The World Bank Financial Sector Development & Regionalization Project I (FSDRP I) (P121611) REPORT NO.: RES41745 DOCUMENT OF THE WORLD BANK RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF FINANCIAL SECTOR DEVELOPMENT & REGIONALIZATION PROJECT I (FSDRP I) APPROVED ON JANUARY 31, 2011 TO EAC SECRETARIAT,EAST AFRICAN COMMUNITY FINANCE, COMPETITIVENESS AND INNOVATION AFRICA Regional Vice President: Hafez M. H. Ghanem Country Director: Deborah L. Wetzel Regional Director: Asad Alam Practice Manager/Manager: Niraj Verma Task Team Leader(s): Yoko Doi The World Bank Financial Sector Development & Regionalization Project I (FSDRP I) (P121611) I. BASIC DATA Product Information Project ID Financing Instrument P121611 Investment Project Financing Original EA Category Current EA Category Not Required (C) Not Required (C) Approval Date Current Closing Date 31-Jan-2011 30-Jun-2020 Organizations Borrower Responsible Agency EAC Secretariat,East African Community EAC Secretariat Project Development Objective (PDO) Original PDO To establish the foundation for financial sector integration among EAC Partner States. Current PDO To establish the foundation for financial sector integration among EAC Partner States. For the purposes of this additional financing the "foundation of financial sector integrationâ refers to formulating a regional approach to financial inclusion, furthering legal and regulatory harmonization and building institutional capacity to manage the increasingly integrated financial sector in the EAC. Summary Status of Financing Net Ln/Cr/Tf Approval Signing Effectiveness Closing Commitment Disbursed Undisbursed IDA-D1410 30-Sep-2016 11-Nov-2016 15-Feb-2017 30-Jun-2020 10.50 9.35 1.25 IDA-H6410 31-Jan-2011 14-Feb-2011 20-Jun-2011 30-Nov-2016 15.48 14.91 0 The World Bank Financial Sector Development & Regionalization Project I (FSDRP I) (P121611) Policy Waiver(s) Does this restructuring trigger the need for any policy waiver(s)? No I. SUMMARY OF PROJECT STATUS AND PROPOSED CHANGES The last implementation support review of the project was held in February 2020. As per the mission objectives, the mission assessed the progress made since the last Implementation Support Mission(ISM), including identifying actions to further accelerate project implementation and informing the EAC FSDRP Project Administration Team (PAT) of critical project closure procedures such as requisite Financial Management activities and the Implementation Completion Result (ICR) report. As reported in the Aide Memoire the mission noted that substantial progress has been made since the previous ISM in June 2019 resulting in an overall disbursement rate of total IDA project funds of 90%. In terms of the overall project funds granted by the WB, the disbursement ratio is 85% as of March 2020 and 92% if the committed amount is included. Overall while the additional financing project made significant progress and was well in line to achieve the PDO including the completion of Capital Market Infrastructure (CMI) activity by the current closing date, COVID19 has thrown an unexpected challenge to the implementation. Understandably EAC Partner States (PSs) governments and EAC Secretariat took various measures to minimize the outbreak of COVID-19 in the region including the decision to suspend all regional meetings, international/regional travels from/to EAC PSs. As a result a few but key remaining activities including CMI have been affected. Remaining CMI activities including on-site capacity training, User Acceptance Testing (UAT) and Go Live face serious challenges to be completed under the current situation. Given that this is an important part of the project, and considering that so much progress had been achieved and the activity is so close to closure, a six month extension is proposed. With this extension, project development outcomes are expected to be fully achieved and project sustainability enhanced. Conversely not extending, would result in the project coming very close, but faltering at the end on account of the exogenous COVID19 delays, and consequently not fully delivering the CMI, which would adversely impact outcomes. II. DETAILED CHANGES LOAN CLOSING DATE(S) Original Revised Proposed Proposed Deadline Ln/Cr/Tf Status Closing Closing(s) Closing for Withdrawal Applications IDA-D1410 Effective 30-Sep-2019 30-Jun-2020 31-Dec-2020 30-Apr-2021 30-Jun-2015, 29-Feb- 2016, 30-Sep-2016, IDA-H6410 Closed 30-Mar-2014 30-Nov-2016, 31-Jan- 2019 The World Bank Financial Sector Development & Regionalization Project I (FSDRP I) (P121611)