        The World Bank                                                                          Implementation Status & Results Report
        Ulaanbaatar Clean Air Project (P122320)


Ulaanbaatar Clean Air Project (P122320)

EAST ASIA AND PACIFIC | Mongolia | Energy & Extractives Global Practice |
IBRD/IDA | Investment Project Financing | FY 2012 | Seq No: 11 | ARCHIVED on 20-Dec-2017 | ISR29291 |


Implementing Agencies: Mongolia, UBCAP Project Management Unit




Key Dates

  Key Project Dates

  Bank Approval Date:03-Apr-2012                                             Effectiveness Date:18-Dec-2012
  Planned Mid Term Review Date:19-Jan-2015                                   Actual Mid-Term Review Date:19-Jan-2015
  Original Closing Date:30-Jun-2017                                          Revised Closing Date:30-Jun-2018




Project Development Objectives

 Project Development Objective (from Project Appraisal Document)
 The development objective (PDO) is to enable consumers in ger areas to access heating appliances producinglessparticulatematteremissions and
 to further develop selected medium-term particulate matter abatement measures in Ulaanbaatarincoordinationwithdevelopment partners.

 Has the Project Development Objective been changed since Board Approval of the Project Objective?
 No

 PHRPDODEL



Components

Name
A. Ger Area Particulate Matter Mitigation:(Cost $16.10 M)
B. Central Ulaanbaatar Particulate Matter Mitigation:(Cost $2.30 M)
C. Public Awareness Raising, Program Coordination and Project Management:(Cost $3.00 M)



Overall Ratings
Name                                                                       Previous Rating                      Current Rating

Progress towards achievement of PDO                                         Satisfactory                        Satisfactory
Overall Implementation Progress (IP)                                        Satisfactory                        Satisfactory
Overall Risk Rating                                                         Moderate                            Moderate


Implementation Status and Key Decisions

12/20/2017                                                                                                                       Page 1 of 11
                                                            Public Disclosure Copy
                                                           Public Disclosure Copy

        The World Bank                                                                                Implementation Status & Results Report
        Ulaanbaatar Clean Air Project (P122320)



 Summary of Progress: The project continues to make progress towards achieving the PDO through a range of measures to reduce air pollution,
 facilitate coordination on air pollution abatement, and protect vulnerable groups from high levels of air pollution. The recent restructuring of the project
 has reallocated the remaining funding from the project, including those from the savings from the clean stove program, to the following activities: (i)
 Provision of HEPA filters to an additional 119 kindergartens and hospitals; (ii) Support to local stove and boiler manufacturers for the design and
 production of clean stoves and boilers and pilot distribution to targeted groups; (iii) Support for energy efficiency measures for detached ger houses; (iv)
 Support for energy efficiency measures and/or non-coal solutions in government buildings; (v) Enhanced public awareness program; (vi) Extended
 project support for the PMU (the restructuring has also included a one-year extension of the closing date of the project to June 30, 2018).
 Sustainability: Despite the documented achievements of the Clean Stove Program in lowering average ambient air pollution levels in Ulaanbaatar (UB)
 during winter months during 2013-2015, the government stopped supporting the clean stove program at the end of 2015. Air pollution from ger
 neighborhoods remains particularly acute, accounting for an estimated three-quarters of PM2.5 in UB in the winter. A multi-faceted effort supported by
 the municipal and national government and international donors remains urgently needed to identify and support effective air pollution control options
 together with measures to protect vulnerable groups (children, the elderly) from high air pollution levels.




12/20/2017                                                                                                                                 Page 2 of 11
                                                           Public Disclosure Copy
                                                  Public Disclosure Copy

        The World Bank                                                     Implementation Status & Results Report
        Ulaanbaatar Clean Air Project (P122320)




12/20/2017                                                                                             Page 3 of 11
                                                  Public Disclosure Copy
                                                          Public Disclosure Copy

               The World Bank                                                                      Implementation Status & Results Report
               Ulaanbaatar Clean Air Project (P122320)




Risks

 Systematic Operations Risk-rating Tool

 Risk Category                                             Rating at Approval              Previous Rating            Current Rating

