Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270) SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270) EUROPE AND CENTRAL ASIA | Kazakhstan | Transport & ICT Global Practice | IBRD/IDA | Investment Project Financing | FY 2009 | Seq No: 19 | ARCHIVED on 27-Dec-2017 | ISR30841 | Implementing Agencies: REPUBLIC OF KAZAKHSTAN, Ministry of Investments and Development Key Dates Key Project Dates Bank Approval Date:30-Apr-2009 Effectiveness Date:09-Dec-2009 Planned Mid Term Review Date:03-Dec-2012 Actual Mid-Term Review Date:27-Nov-2012 Original Closing Date:31-Dec-2013 Revised Closing Date:31-Dec-2021 Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed Project aims to increase transport efficiency along the road sections between Aktobe/Kyzylorda Oblast border and Shymkent and to improve road management and traffic safety in Kazakhstan. Has the Project Development Objective been changed since Board Approval of the Project Objective? Yes Board Approved Revised Project Development Objective (If project is formally restructured)PHRPDODEL The objective of the Project is to improve transport efficiency along road sections in Kyzylorda, South Kazakhstan and Almaty Oblasts, improve road management and increase traffic safety in Kazakhstan. Components Name Upgrade and reconstruction of road sections along the WE-WC Corridor within Kyzylorda oblast (excluding the bypass to Kyzylorda):(Cost $1260.00 M) Upgrade and reconstruction of road sections within South Kazakhstan oblast, including the bypass to Kyzylorda:(Cost $880.00 M) Project Management Consultants:(Cost $14.00 M) Institutional Development, Road Safety, Road Services and Road Asset Management System:(Cost $4.00 M) Supervision of civil works:(Cost $66.00 M) Upgrade and reconstruction of road sections within Almaty oblast:(Cost $276.00 M) Overall Ratings 12/27/2017 Page 1 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270) Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions The Project is progressing well toward achieving the project development objective. About 1,060 km (original Project scope) of the 1,150 km roads supported by the Project has been successfully built and opened to traffic. The section that remains under construction was added to the original scope of the Project in 2012 under the first restructuring of the Project. Of which, the contract of tunnel works was terminated. Re-bidding of the remaining works under the contract was completed, and a new contract was signed. The Borrower also made a satisfactory progress in implementation of institutional development component during first half of FY2018. The Bank team has launched an evaluation survey to identify perceptions of users (including businesses, local residents, freight forwarders, and other road users) regarding to the change in economic conditions before and after the road construction. The project recorded about the US$300 million savings, which the Borrower proposed to finance two additional road sections (Kurty-Togyz and Otar- Uzynagash) as well as road sector reforms. A project restructuring to cover the additional sections was approved by the Bank in June 2017 with the closing date extended to December 31, 2021. The CR has already awarded two contracts for two lots (km 2295-2335 and km 2335-2380) of the Kurty- Togyz section. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Moderate Moderate Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Low Low Institutional Capacity for Implementation and Sustainability -- Moderate Moderate Fiduciary -- Low Low Environment and Social -- Moderate Substantial Stakeholders -- Low Low Other -- Moderate Moderate Overall -- Moderate Moderate Results Project Development Objective Indicators 12/27/2017 Page 2 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270) PHINDPDOTBL Reduce, by the end of the Project, Road User Costs from US$0.26/veh-km to US$0.23/veh-km on Project road sections. (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.26 0.24 0.24 0.23 Date 09-Jun-2009 06-Jun-2017 07-Dec-2017 30-Jun-2018 PHINDPDOTBL Proportion of the Republican road network length that are in Good or Fair conditions (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 53% 67.00 67.00 86% Date 09-Jun-2009 06-Jun-2017 07-Dec-2017 30-Jun-2018 PHINDPDOTBL Reduce, by the end of the Project, the rate (per 100 million veh-km) of road crash fatalities along the Project road sections by atleast 10% (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target to be extracted from Value 11.00 9.50 9.50 RAMS Date 01-Jun-2007 06-Jun-2017 07-Dec-2017 30-Jun-2018 PHINDPDOTBL Implementation and Effective use of Road Management System by the Committee (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target RAMS activities RAMS activities framework completed. framework completed. Value No system in place Equipment tested. The System in place Equipment being system being rolled out tested. in 14 oblasts. Date 09-Jun-2009 06-Jun-2017 07-Dec-2017 30-Jun-2018 Overall Comments 12/27/2017 Page 3 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270) Intermediate Results Indicators PHINDIRITBL Number of kilometers of roads upgraded (cumulative km) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1,148.00 1,148.00 1,227.00 Date 09-Jun-2009 06-Jun-2017 07-Dec-2017 30-Jun-2018 PHINDIRITBL Works, Goods, and Consulting Services contracts processed and managed by the PMC (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target 28(W);1(G);11( Value 0 (W); 0 (G); 0 (CS) 24(w), (0) G, 9(CS) 26(w), (1) G, 10(CS) CS) Date 09-Jun-2009 06-Jun-2017 07-Dec-2017 30-Jun-2018 PHINDIRITBL Training received by the Committee staff from PMC (staff-hours) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 3,500.00 3,500.00 3,000.00 Date 09-Jun-2009 19-Dec-2016 07-Dec-2017 30-Jun-2018 PHINDIRITBL Updating of road data for Republican roads (% of total length per year) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0% 67.00 67.00 100% Date 09-Jun-2009 19-Dec-2016 07-Dec-2017 30-Jun-2018 12/27/2017 Page 4 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270) PHINDIRITBL Road asset management strategy, Rolling multiyearroad maintenance, and rehabilitation programestablished (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target system in place, tested, system in place, being Value Not established being rolled out in 14 Established tested oblasts. Date 09-Jun-2009 19-Dec-2016 07-Dec-2017 30-Jun-2018 PHINDIRITBL Prepare road safety strategy and action plan (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value Not established Established Established Established Date 09-Jun-2009 18-Dec-2015 18-Dec-2015 30-Jun-2018 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P099270 IBRD-76810 Effective USD 2,125.00 2,125.00 0.00 1,800.90 324.10 85% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P099270 IBRD-76810 Effective 30-Apr-2009 13-Jun-2009 09-Dec-2009 31-Dec-2013 31-Dec-2021 Cumulative Disbursements 12/27/2017 Page 5 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270) Restructuring History Level Approved on 25-Jun-2012 ,Level 1 Approved on 25-Jun-2015 ,Level 1 Approved on 16-Jun-2017 Related Project(s) There are no related projects. 12/27/2017 Page 6 of 6 Public Disclosure Copy