGA- The consultancy services for preparing the technical specifications and documents B: Spatial Information and Consultant Pending for procuring building IBRD / 89000 Cadastre System Post Qualification Open - National 0.00 2019-12-02 2019-12-23 2020-02-05 2020-03-06 2020-04-10 2020-11-06 Implementation register system development Modernization Selection and pilot project implementation at selected locations (Services) B4.4 / SGA - Services to translate utility report data B: Spatial Information and Consultant into standard computer Under IBRD / 89000 Cadastre System Post Qualification Open - National 0.00 2019-09-01 2019-09-08 2019-09-28 2019-10-05 2019-11-09 2020-11-08 format fit for data capture Implementation Modernization Selection in the HR-KI system (Services) B4.5 / SGA - Establishment B: Spatial Information and Consultant of official State maps quality Pending IBRD / 89000 Cadastre System Post Qualification Open - National 0.00 2020-01-02 2020-01-12 2020-02-25 2020-03-26 2020-04-30 2020-12-26 control system (goods, Implementation Modernization Selection services) Page 4 C1.3 / SGA - Harmonization of data in 21 Consultant CMs where land registers C: Improving Digital Pending IBRD / 89000 Post Qualification Open - National 0.00 2019-09-30 2019-10-10 2019-11-08 2019-11-23 2019-12-28 2020-12-27 are kept according to the Services Implementation Selection cadastral data no longer in official use C1.5 / SGA - Services of expert geodetic supervision Consultant for execution of geodetic- C: Improving Digital IBRD / 89000 Post Qualification Open - National 429,171.38 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2020-09-16 cadastre services in purpose Services Selection of producing real estate cadastre registry (Services) C4.1 / IA - Land Consultant C: Improving Digital Under Administration Strategy IBRD / 89000 Prior Qualification Open - National 0.00 2019-09-30 2019-10-21 2019-12-04 2020-01-03 2020-02-07 2020-08-05 Services Implementation development (services) Selection D1.3 / IA - Project audit D: Project Management, Least Cost Pending IBRD / 89000 Post Open - National 0.00 2019-09-15 2019-10-06 2019-11-19 2019-12-17 2020-01-16 2020-02-20 2020-03-26 2020-09-22 services (Services) Training, Public Awareness Selection Implementation D3.1 / IA - Public D: Project Management, Quality Based Pending awareness campaign IBRD / 89000 Prior Open - National 0.00 2019-09-30 2019-10-21 2019-12-04 2020-01-01 2020-01-31 2020-03-01 2020-04-05 2021-04-05 Training, Public Awareness Selection Implementation (Services) D3.2 / IA - User Consultant D: Project Management, Pending satisfaction analysis IBRD / 89000 Post Qualification Open - National 0.00 2020-06-01 2020-06-22 2020-08-05 2020-09-04 2020-10-09 2021-04-07 Training, Public Awareness Implementation (Services) Selection C1.5-1 / SGA - Services of expert geodetic supervision for execution of geodetic- Consultant C: Improving Digital cadastre services in purpose IBRD / 89000 Post Qualification Open - National 0.00 Canceled 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2020-09-16 Services of producing real estate Selection cadastre registry (Services) - Lot 1 C1.5-2 / SGA - Services of expert geodetic supervision for execution of geodetic- Consultant C: Improving Digital cadastre services in purpose IBRD / 89000 Post Qualification Open - National 0.00 Canceled 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2020-09-16 Services of producing real estate Selection cadastre registry (Services) - Lot 2 C1.5-3 / SGA - Services of expert geodetic supervision for execution of geodetic- Consultant C: Improving Digital cadastre services in purpose IBRD / 89000 Post Qualification Open - National 0.00 Canceled 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2020-09-16 Services of producing real estate Selection cadastre registry (Services) - Lot 3 C1.5-4 / SGA - Services of expert geodetic supervision for execution of geodetic- Consultant C: Improving Digital cadastre services in purpose IBRD / 89000 Post Qualification Open - National 0.00 Canceled 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2020-09-16 Services of producing real estate Selection cadastre registry (Services) - Lot 4 C1.5-5 / SGA - Services of expert geodetic supervision for execution of geodetic- Consultant C: Improving Digital cadastre services in purpose IBRD / 89000 Post Qualification Open - National 0.00 Canceled 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2020-09-16 Services of producing real estate Selection cadastre registry (Services) - Lot 5 Page 5 C1.5-6 / SGA - Services of expert geodetic supervision for execution of geodetic- Consultant C: Improving Digital cadastre services in purpose IBRD / 89000 Post Qualification Open - National 0.00 Canceled 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2020-09-16 Services of producing real estate Selection cadastre registry (Services) - Lot 6 C1.5-7 / SGA - Services of expert geodetic supervision for execution of geodetic- Consultant C: Improving Digital cadastre services in purpose IBRD / 