Page 1 DRAFT Item No. Package number and name Type Method Plan/ act Cost estimate (US$) Draft Bidding Docs and SPN Bank's No objection to Bidding docs Issuance of Bidding Documents Bid Opening Bid Evaluation Report Bank's No objection to Contract Awd. Contract Signature Contract Completion Bank's Review Component A: Plan 859,000.00 Jul-06 Aug-06 Sept-06 04-Dec-06 25-Dec-06 07-Jan-07 17-Jan-07 Apr-07 Actual 470,011.00 Sept-06 02-Oct-06 19-Oct-06 04-Dec-06 25-Dec-06 07-Jan-07 15-Jan-07 15-May-07 Plan 382,000.00 Jul-06 Aug-06 Sept-06 04-Dec-06 25-Dec-06 07-Jan-07 17-Jan-07 Apr-07 Actual 499,768,00 Sept-06 02-Oct-06 19-Oct-06 08-Jan-07 23-Jan-07 15-Feb-07 10-Mar-07 06-Oct-07 Plan 152,000.00 22-Feb-07 11-Mar-07 Mar-07 15-Apr-07 04-May-07 15-May-07 28-May-07 29-Jun-07 Actual 60,426.00 17-May-07 30-May-07 01-Jun-07 17-Jul-07 02-Aug-07 14-Sept-07 03-Oct-07 26-Oct-07 Plan 182,000.00 22-Feb-07 11-Mar-07 Mar-07 15-Apr-07 02-May-07 10-May-07 18-May-07 18-Jun-07 Actual 213,850.00 17-May-07 30-May-07 01-Jun-07 19-Jul-07 02-Aug-07 28-Aug-07 06-Sept-07. 06-Dec-07 Plan 300,000.00 02-Feb-07 13-Feb-07 27-Feb-07 21-Mar-07 21-Mar-07 28-Mar-07 01-Dec-07 02-Dec-07 Actual 241,500.00 17-May-07 11-Jul-07 11-Jul-07 06-Sept-07. 21-Mar-07 07-Noy-07 11-Dec-07 02-Dec-07 Plan 54,000.00 Sept-06 02-Oct-06 19-Oct-06 15-Feb-07 25-Feb-07 Mar-07 12-Mar-07 pr-07 Actual 169,920.00 09-Mar-07 13-Apr-07 13-Mar-07 22-May-07 25-Feb-07 09-July-07 26-Sept-07 25-Nov-07 Plan 61,000.00 01-Feb-07 13-Feb-07 27-Feb-07 19-Mar-07 19-Mar-07 26-Mar-07 Nov. 2007 Dec-07 Actual 79, 554.00 10-Mar-07 13-Apr-07 10-Mar-07 22-May-07 08-Jun-07 07-Nov-07 20-Nov-07 20-Mar-08 Plan 100,000.00 Oct-07 Oct-07 N/A N/A N/A Nov-07 Nov-07 Jun-08 Actual 110,000.00 05-Jul-07 11-Jul-07 N/A N/A N/A 25-Jun-08 11-Jul-08 31-Mar-09 Plan 86,500.00 N/A N/A N/A N/A N/A N/A 20-Jul-09 26-Feb-10 Actual 86,514.00 N/A N/A N/A N/A N/A N/A 26-Aug-09 26-Feb-10 Plan 197,500.00 20-Feb-09 02-Mar-09 12-May-09 29-May-09 01-Jun-09 12-Jun-09 15-Jun-09 30-Jul-09 Actual 215,570.00 27-Mar-09 02-Apr-09 20-May-09 02-Jun-09 02-Jun-09 09-Nov-09 10-Jun-09 10-Jul-09 Plan 220,000,00 Sep-10 Oct-10 Oct-10 22-Nov-10 Nov-10 Nov-10 Dec-10 Jan-10 Actual Sep-10 05-Oct -10 06-Oct -10 22-Nov-10 02-Dec-10 02-Dec-10 Plan 76,500. 00 20-Feb-09 02-Mar-09 12-May-09 29-May-09 01-Jun-09 12-Jun-09 15-Jun-09 30-Jul-09 Actual 89,635. 