Public Disclosure Copy

        The World Bank                                                                               Implementation Status & Results Report
        Financial Sector Support Project. (P151816)


Financial Sector Support Project. (P151816)

AFRICA | Kenya | Finance & Markets Global Practice |
IBRD/IDA | Investment Project Financing | FY 2015 | Seq No: 5 | ARCHIVED on 31-Oct-2017 | ISR29524 |


Implementing Agencies: Republic of KENYA, Directorate of Budget & Fiscal & Economic Affairs




Key Dates

  Key Project Dates

  Bank Approval Date:30-Apr-2015                                              Effectiveness Date:10-Jul-2015
  Planned Mid Term Review Date:28-Feb-2018                                    Actual Mid-Term Review Date:--
  Original Closing Date:31-Jul-2020                                           Revised Closing Date:31-Jul-2020




Project Development Objectives

 Project Development Objective (from Project Appraisal Document)
 The project's development objective is to strengthen the legal, regulatory and institutional environment for improved financial stability, access
 to and provision of, affordable and long term financing.


 Has the Project Development Objective been changed since Board Approval of the Project Objective?
 No

 PHRPDODEL



Components

Name
Component 1: Strengthening Institutions:(Cost $23.30 M)
Component 2: Enabling Efficient Financial Intermediation:(Cost $6.40 M)
Component 3: Mobilizing Long-Term Finance:(Cost $5.30 M)
Component 4: Supporting Project Management:(Cost $1.30 M)
Contingency:(Cost $0.70 M)



Overall Ratings
Name                                                                        Previous Rating                           Current Rating

Progress towards achievement of PDO                                          Moderately Unsatisfactory                Moderately Unsatisfactory
Overall Implementation Progress (IP)                                         Moderately Unsatisfactory                Moderately Unsatisfactory



10/31/2017                                                                                                                                Page 1 of 8
                                                           Public Disclosure Copy
                                                          Public Disclosure Copy

        The World Bank                                                                             Implementation Status & Results Report
        Financial Sector Support Project. (P151816)


Overall Risk Rating                                                         Moderate                                Moderate


Implementation Status and Key Decisions

 The Financial Sector Support Project (FSSP) was effected on July 10, 2015, with an expected closure date of June 2020. FSSP was build on previous
 financial sector reforms and gains realized through the Financial and Legal Sector Technical Assistance Project (FLSTAP). The FSSP project is
 expected to support Kenyan financial sector authorities in further developing regulatory and supervisory frameworks that continue to be effective in
 mitigating the new risks associated with the financial sector’s rapid development, deepening expansion across sectors, and across borders. It supports
 the upgrade of the supervisory, regulatory, and institutional framework to keep pace with more complex markets and products with the overall objective
 of enhancing stability.


 FSSP’s project components and key interventions include:
 Component 1: Strengthening Financial Institutions
 This component focuses on the overarching reform, modernization, and capacity support to the financial sector institutional framework. This component
 delivers technical assistance to the various beneficiaries, mostly in the form of consultancies, to design roadmaps and action plans, and implementation
 support to realize the planned reforms. It also supports the upgrade of IT systems and delivers capacity support to ensure a more effective functioning
 of the financial architecture.


 Under this component, the project has primarily assisted financial sector regulators in strengthening their surveillance systems, through both IT
 upgradation and advisors and technical assistance on the implementation of risk-based supervision; and helped develop frameworks for deposit
 guarantees and deposit insurance for the non-bank sectors. Beneficiaries of this component include the Central Bank of Kenya (CBK), the Insurance
 Regulatory Authority (IRA, the SACCO Societies Regulatory Authority (SASRA), the Kenya Deposit Insurance Corporation (KDIC),


 Component 2: Enabling Efficient Financial Intermediation
 This component accelerates the financial inclusion agenda in the Republic of Kenya with a focus on strengthening financial infrastructure and making
 more transparent the pricing of financial intermediation (savings and lending) so that more businesses and individuals have access to affordable
 financial products. The component supports consultancies, training and IT purchases.


 Under this component, the Project has committed to support the implementation of a collateral registry system, and provide technical assistance in
 shoring up the legal and regulatory framework for movable property. Additionally, the Project is supporting strengthening of the Insolvency Framework
 through technical assistance, and providing assistance in assessing and strengthening the credit reporting system in Kenya. Key beneficiaries under
 this component include the Office of the Attorney General, and National Treasury.


 Component 3: Increasing Availability of Long-term Finance
 This component focuses on strengthening the demand for and supply of long-term funds so that Kenya’s growing development finance needs for long-
 term projects in infrastructure, housing, etc. can be met. The component includes support via consultancies, training and IT purchases.


