test PROCUREMENT Mozambique : Mozambique Forest Investment Project PLAN General Information Country: Mozambique Banks Approval Date of the Original Procurement Plan: 2017-02-15 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-08-06 Project ID: P160033 GPN Date: Project Name: Mozambique Forest Investment Project Loan / Credit No: IDA / 59590, TF / A4296 Executing Agency(ies): MINISTRY OF LAND, ENVIRONMENT AND RURAL DEVELOPMENT - International Funds Management Unit WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 09/MFIP/W/2017 / Reabilitation Project Coordination and Single Stage - One IDA / 59590 Post Request for Bids Open - National 400,000.00 270,957.71 Signed 2017-06-29 2017-06-12 2017-07-04 2017-08-15 2017-08-17 2017-09-14 2017-09-06 2017-10-19 2017-10-30 2018-04-17 of SPGC Office in Pemba Management Envelope GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Coordination and Single Stage - One Pending 05/G/MFIP/2017 / Vehicles Post Request for Bids Open - National 1,440,000.00 0.00 2017-04-27 2017-05-02 2017-06-13 2017-07-13 2017-08-17 2018-02-13 Management Envelope Implementation 06/MFIP/G/2017 / Furniture Project Coordination and Request for Single Stage - One Pending Post Open - National 20,000.00 0.00 2017-04-09 2017-06-04 2017-12-01 Equipament Management Quotations Envelope Implementation 37/MFIP/G/2017 / IT Strengthening the Enabling Request for Single Stage - One Equipament for UATA in the IDA / 59590 Conditions for Sustainable Post Limited 20,000.00 18,868.76 Signed 2018-02-25 2018-02-15 2018-04-22 2018-03-30 2018-10-19 Quotations Envelope Scope of PNDT Forest Management 80/MFIP/G/2018 / supply and Project Coordination and Single Stage - One Pending IDA / 59590 Post Request for Bids Open - International 114,842.81 0.00 2018-03-30 2018-04-04 2018-05-16 2018-06-15 2018-07-20 2019-01-16 installation of software Management Envelope Implementation 01 /MFIP/G/2017 / IT Project Coordination and Request for Single Stage - One Equipament for Nampula & Cabo IDA / 59590 Post Open - National 20,000.00 0.00 Canceled 2018-03-05 2018-04-30 2018-10-27 Management Quotations Envelope Delgado Project Coordination and Request for Single Stage - One 08/MFIP/G/2017 / Uniform Post Open - National 44,000.00 0.00 Canceled 2017-05-09 2017-07-04 2017-12-25 Management Quotations Envelope 10 /G/MFIP/2017 / IT Promoting Integrated Landscape Request for Single Stage - One Post Open - National 36,000.00 0.00 Canceled 2017-04-10 2017-06-05 2017-12-02 Equipament Management Quotations Envelope 04/MFIP/G/2017 / Technological Project Coordination and Request for Single Stage - One Post Open - National 3,000.00 0.00 Canceled 2017-04-10 2017-06-05 2017-12-04 field equipament Management Quotations Envelope 03/G/MFIP/2017 / Camping Project Coordination and Request for Single Stage - One Post Open - National 32,000.00 0.00 Canceled 2017-06-06 2017-08-01 2018-01-28 Equipament Management Quotations Envelope Strengthening the Enabling 12/G/MFIP/2017 / Office Request for Single Stage - One Conditions for Sustainable Post Open - National 50,000.00 0.00 Canceled 2017-04-10 2017-06-05 2017-12-01 Supplies Quotations Envelope Forest Management Strengthening the Enabling 10/MFIP/G/2017 / IT Request for Single Stage - One Conditions for Sustainable Post Open - National 36,000.00 0.00 