Public Disclosure Copy

        The World Bank                                                            Implementation Status & Results Report
        Afghanistan: Sustainable Development of Natural Resources Project II (P118925)


Afghanistan: Sustainable Development of Natural Resources Project II (P118925)

SOUTH ASIA | Afghanistan | Energy and Mining Global Practice |
IBRD/IDA | Technical Assistance Loan | FY 2011 | Seq No: 5 | ARCHIVED on 13-Dec-2014 | ISR16999 |


Implementing Agencies:




Key Dates

  Key Project Dates

  Board Approval date:31-May-2011                                            Effectiveness Date:21-Sep-2011
  Planned Mid Term Review Date:27-Jan-2014                                   Actual Mid-Term Review Date:27-Jan-2014
  Original Closing Date:30-Jun-2016                                          Revised Closing Date:30-Jun-2016




Project Development Objectives

 Project Development Objective (from Project Appraisal Document)
 to assist the Ministry of Mines (MoM) and the National Environmental Protection Agency (NEPA) in further improving their capacitiesto effectively
 regulate Afghanistan‘s mineral resource development in a transparent and efficient manner, and foster private sectordevelopment.


 Has the Project Development Objective been changed since Board Approval of the Project Objective?
 No

 PHRPDODEL



Components

Name
Component A. Award of Contracts and Licenses:(Cost $8300000.00 M)
Component B: Regulation and Monitoring of Operations:(Cost $19100000.00 M)
Component C: Preservation of Aynak Antiquities and Support for Alternative Livelihoodsthrough Sustainable ASM:(Cost $6600000.00 M)
Component D: Project Implementation Support:(Cost $9000000.00 M)



Overall Ratings
Name                                                                       Previous Rating                          Current Rating

Progress towards achievement of PDO                                         Moderately Satisfactory                 Moderately Satisfactory
Overall Implementation Progress (IP)                                        Moderately Satisfactory                 Satisfactory
Overall Risk Rating                                                         --                                      Substantial



12/13/2014                                                                                                                             Page 1 of 10
                                                          Public Disclosure Copy
                                                          Public Disclosure Copy

        The World Bank                                                            Implementation Status & Results Report
        Afghanistan: Sustainable Development of Natural Resources Project II (P118925)




Implementation Status and Key Decisions

 This ISR is based on discussions with the PMU, other relevant government counterparts, and project consultants (i.e GAF, UNICON,DAFA, GIZ) which
 took place from April - October 2014. (Please note that due to the security situation in the country and the suspension of missions, required several
 missions outside of Kabul, as well as a reliance on VCs and ACs). Key achievements and implementation status during the reporting period include the
 following:
 Project Restructuring: Based on the findings of the MTR, the project restructuring was reciently approved by Bank management. On August 06, 2014
 the Bank received an official letter (No. 23310323) from the Ministry of Finance, Government of Afghanistan, requesting a restructuring of SNDRP2. The
 MTR concluded that there was scope for restructuring of the project to reduce duplication with other donor funded activities and to enhance the project
 responsiveness to the MoMP and NEPA’s evolving priorities in the sector. The restructuring included the cancellation of a number of specific project
 activities and in some cases a reduction in the allocated amount budgeted for other activities, resulting in a US $9 million cancellation in the grant
 amount. The restructuring also include revisions to the project results framework and target indicators.
    Component 1 Award of Contracts and Licenses: Transaction based activities around Hajigak iron ore have been impeded by a weakening
 commodity price, delays in passage of the new Mining Law and appointment of a new Minister. As indicated in the results framework there have been a
 total of 10 larger mining and hydrocarbon tenders throughout the country including: Aynak, Hajigak, Badakhshan Gold, Zarkashan deposit,
 Balkhab Copper Deposit & two oil tenders.

