Feasibility Report cum Preliminary Design for Up-gradation of Ras –                                                 SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan




                                         Table of Contents
CHAPTER - 0.:         EXECUTIVE SUMMARY                                                                                          2

   0.1 Background ............................................................................................................. 2
   0.2 Corridor Description................................................................................................. 2
   0.3 Resettlement Action Plan: Objectives ...................................................................... 2
   0.4 Right of Way ............................................................................................................ 2
   0.5 Resettlement Policy Framework .............................................................................. 2
   0.6 Cut-off Date ............................................................................................................. 2
   0.7 Impact on Land and Structures ................................................................................ 3
   0.8 Land Acquisition ...................................................................................................... 3
   0.9 Categories of Impact ............................................................................................... 3
   0.10Socio-Economic Profile ........................................................................................... 3
   0.11Public Consultations ................................................................................................ 3
   0.12Implementation Arrangement .................................................................................. 3
   0.13Grievance Redress Mechanism ............................................................................... 3
   0.14RAP Implementation Schedule ................................................................................ 3
   0.15Resettlement Budget ............................................................................................... 4

CHAPTER - 1.:         PROJECT BACKROUND                                                                                          5

   1.1 Project Background ................................................................................................. 5
   1.2 Project Location....................................................................................................... 5
   1.3 Importance and Need of the project:- ...................................................................... 6
       1.3.1    Population of Influence Regions ................................................................ 7
   1.4 Need for Social Impact Assessment (SIA) and Resettlement Action Plan (RAP) ..... 7
   1.5 Scope and Objectives of Social Impact Assessment and Resettlement Action Plan 8
   1.6 Approach and Methodology:-................................................................................... 8
   1.7 Structure of the Report:- .......................................................................................... 9

CHAPTER - 2.:         PROJECT DESCRIPTION                                                                                      10

   2.1 Project Profile ........................................................................................................ 10
   2.2 Existing Alignment ................................................................................................. 11
   2.3 Existing Road Features and Constraints................................................................ 12
       2.3.1    Dense Built Up Areas & Settlements ....................................................... 12
       2.3.2    Deficient Vertical and Horizontal Geometry and Improvement................. 13
       2.3.3    Deficient Cross Drainage Structures and Improvements ......................... 13
       2.3.4    Safety of the Users.................................................................................. 14
   2.4 Porposed Structures .............................................................................................. 14
       2.4.1    Major and Minor Bridge ........................................................................... 15
       2.4.2    Vehicular Under Pass (VUP) ................................................................... 17
       2.4.3    Toll Plazas .............................................................................................. 18
   2.5 Right of Way (RoW)............................................................................................... 18
   2.6 Typical Cross Sections .......................................................................................... 19
   2.7 Bypasses and Realignments ................................................................................. 23
   2.8 Service roads ........................................................................................................ 24
   2.9 Other Structures .................................................................................................... 24
       2.9.1    Pedestrians ............................................................................................. 24
       2.9.2    Wayside Amenities.................................................................................. 25
       2.9.3    Bus bays and Truck lay-bys .................................................................... 25
   2.10Road Safety .......................................................................................................... 26

Feedback Infra Pvt. Ltd                                   i                   Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –                                                SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



         2.10.1       Road Accident Black Spot Identification and Removal ............................ 26
         2.10.2       Road User Safety Solutions .................................................................... 27
         2.10.3       Pedestrian Safety .................................................................................... 28
         2.10.4       Road Safety Schedule and Traffic Calming Measures ............................ 29

CHAPTER - 3.:         SOCIO – ECONOMIC PROFILE OF PROJECT INFLUENCE AREA                                                      30

   3.1 Introduction ........................................................................................................... 30
   3.2 Overview of Rajasthan .......................................................................................... 30
   3.3 Project Influence Area (PIA) .................................................................................. 31
   3.4 Demographic Composition: Pali District ................................................................. 32
       3.4.1     Population ............................................................................................... 32
       3.4.2     Social Stratification.................................................................................. 32
       3.4.3     Literacy and Literacy Rate....................................................................... 32
       3.4.4     Workers and Work Participation Rate...................................................... 33
       3.4.5     Categorization of Main Workers on the basis of Occupation ................... 33
       3.4.6     Categorization of Marginal Workers on the basis of Occupation.............. 33
   3.5 Demographic Composition: Ajmer District ............................................................. 33
       3.5.1     Population ............................................................................................... 33
       3.5.2     Social Stratification.................................................................................. 33
       3.5.3     Literacy and Literacy Rate....................................................................... 33
       3.5.4     Workers and Work Participation Rate...................................................... 33
       3.5.5     Categorization of Main Workers on the basis of Occupation ................... 33
       3.5.6     Categorization of Marginal Workers on the basis of Occupation.............. 33
   3.6 Demographic Composition: Rajsamand District ..................................................... 34
       3.6.1     Population ............................................................................................... 34
       3.6.2     Social Stratification.................................................................................. 34
       3.6.3     Literacy and Literacy Rate....................................................................... 34
       3.6.4     Workers and Work Participation Rate...................................................... 34
       3.6.5     Categorization of Main Workers on the basis of Occupation ................... 34
       3.6.6     Categorization of Marginal Workers on the basis of Occupation.............. 34
   3.7 Demographic Composition: Bhilwara District ......................................................... 34
       3.7.1     Population ............................................................................................... 34
       3.7.2     Social Stratification.................................................................................. 34
       3.7.3     Literacy and Literacy Rate....................................................................... 35
       3.7.4     Workers and Work Participation Rate...................................................... 35
       3.7.5     Categorization of Main Workers on the basis of Occupation ................... 35
       3.7.6     Categorization of Marginal Workers on the basis of Occupation.............. 35

CHAPTER - 4.:         REGULATORY FRAMEWORK AND ENTITLEMENT MATRIX                                                             36

   4.1 Introduction ........................................................................................................... 36
   4.2 Applicable National and State Policy Framework ................................................... 36
       4.2.1     The Right to Fair Compensation and Transparency in Land Acquisition,
            Rehabilitation and Resettlement Act, 2013 ..................................................... 36
       4.2.2     The Rajasthan Right to Fair Compensation and Transparency in land
            Acquisition, Rehabilitation and Resettlement Rules, 2016 .............................. 36
   4.3 Resettlement Framework Principles and Entitlement Matrix .................................. 36

CHAPTER - 5.:         PUBLIC INFORMATION AND CONSULTATIONS                                                                    44

   5.1 Introduction ........................................................................................................... 44
   5.2 Classification of Stakeholders ................................................................................ 44
   5.3 Consultation Process............................................................................................. 44

Feedback Infra Pvt. Ltd                                  ii                   Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –                                                SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



   5.4 Stakeholder’s consultation ..................................................................................... 44
       5.4.1    Consultations with Local Community ....................................................... 45
   5.5 Consultation with Land Owner ............................................................................... 51
   5.6 Consultation with Women ...................................................................................... 55
   5.7 Village Panchayat/Municipality corporation ............................................................ 57
   5.8 Consultation with Industries ................................................................................... 59
   5.9 Consultation with NGOs ........................................................................................ 61
   5.10Consultation with Project Developer ...................................................................... 62
   5.11Key Issues/concerns and suggestion .................................................................... 63

CHAPTER - 6.:         ANALYSIS OF ALTERNATIVES                                                                                64

   6.1 Inputs at Different Stages for Minimizing Resettlement .......................................... 64
   6.2 With and Without Project Alternatives .................................................................... 65
       6.2.1     Without Project Scenario ......................................................................... 65
       6.2.2     With Project Scenario .............................................................................. 65
   6.3 Analysis of Alternatives Alignment ......................................................................... 67
       6.3.1     Criteria for Fixing bypasses and realignment........................................... 67
       6.3.2     Alternative Analysis of Bypasses and realignments ................................. 67

CHAPTER - 7.:         EVALUATION OF SOCIAL IMPACT ASSESSMENT                                                                  68

   7.1 Introduction ........................................................................................................... 68
   7.2 Cut-Off Date .......................................................................................................... 68
   7.3 Land Acquisition Estimates for the Project ............................................................. 68
   7.4 Type of Land to be acquired .................................................................................. 68
   7.5 Impact on Structures ............................................................................................. 68
   7.6 Type of Affected Structure ..................................................................................... 69
   7.7 Construction type of Structure ............................................................................... 69
   7.8 Impact on Private structures .................................................................................. 69
   7.9 Impact of Common Property Resources ................................................................ 70
   7.10Ownership status of private structure .................................................................... 71
   7.11Socio-Economic profile of the PAPs along the Project Road ................................. 71
   7.12Total Number of Project Affected Persons (PAPs0 along the project road ............. 71
   7.13Religious Category of PAHs along the Project Road ............................................. 72
   7.14Social Stratification of PAHs .................................................................................. 72
   7.15Vulnerable Groups................................................................................................. 72
   7.16Literacy Status of PAHs ......................................................................................... 73
   7.17Occupation pattern of the family along the Project Road ....................................... 73
   7.18Income Level of the PAHs ..................................................................................... 74
   7.19Conclusion ............................................................................................................ 74

CHAPTER - 8.:         GENDER ANALYSIS                                                                                         75

   8.1 Introduction ........................................................................................................... 75
   8.2 Women’s Participation in the Project ..................................................................... 75
   8.3 Women Headed Household................................................................................... 75

CHAPTER - 9.:         RESETTLEMENT BUDGET                                                                                     76

   9.1 Introduction ........................................................................................................... 76
   9.2 CONCLUSIONS ....................................................... Error! Bookmark not defined.

CHAPTER - 10.: INSTITUTIONAL ARRANGEMENT FOR RAP IMPLEMENTATION                                                               80

Feedback Infra Pvt. Ltd                                 iii                   Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –                                                SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



   10.1Central Level ......................................................................................................... 81
   10.2State Level ............................................................................................................ 81
   10.3Sub-Project Level .................................................................................................. 82
   10.4RAP Implementation Support Agency.................................................................... 83
   10.5Replacement Cost Committee at District Level ...................................................... 84
   10.6Mechanism for Implementation of RAP, Training and Capacity Building – at Project
       and Sub-project Level............................................................................................ 85

CHAPTER - 11.: GRIEVANCE REDRESSAL MECHANISM                                                                                  86

   11.1Grievance Redressal Committee (GRC) ................................................................ 86
   11.2Suggestion and Complaint Handling Mechanism (SCHM) ..................................... 87
   11.3Training and Capacity Building – at Project and Sub-project Level ........................ 88
   11.4Monitoring and Evaluation (M&E) at Project and Sub-project Level ....................... 88

CHAPTER - 12.: IMPLEMENTATION SCHEDULE                                                                                        90

   12.1Coordination with civil works and certification ........................................................ 90

CHAPTER - 13.: MONITORING & EVALUATION (M & E)                                                                                94

   13.1Institutional Arrangement for M & E ....................................................................... 94
   13.2Monitoring and Evaluation (M&E) at Project and Sub-project Level ....................... 94
   13.3Process & Performance Monitoring ....................................................................... 95
   13.4Evaluation ............................................................................................................. 97
   13.5Reporting............................................................................................................... 98




Feedback Infra Pvt. Ltd                                 iv                    Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                                              SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                                                      List of Tables

Table 1-1: Population of broadly influencing regions near project ........................................... 7
Table 1-2: Population distribution in project influence area ..................................................... 7
Table 2-1: District wise project Road alignment ...............................................................11
Table 2-2: Chainage wise breakup of proposed highway.......................................................11
Table 2-3: List of Major Built-Up / Settlements along Project Road ........................................12
Table 2-4: Summary of Existing Structures............................................................................13
Table 2-5: List of Structures ..................................................................................................14
Table 2-6: Proposed Major Bridge .........................................................................................15
Table 2-7: Minor Bridges to be repaired and widening ...........................................................15
Table 2-8: Minor Bridges in Re-Construction .........................................................................16
Table 2-9: Minor Bridges in New-Construction ......................................................................16
Table 2-10: Improvement Proposal of VUP ...........................................................................17
Table 2-11: Improvement Proposal of VUP Grade-II .............................................................18
Table 2-12: Proposed toll plaza locations ..............................................................................18
Table 2-13: Design chainage with length and RoW at additional locations ............................18
Table 2-14: List of Typical Cross Sections .............................................................................19
Table 2-15: Bypass Locations ...............................................................................................23
Table 2-16: Realignment Locations .......................................................................................23
Table 2-17: Locations of the Service Road ............................................................................24
Table 2-18: Pedestrian Subway.............................................................................................24
Table 2-19: Proposed Wayside Amenities .............................................................................25
Table 2-20: List of Proposed Bus bay ....................................................................................25
Table 3-1: An Overview of Rajasthan ....................................................................................30
Table 3-2: Districts at a Glance .............................................................................................31
Table 4-1: Entitlement Matrix .................................................................................................37
Table 5-1: Details of Consultation with local community ........................................................45
Table 5-2: Details of consultation with land owner .................................................................51
Table 5-3: Details of consultation with women .......................................................................55
Table 5-4: Details of consultation with Panchayat and Municipality .......................................57
Table 5-5: Details of consultation with industries ...................................................................59
Table 5-6: Details of consultation with NGOs....................................................................61
Table 6-1: "With and Without" Project Scenarios - A Comparative Assessment ....................65
Table 7-1: Details of available land ........................................................................................68
Table 7-2: Categorization of the private land .........................................................................68
Table 7-3: Type of Affected Structure ....................................................................................69
Table 7-4: Construction type of the affected structure ...........................................................69
Table 7-5: Categorization of private structure ........................................................................69
Table 7-6: Details of CPRs ....................................................................................................70
Table 7-7: Categorization of ownership status .......................................................................71
Table 7-8: Number of PAPs along the Project Road ..............................................................71
Table 7-9: Religious Categories of PAHs along the Project Road ........................................72
Table 7-10: Social Stratification of PAHs along the Project Road ..........................................72
Table 7-11: Categorization of vulnerable category.................................................................72
Table 7-12: Categorization of educational level of PAHs .......................................................73
Table 7-13: Occupation Pattern ............................................................................................74
Table 7-14: Annual Income of Affected household ...............................................................74
Table 9-1: Estimated Budget for Resettlement & Rehabilitation.............................................76
Table 12-1: Implementation Schedule of Resettlement Plan .................................................91
Table 13-1: Performance Monitoring for RAP Implementation ...............................................95
Table 13-2: Impact Indicators ................................................................................................97


 Feedback Infra Pvt. Ltd                                  v                   Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                                               SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan




                                                       List of Figures

Figure 1-1: Key Map of the Project Road ................................................................................ 5
Figure 2-1: Key Map of the Project Road ...............................................................................11
Figure 2-2: Typical Cross Section..........................................................................................22
Figure 2-3: Black Spot ...........................................................................................................27
Figure 3-1: Key map of Rajasthan ......................................................................................31
Figure 10-1: Institutional Arrangement for RAP Implementation ............................................80
Figure 11-1: Grievance Redressal Mechanism ......................................................................87

LIST OF ANNEXURES

        Annexure 1.1:               Letter of Commencement
        Annexure 1.2:               Census survey format
        Annexure 5.1:               Photographs of Consultation with Stakeholders
        Annexure 5.2:               Attendance Sheet of Consultation with Stakeholders
        Annexure 6.1:               Bypasses and Realignments details
        Annexure 7.1:               List of Owners of Private Structure
        Annexure 7.2:               List of CPRs Structures
        Annexure 8.1:               Draft Gender Based Violence
        Annexure:                   Draft Stakeholder Engagement Plan
        Annexure:                   Draft Labour Management Plan




 Feedback Infra Pvt. Ltd                                  vi                   Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –            SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                              LIST OF ABBREVIATIONS
AADT                 Annual Average Daily Traffic
AASHTO               American Association of State Highways and Transportation Officials
WB                   World Bank
ADT                  Average Daily Traffic
BBD                  Benkelman Beam Deflection
NH                   National Highway
BOQ                  Bill of Quantities
CBR                  California Bearing Ratio
CD                   Cross Drainage
DPR                  Detailed Project Report
EIA                  Environmental Impact Assessment
EIRR                 Economic Internal Rate of Return
EMP                  Environmental Management Plan
FMC                  Field Management committees
GPS                  Global Positioning System
GSB                  Granular Sub-Base
HDM                  Highway Design Manual
ICB                  International Competitive Bidding
IMD                  Indian Meteorological Department
IRC                  Indian Roads Congress
IS                   Indian Standard
MoEF                 Ministry of Environment and Forests
MoRT&H               Ministry of Road Transport & Highways
NGOs                 Non Government Organizations
NPV                  Net Present Value
NTHS                 Non Title Holders
Km                   Kilometre
OD Survey            Origin Destination Survey
ONGC                 Oil & Natural Gas Corporation
PAP                  Project Affected Person
PCU                  Passenger Car Units
PIA                  Project Influence Area
PWD                  Public Works Department
RAP                  Resettlement Action Plan
R&R                  Resettlement and Rehabilitation
RCC                  Reinforcement Cement Concrete
ROW                  Right of Way
RUCS                 Road User Cost Study
BC                   Bituminous Concrete
SPM                  Suspended Particulate Matter
TBM                  Temporary Bench Mark
ToR                  Term of Reference
THs                  Title Holders
VOC                  Vehicle Operating Costs



Feedback Infra Pvt. Ltd                 1             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                                        CHAPTER - 0.: EXECUTIVE SUMMARY
0.1    Background


Ministry of Road Transport & Highways (MORT&H) “the Authority�? is engaged in the
development of National Highways and as part of this endeavour, the Authority has decided to
upgrade Ras - Beawar- Asind - Mandal section of NH-158 in the state of Rajasthan.

The National highways Authority of India (NHAI) has appointed M/s. Feedback Infra Pvt. Ltd.
for providing the required consultancy services for preparation of Feasibility Report cum
Preliminary Design for up gradation of Ras-Beawar-Asind-Mandal section of NH 158, in the
state of Rajasthan on Engineering, Procurement and Construction (EPC) basis.


0.2   Corridor Description
The project road starts near Ras (0.000) and ends at mandal (116.750) connecting to NH-79.
The project road is approximately 116.750 (Design Length) km long. The project road falls
under Pali, Ajmer, Rajasamand and Bhilwara districts of Rajasthan. The existing length of
project highway is 134 km with considering the overlapping sections of NH-48 road.


0.3   Resettlement Action Plan: Objectives
The RAP is prepared to ensure that the affected persons are: (i) informed about their options
and rights pertaining to resettlement; (ii) provided prompt and effective compensation at full
replacement cost for loss of assets caused due to the project; (iii) provided assistance (such as
shifting allowance, transition allowance, etc.) during relocation and for a transition period, to
restore their livelihood and standards of living; and, (iv) provided with skill development
assistance such as training, in addition to compensation.
The Objectives of RAP are:

 •    To identify adverse impacts and determine mitigation measures;
 •    To present the entitlements and action plan for the affected persons for payment of
      compensation and assistance for restoring livelihoods and improving or at least retaining
      the living standards in the post resettlement period.
 •
0.4   Right of Way
The RoW for the proposed project is 30m throughout the project. The impacts on land and other
assets have been minimized, within acceptable design principles and standards.
0.5   Resettlement Policy Framework
Resettlement Policy Framework (RPF) has been prepared formulated based on the applicable
and relevant laws relating to the project and also based on the World Bank OP 4.12 on
involuntary resettlement. RPF suggests avoiding or minimizing adverse impacts by exploring
all viable alternative project designs.
0.6   Cut-off Date
Cut-off date i.e. start date of Census survey for non-titleholders is 22nd September 2018.


 Feedback Infra Pvt. Ltd                   2              Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



0.7   Impact on Land and Structures
Census surveys were conducted along the proposed project stretch, with respect to the
approved alignment. Minimum acquisition and disturbance to the existing features is the prime
objective of design. An impact has been minimized with realignments and bypasses in
proposed design.
0.8   Land Acquisition
The private land acquisition of 160.208 hectare is required for the proposed project in which
includes 91.891 hectare of agricultural land, 43.776 hectare of barren, 11.86 hectare forest land
and 9.851 hectare of residential/commercial land and remaining 2.83 hectare of any other land.
0.9   Categories of Impact
The proposed road improvement affects 653 structures which includes 400              private, 82
government, 79 community and 92 religious properties along the corridor.
0.10 Socio-Economic Profile
Total numbers of affected Project Affected Household (PAHs) are 400. The 400 PAHs comprise
2508 PAPs. There are 117 vulnerable households among the affected households.
0.11 Public Consultations
Public consultation meetings were held in 34 locations along the project corridor with road side
communities to obtain their views and suggestions regarding the proposed project
interventions. The consultations have provided inputs towards mitigation of impacts,
improvement in designs, and preparation of resettlement plan and its implementation. Based
on the suggestions, design modifications including realignment and bypasses, provision of road
safety measures such as pedestrian crossings, warning signs, markings, etc have been carried
out.
0.12 Implementation Arrangement
Institutional arrangements for the implementation of RAP have been made part of the RPF. The
Institutional Arrangements will be set up at three levels viz., MoRT&H (Central Govt.), State
Level and Sub-Project Level on partnership model wherein concerned agencies at different
levels supplement and complement each other efforts. The key elements of institutional
arrangements are co-operation/ support, collaboration and sharing of responsibilities with
clearly defined roles, involvement of key stakeholders and vertical and horizontal linkages
amongst different agencies.
0.13 Grievance Redress Mechanism
The Resettlement Policy Framework (RPF) mandates formation of Grievance Redressal
Mechanism in order to resolve disputes in an effective manner and at the door steps of the
PAPs. Compensation and assistance as per eligibility is provided in the entitlement matrix of
the approved RPF. Grievance of PAPs will be brought to the grievance redress committee for
redressal. The decision of the GRC will be binding, unless vacated by court of law.


0.14 RAP Implementation Schedule
The construction tenure of the corridor is 24 months. The on-ground rehabilitation and
resettlement exercises and handing over the encumbrance free stretch for civil works will take


 Feedback Infra Pvt. Ltd                   3              Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –            SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



5 months and afterwards, the NGO will carry out awareness programmes on road safety,
HIV/AIDS prevention campaign, repeat training for PAPs, facilitate overall monitoring, etc.
0.15 Resettlement Budget
The resettlement budget Rs 234.38 Crores includes components such as compensation for land
and structure (private property, cultural property and community assets), R&R assistance and
contingency to cover unforeseen / unanticipated costs.




                                             •••




 Feedback Infra Pvt. Ltd                 4             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                                       CHAPTER - 1.: PROJECT BACKROUND
1.1   Project Background
The Public Works Department (PWD) National Highway (NH) division, under Ministry of Road
Transport & Highways, MORT&H (“Authority�?) is intended to develop and maintain National
Highway 158 (declared in 2013) connecting to Ras-Beawar-Asind-Mandal in the State of
Rajasthan. The objective of the project is to establish the technical, economical and financial
viability of the project and prepare Feasibility and Preliminary Design report for rehabilitation
and up gradation of existing highway to two lanes / four lanes with paved shoulders.

NHAI Delhi through their letter NHAI/RJ/11019/BOT/DPR/NH-158/2013/3718 dated 25th
September, 2013 instructed the consultants to commence the Assignment, and the project
activities thereafter (Letter is attached as annexure 1.1). The Contract agreement for the
assignment was signed on 24th September, 2013. In 11th November 2014, Project Authority
was transferred from NHAI to Public Works Department, NH Division, Rajasthan, through
tripartite agreement.

1.2   Project Location
Project highway starts from Ras (26°18'18.80"N Latitude, 74°11'17.42"E Longitude) and ends
near Mandal (25°26'09.49"N Latitude, 74°35'54.06"E Longitude) connecting to NH-48. The
existing length of project highway is km 116.750 excluding the overlapping sections of NH-8,
and Shree Cement Road (about 134 km including overlapping sections). The project stretch
traverses through rolling and hilly terrain and have mostly poor geometry except few locations
where curve improvement may not be required. Project road is located in Pali, Ajmer,
Rajsamand and Bhilwara districts of Rajasthan. Project road connects the important towns /
villages like Ras, Jagatiya, Bhagatpura, Babra, Roopnagar, Beawar, Laxmipura, Nimba Hera,
Asind, Badnor and Mandal.




Source: Design report
                            Figure 1-1: Key Map of the Project Road




 Feedback Infra Pvt. Ltd                   5              Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



1.3   Importance and Need of the project:-
The project stretches once upgraded will provide shortest route to connect North and North-
West part of Rajasthan to South-East Rajasthan. Project road provides connectivity to major
tourist spots of Nagaur, Ajmer and Chittorgarh. The project road will provide straight route
connectivity to Chittorgarh and further going to Mandsaur and Indore in Madhya Pradesh. On
the north of project road, it connects to Nagaur and Bikaner via Merta.

The Project road connects major centres like Bikaner, Nagaur and Merta in Northern Rajasthan,
Jodhpur and Pali in the Western Rajasthan, Kishangarh, Ajmer and Jaipur on Western side
and Bhilwara, Chittorgarh, Rajsamand, Nathdwara and Udaipur on Southern Rajasthan.

Rajasthan is also a part of the Mumbai-Delhi Industrial corridor is set to benefit economically.
The State gets 39% of the DMIC, with major districts of Jaipur, Alwar, Kota and Bhilwara. The
main industries are based on Minerals, Agriculture and Textiles. Many prominent chemical and
engineering industries are located in Southern Rajasthan. Rajasthan is also eminent in Mining.
Makrana is a hub for White Marbles. Rajasthan has rich salt deposits at Sambhar, Copper
Mines at Khetri, Jhunjhunu. Zinc mines at Dariba, Zawar Mines near Bhilwara. Jodhpur leads
in Handicrafts and Guar Gum industry.

The major agricultural produce of the region is Oilseed, Mustard, Pearl Millet, Coriander, Bajra,
Barley, Fenugreek, and Guar. Rajasthan is the second largest producer of oilseeds. Rajasthan
produces over 72% of guar of the world and 60% of India's barley. Rajasthan is also a major
producer of Aloe Vera, Indian Gooseberries and Oranges and leading producer of Maize.
Bhilwara is one of the largest markets in the south eastern Rajasthan for selling and buying the
agricultural produce and fruits.

Bhilwara is also known for flourishing industry of textiles, with more than 850 manufacturing
units in the town. The main textile product is synthetic fabric used in trousers. Now the city
boasts of producing around 1 million metres per annum of trouser fabric, making Bhilwara one
of the major textile centres in India. The turnover of the textile industry is more than Rs. 1000
crore per annum. The city has nine major and five small spinning mills. The total spindlage
installed at Bhilwara are approximately 4.50 lacs, about 40% of the state capacity. It has 18
modern process houses to process polyester/viscose suiting with the annual capacity of a
billion metres of fabric. In the weaving sector it has approximately 13,500 looms out of which
about 9000 are modern shuttleless ones. An annual export of textiles from the district is of more
than Rs. 270 crores.