00 27-Mar-09 02-Apr-09 20-May-09 02-Jun-09 02-Jun-09 Jun-09 09-Jun-09 09-Jul-09 Plan 62,000.00 02-Feb-09 09-Feb-09 26-Feb-09 27-Feb-09 03-Mar-09 N/A 03-Mar-09 31-Mar-09 LRCSP\ SH 29\1 Formation of the ortophotomaps PRI "FAZO" G FAC G Prior Post Prior Prior Prior SH SH LRCSP\ ICB.G. 6. Acquisition of space imaging 11 12 13 LRCSP\ SH 35 vehicles for 1Comp. And for ALMGCs LRCSP\ SH 38 procurement of geodetic equipment ( GPS base) 7sets for 7 RLCCs ICB ICB SH DC G ICB LRCSP\SH.- 20 photogrammetric eguipment SH LRCSP\ SH 32 SWs procurement: Lot 1 - GIS SWs. Lot 2 - SW on more than 150-300 km work lines computing. Lot 3 - Antivirus SWs. G LRCSP\ SH 29 Formation of the ortophotomaps PRI "FAZO" G SH G Prior Prior Prior Prior Prior Prior Prior ICB 4 5 6 9 3 LRCSP\ICB. G. 3 Office equipment G 7 8 10 1 LRCSP\ICB G.2 PROCUREMENT OF LAND SURVEY AND REGISTRATION EQUIPMENT GIS G 2 REPUBLIC of TAJIKISTAN: Land Registration and Cadastre System for Sustainable Agriculture Project (LRCSP) PROCUREMENT PLAN - GOODS AND WORKS dated December, 28, 2010. G* LRCSP\ICB. G. 1 PROCUREMENT OF LAND SURVEY AND REGISTRATION EQUIPMENT GPS ICB LRCSP\ICB G. 4 Vehicles G LRCSP\ SH.-19 SWs procurement G G LRCSP\ ICB.G. 5 Acquisition of space imaging G Prior LIB Page 2 Item No. Package number and name Type Method Plan/ act Cost estimate (US$) Draft Bidding Docs and SPN Bank's No objection to Bidding docs Issuance of Bidding Documents Bid Opening Bid Evaluation Report Bank's No objection to Contract Awd. Contract Signature Contract Completion Bank's Review Actual 61,400.00 30-Jan-09 03-Feb-09 04-Feb-09 27-Feb-09 27-Feb-09 N/A 02-Feb-09 05-Apr-09 Post SH 13 vehicles for 1Comp. And for ALMGCs controllers G Page 3 Item No. Package number and name Type Method Plan/ act Cost estimate (US$) Draft Bidding Docs and SPN Bank's No objection to Bidding docs Issuance of Bidding Documents Bid Opening Bid Evaluation Report Bank's No objection to Contract Awd. Contract Signature Contract Completion Bank's Review Plan 150,000.00 27-May-07 09-Jul-07 N/A N/A N/A Mar-08 14-Mar-08 14-Jul-08 Actual 41,700.00 27-May-07 09-Jul-07 N/A N/A N/A Mar-08 14-Mar-08 14-Jul-08 Plan 132,000.00 05-Jan-09 12-Jan-09 N/A N/A N/A 24-Apr-09 08-May-09 30-Nov-09 Actual 132,450.00 22-Apr-08 May-09 N/A N/A N/A 12-May-09 15-May-09 30-Nov-10 Plan 50,000.00 03-Feb-09 09-Feb-09 11-Feb-09 27-Feb-09 03-Mar-09 12-Jun-09 03-Mar-09 31Mar-09 Actual 47,460.00 27-Mar-09 20-Apr-09 20-May-09 02-Jun-09 02-Jun-09 09-Nov-09 10-Jun-09 10-Jul-09 Plan 5,600.00 03-Feb-09 09-Feb-09 12-May-09 29-May-09 01-June-09 12-Jun-09 15-Jun-09 30-Jul-09 Actual 5,250. 