Nigeria For APPEALSP PROCUREMENT PLAN (Textual Part) Project information: [Nigeria] [Agro-Processing, Productivity Enhancement and Livelihood Improvement Support Project] (P53390) Project Implementation agency: [Federal Ministry of Agriculture and Rural Development] Date of the Procurement Plan: [October 25, 2018] Period covered by this Procurement Plan: [October 25, 2018 to December 2018] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works).Not Applicable. Goods: is not applicable Works: is not applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable Other Relevant Procurement Information. The project will use the CDD procurement under this project. CDD manual will be produced by the project. PROCUREMENT Nigeria : Agro-Processing, Productivity Enhancement and Livelihood Improvement Support Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2019-04-26 2021-10-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148616 GPN Date: Project Name: Agro-Processing, Productivity Enhancement and Livelihood Improvement Support Project Loan / Credit No: IDA / 59930 LAGOS APPEALS Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned APPEALSP-LGSCO-CW-01 / Under Renovation of Office, Project Management and Request for Single Stage - One 2020-01- IDA / 59930 Post Limited 27,470.00 27,514.10 Implementat 2019-05-11 2019-05-07 2019-07-06 2019-06-13 Conference Room & Training Coordination Quotations Envelope 02 ion Hall NG-LAGOS APPEALS-158867- CW-RFB / Construction/rehabilitation of Infrastructure Support to Single Stage - Two 2021-07- IDA / 59930 Post Request for Bids Open - National 877,780.00 0.00 Canceled 2020-08-10 2020-08-15 2020-09-26 2020-12-09 2021-01-13 7.9 km Farm Access Roads Agribusiness Clusters Envelope 12 (3.8Km at Igbodu, Epe; 4.1 Km at Erikorodo -Phase 1) NG-LAGOS APPEALS-235890- Request for Bids - Under CW-RFB / Infrastructure Support to Single Stage - One Small Works SPD 2022-03- IDA / 59930 Post Request for Bids Open - National 3,966,280.00 0.00 Implementat 2021-05-27 2021-06-28 2021-06-01 2021-07-12 2021-07-13 2021-07-29 2021-08-12 2021-09-16 Construction/Rehabilitation of Agribusiness Clusters Envelope (1 envelope 15 ion Farm Access Road process) NG-LAGOS APPEALS-235893- Primary processing, Value Request for Bids - Pending CW-RFB / Establishment of 12 Addition, Post-Harvest Single Stage - One Small Works SPD 2022-03- IDA / 59930 Post Request for Bids Open - National 1,833,333.00 0.00 Implementat 2021-06-08 2021-06-13 2021-07-25 2021-08-24 2021-09-28 No.s Cottage Processing Management and Women & Envelope (1 envelope 27 ion Centers Youth Empowerment process) NG-LAGOS APPEALS-235891- Request for Bids - Pending CW-RFB / Infrastructure Support to Single Stage - One Small Works SPD 2022-03- IDA / 59930 Post Request for Bids Open - National 458,333.00 0.00 Implementat 2021-06-08 2021-06-13 2021-07-25 2021-08-24 2021-09-28 Construction/Rehabilitation of Agribusiness Clusters Envelope (1 envelope 27 ion 3 No.s of Aggregation Centers process) NG-LAGOS APPEALS-255550- Technical Assistance, Request for Under CW-RFQ / Establishment of Request for Single Stage - One 2022-06- IDA / 59930 Knowledge Management and Post Limited Quotations (Non 55,556.00 0.00 Implementat 2021-10-10 2021-12-05 Library with Solar Energy Quotations Envelope 03 Communication Bank-SPD) ion (Construction of Library) NG-LAGOS APPEALS-257330- Primary processing, Value Request for Bids - Pending CW-RFB / Construction of Addition, Post-Harvest Single Stage - One Small Works SPD 2022-08- IDA / 59930 Post Request for Bids Open - National 1,549,449.00 0.00 Implementat 2021-10-24 2021-10-29 2021-12-10 2022-01-09 2022-02-13 Cottage and Aggregation Management and Women & Envelope (1 envelope 12 ion Centres Youth Empowerment process) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual APPEALSP-LGSCO-GO-01 / Production of Information, Education &Communication Project Management and Request for Single Stage - One materials / Knowledge IDA / 59930 Post Limited 8,240.00 14,793.04 Signed 2019-05-12 2019-08-05 2019-07-07 2019-08-29 2020-01-03 2020-03-25 Coordination Quotations Envelope sharing materials (Fact sheets, Newsletters, leaflets, handbills, manuals, briefs etc APPEALSP-LGSCO-GO-02 / Procurement of Communication equipment; (1)High Megapixel photo Technical Assistance, Request for Single Stage - One camera, (2)HD Professional IDA / 59930 Knowledge Management and Post Limited 4,330.00 174,430.32 Signed 2019-05-11 2019-05-24 2019-07-06 2019-06-20 2020-01-02 2019-08-27 Quotations Envelope Camera, (3) Medium PAS Communication (1);(4) Big Movable PAS(1),(5) Projector and Screen, (6) Media Mobile device APPEALSP-LGSCO-GO-03 / Technical Assistance, Request for Single Stage - One Production of Promotional IDA / 59930 Knowledge Management and Post Limited 10,990.00 20,470.00 Signed 2019-05-12 2019-05-05 2019-07-07 2019-07-02 2020-01-03 2019-09-06 Quotations Envelope items & Bill Boards/Sign posts Communication APPEALSP-LGSCO-GO-04 / Procurement of Office Furniture: 20 Executive Chairs Project Management and Request for Single Stage - One IDA / 59930 Post Limited 13,740.00 13,713.66 Signed 2019-04-27 2019-05-03 2019-06-22 2019-06-11 2019-12-19 2019-07-19 and Tables; Office fittings (e.g Coordination Quotations Envelope curtains,window blind,railings etc) APPEALSP-LGSCO-GO-05 / Procurement of Electrical Equipment and Appliances, 6 Infrastructure Support to Request for Single Stage - One units of 2HP Airconditioners IDA / 59930 Post Limited 18,930.00 5,099.93 Completed 2019-04-29 2019-04-30 2019-06-24 2019-05-31 2019-12-21 2019-09-06 Agribusiness Clusters Quotations Envelope for the training Hall, 30 units of fanS, calculators and Casting machine. APPEALSP-LGSCO-GO-06 / Provision of Alternative Source Infrastructure Support to Request for Single Stage - One of Energy for SCO (Inverter IDA / 59930 Post Limited 27,470.00 74,034.50 Signed 2019-05-14 2019-05-10 2019-07-09 2019-07-02 2020-01-05 2020-05-08 Agribusiness Clusters Quotations Envelope System/ Battery Banks and accessories etc) Page 1 APPEALSP-LGSCO-GO-07 / Procurement of computers and accessories: 20 Nos Computer Laptops with carrier bags for projects officers, Project Management and Request for Single Stage - One IDA / 59930 Post Limited 28,830.00 56,284.84 Signed 2019-04-30 2019-05-02 2019-06-25 2019-07-01 2019-12-22 2019-07-31 External hard drive(EHD) and Coordination Quotations Envelope Flash drives, 20 units of Modem, Printers and Scanners, Global Positioning System (GPS) APPEALSP-LGSCO-GO-08 / Procurement of the following soft wares: 10 units of Database tracking soft ware, Project Management and Request for Single Stage - One IDA / 59930 Post Limited 21,560.00 15,595.85 Completed 2019-04-30 2019-07-15 2019-06-25 2019-07-16 2019-12-22 2019-08-06 5 users Smart draw for Coordination Quotations Envelope excelent chart and reporting; Computer aided design CAD Soft wares APPEALSP-LGSCO-GO-09 / Project Management and Request for Single Stage - One Procurement of 1 unit of IDA / 59930 Post Limited 71,430.00 53,244.42 Signed 2019-05-20 2019-05-30 2019-07-15 2019-06-28 2020-01-11 Coordination Quotations Envelope project Utility vehicle NG-LAGOS APPEALS-158835- Primary processing, Value GO-RFQ / Procurement of Addition, Post-Harvest Request for Single Stage - One IDA / 59930 Post Limited 83,330.00 229,662.72 Signed 2020-04-28 2020-04-23 2020-06-23 2020-05-06 2020-12-20 2020-06-02 facilities for the Establishment Management and Women & Quotations Envelope of Farmers Markets Youth Empowerment