Bhilwara is the only centre in the country producing insulation bricks. There are about 33 units
in district. In the mining sector there is large scale mining of sandstone, soap stone feldspar,
quartz, mica China clay, granite etc. Mica mining has played a very important role in
development of economic and social condition of Bhilwara.

The recent and most important development in Bhilwara is the recognition of the district as
major metallic mineral i.e. Iron Ore, Led, Zinc, producing hub. The district has huge deposits of
low-grade sponge iron ore, which were simply ignored by the industry giants so far. Jindal SAW
recognized the potential and with guidance of GSI developed a huge iron ore mining and
beneficiation plant in the district. Now the district has become a magnet for all major steel
companies of the country. It has put the state of Rajasthan on the map of steel industries of the
Hindustan Zinc Ltd owned mining at village Agucha wherein Asia's largest deposit of Zinc, lead
and silver.
The major centres on the project road are Ras, Beawer, Asind and Mandal. Beawar is the
largest producer of cement in northern India and home to Shree Cement. It is situated in a

 Feedback Infra Pvt. Ltd                   6              Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                   SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



mineral-rich region having reserves of feldspar, quartz, asbestos, soapstone, magnesite,
calcite, limestone, mica, emerald, granite, and masonry stone. Reserves of barytes, fluorite,
wollastonite and vermiculite have also been found.

1.3.1 Population of Influence Regions
The project will pass through 4 districts of Rajasthan which has a total population of 81,85,745,
out of which Pali-20,37,573, Ajmer-25,83,052, Rajsamand- 11,56,597 and Bhilwara-24,08,523.
Considering that these districts are major business centers, the project is expected to boost
economic and industrial development of the area. The table below represents the population of
broadly influencing regions on the project road.
                Table 1-1: Population of broadly influencing regions near project
                    Sr.No.               District               Population

                       1                   Pali                     20,37,573

                       2               Rajsamand                    11,56,597

                       3                 Bhilwara                   2408523

                       4                  Ajmer                     2583052
                Source: Census of India, 2011

During the initial design, 9 major towns/ villages were identified which will be directly benefitted
from this project. The table below represents the population of direct influence area along the
project road.
                   Table 1-2: Population distribution in project influence area
                           Sr.No.   Village/Town             Population
                              1     Ras                      9511
                              2     Babra                    4118
                              3     Roopnagar                3245
                              4     Rajiyawas                2950
                              5     Badnor                   9217
                              6     Asind                    16,611
                              7     Brahmano ki Sareri       4,576
                              8     Mod ka Nimbahera         4,686
                              9     Mandal                   17,361
                                    Source: Census of India, 2011
1.4   Need for Social Impact Assessment (SIA) and Resettlement Action Plan
      (RAP)
The proposed project passes through 4 districts and 23 nos. of Major Built-up / settlements.
Proposed project will have adverse impact on land and structures. Total 160.208 hectare of
private land is required, apart from that 653 structure affects which includes 400 of private and
253 of CPRs.




 Feedback Infra Pvt. Ltd                        7           Public Works Department, Rajasthan
    Feasibility Report cum Preliminary Design for Up-gradation of Ras –                SIA & RAP
    Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



1.5       Scope and Objectives of Social Impact Assessment and Resettlement
          Action Plan

SIA and RAP are project specific, which outlines the extent of impacts on communities due to
the proposed development project and the mitigation of the potential impacts. It details
necessary implementation procedures for rehabilitation and resettlement.

The SIA/RAP study is done for 116.750 km that start from Ras and ends at Mandal excluding
the overlapping sections of NH-8, and Shree Cement road. The design length includes 2
bypasses and 11 realignments also.

The SIA study has been carried out with following objective:

      •    Ensuring social factors are considered in the decision-making process and in final
           design
      •    Ensuring that possible adverse social impacts are either avoided or minimised and
           brought to acceptable level
      •    More informed decision making by involving public since the beginning of project,
           informing the public about the proposal, allowing people to examine the underlying need
           for a project and giving them opportunity to identify problem and suggesting social
           friendly locally available solutions to the identified problem
      •    Improved integration of projects into their social setting
      •    A contribution towards achieving goal of sustainable development

The RAP is prepared to ensure that the affected persons are: (i) informed about their options
and rights pertaining to resettlement; (ii) consulted, provided with technically and economically
feasible resettlement alternatives and offered choices among them; (iii) provided prompt and
effective compensation at full replacement cost for loss of assets caused due to the project; (iv)
provided R&R assistances (such as shifting allowance, transition allowance, etc.) during
relocation and for a transition period, to restore their livelihood and standard of living; and, (v)
provided with skill development assistance such as training, in addition to compensation. The
objectives of RAP are: -

•          To identify adverse impacts and determine mitigation measures;
•          To present the entitlements and action plan for the affected persons for payment of
           compensation and assistance for restoring livelihoods, and improving or at least
           retaining the living standards in the post resettlement period.
•          Facilitate the design of a monitoring programme to check the adequacy and
           implementation of mitigate measures.
1.6       Approach and Methodology:-
This Report has been based, largely, on primary data collected during field survey and is well
supported by a review of available secondary data for preparation of baseline information. The
field research includes preliminary social survey of the project affected persons and properties
within the proposed ROW. The methodology used for SIA study and preparation of RAP is
discussed below:

      •    Census and Socio-economic survey: Census and socio-economic survey was
           conducted for each structure and properties covering owners and squatter (format of
           survey format attached as Annexure 1.2). This survey was conducted to assess the
           extent of impacts due to proposed upgrading of project road.

    Feedback Infra Pvt. Ltd                   8             Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –                    SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



      •    Data Collection from Secondary Sources
           Relevant baseline data on socio-economic were collected from available secondary
           sources, like census of India 2011, District Handbooks and respective government
           portals and website.

      •    Stakeholder’s Consultations
           Consultations with potential project affected persons and local people were conducted
           to inform people about the proposed widening and improvement of the project road and
           also to understand perceptions and obtain their suggestions. Outcome of the
           consultations was shared with the design team of the consultant for integrating the
           social concerns wherever feasible. The main objective of consultations was to promote
           public understanding and find out meaningful solutions for issues related to local needs
           and problems, loss of livelihoods, impact on religious structures, alternatives,
           resettlement issues, etc.
1.7       Structure of the Report:-
           Keeping in mind the above requirement at this stage of detailed study, this report is
           organized in following Chapter including Introduction ones:-

             Chapter 1:      Background and Methodology
             Chapter 2:      Description of the Project
             Chapter 3:      Socio-Economic Profile of Project Influence Area
             Chapter 4:      Regulatory Framework and Entitlement Matrix
             Chapter 5:      Analysis of Alternatives
             Chapter 6:      Stakeholder’s Consultations and Disclosure
             Chapter 7       Evaluation of Social Impacts
             Chapter 8:      Gender Analysis
             Chapter 9:      Resettlement Budget and Financing
             Chapter 10:     Institutional Arrangements
             Chapter 11:     Grievance Redress Mechanism
             Chapter 12:     Implementation Schedule
             Chapter 13:     Monitoring and Evaluation




Feedback Infra Pvt. Ltd                       9              Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                                      CHAPTER - 2.:          PROJECT DESCRIPTION
2.1     Project Profile
Project road starts from Ras (26°18'18.80"N Latitude, 74°11'17.42"E Longitude) and ends
near Mandal (25°26'09.49"N Latitude, 74°35'54.06"E Longitude) connecting to NH-48. The
project stretch traverses through rolling and hilly terrain and have mostly poor geometry except
few locations where curve improvement may not be required. Proposed length of the project
road is km 116.750 excluding the overlapping sections of NH-8, and Shree Cement road.

The length of the project road is 134 km including overlapping bypasses which passes through
Pali, Ajmer, Rajsamand and Bhilwara districts of Rajasthan. The project road under
consideration was declared as NH-158 by MoRTH in January 2013 and it comprises of SH-
39 (Ras to Beawar), Shree Cement Road which is a part of NH-8 (Beawar), MDR-84 and SH-
61. As per the initial design, the project road had overlapping sections at two stretches and
since these overlapping sections are already four lane, so these sections were excluded from
the project after discussion with NHAI. The details of these two stretches are given below:

      1. Overlapping section of Shree Cement Road: There is an existing bypass at Beawar
         which is actually a part of NH-8. After series of discussions with Client during
         finalization of alignments, the Shree Cement Road was dropped from this project, as
         informed during our site visit, this is an extension of existing Beawar bypass of NH-8.
         The movement of traffic and existing bypasses to Beawar also considered in finalizing
         the alignment.
      2. Overlapping section of NH-8: The detailed inventory and analysis of NH-14 bypass
         and NH-8 is also excluded from this report as these sections forming part of project
         highway for connectivity is already developed and under operation by NHAI. Figure
         1.1 shows changes made to alignment i.e. NH declared as per Gazette notification and
         project section included in the development.
Key map of the project highway is shown in Figure below.




 Feedback Infra Pvt. Ltd                   10             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                     SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Source: Design report

                               Figure 2-1: Key Map of the Project Road

The project road starts at km 129.000 (SH-39) at Ras and ends at km 10.940 (SH-61) near
Mandal connecting to NH-48. District wise project length is given below.
                            Table 2-1: District wise project Road alignment

                               Design Chainage
 Road section                                                  Length(km)             District
                         From (km)            To (km)
                            0.000                19.400             19.400              Pali
                           19.400                36.600             17.200             Ajmer
                           36.600                44.100             7.500            Rajsamand
      NH-158
                           44.100                46.350             2.250             Bhilwara
                           46.350                48.100             1.750            Rajsamand
                           48.100             116.750               68.650            Bhilwara
Source: Design report

2.2       Existing Alignment
      •    The present road is having two lane carriageways in most of the length i.e. 94.660 km;
           remaining length comprises of single and intermediate lane.
      •    The existing carriageway is flexible, with exception of rigid pavements for about 5.560
           Km
      •    The width of shoulders is varying from 0.000 to 1.200 m. Shoulders are in fair to poor
           condition in most of the project length
      •    75% (by length) of the project road is in good condition, 17.6% length of project road
           is fair condition and 11.4% length of project road is in poor condition. Failed sections
           are in 5.8% of the length

                        Table 2-2: Chainage wise breakup of proposed highway

                  Existing Chainage (Km)                     Existing
                                                             Length           Project Alignment
                  From                           To           (Km)
 129.000                                148.660 / 73.000    19.660           SH-39

 73.000                                 75.660              2.660            SH-39

 103.640 (of MDR-84)                    30.000              73.640           MDR-84
                                                                             SH-61 connect to NH-
 30.000 (of MDR-84 and SH-61)           10.940 (SH-61)      19.060
                                                                             79
 Existing Length                                            115.020 km
 Proposed Project Length with improvement                   116.750 km
Source: Design report




 Feedback Infra Pvt. Ltd                      11             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                      SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



2.3        Existing Road Features and Constraints
The major constraints or challenges of utilizing the current facility are as listed below:

      a)    Dense Built-up and Settlements
      b)    Right of Way availability
      c)    Condition of the existing pavement
      d)    Condition of existing cross drainage structures
      e)    Safety of Road Users
      f)    Poor Geometry

Project immediate outcome will be improved accessibility to social services and markets,
increased fuel efficiency, reduced travel time, accidents, vehicle emissions and better
employment opportunities apart from agriculture, both through improved access to economic
centres and increased industrial activities in the project area.

2.3.1 Dense Built Up Areas & Settlements
Project road traverses through 23 nos. of Major Built-up / settlements. The presence of these
settlements obstructs the flow of traffic due to reduction in speed. The traffic flowing through
these sections also creates potential hazard to pedestrians. The major settlements are listed
in Table below.
                   Table 2-3: List of Major Built-Up / Settlements along Project Road

 S.                 Chainage (Km)               Length           Name of the
                                                                                        Remarks
 No.            From               To            (Km)           Village / Town
  1            129/250          130/000            0.75       Ras Village
  2            131/600          131/700            0.10       Jagatiya
  3            133/300          133/400            0.10       Mandi Chauraha       SH-39 At Km
  4            135/000          135/300            0.30       Bhagatpura           149.000       of
                                                                                   there is another
  5            138/600          140/200            1.60       Babra Village        km         stone
  6            141/500          141/700            0.20       Babra Village        showing
  7            143/700          143/800            0.10       Bhanwariya Patti     74.000

                            149/600=74/60
  8          149=74/000                            0.60       Roopnagar
                                  0
  9            93/500            91/300            2.20       Jaswantpur Village
  10           88/100            88/300            0.20       Barr Village
  11           82/000            80/100            1.90       Laxmipura Village
  12           80/800            79/700            1.10       Ojiyana Village
  13           77/500            77/200            0.30       Mawla Village        MDR-84
  14           72/900            71/100            1.80       Badnor Village
  15           59/500            58/600            0.90       Pratapura Village
  16           58/000            54/000            4.00       Asind
  17           42/000            41/500            0.50       Pali Kheda Village

 Feedback Infra Pvt. Ltd                      12               Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                      SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



 S.               Chainage (Km)                Length          Name of the
                                                                                      Remarks
 No.         From                   To          (Km)          Village / Town
                                                           Brahmano           Ka
  18         40/200             39/200            1.00
                                                           Sareri Village
  19         37/700             37/500            0.20     Hithiya Village
  20         36/350             36/100            0.25     Kerjalin Village
  21         33/600             33/200            0.40     Nimbahera Village
  22         29/500             29/900            0.90     Mod ka Nimbhera
                                                                                   SH-61
  23         14/900             12/000            2.90     Mandal
Source: Design report and primary

The constraint of improving or upgrading the current road is the land availability in these built-
up sections.

2.3.2 Deficient Vertical and Horizontal Geometry and Improvement
The existing alignment predominantly passes through barren land and traverses through
patches of dense urban built up sections. Alignment comprises of 16 nos. of Vertical and 96
nos. sharp horizontal curves and blind spots. The deficient / substandard horizontal curves
will be improved by providing the required radius as per the codal provision for the design
speed of 80kmph / 100kmph. The curves are improved for maximum possible radius.

2.3.3 Deficient Cross Drainage Structures and Improvements
Some of the major rivers crossing the alignment are Lilri River, Khari River and Mansi River.
Lilri River is flowing from left to right and other two rivers are flowing from right to left in the
direction of increasing chainage.

Part of the project road from chainage km 0.000 to km 36.500, contribute the rainwater through
tributaries, flowing from right to left and finally joined in Lilri River. Lilri River is crossing the
project road at chainage 1.443 Km.

Similarly, Part of the project road from chainage 36.500 Km to 64.000 Km, country slope is
from right to left side of the project road considering increasing chainage. Only small streams
lie in-between, therefore, minor bridges and culverts are proposed in this section.

Similarly, last part of the project road from chainage 64.000 Km to 116.700 Km, country slope
is from right to left side of the project road considering increasing chainage. Two main rivers
namely Khari River at chainage 71.650 Km & Mansi River at chainage 92.554 Km crossing
alignment from right to left. Major bridges are proposed on these rivers. Other than these
locations minor bridges and culverts are proposed.

The project road is having one major bridge, one RoB, 14 minor bridges, 83 slab culverts, 143
pipe culverts, 3 box culverts and 1 causeway. Existing Causeway at Ch.1.479 gets overtopped
and obstructs the continuous traffic during rainy season. All minor bridges are having RCC
solid slab type superstructure, stone masonry wall type substructure and with open foundation.
The pipe culverts are generally in poor working condition, with pipe dia less than or equal to
0.6 m, however some of them are found in choked condition due to accumulation of waste /
garbage and siltation.
                             Table 2-4: Summary of Existing Structures


 Feedback Infra Pvt. Ltd                     13              Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                   SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                      S. No.             Type of structure            Nos.
                           1     Railway Over Bridge (RoB)              1
                           2     Major Bridges                          1
                           3     Minor Bridges                          14
                           4     Slab Culverts                          83
                           5     Pipe Culverts                         143
                           6     Box Culverts                           1
                           7     Causeway                               3
                                                              Total    246
                        Source: Design report

2.3.4 Safety of the Users
With improvement of existing single / intermediate lane to two lane / four lane with paved
shoulder standards, safety of the commuters will increase as this will improve the visibility and
additional carriageway space. Road user will also be facilitated with different project amenities,
slope protection measures, road markings and sign etc., which will improve the safety of
commuters along the project road.

The project stretches passes through Pali, Ajmer, Rajsamand and Bhilwara districts of
Rajasthan. Project road traverses through 23 nos. of Major Built-up / settlements. The
presence of these settlements obstructs the flow of traffic due to reduction in speed. The traffic
flowing through these sections also creates potential hazard to pedestrians. So, Realignments
and Bypasses are proposed are proposed in order to provide a safe and congestion free
passage to road users.

2.4    Proposed Structures
The project road is having one major bridge, one RoB, 14 minor bridges, 83 slab culverts, 143
pipe culverts, 3 box culverts and 1 causeway. Three new major bridges are proposed on
project road. Out of Sixteen minor bridges, five are proposed for repair and widening, four are
proposed for reconstruction and remaining seven are proposed as new structures. One of the
existing ROB is retained with repairs and one additional RoB is proposed over Beawar bypass.
Total 217 number of culverts are proposed including pipe and box culverts. New 5 pedestrian
subway has also been proposed. The summary of proposed structures on the project road is
presented in Table below.
                                      Table 2-5: List of Structures

             Type of           Retained
 S.                                     Repair &                   New        Total
            proposed             with            Reconstruction
 No.                                    Widening                Structures Structures
            structure           Repair

  1            MJB                0              0              0             3           3
  2           MNB                 0              5              4             7          16
  3            Pipe               1              7             80             0          88
  4            Slab               0              0              0             0           0
  5            Box                0              9             71            49          129

 Feedback Infra Pvt. Ltd                        14            Public Works Department, Rajasthan
    Feasibility Report cum Preliminary Design for Up-gradation of Ras –                       SIA & RAP
    Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan




                  Type of        Retained
    S.                                    Repair &                   New        Total
                 proposed          with            Reconstruction
    No.                                   Widening                Structures Structures
                 structure        Repair

     6             ROB                 1            0              0                1            2
     7             VUP                 0            0              0                3            3
     8          VUP Grade-II           0            0              0                8            8
                 Pedestrian
     9                                 0            0              0                5            5
                  Subway
                Total                  2            21            155              76          254
 Source: Design report

 2.4.1 Major and Minor Bridge
 All existing minor bridges are having RCC solid slab type superstructure, stone masonry wall
 type substructure and with open foundation. The pipe culverts are generally in poor working
 condition, with pipe dia less than or equal to 0.6 m, however some of them are found in choked
 condition due to accumulation of waste / garbage and siltation.

 A detailed survey (visual inspection) of the existing structures has been carried out by the
 concerned key professionals to assess and ascertain the existing condition / characteristics of
 bridges and other structures.

 3 major bridges are proposed on Lildi, Mansi and Khari River respectively. Details of proposed
 bridges (major and minor both) are provided in Tables below.
                                    Table 2-6: Proposed Major Bridge


                                   Existing Structure           Proposed Structure
    Existing Design                      Details                     Details
S.                                                                                          Improvement
    Chainage Chainage
No.                                                              Span                         Proposal
      (km)     (km)                        Span /       Width             Width
                                 Type                           (C/C of         Type
                                           Length        (m)               (m)
                                                                 exp.)
                                                                                   PSC         New
1        130+362        1+479     Pipe     34x0.6         -      5x30     2x12.5
                                                                                   Girder   Construction
                                                                                   PSC         New
2           -           71+760     -         -            -      5x30      16
                                                                                   Girder   Construction
                                                                                   RCC         New
3           -           92+554     -         -            -     5x19 *     16
                                                                                   Girder   Construction
 Source: Design Report
                           Table 2-7: Minor Bridges to be repaired and widening




    Feedback Infra Pvt. Ltd                      15              Public Works Department, Rajasthan
       Feasibility Report cum Preliminary Design for Up-gradation of Ras –                             SIA & RAP
       Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan




                               Existing Structure
                                                                 Proposed Structure Details
                                     Details
    Existing  Design
Sl.                                                                                                       Improvement
    Chainage Chainage                           Span
No                                                                                                          Proposal
      (km)     (km)                Span /       (C/C
                              Type        Width                              Width (m)          Type
                                   Length        of
                                                exp.)
                                                                                                          Widening on
                             RCC
 1 135+912      7+018             3x4.5          13.3        3x4.5     12.5+Median+12.5 RCC Box           both side- 2+2
                             Slab
                                                                                                          lane(4 lane)
                                                                                                          Widening on
                             RCC
 2 137+930      9+033             3x6.5          13.1        3x6.5     12.5+Median+12.5 RCC Box           both side- 2+2
                             Slab
                                                                                                          lane(4 lane)
                                                                                                          Widening on
                             RCC
 3 144+098      15+278            2x5.5          13.5        2x5.5     12.5+Median+12.5 RCC Box           both side- 2+2
                             Slab
                                                                                                          lane(4 lane)
                             RCC                                                                          Widening with
 4 79+028       52+836            5x2.9          12.2        5x2.9     16                     RCC Box
                             Slab                                                                         repair
                             RCC                                                                          Widening and
 5 12+160       115+785           2x3.5          12          2x3.5     16                     RCC Box
                             Slab                                                                         Repair.
      Source: Design report and primary survey
                                   Table 2-8: Minor Bridges in Re-Construction


                                Existing Structure
    Existing  Design                                                 Proposed Structure Details
S.                                    Details                                                             Improvement
    Chainage Chainage
No.                                                                                                         Proposal
      (km)     (km)                   Span / Width                    Width
                              Type                 Span (C/C of exp.)                           Type
                                      Length (m)                       (m)
                              RCC                                                                             Re-
1    79+338       52+527               3x2.8      12         2x4.5 (Clear span)          16    RCC Box
                              Slab                                                                         Construction
                              RCC                                                                             Re-
2    79+210       52+655               3x2.9      12         2x4.5 (Clear span)          16    RCC Box
                              Slab                                                                         Construction
                              RCC                                                                             Re-
3    78+296       53+578               5x2.9      12.2       3x5.0 (Clear span)          16    RCC Box
                              Slab                                                                         Construction
                              RCC                                                                             Re-
4    52+993       74+458               3x2.8      12         2x4.5 (Clear span)          16    RCC Box
                              Slab                                                                         Construction
      Source: Design report and primary survey
                            Table 2-9: Minor Bridges in New-Construction




       Feedback Infra Pvt. Ltd                          16                  Public Works Department, Rajasthan
     Feasibility Report cum Preliminary Design for Up-gradation of Ras –                     SIA & RAP
     Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan




                      Existing Structure
    Existing  Design                                         Proposed Structure Details
Sl.                         Details                                                         Improvement
    Chainage Chainage
No                                                                                            Proposal
      (km)     (k m)  Typ Span / Widt                        Span (C/C
                                                                       Width (m) Type
                       e Length      h                        of exp.)
                                                              2x4.5
                                                                       12.5+Medi RCC            New
1     130+342         1+350       Pipe    8x0.6          -    (Clear
                                                                        an+12.5  Box         Construction
                                                              span)
                                                              2x4.5
                                                                       12.5+Medi RCC            New
2     142+151        13+356       Pipe 2 x1.2            -    (Clear
                                                                        an+12.5  Box         Construction
                                                              span)
                                                              3x6.0
                                                                       12.5+Medi RCC            New
3          -         16+492         -           -        -    (Clear
                                                                        an+12.5  Box         Construction
                                                              span)
                                                                                 RCC
                                                                       12.5+Medi                New
4          -         29+644         -           -        -    1x19.0             Girde
                                                                        an+12.5              Construction
                                                                                   r
                                                                                    RCC
                                                                                                New
5          -         46+072         -           -        -    3x18.0          16    Girde
                                                                                             Construction
                                                                                      r
                                                                                    RCC         New
6          -         89+308         -           -        -    1x10.0          16
                                                                                    Slab     Construction
                                                                                    RCC
                                                                                                New
7          -         89+830         -           -        -    1x19.0          16    Girde
                                                                                             Construction
                                                                                      r
     Source: Design report and primary survey

    2.4.2 Vehicular Under Pass (VUP)
    Following are the grade separated structures proposed along the project road. Vehicle
    underpasses will have minimum vertical clearance of 5.5m while the grade-II vehicle
    underpasses will have minimum vertical clearance of 4m.
                                  Table 2-10: Improvement Proposal of VUP

                                          Improvement Proposal
                Design
      S.                                                             Span
               Chainage                                                               Width (m)
      No                        Proposal             Type        arrangement
                 (Km)
                                                                      (m)
                                                     RCC
       1        10+123      New construction                       2x10x5.5        10.5+Median+10.5
                                                     Box
                                                     RCC
       2        25+834      New construction                       2x10x5.5        10.5+Median+10.5
                                                     Box
                                                     RCC
       3        97+825      New construction                       2x10x5.5                 13
                                                     Box
    Source: Design report and primary survey

     Feedback Infra Pvt. Ltd                        17            Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                       SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                         Table 2-11: Improvement Proposal of VUP Grade-II

                                     Improvement Proposal
            Design
 Sl.                                                           Span
           Chainage                                                                  Width (m)
 No                           Proposal         Type        arrangement
             (Km)
                                                                (m)
 1        9+643          New construction    RCC Box 1x12x4                    10.5+Median+10.5
 2        20+264         New construction    RCC Box 1x12x4                    10.5+Median+10.5
 3        60+810         New construction    RCC Box 1x12x4                    13
 4        71+518         New construction    RCC Box 1x12x4                    13
 5        71+875         New construction    RCC Box 1x12x4                    13
 6        73+019         New construction    RCC Box 1x12x4                    13
 7        84+250         New construction    RCC Box 1x12x4                    13
 8        88+527         New construction    RCC Box 1x12x4                    13
Source: Design Report

2.4.3 Toll Plazas
There are two toll plaza locations proposed along project corridor.
                               Table 2-12: Proposed toll plaza locations

 S.                                                         Applicable         Remark (Traffic
                   Location           Tollable section
 No.                                                       Length (km)           Adopted)
           Toll Plaza     1    (Km km 0.000 to km
 1                                                30.050                   km 147.000 of SH-39
           13.905)                 30.050
           Toll Plaza     2    (Km km 30.050 to km
 2                                                 86.695                  km 42.000 of MDR-84
           73.850)                 116.745
 Total Tollable Length(km)                                 116.750
 Source: Design report

2.5       Right of Way (RoW)
The existing RoW varies from 15 - 30m. RoW of 30m is proposed throughout the road.
Additional ROW is required for curve improvements and realignments and for two toll plazas,
Bus Bay, Truck Lay bye and wayside amenities as per final design. Below table provides
details of the locations which will require additional RoW.