  Component 2 Regulation and Monitoring of Operations: An independent external inspection and contract compliance monitoring system is in place,
 but field security has impeded field inspection. Capacity building of National Environmental Protection Agency(NEPA) on inspectorate service functions
 and regulatory monitoring (around ESIA’s) has begun, but the consultant has yet to report back with an overall assessment of the challenges. This
 consultancy was mobilized in August 2014. The MoMP continues to struggle to implement the first Resettlement Action Plan (RAP) for Aynak in a timely
 manner and prepare adequate documentation regarding the process and the associated Grievance Redress Mechanism (GRM); further, the MoMP has
 initiated further acquisition without following the stabndrads set out in the first RAP or in the subsequent Resettlement Policy Framework included in the
 ESMF. To address these weaknesses in MoMP. the Aynak Monitoring & Compliance consultant (GAF) has been asked to reinforce the social
 development consultants within its’ team.
 According to the results framework, the project aims to support the promulgation of six mine related regulations by project closure. Preparation of Mining
 Regulations in the areas of technical, HSE, Explosives, with support from the World Bank, currently is underway. Preparation of financial and
 environmental and social regulations will commence in early 2015. The Bank has urged the government to ensure that all relevant stakeholders are
 adequately consulted with and inputs are considered in the preparation of the regulations.
 Afghanistan Extractive Industies Transparency Initiative (AEITI) underwent validation in 2013, resulting in the Board deciding to extend the country’s
 candidacy by 18 months. Afghanistan had until 10 October 2014 to demonstrate compliance with the 2011 rules (and address 8 identified deficiencies).
 The Bank team has worked closely with DFID and the International Secretariat in Oslo to respond with appropriate capacity building support and policy
 advice; however concern remain that the conditions for compliance have not adequately been met. This as a result of a number of factors including
 frequent changes in key staffing of AEITI. The Secretariat will make recommendation to the Board around the options of suspension, delisting or
 compliance; and the International Secretariat, Bank team and DFID agree that this is priority for the President and new Minister of Finance to resolve
 internally.
 • Component 3 Preservation of Aynak antiquities and support for alternative livelihoods through sustainable artisanal and small-scale mining
 (ASM): As indicated in the results framework, 80 percent of the archeological site located in the "red zone" has been excavated, including through the
 procurement of some 20+ international archeologists, 50 national archeologists, and some 500+ laborers residing in the surrounding communities. Over
 the past year, the MoMP and Ministry of Information and Cultural (MoIC) has significantly increased t heir level of coordination (a bottleneck to progress
 in the past) and ownership over the project.




12/13/2014                                                                                                                              Page 2 of 10
                                                          Public Disclosure Copy
                                                            Public Disclosure Copy

               The World Bank                                                            Implementation Status & Results Report
               Afghanistan: Sustainable Development of Natural Resources Project II (P118925)




Risks

 Systematic Operations Risk-rating Tool

 Risk Category                                                Rating at Approval               Previous Rating           Current Rating

 Political and Governance                                      --                              --                       High
 Macroeconomic                                                 --                              --                       Moderate
 Sector Strategies and Policies                                --                              --                       Substantial
 Technical Design of Project or Program                        --                              --                       Moderate
 Institutional Capacity for Implementation and
 Sustainability
                                                               --                              --                       Moderate
 Fiduciary                                                     --                              --                       Moderate
 Environment and Social                                        --                              --                       High
 Stakeholders                                                  --                              --                       Moderate
 Other                                                         --                              --                       --
 Overall                                                       --                              --                       Substantial


Results

 Project Development Objective Indicators
 PHINDPDOTBL




          Cumulative number of tenders for larger mining and hydrocarbon deposits (Number, Custom)


                                              Baseline                     Actual (Previous)          Actual (Current)          End Target

         Value                                1.00                         10.00                      10.00                     4.00

         Date                                 01-Sep-2011                  01-Apr-2014                25-Nov-2014               30-Dec-2016


         Comments
         The actual number includes , Hajigak, Badakhshan Gold, Zarkashan deposit, Balkhab Copper Deposit & two oil tenders.



