Procurement Plan I. General 1. Project Information Project Name: Third Educational Emergency Project ( TEEP ) Country: IRAQ Project ID: P096234 Credit Number: 4128 IQ 2. Bank's approval date of Procurement Plan Original 2-Apr-07 Revision 1 15-Apr-09 Revision 2 20-Aug-09 3. Date of General Procurement Notice II. Goods, Work and Non-Consulting Services Thresholds 1. Prior Review Threshold 1a. Procurement Category Prior Review Threshold (USD) Comments Goods $ 100,000 Works $ 1,500,000 Non-Consultant Services $ - Include all categories authorized by the loan agreement 1b. Procurement Method Procurement Method Threshold (USD) Comments ICB (Goods) NCB (Goods) $ 200,000 Shopping (Goods) $ 100,000 ICB (Works) $ 10,000,000 NCB (Works) $ 2,500,000 ICB (Non-Consultant Services) $ - Include all methods authorized by the loan agreement 3. Reference to (if any) Project Operational/Procurement Manual: 4. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable 5. Procurement Packages with Methods and Time Schedule: See attached "Goods and Works" shee III. Selection of Consultants 1. Prior Review Threshold 1a. Procurement Category Prior Review Threshold (USD) Comments Consulting Firms (Competitive) $ 200,000 Consulting Firms (Sole Source) all Individual Consultants (Competitive) $ 50,000 Individual Consultants (Sole Source) all 1b. Procurement Method Procurement Method Threshold (USD) Comments QCBS $ - QCB $ - FCS $ - LCS $ - CQS $ 200,000 Consulting Firms (Competitive) $ - Consulting Firms (Sole Source) $ - Individual Consultants (Competitive) $ - Individual Consultants (Sole Source) $ - ICB (Non-Consultant Services) $ - IV. Implementing Agency Capacity Building Activities with Time Schedule IRAQ Comp I Works A Third Emergency Educational Project Procurement Plan 1 2 3 4 5 6 7 8 9 10 12 14 16 18 20 22 24 26 28 29 30 31 34 Submission / Readiness Date Review By Bank (Prior /Post) Plan (P) / Revised (R)/ Actual Procurement System Ref. # Secondary 18 Classrooms Secondary 24 Classrooms No. of Schools Involved Evaluation & Recomm. Primary 12 Classrooms Primary 18 Classrooms Procurement Method Bid Opening Date Completion Date No. of Contracts Invitation Date WB NOL Date WB NOL Date Signing Date Start Date Sl. # (A) Description Contractor Name Addrress Site Address Comments A B C D E F G H I J K L N O P Q R S T U V W X Y AB Component I ( School Construction ) 1.1 WORKS 1.1.1 Construction of New Schools - Phase I 1 P W01-I Bab-18Cr.Sec-Ph-I NCB Prior 1 1 1 18-Jan-10 01-Feb-10 08-Feb-10 08-Mar-10 29-Mar-10 12-Apr-10 10-May-10 24-May-10 22-Aug-11 Al-Ahad Engineering Babel Al-Kifil 2 R/P 18-Jan-10 16-Aug-10 01-Sep-10 30-Sep-10 31-Oct-10 14-Nov-10 30-Nov-10 15-Dec-10 30-Nov-12 Iraq – Hala , Street40 Co. m45 lot no 1/106 3 A 1 1 1 12-Aug-10 16-Aug-10 01-Sep-10 30-Sep-10 09-Feb-11 17-Feb-11 04-May-11 10-Jul-11 Bag/K2- 4P W02-I NCB Prior 1 1 2 1 18-Jan-10 01-Feb-10 08-Feb-10 08-Mar-10 29-Mar-10 12-Apr-10 10-May-10 24-May-10 22-Aug-11 18Cr.Sec+12Cr.Pri- Baghdad.k2 Al- NAHAJ AL- Iraq – Baghdad ,Ù? New 5 R 31-Dec-12 Amiriyah m18 HADHARA CO. Baghdad lot no 6/6584 6 A 1 1 1 2 18-Feb-10 23-Feb-10 25-Feb-10 25-Mar-10 09-Jun-10 10-Jun-10 04-Aug-10 07-Sep-10 Bas- 7P W03-I NCB Prior 1 1 2 1 18-Jan-10 07-Jan-00 04-Feb-00 25-Feb-00 10-Mar-00 07-Apr-00 21-Apr-00 20-Jul-01 Iraq – Basrah- 18Cr.Sec+18Pri.-Ph- Al-Salem Co.&Wael Basrah Al- Ashar/Iraq-Basrah- 8 R 15-Nov-12 Hassan Abdul Hartha Kol'yan Ashar- Opposite to Raheem Co. m13 lot no 9 9 A 1 1 1 2 18-Feb-10 23-Feb-10 25-Feb-10 25-Mar-10 09-Jun-10 10-Jun-10 11-Aug-10 13-Oct-10 sport club 10 P W04-I Nin-18Cr.Pri-Ph-I NCB Prior 1 1 1 18-Jan-10 01-Feb-10 08-Feb-10 08-Mar-10 29-Mar-10 12-Apr-10 10-May-10 24-May-10 22-Aug-11 Nay'nawa 11 R 25-Sep-12 Aswar Qasser Iraq – Mosul ,Ù? New Kojaka m52 lot Nenave Co. Mosul no 5/900 12 A 1 1 1 18-Feb-10 23-Feb-10 25-Feb-10 25-Mar-10 09-Jun-10 10-Jun-10 26-Sep-10 10-Nov-10 17-Sep-12 Bag/R1-12Cr.Pri-Ph- 13 P W05-I NCB Prior 1 1 1 18-Jan-10 01-Feb-10 08-Feb-10 08-Mar-10 29-Mar-10 12-Apr-10 10-May-10 24-May-10 22-Aug-11 Iraq – Baghdad I Al-Afnan Al-Kadraa Baghdad.R1 Al- ,Plaestine Street , 14 R 01-Mar-12 General Contracting Thaalbah m9 lot Near Al-Sakhra Ltd. no 8/11371 15 A 1 1 1 18-Feb-10 23-Feb-10 25-Feb-10 28-Mar-10 26-May-10 10-Jun-10 11-Aug-10 24-Oct-10 01-Mar-12 Restaurant Bag/R2-18Cr.Pri-Ph- 16 P W06-I NCB Prior 1 1 1 18-Jan-10 01-Feb-10 08-Feb-10 08-Mar-10 29-Mar-10 12-Apr-10 10-May-10 24-May-10 22-Aug-11 Baghdad I Beza'yez Al- 17 R Cancelled cancelled Fdailiyah m15 18 A 1 lot no 4/302 Bag/R3-12Cr.Pri-Ph- Al BALOOR Iraq – Baghdad Baghdad.R3 Al- 19 P W07-I NCB Prior 1 1 1 18-Jan-10 01-Feb-10 08-Feb-10 08-Mar-10 29-Mar-10 12-Apr-10 10-May-10 24-May-10 22-Aug-11 I Engineering Co. ,Karada,Arkheta Wazeeriyah Al- 20 R 01-Jul-12 RAWAT AL BROOJ /Iraq – Baghdad Sader City Co. ,Karada Sector 16 m4 lot 21 A 1 1 1 18-Feb-10 23-Feb-10 25-Feb-10 28-Mar-10 26-May-10 10-Jun-10 11-Aug-10 17-Oct-10 30-Jul-12 no 4/13520 22 P W08-I Dew-18Cr.Sec-Ph-I NCB Prior 1 1 1 18-Jan-10 01-Feb-10 08-Feb-10 08-Mar-10 29-Mar-10 12-Apr-10 10-May-10 24-May-10 22-Aug-11 Iraq – Baghdad Deewaniyah Al- Al-Hassnawi ,Plaestine Street , Shamiyah ( Abu 23 R 30-Oct-12 Co.Trade&General Near Sharjah Al-Fedhil ) m23 Contracting 24 A 1 1 1 18-Feb-10 23-Feb-10 25-Feb-10 28-Mar-10 26-May-10 10-Jun-10 11-Aug-10 18-Oct-10 Exchange lot no 2/6402 25 P W09-I Dew-18Cr.Sec-Ph-I NCB Prior 1 1 1 18-Jan-10 01-Feb-10 08-Feb-10 08-Mar-10 29-Mar-10 12-Apr-10 10-May-10 24-May-10 22-Aug-11 Iraq – Baghdad Deewaniyah Al-Hassnawi ,Plaestine Street , Sader Al- 26 R 30-Jun-12 Co.Trade&General Near Sharjah Yousifiyah m18 