PROCUREMENT PLAN (Textual Part) Project information: Pakistan – Pakistan Hydromet & DRM Services – P163924 [country] [Project name] [P-number] Project Implementation agencyies: Pakistan Meteorological Department (PMD) AND National Disaster Management Authority (NDMA)[insert legal name] Date of the Procurement Plan: Feb 21, 2018 [insert date] Period covered by this Procurement Plan: Feb 2018 – Jul 2018[insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Pakistan Federal Public Procurement Rules 2004 [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. – Not Applicable Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: Not Applicable [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: Not Applicable [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. SOPs for Procurement in Operational Manual Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Pakistan : Pakistan Hydromet and Climate Services Project (PHCSP) PLAN General Information Country: Pakistan Bank’s Approval Date of the Original Procurement Plan: 2021-04-07 2021-04-08 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163924 GPN Date: 2020-06-17 Project Name: Pakistan Hydromet and Climate Services Project (PHCSP) Loan / Credit No: IDA / 62460 N Executing Agency(ies): ational Disaster Risk Management Fund WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-NDRMF-228182-GO-RFQ Pending Hydro-meteorological and Request for Single Stage - One / NDRMF- Procurement of IDA / 62460 Post Limited 6,452.00 0.00 Implementati 2021-04-25 2021-05-27 2021-06-26 Climate Services Quotations Envelope Office Equipment on PK-NDRMF-228075-GO-RFQ Pending Hydro-meteorological and Request for Single Stage - One / NDRMF- Procurement of I.T IDA / 62460 Post Limited 6,452.00 0.00 Implementati 2021-04-23 2021-05-27 2021-06-26 Climate Services Quotations Envelope Equipment on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-NDRMF-228184-CS-INDV Individual Hydro-meteorological and Pending / NDRMF- Environment IDA / 62460 Post Consultant Open 56,952.00 0.00 2021-04-15 2021-06-02 2021-06-17 2021-06-27 2024-06-26 Climate Services Implementation Specialist Selection PK-NDRMF-228190-CS-INDV Individual Hydro-meteorological and Pending / NDRMF- Social Safeguard IDA / 62460 Post Consultant Open 56,952.00 0.00 2021-04-15 2021-06-02 2021-06-17 2021-06-27 2024-06-26 Climate Services Implementation Specialist Selection Page 1