 Under this component, the Project is supporting the development of a range of products for long term finance, including around informal pensions, new
 capital market products, and new insurance products. Additionally, this component will assist regulators in upgrading systems and modernizing financial
 infrastructure for issuing long term debt. Key beneficiaries include the Retirement Benefits Authority (RBA), Insurance Regulatory Authority (IRA),
 Capital Markets Authority (CMA), and Central Bank of Kenya (CBK).




Risks


10/31/2017                                                                                                                              Page 2 of 8
                                                          Public Disclosure Copy
                                                         Public Disclosure Copy

               The World Bank                                                                      Implementation Status & Results Report
               Financial Sector Support Project. (P151816)


 Systematic Operations Risk-rating Tool

 Risk Category                                            Rating at Approval               Previous Rating            Current Rating

 Political and Governance                                  Substantial                     Substantial               Substantial
 Macroeconomic                                             Moderate                        Moderate                  Substantial
 Sector Strategies and Policies                            Moderate                        Moderate                  Moderate
 Technical Design of Project or Program                    Moderate                        Moderate                  Moderate
 Institutional Capacity for Implementation and
 Sustainability
                                                           Low                             Low                       Low
 Fiduciary                                                 Moderate                        Moderate                  Substantial
 Environment and Social                                    Low                             Low                       Low
 Stakeholders                                              Low                             Low                       Low
 Other                                                     --                              --                        --
 Overall                                                   Moderate                        Moderate                  Moderate


Results

 Project Development Objective Indicators
 PHINDPDOTBL




      Progress towards achieving compliance with Essential Criteria of Basel Core Principles 12 (consolidated supervision) and 13
     (home-host relations) (Text, Custom)

                                           Baseline                    Actual (Previous)           Actual (Current)           End Target

         Value                             MNC/LC                      --                          No progress                Compliant

         Date                              01-May-2015                 30-Dec-2016                 23-Oct-2017                31-Jul-2020


 PHINDPDOTBL




          Reduced net interest margin (Text, Custom)


                                           Baseline                    Actual (Previous)           Actual (Current)           End Target

         Value                             No                          --                          Yes                        Yes

         Date                              01-May-2015                 --                          23-Oct-2017                31-Jul-2020


 PHINDPDOTBL




          Long-term assets held by pension funds (Percentage, Custom)


                                           Baseline                    Actual (Previous)           Actual (Current)           End Target



10/31/2017                                                                                                                            Page 3 of 8
                                                         Public Disclosure Copy
                                                             Public Disclosure Copy

                  The World Bank                                                                  Implementation Status & Results Report
                  Financial Sector Support Project. (P151816)



               Value                           47.00                        49.00                  49.00                       52.00

               Date                            01-May-2015                  19-Sep-2016            23-Oct-2017                 31-Jul-2020




 Overall Comments
 The first PDO on consolidated supervision and host-home compliance will need to be reconsidered at mid-term. The PDO was developed with the
 CBK, under the stewardship of the former Governor. In light of the many challenges the financial sector has faced since the new CBK governor
 has stepped in, the focus for CBK is directly on strengthening banking supervision in the domestic market before embarking on a more ambitious
 path to look at consolidated and cross-border supervision. This is a strategic shift supported by the task team. The second PDO will also need to
 be reconsidered, since compliance is a direct result of the interest rate cap, rather than any structural achievements that have brought down the
 cost of credit or interest margins.




 Intermediate Results Indicators
 PHINDIRITBL




              Mapping exercise of financial conglomerates (Text, Custom)

                                               Baseline                     Actual (Previous)      Actual (Current)            End Target

               Value                           No                           --                     No                          Yes

               Date                            01-May-2015                  30-Dec-2016            23-Oct-2017                 31-Jul-2020




 PHINDIRITBL




              Number of MDAs services using electronic payment instruments (Number, Custom)

                                               Baseline                     Actual (Previous)      Actual (Current)            End Target

               Value                           0.00                         --                     200.00                      3,000.00

               Date                            01-May-2015                  --                     23-Oct-2017                 31-Jul-2020




10/31/2017                                                                                                                             Page 4 of 8
                                                             Public Disclosure Copy
                                                              Public Disclosure Copy

                  The World Bank                                                                Implementation Status & Results Report
                  Financial Sector Support Project. (P151816)

 PHINDIRITBL




              Increase in Pension coverage (Percentage, Custom)

                                                Baseline                   Actual (Previous)    Actual (Current)          End Target