 Political and Governance                                   --                             Substantial               Substantial
 Macroeconomic                                              --                             Moderate                  Moderate
 Sector Strategies and Policies                             --                             Low                       Low
 Technical Design of Project or Program                     --                             Moderate                  Moderate
 Institutional Capacity for Implementation and
 Sustainability
                                                            --                             Moderate                  Moderate
 Fiduciary                                                  --                             Moderate                  Moderate
 Environment and Social                                     --                             Moderate                  Low
 Stakeholders                                               --                             Substantial               Substantial
 Other                                                      --                             --                        --
 Overall                                                    --                             Moderate                  Moderate


Results

 Project Development Objective Indicators
 PHINDPDOTBL




          Coverage of targeted households with eligible services (Percentage, Custom)


                                            Baseline                   Actual (Previous)           Actual (Current)           End Target

         Value                              0.00                       90.00                       90.00                      80.00

         Date                               18-Dec-2012                19-Jan-2017                 19-Jan-2017                31-Dec-2016


 PHINDPDOTBL




      Approval by relevant counterparts of principle recommendations and action plans developed by the Project for selected
     medium term abatement measures (no. of action plans approved) (Number, Custom)

                                            Baseline                   Actual (Previous)           Actual (Current)           End Target


12/20/2017                                                                                                                            Page 4 of 11
                                                          Public Disclosure Copy
                                                             Public Disclosure Copy

                  The World Bank                                                              Implementation Status & Results Report
                  Ulaanbaatar Clean Air Project (P122320)



               Value                           0.00                       4.00                 4.00                    4.00

               Date                            03-Apr-2012                19-Jan-2017          19-Jan-2017             31-Dec-2015




 PHINDPDOTBL




            Inter-agency and donor coordination framework for air pollution abatement measures developed and functioning (cumulative
           no. of years) (Number, Custom)

                                               Baseline                   Actual (Previous)    Actual (Current)        End Target

               Value                           1.00                       5.00                 5.00                    6.00

               Date                            03-Apr-2012                19-Jan-2017          19-Jan-2017             30-Jun-2018




 Overall Comments




 Intermediate Results Indicators
 PHINDIRITBL




              Laboratory tests supported by UBCAP (Number, Custom)

                                               Baseline                   Actual (Previous)    Actual (Current)        End Target

               Value                           0.00                       572.00               643.00                  155.00

               Date                            03-Apr-2012                19-Jan-2017          14-Jul-2017             31-Dec-2016




 PHINDIRITBL




              Number of stove models proposed for participation (Number, Custom)

                                               Baseline                   Actual (Previous)    Actual (Current)        End Target

               Value                           0.00                       61.00                77.00                   10.00

               Date                            03-Apr-2012                19-Jan-2017          14-Jul-2017             31-Dec-2016




12/20/2017                                                                                                                      Page 5 of 11
                                                             Public Disclosure Copy
                                                                Public Disclosure Copy

                  The World Bank                                                                      Implementation Status & Results Report
                  Ulaanbaatar Clean Air Project (P122320)

 PHINDIRITBL




              Number of stoves declared eligible for UBCAP support (Number, Custom)

                                                Baseline                     Actual (Previous)        Actual (Current)         End Target

               Value                            0.00                         15.00                    22.00                    5.00

               Date                             03-Apr-2012                  19-Jan-2017              14-Jul-2017              31-Dec-2016




 PHINDIRITBL




              Subsidy mechanism disbursing (% of available funds) (Percentage, Custom)

                                                Baseline                     Actual (Previous)        Actual (Current)         End Target

               Value                            0.00                         100.00                   100.00                   100.00

               Date                             18-Dec-2012                  19-Jan-2017              19-Jan-2017              31-Dec-2016




 PHINDIRITBL




              City greening preparatory study prepared (Text, Custom)

                                                Baseline                     Actual (Previous)        Actual (Current)         End Target

                                                                                                                               Final report
               Value                            Not started                  Final report submitted   Final report submitted
                                                                                                                               submitted

               Date                             31-Dec-2011                  06-Oct-2016              06-Oct-2016              31-Dec-2015



 PHINDIRITBL




              City greening pilot implemented (Text, Custom)