Contracting 27 A 1 1 1 18-Feb-10 23-Feb-10 25-Feb-10 28-Mar-10 26-May-10 10-Jun-10 11-Aug-10 18-Oct-10 18-Jul-12 Exchange lot no 22/7514 The original 28 P W10-1 Kar-12Cr.Pri-Ph-I NCB Prior 1 1 1 18-Jan-10 01-Feb-10 08-Feb-10 08-Mar-10 29-Mar-10 12-Apr-10 10-May-10 24-May-10 22-Aug-11 bidding process was terminated on 23-Nov-11 Karbalah Hay Al- and the Bank 29 R 18-Feb-10 23-Feb-10 25-Feb-10 30-Mar-10 04-May-10 Retender, Bank No Objection 30-Nov-11 30-Jun-13 Amarat Al-Andalus Co Iraq - Karbalah Wafaa m61 lot gave no no 3/25154 objection to Retender on 30- Nov-12 and change the review process NonAsciiFileName0.xls Page 2 of 19 12/3/2012 3:25 AM IRAQ Comp I Works A Third Emergency Educational Project Procurement Plan Submission / Readiness Date Review By Bank (Prior /Post) Plan (P) / Revised (R)/ Actual Procurement System Ref. # Secondary 18 Classrooms Secondary 24 Classrooms No. of Schools Involved Evaluation & Recomm. Primary 12 Classrooms Primary 18 Classrooms Procurement Method Bid Opening Date Completion Date No. of Contracts Invitation Date WB NOL Date WB NOL Date Signing Date Start Date Sl. # (A) Description Contractor Name Addrress Site Address Comments The original bidding process was terminated on 23-Nov-11 Karbalah Hay Al- and the Bank Amarat Al-Andalus Co Iraq - Karbalah Wafaa m61 lot gave no A B C D E F G H I J K L N O P Q R S T U V W X no 3/25154 Y objection AB to Retender on 30- Nov-12 and 30 A 1 Post 1 1 24-Nov-11 30-Nov-11 13-Dec-11 11-Jan-12 18-Jan-11 N/A 08-Mar-12 01-Apr-12 change the review process The original 31 P W11-I Naj-18Cr.Sec-Ph-I NCB Prior 1 1 1 18-Jan-10 01-Feb-10 08-Feb-10 08-Mar-10 29-Mar-10 12-Apr-10 10-May-10 24-May-10 22-Aug-11 bidding process was terminated on 23-Nov-11 Najef Al-Jazeera and the Bank 32 R 18-Feb-10 23-Feb-10 25-Feb-10 30-Mar-10 04-May-10 Retender, Bank No Objection 30-Nov-11 21-Jul-13 Abwab Al-Uolaa Co., Iraq - Najaf Al-Risalah m4 gave no lot no 3/10996 objection to Retender on 30- Nov-12 and 33 A 1 Post 1 1 24-Nov-11 30-Nov-11 13-Dec-11 11-Jan-12 18-Jan-11 N/A 08-Mar-12 16-Apr-12 change the review process 34 P W12-I Was-18Cr.Sec-Ph-I NCB Prior 1 1 1 18-Jan-10 01-Feb-10 08-Feb-10 08-Mar-10 29-Mar-10 12-Apr-10 10-May-10 24-May-10 22-Aug-11 Iraq – Baghdad Wassit Al- HIBAT AL-FORAT ,Ù? Saadoon St , 35 R 10-Feb-12 Hifriyah lot no COMPANY Opposite to Palestine 3/416 36 A 1 1 1 18-Feb-10 23-Feb-10 25-Feb-10 30-Mar-10 06-Jun-10 10-Jun-10 11-Aug-10 19-Sep-10 18-Feb-12 Hotel 37 P W13-I Was-12Cr.Pri-Ph-I NCB Prior 1 1 1 18-Jan-10 01-Feb-10 08-Feb-10 08-Mar-10 29-Mar-10 12-Apr-10 10-May-10 24-May-10 22-Aug-11 Iraq – Baghdad Al-Afnan Al-Kadraa Wassit Al- ,Plaestine Street , 38 R 08-Feb-12 General Contracting So'wairah m26 Near Al-Sakhra Ltd. lot no 3/2533 39 A 1 1 1 18-Feb-10 23-Feb-10 25-Feb-10 30-Mar-10 06-Jun-10 10-Jun-10 30-Aug-10 19-Sep-10 08-Feb-12 Restaurant 40 P Subtotal 1.1.1 5 3 7 15 13 41 R/P 42 A 5 2 7 14 12 43 44 1.1.2 Construction of New Schools - Phase II 60 P W14-I WAS-24Cr.Sec-Ph-II NCB Prior 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 Al-Bahar Al-Abiadh Wassit Al- Iraq – Baghdad, Hay R 12-Feb-13 General Contracting Falahiah lot no Al-Sa'adoon Co. Ltd 1/2020/ 46 A 1 1 23-Mar-11 24-Mar-11 08-May-11 05-Jun-11 22-Aug-11 06-Sep-11 17-Oct-11 15-Nov-11 48 P W15-I ANB1-12Cr.Pri-Ph-II NCB Post 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 Al-Najem Al-Thahaby Anbar Haswat Co. for General Iraq – Baghdad , Al 49 R 24-Aug-13 Al-Shamiah lot Trading and Contracts Harthea no. 83/ 19524/47 50 A 1 1 23-Mar-11 24-Mar-11 11-Apr-11 09-May-11 17-Aug-11 N/A 26-Sep-11 22-Nov-11 Ltd 63 P W16-I ANB2-12Cr.Pri-Ph-II NCB Post 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 Anbar Jbalih Al- Soor Dubai Co. for Iraq – Baghdad , Al 64 R 22-Aug-13 Kharab lot no. 9/ General Contracting Mansur 4611/1 65 A 1 1 23-Mar-11 24-Mar-11 11-Apr-11 09-May-11 17-Aug-11 N/A 26-Sep-11 22-Nov-11 60 P W17-I MUT1-18Cr.Pri-Ph-II NCB Post 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 Al-Khuld Co. for Muthana Abu 61 R 08-Oct-13 General Contracting Iraq – Al Muthana Mahaar lot no. Ltd 58/475/37 62 A 1 1 23-Mar-11 24-Mar-11 11-Apr-11 09-May-11 17-Aug-11 N/A 17-Oct-11 21-Nov-11 90 P W18-I NAJ-12Cr.Pri-Ph-II NCB Prior 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 Al-Hadeel Co. for Najaf Hay Al- Haytham Azeez 91 R 08-Oct-13 General Contracting Jamea'a lot no. Aalewe Businesses Ltd 3/26991/4 92 A 1 1 23-Mar-11 24-Mar-11 11-Apr-11 09-May-11 27-Sep-11 12-Oct-11 26-Dec-11 01-Feb-12 BAB1-24Cr.Sec-Ph- Babel Hay Al- 51 P W19-I NCB Prior 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 II Jamea'a Al- Hawks of Iraq group 52 R 18-Jan-14 Iraq – Baghdad for General Contracts Wasiah lot no. 53 A 1 1 23-Mar-11 24-Mar-11 20-Apr-11 18-May-11 27-Nov-11 30-Nov-11 07-Feb-12 19-Mar-12 24/13044/11 BAB2-18Cr.Sec-Ph- 54 P W20-I NCB Prior 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 II Al-Hadeel Co. for Babel Moelha Haytham Azeez 55 R 18-Oct-13 General Contracting Hay Al-A'alam Aalewe Businesses Ltd lot no. 12/211/10 56 A 1 1 23-Mar-11 12-Apr-11 20-Apr-11 18-May-11 27-Sep-11 12-Oct-11 26-Dec-11 01-Feb-12 NonAsciiFileName0.xls Page 3 of 19 12/3/2012 3:25 AM IRAQ Comp I Works A Third Emergency Educational Project Procurement Plan Submission / Readiness Date Review By Bank (Prior /Post) Plan (P) / Revised (R)/ Actual Procurement System Ref. # Secondary 18 Classrooms Secondary 24 Classrooms No. of Schools Involved Evaluation & Recomm. Primary 12 Classrooms Primary 18 Classrooms Procurement Method Bid Opening Date Completion Date No. of Contracts Invitation Date WB NOL Date