 PHINDPDOTBL




      Production data collected and reported for medium scale and for large scale mining and hydrocarbon operations (Number,
     Custom)

                                              Baseline                     Actual (Previous)          Actual (Current)          End Target

         Value                                1.00                         1.00                       1.00                      10.00




12/13/2014                                                                                                                               Page 3 of 10
                                                            Public Disclosure Copy
                                                            Public Disclosure Copy

                The World Bank                                                            Implementation Status & Results Report
                Afghanistan: Sustainable Development of Natural Resources Project II (P118925)



         Date                                 01-Sep-2011                 01-Apr-2014              24-Nov-2014                30-Dec-2016


         Comments
         The Ministry has received the production data from Amu Darya oil production Company (CNPCI).
         These data are including;
         • Daily production report.
         • Seismic Data      Acquisition
         • Well Lock Report
         • Well test Report



 PHINDPDOTBL




          Number of corporatization plans drafted (cumulative) (Number, Custom)


                                              Baseline                    Actual (Previous)        Actual (Current)           End Target

         Value                                0.00                        0.00                     0.00                       2.00

         Date                                 01-Sep-2011                 01-Apr-2014              01-Apr-2014                30-Dec-2016


         Comments
         MoMP have hired a consultancy firm for Afghan Gas Corporatization and Northern Coal. he consultancy for AGE commenced their work in
         Dec. 2013 and the consultancy for NCE commenced their work in June 2014.



 PHINDPDOTBL




          EITI Reconciliation Reports issued (cumulative) (Number, Custom)


                                              Baseline                    Actual (Previous)        Actual (Current)           End Target

         Value                                1.00                        2.00                     3.00                       3.00

         Date                                 01-Sep-2010                 01-Apr-2014              24-Nov-2014                30-Dec-2016


         Comments
               Nov-2014
               Three Reconciliation Reports, one Validation Report and one Scoping study report have been produced.
               1- 1st Reconciliation report covering year 2008-2009
               2- 2nd Reconciliation report covering year 1389
               3- 3rd Reconciliation report covering year 1390.



 PHINDPDOTBL




      Field investigation reports for HSE compliance at medium and large scale mining and oil/gas operations (reports prepared,
     issued, corrective actions taken by operator) (Number, Custom)

                                              Baseline                    Actual (Previous)        Actual (Current)           End Target



12/13/2014                                                                                                                           Page 4 of 10
                                                            Public Disclosure Copy
                                                             Public Disclosure Copy

               The World Bank                                                            Implementation Status & Results Report
               Afghanistan: Sustainable Development of Natural Resources Project II (P118925)



         Value                                1.00                          1.00                      1.00                        5.00

         Date                                 01-Sep-2011                   01-Apr-2014               24-Nov-2014                 30-Dec-2016


         Comments
         Field investigation report for HSE has been completed by CNPCI. 2 other reports for the Dragon and Turkish Petroleum are being drafted
         and would be prepared before the activities of the firm are started (March 2015).



 PHINDPDOTBL




      Percent of Women trained (as a percentage of total trained) in gemstone cutting, polishing and jewelry making. (Number,
     Custom)

                                              Baseline                      Actual (Previous)         Actual (Current)            End Target

         Value                                --                            0.00                      0.00                        40.00

         Date                                 01-Sep-2011                   01-Apr-2014               24-Nov-2014                 30-Dec-2016


         Comments
         Under SDNRP Ⅱ, the consultancy services for Artisanal and Small Mining (ASM) will commence the services by first week of Dec. 2014.



 PHINDPDOTBL




      Percentage of sites in Aynak Valley with antiquities where protection activities have started versus total number of sites within
     the red zone (Percentage, Custom)

                                              Baseline                      Actual (Previous)         Actual (Current)            End Target

         Value                                10.00                         75.00                     80.00                       50.00

         Date                                 01-Sep-2010                   01-Apr-2014               24-Nov-2014                 30-Dec-2016




 Overall Comments
  80 % of the red zone done. Due to high security threat MoMP had to reduce number of the internationals at the site. Therefore, the recovery and
 preservation process become slow. The challenge MoM{ have is to remove the stupas and artifacts on top of the red zone. However, with the
 current team we cannot do it. The plan for removal of the stupas and required resource shared with the Bank during June 2014 mission.