00 27-Mar-09 02-Apr-09 20-May-09 02-Jun-09 02-Jun-09 09-Nov-09 10-Jun-09 10-Jul-09 Plan 33,000.00 20-Mar-09 04-Apr-09 N/A N/A N/A 04-Apr-09 20-Jul-09 31-Dec-10 Actual 49,500.00 20-Mar-09 08-Apr-09 N/A N/A N/A 08-Apr-09 15-May-09 Plan 16,500.00 Oct-10 Oct-10 N/A N/A N/A Oct-10 Oct-10 28-Feb-11 Actual 16,500.00 05-Oct-10 21-Oct-10 N/A N/A N/A 21-Oct-10 25-Oct-10 Plan 15,000.00 May-10 N/A May-10 May-10 Jun-10 N/A Jul-10 27-Sep-10 Actual 14,835.00 02-Jul-10 N/A 07-Jul-10 21-Jul-10 21-Jul-10 N/A 28-Jul-10 04-Okt-10 Plan 5,000.00 10-May-09 N/A May-09 May-09 May-09 N/A 02-Jul-09 10-Nov-09 Actual 4,520.00 Aug-09 N/A 13-Aug-09 27-Aug-09 27-Aug-09 N/A 01-Sep-09 28-Sep-09 Plan 90,000.00 May-10 May-10 N/A N/A N/A May-10 May-10 15-Dec-10 Actual 64,209.00 10-Jun-10 18-Jun-10 N/A N/A N/A 13-Jul-10 15-Jul-10 12-Dec-10 Plan 145,620.00 Jan-11 Jan-11 N/A N/A N/A Jan-11 Feb-11 30-Sept-10 Actual Plan 55,000.00 May-10 May-10 May-10 Jun-10 Jun-10 N/A Jul-10 09-Sept-10 Actual 52,080.00 04-Jun-10 11-Jun-10 14-Jun-10 28-Jun-10 05-Jul-10 N/A 12-Jul-10 01-Oct-10 Plan 16,000.00 Oct-10 N/A Oct-10 Oct-10 Oct-10 N/A Nov-10 28-Dec-10 Actual 14,940.00 27-Oct-10 N/A 27-Oct-10 10-Nov-10 10-Nov-10 N/A 24-Nov-10 Plan 20,000.00 Oct-10 N/A Oct-10 Oct-10 Oct-10 N/A Nov-10 28-Dec-10 LRCSP\ DC- W -5 Geodetic network densification Prior Prior W Post Post Prior Prior SH DC DC Prior 15 14 LRCSP\ DC- W -6 densification network establishment with PRI "FAZO" 16 17 18 20 25 21 23 19 21 LRCSP\SH-37 printers for records printout on blank certificates SH W 24 LRCSP\SH-40 uniform procurement LRCSP\SH-36 laptops LRCSP\SH-42 procurement of cables for establishment of permanently functioning stations in 7 RLCCs SH G LRCSP\DC-39\1 blank certificates procurement from LLC "Polygraph Group" G G DC LRCSP\DC-39 blank certificates procurement from LLC "Polygraph Group" G DC Prior G FAC G SH G G Post Post Post 22 LRCSP\ FAC 29\3 Orthophotomaps production with PRI "FAZO" Prior SH SH G FAC LRCSP\SH-47 Laptops procurement for SCLMG LRCSP\ SH 29\2 Orthophotomaps production with PRI "FAZO" LRCSP\ SH-48 LRCSP\SH-43 Notebooks Prior G SH G Page 4 Item No. Package number and name Type Method Plan/ act Cost estimate (US$) Draft Bidding Docs and SPN Bank's No objection to Bidding docs Issuance of Bidding Documents Bid Opening Bid Evaluation Report Bank's No objection to Contract Awd. Contract Signature Contract Completion Bank's Review Actual 19,950.00 01-Nov-10 N/A 01-Nov-10 15-Nov-10 15-Nov-10 