WB NOL Date Signing Date Start Date Sl. # (A) Description Contractor Name Addrress Site Address Comments A B C D E F G H I J K L N O P Q R S T U V W X Y AB BAG.K3-18Cr.Pri- Baghdad K3 Hay 54 P W21-I NCB Post 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 Ph-II Iraq – Baghdad-Al- Al-Salam Al- 55 R 31-Mar-14 Al-Gharbia Co. Ltd Mansur Tubche lot no 56 A 1 1 23-Mar-11 N/A 11-Apr-11 09-May-11 17-Aug-11 N/A 17-Oct-11 14-Nov-11 12/129/21 BAG.K2-18Cr.Pri- 66 P W22-I NCB Post 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 Ph-II Al-Bahar Al-Abiadh Baghdad Abu Iraq – Baghdad, Hay 67 R 31-Mar-14 General Contracting Dsher lot no Al-Saadon Co. Ltd 3/5768/10 68 A 1 1 23-Mar-11 N/A 20-Apr-11 18-May-11 22-Aug-11 N/A 17-Oct-11 14-Nov-11 BAG.K3-12Cr.Pri- 69 P W23-I NCB Post 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 Ph-II Fakhar Al-Rafidain Baghdad k3 Al- Iraq – Baghdad, Al- 70 R 30-Nov-12 Co. for General Sabiyat lot no Karida Contracts 1/1235/22 71 A 1 1 23-Mar-11 N/A 28-Apr-11 26-May-11 22-Aug-11 N/A 26-Sep-11 10-Oct-11 MUT2-24Cr.Sec-Ph- 78 P W24-I NCB Prior 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 Muthana Al- II Al-Bahar Al-Abiadh Iraq – Baghdad, Hay Rumaitha AM Al- 79 R 13-Jan-14 General Contracting Al-Sa'adoon Khael lot no. Co. Ltd 80 A 1 1 23-Mar-11 28-Mar-11 28-Apr-11 26-May-11 22-Aug-11 06-Sep-11 17-Oct-11 21-Nov-11 65/684/26 BAG.R3-12Cr.Pri- 81 P W25-I NCB Post 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 Ph-II Baghdad R3 Al- Iraq – Baghdad-Al- 82 R 15-Feb-14 Al-Gharbia Co. Ltd Wazeeriyah lot Mansur no 4/31735/38 83 A 1 1 23-Mar-11 N/A 11-Apr-11 09-May-11 17-Aug-11 N/A 17-Oct-11 21-Nov-11 84 P W26-I DIY1-12Cr.Pri-Ph-II NCB Post 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 Fager Diyalah Co. for Iraq – Diyala, Diyalah Abu 85 R 23-Aug-13 General Contracts Baagooba Jasrah 1/488/4 86 A 1 1 23-Mar-11 N/A 20-Apr-11 18-May-11 22-Aug-11 N/A 19-Oct-11 24-Nov-11 BAG.R2-12Cr.Pri- Qaser Al-A Shique 75 P W27-I NCB Post 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 Ph-II General Contracts Baghdad R2 Al- Iraq – Baghdad, Al- 76 R 20-Aug-13 Co. & Janat Al- Zua'afraniyah lot Bab Al-Sharke Morouge General no 1/666/2 77 A 1 1 23-Mar-11 N/A 20-Apr-11 18-May-11 22-Aug-11 N/A 17-Oct-11 21-Dec-11 Contracts Co. 57 P W28-I BAS-12Cr.Pri-Ph-II NCB Post 1 1 1 23-Mar-11 30-Mar-11 20-Apr-11 18-May-11 08-Jun-11 15-Jun-11 22-Jun-11 29-Jun-11 26-Sep-12 Basrah Al-Rebat 58 R 04-Mar-14 Al-Salem Co. Iraq –Al-Basra Al-Kabeer 2219/1880 59 A 1 1 23-Mar-11 N/A 28-Apr-11 26-May-11 22-Aug-11 N/A 17-Oct-11 27-Nov-11 BAG.K1-24Cr.Sec- 45 P W29-I NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Ph-II Baghdad K1 46 R 05-Jan-14 Al-Addai Co. Iraq – Baghdad Abu Gharieb lot no 15/1026/9 47 A 1 1 N/A N/A 31-Oct-11 29-Nov-11 13-Dec-11 N/A 07-Feb-12 18-Mar-12 BAG.K1-24Cr.Sec- 57 P W30-I NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Ph-II Baghdad K1 58 R 24-Dec-13 Al-Hadifa Co. Iraq – Baghdad Kharnabat lot no 1/307/13 59 A 1 1 N/A N/A 31-Oct-11 29-Nov-11 13-Dec-11 N/A 07-Feb-12 04-Mar-12 BAG.R2-18Cr.Pri- 87 P W31-I NCB Prior 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Baghdad R2 Ph-II Waldaiyah- 88 R 22-Jan-14 Majeed Jabbar Co. Iraq – Baghdad Imnesief lot no 89 A 1 1 N/A N/A 31-Oct-11 29-Nov-11 13-Dec-11 N/A 07-Feb-12 04-Mar-12 3/3533/20 93 P W32-I KER-18Cr.Pri-Ph-II NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Karkuk Hay Al- Wasity Tesa'an 94 R 30-Dec-13 Shabra Co. Ninawa- Iraq lot no. 95 A 1 1 N/A N/A 31-Oct-11 29-Nov-11 13-Dec-11 N/A 07-Feb-12 04-Mar-12 393/662/39 NonAsciiFileName0.xls Page 4 of 19 12/3/2012 3:25 AM IRAQ Comp I Works A Third Emergency Educational Project Procurement Plan Submission / Readiness Date Review By Bank (Prior /Post) Plan (P) / Revised (R)/ Actual Procurement System Ref. # Secondary 18 Classrooms Secondary 24 Classrooms No. of Schools Involved Evaluation & Recomm. Primary 12 Classrooms Primary 18 Classrooms Procurement Method Bid Opening Date Completion Date No. of Contracts Invitation Date WB NOL Date WB NOL Date Signing Date Start Date Sl. # (A) Description Contractor Name Addrress Site Address Comments A B C D E F G H I J K L N O P Q R S T U V W X Y AB 96 P W33-I DIY-12Cr.Pri-Ph-II NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Diyalah Al- 97 R 19-Nov-13 Noor Al-Sana Co. Iraq – Baghdad Luqmaniyah 12/3539/4 98 A 1 1 N/A N/A 31-Oct-11 29-Nov-11 13-Dec-11 N/A 07-Feb-12 05-Mar-12 99 P W34-I THI3-24Cr.Sec-Ph-II NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 04-Apr-13 Tareeq Al-Namaa Co. Thiqar Al-Shatra 100 R 14-Apr-14 for general Iraq – Al Muthana lot no. 8/15465 contracting limited 101 A 1 1 N/A N/A 21-Nov-11 20-Dec-11 29-Dec-11 N/A 08-Mar-12 05-Mar-12 54 P W35-I THI-24Cr.Sec-Ph-II NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Tareeq Al-Namaa Co. Thiqar Suq Al- 55 R 14-Apr-14 for general Iraq – Al Muthana Shiuakh lot no. contracting limited 5/494 56 A 1 1 N/A N/A 21-Nov-11 20-Dec-11 29-Dec-11 N/A 08-Mar-12 22-Mar-12 57 P W36-I SAL-18Cr.Sec-Ph-II NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Salah Al-Dien Wadi Sheshien 58 R 29-Dec-13 Al-Ta'aer Al-Hurre Co. Iraq – Baghdad lot no. 59 A 1 1 N/A N/A 31-Oct-11 29-Nov-11 13-Dec-11 N/A 07-Feb-12 27-Feb-12 10/10072/5 72 P W37-I NIN-18Cr.Sec-Ph-II NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Ninawa Hay Al- 73 R 26-Dec-13 Al-Shimal Co. Ninawa- Iraq Arabi Ba'auerah lot no. 43/9/37 74 A 1 1 N/A N/A 31-Oct-11 29-Nov-11 13-Dec-11 N/A 07-Feb-12 10-Mar-12 102 P W38-I Nin-18Cr.Sec-Ph-II NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Nin.Ninawa Al- Sharqia Hay Al- 103 R 22-Apr-14 Asia Al-Safraa Co., Iraq-Ninawa Wahda lot no. 104 A 1 1 N/A N/A 13-Dec-11 11-Jan-12 17-Jan-12 N/A 08-Mar-12 15-Mar-12 (152/5-286/12)/40 BAG.R1-18Cr.Pri- 105 P W39-I NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Ph-II Baghdad R1 Al- 106 R 24-Apr-14 Al-Awael Co Iraq-Baghdad Thaalba lot no. 8/11379/9 107 A 1 1 N/A N/A 13-Dec-11 11-Jan-12 17-Jan-12 N/A 08-Mar-12 22-Mar-12 96 P Subtotal 1.1.2 9 6 4 7 26 8 97 R 98 A 9 6 4 7 26 99 100 1.1.3 Construction of New Schools - Phase III 101 P W40-I Bas-18Cr.Sec-Ph-III NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Al-Salem Co.