Public Disclosure Copy The World Bank Implementation Status & Results Report HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058) HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058) LATIN AMERICA AND CARIBBEAN | Honduras | Transport Global Practice | IBRD/IDA | Specific Investment Loan | FY 2008 | Seq No: 15 | ARCHIVED on 09-May-2015 | ISR18968 | Implementing Agencies: Key Dates Key Project Dates Board Approval date:17-Jun-2008 Effectiveness Date:27-Apr-2009 Planned Mid Term Review Date:18-Jul-2011 Actual Mid-Term Review Date:18-Sep-2011 Original Closing Date:30-Jun-2013 Revised Closing Date:31-May-2015 Project Development Objectives Project Development Objective (from Project Appraisal Document) Original To improve the quality of road network and of road management in support of the government's growth and competitiveness goals through: (i) Improved governance and enhanced road management capacity in SOPTRAVI and the Road Fund; (ii) Improvement in selected road corridors; and (iii) Extension in the scope of the maintenance of the unpaved road network. 7.b Revised To improve the quality of road network and of road management in support of the government's growth and competitiveness goals through: (i) Improved governance and enhanced road management capacity in SOPTRAVI and the Road Fund; (ii) Improvement in selected road corridors; and (iii) Extension in the scope of the maintenance of the unpaved road network; and (iv) improvement of the Recipient capacity to respond promptly and effectively to an eligible emergency. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Road Rehabilitation:(Cost $50.50 M) Micro-enterprises for unpaved network:(Cost $2.50 M) Institutional strengthening:(Cost $3.00 M) Implementation Support:(Cost $5.00 M) IRM Contingent Component Overall Ratings Name Previous Rating Current Rating 5/9/2015 Page 1 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058) Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Satisfactory Overall Risk Rating -- Low Implementation Status and Key Decisions The closing date of the project was extended to May 31, 2015. During the last 6 months the implementing agency focused its attention towards the implementation of remaining institutional strengthening measures and completion of civil works, under the strong leadership of the Minister in INSEP. Key results achieved through this project include: (i) the acceptance of Honduras in the CoST initiative - a targeted initiative to improve the value for money spent on public infrastructure by increasing transparency in the delivery of construction projects; (ii) several activities promoted by the Multi Stakeholder Group created under the CoST umbrella (with representatives from civil society, private sector and Government) to implement the initiative and allow the participation of civil society on the verification of works implemented in the road sector; (ii) the official launch of a Contract Management System and a Complaints Handling Mechanism System that will help improve transparency in the road sector (iii) the official launch of the so-called "Caminos para una Vida Mejor" program, which based on the successful Microenterprises experience implemented through the project in the unpaved network, has been scaled up to cover also the paved network and will contribute to improve the cost-efficiency in the preservation and management of the national road assets. Under this program 32 Microenterprises have been created (16 financed with project funds) to maintain some 1,300 km of roads, generating 254 direct emplyments (30% for women); (iv) the improvement of 127 km of roads (double surface treatment); (v) the reconstruction of five bridges (vi) adressing emergency repairs caused by flooding in one road section (geologic faults contract) and achieving 80% progress in the remaining faults contract still under execution; (v) the procurement of key equipment to modernize INSEP's information technology; (vi) improved staff capacity in areas related to safeguards management, bridges, planning, project design through training provided and goods procured; (vii) the implementation of technical audits carried out for the three main roads work contracts; (viii) and the implementation of HIV/AIDs clauses on the three main road works contracts. 5/9/2015 Page 2 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- -- Low Macroeconomic -- -- Low Sector Strategies and Policies -- -- Low Technical Design of Project or Program -- -- Low Institutional Capacity for Implementation and Sustainability -- -- Low Fiduciary -- -- Low Environment and Social -- -- Low Stakeholders -- -- Low Other -- -- Low Overall -- -- Low Results Project Development Objective Indicators PHINDPDOTBL Roads retuned to good condition (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 127.00 127.00 143.00 Date 17-Jun-2008 30-May-2014 17-Apr-2015 31-May-2015 Comments The overall target of 143 included the original 138 Km under the three main road segments (San Lorenzo-Olanchito, El Porvenir-Marale and 5/9/2015 Page 3 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058) La Esperanza-Camasca) plus some 5 km addition foreseen under the emergency improvement works foreseen to address the effects of tropical storm 16. The main shorcomings in terms of the targets was related to the upgrading of the road section La Esperanza-Camasca, a contract financed by BCIE which only managed to complete 22 km out of the 61 originally envisioned, because the previous administration decided to change the original design from a DST to a concrete pavement and widen the capacity, which requires additional US$20 million, yet to be obtained. However, some 23 additional km or roads where improved under the emergency recovery works from those originally envisioned in the AF and this contributed to reduce the gap left from the BCIE segment. PHINDPDOTBL Unpaved Roads Maintained by Microenterprises (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 310.00 532.00 310.00 Date 17-Jun-2008 30-May-2014 17-Apr-2015 31-May-2015 PHINDPDOTBL Microenterprises in Operation (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 10.00 16.00 10.00 PHINDPDOTBL Time taken to