Canceled 2017-03-08 2017-05-03 2017-10-30 Equipament ( Distics) Quotations Envelope Forest Management 11/MFIP/G/2017 / IT Promoting Integrated Landscape Request for Single Stage - One Post Open - National 50,000.00 0.00 Canceled 2017-03-08 2017-05-03 2017-10-30 Equipament Management Quotations Envelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 86/MFIP/IC/2018 / Communication firm (production Project Coordination and Request for Single Stage - One IDA / 59590 Post Open - National 58,000.00 0.00 Canceled 2018-05-28 2018-07-23 2019-01-19 of communication and Management Quotations Envelope safeguards materials) 86/MFIP/NCS/2018 / Promoting Integrated Landscape IDA / 59590 Post Direct Selection Direct 58,000.00 0.06 Signed 2018-06-18 2018-04-20 2018-06-23 2018-05-15 2018-07-28 2018-05-30 2019-01-24 Communication firm Management CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 16 /CS/MFIP/2017 / Periodic Project Coordination and Quality And Cost- Pending evaluation of forestry governance Post Open - National 200,000.00 0.00 2018-01-30 2018-02-20 2018-04-05 2018-05-03 2018-06-04 2018-07-09 2018-08-13 2019-08-13 Management Based Selection Implementation and forestry concessionaire 17/MFIP/CS/2017 / Preparation Project Coordination and Quality And Cost- IDA / 59590 Prior Open - International 4,000,000.00 4,412,500.00 Signed 2017-01-30 2017-02-17 2017-02-20 2017-03-07 2017-04-05 2017-07-10 2017-05-03 2017-08-03 2017-06-02 2017-10-13 2017-07-07 2018-01-12 2017-08-11 2018-01-18 2018-08-11 of national spatial planning plan Management Based Selection 13 /MFIP/CS/2017 / Service Provider t osupport sustainable Project Coordination and Quality And Cost- Under commercial plantations & IDA / 59590 Prior Open - International 9,900,000.00 0.00 2017-03-29 2017-02-17 2017-04-19 2017-03-07 2017-06-02 2017-07-18 2017-06-30 2017-09-09 2017-07-31 2017-10-14 2017-09-04 2018-05-04 2017-10-09 2021-10-08 Management Based Selection Implementation implementation of agroforestry system Page 1 Strengthening the Enabling 22/MFIP/CS/2017 / Project Pending Conditions for Sustainable Post Least Cost Selection Open - National 50,000.00 0.00 2017-04-06 2017-04-27 2017-06-08 2017-07-06 2017-08-07 2017-09-11 2017-10-16 2018-04-14 Audits Implementation Forest Management 21/MFIP/CS/2017 / Preparation Promoting Integrated Landscape Quality And Cost- Pending Post Open - International 250,000.00 0.00 2017-07-12 2017-08-02 2017-09-15 2017-10-13 2017-11-12 2017-12-17 2018-01-21 2019-01-21 of A- Grievence Mechanism Management Based Selection Implementation 28/MFIP/CS/2017 / Hiring a FAO 1-Forest Information System 2- Promoting Integrated Landscape Registry 3- Training 4-forest IDA / 59590 Prior UN Agencies (Direct) Direct 5,902,144.00 5,902,144.00 Signed 2017-07-25 2017-07-10 2018-01-21 Management management plan 5-DINAF capacity building 6- Small forestry business promotion 18 /CS/MFIP/2017 / Service Project Coordination and Quality And Cost- Provider for Systematic Prior Open - International 2,280,000.00 0.00 Canceled 2018-01-30 2017-02-17 2018-02-20 2017-05-18 2018-04-05 2018-05-03 2018-06-02 2018-07-07 2018-08-13 2021-08-12 Management Based Selection Community land Delimitation 20/MFIP/CS/2017 / Development Promoting Integrated Landscape Quality And Cost- of the action plan for law Prior Open - International 1,750,000.00 0.00 Canceled 2017-02-21 2017-06-06 2017-03-14 2017-06-06 2017-04-27 2017-05-25 2017-06-24 2017-07-29 2017-09-02 2018-09-02 Management Based Selection enforcement inter - agencies 15/MFIP/CS/2017 / Service Promoting Integrated Landscape Quality And Cost- Provider for training biomass IDA / 59590 Prior Open - International 500,000.00 0.00 Canceled 2017-04-10 2017-02-19 2017-05-01 2017-03-07 2017-06-14 2017-07-13 2017-07-12 2017-09-06 2017-08-11 2017-10-18 2017-09-15 2017-12-29 2017-10-20 2018-10-20 Management Based Selection producers 37/MFIP/CS/2018 / Hiring a Consultant service provider for training Promoting Integrated Landscape Under IDA / 59590 Post Qualification Open - National 300,000.00 0.00 2018-02-07 2018-02-13 2018-02-28 2018-02-15 2018-04-13 2018-04-23 2018-05-13 2018-07-24 2018-06-17 2018-12-14 Biomass producer in Cabo Management Implementation Selection Delgado Province 38/MFIP/CS/2018 / Technical Project Coordination and Quality And Cost- Assistance for AQUA ( IDA / 59590 Prior Open - International 1,750,000.00 0.00 Canceled 2018-02-28 2018-02-21 2018-03-21 2018-03-01 2018-05-04 2018-06-01 2018-07-01 2018-08-05 2018-09-09 2019-09-09 Management Based Selection environmental quality agency) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 31/MFIP/IC//2017 / Project Coordination and Individual Consultant Administrative & Financial Post Open 12,000.00 0.00 Canceled 2017-04-20 2017-10-27 2017-06-07 2017-06-28 2017-08-02 2018-08-02 Management Selection Assistant 27/MFIP/IC/2017 / Forestry Project Coordination and Individual Consultant IDA / 59590 Post Open 9,600.00 0.00 Canceled 2017-04-26 2017-10-25 2017-06-14 2017-07-05 2017-08-09 2018-02-05 Technician Management Selection 32/MFIP/IC/2017 / Forestry Project Coordination and Individual Consultant IDA / 59590 Post Open 9,600.00 0.00 Canceled 2017-04-26 2017-10-25 2017-06-14 2017-07-05 2017-08-09 2018-02-05 Technician Management Selection 28/MFIP/IC/2017 / Provincial Project Coordination and Individual Consultant Post Open 18,000.00 0.00 Canceled 2017-04-20 2017-06-07 2017-06-28 2017-08-02 2018-08-02 Delegate Management Selection 33/MFIP/IC/2017 / Low Project Coordination and Individual Consultant Enforcement Advisory for AQUA - IDA / 59590 Post Open 36,000.00 120,000.00 Signed 2017-06-05 2017-06-04 2017-07-24 2017-11-21 2017-08-14 2017-11-21 2017-09-18 2017-11-21 2018-03-17 Management Selection Maputo 35/MFIP/IC/2017 / Human Project Coordination and Individual Consultant IDA / 59590 Post Open 12,000.00 0.00 Canceled 2017-06-25 2017-10-25 2017-06-25 2017-06-25 2017-07-16 2018-01-12 Resources for Zambezia Management Selection 23/MFIP/IC/2017 / law Project Coordination and IDA / 59590 Post Direct Selection Direct 36,000.00 0.00 Canceled 2017-06-19 2017-06-29 2017-09-02 2018-09-02 enforcement advisor para AQUA Management 25/MFIP/IC/2017 / Human Project Coordination and Post Direct Selection Direct 12,000.00 0.00 Canceled 2017-02-15 2017-02-25 2017-05-01 2017-10-28 Resources Management 36/MFIP/CS/2017 / Service Promoting Integrated Landscape Provider for Sistematic IDA / 59590 Prior Direct Selection Direct 2,280,000.00 2,025,041.37 Signed 2017-11-08 2017-11-30 2017-11-18 2017-10-05 2018-01-22 2017-10-06 2018-07-21 Management community land delimitation 36/MFIP/IC/2017 / Supervision