INTERNATIONALBANK FOR WORLD BANK R E T C N O E N STRUCTION PM AND DEVELO September 2003 No. 30 A regular series of notes highlighting recent lessons emerging from the operational and analytical program of the World Bank`s Latin America and Caribbean Region ECONOMIC ANALYSIS OF URBAN UPGRADING PROJECTS Maria Ang�lica Sotomayor Latin America's urban population jumped from 50 percent in economic prices. Embedded taxes in material and labor 1960 to 75 percent in 2000 (108 and 389 million respec- should be deducted, using conversion factors if available. If tively), making it the most urbanized region in the world. not, the analyst should investigate major input market distor- Municipalities throughout Latin tions, such as unskilled labor and America are struggling to keep up with imported goods in economies with this growth, in difficult economic envi- protectionist policies, and adjust ronments, making sustainable provision market prices to correct for major of basic services a huge challenge. The market distortions. Cash flows (in World Bank is working closely with economic prices) should be dis- national, regional and municipal govern- counted using the country's esti- ments in developing and financing urban mated opportunity cost of capital upgrading projects. This article shares when available (e.g. Peru's Ministry some experiences with different tech- of Finance uses 14 percent); other- niques for estimating economic benefits wise a 12% discount rate is com- and costs used by the Bank in appraising monly used in Bank projects. urban upgrading projects1 . The projects usually combine infrastructure invest- ments and complementary activities to Methodologies for strengthen, build capacity and organize assessing economic communities and government at differ- ent levels to ensure appropriate use of benefits services provided and sustainability. Like costs, economic benefits have to be valued at economic prices. Fi- Assessing economic costs nancial income/revenue generated by the consumption of a good (price times quantity) needs to be adjusted Project economic costs include capital to reflect the "true value" of consumption for the consumer, costs, operation and maintenance costs, rehabilitation, re- or "willingness to pay", represented by the area under the settlement, and costs associated with complementary actions demand curve for any given quantity. This includes the and contingencies. Costs of providing additional infrastruc- actual payment and consumer surplus. In the example, if ture (such as sewerage connections) necessary for users to price is $3, consumers will demand 40 units and pay $120, realize intended benefits, should be included, even if not but are willing to pay $160 (area 0, 5, A, 40). financed by the project. Revealed preferences (for goods and services sold in mar- Net incremental costs and benefits need to be assessed under kets) two scenarios: with, and without the project. They should be adjusted for taxes, subsidies, and externalities, to arrive at When a project provides goods or services sold in markets, such as water and electricity, a demand curve can be derived 1 Mass transport and mobility components should be analyzed separately. 1 and (ii) consumers in the market, Figura 1: Willingness to Pay conscious of the attribute being (Financial Revenue + Consumer Surplus) valued. Multicollinearity is almost always present and 5 important, and affects estimated values. To assess estimate reliability, different functional 4 Consumer forms and different variables Surplus should be analyzed. A market price e 3 Contingent valuation pric Financial Revenue The contingent valuation method 2 (CVM) involves directly asking people, in surveys, how much demand they would be willing to pay for 1 cur specific services, although ve commonly used . Iit is the most controversial non-market method. 0 20 40 60 80 100 It is called "contingent" valuation, because people are asked their Quantity willingness to pay, contingent on a specific hypothetical scenario In the example, if price is $3, consumers will demand 40 units and description of the service. and pay $120, but are willing to pay $160 (area 0, 5, A, 40). Applying CVM is generally complicated, lengthy, and from consumers' revealed preferences observed in the mar- expensive. To collect useful data and provide meaningful ket, and used to calculate willingness to pay. Demand can be results, the CV survey must be properly designed, pre-tested estimated using data from companies or household surveys and implemented. CV survey results are often highly (such as ENCOVI in Guatemala) on income, quantities sensitive to what people believe they are being asked to value, consumed, and associated monetary and non-monetary costs as well as the context described in the survey. This makes it (e.g. time spend fetching water). essential for CV researchers to clearly define the specific service(s) and context, and to demonstrate that respondents understand them and are actually stating their values