           The World Bank                                                                       Implementation Status & Results Report
           HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058)


HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058)

LATIN AMERICA AND CARIBBEAN | Honduras | Transport Global Practice |
IBRD/IDA | Specific Investment Loan | FY 2008 | Seq No: 15 | ARCHIVED on 09-May-2015 | ISR18968 |


Implementing Agencies:




Key Dates

  Key Project Dates

  Board Approval date:17-Jun-2008                                         Effectiveness Date:27-Apr-2009
  Planned Mid Term Review Date:18-Jul-2011                                Actual Mid-Term Review Date:18-Sep-2011
  Original Closing Date:30-Jun-2013                                       Revised Closing Date:31-May-2015




Project Development Objectives

 Project Development Objective (from Project Appraisal Document)
 Original To improve the quality of road network and of road management in support of the government's growth and competitiveness goals through:
 (i) Improved governance and enhanced road management capacity in SOPTRAVI and the Road Fund; (ii) Improvement in selected road corridors;
 and (iii) Extension in the scope of the maintenance of the unpaved road network. 7.b Revised To improve the quality of road network and of road
 management in support of the government's growth and competitiveness goals through: (i) Improved governance and enhanced road management
 capacity in SOPTRAVI and the Road Fund; (ii) Improvement in selected road corridors; and (iii) Extension in the scope of the maintenance of the
 unpaved road network; and (iv) improvement of the Recipient capacity to respond promptly and effectively to an eligible emergency.


 Has the Project Development Objective been changed since Board Approval of the Project Objective?
 No

 PHRPDODEL



Components

Name
Road Rehabilitation:(Cost $50.50 M)
Micro-enterprises for unpaved network:(Cost $2.50 M)
Institutional strengthening:(Cost $3.00 M)
Implementation Support:(Cost $5.00 M)
IRM Contingent Component



Overall Ratings
Name                                                                     Previous Rating                        Current Rating



5/9/2015                                                                                                                            Page 1 of 9
                                                        Public Disclosure Copy
                                                           Public Disclosure Copy

           The World Bank                                                                            Implementation Status & Results Report
           HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058)


Progress towards achievement of PDO                                          Moderately Satisfactory                  Moderately Satisfactory
Overall Implementation Progress (IP)                                         Moderately Satisfactory                  Satisfactory
Overall Risk Rating                                                          --                                       Low


Implementation Status and Key Decisions

 The closing date of the project was extended to May 31, 2015. During the last 6 months the implementing agency focused its attention towards the
 implementation of remaining institutional strengthening measures and completion of civil works, under the strong leadership of the Minister in INSEP.
 Key results achieved through this project include: (i) the acceptance of Honduras in the CoST initiative - a targeted initiative to improve the value for
 money spent on public infrastructure by increasing transparency in the delivery of construction projects; (ii) several activities promoted by the Multi
 Stakeholder Group created under the CoST umbrella (with representatives from civil society, private sector and Government) to implement the initiative
 and allow the participation of civil society on the verification of works implemented in the road sector; (ii) the official launch of a Contract Management
 System and a Complaints Handling Mechanism System that will help improve transparency in the road sector (iii) the official launch of the so-called
 "Caminos para una Vida Mejor" program, which based on the successful Microenterprises experience implemented through the project in the unpaved
 network, has been scaled up to cover also the paved network and will contribute to improve the cost-efficiency in the preservation and management of
 the national road assets. Under this program 32 Microenterprises have been created (16 financed with project funds) to maintain some 1,300 km of
 roads, generating 254 direct emplyments (30% for women); (iv) the improvement of 127 km of roads (double surface treatment); (v) the reconstruction
 of five bridges (vi) adressing emergency repairs caused by flooding in one road section (geologic faults contract) and achieving 80% progress in the
 remaining faults contract still under execution; (v) the procurement of key equipment to modernize INSEP's information technology; (vi) improved staff
 capacity in areas related to safeguards management, bridges, planning, project design through training provided and goods procured; (vii) the
 implementation of technical audits carried out for the three main roads work contracts; (viii) and the implementation of HIV/AIDs clauses on the three
 main road works contracts.