N/A 24-Nov-10 27-Dec-10 25 G Post SH Softwares procurement: GIS SWs; Page 5 Item No. Package number and name Type Method Plan/ act Cost estimate (US$) Draft Bidding Docs and SPN Bank's No objection to Bidding docs Issuance of Bidding Documents Bid Opening Bid Evaluation Report Bank's No objection to Contract Awd. Contract Signature Contract Completion Bank's Review Plan 40,000.00 Oct-10 N/A Oct-10 Oct-10 Oct-10 N/A Nov-10 28-Dec-10 Actual 41,600,00 27-Oct-10 N/A 27-Oct-10 10-Nov-10 10-Nov-10 N/A 24-Nov-10 Plan 9,000.00 Oct-10 N/A Oct-10 Oct-10 Oct-10 N/A Nov-10 28-Dec-10 Actual 8,920.00 27-Oct-10 N/A 27-Oct-10 10-Nov-10 10-Nov-10 N/A 24-Nov-10 Plan 11,000.00 Oct-10 N/A Oct-10 Oct-10 Oct-10 N/A Nov-10 28-Dec-10 Actual 10,728.00 27-Oct-10 N/A 27-Oct-10 10-Nov-10 10-Nov-10 N/A 24-Nov-10 Plan 15,000.00 May-10 N/A May-10 Jun-10 Jun-10 N/A Jul-10 28-Sept-10 Actual 14,300,00 07-Jul-10 N/A 14-Jul-10 05-Aug-10 05-Aug-10 N/A 10-Aug-10 26-Aug-10 Component : Plan 6,872.94 Jan-06 N/A Feb-06 Mar-06 10-Mar-06 N/A 13-Mar-06 May-06 Actual 6,872.94 Jan-06 N/A Feb-06 Mar-06 10-Mar-06 N/A 13-Mar-06 May-06 Plan 1,614.11 Jun-06 N/A Dec-06 25-Dec-06 25-Dec-06 N/A 28-Dec-06 29-Jan-07 Actual 1,614.11 Jun-06 N/A Dec-06 25-Dec-06 25-Dec-06 N/A 28-Dec-06 29-Jan-07 Plan 11,591.00 N/A N/A N/A N/A N/A N/A 05- Mar-08 pr- 08 Actual 11,591.00 N/A N/A N/A N/A N/A N/A 05- Mar-08 pr- 08 Plan 11,000.00 02-Dec-08 N/A 16-Dec-08 24-Dec-08 24-Dec-08 N/A 25-Dec-08 24- pr-09 Actual 10,163. 00 02-Dec-08 N/A 16-Dec-08 24-Dec-08 24-Dec-08 N/A 25-Dec-08 24- pr-09 Plan 33,000.00 11-Jan-10 17-Jan-10 27-Jan-10 17-Feb-10 17-Feb-10 1-Apr-10 1-May-10 28-Jun-10 Actual 29,900.00 10-Feb-10 18-Feb-10 22-Feb-10 6-Apr-10 6-Apr-10 20-Apr-10 28-Apr-10 28-Jun-10 Plan 30,000.00 Oct-10 N/A Oct-10 Oct-10 Oct-10 N/A Nov-10 26-Dec-10 Actual 29,862.00 Oct-10 N/A 10-Nov-10 23-Nov-10 23-Nov-10 N/A 26-Nov-10 Plan 30,000.00 Jun-11 N/A Jun-11 Jun-11 Jun-11 N/A Jul-11 Aug-11 Actual Component C: Plan Dec-05 Dec-05 Dec-05 Dec-05 20-Dec-05 N/A 26-Dec-05 26-Jan-06 Actual Dec-05 Dec-05 Dec-05 Dec-05 20-Dec-05 N/A 26-Dec-05 26-Jan-06 Plan 1,732.46 Dec-05 Dec-05 Dec-05 Dec-05 22-Dec-05 N/A 28-Dec-05 26-Jan-06 Actual 1,732.46 Dec-05 Dec-05 Dec-05 Dec-05 22-Dec-05 N/A 28-Dec-05 26-Jan-06 LRCSP\ SH 33\1 Printing materials (informational materials duplication) Post 36 LRCSP\ SH 33\2 Printing materials (informational materials duplication) 38 35 37 LRCSP\ DC High-variety cotton seeds "Flora" and "Carmen " LRCSP \SH 4 Seed Drills 26 30 29 LRCSP\SH-46 Office equipment 28 27 31 32 33 34 Post Post 10,002.32 Post Post SH Prior Post Prior Post Post Post G DC SH G SH G G G G * LRCSP\ SH 33 printing materials G G G G Post Post SH SH SH SH SH SH SH SH SH LRCSP\SH-2 Scanners, printers , digitical photocamera , lock box and office supplies (Comp.D&C) G LRCSP\SH-1 laptops LRCSP\ SH 25\1-n printing materials LRCSP\ SH 16 Equipment on seed delinting G LRCSP\ SH-50 Printers and removable HDDs (hard disks) procurement LRCSP\ SH-51 Procurement of papers and paints for plotters; G LRCSP\ SH-49 Server PCs procurement; Page 6 Item No. Package number and name Type Method Plan/ act Cost estimate (US$) Draft Bidding Docs and SPN Bank's No objection to Bidding docs Issuance of Bidding Documents Bid Opening Bid Evaluation Report Bank's No objection to Contract Awd. Contract Signature Contract Completion Bank's Review Plan 10,000.00 Dec-05 Dec-05 12-Jan-06 26-Jan-06 31-Jan-06 N/A 06-Feb-06 13-Feb-06 Actual 9,972.58 Dec-05 Dec-05 12-Jan-06 26-Jan-06 31-Jan-06 N/A 06-Feb-06 13-Feb-06 Plan 79,000.00 Dec-05 Dec-05 21-Mar-06 14-Apr-06 28-Apr-06 N/A 05-July-06 Aug-06 Actual 79,000.00 Dec-05 Dec-05 21-Mar-06 14-Apr-06 28-Apr-06 N/A 05-July-06 Aug-06 Plan 24,200.00 Nov-06. Nov-06. 15-Nov-06. 11-Dec-06 15-Dec-06 N/A 25-Dec-06 Jan-07 Actual 19,872.74 Nov-06 Nov-06 22-Nov-06 11-Dec-06 15-Dec-06 N/A 18-Dec-06 18-Jan-07 Plan 20,900.00 Nov-06. Nov-06. 29-Dec-06 Jan-07 15-Dec-06 N/A Feb-07 Mar-07 Actual 8,128.05 Nov-06 Nov-06 29-Dec-06 24-Jan-07 15-Dec-06 N/A 29-Mar-07 20-Apr-07 Plan 31,000.00 Nov-06. Nov-06. 16-Feb-07 25-Feb-07 15-Dec-06 N/A 16-Apr-07 May-07 Actual 33,600.00 Nov-06 Nov-06 31-Dec-06 31-Jan-07. 15-Dec-06 N/A 16-May-07 30-Jun-07 Plan 24,000.00 Oct-08 Oct-08 02-Oct-08 16-Oct-08 15-Dec-06 N/A 22-Oct-08 21-Nov-08 Actual 23,760.30 Nov-08 17-Nov-08 22-Dec-08 23-Dec-08 15-Dec-06 N/A 25-Dec-08 14-Feb-09 Plan 42,000.00 Oct-08 Oct-08 02-Oct-08 16-Oct-08 15-Dec-06 N/A 22-Oct-08 21-Nov-08 Actual 42,000.00 Nov-08 17-Nov-08 22-Dec-08 23-Dec-08 15-Dec-06 N/A 25-Dec-08 11-Feb-09 Plan 50,000.00 Feb-10 Mar-10 Mar-10 May-10 May-10 N/A May-10 09-Aug-10 Actual 36,000.00 22-Feb-10 10-Mar-10 06-Apr-10 30-Jun-10 30-Jun-10 N/A 05-Jul-10 02-Aug-10 Plan 25,000.00 Jun-10 N/A Jul-10 Jul-10 Jul-10 N/A Jul-10 16-Aug-10 Actual 16,000.00 14 -Jun-10 N/A 17-Jun-10 09-Jul-10 09-Jul-10 N/A 13-Jul-10 03-Aug-10 Component D: Plan 10,000.00 Jan-06 Jan-06 Jan-06 Jan-06 Feb-06 N/A 13-Mar-06 Apr-06 