for these Non-market methods services when answering the valuation questions. For slum upgrading services such as drainage and parks for which market data are non-existent or insufficient, non-direct methods must be used to assess economic benefits. Method Advantages and Disadvantages Contingent valuation and hedonic pricing are commonly used in urban projects, others random utility and travel cost models. Non-market methods involve more difficulties and Hedonic Pricing Model sources of error. � Estimates values from data on actual choices. Data on property sales and characteristics are readily available, Hedonic Pricing and can be related to other data sources to obtain Hedonic pricing is a good method for estimating the descriptive variables. economic benefits of access to improved urban services. Econometric analysis of data from observed transactions in � Property markets are relatively efficient in responding to the housing market yields estimated marginal values for information, so can be good indications of value. particular non-market attributes of interest (such as access to Property records are often reliable. services, distance to center, etc.) embodied in houses and reflected in housing prices. � Only benefits related to housing prices can be measured. Most slum-upgrading interventions do affect housing This method is relatively straightforward and prices, so the method is generally useful. It can only uncontroversial, because it is based on actual market prices capture willingness to pay for perceived differences in and easily measured data. It is relatively inexpensive if data attributes, and their direct consequences. If are readily available. If data must be gathered and compiled, beneficiaries are unaware of linkages between the costs increase substantially. For this method to work attribute and benefits to them or their property, the value effectively: (i) the housing market should function well (it is will not be reflected in home prices. important to discuss results and values with local realtors); 2 � Hedonic pricing assumes that beneficiaries have oppor- pressing value for the good, respondents might be tunities to select their preferred combination of features, expressing feelings about the scenario or the valuation given their incomes. However, the hous- exercise itself. For example, respondents may ing market may be affected by outside state a positive willingness to pay because influences, like taxes, interest rates, etc. they feel good about the act of paying for a social good (the "warm glow" effect), al- � The method is relatively complex to though they may believe that the good itself is implement and interpret, requiring unimportant. Respondents may state a posi- statistical expertise. Results depend tive willingness to pay to signal that improved heavily on model specification. Much environmental quality is important to them. data must be gathered and manipulated. Alternatively, some respondents may value The time and expense of applying the good, but state low willingness to pay, hedonic pricing depend on data because they disapprove of some aspect of the availability and accessibility. scenario, such as increased taxes. Contingent Valuation � Respondents may make associations � Contingent valuation is enormously that the researcher had not intended. For flexible and can be used to estimate the example, if asked for willingness to pay for economic value of virtually anything. It improved visibility (through reduced is best for estimating values for goods pollution), respondents may answer based on and services that are easily identified and health risks that they associate with air understood by users and consumed in pollution. discrete units (e.g., user days of recreation). � Some researchers argue that people make hypothetical and actual decisions in � It requires competent survey analysts to fundamentally different ways. For example, achieve defensible estimates, but results respondents may fail to take questions are easy to analyze and describe. seriously because they will not actually have Monetary values can be presented as to pay the stated amount. Responses may be means or median values per capita or per unrealistically high if respondents believe household, or as aggregate values for they will not have to pay for the good or affected populations. service but their answer may influence future supply. Responses may be unrealistically low � CV has been widely used for two if respondents believe they will have to pay. decades, and considerable research is being conducted to improve the � If respondents are first asked for their methodology, make results more valid willingness to pay for one part of an and reliable, and better understand its environmental asset (e.g. one lake in an entire strengths and limitations. lake system) and then asked to value the whole asset (e.g. the whole lake system), the � Controversy remains over whether it amounts stated may be similar �the adequately measures willingness to