Public Disclosure Copy

        The World Bank                                        Implementation Status & Results Report
        SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR
        (CAREC 1B & 6B) (P099270)


SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT
CORRIDOR (CAREC 1B & 6B) (P099270)

EUROPE AND CENTRAL ASIA | Kazakhstan | Transport & ICT Global Practice |
IBRD/IDA | Investment Project Financing | FY 2009 | Seq No: 19 | ARCHIVED on 27-Dec-2017 | ISR30841 |


Implementing Agencies: REPUBLIC OF KAZAKHSTAN, Ministry of Investments and Development




Key Dates

  Key Project Dates

  Bank Approval Date:30-Apr-2009                                            Effectiveness Date:09-Dec-2009
  Planned Mid Term Review Date:03-Dec-2012                                  Actual Mid-Term Review Date:27-Nov-2012
  Original Closing Date:31-Dec-2013                                         Revised Closing Date:31-Dec-2021




Project Development Objectives

 Project Development Objective (from Project Appraisal Document)
 The proposed Project aims to increase transport efficiency along the road sections between Aktobe/Kyzylorda Oblast border and Shymkent and to
 improve road management and traffic safety in Kazakhstan.

 Has the Project Development Objective been changed since Board Approval of the Project Objective?
 Yes

 Board Approved Revised Project Development Objective (If project is formally restructured)PHRPDODEL
 The objective of the Project is to improve transport efficiency along road sections in Kyzylorda, South Kazakhstan and Almaty Oblasts, improve road
 management and increase traffic safety in Kazakhstan.




Components

Name
Upgrade and reconstruction of road sections along the WE-WC Corridor within Kyzylorda oblast (excluding the bypass to Kyzylorda):(Cost $1260.00
M)
Upgrade and reconstruction of road sections within South Kazakhstan oblast, including the bypass to Kyzylorda:(Cost $880.00 M)
Project Management Consultants:(Cost $14.00 M)
Institutional Development, Road Safety, Road Services and Road Asset Management System:(Cost $4.00 M)
Supervision of civil works:(Cost $66.00 M)
Upgrade and reconstruction of road sections within Almaty oblast:(Cost $276.00 M)



Overall Ratings

12/27/2017                                                                                                                             Page 1 of 6
                                                         Public Disclosure Copy
                                                          Public Disclosure Copy

           The World Bank                                        Implementation Status & Results Report
           SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR
           (CAREC 1B & 6B) (P099270)


Name                                                                       Previous Rating                          Current Rating

Progress towards achievement of PDO                                         Satisfactory                            Satisfactory
Overall Implementation Progress (IP)                                        Moderately Satisfactory                 Moderately Satisfactory
Overall Risk Rating                                                         Moderate                                Moderate


Implementation Status and Key Decisions

 The Project is progressing well toward achieving the project development objective. About 1,060 km (original Project scope) of the 1,150 km roads
 supported by the Project has been successfully built and opened to traffic. The section that remains under construction was added to the original scope
 of the Project in 2012 under the first restructuring of the Project. Of which, the contract of tunnel works was terminated. Re-bidding of the remaining
 works under the contract was completed, and a new contract was signed. The Borrower also made a satisfactory progress in implementation of
 institutional development component during first half of FY2018. The Bank team has launched an evaluation survey to identify perceptions of users
 (including businesses, local residents, freight forwarders, and other road users) regarding to the change in economic conditions before and after the
 road construction.
 The project recorded about the US$300 million savings, which the Borrower proposed to finance two additional road sections (Kurty-Togyz and Otar-
 Uzynagash) as well as road sector reforms. A project restructuring to cover the additional sections was approved by the Bank in June 2017 with the
 closing date extended to December 31, 2021. The CR has already awarded two contracts for two lots (km 2295-2335 and km 2335-2380) of the Kurty-
 Togyz section.




Risks

 Systematic Operations Risk-rating Tool

 Risk Category                                             Rating at Approval                Previous Rating            Current Rating

 Political and Governance                                   --                               Moderate                  Moderate
 Macroeconomic                                              --                               Moderate                  Moderate
 Sector Strategies and Policies                             --                               Moderate                  Moderate
 Technical Design of Project or Program                     --                               Low                       Low
 Institutional Capacity for Implementation and
 Sustainability
                                                            --                               Moderate                  Moderate
 Fiduciary                                                  --                               Low                       Low
 Environment and Social                                     --                               Moderate                  Substantial
 Stakeholders                                               --                               Low                       Low
 Other                                                      --                               Moderate                  Moderate
 Overall                                                    --                               Moderate                  Moderate


Results

 Project Development Objective Indicators

12/27/2017                                                                                                                              Page 2 of 6
                                                          Public Disclosure Copy
                                                          Public Disclosure Copy

               The World Bank                                        Implementation Status & Results Report
               SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR
               (CAREC 1B & 6B) (P099270)

 PHINDPDOTBL




      Reduce, by the end of the Project, Road User Costs from US$0.26/veh-km to US$0.23/veh-km on Project road sections. (Text,
     Custom)

                                            Baseline                   Actual (Previous)       Actual (Current)          End Target

         Value                              0.26                       0.24                    0.24                      0.23

         Date                               09-Jun-2009                06-Jun-2017             07-Dec-2017               30-Jun-2018


 PHINDPDOTBL




          Proportion of the Republican road network length that are in Good or Fair conditions (Text, Custom)


                                            Baseline                   Actual (Previous)       Actual (Current)          End Target

