The World Bank Report No: ISR3164 Implementation Status & Results Papua New Guinea Public Disclosure Copy Rural Communications Project (P107782) Operation Name: Rural Communications Project (P107782) Project Stage: Implementation Seq.No: 1 Status: ARCHIVED Last Modified Date: 04-Aug-2011 Country: Papua New Guinea Approval FY: 2011 Product Line: IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 22-Jul-2010 Original Closing Date 31-Aug-2015 Planned Mid Term Review Date 03-Jun-2013 Last Archived ISR Date 00000000 Effectiveness Date 07-Mar-2011 Revised Closing Date 31-Aug-2015 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Technical Assistance for NICTA 1.00 UAS Demonstration Projects 13.50 Project Management 0.50 Overall Ratings Public Disclosure Copy Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Overall Risk Rating High Implementation Status Overview The project became effective on March 2011 after delays with the subsidiary agreement due to the creation of NICTA, the new National ICT Authority. The PIU is in place in the Department of Communications and Information, and several consultancies are expected to be introduced this FY. However, multiple procurement reviews have been required for some packages, which have caused additional delay. The PIU and the Bank team are working on these issues and look forward to solving all procurement matters shortly. Page 1 of 3 The World Bank Report No: ISR3164 Results Public Disclosure Copy Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Value Date Comments Data on Financial Performance (as of 27-May-2011) Financial Agreement(s) Key Dates Project Loan No. Status Approval Date Signing Date Effectiveness Date Closing Date P107782 IDA-47910 Effective 22-Jul-2010 09-Aug-2010 07-Mar-2011 31-Aug-2015 Disbursements (in Millions) Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P107782 IDA-47910 Effective XDR 10.00 10.00 0.00 0.04 9.96 0.00 Disbursement Graph Public Disclosure Copy Key Decisions Regarding Implementation Page 2 of 3 The World Bank Report No: ISR3164 Due to new challenges in the industry and the recent creation of NICTA, the Government of Papua New Guinea has requested additional regulatory assistance. The task team believes this will rather help achieve the Project's Development Objective, but it is still too early to determine if a reallocation of resources from component 2 to component 1 will be Public Disclosure Copy needed. Restructuring History Related Projects There are no related projects. Public Disclosure Copy Page 3 of 3