             Table 2-13: Design chainage with length and RoW at additional    locations
              Design Chainage                         Proposed Row
 S. No.                               Length (m)                                    Remarks
              From            To                       LHS       RHS
      1      2940         3160        220             20       20          Bus Bay
      2      3510         3750        240             15       25          Truck Lay bye
      3      4340         4590        250             20       20          Bus Bay
      4      8040         8260        220             20       15          Bus Bay
      5      13780        14030       250             30       80          Toll Plaza-1

 Feedback Infra Pvt. Ltd                      18             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                           SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



              Design Chainage                              Proposed Row
 S. No.                                 Length (m)                                     Remarks
               From          To                            LHS         RHS
      6      16250       16450         200                15          100      Way Side Amenities
      7      17340       17560         220                15          20       Bus Bay
      8      60880       61120         240                25          15       Truck Lay bye
      9      67600       67800         200                15          100      Way Side Amenities
   10        73725       73975         250                22          22       Toll Plaza-2
   11        107130      107370        240                25          15       Truck Lay bye
Source: Design report and primary survey

2.6       Typical Cross Sections
Keeping these basic requirements, various typical cross sections are developed to meet the
need of land use along the project road. Details of Cross Sectional Elements for particular
typical cross sections and location-wise application of TCS are given in tables below and
corresponding typical cross sectional layout are shown in Figure 2.2.
                                Table 2-14: List of Typical Cross Sections

           Design Chainage (m)         Design                               TCS Type
 S.
                                       Length
 No.        From           To           (m)
                                                       Widening / Reconstruction with rigid pavement
  1           0           780              780
                                                       (4-lane)
  2          780         1270              490         New construction with Rigid pavement (4-lane)
                                                       Widening / Reconstruction with rigid pavement
  3         1270         1400              130
                                                       (4-lane)
  4         1400         1550              150         Major Bridge
                                                       Widening / Reconstruction with rigid pavement
  5         1550         1700              150
                                                       (4-lane)
  6         1700         2050              350         New construction with Rigid pavement (4-lane)
                                                       Widening / Reconstruction with rigid pavement
  7         2050         3190              1140
                                                       (4-lane)
  8         3190         3510              320         New construction with Rigid pavement (4-lane)
                                                       Widening / Reconstruction with rigid pavement
  9         3510         4830              1320
                                                       (4-lane)
  10        4830         5960              1130        New construction with Rigid pavement (4-lane)
                                                       Widening / Reconstruction with rigid pavement
  11        5960         7250              1290
                                                       (4-lane)
  12        7250         9240              1990        New construction with Rigid pavement (4-lane)
                                                       New construction with Flexible pavement (4-
  13        9240         10350             1110
                                                       lane) ROB/VUP
  14        10350        11770             1420        New construction with Rigid pavement (4-lane)

 Feedback Infra Pvt. Ltd                          19             Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –                   SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



      Design Chainage (m)       Design                          TCS Type
S.
                                Length
No.     From          To         (m)
                                             Widening / Reconstruction with rigid pavement
15     11770        13020        1250
                                             (4-lane)
16     13020        13780        760         New construction with Rigid pavement (4-lane)
17     13780        14030        250         Toll plaza
18     14030        15190        1160        New construction with Rigid pavement (4-lane)
                                             Widening / Reconstruction with rigid pavement
19     15190        16220        1030
                                             (4-lane)
20     16220        16600        380         New construction with Rigid pavement (4-lane)
                                             Widening / Reconstruction with rigid pavement
21     16600        17550        950
                                             (4-lane)
22     17550        19550         50         New construction with Rigid pavement (4-lane)
                                             New construction with Flexible pavement (4-
23     19550        20910        960
                                             lane) ROB / VUP
24     20910        25550        4640        New construction with Rigid pavement (4-lane)
                                             New construction with Flexible pavement (4-
25     25550        26920        1370
                                             lane) ROB/VUP
26     26920        30050        3130        New construction with Rigid pavement (4-lane)
                                             Widening /       Reconstruction   with    flexible
27     30050        30650        600
                                             pavement
28     30650        31670        1020        New construction with flexible pavement
                                             Widening /       Reconstruction   with    flexible
29     31670        31800        130
                                             pavement
30     31800        33500        1700        New construction with flexible pavement
                                             Widening /       Reconstruction   with    flexible
31     33500        36050        2550
                                             pavement
32     36050        37100        1050        New construction with flexible pavement
                                             Widening /       Reconstruction   with    flexible
33     37100        43000        5900
                                             pavement
34     43000        43480        480         New construction with flexible pavement
                                             Widening /       Reconstruction   with    flexible
35     43480        43600        120
                                             pavement
36     43600        44000        400         New construction with flexible pavement
                                             Widening /       Reconstruction   with    flexible
37     44000        47000        3000
                                             pavement
38     47000        48630        1630        New construction with flexible pavement
                                             Widening /       Reconstruction   with    flexible
39     48630        49600        970
                                             pavement

Feedback Infra Pvt. Ltd                 20                Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –                   SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



      Design Chainage (m)       Design                          TCS Type
S.
                                Length
No.     From          To         (m)
40     49600        49800        200         New construction with flexible pavement
                                             Widening /       Reconstruction   with    flexible
41     49800        50060        260
                                             pavement
42     50060        50700        640         New construction with flexible pavement
                                             Widening /       Reconstruction   with    flexible
43     50700        58650        7950
                                             pavement
44     58650        59770        1120        New construction with flexible pavement
                                             Widening /       Reconstruction   with    flexible
45     59770        60250        480
                                             pavement
                                             Flyover Approach with Retaining Structure And
46     60250        61350        1100
                                             Service Road
                                             Widening /       Reconstruction   with    flexible
47     61350        70020        8670
                                             pavement
48     70020        70850        830         New construction with flexible pavement
                                             Two lane carriageway with service road (New
49     70850        71400        550
                                             construction / Reconsrtuction)
                                             Flyover Approach with Retaining Structure and
50     71400        71550        150
                                             Service Road
51     71550        71685        135         New construction with flexible pavement
52     71685        71835        150         At Major Bridge
                                             Widening /       Reconstruction   with    flexible
53     71835        72600        765
                                             pavement
                                             Flyover Approach with Retaining Structure and
54     72600        73600        1000
                                             Service Road
                                             Widening /       Reconstruction   with    flexible
55     73600        73720        120
                                             pavement
56     73720        73970        250         Toll plaza
                                             Widening /       Reconstruction   with    flexible
57     73970        83640        9670
                                             pavement
                                             Flyover Approach with Retaining Structure And
58     83640        84750        1110
                                             Service Road
                                             Widening /       Reconstruction   with    flexible
59     84750        86800        2050
                                             pavement
60     86800        88100        1300        New construction with flexible pavement
                                             Flyover Approach with Retaining Structure and
61     88100        88900        800
                                             Service Road
62     88900        90100        1200        New construction with flexible pavement

Feedback Infra Pvt. Ltd                 21                Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                     SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



        Design Chainage (m)         Design                           TCS Type
 S.
                                    Length
 No.      From           To          (m)
                                                  Widening /    Reconstruction    with    flexible
 63      90100          92510        2410
                                                  pavement
 64      92510          92600          90         At Major Bridge
 65      92600          92900         300         New construction with flexible pavement
                                                  Widening /    Reconstruction    with    flexible
 66      92900          93700         800
                                                  pavement
 67      93700          95700        2000         New construction with flexible pavement
                                                  Widening /    Reconstruction    with    flexible
 68      95700          97600        1900
                                                  pavement
                                                  Flyover Approach with Retaining Structure And
 69      97600          98550         950
                                                  Service Road
                                                  Widening /    Reconstruction    with    flexible
 70      98550          112830       14280
                                                  pavement
 71      112830         115430       2600         New construction with flexible pavement
                                                  Widening /    Reconstruction    with    flexible
 72      115430         116745       1315
                                                  pavement
Source: Design Report
                                 Figure 2-2: Typical Cross Section




Typical Cross Section VI: Widening to Two lane with Paved Shoulder (Widening &
Reconstruction - Existing Pavement)




Typical Cross Section VII: Two lane with Paved Shoulder with Foot Path and Drain in
Urban section (Widening & Reconstruction - Existing Pavement)

 Feedback Infra Pvt. Ltd                     22             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                    SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan




Typical Cross Section VIII: Two Lane with Paved Shoulders - Bypasses New
Construction (over Existing Road)




Typical Cross Section VIIIA: Two Lane with Paved Shoulders - Bypasses New
Construction

2.7       Bypasses and Realignments
Total two bypasses and 11 realignments have been proposed for project road. A list of
Bypasses proposed, are given in Table below.
                                     Table 2-15: Bypass Locations

                     Design Chainage                 Design            Type of
 S. No.                                                                               Bypass
                 Start               End           Length (km)          Road
      1      21.470              30.050            8.580                          Beawar
      2      86.860              90.100            3.240           MDR-84         Sareri
                                           Total 15.020
Source: Design Report

Re-alignments have been proposed for 11 locations to avoid settlement areas mainly villages,
where geometrics are required to be improve as per design standardsLocation wise list of
realignments are provided in Table below.
                                   Table 2-16: Realignment Locations

  S.        Design Chainage                                            Existing
                                    Length           Village                         Remarks
  No.        Start       End                                            RoW
   1        9.075       11.660     2.585      Babra                 8 to 10       Realignment
   2        19.690      21.470     1.780      Roopnagar             8 to 10       Realignment
   3        30.650      33.500     2.850      Rajiyawas             10 to 15      Realignment

 Feedback Infra Pvt. Ltd                      23               Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                       SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



  S.      Design Chainage                                             Existing
                                   Length           Village                              Remarks
  No.       Start        End                                           RoW
   4      36.045        37.100    1.055       Peepli ka Badiya      8 to 10        Realignment
   5      43.000        44.100    1.100       Heera ka Badiya       8 to 10        Realignment
   6      47.030        48.630    1.600       Kaniya Kheda          8 to 10        Realignment
   7      49.600        50.600    1.000       Oziyana               8 to 10        Realignment
   8      57.950        59.770    1.820       Badnor                8 to 10        Realignment
   9      70.020        72.625    2.605       Asind                 15 to 20       Realignment
   10     93.700        95.700    2.000       Mod ka Nimhera        7 to 8         Realignment
   11     112.830 115.430 2.600               Mandal                10 to 15       Realignment
Source: Design report

2.8     Service roads
Service road has been proposed in major settlement for use by the locals to avoid any conflict
with the Highway Traffic. Locations of service roads are tabulated below.
                               Table 2-17: Locations of the Service Road

                         Design Chainage
                                                                             Length (in Kms)
              From                                 To
             60.250                            61.350                             1.100
             70.850                            71.400                             0.550
             71.400                            71.550                             0.150
             72.600                            73.600                             1.000
             83.640                            84.750                             1.110
             88.100                            88.900                             0.800
             97.600                            98.550                             0.950
Source: Design report

2.9     Other Structures
2.9.1 Pedestrians
5 nos. of subway are proposed along the project highway and locations are detailed in Table
below.
                                    Table 2-18: Pedestrian Subway

                                             Pedestrian Subway
      Design
 S.                                                          Span               Vertical     Width
     Chainage
 No.                       Proposal           Type       arrangement           clearance      (m)
       (Km)
                                                              (m)                 (m)
  1       2.630         New Construction RCC Box              1x4.8               2.75         26
  2       12.895        New Construction RCC Box              1x4.8               2.75         26

 Feedback Infra Pvt. Ltd                      24              Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                    SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                                            Pedestrian Subway
      Design
 S.                                                        Span              Vertical     Width
     Chainage
 No.                        Proposal         Type      arrangement          clearance      (m)
       (Km)
                                                            (m)                (m)
  3       21.730        New Construction RCC Box             1x4.8            2.75          26
  4       35.360        New Construction RCC Box             1x4.8            2.75          14
  5       106.890       New Construction RCC Box             1x4.8            2.75          14
Source: Design Report

2.9.2 Wayside Amenities
The wayside amenities are proposed at the locations as per the below table.
                              Table 2-19: Proposed Wayside Amenities

                                            Design Chainage
 S. No.    Existing Chainage (km)                                    Side         Section
                                                 (km)
      1         145.170 (SH-39)                   16.350             RHS         Ras-Beawar
      2         63.380 (MDR-84)                   67.700             LHS      Beawar-Mandal
Source: Design report

2.9.3 Bus bays and Truck lay-bys
Truck lay byes has been proposed to cater large number of trucks traversing on project road.
Bus Shelters with and without Bus bays are proposed at the locations given in Table below.

                             Table 2-20: List of Proposed Bus bay

            Design Chainage             Remarks            Design Chainage        Remarks
 S. No.
                               Left                                      Right
      1             4.480                                       3.050                Both
      2             8.150                                       4.450
      3             36.650                                     17.450
      4             40.330                                     36.275            Shelter Only
      5             44.650             Shelter Only            38.960
      6             45.780             Shelter Only            42.600            Shelter Only
      7             62.805                                     44.800            Shelter Only
      8             63.950                                     48.100
      9             66.460                                     48.750            Shelter Only
    10              68.925                                     52.200
    11              74.600             Shelter Only            54.050
    12              77.000                                     56.300
    13              89.500                                     61.050
    14              91.800                                     66.750


 Feedback Infra Pvt. Ltd                     25              Public Works Department, Rajasthan
    Feasibility Report cum Preliminary Design for Up-gradation of Ras –                             SIA & RAP
    Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                Design Chainage                  Remarks               Design Chainage           Remarks
    S. No.
                                       Left                                              Right
      15                94.886                                                 68.200
      16                97.750                                                 77.200
      17               101.200                                                 80.200
      18               106.586                                                 91.850
      19               114.086                                                 94.736
      20                                                                       98.020
      21                                                                      106.786
      22                                                                      109.536
      23                                                                      114.216
Source: Design report

2.10 Road Safety
2.10.1 Road Accident Black Spot Identification and Removal
Based on the analysis of the accident data, 2 locations were identified as black spot along the
project road as given below:-

       •    Harnia Mangri near Badnor (17 Fatalities) in 2017-18
       •    Para Chowk near Asind (6 Fatal Accidents) in 2017 -18

The major road accident locations are marked in the Figure 2-3.1




1
    Fatalities data collected from police stations of 7 tehsils i.e. near of the road.

    Feedback Infra Pvt. Ltd                             26                 Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                    SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan




                                      Figure 2-3: Black Spot

2.10.2 Road User Safety Solutions
a) Highway Design: Geometry of the road will be designed as per the applicable Design
speed and relevant codes and standards. The deficient curves (horizontal and vertical) along
the existing geometry will be improved. Super elevation as per the curve radius will be
provided in order to avoid overturning of vehicles due to speed.

Adequate sight distances will be provided in order to avoid blind spots both horizontally and
vertically.

b) Road Signs: As per the applicability and requirement Road signs will be place all along the
road in order to guide the road user to traverse safely. A combination of road signs like
Mandatory – Regulatory signs, Cautionary-Warning signs and Informatory signs will be
installed. Variable Message signs will also be placed at identified locations in order to inform
road user about various details like climatic conditions ahead, diversions, accident zones,
speed reduction zones etc.

c) Traffic Lights / Signals: Traffic signals will be generally installed at intersections to control
the movement of vehicles. All traffic must move in conformity with the traffic lights or signals.
Traffic Signals, Pedestrian Signals and Lane Marking signals,

d) Pavement Markings: Pavement markings will be provided to delineate the centre of road,
identify travel lane, define road edge. Pavement markings also provide information about

 Feedback Infra Pvt. Ltd                    27             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                  SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



special lane use. Markings can also be in the form of patterns, arrows, or other devices set
into or attached to the carriageway or kerbs or to objects within or adjacent to the carriageway,
for control, warning, guidance or information of road users.

2.10.3 Pedestrian Safety
1) Pedestrian Signals
Pedestrian Signals will be installed at the urban locations where pedestrian movement is
heavy.

At crossings with medium pedestrian crossings a push button traffic light can be installed.
Pedestrians can push the button and wait for the light to turn green and then move on and
cross cautiously.

2) Guard Rails and Lighting
Pedestrian Guard Rails will be installed at the following locations.

a) Hazardous locations on Straight Sections: In particularly busy reaches where the road
is congested and vehicles move at a fast pace, guard rails will be provided on both sides of
the carriageway so as to channelize the pedestrian on to the planned crossing locations.

b) At Junctions/Intersections: Railing barriers will be provided to prevent people from
crossing the junctions diagonally at signalised intersections. The barrier must open only at
planned crossing facility (at zebra crossing). At Signalised junctions’ sufficient length of guard
rail will be provided to guide the pedestrian to the neared planned pedestrian crossing.

c) School Colleges: Guard rails will be provided near schools in order to prevent children’s
to run straight into the road.

d) Bus Stops, Railway Stations, Temple etc: Guard rails will be provided alongside walks
with suitable access at bus stops, railway stations and other areas of heavy pedestrian activity
such as cinema houses, stadiums etc.

e) Overpass, Subway etc.: Guard-rails is to be provided at Overpasses and subways in order
to compel the pedestrians to use the facilities provided for them.

3) Pedestrian Crossings
a) Zebra Crossings: Zebra crossings will be provided along with stop lines as per IRC 35 for
safe crossing of pedestrians.

b) Hump Subways: Hump subways are provided by providing the subway partially under
ground and partially over the ground in order to reduce the walking length.

c) Full Subways: Full subways are provided by providing the subway fully under the ground.

d) Foot Overbridge: FoB will be provided where there are space constraints and heavy
pedestrian movement.

4) Footpath
Footpath with Kerb and pedestrian guard rail will be proposed continuously throughout the
urban and built-up sections in order to provide a safe passage for pedestrians to walk along
the traffic.

 Feedback Infra Pvt. Ltd                   28             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –              SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



2.10.4 Road Safety Schedule and Traffic Calming Measures
Detailed Road Safety Schedule and Traffic Calming Measures are provided in the form of
detailed design report. The schedule contains the provision and locations of Road Markings
and Road Signs for all the Major Junctions, Minor Junctions, Schools, Temples, Govt. Offices,
other community buildings etc.




 Feedback Infra Pvt. Ltd                 29            Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                  SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



          CHAPTER - 3.: SOCIO – ECONOMIC PROFILE OF PROJECT
                                            INFLUENCE AREA
3.1   Introduction
The following sections provide briefly the socio-economic profile of the state (Rajasthan), and
affected districts. The project influence area has been considered as the administrative
boundaries of the districts through which the project road traverses. These districts are Ajmer,
Pali, Rajasamand and Bhilwara. The Direct Impact Zone are the census villages and towns
which are likely to be impacted in terms of land acquisition, loss of assets, loss of livelihood
etc., due to the project implementation.
3.2   Overview of Rajasthan
Rajasthan is located in the north-western part of the country, between 69°30’E to 78°13’E
longitudes and 23°30’N to 30°12’N latitudes. In terms of area it is the largest state in India and
covers an area of about 3,42,239 sq. km, which accounts for 11 percent of the total area and
about five per cent of the population of the country. Presenting a rhomboid shape, the State
has a maximum length of 869 km from west to east and 826 km from north to south. The State
is bound on the west by Pakistan, in the north by Haryana and Punjab, in the east by Uttar
Pradesh and Madhya Pradesh, and in the south by Gujarat (Figure 3.1).

The State has 33 administrative districts. More than three-fourth proportion of the total
population is residing in rural areas. An overview of the State is presented below in Table 3.1:
                              Table 3-1: An Overview of Rajasthan

 Socio – Economic Profile of Project Influence Area
 An Overview of Rajasthan
 Indicators                                                                 As of March, 2011
 Area (Sq. km)                                                                        342239
 Population                                                                         68621012
 Rural population (%)                                                                      75
 Urban population (%)                                                                         25
 SC population (%)                                                                        17.16
 ST population (%)                                                                        12.56
 Sex ratio (females+ 1000 males)                                                           926
 Overall literacy (%)                                                                     67.06
 Female literacy (%)                                                                      52.66
 Contribution to Gross State Domestic Product
 Agriculture (%)                                                                        26.37
 Industry (%)                                                                             27.1
 Services (%)                                                                           46.53
 Roads density+100 sq. km                                                               55.09
 Annual rainfall (average mm)                                                             575
 Per capita income (at current prices)- Rs.                            39967 p.a. or 3330 p.m.
 Source: Rajasthan Micro-Finance Report, 2011




 Feedback Infra Pvt. Ltd                   30             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan




                               Figure 3-1: Key map of Rajasthan

The economy of the state is characterized by high incidence of poverty, low literacy rate,
unemployment and low per capita income. The share of agriculture has been declining even
then even then agriculture continues to play an integral part of the development process in the
state as 75% of the population still live in villages and continue to depend on agriculture and
allied activities as a prime source of their livelihood.
3.3   Project Influence Area (PIA)
The project influence area covers Ajmer, Pali, Rajsamand and Bhilwara districts. The area
with its sub-tropical climate has three very well-defined seasons - summers, winters and
monsoons. On the basis of climatic conditions and prevailing agricultural practices, Rajasthan
has been divided into ten agro-climatic zones, each one having special characteristics of its
own. Ajmer district forms part of the Semi-Arid Eastern Plain (IIIA) whereas Pali District and
Rajsamand Districts forms part of Flood Prone Eastern Plain (IIIB). The details of the districts
are presented in Table 3.2:
                                Table 3-2: Districts at a Glance

                                                           Census 2011
Indicators
                                          Pali          Ajmer     Rajsamand          Bhilwara
                                                                                     25.3500°
Latitude                              25.7667° N     26.4500° N      25.0667° N
                                                                                         N
                                                                                     74.6333°
Longitude                             73.3167° E     74.6333° E      73.8667° E
                                                                                         E
Area (sq. km)                           12387           8481            4655           10455
Households (No.)                       418157          494832          243078         498125
Population (No.)                       2037573         2583052         1156597       2408523
Male (%)                                50.33           51.26           50.26          50.68
Female (%)                              49.67           48.74           49.74          49.32
Urban population (%)                    22.58           40.08           15.89          21.28
Rural population (%)                    77.42           59.92           84.11          78.72
SC (%)                                  19.54           18.51           12.81          16.94
ST (%)                                   7.10            2.46           13.90           9.52
Population growth rate (%)              11.94           18.40           17.18          19.60
Population density (per sq. km.)         164             305             248            230
 Feedback Infra Pvt. Ltd                  31             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                                                           Census 2011
Indicators
                                         Pali          Ajmer      Rajsamand          Bhilwara
Sex Ratio (females+ 1000 males)          987            951           990               973
Average Literacy Rate                   62.39          69.33         63.14             61.37
Male Literacy                           76.81          82.44         78.42             75.27
Female Literacy                         48.01          55.68         47.95             47.21
Work Participation Rate (WPR)           41.34          40.79         47.63             47.67
WPR (Male) - %                          51.01          51.82         54.97             55.26
WPR (Female) - %                        31.54          29.20         40.21             39.87
Main Workers                           605288         827181        362584            883329
Main workers (Male) - %                 73.31          72.72         71.14             65.78
Main workers (Female) - %               26.69          27.28         28.86             34.22
                 Cultivation - %        33.06          29.79         39.33             52.28
Main Workers Agriculture - %            19.14           9.40         11.74             8.77
(%)              Household - %           3.15           3.36         2.39              2.41
                 Others - %             44.65          57.45         46.53             36.54
Marginal workers                       237039         226541        188247            264836
Marginal workers (Male) - %             33.48          37.34         32.73             35.32
Marginal workers (Female) - %           66.52          62.66         67.27             64.68
                 Cultivation - %        18.31          23.14         34.51             35.25
Marginal         Agriculture - %        51.23          29.90         34.00             32.30
Workers- %       Household - %           2.96           3.46         2.56              3.36
                 Others - %             27.50          43.50         28.92             29.09
Non-Workers - %                        1195246        1529330       605766           1260358
Male - %                                42.03          41.71         43.22             43.33
Female - %                              57.97          58.29         56.78             56.67
       Source: Census of India, 2011


3.4   Demographic Composition: Pali District

3.4.1 Population
As per Census of India 2011, the total population of the Pali district is 2037573 in which
1025422 (50.33%) are males and 1012151 (49.67%) are females. An average gender ratio of
the district is 987, which shows that there is slightly imbalanced composition of male and
female. 14.60% of population belongs to 0-6 age group. An average gender ratio of the 0-6
age group of the district is 899 females’ children per 1000 male children.
3.4.2 Social Stratification
As per census 2011, an average SC and ST population constitute 26.63% in which 19.54%
are SC and 7.10% are ST.
3.4.3 Literacy and Literacy Rate
As per census 2011, an average literacy rate of the district is 62.39% in which male literacy is
76.81% with respect to the male population and female literacy is 48.01% with respect to the
female population, creating a gender gap of 28.81%.

 Feedback Infra Pvt. Ltd                  32             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



3.4.4 Workers and Work Participation Rate
As per Census of India 2011, the total number of workers in the district is 842327 and the
WPR is 41.34%, in which male’s WPR is 51.01% with respect to male population and female’s
WPR is 31.54% with respect to the female population, creating a gender gap of 19.47%.
3.4.5 Categorization of Main Workers on the basis of Occupation
As per census of India 2011, 44.65% of main workers are involved in other work followed by
the cultivation with 33.06%, agricultural labor with 19.14% and household industrial work with
3.15%.
3.4.6 Categorization of Marginal Workers on the basis of Occupation
As per census of India 2011, 51.23% of marginal workers are involved in agricultural labor
followed by the other worker with 27.50%, cultivation with 18.31%, and only 2.96% workers
are involved in household industrial work.
3.5   Demographic Composition: Ajmer District
3.5.1 Population
As per Census of India 2011, the total population of the Ajmer district is 2583052 in which
1324085 (51.26%) are males and 1258967 (48.74%) are females. An average gender ratio of
the district is 951, which shows that there is slightly imbalanced composition of male and
female. 14.76% of population belongs to 0-6 age group. An average gender ratio of the 0-6
age group of the district is 901 females’ children per 1000 male children.
3.5.2 Social Stratification
As per census 2011, an average SC and ST population constitute 20.96% in which 18.51%
are SC and 2.46% are ST.
3.5.3 Literacy and Literacy Rate
As per census 2011, an average literacy rate of the district is 69.33% in which male literacy is
82.44% with respect to the male population and female literacy is 55.68% with respect to the
female population, creating a gender gap of 26.76%.
3.5.4 Workers and Work Participation Rate
As per Census of India 2011, the total number of workers in the district is 1053722 and the
WPR is 40.79%, in which male’s WPR is 51.82% with respect to male population and female’s
WPR is 29.20% with respect to the female population, creating a gender gap of 22.62%.
3.5.5 Categorization of Main Workers on the basis of Occupation
As per census of India 2011, 57.45% of main workers are involved in other work followed by
the cultivation with 29.79%, agricultural labor with 9.40% and only 3.36% workers are involved
in household industrial work.
3.5.6 Categorization of Marginal Workers on the basis of Occupation
As per census of India 2011, 43.50% of marginal workers are involved in other work, followed
by agricultural labor with 29.90%, cultivation with 23.14% and only 3.46% workers are involved
in household industrial work.