89000 Post Qualification Open - National 0.00 Canceled 2019-09-15 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2020-09-16 Services of producing real estate Selection cadastre registry (Services) - Lot 7 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual A5.1 / MOJ - Design services for adaptation and A: Land Registration equipping of LRO premises IBRD / 89000 Post Direct Selection Direct 535,724.16 Signed 2019-09-15 2019-09-15 2019-09-16 2020-11-22 System Development in Zagreb and design supervision (Services) B1.4 / SGA-Implementation B: Spatial Information and Pending of recommendations for SGA IBRD / 89000 Cadastre System Prior Direct Selection Direct 0.00 2020-03-31 2020-04-10 2020-06-14 2020-09-12 Implementation archive system optimization Modernization B: Spatial Information and B4.3 / SGA-Support to the Under IBRD / 89000 Cadastre System Prior Direct Selection Direct 0.00 2019-09-30 2019-10-10 2019-12-14 2020-12-13 spatial unit registry upgrade Implementation Modernization C1.4 / SGA - Support to C: Improving Digital cadastral map IBRD / 89000 Post Direct Selection Direct 111,750.00 Completed 2019-09-15 2019-09-15 2019-09-16 2019-10-01 Services homogenization (Services) C2.1 / IA - Services of developing JIS interoperability with the C: Improving Digital Pending IBRD / 89000 Prior Direct Selection Direct 0.00 2019-09-30 2019-10-25 2019-12-29 2020-06-26 land register renewal and Services Implementation public display application (ICT supply and installation) C2.2 / IA - Further JIS development and upgrade to C: Improving Digital Pending support functional linking of IBRD / 89000 Prior Direct Selection Direct 0.00 2019-09-30 2019-10-25 2019-12-29 2021-06-21 Services Implementation cadastre and land registry services, e-services D1.1.1 / IA - Project Individual D: Project Management, Under manager & Monitoring and IBRD / 89000 Post Consultant Direct 0.00 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-07-15 Training, Public Awareness Implementation Evaluation Specialist Selection Individual D1.1.2 / IA - Financial D: Project Management, Under IBRD / 89000 Post Consultant Direct 0.00 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-07-15 Specialist Training, Public Awareness Implementation Selection Individual D1.1.3 / IA - Procurement D: Project Management, Under IBRD / 89000 Post Consultant Limited 0.00 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-07-15 Specialist Training, Public Awareness Implementation Selection Individual D: Project Management, Pending D1.1.5 / IA - Translator II IBRD / 89000 Post Consultant Direct 0.00 2019-09-04 2019-09-06 2019-09-10 2019-09-13 2021-07-12 Training, Public Awareness Implementation Selection Page 6 Individual D1.1.6 / IA - IT Expert for D: Project Management, Pending IBRD / 89000 Post Consultant Limited 0.00 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-07-15 JIS Support Training, Public Awareness Implementation Selection D1.1.7 / IA - Training & Individual D: Project Management, Monitoring and Evaluation IBRD / 89000 Post Consultant Limited 91,229.04 Signed 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-07-15 Training, Public Awareness Specialist Selection Individual D1.1.9 / IA - Office D: Project Management, Under IBRD / 89000 Prior Consultant Limited 0.00 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-07-15 Assistant Training, Public Awareness Implementation Selection Individual D1.1.8 / IA - Procurement D: Project Management, Pending IBRD / 89000 Prior Consultant Limited 0.00 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-07-15 Consultant Training, Public Awareness Implementation Selection C4.2 / IA - Support to the Individual Land Administration C: Improving Digital Pending IBRD / 89000 Prior Consultant Open 0.00 2020-03-31 2020-05-19 2020-06-09 2020-07-31 2021-01-31 Strategy implementation Services Implementation Selection (Services) Individual D1.1.10 / MOJ - Architect / D: Project Management, IBRD / 89000 Post Consultant Limited 38,500.48 Signed 2019-09-30 2019-10-05 2019-10-26 2019-11-30 2021-03-31 Civil Engineer Training, Public Awareness Selection Individual D: Project Management, Under D1.1.4 / IA -Translator I IBRD / 89000 Post Consultant Direct 0.00 2019-09-15 2019-09-15 2019-09-15 2019-09-16 2021-07-15 Training, Public Awareness Implementation Selection D2.1 / SGA - Providing of Training Services to build D: Project Management, Under the capacity of judges, court IBRD / 89000 Post Direct Selection Direct 0.00 2019-12-20 2019-12-27 2020-03-01 2021-06-15 Training, Public Awareness Implementation clerks and LR clerks on effective use of JIS D2.3.1 / IA - Providing of Training Services to Support Land Registry and Cadastre Clerks in Effective Using The Joint Information D: Project Management, Pending System (JIS) Module for IBRD / 89000 Post Direct Selection Direct 0.00 2020-01-28 2020-02-05 2020-02-15 2021-06-15 Training, Public Awareness Implementation Performing Procedures of Sporadic Land Registry and Cadastral Data Transformation in the Land Database (LDB) Page 7