&Wael Basrah Al-Rebat 102 R 24-Apr-14 Hassan Abdul Iraq - Basrah Al-Kabeer Raheem Co. 2313/2319 103 A 1 1 N/A N/A 13-Dec-11 11-Jan-12 17-Jan-12 N/A 14-Mar-12 02-May-12 104 P W41-I Kar-18Cr.Pri-Ph-III NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Karbala Al- Al-Kanet Co.for Jazerah Hay Al- 105 R 28-Dec-13 general contraction Iraq – Baghdad Salam lot no. limited 106 A 1 1 N/A N/A 21-Nov-11 20-Dec-11 29-Dec-11 N/A 07-Feb-12 12-Mar-12 3/17039 107 P W42-I Kar-18Cr.Pri-Ph-III NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Karbala Al- Al-Kanet Co.for Jazerah Hay Al- 108 R 14-Apr-14 general contraction Iraq – Baghdad Melad lot no. limited 3/29223/61 NonAsciiFileName0.xls Page 5 of 19 12/3/2012 3:25 AM IRAQ Comp I Works A Third Emergency Educational Project Procurement Plan Submission / Readiness Date Review By Bank (Prior /Post) Plan (P) / Revised (R)/ Actual Procurement System Ref. # Secondary 18 Classrooms Secondary 24 Classrooms No. of Schools Involved Evaluation & Recomm. Primary 12 Classrooms Primary 18 Classrooms Procurement Method Bid Opening Date Completion Date No. of Contracts Invitation Date WB NOL Date WB NOL Date Signing Date Start Date Sl. # (A) Description Contractor Name Addrress Site Address Comments Karbala Al- Al-Kanet Co.for Jazerah Hay Al- A B C D E F G H I J K L N O P Q R S T U V general contraction W Iraq – Baghdad X Y no. AB Melad lot limited 109 A 1 1 N/A N/A 21-Nov-11 20-Dec-11 29-Dec-11 N/A 07-Feb-12 11-Mar-12 3/29223/61 110 P W43-I Ker-12Cr.Pri-Ph-III NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Jibal Al-Shimal Co. 111 R 07-Jan-14 for general Iraq – Baghdad Kerkuk Taza 383/566/41 contracting limited 112 A 1 1 N/A N/A 21-Nov-11 20-Dec-11 29-Dec-11 N/A 07-Feb-12 07-Mar-12 113 P W44-I Thi-24Cr.Sec-Ph-III NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Thiqar Jazerah 114 R 14-Apr-14 Al-Awael Co Iraq - Thiqar lot no. 110/21019 115 A 1 1 N/A N/A 13-Dec-11 11-Jan-12 17-Jan-12 N/A 08-Mar-12 04-Apr-12 116 P W45-I Mis-18Cr.Sec-Ph-III NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Missan 117 R 29-Mar-14 Wafa’a Baghdad Co. Iraq - Missan Magharaba lot no. 55/7686/2 118 A 1 1 N/A N/A 13-Dec-11 11-Jan-12 17-Jan-12 N/A 08-Mar-12 05-Apr-12 119 P W46-I Naj-18Cr.Sec-Ph-III NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 03-Apr-13 Najaf Hay Al- 120 R 27-Jan-14 Al-Ikdam Co. Iraq – Baghdad Intesar lot no. 2/9193/2 121 A 1 1 N/A N/A 21-Nov-11 20-Dec-11 29-Dec-11 N/A 07-Feb-12 07-Mar-12 Fadaa Al-Kawaser 119 P W47-I Anb-12Cr.Pri-Ph-III NCB Post 1 1 1 01-Jul-11 15-Jul-11 22-Jul-11 02-Sep-11 23-Sep-11 07-Oct-11 21-Oct-11 04-Nov-11 01-Feb-13 Anbar Hadetha Co. for General 120 R 30-Jul-13 Contracting Limited & Iraq – Baghdad Al-Khasfa lot no. Zain Al-Diar Co. for 204/700/52 121 A 1 1 N/A N/A 21-Nov-11 20-Dec-11 29-Dec-11 N/A 07-Feb-12 26-Mar-12 General Trading and 122 123 R TBD 124 A 125 P Subtotal 1.1.3 2 3 2 1 8 8 126 R 127 A 2 3 2 1 8 128 P Sub total for Works 1.1 16 12 13 8 49 29 129 R 130 A 16 11 13 8 48 29 131 P Total for Component I (School Construction) 132 R 192 198 234 192 133 A 390 426 NonAsciiFileName0.xls Page 6 of 19 12/3/2012 3:25 AM IRAQ Comp I Works B Third Emergency Educational Project Procurement Plan 1 2 3 4 9 10 12 13 14 16 18 20 22 24 26 28 29 30 31 34 Submission / Readiness Date Review By Bank (Prior /Post) Plan (P) / Revised (R)/ Actual Procurement System Ref. # No. of Schools Involved Evaluation & Recomm. Procurement Method Bid Opening Date Completion Date No. of Contracts Invitation Date WB NOL Date WB NOL Date Signing Date Interval /a Start Date Contractor Sl. # (A) Description Addrress Site Address Comments Name A B C D E F K L N O P Q R S T U V W X Y AB Component I ( School Construction ) 1.1 WORKS 1.1.4 Construction of of Six Classroom & Toilet units Bas 3 Six CR 1 P W50-I NCB Post 3 1 N/A N/A 20-Jan-13 17-Feb-13 10-Mar-13 N/A 21-Apr-13 05-May-13 30-Jan-14 Unit+ Toilet Unit 2 R/P 3 A 1 Mis 3 Six CR 4P W51-I NCB Post 3 1 N/A N/A 20-Jan-13 17-Feb-13 10-Mar-13 N/A 21-Apr-13 05-May-13 30-Jan-14 Unit+ Toilet Unit 5 R 6 A 1 Mut 3 Six CR 7P W52-I NCB Post 3 1 N/A N/A 20-Jan-13 17-Feb-13 10-Mar-13 N/A 21-Apr-13 05-May-13 30-Jan-14 Unit+ Toilet Unit 8 R 9 A 1 Thi 3 Six CR Unit+ 10 P W53-I NCB Post 3 1 N/A N/A 20-Jan-13 17-Feb-13 10-Mar-13 N/A 21-Apr-13 05-May-13 30-Jan-14 Toilet Unit 11 R 12 A 1 Bab 3 Six CR 13 P W54-I NCB Post 3 1 N/A N/A 17-Feb-13 17-Mar-13 07-Apr-13 N/A 19-May-13 02-Jun-13 27-Feb-14 Unit+ Toilet Unit 14 R 15 A 1 Dew 3 Six CR 16 P W55-I NCB Post 3 1 N/A N/A 17-Feb-13 17-Mar-13 07-Apr-13 N/A 19-May-13 02-Jun-13 27-Feb-14 Unit+ Toilet Unit 17 R 18 A 1 Kar 3 Six CR 19 P W56-I NCB Post 3 1 N/A N/A 17-Feb-13 17-Mar-13 07-Apr-13 N/A 19-May-13 02-Jun-13 27-Feb-14 Unit+ Toilet Unit 20 R 21 A 1 Naj 3 Six CR Unit+ 22 P W57-I NCB Post 3 1 N/A N/A 17-Feb-13 17-Mar-13 07-Apr-13 N/A 19-May-13 02-Jun-13 27-Feb-14 Toilet Unit 23 R 24 A 1 NonAsciiFileName0.xls Page 7 of 19 12/3/2012 3:25 AM IRAQ Comp I Works B Third Emergency Educational Project