 Feedback Infra Pvt. Ltd                  33             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



3.6   Demographic Composition: Rajsamand District
3.6.1 Population
As per Census of India 2011, the total population of the Rajsamand district is 1156597 in which
581339 (50.26%) are males and 575258 (49.74%) are females. An average gender ratio of
the district is 990, which shows that there is slightly imbalanced composition of male and
female. 15.22% of population belongs to 0-6 age group. An average gender ratio of the 0-6
age group of the district is 903 females’ children per 1000 male children.
3.6.2 Social Stratification
As per census 2011, an average SC and ST population constitute 26.71% in which 12.81%
are SC and 13.90% are ST.
3.6.3 Literacy and Literacy Rate
As per census 2011, an average literacy rate of the district is 63.14% in which male literacy is
78.42% with respect to the male population and female literacy is 47.95% with respect to the
female population, creating a gender gap of 30.47%.
3.6.4 Workers and Work Participation Rate
As per Census of India 2011, the total number of workers in the district is 550831 and the
WPR is 47.63%, in which male’s WPR is 54.97% with respect to male population and female’s
WPR is 40.21% with respect to the female population, creating a gender gap of 14.76%.
3.6.5 Categorization of Main Workers on the basis of Occupation
As per census of India 2011, 46.53% of main workers are involved in other work followed by
the cultivation with 39.33%, agricultural labor with 11.74% and only 2.39% workers are
involved in household industrial work.
3.6.6 Categorization of Marginal Workers on the basis of Occupation
As per census of India 2011, 34.51% of marginal workers are involved in cultivation, followed
by agricultural labor with 34.00%, other worker with 28.92% and only 2.56% workers are
involved in household industrial work.
3.7   Demographic Composition: Bhilwara District
3.7.1 Population
As per Census of India 2011, the total population of the Bhilwara district is 2408523 in which
1220736 (50.68%) are males and 1187787 (49.32%) are females. An average gender ratio of
the district is 973, which shows that there is slightly imbalanced composition of male and
female. 15.02% of population belongs to 0-6 age group. An average gender ratio of the 0-6
age group of the district is 928 females’ children per 1000 male children.
3.7.2 Social Stratification
As per census 2011, an average SC and ST population constitute 26.46% in which 16.94%
are SC and 9.52% are ST.




 Feedback Infra Pvt. Ltd                  34             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



3.7.3 Literacy and Literacy Rate
As per census 2011, an average literacy rate of the district is 61.37% in which male literacy is
75.27% with respect to the male population and female literacy is 47.21% with respect to the
female population, creating a gender gap of 28.06%.
3.7.4 Workers and Work Participation Rate
As per Census of India 2011, the total number of workers in the district is 1148165 and the
WPR is 47.67%, in which male’s WPR is 55.26% with respect to male population and female’s
WPR is 39.87% with respect to the female population, creating a gender gap of 15.39%.
3.7.5 Categorization of Main Workers on the basis of Occupation
As per census of India 2011, 52.28% of main workers are involved in cultivation followed by
the other work with 36.54%, agricultural labor with 8.77% and only 2.41% workers are involved
in household industrial work.
3.7.6 Categorization of Marginal Workers on the basis of Occupation
As per census of India 2011, 35.25% of marginal workers are involved in cultivation, followed
by agricultural labor with 32.30%, other worker with 29.09% and only 3.36% workers are
involved in household industrial work.




 Feedback Infra Pvt. Ltd                  35             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                   SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



  CHAPTER - 4.: REGULATORY FRAMEWORK AND ENTITLEMENT
                                              MATRIX
4.1   Introduction
This chapter details out the legal and regulatory framework under the ambit of which the SIA
was undertaken and RAP has been prepared. It also reviews the national and state laws of
Rajasthan relevant to the scope of activities under the project, and, discusses the implications
for the project design and implementation.
4.2   Applicable National and State Policy Framework
Below section discusses the National and State policies that are applicable to this project.
4.2.1 The Right to Fair Compensation and Transparency in Land Acquisition,
      Rehabilitation and Resettlement Act, 2013
The Right to Fair Compensation and Transparence in Land Acquisition, Rehabilitation and
Resettlement Act, 2013 has been effective from January1, 2014 after receiving the assent of
the President of Republic of India. This Act extends to the whole of India except the state of
Jammu and Kashmir. The Act replaced the Land Acquisition Act, 1894. The Act has since late
December 2014 been amended to make it more flexible and the description of the amendment
is described below.

The aims and objectives of the Act include is to ensure, in consultation with institutions of local
self-government and Gram Sabhas established under the Constitution of India, a humane,
participative, informed and transparent process for land acquisition for industrialization,
development of essential infrastructural facilities and urbanization with the least disturbance
to the owners of the land and other affected families. It provides for compensation and
resettlement assistance to the affected families whose land or other assets are affected by the
project. A few of key features that are revised from the old Act include the recognition of non-
title holders to compensations if they have lived in the area proposed to be acquired in the
past three years as well as compensations for loss of livelihood.

Section 26 of the Act defines the method by which market value of the land shall be computed
under the proposed law. Schedule I outlines the proposed minimum compensation based on
a multiple of market value. Schedule II through VI outline the resettlement and rehabilitation
entitlements to land owners and livelihood losers, which shall be in addition to the minimum
compensation per Schedule I.
4.2.2 The Rajasthan Right to Fair Compensation and Transparency in land
      Acquisition, Rehabilitation and Resettlement Rules, 2016
This Rule was framed and notified by GoR for the RFCTLARRR Act, 2013. The rule is detailing
the process of social impact assessment and multiplication factor for award of land acquisition.
4.3   Resettlement Framework Principles and Entitlement Matrix
Based on the above analysis of government provisions, the following k e y resettlement
principles, definitions and Entitlement Matrix have been adopted for the Project.

A.      Key Resettlement Principles
           (i)   land acquisition, and other involuntary resettlement impacts will be avoided
                 or minimized exploring all viable alternative sub-project designs;

 Feedback Infra Pvt. Ltd                   36              Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –                   SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



            (ii) where unavoidable, time-bound resettlement plans (RAPs) will be prepared
                   and APs will be assisted in improving or at least regaining their pre-program
                   standard of living;
            (iii) consultation with APs on compensation, disclosure of resettlement
                   information to APs, and participation of APs in planning and implementing
                   sub-projects will be ensured;
            (iv) vulnerable and severely affected households will be provided special
                   assistance;
            (v) payment of compensation to APs including non-titled persons (e.g., informal
                   dwellers/squatters, and encroachers) for acquired assets at replacement
                   rates;
            (vi) payment of compensation and resettlement assistance prior to the
                   contractor taking physical acquisition of the land and prior to the
                   commencement of any construction activities;
            (vii) provision of income restoration and rehabilitation;
            (viii) Establishment of appropriate grievance redress mechanisms.

B.      Key Working Definitions

        Cut-off dates: For Titled-Holders, the cut-off date will be the date of publication of
        preliminary notification for acquisition under Section 4(1) of the RFCT in LARR Act,
        2013. For non-titleholders such as squatters, the cut-off date will be the start date of
        the project census survey as per the final detailed design or updated census survey
        during RP implementation.

        Vulnerable Affected Households: Vulnerable Households are defined as affected
        families who are: (i) below the national poverty level; (ii) headed by women and below
        the average income of affected households; (iii) headed by disabled or elderly and
        below the average income of affected households; (iv) scheduled tribes and
        marginalized scheduled castes.

C.      Entitlement Matrix

        All persons affected by the project and meeting the cut-off date requirements will be
        entitled to a combination of compensation packages and resettlement assistance
        depending on the nature of ownership rights on lost assets and scope of the impacts:
            a. Compensation for the loss of land ,crops/trees at their replacement cost;
            b. Compensation for structures (residential/ commercial) and other immovable
                assets at their replacement cost;
            c. Assistance in lieu of the loss of business/ wage income and income restoration
                assistance;
            d. Assistance for shifting and provision for the relocation site (if required), and
            e. Rebuilding and/ or restoration of community resources/facilities
            f. Additional Support to Vulnerable Families

        An Entitlement Matrix, delineated in Table 4.1 has been developed to summarize
        entitlements.
                                  Table 4-1: Entitlement Matrix
     All awards below shall be exempt from income tax, stamp duty and fees.




Feedback Infra Pvt. Ltd                    37             Public Works Department, Rajasthan
      Feasibility Report cum Preliminary Design for Up-gradation of Ras –                  SIA & RAP
      Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sl.         Impact                Entitled Unit                     Entitlement Details

No.

A. Loss of Private Agricultural, Home-Stead & Commercial Land

 1      Loss of Land       Titleholder/owner/families   For all land acquired under NH Act;
                           families with traditional    Compensation/lease amount shall be
        (agricultural,     land right/occupiers         calculated and payable in accordance
        homestead,                                      with Sections 26 to 30 and Schedule I of
        commercial or                                   RFCTLARR Act 2013
        otherwise)

        within       the
        Corridor      of                                i.   Partial Impact on Land: In case only
        Impact                                               part of any land plot is affected, and
                                                             its owner desires the whole plot be
        (COI)                                                acquired on grounds that the plot has
                                                             become uneconomic or has been
                                                             severed due to LA (under Section 94
                                                             and Note C), the competent authority
                                                             can     award    compensation       for
                                                             remaining part of the plot or award
                                                             25% of actual value upto of the
                                                             remaining land holding as additional
                                                             compensation, allowing the owner to
                                                             retain the remaining land plot, if
                                                             agreeable.



                                                        For all land acquired under NH Act; or
                                                        direct purchase or acquisition of missing
                                                        land parcels/plot (MoRT&H circular date
                                                        28th Decemebr, 2017), Rehabilitation and
                                                        Resettlement Assistance shall be as
                                                        follows ( Schedule II of Act 2013):

                                                        ii. If as a result of land acquisition, the
                                                            land owner becomes landless or is
                                                            reduced to the status of a “small�? or
                                                            “marginal�? farmer, assistance amount
                                                            of Rs. 6 lakhs
                                                                              OR

                                                             annuity policies that shall pay not less
                                                             than two thousand rupees per month
                                                             for each affected land owner for
                                                             twenty years with appropriate
                                                             indexation to the Consumer Price
                                                             Index for Agricultural Labourers.



      Feedback Infra Pvt. Ltd                  38             Public Works Department, Rajasthan
      Feasibility Report cum Preliminary Design for Up-gradation of Ras –                SIA & RAP
      Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sl.         Impact              Entitled Unit                    Entitlement Details

No.

                                                      iii. Each land owner shall be given a one-
                                                           time "Resettlement Allowance" of Rs.
                                                           60,000/- only.
                                                      iv. Refund of stamp duty and registration
                                                           charges incurred for replacement
                                                           land to be paid by the project;
                                                           replacement land must be bought
                                                           within a year from the date of
                                                           payment of compensation to project
                                                           affected persons

B. Loss of Private Structures (Residential/Commercial)

                                                        i. Compensation in accordance with
 2      Structure        Title Holder/ Owner
                                                           Sections 26 to 30 and Schedule I of
        within the
                                                           RFCTLARR Act 2013
        Corridor of
                                                       ii. Right to salvage material from
        Impact (CoI)                                       affected structures
                                                      iii. Three months advance notice to
                                                           vacate structure
                                                      iv. For those losing cattle shed, a one-
                                                           time assistance of Rs. 28,000/- would
                                                           be payable
                                                       v. For each affected family of an artisan
                                                           or self-employed or own non-
                                                           agricultural land, that is displaced and
                                                           must relocate, a one-time assistance
                                                           of Rs. 28,000/- would be payable; and
                                                      vi. One-time subsistence grant of Rs.
                                                           40,000/- for each displaced family
                                                           who are displaced and require to
                                                           relocate;
                                                     vii. One-time financial assistance of Rs.
                                                           60,000/- for each affected family
                                                           towards shifting/transportation cost
                                                           for shifting of the family, building
                                                           materials, belongings and cattle
                                                     viii. Refund of stamp duty and registration
                                                           charges for purchase of new
                                                           alternative      houses/shops          at
                                                           prevailing rates on the market value
                                                           as       determined.          Alternative
                                                           houses/shops must be bought within
                                                           a year from the date of payment of
                                                           compensation
                                                      ix. For a house lost, a constructed house
                                                           shall be provided as per the Indira
                                                           Awas Yojana Specifications or


      Feedback Infra Pvt. Ltd                  39          Public Works Department, Rajasthan
      Feasibility Report cum Preliminary Design for Up-gradation of Ras –                  SIA & RAP
      Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sl.         Impact              Entitled Unit                      Entitlement Details

No.

                                                             equivalent cost of the constructed
                                                             house in lieu, shall be payable.
                                                      x.     In case of partial impact, 25%
                                                             additional award to be paid on
                                                             compensation award for the affected
                                                             part of the structure to enable
                                                             damage        repair      where     the
                                                             owner/occupier of his/her own will,
                                                             interested to retain the remaining part
                                                             of the structure, provided the
                                                             unimpaired continuous use of the
                                                             such structure is possible without
                                                             hazards



                                                       i.    Registered lessees will be entitled to
 3      Structure        Tenants/
                                                             an      apportionment       of     the
        within the
                         Lease Holders                       compensation payable to structure
        Corridor of                                          owner as per applicable local laws.
        Impact (CoI)                                  ii.    One-time financial assistance of Rs.
                                                             60,000/- as transportation.
                                                      iii.   Three months notice to vacate
                                                             structures.

C. Loss of Trees and Crops

                                                       i.    Cash compensation as estimated
 4      Standing         Owners and beneficiaries
                                                             under Section 29(3) of Act to be paid
                         (Registered/ Un-registered
        Trees, Crops                                         at the rate estimated by:
                         tenants, contract
        within the       cultivators, leaseholders           • The Forest Department for timber
        Corridor of                                              trees
        Impact           &                                   • The State Agriculture Extension
                                                                 Department for crops
                         sharecroppers
        (CoI)                                                • The Horticulture Department for
                                                                 fruit/flower bearing trees.


                                                      ii.    Three months advance          notice to
                                                             project affected persons     to harvest
                                                             fruits, standing crops and   removal of
                                                             trees, or compensation       in lieu as
                                                             determined above.



                                                       Registered tenants, contract cultivators &
                                                       leaseholders & sharecroppers will be
                                                       eligible for compensation for trees and

      Feedback Infra Pvt. Ltd                40               Public Works Department, Rajasthan
      Feasibility Report cum Preliminary Design for Up-gradation of Ras –                  SIA & RAP
      Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sl.         Impact              Entitled Unit                        Entitlement Details

No.

                                                         crops as per the agreement document
                                                         between the owner and the beneficiaries.



                                                         Un-registered         tenants,    contract
                                                         cultivators, leaseholders & sharecroppers
                                                         will be eligible for compensation for trees
                                                         and crops as per mutual understanding
                                                         between the owner and the beneficiaries

D. Loss of Residential/ Commercial Structures to Non-Title Holders

 5      Structures       Owners of                       For loss of House
        within the
        Corridor of      Structures or Occupants of      i.    Compensation at PWD BSR without
        Impact (CoI)     structures (Encroachers,              depreciation for structure
        or Govt. land    Squatters) identified as per   ii.    One-time resettlement cost of Rs.
                         Project Census Survey                 28,000 /-
                                                        iii.   Shifting/transportation assistance of
                                                               Rs. 60,000/-
                                                        iv.    Encroachers shall be given three
                                                               months’ notice to vacate occupied
                                                               land    or    cash assistance      at
                                                               replacement cost for loss of
                                                               structures.
                                                        v.     Right to salvage the affected
                                                               materials


                                                         For loss of shop
                                                           i. Compensation at PWD BSR without
                                                              depreciation for structure
                                                          ii. One-time subsistence grant of Rs. 40,
                                                              000/-
                                                         iii. Oneitme rehabilitation grant of Rs.
                                                              28,000/-
                                                         iv. Shifting/transportation assistance of
                                                              Rs. 60,000/-
                                                          v. Encroachers shall be given three
                                                              months’ notice to vacate occupied
                                                              land    or   cash assistance       at
                                                              replacement cost for loss of
                                                              structures.
                                                         vi. Right to salvage the affected
                                                              materials



      Feedback Infra Pvt. Ltd                 41                Public Works Department, Rajasthan
        Feasibility Report cum Preliminary Design for Up-gradation of Ras –                                       SIA & RAP
        Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sl.             Impact                      Entitled Unit                                Entitlement Details

No.



6         Loss of                 Livelihood loser                         Subsistence allowance equivalent to
          employment in                                                    Minimum Wages/Minimum Agricultural
          non-                                                             Wages2 for 3 months
          agricultural
          activities or
          daily
          agricultural                                                     Only agricultural labourers who are in
          wages or other                                                   fulltime / permanent employment of the
          wage workers                                                     land owner, or those affected full time
                                                                           employees of the business, will be
                                                                           eligible for this assistance. Seasonal
                                                                           agricultural labourers will not be entitled
                                                                           for this assistance.

F. Additional Support to Vulnerable Group

                                                                             i. One-time Resettlement Allowance of
7         Families within         Vulnerable affected families
                                                                                Rs. 60,000/-
          the Corridor of
                                                                            ii. Training for skill development. This
          Impact (CoI)                                                          assistance includes cost of training
                                                                                and     financial   assistance    for
                                                                                travel/conveyance and food.
                                                                           iii. Additional Subsistence Grant of Rs.
                                                                                60,000/- for displaced families
                                                                                belonging to Scheduled Caste and
                                                                                tribe Category
                                                                           iv. Displaced vulnerable households will
                                                                                be linked to the government welfare
                                                                                schemes, if found eligible and not
                                                                                having availed the scheme benefit till
                                                                                date.

G. Loss of Community Infrastructure/Common Property Resources

8         Structures &            Affected communities                     Reconstruction of community structure
          other                   and groups                               and common property resources, will be
          resources                                                        done in consultation with community

          (e.g. land,
          water, access
          to structures
          etc.) within the
          Corridor of
          Impact (CoI)

    2   As per rates issued by Department of Labor, Government of project state for different skills and trades


        Feedback Infra Pvt. Ltd                               42                  Public Works Department, Rajasthan
      Feasibility Report cum Preliminary Design for Up-gradation of Ras –              SIA & RAP
      Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sl.         Impact              Entitled Unit                    Entitlement Details

No.

H. Temporary Impact During Construction

                                                       i.  Compensation for temporary impact
9       Land and         Owners of land and
                                                           during conversion e.g. diversion of
        assets           assets
                                                           normal traffic, damage to adjacent
        temporarily
                                                           parcel of land/assets (crops, trees,
        impacted
                                                           structures, etc.) due to movement of
        during
                                                           heavy machinery and plant site
        construction
                                                       ii. Contractor shall bear the cost of
                                                           compensation of any impact on
                                                           structure or land due to movement of
                                                           machinery during construction or
                                                           establishment of construction plant.
                                                      iii. All temporary use of land outside
                                                           ROW, would be done based on
                                                           written approval/ prior approval
                                                           landowner and contractor




      Feedback Infra Pvt. Ltd                 43            Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                  SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



       CHAPTER - 5.: PUBLIC INFORMATION AND CONSULTATIONS
5.1    Introduction
Project affected people were informed about the proposed road development and potential
impacts during consultations. The involvement of the Public consultation has been carried out
in this Project with the objectives of minimizing probable adverse impacts of the project
through alternate design solutions (cross-sectional) and to achieve speedy implementation of
the project through bringing in awareness among the community on the benefits of the project.
5.2    Classification of Stakeholders
Stakeholder analysis typically classifies stakeholders or all those who have an interest in the
project, into three categories:
    • Primary stakeholders are those who are directly or indirectly affected by a project, such
        as the project beneficiaries and the people who are likely to be adversely affected by
        a project.
    • Secondary stakeholders are those who are involved in the delivery of the project
        outputs, such as the government, the implementing agency, the executing agency
        (e.g., contractors, consultants), if any and NGOs, etc.
    • External stakeholders are those who are “outside�? the ambit of the project activities,
        but who can influence the outcome of the project, such as the media, politicians,
        religious leaders and other opinion leaders.

For this project, affected people, influential person, village Sarpanch and panchayat members,
members of the affected villages, local women were considered as Primary stakeholders.
5.3    Consultation Process
The process of stakeholder consultation included:

•     Identification of the relevant stakeholders including all those individuals, groups and
      organizations potentially affected by or interested in the project;
•     Pre informing the stakeholders about the consultation dates and location;
•
•     During the consultation process, imparting information about the project interventions and
      its potential impacts;
•     Recording of their concerns and aspirations through discussions;
•     Responding to their queries in a neutral manner.
5.4    Stakeholder’s consultation
Public consultations meetings were conducted in project corridor villages at 34 locations as
part of the SIA & RAP. Majority of the stakeholders expressed their full support for the widening
and improvement of the proposed project road with suitable compensation. They agreed that
proposed project will have both positive and adverse impact on the community and assets,
especially those who are along the project road. But at the same time, they were aware that
road development will also improve the connectivity of the villages to the major district
headquarters. They anticipated construction activities will generate employment opportunities
for the local people. During public consultation, it was informed that proposed project will have
impacts on residential and commercial structures as well as religious and community
structures, along the road. Details of number and type of consultation conducted along the



 Feedback Infra Pvt. Ltd                   44             Public Works Department, Rajasthan
    Feasibility Report cum Preliminary Design for Up-gradation of Ras –                                                                SIA & RAP
    Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



road are presented in Table 5-1 and the photographs and list of participants is given in
Appendix 5.1 and 5.2 respectively.3
5.4.1 Consultations with Local Community
Consultations were carried out with community affected on the project road to get their
views and suggestions regarding the proposed project. Mostly local people were very
interested and showed their support for proposed project but also expressed their
concerns regarding payment of compensation for assets attached to land and timely
completion of the project. The details of the consultation are given in Table 5-1.


                                 Table 5-1: Details of Consultation with local community
    Sr                                                                                                                                    Remarks
                         Locati               Issues
    .N      Date                                                                 Views and Suggestion
                          ons               discussed
    o.
                                                                      Basically, people of the village are                            Realignment is
                                                                      having no issues with respect to the                            proposed      in
                                                                      proposed project; they felt that project                        final design.
                                                                      will bring development with respect to
                                                                      the economic, health, education,
                                                                      transportation and water etc. in the
                                                                      project corridor. People asked for
                                                                      bypass in the village to avoid
                                        Bypass Option                 involuntary resettlement.
                                                                      Drainage      system     should      be                         Accordingly
                                                                      developed, and proposed road should                             drain has to be
                         Market                                       not be raised from the existing road                            constructed
             03.1                       Drainage                      otherwise village will be bound with
                         place,
     1       1.20                       system                        water during rainy season.
                         Roop-
              15
                         nagar                                        The proposed project will enhance the
                                        Transportation                transportation system in the area
                                        &                             People will commute easily and in
                                        communication                 less time to Ras-Beawer-Asind-
                                        system                        Mandal.
                                                                                                             Compensation
                                                                                                             will be given
                                                                                                             based         on
                                                                                                             RFCTLARR
                                                                                                             Act, 2013 and
                                                                      Compensation should be calculated Rajasthan
                                        Compensation                  on market rate.                        Rules 2016
                                                                                                             Realignment is
                                                                      People asked for bypass in the village proposed       in
                                        Bypass Option                 to avoid involuntary resettlement.     final design.
             04.1
                         City,                                                                               Compensation
     2       1.20
                         Babra                                                                               will be given
              15
                                                                                                             based         on
                                                                      Compensation should be calculated RFCTLARR
                                        Compensation                  on market rate.                        Act, 2013 and
3
    The list of persons involved in the public consultation is limited to those who were willing to allow their name to be added in the document.


