The World Bank Energy Efficiency Project (P108023) REPORT NO.: RES30988 DOCUMENT OF THE WORLD BANK RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF ENERGY EFFICIENCY PROJECT APPROVED ON MAY 28, 2009 TO THE REPUBLIC OF BELARUS ENERGY & EXTRACTIVES EUROPE AND CENTRAL ASIA Regional Vice President: Cyril E Muller Country Director: Satu Kristiina J. Kahkonen Senior Global Practice Director: Riccardo Puliti Practice Manager/Manager: Sameer Shukla Task Team Leader: Feng Liu The World Bank Energy Efficiency Project (P108023) I. BASIC DATA Product Information Project ID Financing Instrument P108023 Investment Project Financing Original EA Category Current EA Category Partial Assessment (B) Partial Assessment (B) Approval Date Current Closing Date 28-May-2009 31-Dec-2017 Organizations Borrower Responsible Agency Energy Efficiency Department, State Standardization The Republic of Belarus Committee,RUE 'Belinvestenergosberezhenie'/ PIU Project Development Objective (PDO) Original PDO The development objective is to improve energy efficiency in heat and power generation in selected towns in Belarus. Summary Status of Financing Net Ln/Cr/Tf Approval Signing Effectiveness Closing Commitment Disbursed Undisbursed IBRD-82810 06-Jun-2013 24-Jun-2013 23-Oct-2013 31-Dec-2017 90.00 89.75 .25 IBRD-76980 28-May-2009 08-Jun-2009 30-Sep-2009 31-Dec-2017 125.00 118.55 6.45 Policy Waiver(s) Does this restructuring trigger the need for any policy waiver(s)? No II. SUMMARY OF PROJECT STATUS AND PROPOSED CHANGES The World Bank Energy Efficiency Project (P108023) The project is reaching successful completion and will be closed on December 31, 2017. The project implementation has been consistently rated satisfactory. The PDO is expected to be achieved satisfactorily at project closing. All combined heat and power (CHP) plants financed by the original loan (US$125 million) are in commercial operation. The two CHP plants, Mogilev CHP-1 and Gomel CHP-1, financed under the additional loan (US$90 million) were also completed and commissioned as of July 2017. As of November 30, 2017, US$118.55 million or about 95 percent of the original loan, and US$89.75 million or close to 100 percent of the additional loan were disbursed. It is expected that by December 31, 2017 the disbursement of the original loan will be unchanged, and the additional loan will be fully disbursed. The total disbursement of the project by the closing date is expected to reach about US$209 million. There were significant cost savings under the implementation of the original loan due to fluctuations in the exchange rates between the Swedish Krona, Euro and the U.S. dollar and a strong competition during the bidding process. The Bank approved the allocation of US$5.9 million savings from the original loan for RUE ‘Minskenergo’ to implement the reconstruction of 110 kV Open Switchgear at Zhodino CHP. The bids evaluation was concluded in August 2016. The lowest bid was disqualified due to a conflict of interest. The clarifications and final decision took several months. The borrower agreed to the negotiations with the second lowest bid, but concluded in April 2017 without reaching an agreement. Given that the project's closing date was extended twice and would not be further extended, there was no time left to proceed with the third lowest evaluated bidder and award and implement the contract. The Bank gave no- objection to the PMU’s proposal to cancel the ICB bidding procedure. The Bank received the Government’s letter for cancellation of the US$5.9 million on December 4, 2017. III. DETAILED CHANGES