Procurement Plan Submission / Readiness Date Review By Bank (Prior /Post) Plan (P) / Revised (R)/ Actual Procurement System Ref. # No. of Schools Involved Evaluation & Recomm. Procurement Method Bid Opening Date Completion Date No. of Contracts Invitation Date WB NOL Date WB NOL Date Signing Date Interval /a Start Date Contractor Sl. # (A) Description Addrress Site Address Comments Name A B C D E F K L N O P Q R S T U V W X Y AB Was 3 Six CR 25 P W58-I NCB Post 3 1 N/A N/A 17-Feb-13 17-Mar-13 07-Apr-13 N/A 19-May-13 02-Jun-13 27-Feb-14 Unit+ Toilet Unit 26 R 27 A 1 Bag K1 2 Six CR 28 P W59-I NCB Post 2 1 N/A N/A 10-Mar-13 07-Apr-13 28-Apr-13 N/A 09-Jun-13 23-Jun-13 20-Mar-14 Unit+ Toilet Unit 29 R/P 30 A 1 Bag K2 2 Six CR 31 P W60-I NCB Post 2 1 N/A N/A 10-Mar-13 07-Apr-13 28-Apr-13 N/A 09-Jun-13 23-Jun-13 20-Mar-14 Unit+ Toilet Unit 32 R 33 A 1 Bag K3 2 Six CR 34 P W61-I NCB Post 2 1 N/A N/A 10-Mar-13 07-Apr-13 28-Apr-13 N/A 09-Jun-13 23-Jun-13 20-Mar-14 Unit+ Toilet Unit 35 R 36 A 1 Bag R1 2 Six CR 37 P W62-I NCB Post 2 1 N/A N/A 10-Mar-13 07-Apr-13 28-Apr-13 N/A 09-Jun-13 23-Jun-13 20-Mar-14 Unit+ Toilet Unit 38 R 39 A 1 Bag R2 2 Six CR 40 P W63-I NCB Post 2 1 N/A N/A 10-Mar-13 07-Apr-13 28-Apr-13 N/A 09-Jun-13 23-Jun-13 20-Mar-14 Unit+ Toilet Unit 41 R 42 A 1 Bag R3 2 Six CR 43 P W64-I NCB Post 2 1 N/A N/A 10-Mar-13 07-Apr-13 28-Apr-13 N/A 09-Jun-13 23-Jun-13 20-Mar-14 Unit+ Toilet Unit 44 R 45 A 1 Anb 3 Six CR 46 P W65-1 NCB Post 3 1 N/A N/A 10-Mar-13 07-Apr-13 28-Apr-13 N/A 09-Jun-13 23-Jun-13 20-Mar-14 Unit+ Toilet Unit 47 R 48 A 1 Diy 3 Six CR Unit+ 49 P W66-I NCB Post 3 1 N/A N/A 10-Mar-13 07-Apr-13 28-Apr-13 N/A 09-Jun-13 23-Jun-13 20-Mar-14 Toilet Unit 50 R 51 A 1 Sal 3 Six CR Unit+ 52 P W67-I NCB Post 3 1 N/A N/A 07-Apr-13 05-May-13 26-May-13 N/A 07-Jul-13 21-Jul-13 17-Apr-14 Toilet Unit 53 R NonAsciiFileName0.xls Page 8 of 19 12/3/2012 3:25 AM IRAQ Comp I Works B Third Emergency Educational Project Procurement Plan Submission / Readiness Date Review By Bank (Prior /Post) Plan (P) / Revised (R)/ Actual Procurement System Ref. # No. of Schools Involved Evaluation & Recomm. Procurement Method Bid Opening Date Completion Date No. of Contracts Invitation Date WB NOL Date WB NOL Date Signing Date Interval /a Start Date Contractor Sl. # (A) Description Addrress Site Address Comments Name A B C D E F K L N O P Q R S T U V W X Y AB 54 A 1 Ker 3 Six CR 55 P W68-I NCB Post 3 1 N/A N/A 07-Apr-13 05-May-13 26-May-13 N/A 07-Jul-13 21-Jul-13 17-Apr-14 Unit+ Toilet Unit 56 R 57 A 1 Nin 3 Six CR Unit+ 58 P W69-I NCB Post 3 1 N/A N/A 07-Apr-13 05-May-13 26-May-13 N/A 07-Jul-13 21-Jul-13 17-Apr-14 Toilet Unit 59 R 60 A 61 P Sub total for Works 1.1.4 54 20 62 R 63 A NonAsciiFileName0.xls Page 9 of 19 12/3/2012 3:25 AM IRAQ Comp I Services Third Emergency Educational Project Procurement Plan 1 2 3 4 6 7 8 10 12 14 16 18 20 22 24 26 28 30 31 32 33 36 Final Evaluation, contract award No Objection Date to issue RFP Expected Proposal Submission Invitation for RFPs/RFQs Date Plan (P) / Revised (R)/ Actual submission /Readiness Date Review by Bank Prior / Post & contract negotiation date No Objection Date to sign Technical Evaluation date Contract Signature Date No. of Schools Involved Advertisement EOI or Short Listing & RFP No Objection Date Selection Method Completion Date No. of Contracts to short list Procureme Start Date contract Date nt Sl. # (A) Description Consultant Name Addrress Site Address Comments System Ref. # A B C D E F H I J K L M N O P Q R S T U V W X AA 1 1.2. CONSULTANTS' SERVICES Component I & Sub Component I 2 1.2.1.1-a Services for Supervision of New Schools Ph-I (Cancelled) 2 1.2.1.1-b Services for Supervision of New Schools Ph-I Baghdad Al- 3 P C62-I SUP Bag-Ph-I 5 1 QCBS Prior 14-Dec-09 18-Jan-10 1-Feb-10 8-Feb-10 8-Mar-10 15-Mar-10 29-Mar-10 12-Apr-10 26-Apr-10 3-May-10 10-May-10 2-Nov-11 Amiriyah m18 lot TECHNICAL no 6/6584 __ STUDIES Baghdad Al- Hassib Salih BUREAU, Thaalbah m9 lot Building, Nidhal 4 R 4 1 7-Apr-10 13-Apr-10 15-Apr-10 15-May-10 26-May-10 1-Jun-10 10-Jun-10 21-Dec-10 28-Dec-10 4-Jan-11 28-Jun-12 Architects, no 8/11371 __ Street, Baghdad, Planners, Baghdad Al- Iraq Managements, Wazeeriyah Al- and Construction Sader City 5 A 1 4 1 10-Feb-10 6-Jun-10 10-Jun-10 12-Jun-10 26-Sep-10 24-Oct-10 27-Oct-10 20-Dec-10 21-Dec-10 16-Jan-11 2-Feb-11 Sector 16 m4 lot no 4/13520 Babel Al-Kifil SUP Bab.Dew.Kar.Naj- m45 lot no 1/106 6 P C63-I 5 1 QCBS Prior 14-Dec-09 18-Jan-10 1-Feb-10 8-Feb-10 8-Mar-10 15-Mar-10 29-Mar-10 12-Apr-10 26-Apr-10 3-May-10 10-May-10 2-Nov-11 __ Deewaniyah Ph-I Design for Future 3rd. Floor, Fouad Al-Shamiyah ( Architects and Habba Bldg., Abu Al-Fedhil ) Consultants, in Opposite m23 lot no 7 R 5 1 7-Apr-10 13-Apr-10 15-Apr-10 15-May-10 26-May-10 1-Jun-10 10-Jun-10 21-Dec-10 28-Dec-10 4-Jan-11 28-Jun-12 association with Palestine Hotel, Al- 2/6402 __ SCHLEGEL Saadoon Street, Deewaniyah Consulting Baghdad, Iraq. Sader Al- Engineers 8 A 1 5 1 10-Feb-10 6-Jun-10 10-Jun-10 12-Jun-10 26-Sep-10 24-Oct-10 27-Oct-10 20-Dec-10 21-Dec-10 16-Jan-11 1-Feb-11 Yousifiyah m18 lot no 22/7514 __ Karbalah Hay Al- 9 P C64-I SUP Bas.Was-Ph-I 4 1 QCBS Prior 14-Dec-09 18-Jan-10 1-Feb-10 8-Feb-10 8-Mar-10 15-Mar-10 29-Mar-10 12-Apr-10 26-Apr-10 3-May-10 10-May-10 2-Nov-11 Basrah Al-Hartha Drestra Building, Kol'yan m13 lot Jnah, Beirut, no 9 __ Wassit Al- KHATIB & ALAMI Lebanon. 