ANNEX 2 - PROCUREMENT PLAN TEMPLATE FOR CONSULTING SERVICES AND GOODS (RESPONSE TO QUESTION B9). A. Consulting Services N Description (QCBS, CQS, ICS and Review by WB (Prior Proposal Submission Cost Estimate incl. Contract Duration o. Issuance of REOI Selection Method Type of Contract Contract Signing Issuance of RFP Funding Source Contract Start Package No. VAT (USD) (months) or Post) etc.) Resettlement Policy Framework and FRM- 1 200,000 PPTAF CQS LS Post 9/2014 11/2014 11/2014 12/2014 12/2014 8 Resettlement Action Plan PPTAF 01 Environment impact assessment and FRM- 2 environment management 298,000 PPTAF CQS LS Post 9/2014 11/2014 12/2014 12/2014 12/2014 8 PPTAF 02 plan. Review, update and amend the existing FSs of works items under Tham Luong – Ben Cat – Nuoc Len basin, consisting of: - FS of Tham Luong – Ben Cat – Nuoc Len main canal dredging and embankment. FRM- 3 200,000 PPTAF CQS LS Prior 8/2014 10/2014 11/2014 11/2014 11/2014 5 - FS of Nuoc Len Sluice PPTAF 03 Gate. - FS of Vam Thuat Sluice Gate. - FS of secondary canals connected to Tham Luong – Ben Cat – Nuoc Len canal. - FS of primary interceptor N Description (QCBS, CQS, ICS and Review by WB (Prior Proposal Submission Cost Estimate incl. Contract Duration o. Issuance of REOI Selection Method Type of Contract Contract Signing Issuance of RFP Funding Source Contract Start Package No. VAT (USD) (months) or Post) etc.) system. - FS of collecting stormwater and wastewater sewers systems in Go Vap district. Bidding documents preparation of civil works & equipments Vam Thuat tidal sluice gate. Survey, detailed design, FRM - 4 530,000 PPTAF QCBS LS Prior 9/2014 11/2014 1/2015 4/2015 4/2015 5 cost estimate, bidding PPTAF 04 documents preparation of civil works & equipments for Nuoc Len tidal sluice gate. Verification of detailed design and cost estimate of Nuoc Len tidal sluice FRM- 5 15,000 PPTAF CQS LS Post 3/2015 5/2015 5/2015 6/2015 6/2015 3 gate. PPTAF 05 Project Implementation Manual , Procurement FRM- 6 Plan for initial 18 month. 50,000 PPTAF CQS LS Post 11/2014 1/2015 1/2015 2/2015 2/2015 6 PPTAF 06 N Description (QCBS, CQS, ICS and Review by WB (Prior Proposal Submission Cost Estimate incl. Contract Duration o. Issuance of REOI Selection Method Type of Contract Contract Signing Issuance of RFP Funding Source Contract Start Package No. VAT (USD) (months) or Post) etc.) Study retention ponds serving for flood prevention and drainage in FRM- 7 145,000 PPTAF CQS LS Post 8/2014 10/2014 11/2014 12/2014 12/2014 4 Tham Luong – Ben Cat – PPTAF 07 Nuoc Len basin. Individual Support for FRM- Time- 8 200,000 PPTAF 08 PPTAF IC Prior 8/2014 8/2014 9/2014 9/2014 9/2014 15 Procurement based Goods, Non-Consulting Services Type of Contract: Shopping , Direct Selection Method Contract Signing Issuance of RFQ incl. VAT (USD) Funding Source Review by WB (Prior or Post) Bids Received Cost Estimate Delivery Date Package No. Contracting No. Description SOE, PO, 1 Office equipment 95,900 FRM-PPTAF 09 PPTAF Goods SOE Post 8/2014 9/2014 9/2014 10/2014 procurement for PMU of Works Construction serving for PPTAF sub- project. Total: 95,900