5/9/2015                                                                                                                                   Page 2 of 9
                                                           Public Disclosure Copy
                                                             Public Disclosure Copy

               The World Bank                                                                          Implementation Status & Results Report
               HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058)




Risks

 Systematic Operations Risk-rating Tool

 Risk Category                                                 Rating at Approval               Previous Rating           Current Rating

 Political and Governance                                       --                              --                       Low
 Macroeconomic                                                  --                              --                       Low
 Sector Strategies and Policies                                 --                              --                       Low
 Technical Design of Project or Program                         --                              --                       Low
 Institutional Capacity for Implementation and
 Sustainability
                                                                --                              --                       Low
 Fiduciary                                                      --                              --                       Low
 Environment and Social                                         --                              --                       Low
 Stakeholders                                                   --                              --                       Low
 Other                                                          --                              --                       Low
 Overall                                                        --                              --                       Low


Results

 Project Development Objective Indicators
 PHINDPDOTBL




          Roads retuned to good condition (Kilometers, Custom)


                                              Baseline                      Actual (Previous)          Actual (Current)           End Target

         Value                                0.00                          127.00                     127.00                     143.00

         Date                                 17-Jun-2008                   30-May-2014                17-Apr-2015                31-May-2015


         Comments
         The overall target of 143 included the original 138 Km under the three main road segments (San Lorenzo-Olanchito, El Porvenir-Marale and


5/9/2015                                                                                                                                   Page 3 of 9
                                                             Public Disclosure Copy
                                                             Public Disclosure Copy

               The World Bank                                                                        Implementation Status & Results Report
               HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058)



         La Esperanza-Camasca) plus some 5 km addition foreseen under the emergency improvement works foreseen to address the effects of
         tropical storm 16. The main shorcomings in terms of the targets was related to the upgrading of the road section La Esperanza-Camasca, a
         contract financed by BCIE which only managed to complete 22 km out of the 61 originally envisioned, because the previous administration
         decided to change the original design from a DST to a concrete pavement and widen the capacity, which requires additional US$20 million,
         yet to be obtained. However, some 23 additional km or roads where improved under the emergency recovery works from those originally
         envisioned in the AF and this contributed to reduce the gap left from the BCIE segment.



 PHINDPDOTBL




          Unpaved Roads Maintained by Microenterprises (Kilometers, Custom)


                                              Baseline                      Actual (Previous)         Actual (Current)           End Target

         Value                                0.00                          310.00                    532.00                     310.00

         Date                                 17-Jun-2008                   30-May-2014               17-Apr-2015                31-May-2015


 PHINDPDOTBL




          Microenterprises in Operation (Number, Custom Supplement)



                                              Baseline                      Actual (Previous)         Actual (Current)           End Target

         Value                                0.00                          10.00                     16.00                      10.00




 PHINDPDOTBL




          Time taken to disburse funds requested by Government for an eligible emergency (Months, Custom)


                                              Baseline                      Actual (Previous)         Actual (Current)           End Target

         Value                                --                            --                        --                         1.00

         Date                                 --                            --                        --                         31-May-2015


         Comments
         This component was not triggered and as such no indicator needed to be measured. Not Applicable



 PHINDPDOTBL




          Vehicle operating costs reduced (US$/Km) (Text, Custom)


                                              Baseline                      Actual (Previous)         Actual (Current)           End Target

         Value                                0.22-0.88                     --                        --                         0.16-0.82



5/9/2015                                                                                                                                  Page 4 of 9
                                                             Public Disclosure Copy
                                                                    Public Disclosure Copy

                   The World Bank                                                                            Implementation Status & Results Report
                   HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058)



               Date                                  17-Jun-2008                   --                         17-Apr-2015                 31-May-2015


               Comments
               It is not clear what the baseline and end target values that appear in the PAD's results framework represent or where have they been taken
               from. They do not coincide with the numbers that appear in Table 9.4 or 9.5 in pages 69 and 70 of the PAD. For this reason we propose:
               (i) to use the values in Tables 9.4 and 9.5 of the PAD to estimate the expected percentage reduction in VOCs (average for the 6 vehicle
               categories) for the two roads supported by the project: El Porvenir -Marale and San Lorenzo -Olanchito and measure the impact of this
               component through the two additional indicators included below.



