Public Disclosure Copy

        The World Bank                                                                                Implementation Status & Results Report
        Mato Grosso do Sul State Road Transport Project (P118410)


Mato Grosso do Sul State Road Transport Project (P118410)

LATIN AMERICA AND CARIBBEAN | Brazil | Transport & ICT Global Practice |
IBRD/IDA | Specific Investment Loan | FY 2010 | Seq No: 11 | ARCHIVED on 15-Jan-2016 | ISR21837 |


Implementing Agencies: AGESUL




Key Dates

  Key Project Dates

  Bank Approval Date:04-May-2010                                               Effectiveness Date:23-Nov-2010
  Planned Mid Term Review Date:15-Oct-2012                                     Actual Mid-Term Review Date:24-Oct-2012
  Original Closing Date:30-Jun-2015                                            Revised Closing Date:30-Jun-2016




Project Development Objectives

 Project Development Objective (from Project Appraisal Document)
 The Project development objective is to improve the efficiency of the Borrower#s road network in the Project area. Efficiency improvement is
 expected as a result of the Project#s financial support to selected investments of the state investment program in road infrastructure and to activities
 that seek to strengthen the State Government#s overall capacity to manage the road network, including planning preparation, execution and
 monitoring of work programs at the administrative, engineering and environment levels. Efficiency gains are expected to result in inter alia improved
 accessibility and safety, and reduced logistics costs.


 Has the Project Development Objective been changed since Board Approval of the Project Objective?
 No

 PHRPDODEL



Components

Name
State Road Rehabilitation and Surfacing:(Cost $290.00 M)
Institutional Strengthening:(Cost $10.00 M)



Overall Ratings
Name                                                                         Previous Rating                           Current Rating

Progress towards achievement of PDO                                           Satisfactory                             Satisfactory
Overall Implementation Progress (IP)                                          Satisfactory                             Satisfactory
Overall Risk Rating                                                           --                                       Low



1/15/2016                                                                                                                                  Page 1 of 7
                                                           Public Disclosure Copy
                                                            Public Disclosure Copy

        The World Bank                                                                                Implementation Status & Results Report
        Mato Grosso do Sul State Road Transport Project (P118410)



Implementation Status and Key Decisions

 Project implementation is satisfactory. Works have been executed in an efficient fashion and institutional strengthening activities, while slightly delayed,
 continue with satisfactory implementation.




Risks

 Systematic Operations Risk-rating Tool

 Risk Category                                               Rating at Approval                Previous Rating              Current Rating

 Political and Governance                                     --                               --                          Moderate
 Macroeconomic                                                --                               --                          Moderate
 Sector Strategies and Policies                               --                               --                          Low
 Technical Design of Project or Program                       --                               --                          Low
 Institutional Capacity for Implementation and
 Sustainability
                                                              --                               --                          Low
 Fiduciary                                                    --                               --                          Low
 Environment and Social                                       --                               --                          Moderate
 Stakeholders                                                 --                               --                          Moderate

1/15/2016                                                                                                                                   Page 2 of 7
                                                            Public Disclosure Copy
                                                                Public Disclosure Copy

               The World Bank                                                                              Implementation Status & Results Report
               Mato Grosso do Sul State Road Transport Project (P118410)


 Other                                                             --                               --                          --
 Overall                                                           --                               --                          Low


Results

 Project Development Objective Indicators
 PHINDPDOTBL




          Reduction of operating costs to vehicle users, per average vehicle-km on state network (Percentage, Custom)


                                                Baseline                        Actual (Previous)          Actual (Current)              End Target

         Value                                  0.00                            --                         --                            -5.00

         Date                                   31-Dec-2008                     01-Nov-2013                31-Dec-2015                   30-Jun-2016


         Comments
         The Pavement Management System, which will be able to provide vehicle operating costs, is currently under development. The results for
         this indicator will be available in the next ISR.



 PHINDPDOTBL




          Increase in use of road transport infrastructure on Project surfaced roads (Percentage, Custom)


                                                Baseline                        Actual (Previous)          Actual (Current)              End Target

         Value                                  0.00                            --                         --                            15.00

         Date                                   31-Dec-2008                     01-Nov-2013                31-Dec-2015                   30-Jun-2016


         Comments
         This indicator is still being computed, based on the now finalized updated traffic surveys on Project roads. While the indicator is not
         finalized, we anticipate that this indicator wil be reached.




 PHINDPDOTBL




          Roads in good and fair condition as a share of total classified roads (Percentage, Core)


                                                Baseline                        Actual (Previous)          Actual (Current)              End Target

         Value                                  49.00                           81.03                      82.00                         66.00

         Date                                   31-Dec-2008                     01-Nov-2013                30-Jun-2015                   30-Jun-2016




1/15/2016                                                                                                                                          Page 3 of 7
                                                                Public Disclosure Copy
                                                                   Public Disclosure Copy

                   The World Bank                                                                          Implementation Status & Results Report
                   Mato Grosso do Sul State Road Transport Project (P118410)


 Overall Comments
 Based on the road condition survey in 2015.