    Feedback Infra Pvt. Ltd                                         45                      Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –           SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sr                                                                               Remarks
             Locati         Issues
.N   Date                                      Views and Suggestion
              ons         discussed
o.
                                                                              Rajasthan
                                                                              rules 2016
                                        Local people of the village are       Local labour
                                        involved in agriculture and labour    and     women
                                        work and demanded for employment      will          be
                      Occupation        during construction.                  preferred
                                        Women are involved in agriculture     during
                      Women             and rearing animal.                   construction.
                                                                              Realignment is
                                        Local people demanded to proposed
                                                                              proposed       in
                                        bypass to avoid resettlement in the
                                                                              final design.
                      Bypass Option     village.
                                                                            Compensation
                                                                            will be given
                                                                            based         on
                                                                            RFCTLARR
     04.1     City,                                                         Act, 2013 and
3    1.20    Rajiya                   Compensation should be calculated Rajasthan
      15      was     Compensation    on market rate.                       rules 2016
                                                                            Local labour
                                                                            will          be
                                                                            preferred
                                      Local people demanded employment during
                      Occupation      during construction.                  construction.
                                      Women are involved in agriculture
                      Women           and rearing animal.
                                                                            Ownership
                                                                            details of the
                                                                            affected land
                                                                            would         be
                                      People even showed their concern
                                                                            verified during
                                      regarding the ownership status as
                                                                            RAP
                                      reflected in revenue records. In many
                                                                            implementatio
                                      cases, the name of owner in the land
                                                                            n. NGO will be
                                      records is not updated after the land
                                                                            appointed to
                                      is sold to another party/ person. The
                                                                            undertake this
     05.1                             land record thus still shows the name
                                                                            activity    and
4    1.20    Asind                    of the previous owner.
                                                                            accordingly
      15
                                                                            compensation
                      Related      to                                       will be paid.
                      revenue record
                                                                            Compensation
                                                                            will be given
                                                                            based         on
                                                                            RFCTLARR
                                                                            Act, 2013 and
                                      Compensation should be given on Rajasthan
                      Compensation    market rate.                          rules 2016



Feedback Infra Pvt. Ltd                46            Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –            SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sr                                                                               Remarks
             Locati         Issues
.N   Date                                      Views and Suggestion
              ons         discussed
o.
                                                                              The existing
                                                                              road is being
                                                                              widened       as
                                                                              per the final
                      Structures      Demanded to save structures.            design
                                                                              Compensation
                                                                              will be given
                                                                              based         on
                                                                              RFCTLARR
     05.1                                                                     Act, 2013 and
5    1.20   Badnor                    Compensation should be calculated Rajasthan
      15              Compensation    on market rate.                         rules 2016
                                      It has been recorded during the
                                      consultation that no gender-based
                      Gender based violence has been recorded at the
                      violence        project corridor.
                                                                              Compensation
                                                                              will be given
                                                                              based         on
                                                                              RFCTLARR
                                                                              Act, 2013 and
                                      Compensation should be calculated Rajasthan
                      Compensation    on market rate.                         rules 2016
                                                                              Ownership
                                                                              details of the
     19.0                                                                     affected land
6    9.20   Badnor                                                            would         be
      18                                                                      verified during
                                                                              RAP
                                                                              implementatio
                                                                              n. NGO will be
                                                                              appointed to
                                                                              undertake this
                                                                              activity    and
                                      People demanded that compensation accordingly
                      Related      to to be given to the person having compensation
                      revenue record possession on affected land.             will be paid.
                                      Agreed with the proposal. During The existing
                                      discussion reveals that there is 30- road is being
                                      meter land is available in market area. widened       as
                      Widening of the They asked to provide safety signage per the final
                      road            in the market area                      design
     05.1
                                                                              Compensation
7    1.20   Sopura
                                                                              will be given
      15
                                                                              based         on
                                                                              RFCTLARR
                                      Compensation should be calculated Act, 2013 and
                                      on market rate where land acquisition Rajasthan
                      Compensation    is applicable.                          rules 2016

Feedback Infra Pvt. Ltd                47            Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –              SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sr                                                                                  Remarks
             Locati         Issues
.N   Date                                      Views and Suggestion
              ons         discussed
o.
                                       Considering the migration of small        Local labour
                                       farmer to other states like Gujarat and   will        be
                                       Humpy, for need of work, local people     preferred
                                       demanded that local labour should be      during
                                       provided       with        employment     construction.
                                       opportunities during construction
                      Occupation       stage.
                                       Women are involved in agriculture
                      Women            and rearing animal.
                      Desired skill in Mainly youth desired engineering in
                      Youth            electrical, mechanical, civil and IT.
                                       Bypass has been proposed in the           Realignment is
                                       village, community welcomed the           proposed       in
                      Bypass option    proposal of bypass                        final design.
                                                                                 Compensation
                                                                                 will be given
                                                                                 based         on
                                                                                 RFCTLARR
             Kaniya
     06.1                                                                        Act, 2013 and
             Khera
8    1.20                             Compensation should be calculated          Rajasthan
               &
      15              Compensation    on market rate.                            rules 2016
             Kotda
                                      Local people of the village are            Local labour
                                      involved in agriculture and labour         will          be
                                      work        therefore       demanded       preferred
                                      employment       opportunity   during      during
                      Occupation      construction.                              construction.
                                      Women are involved in agriculture
                      Women           and rearing of animal.
                                      Bypass should be proposed in Ras           The existing
                                      market up to proposed chainage             road is being
                                      0+000 to 3+000 km.                         widened       as
                                      If not possible, minimize the RoW to       per the final
                                      save their residential as well as          design and all
                                      commercial structure.                      construction
                                      RoW should not be more than 30             activities will
                      Bypass option   meter in agricultural land.                be      confined
                      Widening     on Widening of the road should be equal       within existing
     16.0             both side       on both side of the road.                  RoW.
9    9.20     Ras                                                           Accordingly
      18              Drainage          Drainage     system    should  be   drain has to be
                      system            developed as per area need          constructed.
                                        Men were showed their interest on   Appropriate
                                        heavy traffic during school time.   measures will
                                        There should be signboard for       be taken for
                      Safety            crossing the road                   safety.
                                                                            Compensation
                                                                            will be given
                                        Compensation should be given as per based        on
                      Compensation      market rate                         RFCTLARR
Feedback Infra Pvt. Ltd                48             Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –               SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sr                                                                                  Remarks
             Locati         Issues
.N   Date                                       Views and Suggestion
              ons         discussed
o.
                                                                                  Act, 2013 and
                                                                                  Rajasthan
                                                                                  rules 2016
                                          Lose of residential as well as          The existing
                                          commercial structure, mean a            road is being
                                          psychologically disturbance to the      widened    as
                                          affected families therefore demanded    per the final
                                          to save their structures.               design
                                          Hanuman temple falling along the
                      Structures          RoW (7mtr) which should be avoided
                                                                                  The existing
                                                                                  road is being
                      Widening        on Local people asked to widening           widened     on
                      both side          should be on both side of the road.      both sides.
                                         Local villages people happy with the     Appropriate
                                         proposed project and they are            measures will
                                         demanding for signage along the          be taken for
     18.0             Safety             roadside                                 safety.
            Chhata
10   9.20                                                                         Compensation
             rpura
      18                                                                          will be given
                                                                                  based       on
                                                                                  RFCTLARR
                                                                                  Act, 2013 and
                                       Compensation should be on current          Rajasthan
                      Compensation     market price.                              rules 2016
                                       Main source of the water is a well and
                      Water            hand pump only.
                                       Affected people including sarpanch         The existing
                                       suggested     saving     the     village   road is being
                                       proposed bypass in the village. They       widened    as
                                       suggested that land is available in        per the final
                                       right hand side of the existing road       design.
                      Bypass option    near the pond.
                                       Local people will lose their residential
                      Loss          of as well as commercial structure due to
                      structure        widening of the road.
             Mawal                     Both men and Women were showing           Appropriate
     19.0
               a-                      their concern regarding the safety of     measures will
11   9.20
             Fatehg                    children and animal. They asked to        be taken for
      18
              arh     Safety           proposed bypass for their safety.         safety.
                                                                                 Compensation
                                                                                 will be given
                                                                                 based       on
                                                                                 RFCTLARR
                                                                                 Act, 2013 and
                                          Compensation should be calculated Rajasthan
                      Compensation        on market rate.                        rules 2016
                                          Main source of the water is a well and
                      Water               hand pump only.

Feedback Infra Pvt. Ltd                  49            Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –              SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sr                                                                                 Remarks
             Locati         Issues
.N   Date                                      Views and Suggestion
              ons         discussed
o.
                                        Loss of residential as well as           The existing
                                        commercial structure, mean a             road is being
                                        psychological disturbance to the         widened    as
                                        affected families. They demanded to      per the final
                                        save their structures. Available land    design.
                                        from structure to structure is 24-26
                      Structures        meter in the market.
                                        During consultation it was recorded      Appropriate
     20.0
                                        that an accident took place before 7-8   measures will
12   9.20    Palari
                                        years. They are showing their            be taken for
      18
                                        concern regarding the safety of their    safety
                      Safety            small children and animals.
                                        Local people of the village are          Local labour
                                        involved in agriculture and labor work   will        be
                                        therefore demanded employment            preferred
                                        opportunity during construction.         during
                                        Women are involved in agriculture        construction.
                      Occupation        and rearing animal.
                                        People of Brahmano ki Sareri have no     The bypass is
                                        issues with the proposed project. The    being
                                        bypass already has been proposed in      proposed as
                                        the village but they demanded that       per the final
                                        existing road is to be repaired at the   design.
                                        time of construction of proposed
                      Bypass Option     project.
                                                                                 Compensation
                                                                                 will be given
     21.0    Brahm
                                                                                 based       on
13   9.20    ano ki
                                                                                 RFCTLARR
      18     Sareri
                                                                                 Act, 2013 and
                                        Compensation should be calculated        Rajasthan
                      Compensation      on market rate.                          rules 2016
                                        Local people of the village are          Local labour
                                        involved in agriculture and labor work   will        be
                                        therefore demanded employment            preferred
                      Occupation        opportunity during construction.         during
                                        Women are involved in agriculture        construction.
                      Women             and rearing animal.
                                        People of the village welcome to the     The
                                        proposed project and they having no      realignment is
                                        issues with respect to the proposed      being
                                        project. The bypass already has been     proposed      in
             More
     21.0                               proposed in the village. Local people    final design.
               ka
14   9.20             Bypass Option     asked to repair the existing road.
             Nimba
      18                                                                  Compensation
             heda
                                                                          will be given
                                                                          based      on
                                        Compensation should be calculated RFCTLARR
                      Compensation      on market rate.                   Act, 2013 and

Feedback Infra Pvt. Ltd                50            Public Works Department, Rajasthan
       Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
       Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



       Sr                                                                                    Remarks
                       Locati         Issues
       .N       Date                                       Views and Suggestion
                        ons         discussed
       o.
                                                                                         Rajasthan
                                                                                         rules 2016
                                                                                         Local labour
                                                  Local people of the village are will               be
                                                  involved in agriculture and labor work preferred
                                                  therefore demanded employment during
                                 Occupation       opportunity during construction.       construction.
                                                  Women are involved in agriculture
                                 Women            and rearing animal.
                                 Desired skill in Mainly youth desired engineering in
                                 Youth            electrical, mechanical, civil and IT.


      Major recommendations and outcome of the consultation

            ▪    People demanded bypass for Ras market, Mawla village and Asind market.
            ▪    Saving of the structures is the major concern along the project road.
            ▪    Jagtiya, Bhagatpura and Kundiya kapadiya villagers want to avoid their structure and
                 road to be constructed within availablility of land.
            ▪    Ras, Kundiya Kapaiya, Pipli Kapadiya village having temple and will be affected in
                 proposed project; therefore, it should be avoided.
            ▪    The land owners expecting compensation as per market value.
            ▪    Expecting employment opportunities from the project.
            ▪    Ground water level is 100-120 feet; therefore, they asked that government should
                 arrange water supply in the project corridor.
            ▪    Trauma center is not available on or near the project corridor therefore demanded to
                 propose trauma center.
            ▪    Villager’s advice to engage local people during the construction.
            ▪    The people expressed concerns over movement of heavy traffic, as their children are
                 not safe to cross the road.
      5.5       Consultation with Land Owner
      Consultations were carried out with affected land owners to get their views and suggestions
      regarding proposed project. Most of the land owner were very interested and showed their
      support for proposed project but also expressed their concern regarding payment of
      compensation and timely completion of the project. The detail of the consultation is given in
      Table 5-2.
                                Table 5-2: Details of consultation with land owner
Sr.                                        Issues                                             Remarks
         Date           Locations                            Views and Suggestion
No.                                      discussed
                                                          Compensation should be        Compensation will
                           Near                           calculated on market rate.    be given based on
                         Sarpanch                         Land owner showed their       RFCTLARR, Act
1     03.11.2015                        Compensation
                          house,                          concern compensation rates    2013 and Rajasthan
                         Sahapura                         as DLC rate and market rate   rules 2016
                                                          having a huge difference.



       Feedback Infra Pvt. Ltd                     51             Public Works Department, Rajasthan
      Feasibility Report cum Preliminary Design for Up-gradation of Ras –                SIA & RAP
      Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sr.                                   Issues                                                Remarks
        Date        Locations                          Views and Suggestion
No.                                 discussed
                                                                                       Ownership details of
                                                    People even showed their           the affected land
                                                    concern     regarding      the     would be verified
                                                    ownership status as reflected      during          RAP
                                                    in revenue records. In many        implementation.
                                                    cases, the name of owner in        NGO       will    be
                                     Related to
                                                    the land records is not            appointed          to
                                   revenue record
                                                    updated after the land is sold     undertake        this
                                                    to another party/ person. The      activity         and
                                                    land records thus still shows      accordingly
                                                    the name of the previous           compensation will be
                                                    owner.                             paid.

                                                    People suggested that efforts
                                                    should be made during design
                                                    finalisation to save trees and
                                                    dharmshala             wherever
                                    Avoid CPR
                                                    possible. And in case of any
                                                    impact on CPRs, facilities like
                                                    waiting room with water facility
                                                    should be provided.
                                                    It was informed during the         Ownership details of
                                                    consultation that as per the       the affected land
                                                    existing culture of the area,      would be verified
                                                    villagers distribute or transfer   during RAP
                                                    their land with mutual consent     implementation.
                                     Related to     and the name of the new            NGO will be
                                   revenue record   owner is not reflected in the      appointed to
                                                    land records.                      undertake this
                                                    Farmers wanted, competent          activity and
                                                    authority checked each plot        accordingly
                                                    and give compensation to the       compensation will
                                                    occupier.                          be paid.
                    Chouraha,
2     04.11.2015                                    Compensation should be             Compensation will
                    Fatakheda
                                                    calculated on market rate.         be given based on
                                                    Land owner showed their            RFCTLARR, Act
                                   Compensation
                                                    concern compensation rates         2013 and Rajasthan
                                                    as DLC rate and market rate        rules 2016.
                                                    having a huge difference.
                                                    Compensation for unviable                    -
                                   Unviable Land
                                                    land to be given also.
                                                    In case of impact on                         -
                                                    resources used for irrigation
                                      Irrigated
                                                    purpose, alternatives sources
                                     Resources
                                                    may be provided by the
                                                    competent authority.
                                                    Compensation should be
                                                    calculated on market rate.          Compensation will
                    Post office,
3     04.11.2015                   Compensation                                         be given based on
                     Badnor                         Land owner showed their
                                                                                         RFCTLARR, Act
                                                    concern compensation rates

      Feedback Infra Pvt. Ltd                52             Public Works Department, Rajasthan
      Feasibility Report cum Preliminary Design for Up-gradation of Ras –               SIA & RAP
      Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sr.                                   Issues                                               Remarks
        Date        Locations                          Views and Suggestion
No.                                 discussed
                                                    as DLC rate and market rate       2013 and Rajasthan
                                                    having a huge difference.             rules 2016
                                                    Appropriate compensation to
                                                    be given for loss of trees and
                                                    wells.
                                                                                      Ownership details of
                                                    Landholders showed their
                                                                                      the affected land
                                                    concern regarding the
                                                                                      would be verified
                                                    ownership status as reflected
                                                                                      during RAP
                                                    in revenue records. In many
                                                                                      implementation.
                                                    cases, the name of owner in
                                    Related to                                        NGO will be
                                                    the land records is not
                                  revenue record                                      appointed to
                                                    updated after the land is sold
                                                                                      undertake this
                                                    to another party/ person. The
                                                                                      activity and
                                                    land records thus still shows
                                                                                      accordingly
                                                    the name of the previous
                                                                                      compensation will
                                                    owner.
                                                                                      be paid.
                                                    Considering the migration of      Local labour will be
                                                    small farmer to other states      preferred during
                                                    like Gujarat and Humpy, for       construction.
                                                    need of work, local people
                                     Migration
                                                    demanded that local labour
                                                    should be provided with
                                                    employment opportunities
                                                    during construction stage.
                                                                                      Affected owner
                                                    Patta owners of the village       having patta is
                                                    has demanded for                  considered as a title
                                       Patta
                                                    compensation of the loss of       holder and
                                                    structures built on patta land.   compensation will
                    Chauraha,
4     05.11.2015                                                                      be given the same.
                   Jaswantpura
                                                                                      Compensation will
                                                                                      be given based on
                                                    Compensation should be
                                  Compensation                                        RFCTLARR, Act
                                                    given on market rate.
                                                                                      2013 and Rajasthan
                                                                                      rules 2016
                                                    Initially the land owner          The existing road is
                                                    suggested for realignment or      being widened as
                                  Bypass option     bypass at this location. Later,   per the final design
                                                    they have demanded for
                                                    widening of existing road.
                                                    Compensation should be
                                                                                      Compensation will
                     Mawala-                        calculated on market rate.
5     05.11.2015                                                                      be given based on
                    Fatehgarh                       Land owner showed their           RFCTLARR, Act
                                  Compensation
                                                    concern compensation rates        2013 and Rajasthan
                                                    as DLC rate and market rate       rules 2016
                                                    having a huge difference.
                                                    land owner demanded that          Ownership details of
                                    Related to
                                                    compensation should be            the affected land
                                  revenue record
                                                    given to the affected person      would be verified
      Feedback Infra Pvt. Ltd                  53           Public Works Department, Rajasthan
      Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
      Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sr.                                   Issues                                                  Remarks
        Date        Locations                          Views and Suggestion
No.                                 discussed
                                                    having possession of                during RAP
                                                    acquiring land after                implementation.
                                                    verification by Patwari.            NGO will be
                                                                                        appointed to
                                                                                        undertake this
                                                                                        activity and
                                                                                        accordingly
                                                                                        compensation will
                                                                                        be paid.
                                                    Compensation should be              Compensation will
                                                    calculated on market rate.          be given based on
                                                    Land owner showed their             RFCTLARR, Act
                                  Compensation
                                                    concern compensation rates          2013 and Rajasthan
                                                    as DLC rate and market rate         rules 2016
                                                    having a huge difference.
                                                    Affected family to be               Local labour will be
                   Chauraha,
6     05.11.2015                   Employment       preferred in employment             preferred during
                   Badiya Hira
                                                    during construction                 construction.
                                                    Two very old temples exists         The existing road is
                                                    near Badiya Hira village on         being widened as
                                                    forest land and there is no         per the final design.
                                  Religious place
                                                    other option to widen the road
                                                    therefore, villagers suggested
                                                    a bridge on the same temple.
                                                                                        Based on the design
                                                                                        feasibility,       the
                                                                                        existing road is being
                                                    Landholders losing small land
                                                                                        widened.
                                   Land in place    plots have demanded for
                                                                                        Compensation will
                                     of Land        providing government land
                                                                                        be paid to the
                                                    available in the village.
                                                                                        affected land holders
                                                                                        as        per     their
                                                                                        entitlements.
                                                    Compensation should be              Compensation will
                                                    calculated on market rate.          be given based on
                                                    Land owner showed their             RFCTLARR,          Act
                                  Compensation      concern        about          the   2013 and Rajasthan
7     06.11.2015        Bar                         compensation amount as DLC          rules 2016.
                                                    rate and market rate having a
                                                    huge difference.
                                                    With the loss of irrigation         Compensation will
                                                    resources due to road               be given based on
                                                    widening, the land will become      RFCTLARR,      Act
                                                    unirrigated.      Landholders       2013 and Rajasthan
                                     Irrigation     demanded that the competent         rules 2016.
                                    resources       authority    should      provide
                                                    alternative            irrigation
                                                    arrangements.
                                                    Farmers demanded that the
                                                    implementing agency should

      Feedback Infra Pvt. Ltd                54              Public Works Department, Rajasthan
       Feasibility Report cum Preliminary Design for Up-gradation of Ras –                    SIA & RAP
       Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sr.                                       Issues                                                  Remarks
         Date           Locations                           Views and Suggestion
No.                                     discussed
                                                         dig wells at their own cost as
                                                         the government compensation
                                                         is much less that the actual
                                                         cost incurred (approx. 5 lakh
                                                         rupees).
      Major outcome and suggestion

            ▪    Compensation of land and attached asset to be given based on market rate.
            ▪    Expectation of employment opportunities from the project.
            ▪    Land owner demanded that compensation to be given to the person having possession
                 on affected land and a joint verification should be done to ascertain the ownership
                 status before payment of compensation
      5.6       Consultation with Women
      Focus group discussions were conducted with women group to take their suggestions and
      concerns related to the implementation of this project. It was noted during the discussions that
      women in the study area consistently lagging behind in terms of access to education, health
      care, jobs etc.

      During consultation with women group, issues related to safety of their children, resettlement
      of their residential as well as commercial structure, gender-based benefits and constraints of
      the project, were discussed. As many households do not have tap water facility in the area,
      so women and girls need to cross the road to fetch water as many a times the water resources
      are on the other side of the road. Safety of children is also a concern considering the increase
      in the number of vehicles due to better road connectivity. Cattle also cross the road and there
      are issues related to their safety as well. They suggested avoiding demolition of the structure
      because they have been settled there from a long time and proposed considering bypasses
      to avoid any impact on the settlements.

      During consultation it was also recorded that no one complained about any gender-based
      violence issue.

      In general, women welcomed the road project as it will help the villagers to easily avail the
      medical facility near Beawer, Mandal and Bhilwara town. Mostly girls drop their education after
      10th and 12th due to unavailability of the colleges near the village/town. With better connectivity,
      the women group anticipated that more girls will avail better educational and health facilities.
      The details of Focus Group Discussions/ consultations are given in Table 5-3.

                                 Table 5-3: Details of consultation with women
       Sr.              Loc                                                               Remarks
                                   Issues
       No       Date    atio                           Views and Suggestion
                                 discussed
        .                ns
                                                Local women are involved in           Local labour and
                                                agriculture and household work        women labor will
                16.09
        1               RAS                     and a few women go in                 be      preferred
                .2018
                                                MGNREGA and demanded for              during
                               Employment       employment during construction        construction.



       Feedback Infra Pvt. Ltd                    55              Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sr.           Loc                                                               Remarks
                            Issues
No    Date    atio                          Views and Suggestion
                          discussed
 .             ns
                                      Women showed their concern on         Appropriate
                                      heavy traffic during school time.     measures will be
                                      Considering      this,    adequate    taken for safety.
                                      provisions should be made in
                     Safety           road designs
                                      Mahila Sangathan are working in
                                      village but sangathan not
                                      participate in any social activity.
                                      Even these sangathan are not
                                      involved in any economic
                                      activity.
                                      Sangathan are interested if they
                                      get some kind of work like mess
                                      for construction worker. Such
                                      opportunities may be provided
                     SHG              during road construction.
                                      Mahila Sangathan are working in
                                      village but sangathan not
                                      participate in any social activity.
                                      Even these sangathan are not
                     Mahila           involved in any economic
                     Sangathan        activity.
                     Women            Women        are     involved    in
                     involvement      agriculture and household work
                                      Safety signage should be              Appropriate
                                      marked in the residential area.       measures will be
                                      Traffic speed near the settlement     taken for safety
                     Safety           area should be restricted.
                                                                            Compensation
                                                                            will be given
              Kun
                                                                            based            on
              diya
      18.09                                                                 RFCTLARR, Act
 2            Kap
      .2018                                                                 2013           and
              adiy
                                      Compensation       should      be     Rajasthan rules
               a
                     Compensation     calculated on market rate.            2016.
                                      Structure should be saved             The        existing
                                      whereas possible. One temple is       road is being
                                      located on the LHS of the             widened as per
                                      existing road. Efforts should be      the final design.
                     Structures       made to save the temple.
                                      Main source of the water is a well
                     Water            only.
                                      Hospital is available in Pipli
                                      Kapadiya and hospital doesn’t
                                      have proper staff. Due to
                                      unavailability of medical facility
                                      villagers went to Beawer and
                     Hospital         Mandal town.


Feedback Infra Pvt. Ltd                56             Public Works Department, Rajasthan
     Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
     Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



     Sr.            Loc                                                             Remarks
                                 Issues
     No     Date    atio                           Views and Suggestion
                               discussed
      .              ns
                                                                           The        existing
                                             Affected women suggested to road is being
                                             save the village and proposed widened as per
                            Bypass option    bypass in the village.        the final design.

                                             Women       are    involved  in
           19.09   Mavl                      agriculture    and    household
     3
           .2018    a                        activities.

                                             They do not participate in any
                                             social activity.

                            Involvement of Main decision taken by male
                            women          member in village.

    5.7    Village Panchayat/Municipality corporation
    Panchayat and municipality welcomed the project and expected that the construction of the
    road will be completed by end 2020. During the SIA and RAP preparation, consultations
    were conducted with 4 panchayats and 1 Municipality. Details of the consultation is given in
    Table 5-4
                   Table 5-4: Details of consultation with Panchayat and Municipality

S                                                                                       Remarks
r           Panchay
. Dat          at/           Issues
                                              Views and Suggestion
N e         Municipa       discussed
o             lity
.
                                                                               The existing road is
                           Widening    Widening of the road should be equal
                                                                               being widened on
                           on both     on both side of the road and
                                                                               both sides of the
                             side      demanded to save the structure.
                                                                               road.
    17.                                Safety signage should be marked in
            Panchaya         Safety
    09.                                the residential area.
1              t-
    201                                                                        Compensation will be
            Sahapura
     8                                                                         given based on
                           Compensat   Compensation should be calculated       RFCTLARR Act,
                              ion      on market rate.                         2013 and Rajasthan
                                                                               land acquisition rules
                                                                               2016.
                                                                               Compensation will be
    19.                                                                        given based on
    09.     Panchaya       Compensat   Compensation should be calculated       RFCTLARR Act,
2
    201     t- Badnor         ion      on market rate.                         2013 and Rajasthan
     8                                                                         land acquisition rules
                                                                               2016.


     Feedback Infra Pvt. Ltd                  57             Public Works Department, Rajasthan
    Feasibility Report cum Preliminary Design for Up-gradation of Ras –             SIA & RAP
    Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



S                                                                                 Remarks
r         Panchay
. Dat        at/         Issues
                                           Views and Suggestion
N e       Municipa     discussed
o           lity
.

                       Delaying in
                                     Local people demanded that project
                       constructio
                                     to be timely complete.
                           n

                                 Sarpanch demanded preference of            Local labour will be
                       Employmen
                                 local people in employment during          preferred during
                           t
                                 construction.                              construction.
                                     Municipality chairman and member       The existing road is
                                     of municipality demanded for bypass    being widened as per
                         Bypass      in entire Asind city.                  the final design.
                         option      Municipality has been proposed a
                                     residential colony which may
                                     disturbed due to widening.
    20.                              Asind municipality has been
    09.   Municipali     Master      proposed master plan in city so they
3
    201   ty- Asind       Plan       have concern that it may affect the
     8                               plan.


                                     Demanded to avoid to the demolition
                       Structures
                                     of the structure.


                                     Local people will lose their residential The existing road is
                                     as well as commercial structure due to being widened as per
                         Loss of
                                     widening of the road. Sarpanch the final design.
                        structure
                                     demanded to save these structures
                                     whereas possible.
    20.   Panchaya                                                     Compensation will be
    09.      t-                                                        given   based       on
4                      Compensat     Compensation should be calculated RFCTLARR          Act,
    201   Shekhaw
     8       as           ion        on market rate.                   2013 and Rajasthan
                                                                       land acquisition rules
                                                                       2016
                                     It has been recorded during the
                        Gender
                                     consultation      no gender-based
                         based
                                     violence has been recorded in and
                        violence
                                     near the village.
                                                                       Compensation will be
    21.                                                                given   based       on
    09.   Panchaya     Compensat     Compensation should be calculated RFCTLARR          Act,
5
    201   t- Mandal       ion        on market rate.                   2013 and Rajasthan
     8                                                                 land acquisition rules
                                                                       2016

    Feedback Infra Pvt. Ltd                 58            Public Works Department, Rajasthan
        Feasibility Report cum Preliminary Design for Up-gradation of Ras –                    SIA & RAP
        Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



      S                                                                                     Remarks
      r           Panchay
      . Dat          at/         Issues
                                                    Views and Suggestion
      N e         Municipa     discussed
      o             lity
      .
                                             Local people of the village are Local labour will be
                                             involved in agriculture, labour and preferred during
                               Occupation
                                             some are working in the textile construction.
                                             factories in Mondal and Bhilwara.
                                             Women are involved in private jobs,
                                Women        agriculture, rearing animal and
                                             household work.