disburse funds requested by Government for an eligible emergency (Months, Custom) Baseline Actual (Previous) Actual (Current) End Target Value -- -- -- 1.00 Date -- -- -- 31-May-2015 Comments This component was not triggered and as such no indicator needed to be measured. Not Applicable PHINDPDOTBL Vehicle operating costs reduced (US$/Km) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.22-0.88 -- -- 0.16-0.82 5/9/2015 Page 4 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058) Date 17-Jun-2008 -- 17-Apr-2015 31-May-2015 Comments It is not clear what the baseline and end target values that appear in the PAD's results framework represent or where have they been taken from. They do not coincide with the numbers that appear in Table 9.4 or 9.5 in pages 69 and 70 of the PAD. For this reason we propose: (i) to use the values in Tables 9.4 and 9.5 of the PAD to estimate the expected percentage reduction in VOCs (average for the 6 vehicle categories) for the two roads supported by the project: El Porvenir -Marale and San Lorenzo -Olanchito and measure the impact of this component through the two additional indicators included below. PHINDPDOTBL Reduced Vehicle Operating Cost (Percentage) for El Porvenir-Marale (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 44.00 35.00 PHINDPDOTBL Reduced Vehicle Operating Costs (percentage) San Lorenzo-Olanchito (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 39.00 44.00 Overall Comments Intermediate Results Indicators PHINDIRITBL Completion of road improvements (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0 127 127 138 km Date 17-Jun-2008 30-May-2014 17-Apr-2015 31-May-2015 Comments The overall target of included the original 138 Km under the three main road segments (San Lorenzo-Olanchito, El Porvenir-Marale and La Esperanza-Camasca). The main shorcomings in terms of the targets was related to the upgrading of the road section La Esperanza- Camasca, a contract financed by BCIE which only managed to complete 22 km out of the 61 originally envisioned, because the previous 5/9/2015 Page 5 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058) administration decided to change the original design from a DST to a concrete pavement and widen the capacity, which requires additional US$20 million, yet to be obtained. However, some 23 additional km or roads where improved under the emergency recovery works from those originally envisioned in the AF and this contributed to reduce the gap left from the BCIE segment. PHINDIRITBL Strategic Sector Plan Introduced (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N Y Y Y Date 17-Jun-2008 30-May-2014 17-Apr-2015 31-May-2015 PHINDIRITBL Contract Management Tracking System Introduced and Maintained (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N Y Y Date 17-Jun-2008 30-May-2014 17-Apr-2015 31-May-2015 PHINDIRITBL Social Management Capacity Enhanced (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N Y Y Y Date 17-Jun-2008 30-May-2014 17-Apr-2015 31-May-2015 5/9/2015 Page 6 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058) PHINDIRITBL HIV/AIDS clauses in use in road construction and maintenance contracts (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 17-Jun-2008 30-May-2014 17-Apr-2015 31-May-2015 PHINDIRITBL Training carried out in SOPTRAVI and Fondo Vial (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Less than 10% of staff At least 30% of Value -- -- each year staff each year Date 17-Jun-2008 30-May-2014 17-Apr-2015 31-May-2015 Comments To be provided by the Government before the project closing. PHINDIRITBL Staff trained on Transparency/Access to Information Law (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 60.00 100.00 60.00 Date 17-Jun-2008 08-Jun-2011 02-Sep-2011 31-May-2015 PHINDIRITBL Create, Equip and Staff Training Center (Yes/No, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value N N Y Y Date 17-Jun-2008 08-Jun-2011 02-Sep-2011 31-May-2015 5/9/2015 Page 7 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058) PHINDIRITBL Complaints policy and handling mechanism in place (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No NO YES Yes Date 17-Jun-2008 30-May-2014 17-Apr-2015 31-May-2015 Comments System has been designed and officially/publicly launched in an event carried out in Casa Presidencial alomg with the Contract Management System. System is in place, complaints are being received, however, internal procedures are being revised to improve its operationalization. PHINDIRITBL Roads rehabilitated, Non-rural (Kilometers, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 127.00 127.00 138.00 Date 17-Jun-2008 30-May-2014 17-Apr-2015 31-May-2015 Comments This target included the original 138 Km under the three main road segments (San Lorenzo-Olanchito, El Porvenir-Marale and La Esperanza-Camasca). The main shorcomings in terms of the targets was related to the upgrading of the road section La Esperanza- Camasca, a contract financed by BCIE which only managed to complete 22 km out of the 61 originally envisioned, because the previous administration decided to change the original design from a DST to a concrete pavement and widen the capacity, which requires additional US$20 million, yet to be obtained. However, some 23 additional km or roads where improved under the emergency recovery works from those originally envisioned in the AF and this contributed to reduce the gap left from the BCIE segment. Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P109058 IDA-44660 Effective XDR 29.60 29.60 0.00 29.39 0.21 99% P109058 IDA-45830 Effective XDR 16.80 13.66 3.14 12.75 0.91 93% Key Dates (by loan) 5/9/2015 Page 8 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P109058 IDA-44660 Effective 17-Jun-2008 13-Oct-2008 27-Apr-2009 30-Jun-2013 31-May-2015 P109058 IDA-45830 Effective 21-May-2009 02-Aug-2010 19-Nov-2010 30-Jun-2013 31-May-2015 Cumulative Disbursements Restructuring History Level Approved on 25-Aug-2011 ,Level Approved on 19-Jun-2013 ,Level 2 Approved on 08-Dec-2014 ,Level 2 Approved on 27-Apr-2015 Related Project(s) P115568-Additional Financing Second Road Rehabilitation and Improvement Project 5/9/2015 Page 9 of 9 Public Disclosure Copy