         Value                              53%                        67.00                   67.00                     86%

         Date                               09-Jun-2009                06-Jun-2017             07-Dec-2017               30-Jun-2018


 PHINDPDOTBL




      Reduce, by the end of the Project, the rate (per 100 million veh-km) of road crash fatalities along the Project road sections by
     atleast 10% (Text, Custom)

                                            Baseline                   Actual (Previous)       Actual (Current)          End Target

                                                                       to be extracted from
         Value                              11.00                                              9.50                      9.50
                                                                       RAMS

         Date                               01-Jun-2007                06-Jun-2017             07-Dec-2017               30-Jun-2018


 PHINDPDOTBL




          Implementation and Effective use of Road Management System by the Committee (Text, Custom)


                                            Baseline                   Actual (Previous)       Actual (Current)          End Target

                                                                                               RAMS activities
                                                                       RAMS activities
                                                                                               framework completed.
                                                                       framework completed.
         Value                              No system in place                                 Equipment tested. The     System in place
                                                                       Equipment being
                                                                                               system being rolled out
                                                                       tested.
                                                                                               in 14 oblasts.

         Date                               09-Jun-2009                06-Jun-2017             07-Dec-2017               30-Jun-2018




 Overall Comments




12/27/2017                                                                                                                      Page 3 of 6
                                                          Public Disclosure Copy
                                                                Public Disclosure Copy

                  The World Bank                                        Implementation Status & Results Report
                  SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR
                  (CAREC 1B & 6B) (P099270)



 Intermediate Results Indicators
 PHINDIRITBL




              Number of kilometers of roads upgraded (cumulative km) (Text, Custom)

                                                 Baseline                    Actual (Previous)      Actual (Current)       End Target

               Value                             0.00                        1,148.00               1,148.00               1,227.00

               Date                              09-Jun-2009                 06-Jun-2017            07-Dec-2017            30-Jun-2018




 PHINDIRITBL




              Works, Goods, and Consulting Services contracts processed and managed by the PMC (Text, Custom)

                                                 Baseline                    Actual (Previous)      Actual (Current)       End Target

                                                                                                                           28(W);1(G);11(
               Value                             0 (W); 0 (G); 0 (CS)        24(w), (0) G, 9(CS)    26(w), (1) G, 10(CS)
                                                                                                                           CS)

               Date                              09-Jun-2009                 06-Jun-2017            07-Dec-2017            30-Jun-2018



 PHINDIRITBL




              Training received by the Committee staff from PMC (staff-hours) (Text, Custom)

                                                 Baseline                    Actual (Previous)      Actual (Current)       End Target

               Value                             0.00                        3,500.00               3,500.00               3,000.00

               Date                              09-Jun-2009                 19-Dec-2016            07-Dec-2017            30-Jun-2018




 PHINDIRITBL




              Updating of road data for Republican roads (% of total length per year) (Text, Custom)

                                                 Baseline                    Actual (Previous)      Actual (Current)       End Target

               Value                             0%                          67.00                  67.00                  100%

               Date                              09-Jun-2009                 19-Dec-2016            07-Dec-2017            30-Jun-2018




12/27/2017                                                                                                                        Page 4 of 6
                                                                Public Disclosure Copy
                                                                    Public Disclosure Copy

                  The World Bank                                        Implementation Status & Results Report
                  SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR
                  (CAREC 1B & 6B) (P099270)

 PHINDIRITBL




              Road asset management strategy, Rolling multiyearroad maintenance, and rehabilitation programestablished (Text, Custom)

                                                    Baseline                     Actual (Previous)          Actual (Current)             End Target

                                                                                                            system in place, tested,
                                                                                 system in place, being
               Value                                Not established                                         being rolled out in 14       Established
                                                                                 tested
                                                                                                            oblasts.

               Date                                 09-Jun-2009                  19-Dec-2016                07-Dec-2017                  30-Jun-2018


 PHINDIRITBL




              Prepare road safety strategy and action plan (Text, Custom)

                                                    Baseline                     Actual (Previous)          Actual (Current)             End Target

               Value                                Not established              Established                Established                  Established

               Date                                 09-Jun-2009                  18-Dec-2015                18-Dec-2015                  30-Jun-2018




 Overall Comments




 Data on Financial Performance

Disbursements (by loan)

 Project               Loan/Credit/TF   Status        Currency        Original   Revised      Cancelled    Disbursed      Undisbursed                  Disbursed

 P099270               IBRD-76810       Effective     USD             2,125.00   2,125.00           0.00     1,800.90           324.10                        85%


Key Dates (by loan)
 Project               Loan/Credit/TF   Status        Approval Date      Signing Date       Effectiveness Date   Orig. Closing Date      Rev. Closing Date

 P099270               IBRD-76810       Effective     30-Apr-2009        13-Jun-2009        09-Dec-2009          31-Dec-2013             31-Dec-2021



Cumulative Disbursements




12/27/2017                                                                                                                                      Page 5 of 6
                                                                    Public Disclosure Copy
                                                     Public Disclosure Copy

        The World Bank                                        Implementation Status & Results Report
        SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR
        (CAREC 1B & 6B) (P099270)




 Restructuring History

 Level Approved on 25-Jun-2012 ,Level 1 Approved on 25-Jun-2015 ,Level 1 Approved on 16-Jun-2017




 Related Project(s)

There are no related projects.




12/27/2017                                                                                         Page 6 of 6
                                                     Public Disclosure Copy