NG-LAGOS APPEALS-158940- Project Management and Request for Single Stage - One GO-RFQ / Procurement of 2 IDA / 59930 Post Limited 154,000.00 138,069.27 Signed 2020-03-28 2020-03-30 2020-05-23 2020-04-24 2020-11-19 2020-04-28 Coordination Quotations Envelope Utility vehicles NG-LAGOS APPEALS-158738- Primary processing, Value GO-RFQ / Procurement of Addition, Post-Harvest Request for Single Stage - One IDA / 59930 Post Limited 27,780.00 0.00 Canceled 2020-09-26 2020-11-21 2021-05-20 facilities for the Establishment Management and Women & Quotations Envelope of One-Stop-Shop Youth Empowerment APPEALSP-LGSCO-GO-9C / Technical Assistance, Pending Procurement of (Furniture, Request for Single Stage - One IDA / 59930 Knowledge Management and Post Limited 27,778.00 0.00 Implementati 2021-08-08 2021-10-03 2022-04-01 Workstation etc)for the Quotations Envelope Communication on Establishment of Library APPEALSP-LGSCO-GO-08C / Technical Assistance, Pending Procurement of knowleged Request for Single Stage - One IDA / 59930 Knowledge Management and Post Limited 27,778.00 0.00 Implementati 2021-08-04 2021-09-29 2022-03-28 material repository for Quotations Envelope Communication on Development of e-library NG-LAGOS APPEALS-257362- GO-RFB / Procurement and Pending Infrastructure Support to Single Stage - One Installation of Energy IDA / 59930 Post Request for Bids Open - National 194,444.00 0.00 Implementati 2021-10-20 2021-10-25 2021-12-06 2022-01-05 2022-02-09 2022-08-08 Agribusiness Clusters Envelope interventions for production on clusters NG-LAGOS APPEALS-255548- Primary processing, Value GO-RFQ / Procurement and Pending Addition, Post-Harvest Request for Single Stage - One Installation of Solar Powered IDA / 59930 Post Limited 97,223.00 0.00 Implementati 2021-10-05 2021-11-30 2022-05-29 Management and Women & Quotations Envelope Mobile Market kiosk (Eko City on Youth Empowerment Neighbourhood Market) NG-LAGOS APPEALS-255568- GO-RFQ / Procurement and Pending Infrastructure Support to Single Stage - One Installation of Energy IDA / 59930 Post Request for Bids Open - National 194,444.00 0.00 Implementati 2021-10-20 2021-10-25 2021-12-06 2022-01-05 2022-02-09 2022-08-08 Agribusiness Clusters Envelope interventions for production on clusters NG-LAGOS APPEALS-257344- Primary processing, Value GO-RFB / Procurement, Pending Addition, Post-Harvest Single Stage - One Supply and Installation of IDA / 59930 Post Request for Bids Open - National 856,799.69 0.00 Implementati 2021-10-27 2021-11-01 2021-12-13 2022-01-12 2022-02-16 2022-08-15 Management and Women & Envelope Equipment for 15 No.s on Youth Empowerment Cottage and Aggregation Centres NG-LAGOS APPEALS-258428- Primary processing, Value GO-RFQ / Provision of 10 NOs Pending Addition, Post-Harvest Request for Single Stage - One solar powered Market kiosks IDA / 59930 Post Limited 97,000.00 0.00 Implementati 2021-10-20 2021-12-15 2022-06-13 Management and Women & Quotations Envelope For SMEs across the 3 value on Youth Empowerment chain NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-LAGOS APPEALS-156950- Consultant CS-CQS / Feasibility study on Production and Productivity IDA / 59930 Post Qualification Open - National 40,280.00 0.00 Under Review 2020-04-30 2020-06-04 2020-05-21 2020-09-14 2020-07-04 2020-07-20 2020-08-03 2020-09-07 2021-03-06 the establishment of bird Enhancement Selection hatchery in the State NG-LAGOS APPEALS-162010- CS-CQS / Engagement of a Primary processing, Value Consultants for the facilitation Consultant Addition, Post-Harvest of all activities for the PWDs IDA / 59930 Post Qualification Open - National 33,330.00 0.00 Under Review 2020-03-09 2020-03-20 2020-03-30 2020-05-13 2020-06-12 2020-07-17 2021-01-13 Management and Women & (Training, Mentoring, Selection Youth Empowerment Monitoring etc) support under the WYEP NG-LAGOS APPEALS-162013- Primary processing, Value CS-CQS / Engagement of Consultant Addition, Post-Harvest Consultancy to facilitate IDA / 59930 Post Qualification Open - National 27,780.00 0.00 Under Review 2020-05-25 2019-06-20 2020-06-15 2020-07-29 2020-08-28 2020-10-02 2021-03-31 Management and Women & International Market Selection Youth Empowerment Expectation for Aquaculture Page 2 NG-LAGOS APPEALS-161811- Primary processing, Value Consultant CS-CQS / Feasibility Study on Addition, Post-Harvest Under IDA / 59930 Post Qualification Open - National 27,780.00 0.00 2020-04-20 2020-05-28 2020-05-11 2020-06-24 2020-07-24 2020-08-28 2021-02-24 production of Egg Powder Management and Women & Implementation Selection technology in the State. Youth Empowerment NG-LAGOS APPEALS-161999- CS-CQS / Technical Consultant Assistance for the conduct of Production and Productivity IDA / 59930 Post Qualification Open - National 27,780.00 0.00 Canceled 2020-03-31 2020-04-21 2020-06-04 2020-07-04 2020-08-08 2021-02-04 Need Assessment for the Enhancement Selection selected value chains of Poultry, Aquaculture and Rice. NG-LAGOS APPEALS-162000- CS-CQS / Consultancy to Consultant source for climate smart, Production and Productivity IDA / 59930 Post Qualification Open - National 27,780.00 0.00 Canceled 2020-05-18 2020-06-08 2020-07-22 2020-08-21 2020-09-25 2021-03-24 nutrition sensitive and Enhancement Selection improved technologies to enhance Farmers productivity NG-LAGOS APPEALS-162005- Technical Assistance, Consultant CS-CQS / Consultancy on IDA / 59930 Knowledge Management and Post Qualification Open - National 27,880.00 0.00 Canceled 2020-06-09 2020-06-30 2020-08-13 2020-09-12 2020-10-17 2021-04-15 Production of Project Communication Selection Documentary NG-LAGOS APPEALS-162001- Consultant CS-CQS / Technical Support Project Management and IDA / 59930 Post Qualification Open - National 27,780.00 0.00 Canceled 2020-04-28 2020-05-19 2020-07-02 2020-08-01 2020-09-05 2021-03-04 to strengthen the fiduciary Coordination Selection system of the Project NG-LAGOS APPEALS-162006- CS-CQS / Technical Technical Assistance, Consultant Assistance on Production of IDA / 59930 Knowledge Management and Post Qualification Open - National 41,670.00 0.00 Canceled 2020-04-29 2020-05-20 2020-07-03 2020-08-02 2020-09-06 2021-03-05 Knowledge and learning Communication Selection products NG-LAGOS APPEALS-162008- CS-CQS / Consultancy Consultant services for the Enviromental Project Management and IDA / 59930 Post Qualification Open - National 33,330.00 0.00 Canceled 2020-03-23 2020-04-13 2020-05-27 2020-06-26 2020-07-31 2021-01-27 and Social Impact Assesmemt Coordination Selection (including ESMP) for Rural Infrastructural support NG-LAGOS APPEALS-158859- Consultant CS-CQS / Engagement of Infrastructure Support to IDA / 59930 Post Qualification Open - National 36,105.55 0.00 Canceled 2020-04-15 2020-05-06 2020-06-19 2020-07-19 2020-08-23 2021-02-19 Consultant for the Design of Agribusiness Clusters Selection 14.66 Km Farm Access Road. NG-LAGOS APPEALS-162012- CS-CQS / Consultancy on Primary processing, Value Market Sensitivity Analysis Consultant Addition, Post-Harvest and Determination of IDA / 59930 Post Qualification Open - National 27,780.00 0.00 Canceled 2020-04-30 2020-05-21 2020-07-04 2020-08-03 2020-09-07 2021-03-06 Management and Women & Consumer Preference for Selection Youth Empowerment Poultry, Aquaculture and Rice value chains INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual APPEALSP-LGSCO-CS-01 / Consultancy on the conduct of Primary processing, Value Individual Technical Feasibility Studies Addition, Post-Harvest IDA / 59930 Post Consultant Limited 