Actual 10,000.00 Jan-06 Jan-06 Jan-06 Jan-06 Feb-06 N/A 13-Mar-06 Apr-06 Plan 10,000.00 Jan-06 Jan-06 Jan-06 Jan-06 Feb-06 N/A 29-Mar-06 Apr-06 Actual 10,000.00 Jan-06 Jan-06 Jan-06 Jan-06 Feb-06 N/A 29-Mar-06 Apr-06 Plan 9,965.75 Mar-06 Mar-06 20-Mar-06 29-Mar-06 29-Mar-06 N/A 30-Mar-06 Apr-06 Actual 9,965.75 Mar-06 Mar-06 20-Mar-06 29-Mar-06 29-Mar-06 N/A 30-Mar-06 Apr-06 Plan 10,000.00 Mar-06 Mar-06 Mar-06 Mar-06 Mar-06 N/A 02-May-06 Jun-06 Actual 10,000.00 Mar-06 Mar-06 Mar-06 Mar-06 Mar-06 N/A 02-May-06 Jun-06 Plan 10,000.00 May-06 May-06 May-06 Jun-06 Jun-06 N/A 06-Jul-06 Aug-06 Actual 10,000.00 May-06 May-06 May-06 Jun-06 Jun-06 N/A 06-Jul-06 Aug-06 LRCSP\ SH- 31/2 Vehicles for component C G SH LRCSP \ SH- 17 omputer, ffice equipment Post 39 LRCSP\SH-11 Generator ( Vehicles Generator) Post G SH SH SH SH 47 51 52 LRCSP\SH-12 laptops 46 42 45 44 40 41 43 50 48 49 Post G G G G G G G Post Post Post Post SH SH Post Post Post Post Post SH SH SH SH SH Post LRCSP\ SH- 31/1 Vehicles (one for B-2 Subcomponent and another one for M&E carrying out) LRCSP\ SH- 31 Vehicles C LRCSP\SH-08 Scanners, printers, digitical photocamera, lock box and office supplies G G G G Post LRCSP\SH-07 Office Furniture LRCSP\SH-09 ffice equipment LRCSP-SH-3 PCs (Personal computers), UPSs (Comp.D&C) LRCSP\SH-15 Office Furniture LRCSP\SH-30 Office Furniture LRCSP\ SH- 18 Vehicles B C LRCSP\SH-05 laptops G SH SH Page 7 Item No. Package number and name Type Method Plan/ act Cost estimate (US$) Draft Bidding Docs and SPN Bank's No objection to Bidding docs Issuance of Bidding Documents Bid Opening Bid Evaluation Report Bank's No objection to Contract Awd. Contract Signature Contract Completion Bank's Review Component A: Plan 3,000.00 May-07 May-07 May-07 Jun-07 Jun-07 N/A Aug-07 02-Oct-07 Actual 3,174.00 May-07 May-07 20-Jun-07 Jun-07 Jun-07 N/A 21-Jul-08 21-Aug-08 Plan 3,000.00 May-07 May-07 May-07 Jun-07 Jun-07 N/A 03-Jun-08 03-Jul-08 Actual 3,000.00 May-07 May-07 May-07 Jun-07 Jun-07 N/A 03-Jun-08 03-Jul-08 Plan 3,000.00 May-07 May-07 May-07 Jun-07 Jun-07 N/A 10-Jun-08 10-Jul-08 Actual 3,000.00 May-07 May-07 May-07 Jun-07 Jun-07 N/A 12-Jun-08 12-Jul-08 Plan 3,000.00 Mar-07 Mar-07 Mar-07 Apr-07 Apr-07 N/A 29-Apr-08 29-May-08 Actual 2,890.00 Mar-07 Mar-07 Mar-07 Apr-07 Apr-07 N/A 02-May-08 06-Jun-08 Plan 3,000.00 May-07 May-07 May-07 Jun-07 Jun-07 N/A 17-Jun-08 17-Jul-08 Actual 3,000.00 May-07 May-07 May-07 Jun-07 Jun-07 N/A 17-Jun-08 17-Jul-08 Plan 3,000.00 