Public Disclosure Copy The World Bank Implementation Status & Results Report Zhuzhou Brownfield Remediation Project (P147381) Zhuzhou Brownfield Remediation Project (P147381) EAST ASIA AND PACIFIC | China | Environment & Natural Resources Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 5 | ARCHIVED on 28-Jun-2018 | ISR31138 | Implementing Agencies: People's Republic of China, Zhuzhou PMO Key Dates Key Project Dates Bank Approval Date:31-Mar-2016 Effectiveness Date:13-Sep-2016 Planned Mid Term Review Date:16-Sep-2019 Actual Mid-Term Review Date:-- Original Closing Date:31-Dec-2021 Revised Closing Date:31-Dec-2021 Project Development Objectives Project Development Objective (from Project Appraisal Document)

The project development objective is to reduce public exposure to contaminated land in the Project Area using risk-based remediation approaches.

Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Component 1: Remediation of contaminated plots:(Cost $137.43 M) Component 2: Associated treatment and disposal works:(Cost $46.80 M) Component 3: Capacity building and knowledge management:(Cost $8.23 M) Component 4: Project Management, monitoring and evaluation:(Cost $20.98 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Moderately Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Satisfactory Overall Risk Rating  Substantial  Substantial 6/28/2018 Page 1 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhuzhou Brownfield Remediation Project (P147381) Implementation Status and Key Decisions Implementation has been on track since last mission; most agreed actions have been taken. Design progress has been made which will enable procurement of multiple civil works contracts by end of calendar 2018. The project is still expected to achieve its objectives. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Low  Low  Low Macroeconomic  Moderate  Moderate  Moderate Sector Strategies and Policies  Moderate  Moderate  Moderate Technical Design of Project or Program  Moderate  Moderate  Substantial Institutional Capacity for Implementation and Sustainability  Substantial  Substantial  Substantial Fiduciary  Moderate  Moderate  Moderate Environment and Social  Substantial  High  High Stakeholders  Substantial  Substantial  Substantial Other  --  --  -- Overall  Substantial  Substantial  Substantial Results Project Development Objective Indicators PHINDPDOTBL  People in the Project Area with reduced potential risk of exposure to contaminated land. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 6,237.00 Date 31-Aug-2015 15-Dec-2017 23-Jun-2018 31-Dec-2021 PHINDPDOTBL  Contaminated land managed or dump sites closed under the project (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target 6/28/2018 Page 2 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhuzhou Brownfield Remediation Project (P147381) Value 0.00 0.00 0.00 284.00 Date 31-Aug-2015 15-Dec-2017 23-Jun-2018 31-Dec-2021 PHINDPDOTBL  Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 262,000.00 Date 31-Aug-2015 15-Dec-2017 23-Jun-2018 31-Dec-2021 PHINDPDOTBL  Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 PHINDPDOTBL  Share of people living in the Zhuzhou's Quingshuitang core industrial area indicating that sufficient information is available regarding the area's remediation process and grievance redress mechanism (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 31-Aug-2015 15-Dec-2017 23-Jun-2018 31-Dec-2021 PHINDPDOTBL  Verified remediation works implemented per risk-based design (Hectare(Ha), Custom) 6/28/2018 Page 3 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhuzhou Brownfield Remediation Project (P147381) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 273.00 Date 31-Aug-2015 15-Dec-2017 23-Jun-2018 31-Dec-2021 Overall Comments Implementation of first two contracts are under way. Results for one of the subareas are expected to be available by end of 2018. Intermediate Results Indicators PHINDIRITBL  Project sites in the Zhuzhou's Qingshuitang core industrial area remediated and meet contamination levels based on their intended future land use (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 6.00 Date 31-Aug-2015 15-Dec-2017 23-Jun-2018 31-Dec-2021 PHINDIRITBL  People trained in contaminated site remediation (Number (Thousand), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 200.00 Date 31-Aug-2015 -- 23-Jun-2018 31-Dec-2021 PHINDIRITBL  Environmental monitoring reports publicly disclosed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 31-Aug-2015 15-Dec-2017 23-Jun-2018 31-Dec-2021 6/28/2018 Page 4 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhuzhou Brownfield Remediation Project (P147381) PHINDIRITBL  Industrial or municipal solid waste reduced or recycled under the project (Tones/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1,100,000.00 Date 31-Aug-2015 15-Dec-2017 23-Jun-2018 31-Dec-2021 PHINDIRITBL  Project activities related to relocation of manufacturing sites and compensation of workers fully comply with national standards (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 31-Aug-2015 -- 23-Jun-2018 31-Dec-2021 PHINDIRITBL  Updated spatial zoning plan for Qinghuitang Core Area tailored to remediation concepts and brownfield redevelopment requirements (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Spatial zoning plan updated Spatial zoning plan does Spatial zoning plan does taking in not take into account site not take into account consideration Value -- investigation and risk site investigation and risk assessment results risk assessment results assessment and cost effectiveness Date 31-Aug-2015 -- 23-Jun-2018 31-Dec-2021 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed 6/28/2018 Page 5 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhuzhou Brownfield Remediation Project (P147381) P147381 IBRD-85870 Effective USD 150.00 150.00 0.00 5.38 144.63 3.6% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P147381 IBRD-85870 Effective 31-Mar-2016 01-Jun-2016 13-Sep-2016 31-Dec-2021 31-Dec-2021 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/28/2018 Page 6 of 6 Public Disclosure Copy