               Value                            15.00                      18.20                19.50                     20.00

               Date                             01-May-2015                30-Dec-2016          23-Oct-2017               31-Jul-2020




 PHINDIRITBL




              Draft framework for sub-national entities on debt management (Text, Custom)

                                                Baseline                   Actual (Previous)    Actual (Current)          End Target

                                                                                                Assessment of financing
               Value                            No                         --                   gaps for Counties is      Yes
                                                                                                ongoing

               Date                             01-May-2015                --                   23-Oct-2017               31-Jul-2020


 PHINDIRITBL




              Increase in banked retail investor accounts accessing Trearusy Mobile Direct (TMD) (Number, Custom)

                                                Baseline                   Actual (Previous)    Actual (Current)          End Target

               Value                            15,000.00                  --                   103,000.00                150,000.00

               Date                             01-May-2015                --                   23-Oct-2017               31-Jul-2020




 PHINDIRITBL




              Draft legal framework for a secured transactions regime (Text, Custom)

                                                Baseline                   Actual (Previous)    Actual (Current)          End Target

               Value                            No                         --                   Yes                       Yes

               Date                             01-May-2015                --                   23-Oct-2017               31-Jul-2020




10/31/2017                                                                                                                        Page 5 of 8
                                                              Public Disclosure Copy
                                                             Public Disclosure Copy

                  The World Bank                                                                    Implementation Status & Results Report
                  Financial Sector Support Project. (P151816)

 PHINDIRITBL




              Depth of credit information index (Number, Custom)

                                               Baseline                   Actual (Previous)         Actual (Current)            End Target

               Value                           0.00                       7.00                      7.00                        3.00

               Date                            01-May-2015                30-Dec-2016               23-Oct-2017                 31-Jul-2020




 PHINDIRITBL




              Draft framework / regulation for new long term products (Number, Custom)

                                               Baseline                   Actual (Previous)         Actual (Current)            End Target

               Value                           0.00                       --                        0.00                        2.00

               Date                            01-May-2015                --                        23-Oct-2017                 31-Jul-2020




 PHINDIRITBL




              Increase in volume of secondary market transactions of government debt (Text, Custom)

                                               Baseline                   Actual (Previous)         Actual (Current)            End Target

               Value                           N/A                        --                        Yes                         Yes

               Date                            01-May-2015                30-Dec-2016               23-Oct-2017                 31-Jul-2020




 PHINDIRITBL




              Increase in Insurance coverage (Percentage, Custom)

                                               Baseline                   Actual (Previous)         Actual (Current)            End Target

               Value                           3.70                       --                        2.92                        6.00

               Date                            01-May-2015                --                        23-Oct-2017                 31-Jul-2020




 Overall Comments
 Several of the intermediate indicators will also need to be reconsidered. Mapping exercise of financial conglomerates needs to be discussed
 again with the CBK to gauge their appetite to shift strategic focus on consolidated supervision. The indicator for MDAs appears overly ambitious
 from the design stage, and the PBA has shifted several times since project effectiveness, including to regulatory authorities outside the scope of
 support of the FSSP. Increase in insurance coverage may need to be revised, as the baseline was revised downwards in 2015 following Kenya’s
 rebasing of the economy.


10/31/2017                                                                                                                              Page 6 of 8
                                                             Public Disclosure Copy
                                                            Public Disclosure Copy

           The World Bank                                                                          Implementation Status & Results Report
           Financial Sector Support Project. (P151816)




 Data on Financial Performance

Disbursements (by loan)

 Project        Loan/Credit/TF    Status      Currency        Original   Revised      Cancelled   Disbursed    Undisbursed                   Disbursed

 P151816        IDA-56270         Effective   USD               37.00      37.00           0.00         4.66           32.33                        13%


Key Dates (by loan)
 Project       Loan/Credit/TF    Status       Approval Date      Signing Date      Effectiveness Date   Orig. Closing Date     Rev. Closing Date

 P151816       IDA-56270         Effective    30-Apr-2015        04-Jun-2015       10-Jul-2015          31-Jul-2020            31-Jul-2020



Cumulative Disbursements




 Restructuring History

  There has been no restructuring to date.




10/31/2017                                                                                                                            Page 7 of 8
                                                            Public Disclosure Copy
                                                 Public Disclosure Copy

        The World Bank                                                    Implementation Status & Results Report
        Financial Sector Support Project. (P151816)



 Related Project(s)

There are no related projects.




10/31/2017                                                                                             Page 8 of 8
                                                 Public Disclosure Copy