May-07 May-07 May-07 Jun-07 Jul-07 N/A 30-Aug-07 30-Sep-08 Actual 3,000.00 May-07 May-07 May-07 Jun-07 Jul-07 N/A 27-Aug-07 29-Sep-08 Plan 3,000.00 May-07 May-07 May-07 Jun-07 Jul-07 N/A 15-Aug-08 15-Sep-08 Actual 3,062.00 May-07 May-07 May-07 Jun-07 Jul-07 N/A 18-Aug-08 Sep-08 Plan 5,000.00 Nov-09 N/A Nov-09 Dec-09 Dec-09 N/A Dec-09 12-Feb-10 Actual 4,966.09 Nov-09 N/A 20-Nov-09 05-Dec-09 05-Dec-09 N/A 12-Dec-09 12-Feb-10 Plan 4,500. 00 Nov-09 N/A Nov-09 Nov-09 Nov-09 N/A Dec-09 11-May-10 Actual 4,513.71 11-Nov-09 N/A 13-Nov-09 28-Nov-09 28-Nov-09 N/A 04-Dec-09 11-May-10 Plan 5,000.00 Dec-10 N/A Jan-11 Jan-11 Jan-11 N/A Jan-11 27-Feb-11 Actual 4,566,00 Dec-10 N/A 06-Dec-10 20-Dec-10 20-Dec-20 N/A 27-Dec-10 Plan 3,500.00 Nov-09 N/A Nov-09 Nov-09 Nov-09 N/A Dec-09 01-Feb-10 Actual 3,503.17 Nov-09 N/A 09-Nov-09 30-Nov-09 30-Nov-09 N/A 01-Dec-09 01-Feb-10 Plan 4,000.00 Nov-09 N/A Nov-09 Dec-09 Dec-09 N/A Dec-09 03-Feb-10 Actual 3, 962.00 02-Nov-09 N/A 02-Nov-09 01-Dec-09 01-Dec-09 N/A 03-Dec-09 03-Feb-10 SW W Post LRCSP\ SH W 3\1 Gissar Land Regional Center Offices repair SW W W 59 LRCSP\ SH W 3 MBAR (Khorog) Land Regional Center Offices repair LRCSP\ SH W 3\5 Khodjent Land Regional Center Offices repair 61 62 60 LRCSP\ SH W 3\4 Kulyab Land Regional Center Offices repair LRCSP\ SH W 3\3 Vakhsh Land Regional Center Offices repair 64 W LRCSP\ SH W 3 Kulyab Land Regional Center Offices repair 57 W SW 54 LRCSP\ SH W 3 Rasht Land Regional Center Offices repair 53 LRCSP\ SH W 3 Gissar Land Regional Center Offices repair 63 58 LRCSP\ SH W 3 Zarafshon Land Regional Center Offices repair LRCSP\ SH W 3\2 Rasht Land Regional Center Offices repair 56 55 LRCSP\ SH W 3 Vakhsh Land Regional Center Offices repair SW SW SW SW W Post SW Post W SW SW SW Post Post Post Post LRCSP\ SH W 3 Khodjent Land Regional Center Offices repair Post Post Post Post Post W SW W W W W Page 8 Item No. Package number and name Type Method Plan/ act Cost estimate (US$) Draft Bidding Docs and SPN Bank's No objection to Bidding docs Issuance of Bidding Documents Bid Opening Bid Evaluation Report Bank's No objection to Contract Awd. Contract Signature Contract Completion Bank's Review Plan 3,500.00 Dec-10 N/A Jan-11 Jan-11 Jan-11 N/A Jan-11 Mar-11 Actual Plan 10,000.00 Dec-09 N/A Jan-10 Jan-10 Jan-10 N/A Feb-10 19-Apr-10 Actual 9,980.00 Dec-09 N/A 02-Dec-09 16-Dec-09 16-Dec-09 N/A 21-Dec-09 20-Apr-10 Plan 4,500. 