 PHINDPDOTBL




              Reduced Vehicle Operating Cost (Percentage) for El Porvenir-Marale (Percentage, Custom Supplement)



                                                     Baseline                      Actual (Previous)          Actual (Current)            End Target

               Value                                 0.00                          --                         44.00                       35.00




 PHINDPDOTBL




              Reduced Vehicle Operating Costs (percentage) San Lorenzo-Olanchito (Percentage, Custom Supplement)



                                                     Baseline                      Actual (Previous)          Actual (Current)            End Target

               Value                                 0.00                          --                         39.00                       44.00




 Overall Comments

 Intermediate Results Indicators
 PHINDIRITBL




              Completion of road improvements (Text, Custom)

                                                     Baseline                      Actual (Previous)          Actual (Current)           End Target

               Value                                 0                             127                        127                        138 km

               Date                                  17-Jun-2008                   30-May-2014                17-Apr-2015                31-May-2015


               Comments
               The overall target of included the original 138 Km under the three main road segments (San Lorenzo-Olanchito, El Porvenir-Marale and La
               Esperanza-Camasca). The main shorcomings in terms of the targets was related to the upgrading of the road section La Esperanza-
               Camasca, a contract financed by BCIE which only managed to complete 22 km out of the 61 originally envisioned, because the previous


5/9/2015                                                                                                                                          Page 5 of 9
                                                                    Public Disclosure Copy
                                                                    Public Disclosure Copy

                   The World Bank                                                                           Implementation Status & Results Report
                   HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058)



               administration decided to change the original design from a DST to a concrete pavement and widen the capacity, which requires additional
               US$20 million, yet to be obtained. However, some 23 additional km or roads where improved under the emergency recovery works from
               those originally envisioned in the AF and this contributed to reduce the gap left from the BCIE segment.




 PHINDIRITBL




              Strategic Sector Plan Introduced (Yes/No, Custom)

                                                     Baseline                     Actual (Previous)          Actual (Current)           End Target

               Value                                 N                            Y                          Y                          Y

               Date                                  17-Jun-2008                  30-May-2014                17-Apr-2015                31-May-2015




 PHINDIRITBL




              Contract Management Tracking System Introduced and Maintained (Yes/No, Custom)

                                                     Baseline                     Actual (Previous)          Actual (Current)           End Target

               Value                                 N                            N                          Y                          Y

               Date                                  17-Jun-2008                  30-May-2014                17-Apr-2015                31-May-2015




 PHINDIRITBL




              Social Management Capacity Enhanced (Yes/No, Custom)

                                                     Baseline                     Actual (Previous)          Actual (Current)           End Target

               Value                                 N                            Y                          Y                          Y

               Date                                  17-Jun-2008                  30-May-2014                17-Apr-2015                31-May-2015




5/9/2015                                                                                                                                        Page 6 of 9
                                                                    Public Disclosure Copy
                                                                   Public Disclosure Copy

                   The World Bank                                                                   Implementation Status & Results Report
                   HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058)

 PHINDIRITBL




              HIV/AIDS clauses in use in road construction and maintenance contracts (Text, Custom)

                                                    Baseline                    Actual (Previous)   Actual (Current)      End Target

               Value                                No                          Yes                 Yes                   Yes

               Date                                 17-Jun-2008                 30-May-2014         17-Apr-2015           31-May-2015




 PHINDIRITBL




              Training carried out in SOPTRAVI and Fondo Vial (Text, Custom)

                                                    Baseline                    Actual (Previous)   Actual (Current)      End Target

                                                    Less than 10% of staff                                                At least 30% of
               Value                                                            --                  --
                                                    each year                                                             staff each year

               Date                                 17-Jun-2008                 30-May-2014         17-Apr-2015           31-May-2015


               Comments
               To be provided by the Government before the project closing.