pay "embedding effect." Respondents' expressed for environmental quality. CV assumes willingness to pay sometimes depends on that people understand the good in where something is placed on a list of things question and will state contingent being valued �the "ordering problem." preferences just as they would reveal Respondents may give different willingness to them in a real market. However, most pay amounts, depending on the payment people are unfamiliar with placing vehicle chosen. For example, taxes may elicit monetary values on environmental goods protest responses from those who oppose tax and services and may lack an adequate increases. Contributions or donations may basis for stating their true value. CVM is elicit answers that reflect people's sense of difficult to apply in valuing continuous their "fair share", rather than expressing their variables such as water consumed actual value for the good. through a piped system. � Strategic bias arises when the respondent provides an biased answer tailored, to influ- � Answers to willingness to pay questions ence a particular outcome. Information bias may be biased because respondents answer a different may arise when respondents are asked to question than the surveyor intended. Rather than ex- value attributes with which they have little or no experi- 3 Approaches for Analyzing Urban Upgrading Projects Method for estimation of NPV EIRR Project and components economic benefits (US$ 000) (%) The Venezuela-Caracas Slum Upgrading Project is financing basic urban services and infrastructure in two informal settlement areas, including water, sanitation, access, drainage, community centers, public lighting, electricity and resettlement housing. Communities determine their own neighborhood improvement plans. 19,645 a/ Potable Water Contingent Valuation - Sewerage Contingent Valuation 1,863 a/ - Access Travel time and vehicle Principal 9,986 a/ - operating costs Secondary 34,843 a/ Colombia's Bogot� Urban Services Project is providing improved mobility and access through major urban transport investments and water, sanitation and related basic services, particularly for 1.2 million residents in low-income areas. Travel time and vehicle Mobility 122,300 25% operating costs Urban Upgrading: I. Perdomo Hedonic-property values b/ 1,456 19% G. Yomasa 13,624 60% Brazil's Recife Urban Upgrading Project is improving water, sanitation, lighting, transport, land tenure security, macro and micro drainage, offering parks and recreation areas in low income areas in the Beberibe basin. Beberibe basin (indirect Hedonic-property values 12,176 34% impact area) Urban upgrading in low- Hedonic-property values 51,079 38% income areas Resettlement (risk prone Hedonic-property values 2,380 25% areas) Water Revealed preferences 8,238 37% a/ NPV calculated using a 10% discount rate. b/ Economic analysis based on a sample of investments in two areas (I. Perdomo and G. Yomasa). ence; the amount and type of information presented to respondents may affect their answers. ******** � Non-response bias is a concern when sampling respondents, since individuals who do not respond may have, on average, different values than individuals who do respond. Learn More http://www.worldbank.org/urban/ World Bank's recent experience in LAC and about our projects... http://www4.worldbank.org/sprojects/ Given the complexity of urban upgrading projects, and their importance for achieving poverty reduction goals in the About the Author region, efforts have been made by the Bank to integrate Maria Ang�lica Sotomayor is an Economist in the Water & different approaches in analyzing these projects to account Sanitation Cluster of the Finance, Private Sector and Infra- for attributes of goods and services and user attitudes not structure Department in the World Bank's Latin America captured by traditional market methods of valuation. The Caribbean Region. following table summarizes the results of the economic analysis of some of the latest urban upgrading projects Special thanks to Maria Emilia Freire, Urban Regional Advisor, financed by the Bank in the region. The complexity of the Dean Cira, task manager of the Caracas and Recife projects, analysis and the use of appropriate valuation techniques has Thakoor Persaud task manger of the Bogot� project and Vitor evolved and will continue to do so as projects have become Serra, for their valuable inputs and comments. more complex to better respond to new development challenges in the region. In making the decision of what About "en breve" method to use the only rule is to use revealed preferences whenever possible. When revealed preferences are not used, "en breve" appears every two weeks in English and Span- ish (occasionally Portuguese). To subscribe send and email hedonic pricing works well if the project is expected to to "en_breve@worldbank.org" Visit the archive at: increase overall property values, whereas for environmental benefits contingent valuation is better. http://www.worldbank.org/en_breve 4