10 R 4 1 7-Apr-10 13-Apr-10 15-Apr-10 15-May-10 26-May-10 21-Dec-10 4-Jan-11 18-Jan-11 25-Jan-11 1-Feb-11 26-Jul-12 Hifriyah lot no OFFSHORE S.A.L. P.O. Box: 3/416 __ Wassit 14/6203, Beirut, Al-So'wairah m26 Lebanon. lot no 3/2533 11 A 1 4 1 10-Feb-10 6-Jun-10 10-Jun-10 12-Jun-10 26-Sep-10 24-Oct-10 21-Dec-10 3-Jul-11 5-Jul-11 5-Jul-11 19-Jul-11 12 P C65-I SUP Nin-Ph-I 1 1 QCBS Post 14-Dec-09 18-Jan-10 1-Feb-10 8-Feb-10 8-Mar-10 15-Mar-10 29-Mar-10 12-Apr-10 26-Apr-10 3-May-10 10-May-10 2-Nov-11 TECHNICAL STUDIES Hassib Salih BUREAU, Building, Nidhal Nay'nawa Kojaka 13 R 1 1 7-Apr-10 13-Apr-10 15-Apr-10 15-May-10 26-May-10 1-Jun-10 10-Jun-10 21-Dec-10 28-Dec-10 4-Jan-11 28-Jun-12 Architects, Street, Baghdad, m52 lot no 5/900 Planners, Iraq Managements, and Construction 14 A 1 1 1 10-Feb-10 6-Jun-10 10-Jun-10 12-Jun-10 26-Sep-10 24-Oct-10 27-Oct-10 3-Jul-11 5-Jul-11 5-Jul-11 31-Jul-11 15 P Subtotal for 1.2.1.1-b 15 4 16 R 14 4 17 A 4 18 19 1.2.1.2 Services for Supervision of New Schools Ph-II 84 1.2.1.3 Services for Supervision of New Schools Ph-III (Canclled) 112 P Subtotal for 1.2.1 50 28 113 R 49 28 114 A 115 NonAsciiFileName0.xls Page 10 of 19 12/3/2012 3:25 AM IRAQ Comp I Services Third Emergency Educational Project Procurement Plan Final Evaluation, contract award No Objection Date to issue RFP Expected Proposal Submission Invitation for RFPs/RFQs Date Plan (P) / Revised (R)/ Actual submission /Readiness Date Review by Bank Prior / Post & contract negotiation date No Objection Date to sign Technical Evaluation date Contract Signature Date No. of Schools Involved Advertisement EOI or Short Listing & RFP No Objection Date Selection Method Completion Date No. of Contracts to short list Procureme Start Date contract Date nt Sl. # (A) Description Consultant Name Addrress Site Address Comments System Ref. # A B C D E F H I J K L M N O P Q R S T U V W X AA 116 117 1.2.2 Consultancy Services for Design and Subcomponent I Design Services for 12 TECHNICAL Hassib Salih 118 P C47-I 12 1 CQS Prior 14-Feb-08 6-Mar-08 21-Mar-08 23-Mar-08 30-Mar-08 30-Mar-08 13-Apr-08 6-Apr-08 20-Apr-08 5-May-08 12-May-08 10-Aug-08 Sites Ph-I STUDIES Building, Nidhal 119 R 1 12 1 14-Feb-08 6-Mar-08 18-Mar-08 23-Mar-08 27-Mar-08 27-Mar-08 27-Mar-08 07-Apr-08 14-Apr-08 18-May-08 18-May-08 18-Aug-08 BUREAU, Street, Baghdad, Many Delayed Design Services for 16 120 A 1 16 1 14-Feb-08 6-Mar-08 18-Mar-08 23-Mar-08 27-Mar-08 27-Mar-08 27-Mar-08 07-Apr-08 14-Apr-08 18-May-08 18-May-08 30-Nov-09 Architects, Iraq Sites Ph-I Training on Contract 121 P C48-I N/A 1 QCBS Prior 5-Oct-09 9-Nov-09 23-Nov-09 30-Nov-09 28-Dec-09 11-Jan-10 25-Jan-10 1-Feb-10 15-Feb-10 22-Feb-10 1-Mar-10 29-Mar-10 Subcomponent I Management /60 Persons 122 R 30-Jun-11 04-Aug-11 18-Aug-11 25-Aug-11 22-Sep-11 06-Oct-11 20-Oct-11 27-Oct-11 10-Nov-11 17-Nov-11 24-Nov-11 22-Dec-11 N/A 123 A Training on Quality 124 P C49-I N/A 1 QCBS Prior 26-Apr-10 31-May-10 14-Jun-10 21-Jun-10 19-Jul-10 19-Jul-10 2-Aug-10 2-Aug-10 16-Aug-10 23-Aug-10 30-Aug-10 27-Sep-10 Subcomponent I Control /20 Persons 125 R 31-Jul-11 04-Sep-11 18-Sep-11 25-Sep-11 23-Oct-11 06-Nov-11 20-Nov-11 27-Nov-11 11-Dec-11 18-Dec-11 25-Dec-11 22-Jan-12 N/A 126 A Developing a Manual of 127 P C50-I N/A 1 QCBS Prior 25-Oct-10 29-Nov-10 13-Dec-10 20-Dec-10 17-Jan-11 31-Jan-11 14-Feb-11 21-Feb-11 7-Mar-11 14-Mar-11 21-Mar-11 27-Jun-11 School Standards & 128 R N/A Cancelled 129 A 136 P C51-I School Mapping N/A 1 QCBS Prior 12-Oct-09 16-Nov-09 30-Nov-09 7-Dec-09 4-Jan-10 18-Jan-10 1-Feb-10 15-Feb-10 1-Mar-10 8-Mar-10 15-Mar-10 14-Jun-10 137 R 31-Jan-11 07-Mar-11 21-Mar-11 28-Mar-11 25-Apr-11 09-May-11 23-May-11 06-Jun-11 20-Jun-11 27-Jun-11 04-Jul-11 03-Oct-11 N/A Cancelled 138 A 136 P Subtotal for 1.2.2 43 11 137 R 1 1 138 A 1 1 139 P Total for Consultancy Services 1.2 39 140 R 1 29 141 A 1 1 NonAsciiFileName0.xls Page 11 of 19 12/3/2012 3:25 AM IRAQ Comp I Goods Third Emergency Educational Project Procurement Plan 1 2 3 4 5 6 8 10 12 14 16 18 20 22 23 24 25 26 29 Submission / Readiness Date Review By Bank (Prior /Post) Plan (P) / Revised (R)/ Actual Procurement System Ref. # Evaluation & Recomm. No. of Schools Involved Procurement Method Bid Opening Date Completion Date No. of Contracts Execution /b Invitation Date WB NOL Date WB NOL Date Signing Date Start Date Sl. # (A) Description Contractor Name Addrress Comments A B C D E F G H J K L M N O P Q R S T W 1 1.3 Goods for Schools Furniture & Equipments 2 3 P G01-I Laboratory Equipments Ph-I ICB Prior 15 1 27-Sep-10 04-Oct-10 18-Oct-10 29-Nov-10 20-Dec-10 03-Jan-11 17-Jan-11 31-Jan-11 175 25-Jul-11 Supplying Students Desks & Whiteboards for Schools which include ; • Student Desks two sizes, Small for Primary Schools 4 R ICB Prior 48 1 05-Aug-12 06-Aug-12 09-Aug-12 08-Oct-12 29-Oct-12 12-Nov-12 26-Nov-12 10-Dec-12 175 03-Jun-13 and Big for Secondary Schools. • Whiteboards (240*120 cm) double face, one for chalk writing (green color) and the second for magic 5 A 05-Jun-12 06-Aug-12 13-Aug-12 08-Oct-12 11-Oct-12 6 P G02-I School Furniture Ph-I ICB Prior 15 1 27-Sep-10 04-Oct-10 18-Oct-10 29-Nov-10 20-Dec-10 03-Jan-11 17-Jan-11 31-Jan-11 175 25-Jul-11 Supplying Laboratory Equipment for Schools which include; 7 R 1- Primary School General Science Laboratory ICB Prior 48 1 18-Sep-12 25-Sep-12 02-Oct-12 01-Dec-12 22-Dec-12 05-Jan-13 19-Jan-13 02-Feb-13 175 27-Jul-13 2- Secondary Schools Biology Laboratory 3- Secondary Schools Chemical Laboratory 4- Secondary Schools Physics Laboratory 8 A 18-Sep-12 27-Sep-12 07-Oct-12 9 P G03-I Laboratory Ph-II Equipments Furniture Supplying Laboratories and General ICB Prior 25 1 09-May-12 16-May-12 30-May-12 11-Jul-12 01-Aug-12 15-Aug-12 29-Aug-12 12-Sep-12 175 06-Mar-13 Equipment for Primary and Secondary Schools which include ; • Apparatus Cupboards for Laboratory. • Fume cupboard wall, wall standing (hood). 