 PHINDIRITBL




              Staff trained on Transparency/Access to Information Law (Percentage, Custom Supplement)

                                                    Baseline                    Actual (Previous)   Actual (Current)      End Target

               Value                                0.00                        60.00               100.00                60.00

               Date                                 17-Jun-2008                 08-Jun-2011         02-Sep-2011           31-May-2015




 PHINDIRITBL




              Create, Equip and Staff Training Center (Yes/No, Custom Supplement)

                                                    Baseline                    Actual (Previous)   Actual (Current)      End Target

               Value                                N                           N                   Y                     Y

               Date                                 17-Jun-2008                 08-Jun-2011         02-Sep-2011           31-May-2015




5/9/2015                                                                                                                          Page 7 of 9
                                                                   Public Disclosure Copy
                                                                      Public Disclosure Copy

                   The World Bank                                                                           Implementation Status & Results Report
                   HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058)

 PHINDIRITBL




              Complaints policy and handling mechanism in place (Text, Custom)

                                                        Baseline                   Actual (Previous)         Actual (Current)             End Target

               Value                                    No                         NO                        YES                          Yes

               Date                                     17-Jun-2008                30-May-2014               17-Apr-2015                  31-May-2015


               Comments
               System has been designed and officially/publicly launched in an event carried out in Casa Presidencial alomg with the Contract
               Management System. System is in place, complaints are being received, however, internal procedures are being revised to improve its
               operationalization.


 PHINDIRITBL




              Roads rehabilitated, Non-rural (Kilometers, Core)

                                                        Baseline                   Actual (Previous)         Actual (Current)             End Target

               Value                                    0.00                       127.00                    127.00                       138.00

               Date                                     17-Jun-2008                30-May-2014               17-Apr-2015                  31-May-2015


               Comments
               This target included the original 138 Km under the three main road segments (San Lorenzo-Olanchito, El Porvenir-Marale and La
               Esperanza-Camasca). The main shorcomings in terms of the targets was related to the upgrading of the road section La Esperanza-
               Camasca, a contract financed by BCIE which only managed to complete 22 km out of the 61 originally envisioned, because the previous
               administration decided to change the original design from a DST to a concrete pavement and widen the capacity, which requires additional
               US$20 million, yet to be obtained. However, some 23 additional km or roads where improved under the emergency recovery works from
               those originally envisioned in the AF and this contributed to reduce the gap left from the BCIE segment.




 Overall Comments



Data on Financial Performance

Disbursements (by loan)

Project                  Loan/Credit/TF     Status        Currency      Original   Revised     Cancelled    Disbursed      Undisbursed                 Disbursed

P109058                  IDA-44660          Effective     XDR             29.60      29.60          0.00         29.39             0.21                          99%

P109058                  IDA-45830          Effective     XDR             16.80      13.66          3.14         12.75             0.91                          93%


Key Dates (by loan)



5/9/2015                                                                                                                                           Page 8 of 9
                                                                      Public Disclosure Copy
                                                      Public Disclosure Copy

           The World Bank                                                                  Implementation Status & Results Report
           HONDURAS ROAD REHABILITATION AND IMPROVEMENT II (P109058)



 Project      Loan/Credit/TF   Status      Approval Date   Signing Date    Effectiveness Date   Orig. Closing Date   Rev. Closing Date

 P109058      IDA-44660        Effective   17-Jun-2008     13-Oct-2008     27-Apr-2009          30-Jun-2013          31-May-2015
 P109058      IDA-45830        Effective   21-May-2009     02-Aug-2010     19-Nov-2010          30-Jun-2013          31-May-2015



Cumulative Disbursements




 Restructuring History

  Level Approved on 25-Aug-2011 ,Level Approved on 19-Jun-2013 ,Level 2 Approved on 08-Dec-2014 ,Level 2 Approved on 27-Apr-2015




 Related Project(s)

 P115568-Additional Financing Second Road Rehabilitation and Improvement Project




5/9/2015                                                                                                                    Page 9 of 9