 Intermediate Results Indicators




12/13/2014                                                                                                                                Page 5 of 10
                                                             Public Disclosure Copy
                                                                     Public Disclosure Copy

                   The World Bank                                                            Implementation Status & Results Report
                   Afghanistan: Sustainable Development of Natural Resources Project II (P118925)

 PHINDIRITBL




            Publication of a new Mining Sector Development Strategy and new policies and plans regarding quarrying and ASM mining
           (Text, Custom)

                                                      Baseline                      Actual (Previous)          Actual (Current)            End Target

                                                                                    One main and 18            One main and 18
                                                      Overarching national
                                                                                    individual policies        individual policies         ASM Mining
                                                      Extractive Industries
               Value                                                                including ASM have         including ASM have          plan approved
                                                      Excellence Program
                                                                                    been made approved         been made approved          and published
                                                      (NEIEP) published in draft
                                                                                    and published.             and published.

               Date                                   01-Sep-2011                   01-Apr-2014                24-Nov-2014                 31-Dec-2015

 PHINDIRITBL




              % of new geodata collected as a percentage to total area (Percentage, Custom)

                                                      Baseline                      Actual (Previous)          Actual (Current)            End Target

               Value                                  10.00                         80.00                      85.00                       85.00

               Date                                   01-Sep-2011                   01-Apr-2014                24-Nov-2014                 30-Dec-2016


               Comments
               GIZ-IS have identified more than 300 scientific reports & papers published from 1830 to 2014 in scientific journals, conferences & etc. The
               two GIZ-IS librarians have so far added more than 100 to the Ministry database.


 PHINDIRITBL




              Percent of licenses digitized (Percentage, Custom)

                                                      Baseline                      Actual (Previous)          Actual (Current)            End Target

               Value                                  5.00                          90.00                      90.00                       85.00

               Date                                   01-Sep-2011                   01-Apr-2014                24-Nov-2014                 30-Dec-2016




 PHINDIRITBL




              Number of days to process medium scale licenses (Days, Custom)

                                                      Baseline                      Actual (Previous)          Actual (Current)            End Target

               Value                                  180.00                        90.00                      150.00                      --

               Date                                   01-Sep-2011                   01-Apr-2014                02-Dec-2014                 30-Dec-2016


               Comments
               MoMP cadaster decentralized to 34 provincial offices. The Cadastre office sometimes cant properly manage the situation.




12/13/2014                                                                                                                                         Page 6 of 10
                                                                     Public Disclosure Copy
                                                                    Public Disclosure Copy

                   The World Bank                                                            Implementation Status & Results Report
                   Afghanistan: Sustainable Development of Natural Resources Project II (P118925)




 PHINDIRITBL




              Number of trained mine inspectors (cumulative) (Number, Custom)

                                                    Baseline                      Actual (Previous)           Actual (Current)            End Target

               Value                                30.00                         32.00                       32.00                       50.00

               Date                                 01-Sep-2011                   01-Apr-2014                 02-Dec-2014                 30-Dec-2016


               Comments
               The Geomin (Consulting firm) is hired to train the inspectors. The Team planning to commence their services by first week of December
               2014.


 PHINDIRITBL




              Staffing and annual budget for the compliance office at NEPA (Text, Custom)

                                                    Baseline                      Actual (Previous)           Actual (Current)            End Target

                                                                                                              One National
                                                                                                              (Translator/Interpreter).
                                                                                                              The contract of
                                                                                  Two national, in
                                                                                                              Consultancy Services        Additional staff
                                                                                  addition to one
                                                                                                              for Building Regulatory     positons
                                                                                  international.
               Value                                0                                                         Capacity in the National    identified and in
                                                                                  Procurement of a firm
                                                                                                              Environmental               the process of
                                                                                  for capacity building for
                                                                                                              Protection Agency was       being filled.
                                                                                  NEPA is finalized.
                                                                                                              awarded to SIM S.p.A
                                                                                                              and commenced their
                                                                                                              work on 1st Sep. 2014.

