Public Disclosure Copy The World Bank Implementation Status & Results Report Kafue-Muzuma-Victoria Falls Regional Transmission Line Reinforcement Project (P124351) Kafue-Muzuma-Victoria Falls Regional Transmission Line Reinforcement Project (P124351) AFRICA | Africa | Energy & Extractives Global Practice | IBRD/IDA | Specific Investment Loan | FY 2012 | Seq No: 8 | ARCHIVED on 02-Feb-2017 | ISR26242 | Implementing Agencies: Key Dates Key Project Dates Bank Approval Date:15-May-2012 Effectiveness Date:06-Dec-2012 Planned Mid Term Review Date:31-Oct-2016 Actual Mid-Term Review Date:02-Nov-2016 Original Closing Date:31-Dec-2015 Revised Closing Date:30-Jun-2017 Project Development Objectives Project Development Objective (from Project Appraisal Document) To improve the reliability of ZESCO's regional power trade transmission network infrastructure along the Kafue Town - Muzuma - Victoria Falls corridor. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Component 1: Upgrading of the existing 220kV transmission line:(Cost $24.00 M) Component 2: Reinforcement and Construction of Substations:(Cost $71.00 M) Component 3: Project Management, Environmental and Social Mitigation, and Training:(Cost $5.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Unsatisfactory Moderately Unsatisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate 2/2/2017 Page 1 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Kafue-Muzuma-Victoria Falls Regional Transmission Line Reinforcement Project (P124351) Implementation Status and Key Decisions Project implementation has improved with a number of corrective actions implemented by ZESCO including closer supervision of the contractors by the PIU resulting in adequate resources being provided by the contractors (new project manager, additional equipment and manpower) and allowing longer line shutdowns for the stringing works. However, despite the achieved and promising progress on the transmission lines works, implementation of works for substations (Kafue Town Muzuma substation and Livingston substation) is expected to be completed only in September 2017, i.e. beyond the current closing date of June 30, 2017. The Government has therefore submitted a request to extend the closing date to December 2017 to allow the completion of works. The request is currently being considered. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Moderate Moderate Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Low Low Institutional Capacity for Implementation and Sustainability -- High High Fiduciary -- Substantial Substantial Environment and Social -- Moderate Moderate Stakeholders -- Low Low Other -- -- -- Overall -- Moderate Moderate Results Project Development Objective Indicators PHINDPDOTBL Average interruption frequency per year in the project area (Number, Core) Baseline Actual (Previous) Actual (Current) End Target Value 5.00 5.00 5.00 3.00 Date 30-Sep-2012 28-May-2016 02-Dec-2016 30-Jun-2017 2/2/2017 Page 2 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Kafue-Muzuma-Victoria Falls Regional Transmission Line Reinforcement Project (P124351) PHINDPDOTBL Customers served in the project area (Number, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 125,000.00 130,000.00 130,000.00 200,000.00 PHINDPDOTBL Electricity Trade (Gigawatt-hour (GWh), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 264.00 264.00 264.00 528.00 Date 30-Sep-2012 28-May-2016 02-Dec-2016 30-Jun-2017 Overall Comments Intermediate Results Indicators PHINDIRITBL Transmission lines constructed or rehabilitated under the project (Kilometers, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 152.00 348.00 Date 30-Sep-2012 28-May-2016 02-Dec-2016 30-Jun-2017 2/2/2017 Page 3 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Kafue-Muzuma-Victoria Falls Regional Transmission Line Reinforcement Project (P124351) PHINDIRITBL Transmission lines rehabilitated under the project (Kilometers, Core Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 152.00 348.00 Date 30-Sep-2012 28-May-2016 02-Dec-2016 30-Jun-2017 PHINDIRITBL Substations upgraded and functional (Kafue Town) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value NO NO NO YES Date 30-Sep-2012 28-May-2016 02-Dec-2016 30-Jun-2017 PHINDIRITBL Transmission Line capacity Increase (Volts, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 220,000.00 220,000.00 220,000.00 330,000.00 Date 30-Sep-2012 28-May-2016 02-Dec-2016 30-Jun-2017 PHINDIRITBL Substations Constructed and functional (Livingstone) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value NO NO NO YES Date 30-Sep-2012 28-May-2016 02-Dec-2016 30-Jun-2017 2/2/2017 Page 4 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Kafue-Muzuma-Victoria Falls Regional Transmission Line Reinforcement Project (P124351) PHINDIRITBL Substation Upgraded and functional (Muzuma) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value NO NO NO YES Date 30-Sep-2012 28-May-2016 02-Dec-2016 30-Jun-2017 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P124351 IDA-50900 Effective XDR 37.10 37.10 0.00 34.64 2.46 93% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P124351 IDA-50900 Effective 15-May-2012 07-Sep-2012 06-Dec-2012 31-Dec-2015 30-Jun-2017 Cumulative Disbursements 2/2/2017 Page 5 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Kafue-Muzuma-Victoria Falls Regional Transmission Line Reinforcement Project (P124351) Restructuring History Level 2 Approved on 09-Oct-2015 Related Project(s) There are no related projects. 2/2/2017 Page 6 of 6 Public Disclosure Copy