The World Bank                                                                             Implementation Status & Results Report
            Dar es Salaam Maritime Gateway Project (P150496)



Dar es Salaam Maritime Gateway Project (P150496)

 AFRICA | Tanzania | Transport Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 4 | ARCHIVED on 25-Jun-2019 | ISR37610 |


 Implementing Agencies: Tanzania Ports Authority (TPA), THE UNITED REPUBLIC OF TANZANIA



 Key Dates

  Key Project Dates

   Bank Approval Date: 30-Jun-2017                                             Effectiveness Date: 27-Apr-2018
   Planned Mid Term Review Date: 30-Jun-2021                                   Actual Mid-Term Review Date: --
   Original Closing Date: 30-Jun-2024                                          Revised Closing Date: 30-Jun-2024
 pdoTable

 Project Development Objectives
  Project Development Objective (from Project Appraisal Document)
  The Project Development Objective is to improve the effectiveness and efficiency of the Port of Dar es Salaam, for the benefit of public and private
  stakeholders.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components            Table




 Name
 Improving the Physical Infrastructure.:(Cost $400.00 M)
 Institutional Strengthening and Implementation Assistance:(Cost $21.00 M)


 Overall Ratings

 Name                                                                        Previous Rating                          Current Rating

 Progress towards achievement of PDO                                         Satisfactory                            Satisfactory
 Overall Implementation Progress (IP)                                        Satisfactory                            Moderately Satisfactory
 Overall Risk Rating                                                         Substantial                             Substantial


 Implementation Status and Key Decisions
  Signing and Effectiveness The Credit, Grant and Project Agreements were completed and signed on September 28, 2017 and the Credit and
  Grant declared effective on April 17, 2018.
  Significant progress has been achieved in implementation of civil works in past 12 months. The execution of the works contract to
  rehabilitate berths 1-7 and construct a new multipurpose berth at Gerezani Creek has progressed well, with 40 percent of the scheduled works
  under that contract now complete.




6/25/2019                                                                                                                      Page 1 of 5
                 The World Bank                                                                     Implementation Status & Results Report
                 Dar es Salaam Maritime Gateway Project (P150496)




  Risks

 Systematic Operations Risk-rating Tool

  Risk Category                                                Rating at Approval       Previous Rating            Current Rating

  Political and Governance                                     Substantial             Substantial               Substantial
  Macroeconomic                                                Substantial             Substantial               Substantial
  Sector Strategies and Policies                               Moderate                Substantial               Substantial
  Technical Design of Project or Program                       Substantial             Substantial               Substantial
  Institutional Capacity for Implementation and
  Sustainability                                               Substantial             Substantial               Substantial
  Fiduciary                                                    Substantial             Substantial               Substantial
  Environment and Social                                       Substantial             High                      High
  Stakeholders                                                 Substantial             Substantial               Substantial
  Other                                                        --                       --                         --
  Overall                                                      Substantial             Substantial               Substantial


  Results

 PDO Indicators by Objectives / Outcomes


   To improve the effectiveness and efficiency of the Port for benefit of public and private stakeholdr
    IN00715970




    ►Actual        throughput capacity (Number, Custom)

                                           Baseline                 Actual (Previous)        Actual (Current)       End Target
    Value                                 15.00                     0.00                     0.00                   25.00

    Date                                  31-Dec-2016               27-Feb-2018              27-Feb-2018           30-Jun-2024
    IN00716026




    ►TPA          Restructured to reflect new responsibilities (Text, Custom)

                                           Baseline                 Actual (Previous)        Actual (Current)       End Target
    Value                                 Not implemented           not implemented          not implemented        Implemented

    Date                                  31-Dec-2016               27-Feb-2018              27-Feb-2018           30-Jun-2024
    IN00716027




    ►Ship         Waiting Time (Hours, Custom)

                                           Baseline                 Actual (Previous)        Actual (Current)       End Target
    Value                                 80.00                     0.00                     0.00                   30.00



6/25/2019                                                                                                               Page 2 of 5
                 The World Bank                                                            Implementation Status & Results Report
                 Dar es Salaam Maritime Gateway Project (P150496)



    Date                                31-Dec-2016             27-Feb-2018         27-Feb-2018           30-Jun-2024
    IN00716028




    ►Berth         Occupancy (Percentage, Custom)