13,740.00 13,793.10 Completed 2019-04-18 2019-06-26 2019-04-23 2019-05-03 2019-05-14 2019-07-04 2019-06-18 2019-08-23 2019-12-15 2019-12-06 on Market Information / Management and Women & Selection Opprtunities for the selected Youth Empowerment value chains in the State. APPEALSP-LGSCO-CS-02 / Consultancy for the Technical Assistance, Individual engagement of Technical IDA / 59930 Knowledge Management and Post Consultant Limited 13,740.00 0.00 Canceled 2019-05-19 2019-06-26 2019-05-24 2019-06-14 2019-07-19 2020-01-15 assistant to strengthen the Communication Selection financial management of the Project. APPEALSP-LGSCO-CS-03 / Technical Assistance, Individual Conduct of Survey on effective IDA / 59930 Knowledge Management and Post Consultant Limited 13,740.00 0.00 Canceled 2019-05-21 2019-06-26 2019-05-26 2019-07-30 2019-06-16 2019-07-21 2020-01-17 communication channels in Communication Selection Lagos State APPEALSP-LGSCO-CS-04 / Individual Engagement of consultant for Project Management and IDA / 59930 Post Consultant Limited 8,240.00 13,226.06 Under Review 2019-09-26 2019-06-26 2019-10-01 2019-08-01 2019-10-22 2019-09-26 2019-11-26 2019-09-13 2020-05-24 2020-01-22 the development of greivance Coordination Selection redress mechanism(GRM) APPEALSP-LGSCO-CS-05 / Technical Assistance, Individual Production & Airing of Jingles IDA / 59930 Knowledge Management and Post Consultant Limited 13,740.00 13,679.90 Under Review 2019-04-29 2019-06-26 2019-05-04 2019-06-27 2019-05-25 2019-07-26 2019-06-29 2019-08-05 2019-12-26 2020-03-02 (Yoruba, English, Pidgin on Communication Selection Radio NG-LAGOS APPEALS-162004- CS-INDV / Consultancy on Technical Assistance, Individual News feature of project IDA / 59930 Knowledge Management and Post Consultant Limited 19,440.00 0.00 Under Review 2020-03-31 2019-07-03 2020-04-05 2020-04-26 2020-05-31 2020-11-27 activities in print and Communication Selection electronic media NG-LAGOS APPEALS-158943- Technical Assistance, Individual CS-INDV / Conduct of Survey IDA / 59930 Knowledge Management and Post Consultant Limited 27,780.00 0.00 Under Review 2020-04-20 2020-07-07 2020-04-25 2020-05-16 2020-06-20 2020-12-17 on effective communication Communication Selection channels in Lagos State NG-LAGOS APPEALS-158856- Individual Project Management and CS-INDV / Consultancy for IDA / 59930 Post Consultant Limited 8,330.00 0.00 Canceled 2020-06-10 2020-06-15 2020-07-06 2020-08-10 2021-02-06 Coordination GBV mapping in the State Selection NG-LAGOS APPEALS-158845- CS-INDV / Engagement of Individual Infrastructure Support to Consultant for preparation of IDA / 59930 Post Consultant Limited 13,890.00 0.00 Canceled 2020-09-23 2020-09-28 2020-10-19 2020-11-23 2021-05-22 Agribusiness Clusters ESMP for 3NO Cottage Selection Industries Page 3 NG-LAGOS APPEALS-158903- Individual CS-INDV / Consultancy on the Infrastructure Support to IDA / 59930 Post Consultant Limited 16,670.00 0.00 Canceled 2020-04-15 2020-04-20 2020-05-11 2020-06-15 2020-12-12 Design and Supervision of Agribusiness Clusters Selection Energy Interventions NG-LAGOS APPEALS-158889- CS-INDV / Engagement of Individual Infrastructure Support to consultant for the Design of 2 IDA / 59930 Post Consultant Limited 25,000.00 0.00 Canceled 2020-04-24 2020-04-29 2020-05-20 2020-06-24 2020-12-21 Agribusiness Clusters Nos of Jetties (Badagry; Selection Agbowa) NG-LAGOS APPEALS-158916- Individual CS-INDV / Engagement of Project Management and IDA / 59930 Post Consultant Limited 27,780.00 0.00 Canceled 2020-10-19 2020-10-24 2020-11-14 2020-12-19 2021-06-17 Technical Assistant on Coordination Selection Agricultural Production Survey Individual APPEALSP-LGSCO-CS-03C / Infrastructure Support to IDA / 59930 Post Consultant Limited 19,444.00 0.00 