Promoting Integrated Landscape Individual Consultant Under Work for Reabilitation of SPGC TF / A4296 Post Open 40,000.00 0.00 2017-12-20 2018-03-07 2018-02-07 2018-03-29 2018-02-28 2018-06-28 2018-04-04 2018-10-01 Management Selection Implementation OffIce in Cabo Delgado 39/MFIP/IC/2018 / Project Coordination and IDA / 59590 Post Direct Selection Direct 11,520.00 14,400.00 Signed 2018-03-12 2018-03-22 2018-01-03 2018-05-26 2017-06-01 2018-11-22 Communication officer Maputo Management 40/MFIP/IC/2018 / Coordinator In Project Coordination and IDA / 59590 Post Direct Selection Direct 15,000.00 15,000.00 Signed 2018-03-13 2016-05-19 2018-03-23 2018-01-02 2018-05-27 2016-06-01 2018-11-23 Zambezia Province Management 41/MFIP/IC/2018 / Safeguards Project Coordination and IDA / 59590 Post Direct Selection Direct 26,250.00 26,250.00 Signed 2018-03-13 2015-03-18 2018-03-23 2018-01-02 2018-05-27 2017-07-01 2018-11-23 Officer Management 43/MFIP/IC/2018 / Project Coordination and Administrative Assistant Cabo IDA / 59590 Post Direct Selection Direct 14,000.00 0.00 Canceled 2018-03-12 2018-03-22 2018-05-26 2018-11-22 Management Delgado 45/MFIP/IC/2018 / Forestry Project Coordination and IDA / 59590 Post Direct Selection Direct 41,800.00 44,000.00 Signed 2018-03-14 2017-08-22 2018-03-24 2017-08-24 2018-05-28 2017-09-01 2018-11-24 Specialist Management 46/MFIP/IC/2018 / Fip Project Coordination and IDA / 59590 Post Direct Selection Direct 75,240.00 95,040.00 Signed 2018-03-13 2018-01-02 2018-03-23 2017-08-03 2018-05-27 2017-09-01 2018-11-23 Coordinator Management 48/MFIP/IC/2018 / TECHNICAL Project Coordination and IDA / 59590 Post Direct Selection Direct 19,200.00 39,600.00 Signed 2018-03-14 2015-08-26 2018-03-24 2016-10-10 2018-05-28 2016-10-01 2018-11-24 ASSISTANT FIP-MAPUTO Management 49/MFIP/IC/2018 / LAWYER Project Coordination and IDA / 59590 Post Direct Selection Direct 74,000.00 79,200.00 Signed 2018-03-14 2018-03-29 2018-03-24 2018-01-03 2018-05-28 2018-01-01 2018-11-24 MOZFIP MAPUTO Management Page 2 50/MFIP/IC/2018 / PROJECT Project Coordination and IDA / 59590 Post Direct Selection Direct 40,500.00 48,600.00 Signed 2018-03-13 2017-01-05 2018-03-23 2016-11-21 2018-05-27 2017-01-02 2018-11-23 COORDINATOR REED Management Project Coordination and 52/MFIP/IC/2018 / Economist IDA / 59590 Post Direct Selection Direct 60,000.00 65,000.00 Signed 2018-03-14 2017-01-20 2018-03-24 2017-01-20 2018-05-28 2017-02-01 2018-11-24 Management 53/MFIP/IC/2017 / MRV Project Coordination and IDA / 59590 Post Direct Selection Direct 22,000.00 21,120.00 Signed 2018-03-15 2018-03-25 2018-04-02 2018-05-29 2017-05-01 2018-11-25 ASSISTANT Management 54/MFIP/IC/2018 / MRV Project Coordination and IDA / 59590 Post Direct Selection Direct 22,000.00 22,000.00 Signed 2018-03-14 2017-03-14 2018-03-24 2017-04-25 2018-05-28 2017-05-01 2018-11-24 ASSISTANT 3 Management 55/MFIP/IC/2018 / MRV Project Coordination and IDA / 59590 Post Direct Selection Direct 22,000.00 22,000.00 Signed 2018-03-14 2018-01-02 2018-03-24 2017-04-25 2018-05-28 2018-04-01 2018-11-24 ASSISTANT 2 Management 57/MFIP/IC/2018 / MRV Project Coordination and IDA / 59590 Post Direct Selection Direct 22,000.00 22,000.00 Signed 2018-03-14 2017-03-14 2018-03-24 2017-04-25 2018-05-28 2017-05-01 2018-11-24 ASSISTANT 4 Management 