       Major recommendation and outcomes
             ▪    As the road passes through a market area in Asind Municipality, The Chairman of the
                  Municipality has demanded to vaoid the existing market area. This will also not interfer
                  wth any of the activities/ interventions as planned under the master plan.
             ▪    The Gram Panchayats consulted was observed to be supportive of the project. They
                  felt that the proposed project can bring development in the area and they demanded
                  greater engagement of local community as well as to avoid structures whereas
                  possible
             ▪    Village Panchayat expect local benefits like enhancement the local infrastructure,
                  targeted social investment programme through government initiatives.
             ▪    The panchayat also expressed concerns over movement of heavy traffic, as they fear
                  safety of children and livestock which roam around freely in the area.
             ▪    The Village Panchayat hinted at the following activities:
                  •        Measures to improve the water availability of the area; and
                  ▪        Contribute towards developmental activities of the area.
                  ▪        Start govt bus transport system in the project corridor.


       5.8       Consultation with Industries
       Cement factories were identified as a major beneficiary of the project i.e. Ambuja Cement and
       Shree Cement in Ras and Beawar respectively and consultations were carried out with both
       factories. Approx. 500 truck trips from Ras and Beawar to Chittore, Gujarat and Madhya
       Pradesh of each factory that shows the value of the road for these cement factories.
       Considering this, consultations were also conducted with different agencies and factory
       owners to take note of their concerns and suggestions also. Details of the consultation is given
       in Table 5-5.
                               Table 5-5: Details of consultation with industries
Sr.                Location         Issues                                                   Remarks
       Date                                              Views and Suggestion
No.                   s           discussed
                                                  No export and import of raw materials     Existing
                    Railway
      17.09.2                     Export and      in a large scale at Beawer railway        road is
18                  Station,
       018                          Import        station. Major movement of materials      being used
                    Beawer
                                                  is done by roads only.


        Feedback Infra Pvt. Ltd                     59             Public Works Department, Rajasthan
        Feasibility Report cum Preliminary Design for Up-gradation of Ras –               SIA & RAP
        Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sr.             Location        Issues                                                   Remarks
       Date                                          Views and Suggestion
No.                s          discussed
                                              Goods train stopped only 2 minutes in     for export
                                              Beawer railway station                    and import.
                                              Approx 500 daily trips from Ras-          Cement
                                              Beawer to Chittore, Gujarat and           Industry is
                              Daily Truck     Madhya Pradesh                            major
                                  trip                                                  beneficiary
                                              Out of 500 trips 200 trips in and out
                                              from Ras-Beawer                           of the
                                                                                        poject.
                                              Having 300 trucks parking capacity in
                                  Parking     the factory premises
                                  Capacity    During site visit no truck were park on
                                              or near the road
                                              Having 8 clinker units
                                              Production of clinker is 30000-32000
                             Clinker Units    ton/day
                  Shree
      17.09.2                                 15000-ton clinker is used in domestic
19               cement
       018                                    purposes
                 limited
                               Cement         Total Cement production is 17000-
                              production      18000 ton a day.
                                              Approx 10000 employees are working
                              Man Power
                                              in the factory.
                                              Mainly raw material comes from
                             Raw material     Hindustan Zink Limited, Udaipur by
                                              road.
                                              Goods train is not used to import and
                                  Railway
                                              export the raw materials.
                                              Type of employees required are
                             Desired skills
                                              Electrician, mechanical, fitters,
                            for employees
                                              welders, Masons and security guards
                                              Daily trips of the truck are approx 450   Cement
                                              from Ras-Beawer, Chittore, and            Industry is
                              Trips of the    Goutam Buddh Nagar by road.               major
                             Truck per day    Out of 450 trips, 300 vehicles export     beneficiary
                                              and 150 are import from chittore to       of the
                                              Udaipur.                                  project.
                Ambuja
      17.09.2                                 Having capacity of approx 300 trucks
20              Cement
       018                                    in the factory premises
                Factory           Parking
                                  Capacity    During site visit no truck was seen
                                              park on or near the road.
                                              Having 4 clinker units
                             Clinker Units    9000 ton both cements and clinker
                                              dispatched daily



        Feedback Infra Pvt. Ltd                 60              Public Works Department, Rajasthan
       Feasibility Report cum Preliminary Design for Up-gradation of Ras –                   SIA & RAP
       Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Sr.              Location         Issues                                                   Remarks
      Date                                             Views and Suggestion
No.                 s           discussed
                                                Approx 1500 employees are working
                               Man Power
                                                in the factory
                                                Mainly raw material comes from
                               Raw material
                                                Hindustan Zink Limited, Udaipur
                                                Railway is not used to import and
                                 Railway
                                                export in factory
                                                Type of employees required are
                               Desired skills
                                                Electrician, mechanical, fitters,
                              for employees
                                                welders, Masons and security guards
      Major recommendation and outcome

           •   The proposed project will provide shortest route to connect North and North-West part
               of Rajasthan to South-East Rajasthan
           •   Reduce travel time between Chittorgarh to Ras and Udaipur to Ras.
           •   Create new opportunity of employment
           •   Entire transport does via road being goods train is stopped in Beawar for only 2 minutes.
      5.9      Consultation with NGOs
      No NGO is working directly in the project corridor, some NGOs are working in Beawar and
      Ajmer. Consultations were carried out with identified NGOs to understand their views with
      respect to the proposed project. Details of the consultation are given in Table 5-6.
                                 Table 5-6: Details of consultation with NGOs

        Sr.                                       Issues            Views and             Remarks
        No.        Date        Locations        discussed           Suggestion
                                                               They majorly help
                                                               the        industrial
                                                               workers            in
                                                               addressing issues
                                                                                     Local labour
                                                               with           their
                                                                                        will be
                                                               employers/ factory
                                                                                       preferred
                                                               management.
                                                                                        during
                                                                Suggested         to
                                                                                     construction.
                                                               provide
                                                               employment
                 22.09.20                                      opportunities      to
       1         18          GSVS, NGO          Employment     local labour
                                                               Works on girl’s
                                                               education program
                                                                                          proposed
                                                         As the schools                  project will
                                                         dropouts is quiet              improve the
                                                         high in the area,              connectivity
                                              Higher     with    better road             and help to
                 22.09.20    Room to Read, education for connectivity,     the             reduce
       2         18          NGO               girls     project will help the
       Feedback Infra Pvt. Ltd                    61             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                    SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                                                          girls in the project      dropouts in
                                                          area to avail better        female.
                                                          education facilities.




                                                          Better   road    is
                                                          necessary       to
                                                          development of the
                                           Necessity      area.
                                                          Aryama seva samiti
                                                          working under Deen
                                                          Dayal     Upadhyay Local labour
                                                          yojana    for   skill   will be
                                                          development            preferred
                                                          Proposed that the       during
                                                          project       should construction.
                                                          generate
          22.09.20    Aryama Seva                         employment
 3        18          Samiti, NGOs       Employment       opportunity
Major recommendation and outcome

     ▪   They felt that proposed project is essential for the development of the area.
     ▪   Corridor from Sanwas village to Mandal is not well connected with the transport system
         therefore community has to spend much time to go to Beawer and Mandal so that
         proposed project will bring changes in their socio-economic profile.
     ▪   Some student especially girls drop their education after 10th and 12th due to far distance
         from their residence. It’s not their culture for female to commute far alone from their
         residence but denied the security issue with respect to female in the project corridor.
     ▪   Sometime community has to face difficulty during medical emergency due to road
         connectivity. It becomes worse when someone has to use public transport in the
         medical emergency. No govt. bus is available on this route therefore has to use private
         bus but their frequency is less than usual.
     ▪   Civil societies asked to develop the infrastructural facilities in the area with respect to
         health, education and water.
5.10 Consultation with Project Developer
During the study period, Social team consulted with EE PWD, Pali at his office and on
proposed project to understand about the project and other social features around the project
site

     •   They shall give direction to the contractor to engage the local people, panchayat,
         Municipal Corporation and civil societies in the proposed project.
     •   They already consulted with the different stakeholders and shall be consulted in every
         stage of the project.
Photographs of Consultation and Group Discussion with different stakeholders are
given in Annexure 5.1


 Feedback Infra Pvt. Ltd                    62              Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



5.11 Key Issues/concerns and suggestion
Though, the project road stretch passes through four different districts of Pali, Ajmar,
Rajsamand and Bhilwara, the settlement pattern as well as socio-economic profile across this
whole stretch of 116.750 Km has a lot of uniformity. Even the issues that have emerged as a
result of this consultative process are also quite common, with minor variations. The key
Issues raised during Consultations are as follows:

   •   Resettlement was the main issue of the affected, local and influential person of the
       project corridor.
   •   Participants also suggested in detail in every meeting. General consensus was on
       replacement value for any immovable property acquired. Participants also suggested
       that compensation be paid in time with one single installment so that the amount can
       be used in a fruitful manner.
   •   Safety of children, local people and animal was another concern. Participants were
       informed that road safety provisions, extra wide road, footpath and drains should be
       provided in the settlement areas.
   •   It was the major concern of the local people to develop the drainage system of the
       area.
   •   Some location people asked to proposed bypass.
   Thus, on the basis of above consultation/ group discussion with local community/ villagers/
   village sarpanch/ village panchayat members/ influential person of the region/ government
   officials and various stake holders, we may conclude that proposed project will prove
   beneficial not only to local region but also up to state and national level for a long term.
   There is a big support of local community in favor of the project.




 Feedback Infra Pvt. Ltd                 63             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                             CHAPTER - 6.: ANALYSIS OF ALTERNATIVES
This Chapter details the various alternatives considered to decide on the feasibility of the
project and in design finalization. The analysis has been done at two levels, firstly, the
alternative analysis was done considering the “with and without project scenarios�? which
considered the potential social impacts, both positive and negative, of the sub-project.
Secondly, an analysis has also been made during finalization of bypasses and realignments
taking into consideration the requirement in meeting the design standards for smooth flow of
traffic and also social impact of the opted designs on assets and requirements of land along
the road, bypasses and realignments. Both the analysis is detailed in the below section:

6.1   Inputs at Different Stages for Minimizing Resettlement
Regarding resettlement and rehabilitation input, it may be mentioned here that from the very
beginning of the project formation, social and environmental team worked hand to hand with
engineering design group. These inputs in concrete terms were made available at the following
stages:
        a) Stage 1: Potential resettlement and rehabilitation issues were identified at the
           preliminary reconnaissance visit. Field Surveyors identified the villages and urban
           areas with inadequate road width and design team was provided this input.
        b) Stage 2: Right of way was ascertained from Rajasthan PWD and Revenue
           Department and where in doubt, actual measurements were made and data on
           land available for road widening and the land acquisition requirement was collected
           and provided to the Design team. The socio-economic and census surveys of the
           potentially project affected persons were initiated from the very beginning. A Social
           Assessment was done of the 100% potentially affected population within the likely
           corridor of impact (30 meters). The social assessment registered the household
           members and individuals within the potential corridor of impact, enumerated the
           sites and in fact gathered sufficient demographic and social information to
           determine whether they were to be categorized as vulnerable groups with special
           entitlements under the project as per Entitlement Matrix. Socio-economic survey
           provided the base line against which mitigation measures and support has been
           measured and survey included the needs and resources of different groups and
           individuals including women headed households and gender analysis.
        c) Stage 3: R & R team working in the field, weighed up the alternative alignment
           options proposed by the Survey and Engineering team and this field information
           were shared and discussed with engineering design team, so that they make such
           a plan, which could avoid or minimize adverse impact on large number of
           households. In response, the engineering team considered various options.
        d) Stage 4: Local level consultation regarding the impact of widening of the road
           through the villages and towns was conducted and alternative suggestions offered
           by them were considered. Social and environmental inputs were provided at the
           feasibility stage and recommendations were made according to the findings of the
           social and environmental surveys.
        e) Stage 5: Full coordination and cooperation between the resettlement and
           Rehabilitation team and Engineering team results in:
            a) Unnecessary displacement avoided by modifying the alignment
            b) Fixing the speed in the built-up areas including schools and hospitals as per
                 local needs and problems of the people
            c) Deciding the rural and urban road cross-sections based on field surveys and
                 likely impact on the people
            d) Evolving Community consensus on shifting the existing shrines and religious
                 structures

 Feedback Infra Pvt. Ltd                  64             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                   SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



6.2   With and Without Project Alternatives
6.2.1 Without Project Scenario
The existing project road section varies from single lane to two lanes with earthen shoulders
with varying pavement width. With present and projected high traffic volumes, the capacity of
the present highway is insufficient for handling the high volume of traffic and calls in for
improvements to a 2 lane and 4 lane carriageways with paved & Granular shoulder. The
project highway has many roadside settlements and the traffic flow is seriously impacted by
severe conflicts between the local and the through traffic. This is further compounded by the
various land use conflicts, in terms of uncontrolled development along the highway. The
population growth, increase in traffic volumes and the economic development along the
corridor would continue to occur and will worsen the already critical situation. Moreover, if it is
decided not to proceed with the project, then the attendant reduced socio-economic
development of this remote, relatively poor connected area cannot be justified. Therefore,
alternative action of not going ahead with the project is neither a reasonable nor a prudent
course of action, as it would amount to failure to initiate any further improvements and impede
economic development.

6.2.2 With Project Scenario
The ‘with project scenario’ is found to have a positive impact in the long run on social,
environmental, economic and financial issues. This scenario includes the widening to 2 / 4
lanes of the existing single / two lanes stretch as envisaged in the project objectives. The
scenario is economically viable and will improve the existing conditions. It, would thereby,
contribute to the development goals envisaged by the Governments of Rajasthan and India,
and enhance the growth potential of the area.

To avoid the acquisition of land and properties, the project envisages the development within
the minimum RoW as much as possible. However, need for land acquisition has been
envisaged for bypass, realignment and curve improvement sections.

In spite of the various development benefits likely to accrue due to the project, as is the case
of every road development project, the project would be accompanied by certain impacts on
the natural, social and environmental components. Wherever avoidance of negative impact
has not been possible, appropriate mitigation and enhancement actions will be worked out to
effectively offset the social damages inflicted due to the project. A detailed Resettlement
Action Plan (RAP) has been worked out to compensate the affected people for the loss of their
assets and also to improve the well-being and livelihood of the people to be impacted.
Comparative assessments of the “with and without�? project scenarios are presented in the
following Table.
        Table 6-1: "With and Without" Project Scenarios - A Comparative Assessment

 Component              "With" Project Scenario                 'Without" Project Scenario
                        2-lane and 4-lane carriageway with Existing single / two lane
 Highway
                        paved/granular    shoulder    with carriageway     with  poor
 Geometrics
                        geometric improvements             geometrics
 Design Speed           Design speed 80-100 Kmph                40 – 60 kmph
                        Free flow of traffic due to widened
 Congestion        in                                       Congestion in urban areas and
                        carriageway       and      improved
 Settlements                                                rural areas
                        geometry


 Feedback Infra Pvt. Ltd                   65              Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                  SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



 Component               "With" Project Scenario                 'Without" Project Scenario
                         Bypasses,       realignment     and
                         subways for safety of pedestrian.
                                                                 Pedestrian safety an issue of
                         Along the settlement stretches with
                                                                 major concern especially along
 Pedestrian safety       significant    pedestrian    traffic,
                                                                 the settlements and congested
                         provision of pedestrian (zebra)
                                                                 sections.
                         crossings and footpath has been
                         kept in urban sections.
                         Reduction in time and fuel
 Better                  consumption for easy and fast Increased vehicle operating
 Transportation          movement through the major towns costs due to reduced speeds
 Facilities              and villages. Better Access to
                         markets
 Economic                There will be increased access to
 Development             markets. Local people will be The economy will remain static.
                         employed during construction of the
                         project road. Better transport
                         facilities will lead to access to new
                         employment centers. Project may
                         provide job / livelihood opportunities
                         to people through commercial
                         establishment in area due to good
                         connectivity with other cities and
                         towns.
 Loss of Property Some people will lose their                    The road side may further be
 and livelihood   property and livelihood due to land            encroached.
                  acquisition for bypasses and
                  widening of existing road where
                  RoW is not sufficient to
                  accommodate the road design.

 Access to basic Easy access to basic facilities due Difficulty in accessing the basic
 facilities such as to fine road                     facilities due to heavy traffic.
 Markets, schools,
 Hospitals etc.
                         Higher potential for development Development activities will be
 Development             due to improvement in access and greatly hampered by the gross
                         consequent increase in connectivity inadequacy of infrastructure.
Source: Design Report and Primary survey

By looking at the above table, “with�? project scenario, with its some adverse impacts is more
acceptable than the “without�? project scenario which would mean an aggravation of the
existing problems. The potential benefits of the proposed road improvements are substantial
and far-reaching both in terms of the geographical spread and time. Hence, it is clear that the
implementation of the project will have definite advantage to area in development of its
economy and progress for its people.



 Feedback Infra Pvt. Ltd                    66             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                  SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



6.3       Analysis of Alternatives Alignment
After having examined the feasibility of the road-improvement in the existing alignment, it is
concluded that some of the project segment (mainly thickly built- up stretches) may have social
constrains during construction because these critical stretches are experiencing congestion,
encroachment of RoW and poor geometry. The major difficulties in following the existing
alignment option completely, is the magnitude of land acquisition & social disruption and
unsafe traffic condition. Therefore, realignment and bypasses have been suggested in the
built-up stretches. Alternatives for these bypasses and realignments have been considered
keeping in view social and technical parameters and based on the analysis of alternatives, the
best alternative has been finalized.

For the remaining stretch, the selection of the alignment along various sections has been
worked out based on continuous interaction between the highway, social and environmental
teams. Mostly concentric widening of the existing alignment has been considered to fully utilise
the available RoW. The project road shall be rigid and flexible pavement throughout the
stretch.

6.3.1 Criteria for Fixing bypasses and realignment
Obligatory sensitive reasons through which bypasses and realignment options should not
pass, are detailed in sections below.

Habitations: Proposed alignment has been fixed in such a way that it traverses at a minimum
distance of 200-300m from built up areas and avoiding important buildings and structures.
However, Bypasses and realignment options have been adopted to minimise the impact on
settlement due to project.

Moreover, the alternative options have been worked out keeping the following in mind:

      •    The project should be constructible and easy to maintain; the project should reduce
           the vehicle operation cost with respect to the existing option already available
      •    The alignment should be finalized giving due consideration to siting/location of major
           structures including Major / Minor Bridges and ROBs
      •    Alignment should follow the unused / barren land to the extent possible to reduce the
           cost of land acquisition and carbon foot print.

6.3.2 Alternative Analysis of Bypasses and realignments
Bypasses have been proposed to avoid various built-up areas along the project
highway, where geometric improvements are not possible as per design standards.
Before declaring it as National Highway, the road comprised of SH-39 and MDR-84,
which had poor geometrics. Bypasses and realignments are inevitable at many places
to improve the geometrics and mitigating the risks of social impacts. The details of
alternative analysis furnished and given as an annexure 6.1.




 Feedback Infra Pvt. Ltd                    67             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



   CHAPTER - 7.: EVALUATION OF SOCIAL IMPACT ASSESSMENT
7.1   Introduction
The proposed road improvements will be carried out within the available RoW of 30m
throughout the project road and will involve land acquisition. The detail of the impact is
alienated in respective below sections.
7.2   Cut-Off Date
Cut-off date i.e. start date of Census survey for non-titleholders is 22nd September 2018.
7.3   Land Acquisition Estimates for the Project
Proposed project required 360.61 hectare land out of which 116.16 (32.21%) hectare land is
available and 244.45 hectare of land will be acquired which includes 160.25 (44.43%) hectare
of private, 67.938 (18.84%) of government and remaining 16.2995 (4.52%) hectare of forest
land will be acquired. A detail of the land acquisition is presented in Table 7-1.
                               Table 7-1: Details of available land
                                                     Land to be Acquired       Total
                Length      Available Land       Private    Govt.     Forest   Land
                  (in       (Existing ROW)        Land      Land       Land  Required
 Stretch         KM)             (in ha)        Required Required Required    (in ha)
 Ras-
 Beawar-
 Asind-
 Mandal         116.75          116.163         160.2077        67.938     16.2995   360.608
 Percentage       -              32.21            44.43          18.84      4.52       100
7.4   Type of Land to be acquired
Approx. 160.208 hectare private land is required for the proposed project which includes
91.891 hectare of agricultural land followed by 43.776 hectare of barren land and 11.86
hectare of forest land . Details of the affected private land are given in Table 7-2.
                           Table 7-2: Categorization of the private land
 Type of Private land                   Area (in Ha)            Percentage
 Agricultural                                           91.89                           57.36
 Barren                                                 43.78                           27.32
 Forest                                                 11.86                             7.4
 Residential and Commercial Plots                        9.85                            6.15
 Others                                                  2.83                            1.77
 TOTAL                                                 160.21                            100
Source: 3D

7.5   Impact on Structures
The properties likely to be affected by the proposed project are surveyed by using structured
questionnaire. These properties include residential, commercial, residential-cum-commercial
and boundary wall. It has been attempted to get the details of various structures that are
located within the proposed ROW of the project road. The survey data reveals that there are
653 affected structures which include 400 private structure and 253 of CPRs. CPRs includes
92 of religious, 79 of community and 82 of government structures within 30 meter right of way

 Feedback Infra Pvt. Ltd                   68              Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                     SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



on the existing road. The details of the affected structure are given as an annexure 7.1 & 7.2
and in following sections.
7.6   Type of Affected Structure
The result of social survey reveals that out of 653 structures, 61.26% of the structure are
residential followed by 14.09% of religious structure, 12.56% of government structure and
12.10% of community structure. The details of the type of affected structure are given in Table
7-3.
                               Table 7-3: Type of Affected Structure

 Type of structure                Number                           Percentage
 Private                          400                              61.26
 Government                       82                               12.56
 Community                        79                               12.10
 Religious                        92                               14.09
 Total                            653                              100.00
Source: Census Survey, 2018

7.7   Construction type of Structure
As per the census survey, maximum numbers of the constructed structures, which are likely
to be impacted within the RoW are permanent with 83.46% and only 10.11% of structure are
semi-permanent. Number of temporary structures are very less, only 6.43% of the total
affected structures. The details of the structures as per their construction type are summarized
in the Table 7-4.
                      Table 7-4: Construction type of the affected structure
 Construction type of
 Structure                              No.                         Percentage
 Permanent                              545                         83.46
 Semi-Permanent                         66                          10.11
 Temporary                              42                          6.43
 Total                                  653                         100
Source: Census Survey, 2018

7.8   Impact on Private structures
Out of total 653 affected structures, 400 are private structures. The census survey reveals that
private structure includes, 43.75% of the structure are residential followed by 32.75% of
commercial structure and, 13% of residential-cum-commercial. The detail of affected
structures is given in Table 7-5.
                           Table 7-5: Categorization of private structure

             Usage of Structure                       Numbers                  Percentage

 Residential                                             175                     43.75
 Commercial                                              131                     32.75
 Residential-cum-commercial                              52                        13
 Boundary Wall                                           37                       9.25
 Cattle Shed                                              5                       1.25

 Feedback Infra Pvt. Ltd                      69           Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                  SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



 Total                                                  400                     100
Source: Census Survey, 2018

7.9   Impact of Common Property Resources
Census survey reveals that 253 CPRs will be affected by the proposed project. Out of 253
CPRs 36.36% are religious structure followed by 33.73% of government structure and the
remaining 30.20% are community structure. It was noted during census survey that many
households have a small shrine in front of their house or in their fields for worshipping as per
their traditional beliefs. These shrines are called as “Dev Sthana�? in local language. About 69
such shrines (Dev Sthan) will be impacted due to road widening. Relocation of these shrines
were discussed with the affected households during survey. People agreed to relocate these
shrines if compensation is paid for their reconstruction.

In case of schools, mostly the boundary wall of the schools will be impacted and there would
not be much impact on the main building. The details of the affected CPRs are given in Table
7-6.