                                                Baseline                     Actual (Previous)        Actual (Current)         End Target

                                                                                                                               Pilot
               Value                            Not started                  Pilot implemented        Pilot implemented
                                                                                                                               implemented

               Date                             31-Dec-2011                  11-Jan-2016              11-Jan-2016              31-Dec-2015




12/20/2017                                                                                                                              Page 6 of 11
                                                                Public Disclosure Copy
                                                              Public Disclosure Copy

                  The World Bank                                                                     Implementation Status & Results Report
                  Ulaanbaatar Clean Air Project (P122320)

 PHINDIRITBL




              Power plant emissions control feasibility study prepared (Text, Custom)

                                                Baseline                    Actual (Previous)        Actual (Current)         End Target

                                                                                                                              Final report
               Value                            Not started                 Final report submitted   Final report submitted
                                                                                                                              submitted

               Date                             31-Dec-2011                 03-Dec-2015              03-Dec-2015              31-Dec-2015



 PHINDIRITBL




              Housing policy study prepared (Text, Custom)

                                                Baseline                    Actual (Previous)        Actual (Current)         End Target

                                                                                                                              Final report
               Value                            Not started                 final report submitted   final report submitted
                                                                                                                              submitted

               Date                             31-Dec-2011                 03-Dec-2015              03-Dec-2015              31-Dec-2015



 PHINDIRITBL




              District heating preparatory study prepared (Text, Custom)

                                                Baseline                    Actual (Previous)        Actual (Current)         End Target

                                                                                                                              Final report
               Value                            Not started                 Final report submitted   Final report submitted
                                                                                                                              submitted

               Date                             31-Dec-2011                 03-Dec-2015              03-Dec-2015              31-Dec-2015



 PHINDIRITBL




              Monitoring and analysis equipment supplied (cumulative number of bid packages) (Number, Custom)

                                                Baseline                    Actual (Previous)        Actual (Current)         End Target

               Value                            0.00                        5.00                     5.00                     3.00

               Date                             31-Dec-2011                 19-Jan-2017              19-Jan-2017              31-Dec-2016




12/20/2017                                                                                                                           Page 7 of 11
                                                              Public Disclosure Copy
                                                                     Public Disclosure Copy

                   The World Bank                                                                              Implementation Status & Results Report
                   Ulaanbaatar Clean Air Project (P122320)

 PHINDIRITBL




              Persons trained in air quality monitoring, analysis and management (cumulative number) (Number, Custom)

                                                      Baseline                      Actual (Previous)          Actual (Current)             End Target

               Value                                  0.00                          34.00                      34.00                        15.00

               Date                                   31-Dec-2011                   19-Jan-2017                19-Jan-2017                  31-Dec-2016




 PHINDIRITBL




              Effective project management and reporting established (No. of project progress reports per year) (Number, Custom)

                                                      Baseline                      Actual (Previous)          Actual (Current)             End Target

               Value                                  0.00                          14.00                      14.00                        2.00

               Date                                   31-Dec-2011                   19-Jan-2017                19-Jan-2017                  31-Dec-2016




 PHINDIRITBL




              Monthly reports on coordination activities prepaed by the municipality (No. of reports annually) (Number, Custom)

                                                      Baseline                      Actual (Previous)          Actual (Current)             End Target

               Value                                  0.00                          25.00                      26.00                        4.00

               Date                                   31-Dec-2011                   19-Jan-2017                14-Jul-2017                  31-Dec-2016




 PHINDIRITBL




              Consultants for supporting coordination hired (cumulative number) (Number, Custom)

                                                      Baseline                      Actual (Previous)          Actual (Current)             End Target

               Value                                  0.00                          2.00                       4.00                         2.00

               Date                                   03-Apr-2012                   19-Jan-2017                10-Nov-2017                  31-Dec-2016


               Comments
               Additional 2 contracts of consulting services were done and under implementation. 1. Detailed design for pilot project mini DH plant. 2. Heat
               loss measurement and energy auditor on EE packages /household level EE measures and kindergartens.