58/MFIP/IC/2017 / FIP CO Project Coordination and IDA / 59590 Post Direct Selection Direct 61,600.00 61,600.00 Signed 2018-03-19 2016-05-02 2018-03-29 2017-02-24 2018-06-02 2017-05-01 2018-11-29 COORDINATOR Management 59/MFIP/IC/2018 / FIP Project Coordination and IDA / 59590 Post Direct Selection Direct 25,000.00 25,000.00 Signed 2018-03-20 2018-03-23 2018-03-30 2018-02-21 2018-06-03 2017-10-16 2018-11-30 MANAGER Management 60/MFIP/IC/2018 / INTERNAL Project Coordination and IDA / 59590 Post Direct Selection Direct 14,000.00 14,000.00 Signed 2018-03-20 2017-05-02 2018-03-30 2017-04-20 2018-06-03 2017-06-01 2018-11-30 AUDITOR MAPUTO Management 61/MFIP/IC/2018 / LAND Project Coordination and IDA / 59590 Post Direct Selection Direct 12,600.00 12,600.00 Signed 2018-03-20 2017-01-30 2018-03-30 2017-02-15 2018-06-03 2017-04-20 2018-11-30 ASSISTANT CABO DELGADO Management 63/MFIP/IC/2018 / COMMUNITY Project Coordination and DEVELOPMENT ASSISTANT IDA / 59590 Post Direct Selection Direct 14,000.00 14,000.00 Signed 2018-03-20 2018-03-08 2018-03-30 2018-01-03 2018-06-03 2017-05-30 2018-11-30 Management ZAMBEZIA 64/MFIP/IC/2018 / BIOMASS Project Coordination and ENERGY SPECIALIST AND IDA / 59590 Post Direct Selection Direct 14,000.00 14,000.00 Signed 2018-03-20 2018-01-02 2018-03-30 2018-01-02 2018-06-03 2017-05-29 2018-11-30 Management NATIVE FORESTS 65/MFIP/IC/2018 / DONAF Project Coordination and IDA / 59590 Post Direct Selection Direct 14,000.00 14,000.00 Signed 2018-03-20 2017-04-26 2018-03-30 2018-03-15 2018-06-03 2017-05-03 2018-11-30 ADVISOR Management Project Coordination and 66/MFIP/IC/2018 / I.T MAPUTO IDA / 59590 Post Direct Selection Direct 12,000.00 12,000.00 Signed 2018-03-20 2018-01-02 2018-03-30 2018-01-02 2018-06-03 2017-06-30 2018-11-30 Management 67/MFIP/IC/2018 / Project Coordination and MONITORING AND IDA / 59590 Post Direct Selection Direct 21,000.00 36,000.00 Signed 2018-03-20 2018-01-02 2018-03-30 2018-01-03 2018-06-03 2017-08-17 2018-11-30 Management EVALUATION SPECIALIST 68/MFIP/IC/2018 / SPECIALIST FOR INFORMATION MANAGEMENT AND Project Coordination and IDA / 59590 Post Direct Selection Direct 18,000.00 18,000.00 Signed 2018-03-20 2017-10-12 2018-03-30 2017-10-12 2018-06-03 2017-10-12 2018-11-30 MONITORING OF THE Management PROJECT OF PERMANENT PLOTS 70/MFIP/IC/2018 / AQUA Project Coordination and IDA / 59590 Post Direct Selection Direct 22,500.00 22,500.00 Signed 2018-03-20 2018-04-02 2018-03-30 2017-10-11 2018-06-03 2017-10-13 2018-11-30 JURIST Management 71/MFIP/CS/2018 / training of Project Coordination and Under extension workers in IDA / 59590 Post Direct Selection Direct 19,100.00 0.00 2018-03-27 2018-04-06 2018-06-10 2018-12-07 Management Implementation conservation agriculture 72/MFIP/CS/18 / TRAINING OF THE NIMALA COMMUNITY AND ESTABLISHMENT OF A PILOT Project Coordination and Under IDA / 59590 Post Direct Selection Direct 17,600.00 0.00 2018-03-22 2018-05-14 2018-04-01 2018-06-05 2018-12-02 MECHANISM FOR Management Implementation INTEGRATED MINERAL RESOURCES MANAGEMENT 73/MFIP/CS/2018 / REPORT ON THE ANALYSIS OF HISTORICAL DATA ON DISMANTLING AND RESULTS Project Coordination and IDA / 59590 Post Direct Selection Direct 44,000.00 44,000.00 Signed 2018-03-27 2018-01-10 2018-04-06 2018-04-13 2018-06-10 2018-04-20 2018-12-07 OF THE NATIONAL