Under Review 2021-06-22 2021-07-08 2021-06-27 2021-07-18 2021-08-22 2022-02-18 Design of Energy for Clusters Agribusiness Clusters Selection APPEALSP-LGSCO-CS-02C / Individual Infrastructure Support to Engagement of consultant for IDA / 59930 Post Consultant Limited 20,834.00 14,792.20 Signed 2021-05-29 2021-07-08 2021-06-03 2021-07-12 2021-06-24 2021-08-11 2021-07-29 2021-07-09 2022-01-25 Agribusiness Clusters the design of Jetties Selection Individual NG-LAGOS APPEALS-158941- Project Management and IDA / 59930 Post Consultant Limited 13,890.00 0.00 Canceled 2020-04-02 2020-04-07 2020-04-28 2020-06-02 2020-11-29 CS-INDV / Market Price Survey Coordination Selection NG-LAGOS APPEALS-257364- CS-INDV / Consultancy on the Individual Preparation of ESIA for Lagos Project Management and Pending IDA / 59930 Post Consultant Limited 19,440.00 0.00 2021-10-12 2021-10-17 2021-11-07 2021-12-12 2022-06-10 APPEALS on priority value Coordination Implementation Selection Chains on Poultry, rice and Aquaculture NG-LAGOS APPEALS-257365- Individual CS-INDV / Baseline Survey on Project Management and Under IDA / 59930 Post Consultant Limited 18,060.00 0.00 2021-10-10 2021-10-04 2021-10-15 2021-11-05 2021-12-10 2022-06-08 Pest Management in Lagos Coordination Implementation Selection APPEALS NG-LAGOS APPEALS-255546- CS-INDV / Engagement of Consultant for preparation of Individual Project Management and Under Enviromental and Social IDA / 59930 Post Consultant Limited 30,556.00 0.00 2021-09-29 2021-10-04 2021-10-04 2021-10-25 2021-11-29 2022-05-28 Coordination Implementation Management Plan (ESMP) for Selection Rural Infrastructural support for Lagos State NG-LAGOS APPEALS-255553- CS-INDV / Engagement of Individual Project Management and Pending Consultant for preparation of IDA / 59930 Post Consultant Limited 25,000.00 0.00 2021-10-04 2021-10-09 2021-10-30 2021-12-04 2022-06-02 Coordination Implementation ESMP for 12 NO Cottage Selection Industries NG-LAGOS APPEALS-255558- CS-INDV / Consultancy on Primary processing, Value Individual strategies for Market Addition, Post-Harvest Pending IDA / 59930 Post Consultant Limited 16,667.00 0.00 2021-10-11 2021-10-16 2021-11-06 2021-12-11 2022-06-09 Development and Growth for Management and Women & Implementation Selection the value chains of Youth Empowerment Aquaculture, Rice and Poultry. NG-LAGOS APPEALS-257361- Individual Project Management and Pending CS-INDV / Conduct of Ouput IDA / 59930 Post Consultant Limited 16,670.00 0.00 2021-10-20 2021-10-25 2021-11-15 2021-12-20 2022-06-18 Coordination Implementation Survey Selection NG-LAGOS APPEALS-257360- Individual Project Management and Pending CS-INDV / Technology IDA / 59930 Post Consultant Limited 16,670.00 0.00 2021-10-20 2021-10-25 2021-11-15 2021-12-20 2022-06-18 Coordination Implementation Adoption Survey Selection NG-LAGOS APPEALS-257367- CS-INDV / Engagement of Individual Infrastructure Support to Individual consultant for the IDA / 59930 Post Consultant Limited 33,334.00 0.00 Under Review 2021-10-20 2021-10-11 2021-10-25 2021-11-15 2021-12-20 2022-06-18 Agribusiness Clusters supervision of farm access Selection roads NG-LAGOS APPEALS-257358- CS-INDV / Engagement of Individual Project Management and Pending Individual Consultant for IDA / 59930 Post Consultant Limited 16,670.00 0.00 2021-10-20 2021-10-25 2021-11-15 2021-12-20 2022-06-18 Coordination Implementation conduct of Household Survey Selection (Lagos APPEALS) NG-LAGOS APPEALS-257355- CS-INDV / Engagement of Individual Individual Consultant for Project Management and Pending IDA / 59930 Post Consultant Limited 16,670.00 0.00 2021-10-20 2021-10-25 2021-11-15 2021-12-20 2022-06-18 conduct of APPEALS Coordination Implementation Selection CIG/Cluster Assessment Survey Page 4