               Date                                 01-Sep-2011                   01-Oct-2014                 02-Dec-2014                 31-Dec-2015




12/13/2014                                                                                                                                        Page 7 of 10
                                                                    Public Disclosure Copy
                                                                      Public Disclosure Copy

                   The World Bank                                                            Implementation Status & Results Report
                   Afghanistan: Sustainable Development of Natural Resources Project II (P118925)

 PHINDIRITBL




              Number of inspectors trained in inspecting appropriate mining techniques and environmental management (Number, Custom)

                                                      Baseline                       Actual (Previous)          Actual (Current)             End Target

               Value                                  10.00                          --                         10.00                        30.00

               Date                                   01-Dec-2011                    --                         02-Dec-2014                  30-Jun-2016


               Comments
               The Consultant hired under SDNRP –II will commence the services by first week of December 2014. At least 10 inspectors were trained
               during SDNRP1.


 PHINDIRITBL




              Number of Mining Regulations Promulgated (Number, Custom)

                                                      Baseline                       Actual (Previous)          Actual (Current)             End Target

               Value                                  0.00                           0.00                       0.00                         6.00

               Date                                   12-Aug-2014                    01-Oct-2014                02-Dec-2014                  30-Jun-2016


               Comments
               First draft of Health & Safety, Technical and Explosive nearly being completed. Work on preparation of the financial regulations just started.
               However, there is no progress on Environmental & Social regulations


 PHINDIRITBL




              NEPA Promulgates sector standards for mining (Text, Custom)

                                                      Baseline                       Actual (Previous)          Actual (Current)             End Target

                                                                                                                                             Final draft
               Value                                  0                              0                          0                            standard tabled
                                                                                                                                             for adoption

               Date                                   12-Aug-2014                    01-Oct-2014                24-Nov-2014                  30-Jun-2016


 PHINDIRITBL




            Annual Report for contract compliance monitoring of Aynak and Hajigak prepared and publicly disseminated (Number,
           Custom)

                                                      Baseline                       Actual (Previous)          Actual (Current)             End Target

               Value                                  0.00                           2.00                       2.00                         5.00

               Date                                   30-Sep-2012                    01-Oct-2014                24-Nov-2014                  30-Jun-2016




12/13/2014                                                                                                                                           Page 8 of 10
                                                                      Public Disclosure Copy
                                                          Public Disclosure Copy

           The World Bank                                                            Implementation Status & Results Report
           Afghanistan: Sustainable Development of Natural Resources Project II (P118925)



 Overall Comments
 So far 12 quarterly reports and 2 annual report have been produced. There is only two annual report as the project was originally two years.
 There would have been a project final report after that, but the project has been extended & so the final report will come at the end.



 Data on Financial Performance

Disbursements (by loan)

 Project       Loan/Credit/TF    Status      Currency       Original    Revised      Cancelled     Disbursed      Undisbursed                   Disbursed

 P118925       IDA-H6990         Effective   XDR               32.80       32.80           0.00         10.07             22.73                        31%


Key Dates (by loan)
 Project       Loan/Credit/TF    Status      Approval Date      Signing Date       Effectiveness Date    Orig. Closing Date       Rev. Closing Date

 P118925       IDA-H6990         Effective   31-May-2011        16-Jul-2011        21-Sep-2011           30-Jun-2016              30-Jun-2016



Cumulative Disbursements




 Restructuring History

  Level 2 Approved on 25-Nov-2014




 Related Project(s)

12/13/2014                                                                                                                              Page 9 of 10
                                                          Public Disclosure Copy
                                                Public Disclosure Copy

        The World Bank                                                            Implementation Status & Results Report
        Afghanistan: Sustainable Development of Natural Resources Project II (P118925)



There are no related projects.




12/13/2014                                                                                                   Page 10 of 10
                                                Public Disclosure Copy