FOREST Management INVENTORY AND ITS IMPLICATIONS IN THE DECISION-MAKING 74/MFIP/CS/2018 / TRAINING IN BIOMASS ENERGY Project Coordination and Under IDA / 59590 Post Direct Selection Direct 26,667.80 0.00 2018-03-28 2018-05-14 2018-04-07 2018-06-11 2018-12-08 TECHNIQUES IN THE Management Implementation PROVINCE OF ZAMBEZIA 75/MFIP/CS/2018 / FOREST Project Coordination and Pending IDA / 59590 Post Direct Selection Direct 172,000.00 0.00 2018-03-29 2018-04-08 2018-06-12 2018-12-09 CERTIFICATION Management Implementation 74/MFIP/IC/2018 / Elaboration of Project Coordination and PAP ( permanent sampling plots) IDA / 59590 Post Direct Selection Direct 22,000.00 22,000.00 Signed 2018-03-29 2017-11-30 2018-04-08 2017-12-06 2018-06-12 2017-12-26 2018-12-09 Management manual 76/MFIP/CS/18 / Elaboration of Project Coordination and Individual Consultant IDA / 59590 Post Direct 22,500.00 22,500.00 Signed 2018-03-27 2017-10-12 2018-04-06 2017-11-01 2018-04-27 2017-11-08 2018-06-01 2017-10-30 2018-11-28 the Forest Inventory Report Management Selection 77/MFIP/IC/18 / Elaboration of Project Coordination and IDA / 59590 Post Direct Selection Direct 10,000.00 10,000.00 Signed 2018-03-29 2018-04-01 2018-04-08 2018-04-01 2018-06-12 2017-10-12 2018-12-09 the DGM PIM Management 78/MFIP/IC/2018 / PREPARATION OF THE MAP Project Coordination and OF USE OF SOIL COVERAGE IDA / 59590 Post Direct Selection Direct 7,200.00 7,200.00 Signed 2018-03-28 2018-01-02 2018-04-07 2018-01-02 2018-06-11 2017-09-29 2018-12-08 Management BASED ON IMAGES SENTINEL 2016 Page 3 81/MFIP/IC/2018 / hiring individual consult to elaborate Project Coordination and Individual Consultant Under IDA / 59590 Post Open 15,000.00 0.00 2018-04-26 2018-04-20 2018-06-14 2018-07-05 2018-08-09 2019-02-05 Nkoe and Litandacua-Macomia Management Selection Implementation Management Plan 42/MFIP/IC/2018 / Financial Project Coordination and IDA / 59590 Prior Direct Selection Direct 26,250.00 0.00 Canceled 2018-03-09 2018-03-27 2018-03-19 2018-05-23 2018-11-19 assistente Management 47/MFIP/IC/2018 / Procurement Project Coordination and IDA / 59590 Prior Direct Selection Direct 72,187.50 0.00 Canceled 2018-03-12 2018-03-27 2018-03-22 2018-05-26 2018-11-22 Assistant Management 30 /MFIP/IC/2017 / Human Project Coordination and Post Direct Selection Direct 12,000.00 0.00 Canceled 2017-02-15 2017-02-25 2017-05-01 2017-10-28 Resources Management Project Coordination and Individual Consultant 24/MFIP/IC/2017 / lAWYER Prior Open 14,400.00 0.00 Canceled 2017-05-01 2017-06-19 2017-07-10 2017-08-14 2018-02-10 Management Selection 26/MFIP/IC/2017 / Project Coordination and Individual Consultant Administrative & Financial Post Open 12,000.00 0.00 Canceled 2017-04-20 2017-06-07 2017-06-28 2017-08-02 2018-08-02 Management Selection Assistant 34/MFIP/IC/2017 / Human Project Coordination and Individual Consultant IDA / 59590 Post Open 12,000.00 0.00 Canceled 2017-06-28 2017-10-27 2017-08-16 2017-09-06 2017-10-11 2018-04-09 Resources for Cabo Delgado Management Selection 44/MFIP/IC/2018 / administrative Project Coordination and IDA / 59590 Post Direct Selection Direct 14,000.00 0.00 Canceled 2018-03-13 2018-03-23 2018-05-27 2018-11-23 assistant Cabo Delgado Management 80/MFIP/IC/2018 / Procurement Project Coordination and Under IDA / 59590 Prior