The World Bank Implementation Status & Results Report Lao National Road 13 Improvement and Maintenance (P163730) Lao National Road 13 Improvement and Maintenance (P163730) EAST ASIA AND PACIFIC | Lao People's Democratic Republic | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 6 | ARCHIVED on 13-Jan-2021 | ISR44628 | Implementing Agencies: Ministry of Public Works and Transport, Lao People's Democratic Republic Key Dates Key Project Dates Bank Approval Date: 18-May-2018 Effectiveness Date: 22-Jan-2019 Planned Mid Term Review Date: 25-Oct-2021 Actual Mid-Term Review Date: Original Closing Date: 31-May-2023 Revised Closing Date: 31-May-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To improve the road condition, safety and climate resilience on critical sections of National Road 13. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Road Improvement and Maintenance:(Cost $120.50 M) Technical Assistance and Supervision:(Cost $4.80 M) Project Management:(Cost $2.70 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The project implementation is progressing. A joint WB, AIIB and NDF implementation support mission was conducted during December 14-18, 2020. With Covid-19 pandemic remained in place, the overall works progress has been affected due to delays in mobilization of contractor’s personnel and equipment. To date, 10 percent of road works has been completed, with 2 percent lag compared to the revised work plan. Good progress is made on the implementation of RAP and land acquisition, with only 1 percent of AHs remains to be settled on a case by case. Urgent actions are needed to improve road safety and traffic management. Preparation of the additional 6 km of NR13 North is underway and will be expedited. 1/13/2021 Page 1 of 7 The World Bank Implementation Status & Results Report Lao National Road 13 Improvement and Maintenance (P163730) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial Substantial Substantial Macroeconomic High Substantial Substantial Sector Strategies and Policies Substantial Moderate Moderate Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Moderate Moderate Moderate Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Moderate Other Moderate Moderate Moderate Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes Objective 1: Road Condition IN00927557 ►Road condition: Reduction in vehicle operating costs on the project road (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 Civil works is underway. No change in actual values of indicators during this reporting period. Comments: Objective 2: Road Safety IN00927558 ►Road safety: Increase in average iRAP star rating of the project road (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1.00 1.00 1.00 3.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 1/13/2021 Page 2 of 7 The World Bank Implementation Status & Results Report Lao National Road 13 Improvement and Maintenance (P163730) Civil works is underway. No change in actual values of indicators during this reporting period. Comments: Objective 3: Climate Resilience IN00927559 ►Climate resilience: Project road upgraded and improved, with climate resilient measures (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 Civil works is underway. No change in actual values of indicators during this reporting period. Comments: Overall Comments PDO Road improvement works are underway. Intermediate Results Indicators by Components Road Improvement and Maintenance IN00927560 ►Reduction in average IRI (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 7.00 7.00 7.00 3.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 Civil works is underway. No change in actual values of indicators during this reporting period. Comments: IN00927612 ►Kilometers of road upgraded from 2 to 4 lanes, with climate resilience measures (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 19.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 Civil works is underway. No change in actual values of indicators during this reporting period. Comments: IN00927614 1/13/2021 Page 3 of 7 The World Bank Implementation Status & Results Report Lao National Road 13 Improvement and Maintenance (P163730) ►Kilometers of road improved on 2 lanes, with climate resilience measures (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 39.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 Civil works is underway. No change in actual values of indicators during this reporting period. Comments: IN00927616 ►Roads rehablitated (Kilometers, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 58.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 Civil works is underway. No change in actual values of indicators during this reporting period. Comments: IN00927617 Roads rehabilitated - non-rural (Kilometers, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 58.00 IN00927618 ►Kilometers of roads transferred to performance based O&M phase under OPBRC (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 58.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 Civil works is underway. No change in actual values of indicators during this reporting period. Comments: IN00927619 ►Percentage of adjacent markets with improved pedestrian facilities, with focus on safety of women traders and school children (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 90.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 Civil works is underway. No change in actual values of indicators during this reporting period. Comments: IN00927620 ►Share of women employed in paid jobs in implementation of OPBRC (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target 1/13/2021 Page 4 of 7 The World Bank Implementation Status & Results Report Lao National Road 13 Improvement and Maintenance (P163730) Value 0.00 10.00 10.00 15.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 IN00927621 ►Contractor’s workforce trained on ESHS, OHS and GBV Code of Conduct (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 100.00 100.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2019 Training on Code of Conduct has been provided by contractor and monitored by supervision consultants Comments: and MPWT. IN00927622 ►Project beneficiaries (number), of which female (percentage) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 500,000.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 Project beneficiaries are people who live in the project area and derive benefits from an intervention. The Comments: project is at early implementation phase, with only 10 percent of civil works underway. IN00927623 Female project beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 47.00 Technical Assistance and Supervision IN00927611 ►Grievances registered related to delivery of the project addressed, with disagrigated data by gender (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 97.00 99.00 90.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 The indicator includes registration and resolution of grievances received arising from project activities, Comments: with gender disaggregated data. IN00927613 ►Total Number of MPWT staff received training on OPBRC and related topics (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 82.00 98.00 40.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 1/13/2021 Page 5 of 7 The World Bank Implementation Status & Results Report Lao National Road 13 Improvement and Maintenance (P163730) The indicator measures the number of MPWT staff attending the full duration of the training course on Comments: OPBRC. Number of Trainings have been conducted and provided by WB consultant on the subject. IN00927615 ►Number of MPWT female staff received training on OPBRC and related topics (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 15.00 19.00 15.00 Date 02-May-2018 25-Jun-2020 18-Dec-2020 31-May-2023 The indicator will measure the number of MPWT female staff attending the OPBRC training to support their knowledge and skills development and future participation in planning and decision making in the Comments: road sector. Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P163730 IDA-62260 Effective USD 40.00 40.00 0.00 3.54 35.44 9.1% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P163730 IDA-62260 Effective 18-May-2018 23-Jul-2018 22-Jan-2019 31-May-2023 31-May-2023 Cumulative Disbursements 1/13/2021 Page 6 of 7 The World Bank Implementation Status & Results Report Lao National Road 13 Improvement and Maintenance (P163730) PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History Level 2 Approved on 28-Apr-2019 Related Project(s) There are no related projects. 1/13/2021 Page 7 of 7