                                        Baseline                Actual (Previous)   Actual (Current)       End Target
    Value                               55.00                   0.00                0.00                   40.00

    Date                                31-Dec-2016             27-Feb-2018         27-Feb-2018           30-Jun-2024
    IN00716029




    ►Operational        Productivity (Number, Custom)

                                        Baseline                Actual (Previous)   Actual (Current)       End Target
    Value                               16.00                   0.00                0.00                   24.00

    Date                                31-Dec-2016             27-Feb-2018         27-Feb-2018           30-Jun-2024
    IN00716030




    ►Vessel         Turnaround Time (Hours, Custom)

                                        Baseline                Actual (Previous)   Actual (Current)       End Target
    Value                               80.00                   0.00                0.00                   60.00

    Date                                31-Dec-2016             27-Feb-2018         27-Feb-2018           30-Jun-2024


 Overall Comments           PDO




  TPA is expected to update the results framework ahead of a late June mission; that update will be reflected in
  the next ISR.



 Intermediate Results Indicators by Components


   Improving the Physical Infrastructure.
    IN00716032




    ►Multipurpose        berth constructed and operational (Percentage, Custom)

                                        Baseline                Actual (Previous)   Actual (Current)       End Target
    Value                               0.00                    0.00                0.00                   100.00

    Date                                31-Dec-2016             27-Feb-2018         27-Feb-2018           30-Jun-2024
    IN00716033




    ►Berths         8-11 Strengthened and Deepened (Percentage, Custom)

                                        Baseline                Actual (Previous)   Actual (Current)       End Target
    Value                               0.00                    0.00                0.00                   100.00

    Date                                31-Dec-2016             27-Feb-2018         27-Feb-2018           30-Jun-2024


6/25/2019                                                                                                     Page 3 of 5
                 The World Bank                                                                              Implementation Status & Results Report
                 Dar es Salaam Maritime Gateway Project (P150496)


    IN00716034




    ►Entrance         Channel and Turning Basin Dredged (Number, Custom)

                                           Baseline                   Actual (Previous)              Actual (Current)          End Target
    Value                                 10.00                       10.00                          10.00                     15.40

    Date                                  31-Dec-2016                 27-Feb-2018                    27-Feb-2018               30-Jun-2024
    IN00716035




    ►Berths         1-7 Strengthened and Deepened (Percentage, Custom)

                                           Baseline                   Actual (Previous)              Actual (Current)          End Target
    Value                                 0.00                        0.00                           0.00                      100.00

    Date                                  31-Dec-2016                 27-Feb-2018                    27-Feb-2018               30-Jun-2024



   Institutional Strengthening and Implementation Assistance
    IN00716031




    ►Implementation         of Port Community System and Terminal Operating Systems (Text, Custom)

                                           Baseline                   Actual (Previous)              Actual (Current)          End Target
                                                                                                                               New Systems
    Value                                 No systems                  No system yet                  No system yet
                                                                                                                               Operational

    Date                                  31-Dec-2016                 27-Feb-2018                    27-Feb-2018               30-Jun-2024




 Data on Financial Performance

 Disbursements (by loan)

 Project            Loan/Credit/TF    Status      Currency      Original     Revised    Cancelled      Disbursed        Undisbursed                % Disbursed

 P150496            IDA-61170         Effective   USD             345.00      345.00          0.00           113.90           231.10                      33%

 P150496            TF-A5002          Effective   USD              12.00       12.00          0.00             4.40             7.60                      37%


 Key Dates (by loan)
 Project             Loan/Credit/TF   Status      Approval Date     Signing Date       Effectiveness Date       Orig. Closing Date      Rev. Closing Date

 P150496             IDA-61170        Effective   30-Jun-2017       02-Oct-2017        27-Apr-2018              30-Jun-2024             30-Jun-2024
 P150496             TF-A5002         Effective   30-Jun-2017       02-Oct-2017        27-Apr-2018              30-Sep-2021             30-Sep-2021


Cumulative Disbursements




6/25/2019                                                                                                                            Page 4 of 5
            The World Bank                                     Implementation Status & Results Report
            Dar es Salaam Maritime Gateway Project (P150496)




  Restructuring History

  There has been no restructuring to date.


  Related Project(s)

  There are no related projects.




6/25/2019                                                                         Page 5 of 5