Direct Selection Direct 72,187.00 0.00 2018-04-24 2018-05-08 2018-05-04 2018-07-08 2019-01-04 Assistant I Management Implementation 83/MFIP/IC/2018 / Financial Project Coordination and IDA / 59590 Post Direct Selection Direct 26,250.00 30,000.00 Signed 2018-04-24 2018-01-02 2018-05-04 2018-01-03 2018-07-08 2016-08-01 2019-01-04 Assistant Management 84/MFIP/IC/2018 / Forest Project Coordination and Individual Consultant Pending IDA / 59590 Post Open 33,600.00 0.00 2018-06-28 2018-08-16 2018-09-06 2018-10-11 2019-04-09 Specialist for Cabo Delgado Management Selection Implementation 85/MFIP/IC/2018 / Think Project Coordination and Under IDA / 59590 Post Direct Selection Direct 290,000.00 0.00 2018-04-27 2018-05-14 2018-05-07 2018-07-11 2019-01-07 Quirimbas Management Implementation 51/MFIP/IC/2018 / Procurement Project Coordination and Under IDA / 59590 Prior Direct Selection Direct 12,500.00 0.00 2018-03-14 2018-05-08 2018-03-24 2018-05-28 2018-11-24 Assistant II Management Implementation 87/MFIP/IC/2018 / Elaboration of Project Coordination and Individual Consultant the communal management plan IDA / 59590 Post Open 44,000.00 44,000.00 Signed 2018-04-30 2018-06-18 2018-01-10 2018-07-09 2018-04-30 2018-08-13 2018-04-30 2019-02-09 Management Selection nipiode and uape Strengthening the Enabling Individual Consultant 29/MFIP/IC/2017 / lawer IDA / 59590 Conditions for Sustainable Post Open 14,400.00 0.00 Canceled 2017-05-01 2017-06-19 2017-07-10 2017-08-14 2018-02-10 Selection Forest Management 62/MFIP/IC/2018 / COMMUNITY Project Coordination and DEVELOPMENT ASSISTANT IDA / 59590 Post Direct Selection Direct 33,600.00 0.00 Canceled 2018-03-20 2018-03-30 2018-06-03 2018-11-30 Management CABO DELGADO 87/MFIP/CS/2018 / Project Coordination and Individual Consultant Pending COMMUNITY DEVELOPMENT IDA / 59590 Post Open 33,600.00 0.00 2018-06-20 2018-08-08 2018-08-29 2018-10-03 2019-04-01 Management Selection Implementation ASSISTANT CABO DELGADO 88/MFIP/CS/2018 / Service Provider for Periodic Evaluation of Promoting Integrated Landscape Under IDA / 59590 Post Direct Selection Direct 200,000.00 0.00 2018-06-25 2018-07-24 2018-07-05 2018-09-08 2019-03-07 Forest Concessions and Forest Management Implementation Governance in Mozambique 89/MFIP/IC/18 / Hiring of individual consultant for training members of the associations of Promoting Integrated Landscape Individual Consultant Pending IDA / 59590 Post Open 9,000.00 0.00 2018-08-29 2018-10-17 2018-11-07 2018-12-12 2019-06-10 NIPIODE and ANAWAPE, in the Management Selection Implementation area of Administration and Finance 90/MFIP/IC/18 / Hiring of individual consultant to train members of the associations of Promoting Integrated Landscape Individual Consultant Pending IDA / 59590 Post Open 10,500.00 0.00 2018-08-30 2018-10-18 2018-11-08 2018-12-13 2019-06-11 NIPIODE and ANAWAPE, in the Management Selection Implementation area of Forest Enforcement and Legislation 91/MFIP/IC/18 / Hiring of individual consultant to train members of the associations of Project Coordination and Individual Consultant Pending NIPIODE and ANAWAPE, in the IDA / 59590 Post Open 20,250.00 0.00 2018-08-21 2018-10-09 2018-10-30 2018-12-04 2019-06-02 Management Selection Implementation area of Governance and Community Management of Natural Resources Page 4