 Intermediate Results Indicators
 PHINDIRITBL




              Roads rehabilitated, Non-rural (Kilometers, Core)

                                                    Baseline                     Actual (Previous)         Actual (Current)           End Target

               Value                                0.00                         975.07                    1252.00                    1200.00

               Date                                 01-Jun-2010                  29-Jan-2014               31-Dec-2015                30-Jun-2016


               Comments
               As of the end of 2015, 799km and 453km have been rehabilitated and surfaced respectively.
               As regards rehabilitation works, MS164 (34.2+39.0 km) and MS240 (85.8 km) were assessed elligible - technical, economic, safeguards.
               As regards surfacing works, MS080 (10.1 km), MS316 (15.8 km), MS135 (15.9 km) and MS112 (28.7 + 29.2 + 28.9 km) were assessed
               elligible - technical, economic, safeguards.



 PHINDIRITBL




              Roads rehabilitated (Kilometers, Custom Breakdown)

                                                    Baseline                     Actual (Previous)         Actual (Current)           End Target

               Value                                --                           --                        799.00                     700.00

               Date                                 --                           --                        31-Dec-2015                30-Jun-2016




 PHINDIRITBL




              Roads paved (Kilometers, Custom Breakdown)

                                                    Baseline                     Actual (Previous)         Actual (Current)           End Target

               Value                                --                           --                        453.00                     450.00

               Date                                 --                           --                        31-Dec-2015                30-Jun-2016




1/15/2016                                                                                                                                       Page 4 of 7
                                                                   Public Disclosure Copy
                                                                     Public Disclosure Copy

                   The World Bank                                                                             Implementation Status & Results Report
                   Mato Grosso do Sul State Road Transport Project (P118410)

 PHINDIRITBL




              Pilot of a result-based maintenance and rehabilitation contract implemented (CREMA) in AGESUL (Yes/No, Custom)

                                                     Baseline                       Actual (Previous)         Actual (Current)            End Target

               Value                                 N                              Y                         Y                           Y

               Date                                  01-Jun-2010                    01-Nov-2013               31-Dec-2015                 30-Jun-2016


               Comments
               The CREMA is under contract on MS-276/480.


 PHINDIRITBL




              Integrated monitoring and evaluation system of state investments and/or spending in SEMAC (Yes/No, Custom)

                                                     Baseline                       Actual (Previous)         Actual (Current)            End Target

               Value                                 N                              Y                         Y                           Y

               Date                                  01-Jun-2010                    01-Nov-2013               31-Dec-2015                 30-Jun-2016


               Comments
               The Financial Planning system (Sistema de Planejamento Financeiro, SPF) has been rolled out within the State administration.


 PHINDIRITBL




              Modern management tools in AGESUL (Text, Custom)

                                                     Baseline                       Actual (Previous)         Actual (Current)            End Target

                                                     Lack of sufficient
               Value                                                                --                        1                           2
                                                     management tools

               Date                                  01-Jun-2010                    01-Nov-2013               31-Dec-2015                 30-Jun-2016


               Comments
               The indicator is partially met, for now: the first tool (KRONOS) has already been rolled out, while the second system (Pavement
               Management System) is currently under finalization. We anticipate that this indicator will be reached.




1/15/2016                                                                                                                                        Page 5 of 7
                                                                     Public Disclosure Copy
                                                                       Public Disclosure Copy

                   The World Bank                                                                              Implementation Status & Results Report
                   Mato Grosso do Sul State Road Transport Project (P118410)

 PHINDIRITBL




              Consolidated environmental management tools in IMASUL (Yes/No, Custom)

                                                        Baseline                     Actual (Previous)         Actual (Current)              End Target

               Value                                    N                            N                         Y                             Y

               Date                                     01-Jun-2010                  01-Nov-2013               31-Dec-2015                   30-Jun-2016


               Comments
               Georferencing system rolled out.


 PHINDIRITBL




              Integrated road management system operational in AGESUL (Text, Custom)

                                                        Baseline                     Actual (Previous)         Actual (Current)              End Target

                                                        No Pavement                                                                          PMS
               Value                                                                 --                        PMS not operational
                                                        Management System                                                                    operational

               Date                                     01-Jun-2010                  --                        31-Dec-2015                   30-Jun-2016


               Comments
               The database of the road conditions and traffic survey is ready. The model has been developped and is currently being tested. The
               Pavement Management System is expected t be operational in March 2016




 Overall Comments



 Data on Financial Performance

Disbursements (by loan)

 Project                 Loan/Credit/TF     Status          Currency      Original   Revised     Cancelled    Disbursed      Undisbursed                   Disbursed

 P118410                 IBRD-78720         Effective       USD             300.00    300.00           0.00         298.43            1.57                         99%


Key Dates (by loan)
 Project                 Loan/Credit/TF     Status          Approval Date     Signing Date     Effectiveness Date     Orig. Closing Date     Rev. Closing Date

 P118410                 IBRD-78720         Effective       04-May-2010       16-Sep-2010      23-Nov-2010            30-Jun-2015            30-Jun-2016



Cumulative Disbursements



1/15/2016                                                                                                                                            Page 6 of 7
                                                                       Public Disclosure Copy
                                                    Public Disclosure Copy

        The World Bank                                                                    Implementation Status & Results Report
        Mato Grosso do Sul State Road Transport Project (P118410)




 Restructuring History

 Level Approved on 11-Sep-2012 ,Level 2 Approved on 10-Sep-2014 ,Level 2 Approved on 29-Jun-2015




 Related Project(s)

There are no related projects.




1/15/2016                                                                                                              Page 7 of 7