Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia-Transport Sector Project in Support of RSDP4 (P117731) Ethiopia-Transport Sector Project in Support of RSDP4 (P117731) AFRICA | Ethiopia | Transport & ICT Global Practice | IBRD/IDA | Specific Investment Loan | FY 2013 | Seq No: 8 | ARCHIVED on 10-Apr-2017 | ISR25822 | Implementing Agencies: Key Dates Key Project Dates Bank Approval Date:25-Sep-2012 Effectiveness Date:25-Jan-2013 Planned Mid Term Review Date:24-Apr-2017 Actual Mid-Term Review Date:-- Original Closing Date:30-Apr-2019 Revised Closing Date:30-Apr-2019 Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed Project Development Objective is to improve the condition of priority regional trade corridors and link roads being upgraded under this project. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Civil Works and Works Supervision:(Cost $336.62 M) Support To Modernize ERA:(Cost $9.00 M) Contingency:(Cost $69.38 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Moderately Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Unsatisfactory Overall Risk Rating  Moderate  High Implementation Status and Key Decisions 4/10/2017 Page 1 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia-Transport Sector Project in Support of RSDP4 (P117731) The project is financing the upgrading of a total of 435km of roads to paved asphalt concrete standard. Three contracts for the Kombolcha-Bati-Mille (two contracts) and Mizan-Dima roads were awarded in September 2013. The contractors are working on site and progress on the two Kombolcha-Bati-Mille contracts has improved, with some asphalt works underway. Progress on the Mizan-Dima road continues to be delayed. Work has started on two further contracts for the upgrading of the Ambo-Woliso and Konso-Yabello roads, and it is expected that the contract for the Debre Birhan - Ankober road will be awarded in the near future. In addition, the project will support ERA's modernisation programme through three technical assistance consultancy contracts: (i) Better Contract and Project Management Practice at ERA, focusing on the enhancement of contract management, project management and safeguards implementation capacity; (ii) Technical Audits and Quality Management, aimed at enhancing ERA’s capacity to undertake technical auditing of the design and delivery process, and (iii) Enhancing road asset management capacity. This will build on previous support for Output Based and Performance based Road Contracting (OPRC) for asset management, by providing Technical Assistance (TA) to develop and supervise an OPRC for road rehabilitation and maintenance on road networks totaling 650km. Support will also be provided to prepare design and feasibility reports of follow-on projects, including Environmental and Social Impact Assessments. 4/10/2017 Page 2 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia-Transport Sector Project in Support of RSDP4 (P117731) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  Moderate  Moderate Macroeconomic  --  Moderate  Moderate Sector Strategies and Policies  --  Moderate  Moderate Technical Design of Project or Program  --  Moderate  Moderate Institutional Capacity for Implementation and Sustainability  --  Moderate  Moderate Fiduciary  --  Moderate  Moderate Environment and Social  --  Substantial  High Stakeholders  --  Low  Substantial Other  --  Substantial  -- Overall  --  Moderate  High Results Project Development Objective Indicators 4/10/2017 Page 3 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia-Transport Sector Project in Support of RSDP4 (P117731) PHINDPDOTBL  Proportion of rural land area within 2km of an all-season road (Rural Access Index) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 17.80 17.80 57.30 40.00 Date 30-Jun-2011 25-Dec-2015 02-Dec-2016 31-Dec-2018 Comments Target met. PHINDPDOTBL  Direct project beneficiaries (Number, Core) Baseline Actual (Previous) Actual (Current) End Target Value 1,943,400.00 1,943,400.00 1,943,400.00 2,325,900.00 Date 01-Jan-2013 05-Jun-2015 02-Dec-2016 31-Dec-2018 PHINDPDOTBL  Female beneficiaries (Percentage, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 50.00 50.00 50.00 50.00 PHINDPDOTBL  Travel Time of Heavy Goods Vehicle on Addis - Mille - Djibouti trade route (Days) (Days, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 6.00 6.00 6.00 5.00 Date 30-Jun-2011 05-Jun-2015 02-Dec-2016 31-Dec-2018 4/10/2017 Page 4 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia-Transport Sector Project in Support of RSDP4 (P117731) PHINDPDOTBL  Average travel time on subject roads at completion compared with pre-construction base-line (km/hr) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 25.00 25.00 25.00 80.00 Date 30-Jun-2011 05-Jun-2015 02-Dec-2016 31-Dec-2018 Overall Comments Intermediate Results Indicators PHINDIRITBL  Roads constructed, non-rural (Kilometers, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 218.70 434.50 Date 30-Jun-2012 05-Jun-2015 02-Dec-2016 31-Dec-2018 PHINDIRITBL  Number of Supervision Contracts awarded (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 5.00 5.00 5.00 Date 30-Jun-2012 05-Jun-2015 02-Dec-2016 30-Jun-2015 Comments Target met 4/10/2017 Page 5 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia-Transport Sector Project in Support of RSDP4 (P117731) PHINDIRITBL  Number of person-days of professional training done under the TA components (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5,000.00 Date 31-Dec-2012 05-Jun-2015 02-Dec-2016 31-Dec-2018 PHINDIRITBL  Percentage of female professionals trained (as a percentage of total people trained) (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 PHINDIRITBL  All construction contracts delivered within 25% of the original estimated time and cost (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 31-Dec-2012 05-Jun-2015 02-Dec-2016 31-Dec-2012 PHINDIRITBL  Concept Design and Bid Documentation for OPRC contract prepared (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 31-Dec-2012 05-Jun-2015 02-Dec-2016 31-Dec-2014 Overall Comments 4/10/2017 Page 6 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia-Transport Sector Project in Support of RSDP4 (P117731) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P117731 IDA-51550 Effective XDR 273.50 273.50 0.00 164.91 108.59 60% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P117731 IDA-51550 Effective 25-Sep-2012 18-Oct-2012 25-Jan-2013 30-Apr-2019 30-Apr-2019 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) 4/10/2017 Page 7 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia-Transport Sector Project in Support of RSDP4 (P117731) There are no related projects. 4/10/2017 Page 8 of 8 Public Disclosure Copy