12/20/2017                                                                                                                                          Page 8 of 11
                                                                     Public Disclosure Copy
                                                              Public Disclosure Copy

                  The World Bank                                                                   Implementation Status & Results Report
                  Ulaanbaatar Clean Air Project (P122320)

 PHINDIRITBL




            Communications plan for collecting air quality program information across donors and agencies, satisfactory to the PMU, is
           preparedby the municipality (No. annual plans) (Number, Custom)

                                                Baseline                   Actual (Previous)       Actual (Current)         End Target

               Value                            0.00                       2.00                    3.00                     1.00

               Date                             31-Dec-2011                19-Jan-2017             14-Jul-2017              31-Dec-2016



 PHINDIRITBL




            Share of communications targets (e.g., meetings with agencies and donors, information collected) in approved
           communications plan achieved by the municipality (% share of target) (Percentage, Custom)

                                                Baseline                   Actual (Previous)       Actual (Current)         End Target

               Value                            0.00                       100.00                  100.00                   100.00

               Date                             31-Dec-2011                19-Jan-2017             19-Jan-2017              31-Dec-2016



 PHINDIRITBL




              Number of kindergartens that receive high-efficiency particulate (HEPA) filters (Number, Custom)

                                                Baseline                   Actual (Previous)       Actual (Current)         End Target

               Value                            0.00                       --                      500.00                   950.00

               Date                             15-May-2015                --                      10-Nov-2017              29-Jun-2018




 PHINDIRITBL




              Persons/ local producers trained in clean stove development, ceramic molding and production (Number, Custom)

                                                Baseline                   Actual (Previous)       Actual (Current)         End Target

               Value                            0.00                       --                      28.00                    28.00

               Date                             15-May-2015                --                      10-Nov-2017              30-Jun-2018




12/20/2017                                                                                                                           Page 9 of 11
                                                              Public Disclosure Copy
                                                                        Public Disclosure Copy

                   The World Bank                                                                                 Implementation Status & Results Report
                   Ulaanbaatar Clean Air Project (P122320)

 PHINDIRITBL




            Number of households benefited from energy efficiency demonstration work and retrofitted their detached houses (Number,
           Custom)

                                                        Baseline                     Actual (Previous)            Actual (Current)              End Target

               Value                                    0.00                         --                           175.00                        200.00

               Date                                     15-May-2015                  --                           10-Nov-2017                   30-Jun-2018



 PHINDIRITBL




              Number of HOBs replaced by non-coal heating appliances at government buildings (Number, Custom)

                                                        Baseline                     Actual (Previous)            Actual (Current)              End Target

               Value                                    0.00                         --                           0.00                          6.00

               Date                                     15-May-2015                  --                           06-Nov-2017                   30-Jun-2018


               Comments
               The feasibility study undertaken for the replacement of HOBs found that in order to make non-coal heating options feasible, it is necessary
               to first undertake energy efficiency measures in the respective government buildings. Therefore, the pilot was converted to supporting
               energy efficiency measures for government buildings which had already replaced their HOBs to non-coal heating appliances. Although the
               project is therefore not expected to directly replace HOBs with non-coal heating appliances, this indicator will likely be met through UB’s
               own funds.




 Overall Comments




Data on Financial Performance

Disbursements (by loan)

Project                  Loan/Credit/TF     Status        Currency        Original   Revised        Cancelled    Disbursed      Undisbursed                   Disbursed

P122320                  IDA-50390          Effective     USD               15.00         15.00           0.00         11.99             2.25                          80%


Key Dates (by loan)
Project                  Loan/Credit/TF     Status        Approval Date      Signing Date         Effectiveness Date     Orig. Closing Date     Rev. Closing Date

P122320                  IDA-50390          Effective     03-Apr-2012        04-Apr-2012          18-Dec-2012            30-Jun-2017            30-Jun-2018


12/20/2017                                                                                                                                             Page 10 of 11
                                                                        Public Disclosure Copy
                                                     Public Disclosure Copy

        The World Bank                                                        Implementation Status & Results Report
        Ulaanbaatar Clean Air Project (P122320)




Cumulative Disbursements




 Restructuring History

 Level 1 Approved on 10-Nov-2014 ,Level 2 Approved on 14-Jun-2017