10 R ICB Prior 48 1 18-Sep-12 25-Sep-12 02-Oct-12 01-Dec-12 22-Dec-12 05-Jan-13 19-Jan-13 02-Feb-13 175 27-Jul-13 • Teacher and Teacher Worktables. • Student Stool. • Portable wireless sound speaker system • Digital Media System 11 A 18-Sep-12 27-Sep-12 07-Oct-12 12 P G04-I School Furniture Ph-III ICB Prior 25 1 09-May-12 16-May-12 30-May-12 11-Jul-12 01-Aug-12 15-Aug-12 29-Aug-12 12-Sep-12 175 06-Mar-13 Supplying Schools Laboratory Metal Furniture which include:- • Various types or work benches for laboratories. 13 R • Auxiliary metal frame trolleys. ICB Prior 48 1 18-Sep-12 25-Sep-12 09-Oct-12 20-Nov-12 11-Dec-12 25-Dec-12 08-Jan-13 22-Jan-13 175 16-Jul-13 • Metal Cabinets • Students stool. • White boards. 14 A 15 P G05-I Laboratory Equipments Ph-III ICB Prior 9 1 31-Dec-12 07-Jan-13 21-Jan-13 04-Mar-13 25-Mar-13 08-Apr-13 22-Apr-13 06-May-13 175 28-Oct-13 Supplying Schools Laboratory Equipments These equipments consist • Science Laboratory equipments for primary schools Cance 16 R • Biology Laboratory equipments for Secondary ICB Prior 48 1 05-Jul-12 12-Jul-12 26-Jul-12 06-Sep-12 27-Sep-12 11-Oct-12 25-Oct-12 08-Nov-12 175 02-May-13 Schools lled • Physics Laboratory equipments for Secondary Schools 17 A 18 P G06-I School Furniture Ph-III ICB Prior 9 1 31-Dec-12 07-Jan-13 21-Jan-13 04-Mar-13 25-Mar-13 08-Apr-13 22-Apr-13 06-May-13 175 28-Oct-13 19 R TBD ICB Prior 48 1 01-May-13 08-May-13 22-May-13 03-Jul-13 24-Jul-13 07-Aug-13 21-Aug-13 04-Sep-13 175 26-Feb-14 Cance lled NonAsciiFileName0.xls Page 12 of 19 12/3/2012 3:25 AM A Sl. # 23 22 21 20 Plan (P) / Revised (R)/ Actual B P A R A (A) C Procurement System Ref. # Subtotal 1.3 NonAsciiFileName0.xls D Description E Procurement Method F Review By Bank (Prior /Post) G No. of Schools Involved 6 6 H No. of Contracts J Submission / Readiness Date K WB NOL Date L Invitation Date IRAQ Page 13 of 19 Procurement Plan M Bid Opening Date N Evaluation & Recomm. Third Emergency Educational Project O WB NOL Date P Signing Date Q Start Date Execution /b R Completion Date S Contractor Name T Addrress 12/3/2012 3:25 AM Comp I Goods W lled Comments Cance IRAQ Comp II Services Third Emergency Educational Project Procurement Plan 1 2 4 5 6 8 10 12 14 16 18 20 22 24 26 28 29 30 33 Plan (P) / Revised (R)/ Actual Final Evaluation date ( the No Objection Date to issue Review by Bank Prior / Post combined evalution report No Objection Date to sign Technical Evaluation date and negotiation contract ) Contract Signature Date Invitation for RFPs Date EOI/Readiness Date Short Listing & RFP Expected Proposal No Objection Datet Selection Method Submission Date Completion Date Receive EOI's RFP to short list Advertisement Start Date Procure contract Sl. # ment Comment (A) Description Consultant Name Addrress System s Ref. # A B C D F G H I J K L M N O P Q R S T U X 1 Component II Support to System Development 2 2.1 Services International Firm ( ABU Consult® Berlin GmbH 3 P C53-II IC Prior 7-Sep-09 12-Oct-09 19-Oct-09 2-Nov-09 9-Nov-09 18-Jan-10 Curriculum Development ) Training and Advisory Services Worldwide, in association with (as 4 R QCBS 15-Dec-10 26-Jan-11 24-Feb-11 3-Mar-11 10-Mar-11 14-Apr-11 5-May-11 12-May-11 9-Jun-11 16-Jun-11 23-Jun-11 30-Jun-11 11-Nov-11 joint-venture) Sustainable Research & Development Center 5 A 27-Sep-11 12-Oct-11 19-Dec-11 17-Jan-12 19-Apr-12 20-Jun-12 14-Sep-12 17-Sep-12 9-Oct-12 (SRD) Training Delivery (Int 6 P C54-II QCBS Prior 15-Feb-10 22-Mar-10 29-Mar-10 5-Apr-10 17-May-10 31-May-10 14-Jun-10 28-Jun-10 5-Jul-10 19-Jul-10 26-Jul-10 24-Jan-11 Training firm Curriculum) 7 R canceled 8 A Preperation of Teachers 9 P C55-II Training Materials( 10 QCBS Prior 7-Sep-09 12-Oct-09 19-Oct-09 26-Oct-09 7-Dec-09 21-Dec-09 4-Jan-10 18-Jan-10 25-Jan-10 8-Feb-10 15-Feb-10 1-Mar-10 Trainers ) (Int Training firm ) 10 R 20-Nov-10 4-Dec-10 11-Dec-10 22-Jan-11 5-Feb-11 19-Feb-11 5-Mar-11 12-Mar-11 26-Mar-11 2-Apr-11 CONSORTIUM Organization Reconstruction R1 17-Feb-11 24-Feb-11 31-Mar-11 21-Apr-11 28-Apr-11 26-May-11 2-Jun-11 9-Jun-11 16-Jun-11 Travail France officially registered as ORT France / (ORT), School of Education of the University College 11 A 16-Feb-11 23-Feb-11 30-Mar-11 of Dublin / (UCD) (Dublin) and Iraq Management Consultancy (Iraq) R/A 10-Feb-11 16-Feb-11 23-Feb-11 5-Apr-11 17-Apr-11 26-Apr-11 A 28-Sep-11 12-Oct-11 1-Jan-12 7-Feb-12 13-Feb-12 19-Mar-12 18-May-12 22-May-12 4-Oct-12 19-Oct-12 12-Nov-12 9 P Subotal for 2.1 10 R 11 A P Total for Component II R A NonAsciiFileName0.xls Page 14 of 19 12/3/2012 3:25 AM IRAQ Comp II Training Third Emergency Educational Project Procurement Plan Procurement System Ref. # Submission / Readiness Evaluation & Recomm. Review By Bank (Prior Plan (P) / Revised (R)/ Procurement Method Bid Opening Date Completion Date Invitation Date Signing Date Start Date Actual (A) /Post) Date Sl. # Description Comments A B C D E F H I J K L M N O 1 Component II Support to System Development 2 2.3 Operating Cost 3 P 2.3.1 Training Workshops/Curriclum Expenses N/A 28-Feb-11 30-May-11 4 R 15-Aug-11 14-Sep-11 5 A 6 P 2.3.2 Teachers Training 70 Trainers Expenses N/A 22-Mar-10 21-Jun-10 7 R 30-Apr-11 30-Jul-11 R1 30-Jun-11 29-Sep-11 8 A 9 P 2.3.3 Teachers Training / 6000 persons Expenses N/A 12-Jul-10 11-Jun-12 10 R 15-Jun-11 15-May-13 11 A 15-Sep-11 15-Aug-13 6 P Subotal for 2.3 7 R 8 A NonAsciiFileName0.xls Page 15 of 19 12/3/2012 3:25 AM IRAQ Comp II Goods Third Emergency Educational Project Procurement Plan Submission / Readiness Date Review By Bank (Prior /Post) Plan (P) / Revised (R)/ Actual Procurement System Ref. # Evaluation & Recomm. Procurement Method Bid Opening Date Completion Date Invitation Date Signing Date Start Date Contractor Sl. # (A) Description Addrress Comments Name A B C D E F H I J K L M N O P S 1 Component II Support to System Development 2 2.2 Goods 3 4 P G09-II Equipment Teacher Trianing Sh Post 14-Dec-09 21-Dec-09 28-Dec-09 04-Jan-10 11-Jan-10 18-Jan-10 25-Jan-10 5 R 26-Jan-11 02-Feb-11 09-Feb-11 16-Feb-11 23-Feb-11 02-Mar-11 09-Mar-11 6 R1 15-Jul-11 22-Jul-11 29-Jul-11 05-Aug-11 12-Aug-11 19-Aug-11 26-Aug-11 A 7 P G10-II Equipment Curriculum devlopment Sh Post 22-Feb-10 01-Mar-10 08-Mar-10 15-Mar-10 22-Mar-10 29-Mar-10 05-Apr-10 8 R 20-Jun-11 27-Jun-11 04-Jul-11 11-Jul-11 18-Jul-11 25-Jul-11 01-Aug-11 9 R1 30-Jul-11 06-Aug-11 13-Aug-11 20-Aug-11 27-Aug-11 03-Sep-11 10-Sep-11 A 10 P G11-II Training Materials / Teachers Training Sh Post 30-Nov-09 07-Dec-09 14-Dec-09 21-Dec-09 28-Dec-09 04-Jan-10 11-Jan-10 Several 11 R 10-Jan-11 17-Jan-11 24-Jan-11 31-Jan-11 07-Feb-11 14-Feb-11 21-Feb-11 Packages 12 R1 15-Jul-11 22-Jul-11 29-Jul-11 05-Aug-11 12-Aug-11 19-Aug-11 26-Aug-11 A 10 P Subotal for 2.2 11 R 12 A NonAsciiFileName0.xls Page 16 of 19 12/3/2012 3:25 AM IRAQ Comp III Goods & NCS Third Emergency Educational Project Procurement Plan Review By Bank (Prior /Post) Plan (P) / Revised (R)/ Actual Procurement System Ref. # Evaluation & Recomm. WB No Objection Date Procurement Method Bid Opening Date Completion Date Invitation Date Signing Date Start Date Sl. # (A) Description Contractor Name A B C D E F I J K K L M N O 1 3.1 Component III Goods & Non Cosulting Services 2 3 P G13-III computers Sh Prior 10-Oct-11 17-Oct-11 24-Oct-11 31-Oct-11 07-Nov-11 21-Nov-11 Advanced Technologies 4 R 01-Jan-11 08-Jan-11 15-Jan-11 22-Jan-11 29-Jan-11 05-Feb-11 Computers and Networks 5 A 31-Mar-11 05-Apr-11 6 P G14-III printers , …. Sh Post 07-Oct-13 14-Oct-13 21-Oct-13 28-Oct-13 04-Nov-13 18-Nov-13 Al-Badri Information 7 R 01-Jan-11 08-Jan-11 15-Jan-11 22-Jan-11 29-Jan-11 05-Feb-11 Technology Co. LTD 8 A 03-May-12 09-May-12 10-May-12 N/A 07-Jun-12 12-Jun-12 12-Jun-12 9 P G15-III Office furniture Sh Post 12-Oct-09 19-Oct-09 26-Oct-09 02-Nov-09 09-Nov-09 23-Nov-09 10 R 01-Mar-11 08-Mar-11 15-Mar-11 22-Mar-11 29-Mar-11 05-Apr-11 Al-Arkan Bureau 11 A Supplying Guard Caravan 18-Jun-12 19-Jun-12 20-Jun-12 N/A 06-Jun-12 07-Jul-12 07-Jul-12 office equipment (copy 12 P G16-III Sh Post 10-Oct-11 17-Oct-11 24-Oct-11 31-Oct-11 07-Nov-11 21-Nov-11 machines .. Etc ) 13 R 01-Jan-11 08-Jan-11 15-Jan-11 22-Jan-11 29-Jan-11 05-Feb-11 14 A 15 P G17-III office electrical generator Sh Prior 12-Oct-09 19-Oct-09 26-Oct-09 02-Nov-09 09-Nov-09 23-Nov-09 Al-Qaswaa Engineering 16 R 01-Mar-11 08-Mar-11 15-Mar-11 22-Mar-11 29-Mar-11 05-Apr-11 FZE 17 A 07-Mar-12 10-Mar-12 11-Mar-12 16-Mar-12 18-Mar-12 04-Apr-12 04-Apr-12 18 P G18-III computers - 30 Laptop Sh Prior 25-Mar-12 01-Apr-12 08-Apr-12 15-Apr-12 22-Apr-12 06-May-12 Al-Taif Computer Services 19 R Mr. Abdul Salam Hashim Rahma 20 A 29-Feb-12 29-Feb-12 04-Mar-12 22-Mar-12 09-Apr-12 19-Apr-12 19-Apr-12 21 P NCS1-III Office Renting Sh Prior 25-Mar-12 01-Apr-12 08-Apr-12 15-Apr-12 22-Apr-12 06-May-12 22 R 30-Jun-12 Ne'ma Noori Abdulahad 23 A 12-Feb-12 12-Feb-12 12-Feb-12 23-Mar-12 09-Apr-12 01-Mar-12 30-Jun-13 24 P Total for 3.1 25 R 26 A NonAsciiFileName0.xls Page 17 of 19 12/3/2012 3:25 AM A Sl. # 3 2 1 Plan (P) / Revised (R)/ B R A Actual (A) Procurement System C NonAsciiFileName0.xls Ref. # P 3.2 Operating Costs D Description E Procurement Method Review By Bank (Prior F /Post) Submission / H Readiness Date I Invitation Date J Bid Opening Date IRAQ Page 18 of 19 Procurement Plan K Evaluation & Recomm. Third Emergency Educational Project L Signing Date M Start Date 02-Jan-09 N Completion Date 31-Oct-03 Q Comments Comp III Operating Cost 12/3/2012 3:25 AM IRAQ Comp III Services Third Emergency Educational Project Procurement Plan No Objection Date to sign Final Evaluation, contract No Objection Date to issue Review by Bank Prior / Post Contract Signature Date Invitation for RFPs Date Technical Evaluation Expected Proposal No Objection Date EOI/Readiness Date award & contract Short Listing & RFP Submission Date Completion Date negotiation date Selection Method RFP to short list Advertisement Start Date contract Procurem Sl. # ent Description Consultant Name Addrress Comments System Ref. # A C D F G H I J K L M N O P Q R S T U X 1 3.3 CONSULTANTS' SERVICES Component III 2 Consultants for Project Management (PMT Team) & Auditing 3 C56-III Auditing Firm LCS Prior 07-Sep-08 05-Oct-08 26-Jul-09 02-Aug-09 30-Aug-09 6-Sep-09 13-Sep-09 20-Sep-09 27-Sep-09 04-Oct-09 30-Oct-09 No Objection 4 1 15-Oct-09 Delayed 5 1 SSS 14-Oct-10 31-Oct-13 Subhi Noori Baghdad Al- 6 C61-III Financial officer IC Prior 01-Aug-06 30-June-2013 Ended Flayeh Salhiah Baghdad Hay Abbas Naim 7 C58-III Project Architect IC Prior 26-Apr-09 13-May-09 01-May-09 30-Nov-12 14th of July Amended Mohsun M508 Z40 D15 M&E and Implementation 8 C59-III IC Prior 31-Mar-11 07-Apr-11 Scot Advisor Individual Consultant For Dr. Mu’taz Baghdad / Bab 9 C60-III IC Prior 12-Apr-12 15-Apr-12 31-Aug-12 Foundation Redesign Kadhum Al-Muodhum 10 C66-III Enviromental Consultant IC Prior 16-Apr-12 01-May-12 30-Jun-13 Dr. Zaineb Ismail Individual Consultant For 11 C67-III Vairiation Orders related to IC Prior 6-Nov-12 13-Nov-12 18-Nov-12 06-Jan-13 Foundation Redesign 10 11 Subtotal for 3.3 12 1 13 1 14 Total for Component III 15 1 16 1 NonAsciiFileName0.xls Page 19 of 19 12/3/2012 3:25 AM