00 Jun-10 N/A Jun-10 Jun-10 Jun-10 N/A Jun-10 08-Sep-10 Actual 4,496.00 07-Jun-10 N/A 11-Jun-10 28-Jun-10 28-Jun-10 N/A 08-Jul-10 08-Sep-10 Plan 5,000.00 Jun-10 N/A Jun-10 Jun-10 Jun-10 N/A Jun-10 02-Nov-10 Actual 4,989,00 16-Aug-10 N/A 16-Aug-10 31-Aug-10 31-Aug-10 N/A 02-Sep-10 26-Nov-10 Component : Plan 114,000.00 Mar-06 27-Mar-06 Apr-06 14-Apr-06 May-06 28-Jun-06 4-Jul-06 Oct-06 Actual 85,976.00 Mar-06 27-Mar-06 Apr-06 14-Apr-06 May-06 28-Jun-06 4-Jul-06 Oct-06 Plan 8,736.00 15-Sep-08 16-Sept-08 30-Sept-08 13-Oct-08 Oct-08 N/A Oct-08 Dec-08 Actual 8,477.40 15-Sep-08 16-Sept-08 30-Sept-08 13-Oct-08 Oct-08 N/A 21-Oct-08 21-Dec-08 Component D: Plan 9,950.00 Jun-06 N/A Jun-06 Jun-06 Jun-06 N/A Jun-06 Jul-06 Actual 9,950.00 Jun-06 N/A Jun-06 Jun-06 Jun-06 N/A Jun-06 Jul-06 Procurement plan updated by: Davlatov J. LRCSP\ NCB W -1 LRCSP\ SH W 3\7 MBAR (Khorog) Land Regional Center Offices repair LRCSP\ SH W 3\6 Zarafshon Land Regional Center Offices repair W 66 LRCSP\ SH W - 2 Office building repair 67 LRCSP\ SH W 4 Repair of Rasht RLCCs additonal office space 68 LRCSP\ SH W 5. Repair the roof of the MBAR (Khorog) Regional Land Cadastre Centers Offices 71 69 LRCSP\ SH W 6 Reconstruction of the part of the 4-th floor of SPI "Tajikgiprozem” building. 70 65 W SW W SW Post Post W Prior NCB W SW Post Post Post Post SW W SW W SW Page 9 Comments Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Page 10 Comments Completed Page 11 Comments Completed Contract was concluded Completed Contract was concluded Completed The Amendment # 1 dated February, 19, 2010, on contract completion periods extension (WB no objection, dated February, 19, 2010) was introduced, in order to procure completely the10, 000 numbers of blank Certificates, The Amendment # 2 dated June, 07, 2010 (WB no objection, dated une, 07, 2010) on additional procurement of 5, 000 numbers of blank Certificates copies. Completed Completed Completed New procurement Completed Completed Completed Page 12 Comments Completed Page 13 Comments Completed Completed Completed Completed Contract was concluded New procurement Completed Completed Completed Completed Contract was concluded Contract was concluded Contract was concluded Page 14 Comments Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Page 15 Comments Completed Completed Completed Completed Completed Completed Completed Completed Contract was concluded. Completed Completed Completed Completed Page 16 Comments Completed Completed Completed Dates are changed Completed Completed Completed