                                     Table 7-6: Details of CPRs

         Category                         Properties              No.        Percentage

                              Temple                                    23                9.09
         Religious            Dev Sthan                                 69               27.27
                       Total Religious                                  92               36.36
                              Chabutara                                 19                7.51
                              Warehouse                                 1                 0.40
                              Drinking Water Tap                        11                4.35
                              Samudayik Bhawan                          1                 0.40
                              Water tank (Cattle)                       14                5.53
                              Well                                      22                8.70
      Community               Water Tank                                11                4.35
                      Total Community                                   79               31.23
                              Government School                         13                5.14
                              Private School                            1                 0.40
                              Community School                          1                 0.40
                              Ambedkar Hostel                           1                 0.40
                              Anganwadi                                 1                 0.40
                              Police Chouki                             1                 0.40
                              Gram Panchayat                            3                 1.19
                              Other Government Structure                7                 2.77
                              Tehsil Office                             1                 0.40
                              Sahkari Samiti                            5                 1.98
                              Cotton Factory                            1                 0.40
                              Power House                               1                 0.40
      Government              Bus Stop                                  15                5.93
 Feedback Infra Pvt. Ltd                       70          Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                  SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                              Public Toilet                              1                   0.40
                              Pond                                       6                   2.37
                              Hand Pump                              22                      8.70
                              Government Water Tank                      2                   0.79
                     Total Government                                82                  32.41
                         Grand Total                                253                 100.00
Source: Census Survey, 2018

7.10 Ownership status of private structure
As per the information collected during census survey that total 88.5% structure are title holder
and only 11.5% structure are non-title holder. It is recorded that all non-title holder are
considered as a squatter. Detail of the ownership is alienated in Table 7-7.
                           Table 7-7: Categorization of ownership status

 Ownership type                      Number                       Percentage
 Titleholder                         354                          88.5
 Non-title holder (Squatter)         46                           11.5

 Total                               400                          100
Source: Census Survey, 2018

7.11 Socio-Economic profile of the PAPs along the Project Road
The purpose of social impact assessment was to create a broad database of the affected
properties as well as the project-affected persons (PAPs) in order to understand the social
profile of the project-affected households. It helps to appraise the positive as well as negative
impact on the affected families due to the proposed project. The socio-economic details of the
affected households were collected during the survey, as explained in below sections.
7.12 Total Number of Project Affected Persons (PAPs along the project road)
Census and Socio-Economic survey has been carried out for all the affected households. Total
400 households are affected due to the proposed project. There are altogether 2508 persons
(family members of affected households). As given in below table, out of the 2508 PAPs,
53.91% are male and 46.09% are female. The socio-economic profile of the affected
households is analyzed and presented in the following sections.
                        Table 7-8: Number of PAPs along the Project Road
                                                           No of affected
 Sl. No.       Category                                                          Percentage
                                                               PAPs
 1             Male                                            1352                  53.91
 2             Female                                          1156                  46.09
 Total                                                         2508                   100
Source: Census Survey, 2018




 Feedback Infra Pvt. Ltd                      71          Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                      SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



7.13 Religious Category of PAHs along the Project Road
Majority of the PAHs belongs to Hindu population (81.75%) and 9.50% population Muslim
category respectively. No information could be collected for about 8.75% of the affected
households as reflected in Table 7.9.
                Table 7-9: Religious Categories of PAHs along the Project Road

 Sl. No.           Religious Group                No of affected PAHs           Percentage
        1          Hindu                                     327                        81.75
        2          Muslim                                     38                         9.5
        3          No information                             35                        8.75
                                        Total                400                         100
Source: Census Survey, 2018

7.14 Social Stratification of PAHs
Out of the 400 PAFs, 247 belong to Other Backward Castes (OBC), 59 are General category,
54 are SC and no one was available during the survey to provide information for remaining 35
households. Only 5 ST households impacted due to the project. It was noted during the survey
and the field visit that these ST households are not located at one location and have merged
with mainstream population. The social category of the affected households is given in
Table 7-10.
                Table 7-10: Social Stratification of PAHs along the Project Road

   Sl. No.     Social Category                             No of PAHs                   Percentage
      1        General                                             59                      14.75
      2        OBC                                                247                      61.75
      3        SC                                                  54                      13.5
      4        ST                                                   5                      1.25
      5        No Information (Not available)                      35                      8.75
                                                     Total        400                       100
 Source: Census Survey, 2018

7.15 Vulnerable Groups
Vulnerable families constitute that portion of the population which is denied the opportunity to
fully explore and utilize its abilities and thus enjoy a quality of life. These people are left behind
in today's advancing economy and need special attention and care thus BPL, women headed
household (WHH), schedule caste (SC), schedule tribes (ST) physical handicapped (Divyang)
are considered in vulnerable groups.

There are 117 vulnerable families will be affected which includes 45.30% of SC category
followed by 25.64% are Women Headed households, 22.22% of BPL and only 4.27% of ST
and 2.56% of divyang.The Entitlement matrix for this project has specific provisions for
vulnerable group and additional assistance will be provided to the households belonging to
vulnerable category. The details of the vulnerable category are given in Table 7-11.
                        Table 7-11: Categorization of vulnerable category
       Category                            No.                              Percentage
 BPL                                        26                                  22.22


 Feedback Infra Pvt. Ltd                     72              Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                    SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan




 WHH                                      30                                 25.64

 SC                                       53                                 45.30

 ST                                       5                                    4.27

 Divyang                                  3                                    2.56

 Total                                   117                                 100.00
Source: Census Survey, 2018

7.16 Literacy Status of PAHs
The social development of a region is signified by many indices. One of which is literacy status
of the population. The literacy rate (read, write and understand) in the affected households is
around 66.75%. Among the literate households one-fourth (24.75%) has achieved primary
level of education and secondary and senior secondary education is comprises 17.5%.

 As per the information collected during the census survey, it is found that the educational
level of the area reveals that overall scenario of education level is not encouraged among the
surveyed HHs as significant percentage of population i.e. 2.00% and 1.50% have completed
graduate and post graduate respectively. The details of the education of PAHs are given Table
7-12.
                     Table 7-12: Categorization of educational level of PAHs

 Education Level                                No.                Percentage

 Illiterate                                           133                       33.25
 Literate                                             16                          4
 Primary                                              99                        24.75
 Upper Primary                                        33                        8.25
 Secondary                                            44                         11
 Senior Secondary                                     26                         6.5
 Graduate                                             8                           2
 Post Graduate                                        6                          1.5
 No Information                                       35                        8.75
 Total                                                400                        100
 Literacy Rate                                                       66.75
Source: Census Survey, 2018

7.17 Occupation pattern of the family along the Project Road
The occupation pattern shows that primary sector agriculture comprises a 53.00% of the total
workers. This is followed by 24.25% of workers engaged in business and labour and service
i.e., 5.75% and 4.75% of the total workers respectively and only 3.50% of the total workers
are self employed. Details of the occupation of the project affected families are given in (Table
7-13).

 Feedback Infra Pvt. Ltd                   73               Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                                  Table 7-13: Occupation Pattern

            Sl. No.            Occupation                No.           Percentage
               1        Service                          19                4.75
               2        Business                         97               24.25
               3        Agriculture                      212              53.00
               4        Labour                           23                5.75
               5        Self Employed                    14                3.50
               6        No Information                   35                8.75
                                            Total        400               100
       Source: Census Survey, 2018

7.18 Income Level of the PAHs
The level of household income among the HHs within the RoW (Table7-14) illustrate that an
overwhelming majority, 38%, have an income level between Rs.60001 and Rs. 120000 a year
followed by 26.75% of HHs earning more than 120000 a year and 26.50% of HHs earning up
to 60000 a year. The proposed improvement will considerably reduce the travel time between
the locality and Ras, Beawar, Asind and Mandal. This will facilitate growth of more economic
activities, access to better economic prospect outside the area and hence increase the income
opportunities. Average annual household income of the affected population is given in Table
7-14.
                        Table 7-14: Annual Income of Affected household

 Sl.                                                           No of affected
         Category                                                                      %
 No.                                                           household

   1     Upto 60000 per annum                                           106             26.50
   2     More than 60000 <120000 per annum                              152             38.00
   3     More than INR 120000 per annum                                 107             26.75
   4     No Information                                                 35               8.75
                                                      Total             400              100
Source: Census Survey, 2018

7.19 Conclusion
The census survey analysis of the project affected persons reveals their dependency on the
project corridor. This dependency is either in the form of place for residence or for livelihood
generation. Affected people shall be consulted at every stage of the project planning and
implementation. Their worries and suggestions shall be taken into account and the negative
impacts shall be mitigated.




 Feedback Infra Pvt. Ltd                   74             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                                           CHAPTER - 8.: GENDER ANALYSIS
8.1   Introduction
Though the project study does not identify any particular direct adverse impacts to women
under the project, however the project during implementation and the operation phases would
identify any issues for being adopted to enhance the quality life of the women living along the
project corridor.

8.2   Women’s Participation in the Project
The gender composition of PAPs shows that the female and male ratio is having a huge
difference. The gender ratio is 851 female per 1000 male person.

The Gender Development Index (GDI) value for India is very low and the socio-economic
profile of the project area shows much lower socio-economic standing for women. They are
largely involved in domestic, agricultural work and have very low economic participation rate
(i.e. productive or gainful employment). In the project area, mostly women are housewives
and they might face hardship, stress and continue to suffer during the transition period of the
project. Often, the duration of this process is lengthened due to delays in payment of
compensation, rehabilitation assistance and implementation of the R&R., reconstructing and
placement of the livelihood systems. The longer the transition period, more are the sufferings
to the women.

8.3   Women Headed Household
Female-headed households are considered a vulnerable group as per these SIA. The
resettlement plan ensures that socio-economic conditions, needs and priorities of women in
the affected area are identified and the process of land acquisition and resettlement does not
disadvantage women. Focus groups discussions have been conducted with women along the
project areas to address their specific women’s issues. During disbursement of compensation
and provision of assistance, priority will be given to female-headed households.
However, thirty (30) households are women headed along the proposed project area. The
details of women headed households are given as an Annexure 8-1.




 Feedback Infra Pvt. Ltd                  75             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                        SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                                             CHAPTER - 9.: RESETTLEMENT BUDGET
9.1   Introduction
Compensation for Land and RR
Land will be acquired in accordance with provisions of Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 and while
determining the compensation for land, the competent authority will be guided by the
provisions of Sec 26, Sec 27, Sec 28, Sec 29 and Sec 30 of RFCTLARR Act, 2013. The
compensation includes, the multiplying factor of 1.25-2.00 times on the land value being the
higher of the guideline value or average of higher 50% of sale deed rates for the preceding 3
years or any rates consented for PPP or private projects. In addition, 100% solatium will be
added. Following are the criteria in assessing and determining the market value of the land:
Higher of

      i)           market value as per Indian Stamp Act, 1899 for the registration of sale deed or
                   agreements to sell, in the area where land is situated; or
      ii)          average sale price for similar type of land, situated in the nearest village or
                   nearest vicinity area ascertained from the highest 50% of sale deeds of the
                   preceding 3 years; or
      iii)         Consented amount paid for PPPs or private companies.


The market value in Rural areas shall be multiplied by a factor as notified by GoR . Plus 100%
solatium and 12% additional on basic market value from date of 3A notification to award. Title
holders, whose land is severed, will have the option of surrendering the severed portion of the
remaining unviable land
Agricultural land owners whose livelihood is primarily dependent on the agricultural land, who
loses 1/3rd of annual family income due to the acquisition of the said agricultural land will be
entitled for Rs.6,00,000/- as onetime payment in lieu of annuity policy.
The total RR estimated budget are Rs 234.38 Crores
                 Table 9-1: Estimated Budget for Resettlement & Rehabilitation

  A                                             Compensation for Land Acquisition
                                                   Unit of
                                                   Entitlemen
                            Particulars            t             Cost (in Rs)
                  Basic Land Rate (average         INR/Hectar
             1    DLC) (In INR)                    e                 1280400

             2    Total Private Land (in Hectare.)    in Hectare       160.2075
                  Basic Land Cost (In INR)                           205129683
             3                                        INR
                  Land cost after applying
             4    multiplication Factor               1.5            307694525
             5    Solatium @100%                      100%           307694525
                                                      12% per
             6    Additional Interest on land rate    Annum           24615562
                                                                     640004611
                  Total Land Cost (Sub-total A)

 Feedback Infra Pvt. Ltd                             76            Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –                      SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



 B                                     Compensation for Private Structure
                                                         Rate/U
                                         Unit of         nit (in   No. of            Cost (in     Remark
           Particulars                   Entitlement     Rs)       units             Rs)          s
                                                                                                  No.s
                                                                                                  Based
                                           Residential/Co                                         on
                                           mmercial/Resi                                          Census
           Permanent Structure             -cum-              80000                               survey
       6   Lumpsum @800000                 Commercial             0            284    227200000   data
                                           Residential/Co
                                           mmercial/Resi
           Semi-Permanent Structure        -cum-              60000
       7   Lumpsum @600000                 Commercial             0             45     27000000
                                           Residential/Co
                                           mmercial/Resi
           Temporary Structure             -cum-              15000
       8   @150000                         Commercial             0             29      4350000
                                           Boundary
           Permanent Structure             wall/Cattle        15000
       9   Lumpsum @150000                 Shed                   0             33      4950000
                                           Boundary
           Semi-Permanent Structure        wall/Cattle        10000
      10   Lumpsum @100000                 Shed                   0              9       900000


      11   Sub Total                             -              -          -          264400000


      12   Solatium @100%                        -              -          -          264400000
           Sub-Total B                                                                528800000

                                 Resettlement and Rehabilitation for Loss of Land
 C
                                                             Rate/U
                                           Unit of           nit (in   No. of        Cost (in     Remark
           Particulars                     Entitlement       Rs)       units         Rs)          s
                                                                                                  1402
                                                                                                  are
                                                                                                  plots
                                                                                                  and
                                                                                                  have
                                                                                                  been
                                                                                                  conside
           One time grant of Rs. 600,000   Affected           6,00,0                              red for
      13   or annuity                      Family                 00       1402       841200000   annuity




           Sub-total C                                                           841200000
 D                 Resettlement and Rehabilitation of Loss of private structure for Title Holder
                                                          Rate/U
                                        Unit of           nit (in   No. of      Cost (in       Remark
           Particulars                  Entitlement       Rs)       units       Rs)            s
                                        Each Cattle
      14   Cattle Shed                  Shed               28000            5        140000

Feedback Infra Pvt. Ltd                    77               Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –                       SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                                            Each Artisan
                                            or Self
      15   Artisan or Self Employed         Employed          28000              14       392000
           One time subsistence             Each affected
      16   allowance                        Family            40000          354        14160000
                                            Each affected
      17   One time Financial allowance     Family            60000          354        21240000
                                            Commercial
      18   Loss of Livelihood               Structure         28000              85      2380000
                                                                              38312000
           Sub-Total D
             Resettlement and Rehabilitation of Loss of Residencial/Commercial Structure to Non-
 E                                                Title Holder
                                                          Rate/U
                                         Unit of          nit (in No. of    Cost (in       Remark
           Particulars                   Entitlement      Rs)     units     Rs)            s
           One time subsistence          Each affected
      19   allowance                     Family            40000         46     1840000
           One time
           Shifting/Transportation       Each affected
      20   assistance                    Family            60000         46     2760000
                                         Commercial
      21   Loss of Livelihood            Structure         28000         46     1288000
           Sub-Total E                                                                    588800
 F                                    Additional Support to vulnerable Groups
                                                            Rate/U
                                            Unit of         nit (in  No. of           Cost (in     Remark
           Particulars                      Entitlement     Rs)      units            Rs)          s
           One time subsistence             BPL/WHH/SC/
      22   allowance                        ST/Divyang       60000         117           7020000
           Sub-total F                                                        7020000
                                Religious/Community/Government Assets (Lumpsum)
 G
                                                             Rate/U
                                            Unit of          nit (in    No. of        Cost (in     Remark
           Particulars                      Entitlement      Rs)        units         Rs)          s
           Temple Lumpsum @300000                  -          40000              23
                                                                                         9200000
      23                                                            0
           Shrine (Devsthan) Lumpsum              -           10000              69
                                                                                         6900000
      24   @100000                                                  0
           Chabutara Lumpsum                      -           10000              19
                                                                                         1900000
      25   @100000                                                  0
           Well/Handpump/Govt. Water              -           30000              46
                                                                                        13800000
      26   tank @300000                                             0
           Small water tank/Water tank            -           15000              36
           (Cattle)/Water Tap @150000                               0                    5400000
      27
           Bus Stop/Other                         -           20000              23
           Structure/Public Toilet                                  0                    4600000
      28   @200000
           School/Panchayat                       -           70000              31
           house/Tehsil/Sahkari                                   0
           samiti/Anganwadi/Community
                                                                                        21700000
           center/Power
           house/factory/ware
      29   house@700000

Feedback Infra Pvt. Ltd                    78               Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –           SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



           Pond Lumpsum @1000000              -         10000         6
                                                                             6000000
      30                                                   00
           Sub-Total G                                                      69500000
           Grand Total (In
           Rs.)(A+B+C+D+E+F+G)                                            2130724611
 H         10% contingencies                                               213072461
           Grand Total (In
                                                                          2343797072
           Cr.)(A+B+C+D+E+F+G+H)




Feedback Infra Pvt. Ltd                79            Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                       SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



            CHAPTER - 10.: INSTITUTIONAL ARRANGEMENT FOR RAP
                                              IMPLEMENTATION
Institutional arrangements for the implementation of RAP have been made fixed by making it
a part of the RPF. The Institutional Arrangements will be set up at three levels viz., MoRT&H
(Central Govt.), State Level and Sub-Project Level on partnership model wherein concerned
agencies at different levels supplement and complement each other efforts. The key elements
of institutional arrangements are co-operation/ support, collaboration and sharing of
responsibilities with clearly defined roles, involvement of key stakeholders and vertical and
horizontal linkages amongst different agencies. The institutional arrangement is discussed
below and depicted in Figure 10.1
                 Figure 10-1: Institutional Arrangement for RAP Implementation




                                    Project Authority                 Social Development
                                    CE (EAP), MoRTH                    Specialist (SDS)




                              EE (Designated Social Officer),
                                         MoRTH




     SCHM (CE)             Regional Oficer, MoRTH (Supported
                             by Land Acquisition cum Social
      (general                                                                     M&E Agency
                                 Development Officer)
       project                                                                               )
                                                                                  (Third party
       related




       GRC at
                               PIU -- AEE/AE (Designated as                        District Level
    District Level
                                      R&R Officer)                               Replacement Cost
    (R&R related
                                                                                    Committee
       issues)




                                NGO / Consultancy Firm




 Feedback Infra Pvt. Ltd                     80                 Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



10.1 Central Level
At Central Level, the Chief Engineer (EAP), MoRTH, Govt. of India will be overall responsible
for the implementation of RAP. Chief Engineer (EAP) will have all delegated administrative
and financial decisions with regard to implementation of the project as well as land acquisition
and RAP implementation. It will include further augmenting the capacity of MoRTH with regard
to resettlement and rehabilitation and management of other social issues. CE (EAP) will be
assisted by a team comprising EE designated as Social Officer and a suitable number of
technical and secretarial staff. MORTH also will engage a Social Development Specialist
(SDS) either as individual consultant or through Project Management Consultant (PMC), to
work with EAP and assist Social Officer. The EAP will be responsible for ensuring training,
guidance, and recommendations for handling policy and implementation issues at the state
and sub-project levels in compliance with RPF. The Social Development Specialist either
individually or with PMC will provide policy and strategic assistance to EAP on social issues
including land acquisition and rehabilitation and resettlement. The designated Social Officer
will be specifically responsible for implementation of RAP. The Social Officer will ensure that
all social safeguards issues are complied with as per the RPF. The roles and responsibilities
of the SDS would broadly include the following:

Institutional arrangement at Central Level will include augmenting the capacity of MoRTH with
regard to resettlement and rehabilitation. A team comprising Executive Engineer designated
as Social Development Specialist (SDS) and a suitable number of Technical and Secretarial
Staff will assist CE (EAP). The designated SDS will be directly involved in the implementation
of RAP. The SDS will ensure that all resettlement and rehabilitation issues are complied with
as per the RPF. The roles and responsibilities of the SDS would broadly include the following:

   ▪   Ensure preparation and disclosure of SIA, RAP and Land Acquisition Plan for sub
       projects as per RPF.
   ▪   Ensure adequate staffing at state and sub project level to ensure timely implementation
       of RAP.
   ▪   Guide and supervise in matters related to resettlement and rehabilitation to state and
       sub-project level offices.
   ▪   Compile data related to resettlement and rehabilitation activities received from field
       offices and update Chief Engineer (CE) and suggest suitable measures to be taken.
   ▪   Interact with implementation agencies at state and sub-project level on a regular basis.
   ▪   Undertake field visits as and when required.
   ▪   Facilitate necessary help needed at site with regard to LA and R&R issues.
   ▪   Co-ordinate with state government department in matters related to implementation of
       R&R.
   ▪   Ensure budgetary provision for resettlement and rehabilitation of PAPs and relocation,
       rehabilitation and reconstruction of common property resources (CPRs).
   ▪   Ensure timely release of budget for implementation of RAP.
   ▪   Monitor implementation of RAP carried out by the agency through RRO at subproject
       level.
   ▪   Perform other roles and responsibilities related to implementation of RAP as assigned
       by the CE (EAP) from time to time.
   ▪   Ensure free, prior and informed consultation with vulnerable groups along the project
       and also ensure that sufficient supporting documentation is maintained.
   ▪    Ensure third party audit of RAP implementation.

10.2 State Level
At State Level, a Land Acquisition cum Social Development Officer will be appointed in the
Project Coordination Unit (PCU) headed by Nodal officer. Additional sociologist as individual
 Feedback Infra Pvt. Ltd                  81             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



consultant will also be engaged to assist LA cum SDO in states as required, particularly in
states with larger share of sub projects in Rajasthan. The roles and responsibilities of the LA
cum SDO would broadly include the following:

   ▪   Facilitate preparation and implementation of land acquisition and RAP in compliance
       with RPF,
   ▪   Ensure consultation and stakeholder participation in finalization of RAP,
   ▪   Guide and supervise RAP implementation at sub-project level,
   ▪   Interact with RAP implementation support agencies and undertake field visits for first-
       hand information,
   ▪   Guide and supervise the RAP implementing agency to roll out HIV prevention activities,
   ▪   Compile data on LA progress and RAP implementation activities received from field
       offices and update EAP, MoRTH and suggest suitable measures to be taken,
   ▪   Co-ordinate with various government departments in matters related to implementation
       of RAP,
   ▪   Check implementation of RAP carried out by the agency from time to time by
       undertaking site visits and consultations with PAPs,
   ▪   Perform other roles and responsibilities related to implementation of RAP as assigned
       by the EAP, MoRTH from time to time,
   ▪   Facilitate and cooperate in Third party Audit of RAP implementation.
   ▪   Ensure a well-functioning GRM including “confidential�? handling of complaints relating
       to Gender Based Violence.

10.3 Sub-Project Level
A Project Implementation Unit (PIU) comprising officials of State PWD will be constituted at
sub- project level and headed by the Superintending Engineer/ Executive Engineer who will
be designated as Project Director. The PIU will be responsible for the project execution
including RAP implementation. There will be a designated or appointed Resettlement &
Rehabilitation Officer (RRO) at respective PIUs who will be responsible only for the
implementation of RAP at site. Additional sociologist as individual consultant will also be
engaged to assist RRO as required. RRO will assist Project Director at PIU in all matters
related to resettlement and rehabilitation. The roles and responsibilities of the Resettlement
and Rehabilitation Officer are as under:

   ▪   Ensure RAP implementation with assistance from implementation agency as per the
       time line agreed upon.
   ▪   Interact with RAP implementation agency on a regular basis.
   ▪   Undertake field visits with implementation agency from time to time.
   ▪   Co-ordinate with district administration and other departments in matters related to
       implementation of R&R.
   ▪   Facilitate necessary help needed at site with regard to LA and R&R, HIV issues to
       implementation agency.
   ▪   Ensure distribution of Resettlement and Rehabilitation Policy and entitlement matrix
       for the project to PAPs.
   ▪   Ensure preparation and distribution of photo identity cards.
   ▪   Ensure and attend meetings organised by implementation agency on thematic areas
       related to resettlement and rehabilitation policy and entitlements and awareness
       generation including aspects relating to GBV.
   ▪   Ensure inclusion of PAPs who could not be enumerated during census but have
       documentary evidence to be included in the list of PAPs.

 Feedback Infra Pvt. Ltd                  82             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –               SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



   ▪   Ensure preparation of identity cards, and approval from the PCU and distribution of the
       same to PAPs.
   ▪   Ensure timely preparation of micro-plan from RAP implementation agency and
       approval from PCU.
   ▪   Ensure disbursement of resettlement and rehabilitation assistance in a transparent
       manner.
   ▪   Participate in meetings related to resettlement and rehabilitation issues.
   ▪   Facilitate in opening of joint account of PAPs.
   ▪   Ensure release of compensation and assistance before taking over the possession of
       land for start of construction work.
   ▪   Ensure relocation, rehabilitation and reconstruction of CPRs before dismantling
       through proper mechanism.
   ▪   Ensure development of resettlement sites, where required.
   ▪   Attend and participate in Grievance Redress Committee meetings for redressal of
       grievances of PAPs and other committees involving R&R matters,
   ▪   Liaison with government and other agencies for inclusion of PAPs in employment and
       income generation programme/scheme.
   ▪   Ensure that tribal families get equal opportunity to participate during implementation
       and become overall beneficiaries in the project.
   ▪   Prepare monthly progress report related to physical and financial progress of
       implementation of RAP and submit to PCU.
   ▪   Provide all necessary information and data related to R&R on monthly basis to
       designated Social Officer at Central Level through Project Director.
   ▪   Carry out any other work related to resettlement and rehabilitation that may be
       entrusted from time to time by the PCU for compliance of R&R.

Besides, other institutional arrangements required for the implementation of RAP include
engagement of RAP IA for the implementation of RAP, formation of District level committee to
fix the replacement cost of affected properties, Grievance redressal mechanism, Suggestion
and Complaint handling mechanism, engagement of monitoring and evaluation agency, etc.
Roles and responsibilities of each agency are discussed below.

10.4 RAP Implementation Support Agency
 The Project Authority [CE(EAP), MoRTH: To implement RAP for each of the sub-project, will
engage the services of NGOs/Consultancy firms having experience in resettlement and
rehabilitation issues. Broad roles and responsibilities of implementation agency would be as:

       ▪   The RAP implementation agency will be the main link between the Project Authority
           and PAPs,
       ▪   Shall be responsible for verification of PAPs as prepared by the DPR consultants,
       ▪   Undertake public information campaign along with RRO at the commencement of
           the RAP,
       ▪   Develop rapport with PAPs,
       ▪   Distribute pamphlets of R&R Policy including Entitlement Matrix to PAPs,
           Panchayat Raj Institutions, and concerned Govt. Offices in the project area, etc.
       ▪   Include PAPs who could not be enumerated during census cum socio-economic
           survey and certification from R&R Officer,
       ▪   Distribute identity cards for PAPs,

 Feedback Infra Pvt. Ltd                 83             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



      ▪   Prepare and submit micro-plan to RRO for approval from PCU,
      ▪   Organize consultations at regular interval with PAPs with regard to resettlement and
          rehabilitation,
      ▪   Organize training program for skill up gradation of the PAPs,
      ▪   Assist PAPs in all matters related to compensation and R&R,
      ▪   Assist and facilitate aggrieved PAPs (for compensation and assistance) by bringing
          their cases to GRC,
      ▪   Facilitate in opening of joint account of PAPs,
      ▪   Generate awareness about the alternative economic livelihood and enable PAPs to
          make informed choice,
      ▪   Consultations with PAPs regarding the choice of resettlement (i.e. self or assisted),
          development of resettlement site, participation of women, etc.
      ▪   Identify training needs of PAPs for income generation and institutions for imparting
          training,
      ▪   Undertake outreach activities for HIV prevention for awareness and behaviour
          change as per RAP,
      ▪   Hold consultations with local people and Panchayat Raj Institutions with regard to
          relocation, rehabilitation, reconstruction of affected CPRs as well as provision of
          new facilities under the project,
      ▪   Participate in various meetings relating to RAP preparation and implementation,
      ▪   Submit monthly progress report, and
      ▪   Undertake any other activities that may be required for the implementation of RAP,
          etc.

10.5 Replacement Cost Committee at District Level
A committee at district level will be constituted to fix the replacement cost of land in case of
lands acquired through Direct Purchase method or Land lease, structures and other properties
(trees, crops and other assets, tube well, hand pump, etc). The committee may be chaired by
the District Collector/ Dy. Commissioner or his designated representative (not below the rank
of SDM), Project Director-cum-Executive Engineer of the concerned PIU, District Agriculture
Officer, Range Officer (Forest Department, if required), an independent certified valuer,
Executive Engineer of the concerned District, elected representative (MLA) of the concerned
area and Team Leader of RAP implementation agency.

The highest value of land obtained by the three methods mentioned in Section 26 and
Schedule 1 of RFCTLARR will be presented by the Project Authority and approved by the
committee as the replacement cost. Similarly, latest schedule of rates of the concerned
districts shall be used for obtaining replacement cost of structures. For items not available in
the schedule of rates, for those items market rates shall be collected from three different
sources and then replacement cost shall be fixed by the committee. For replacement costs of
crops, trees and other such items similar methods will be followed.

For titleholders the difference of replacement amount and the compensation paid by the
Competent Authority (CA) as per the NH Act shall be paid by the Project Authority to the
entitled persons as assistance. The differential amount will be included in the micro plan to be
prepared by the RAP IA.




 Feedback Infra Pvt. Ltd                  84             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                 SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



The committee will be constituted through an executive order and or other suitable instrument
within one month (30 days) from the date of mobilization of RAP implementation agency at
site.

10.6 Mechanism for Implementation of RAP, Training and Capacity Building –
     at Project and Sub-project Level
Training and development of project staff is an integral part for implementing GNHCP. A
training needs identification shall be carried out at Central, Regional and Site level, based on
which focused training modules will be developed in the first six months of project
implementation;

   ▪   Strengthening in house capacity to implement the provisions of RPF/RAP,
   ▪   Creating Awareness, providing the tools for implementation of RAP, and
       accompanying set of management procedures to all departments,
   ▪   Developing competence within key officials to provide training in their respective level.

Based on skill requirement/improvement at all levels for proper implementation of RPF, a
training programme focusing project implementing partners at Centre, State and field PIUs
has been developed which will be implemented by the Project Authority (MoRTH) in the next
two years. These training programs, which will be zeroed down after a quick training needs
assessment, are to be conducted with the help of local and national training institutions and
experts in various aspects of social management. MoRTH will also identify courses offered by
the premier institutions in India and abroad on social management and inter-phase these with
identified programme. There is a provision for separate budget for this activity. The budget
reported under “institutional�? head includes the cost estimates of training programs discussed
above.




 Feedback Infra Pvt. Ltd                  85             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –              SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                CHAPTER - 11.: GRIEVANCE REDRESSAL MECHANISM
The Resettlement Policy Framework (RPF) mandates formation of Grievance Redressal
Mechanism in order to resolve disputes in an effective manner and at the door steps of the
PAPs. Compensation and assistance as per eligibility is provided in the entitlement matrix of
the approved RPF. Grievance of PAPs will be brought to the grievance redress committee for
redressal. The decision of the GRC will be binding, unless vacated by court of law.

11.1 Grievance Redressal Committee (GRC)
The GRC will be constituted by the Project Authority with the aim to settle as many disputes
as possible on LA and R&R through consultations and negotiations. There will be one GRC
for each PIU. The GRC will comprise six members headed by a retired Revenue Officer/Social
Welfare Officer not below Group I officer rank. Other members of the GRC will include the
concerned Project Director-cum-Executive, a retired PWD Officer (not below the rank of
Executive Engineer), RRO, representative of PAPs and Sarpanch (Elected Head of Village)
of the concerned village.

Grievances of PAPs in writing will be brought to GRC for redressal by the RAP implementation
agency. The RAP implementation agency will provide all necessary help to PAPs in presenting
his/her case before the GRC. The GRC will respond to the grievance within 15 days. The GRC
will normally meet once in a month but may meet more frequently, if the situation so demands.
A time period of 45 days will be available for redressing the grievance of PAPs. The decision
of the GRC will not be binding to PAPs. The decision of the Grievance Committees will not
be binding on the DPs and they will have the option of taking recourse to court of law,
if he/she so desires at his or her own expense. Broad functions of GRC are as under:

   ▪       Record the grievances of PAPs, categorize and prioritize them and provide solution
           to their grievances related to resettlement and rehabilitation assistance.

   ▪       The GRC may undertake site visit, ask for relevant information from Project
           Authority and other government and non-government agencies, etc, in order to
           resolve the grievances of PAPs. Fix a time frame within the stipulated time period
           of 45 days for resolving the grievance.

   ▪       Inform PAPs through implementation agency about the status of their case and
           their decision to PAPs and Project Authority for compliance.

   ▪       In case of grievances/complaints relating to GBV, ensure confidentiality and
           appropriate referral to mapped service providers


The GRC will be constituted within 3 months by an executive order from competent authority
(centre/ state) from the date of mobilization of RAP implementation agency. The RRO will
persuade the matter with assistance from implementation agency in identifying the suitable
persons from the nearby area for the constitution of GRC. Secretarial assistance will be
provided by the PIU as and when required.




 Feedback Infra Pvt. Ltd                 86            Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                   SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                    Figure 11-1: Grievance Redressal Mechanism

                                    Grievance Redressal Mechanism


                                       BROAD FUNCTION


         RECORD,
             ,                UNDERSTAND
                              UNDERTAK                 Fix a time         CONVEY
         CATEGORIZE           EFIELD
                                FIELDVISITS,,          frame to           DECISION
         AND                     ASKSASK
                              VISITS, FOR              resolve the        OF GRC TO
         PRIORITIZE           FOR                      grievance          PAPS IN
         GRIEVANCES           RELEVANT                 within             WRITING
                              PAPERS ETC               stipulated
                                       P R O     C E   S S
                              AS                       time period
                              REQUIRED
                                    GRIE                             PIU CO-ORDINATES
                                                                           -
         DECISION OF                                                 WITH GRC AND PAPS
         GRC MEETING IS             VAN
         DRAFTED                     CE
        GRC MINUTES                 RED                ME              NGO INITIATES
        PREPARED AND                                   ETI              NECESSARY
         GRC DECISIONS
        SIGNED  BY
                                    GRIEV              NG             PREPARATION TO
         CONVEYED TO
        MEMBERS
                                    ANCE               OR
         PAPS IN                                                        RRO CHECK
                                     NOT               GA
         WRITING
       GRC DECISION                                                    GRIEVANCE &
                                    REDRE                             CATEGORIZE AND
       SENT TO PA/EA
       FOR
       INFORMATION                                                       PAPS LODGE
       ANDBACK TO RRO                OPTION TO                        GRIEVANCE TO PIU
          FOR
       COMPLIANCE                    MOVE COURT                      DIRECTLY OR TO R&R
          IMPLEMENTATI
          ON
        NGO TO INITIATE               PAPS                             POTENTIAL
        ACTI ON                       GRIEVANC                         GRIEVANCES OF
                                      E MET                            PAPS


PAPs will be fully made aware about the GRM for effective, inexpensive and amicable
settlement of claims for compensation and assistance by holding meetings with PAPs, public
meetings and distributing leaflets containing salient features and procedures of GRM. The
RAP IA will assist the PAPs in getting their record of rights updated in case of disputes related
to land. The RRO with support from RAP IA will make all possible efforts for amicable
settlement. The RAP IA will document all cases brought to GRC and maintain the records of
the proceedings of the grievance redressal committee meetings.

11.2 Suggestion and Complaint Handling Mechanism (SCHM)
The MoRTH recognizes the importance of this and hence intends to establish a SCHM for the
GNHCP. The communication channels to report project related complaints/concerns will be
disclosed at all levels of institutions—MoRTH, State and Sub-project levels.



 Feedback Infra Pvt. Ltd                   87                Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                   SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



Though the Right to Information Act, 2005 an Act of the Parliament of India provides for setting
out the practical regime of right to information for citizens. The Act applies to all States and
Union Territories of India except the State of Jammu and Kashmir. Under the provisions of the
Act, any citizen may request information from a "public authority" (a body of Government or
"instrumentality of State") which is required to reply expeditiously or within thirty days. The Act
also requires every public authority to computerize their records for wide dissemination and to
proactively publish certain categories of information so that the citizens need minimum
recourse to request for information formally. In other words, under the act, citizens have right
to seek information from concerned agencies by following the set procedures. However, it is
quite likely that many people may not use the provisions of this Act, only in limited cases
covering serious concerns. Being an inter-state project involving several states and large scale
of civil works along with R&R and Environment issues, the project is likely to receive many
suggestions, complaints, inquiries, etc through the project implementation period. Therefore,
MoRTH has agreed to establish SCHM as a good practice to address public concerns
pertaining to various issues. SCHM will report all project related LA and R&R of the PAPs for
redressal through the concerned PIU or GRC as appropriate. Several communication
channels viz., toll free phone number, dedicated email, mechanism for on line submission of
suggestions/complaints/inquiries, provision of suggestion/complaint box (at site and project
office), post and other suitable means shall be set up for suggestion and complaint handling.


11.3 Training and Capacity Building – at Project and Sub-project Level
Training and development of project staff is an integral part of project implementation. A
training needs identification shall be carried out at Corporate, Regional and Site level, based
on which focused training modules will be developed in the first six months of project
implementation;
    ➢ Strengthening in house capacity to implement the provisions of RAP,
    ➢ Creating awareness, providing the tools for implementation of RAP, strategy and
        accompanying set of management procedures to all departments,
    ➢ Developing competence of key officials to provide training at respective level.
Based on skill requirement/improvement at all levels for proper implementation of RAP, a
training programme focusing project implementing partners at Centre, State and field PIU has
been developed (Annexure-12) which will be implemented by the PMU, MoRTH in the next
two years. These training programs, which will be zeroed down after a quick training needs
assessment, are to be conducted with the help of local and national training institutions and
experts in various aspects of social management. MoRTH will also identify courses offered by
the premier institutions in India and abroad on social management and inter-phase with
identified programme. Provision for separate budget has been made for this activity. The
budget reported under “institutional�? head includes the cost estimates of training programs
discussed above.

11.4 Monitoring and Evaluation (M&E) at Project and Sub-project Level

38.     The Resettlement Action Plan will contain indicators and benchmarks for achievement
of the objectives under the resettlement programme. These indicators and benchmarks will
be of three kinds: i) Proposed indicators, indicating project inputs, expenditures, staff
deployment, etc. ii) Output indicators, indicating results in terms of numbers of affected
persons compensated and resettled, training held, credit disbursed, etc, iii) Impact indicators,
related to the longer-term effect of the project on people’s lives.




 Feedback Infra Pvt. Ltd                   88              Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                  SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



The benchmarks and indicators will be limited in number and combine quantitative and
qualitative types of data. Some of these indicators may include, percentage of PAPs actually
paid compensation before any loss of assets; percentage of PAPs whose incomes after
resettlement are better than, or at least same as before resettlement; percentage of assets
valued at replacement cost compensation; percentage grievances resolved; and/or
percentage of cases to court. The first two types of indicators, related to process and
immediate outputs and results, will be monitored to inform project management about
progress and results, and to adjust the work programme where necessary if delays or
problems arise. The results of this monitoring will be summarized in reports which will be
submitted to the World Bank on a regular basis. Provision will be made for participatory
monitoring involving the project affected persons and beneficiaries of the resettlement
programme in assessing results and impacts. The Project Authority will engage services of an
external agency (third party), which will undertake independent concurrent evaluations at least
twice a year during the project implementation period. At the end of the project, an impact
evaluation will be carried out as part of the project completion report. Such independent
evaluation will focus on assessing whether the overall objectives of the project have been met
and will use the defined impact indicators as a basis for evaluation. Specifically, the evaluation
will assess: (i) The level of success (including the constraints and barriers) in land acquisition
programme, resettlement plan, and income recovery of the PAPs after they have been
displaced from the project affected area, and, (ii) the types of complaints/ grievances and the
success of the handling of grievance and public complaints towards the construction of
project’s infra-structures, means of redress for assets and lands and the amount of
compensation, resettlement, and other forms of complaints.

Summarizing, M&E would be carried out for regular assessment of both process followed and
progress of the RAP implementation. The internal monitoring will be carried out by the State
PCU by the LA cum SDO with assistance from NGO/Consultancy firm and a quarterly report
will be submitted to MoRTH. Each quarterly report would also be uploaded on the MoRTH
website. The external agency (third party) however, would conduct assessment annually for
each sub-project by undertaking field visits and all other necessary activities including
consultations. The annual reports would cover detailed information on process and progress
of RAP implementation. The report would highlight issues, if any that need attention of the
Project Authority and suggest corrective measures that may be followed for better
implementation of RAP.




 Feedback Infra Pvt. Ltd                   89             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                      SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan



                              CHAPTER - 12.: IMPLEMENTATION SCHEDULE
12.1 Coordination with civil works and certification
Implementation of RAP will include land acquisition, and resettlement and rehabilitation (R&R)
activities. The implementation process will cover (i) identification of cut-off date and
notification; (ii) verification of properties of PAPs and estimation of their type and level of losses
and distribution of identity cards; (iii) preparation of PAPs for relocation through consultation,
however, the process of consultation will continue throughout the RAP implementation and
(iv) relocation and resettlement of the PAPs.
Implementation schedule should be revised, post-finalization of entitlements, compensation
packages and the budget. This should depend on the magnitude of work to be undertaken as
part of RAP implementation. PAPs should be given sufficient notice period to vacate their
property before civil works begins. No civil works should begin until all PAPs receive the
approved compensation package. Civil works should therefore be linked with the completion
of land acquisition. In this case, all land transfers from Government have to be completed.
Depending on the ownership, PIU should coordinate the DC’s office and the Revenue
Department. A draft Implementation Schedule is given in Table 12.1, subject to change after
revalidation of RAP.
It is assumed that implementation will take minimum 36 months to hand over land for civil
works. Training for income restoration, if proposed, however shall continue for another month,
estimating a total period for RAP implementation




 Feedback Infra Pvt. Ltd                     90              Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras – Beawar                                                 SIA & RAP
– Asind – Mandal Section of NH-158 in the State of Rajasthan

                                      Table 12-1: Implementation Schedule of Resettlement Plan

                                                    2019                       2020                         2021               2022
              Activities
                                          1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12       1

Project Preparation Stage


Screening project impact

Public Consultation on alignment

Updating the affected family
information
Initiation of the implementation of the
RP activities
RP Implementation Stage

Obtain RP approval from MORTH

Disclosure of RP

Hiring NGO for RP Implementation

Formation of GRC (Grievance
Mechanism)

Implementation of GRC




Feedback Infra Pvt. Ltd                                    91                                    Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras – Beawar                                                 SIA & RAP
– Asind – Mandal Section of NH-158 in the State of Rajasthan


                                                     2019                       2020                        2021               2022
              Activities
                                           1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12      1

Public Consultation

Co-ordination with district authority
for LA

Submission of LA proposals to DC

Declaration of cut-off date (LA
notification)

Payment of compensation

Taking procession of acquired land

Handling over the acquired land to
contractor
Notify the date of construction start to
DPs

Income Restoration Program

Awareness Training

Rehabilitation of DPs

Monitoring and Reporting Period



Feedback Infra Pvt. Ltd                                     92                                   Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras – Beawar                                           SIA & RAP
– Asind – Mandal Section of NH-158 in the State of Rajasthan


                                                  2019                       2020                     2021               2022
              Activities
                                     1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12      1

Internal monitoring and reporting

Hiring Construction Supervision
Consultant

External monitoring and reporting




Feedback Infra Pvt. Ltd                                   93                               Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –               SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan


                   CHAPTER - 13.: MONITORING & EVALUATION (M & E)
Monitoring and evaluation are important activities of infrastructure development project
particularly, those involving involuntary resettlement. It helps making suitable changes, if
required during the course of implementation of RAP and also to resolve problems faced by
the PAPs. Monitoring is periodical checking of planned activities and provides midway inputs,
facilitates changes, if necessary and provides feedback to project authority for better
management of the project activities. Evaluation on the other hand assesses the resettlement
effectiveness, impact and sustainability of R&R activities. In other words, evaluation is an
activity aimed at assessing whether the activities have actually achieved their intended goals
and purposes. Thus monitoring and evaluation of resettlement action plan implementation are
critical in order to measure the project performance and fulfillment of project objectives.

The monitoring and evaluation of RAP implementation will ensure monitoring of key indicators
on inputs, outputs, project processes and evaluation of impact indicators. The overall purpose
of the monitoring is to keep track of the implementation processes and progress, achievement
of performance targets fixed in the annual work plans, learning lessons and taking corrective
actions to deal with emerging constraints and issues. Monitoring and evaluation will constitute
the following:

   ▪   Implementation progress (physical and financial aspects), monitoring of inputs, and
       outputs;
   ▪   Process documentation (case studies and lessons learnt);
   ▪   Impact evaluation based on sample survey and consultations; and
   ▪   Thematic studies.

13.1 Institutional Arrangement for M & E
The Resettlement Policy Framework (RPF) stipulates hiring services of an external agency
(third party) for monitoring and evaluation of RAP implementation. This means the project
authority through an external agency will carry out monitoring and evaluation from the
subsequent month of the mobilization of RAP IA at project site. Internal monitoring will be
carried out by the Social Officer of Project Coordination Unit (PCU) with assistance from R&R
officer and RAP IA whereas external monitoring and evaluation will be carried by the third
party engaged for the purpose. This will help monitor project activities closely. Regular
monitoring by undertaking site visits and consultations with PAPs will help identify potential
difficulties and problems faced in the implementation and accordingly help take timely
corrective measures including deviations, if needed.

Components of monitoring will include performance monitoring i.e., physical progress of the
work and impact monitoring and external evaluation. Indicative indicators to be monitored
related to performance are provided in the following sections. In case during the project
implementation, if some other indicators are found relevant they will also be considered for
monitoring.

13.2 Monitoring and Evaluation (M&E) at Project and Sub-project Level
The Resettlement Action Plan contains indicators and benchmarks for achievement of the
objectives under the resettlement programme. These indicators and benchmarks will be of
three kinds:

   1) Proposed indicators, indicating project inputs, expenditures, staff deployment, etc.

   2) Output indicators, indicating results in terms of numbers of affected People
      compensated and resettled, training held, credit disbursed, etc,


 Feedback Infra Pvt. Ltd                  94             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                  SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan

      3) Impact indicators, related to the longer-term effect of the project on People’s lives.

The benchmarks and indicators will be limited in number, and combine quantitative and
qualitative types of data. Some of these indicators may include, percentage of PAPs actually
paid compensation before any loss of assets; percentage of PAPs whose incomes after
resettlement are better than, or at least same as before resettlement; percentage of assets
valued at replacement cost compensation; percentage grievances resolved; and/or
percentage of cases to court. The first two types of indicators, related to process and
immediate outputs and results, will be monitored to inform project management about
progress and results, and to adjust the work programme where necessary if delays or
problems arise. The results of this monitoring will be summarized in reports which will be
submitted to the World Bank on a regular basis. Provision will be made for participatory
monitoring involving the project affected people and beneficiaries of the resettlement
programme in assessing results and impacts. The Project Authority will engage services of an
external agency (third party), which will undertake independent concurrent evaluations at least
twice a year during the project implementation period. At the end of the project an impact
evaluation will be carried out as part of the project completion report. Such independent
evaluation will focus on assessing whether the overall objectives of the project are being met
and will use the defined impact indicators as a basis for evaluation. Specifically, the evaluation
will assess: (i) The level of success (including the constraints and barriers) in land acquisition
programme, resettlement plan, and income recovery of the PAPs after they have been
displaced from the project affected area, and, (ii) the types of complaints/ grievances and the
success of the handling of grievance and public complaints towards the construction of
project’s infra-structures, means of redress for assets and lands and the amount of
compensation, resettlement, and other forms of complaints.

Summarizing, M&E would be carried out for regular assessment of both the process followed
and progress of the RAP implementation. The internal monitoring will be carried out by the
State PCU by the Land Acquisition cum Social Development Officer with assistance from RAP
Implementation Support Agency and a quarterly report will be submitted to MoRTH. Each
quarterly report would also be uploaded on the MoRTH website. The external agency (third
party) however, would conduct assessment six monthly for each sub-project by undertaking
field visits and all other necessary activities including consultations. The six monthly reports
would cover detailed information on process and progress of RAP implementation. The report
would highlight issues, if any that need attention of the Project Authority and suggest corrective
measures that may be followed for better implementation of RAP.

13.3 Process & Performance Monitoring
Process monitoring would enable the project authority to assess whether the due process are
being followed or not, whereas performance monitoring would mainly relate to achievement in
measurable terms against the set targets. Monitoring report will also provide necessary
guidance and inputs for any changes, if required during the course of the implementation. A
list of indicators is given in Table 13.1.
                   Table 13-1: Performance Monitoring for RAP Implementation

 Sr.                                                                          Achievement
                           Indicators                      Target   Status                Remarks
 No.                                                                             (in %)
         Land acquisition (Private)
  1
         Notification published u/s 3D
         Award declared u/s ……. for
         Land area (ha)


 Feedback Infra Pvt. Ltd                     95             Public Works Department, Rajasthan
Feasibility Report cum Preliminary Design for Up-gradation of Ras –              SIA & RAP
Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan


Sr.                                                                        Achievement
                          Indicators                     Target   Status               Remarks
No.                                                                           (in %)
      Land owners (No.)
      Compensation disbursed by           Competent
      Authority to land owners (No.)
      Govt. land transfer (ha)
      Verification of identified PAPs completed
 2
      (No.)
      New PAPs added, if any (who could not
 3
      be enumerated at the time of survey)
      Consultations held with regard to RAP
 4
      (dissemination of information, awareness
      generation, entitlements, HIV/ AIDS, SCHM,
      etc) – No.
      Leaflets, containing salient features of RAP,
 5
      hand bills, fliers and other awareness
      materials distributed (No.)
      Measurement of structures likely to be
 6
      affected completed (No.)
      Date of formation of DLC
 7
      Meetings held by DLC for fixing the
 8
      replacement cost (No.)
      Valuation of affected properties completed
 9
      (No.)
      Micro plan submitted for THs for approval
10
      (No.)
      Identity cum entitlement card issued to PAPs
11
      (No.)

      Consultations held with local community
12
      regarding relocation or rehabilitation of CPRs
      (No.)
      Estimate       submitted     for     relocation/
13
      rehabilitation of CPRs for approval
      Agency to carryout relocation/ rehabilitation of
14
      CPRs as agreed by the project authority
      R&R assistances disbursed to PAPs (THs –
15
      No.
      PAPs re-established their shops/ business
16
      (No.)
      PAPs covered under income generation
17
      schemes (No.)
      PAPs provided training for alternate livelihood
18
      (No.)
      CPRs relocated/ rehabilitated (No.)
19
      Grievance/ complaints brought to GRC for
20
      redressal (No.)
21    GRC meeting held and cases resolved (No.)
22    Various channels of SCHM used by category
      (No.)


Feedback Infra Pvt. Ltd                   96             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –                   SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan


 Sr.                                                                           Achievement
                      Indicators                            Target   Status                Remarks
 No.                                                                              (in %)
 23 Consultation meetings held by LA cum SDO
     of Project Coordination Unit (PCU) (No.)

13.4 Evaluation
The external agency engaged by the Project Authority shall carry out the evaluation at two
stages viz., mid-term and after the completion of RAP implementation. The evaluation will be
carried out under a set term of reference. The evaluation study would involve both quantitative
and qualitative surveys and compare results before and after the implementation of the project.
It will focus on assessing whether the overall objectives of the project are being met and will
use the defined impact indicators as a basis for evaluation. The evaluation study would
undertake the following but not limited to:

      ▪   Review monthly progress report submitted by RAP Implementation Agency (RAP IA);
      ▪   Undertake consultations with PAPs in order to assess their point of view with regard to
          overall process;
      ▪   Intensity and effectiveness of information dissemination with regard to RAP
          implementation covering eligibility of different categories of PAPs, frequency of
          interactions by RAP IA personnel with PAPs, deployment of RAP IA staff, quality of
          rapport maintained by RAP IA personnel with PAPs, capability of RAP IA personnel,
          behavior of RAP IA staff, availability of RAP IA staff, level of satisfaction as regards
          the work of RAP IA, etc;
      ▪   Collect information about distribution of awareness generation materials, entitlements,
          distribution of identity cum entitlement card, adequacy of dissemination of information,
          consultations meetings with regard to policy and eligibility for entitlement, alternatives
          and relocation related issues, measurement and valuation of affected properties,
          understanding and use of grievance procedure, disbursement of assistance, and other
          R&R related issues, compliance of resettlement policy, etc;
      ▪   Conduct sample survey (25% of PAPs) for making comparative analysis substantiated
          by qualitative surveys and case studies, etc.

It may be noted that one of the key objectives of the project is improvement or at least
restoration of economic status of the PAPs to the pre project level. An illustrative list of
indicators is given in Table 13.2, which would be measured against the baseline data collected
for the preparation of RAP. The M&E agency would finally select the indicators for the
evaluation of the project depending upon the progress of R&R activities.
                                     Table 13-2: Impact Indicators
                                                                                           During/after
 Sr.                                                                  Before Project
                         Indicator                        Unit                                RAP
 No.                                                                 Implementation
                                                                                         Implementation

  1       Monthly income of family/household

  2       Consumer durables/material Assets
          owned

  3       Ownership of Transport and farm
          implements owned



 Feedback Infra Pvt. Ltd                      97             Public Works Department, Rajasthan
 Feasibility Report cum Preliminary Design for Up-gradation of Ras –             SIA & RAP
 Beawar – Asind – Mandal Section of NH-158 in the State of Rajasthan

                                                                                    During/after
 Sr.                                                            Before Project
                      Indicator                      Unit                              RAP
 No.                                                           Implementation
                                                                                  Implementation

  4    Occupation of head of Household and
       other members

  5    Type of dwelling units

  6    Number of Earning
       members/households

  7    Family under debt

  8    Size of loan

  9    Households purchased loans

 10    Households with various sizes of land

 11    Ownership/tenancy of dwelling units
       (owner, encroacher, squatter)

 12    Access to water and sanitation facilities

 13    Access to modern sources of lighting
       and cooking

 14    Animal and poultry birds owned

 15    Migration for employment

13.5 Reporting
Monthly Progress Reports on the progress of RAP implementation including mobilization of
staff members, opening of site offices, etc of the project would be prepared by RAP IA and
submitted to the R&R Officer at sub-project level.

Quarterly Monitoring Reports shall be compiled by the LA cum SDO of Project Coordination
Unit (PCU) and submitted to MoRTH for review and onward submission to World Bank

Six monthly reports shall be prepared by the M&E agency by undertaking site visits and review
of progress report, consultations, etc.

Evaluation Report shall be prepared by the M&E agency at the end of the project
implementation as part of the project completion report.




 Feedback Infra Pvt. Ltd                   98          Public Works Department, Rajasthan