Document of
                                       The World Bank

                               FOR OFFICIAL USE ONLY

                                                                           Report No: 66413-MA




                             PROJECT APPRAISAL DOCUMENT

                                             ON A

                               PROPOSED GRANT FROM THE

                            GLOBAL ENVIRONMENT FACILITY

                          IN THE AMOUNT OF US$ 5.18 MILLION

                                            TO THE

                                  KINGDOM OF MOROCCO

                                            FOR AN

                INTEGRATED COASTAL ZONE MANAGEMENT PROJECT



                                         June 13, 2012



 Sustainable Development Department
 Middle East and North Africa Region


This document has a restricted distribution and may be used by recipients only in the
performance of their official duties. Its contents may not otherwise be disclosed without World
Bank authorization.
                               CURRENCY EQUIVALENTS
                         (Exchange Rate Effective 11 November 2011)
                              Currency Unit = MAD (Moroccan Dirham)
                                 8.14 MAD = US$1


                                       FISCAL YEAR
                                 January 1 – December 31

                           ABBREVIATIONS AND ACRONYMS

ACCMA   Adaptation to Climate Change in Morocco (Adaptation au changement climatique
        au Maroc)
ADA     Agricultural Development Agency (Agence pour le Développement Agricole)
CPS     Country Partnership Strategy
DE      Department of the Environment (Département de l’environnement)
DFID    Department for International Development (UK)
DMF     Department of Maritime Fisheries (Département de la Pêche Maritime)
EMC     Eastern Mediterranean Coast
ERSDO   Eastern Region Sustainable Development Observatory (Observatoire Régional du
        développement durable de l’Oriental)
GEF     Global Environment Facility
HCWFFAD High Commission for Water, Forestry and the Fight Against Desertification
        (Haut-commissariat aux Eaux et Forêts et à la Lutte contre la Désertification)
ICZM    Integrated Coastal Zone Management
IDRC    International Development Research Center (Canada)
MAMF    Ministry of Agriculture and Maritime Fisheries (Ministère de l’Agriculture et de la
        Pêche Maritime)
MEF     Ministry of the Economy and Finance (Ministère de l’Economie et des Finances)
MAGG    Ministry of General Affairs and Governance (Ministère des Affaires Générales et
        de la Gouvernance)
MEMWE   Ministry of Energy, Mines, Water and the Environment (Ministère de l’Énergie,
        des Mines, de l’Eau et de l’Environnement)
MT      Ministry of Tourism (Ministère du Tourisme)

NADA         National Aquaculture Development Agency (Agence Nationale pour le
             Développement de l’Aquaculture)
NEO          National Environmental Observatory (Observatoire National de l’Environnement)
NFO          National Fisheries Office (Office National des Pêches)
NFRI         National Fisheries Research Institute (Institut National de Recherche Halieutique)
NSP          National Sanitation Program (Programme national d’assainissement)
PMU          Project Management Unit (Unité de Gestion du Projet)




                                               ii
PMV        Plan Maroc Vert
RDA        Regional Direction of Agriculture (Direction Régionale de l’Agriculture)
SBEI       Site of Biological and Ecological Interest (Site d’Intérêt Biologique et Ecologique)
SMAP III   Short and Medium-term Priority Environmental Action Programme, Phase III
TCC        Technical Coordination Committee




                  Regional Vice President:         Inger Andersen
                        Country Director:          Simon Gray
                          Sector Director:         Junaid Kamal Ahmad
                         Sector Manager:           Hoonae Kim
                       Task Team Leader:           Song Li




                                             iii
                                KINGDOM OF MOROCCO
                    INTEGRATED COASTAL ZONE MANAGEMENT PROJECT

                                                    TABLE OF CONTENTS

                                                                                                                                            Page

PAD DATA SHEET..................................................................................................................... vi

I.        STRATEGIC CONTEXT .................................................................................................1
          A. Country Context and Issues .......................................................................................... 1
          B. Sectoral and Institutional Context ................................................................................. 4
          C. Higher Level Objectives to which the Project Contributes .......................................... 5

II.       PROJECT DEVELOPMENT OBJECTIVES ................................................................6
          PDO..................................................................................................................................... 6
          PDO Level Results Indicators ............................................................................................. 6

III.      PROJECT DESCRIPTION ..............................................................................................7
          A. Project Components ...................................................................................................... 8
          B. Project Financing ........................................................................................................ 12
          C. Lessons Learned and Reflected in the Project Design ................................................ 13
          D. Institutional and Implementation Arrangements ........................................................ 14
          E. Results Monitoring and Evaluation ............................................................................ 16
          F. Sustainability............................................................................................................... 18

IV.       KEY RISKS AND MITIGATION MEASURES ..........................................................19
          A. Risk Ratings Summary Table ..................................................................................... 19
          B. Overall Risk Rating Explanation ................................................................................ 19

V.        APPRAISAL SUMMARY ..............................................................................................20
          A. Economic and Financial Analyses .............................................................................. 20
          B. Technical ..................................................................................................................... 20
          C. Financial Management ................................................................................................ 21
          D. Procurement ................................................................................................................ 21
          E. Social (including Safeguards) ..................................................................................... 22
          F. Environment (including Safeguards) .......................................................................... 24

Annex 1: Results Framework and Monitoring .........................................................................26

                                                                       iv
Annex 2: Detailed Project Description .......................................................................................29

Annex 3: Implementation Arrangements ..................................................................................35

Annex 4: Operational Risk Assessment Framework (ORAF) .................................................52

Annex 5: Implementation Support Plan ....................................................................................55

Annex 6: Incremental Cost Analysis ..........................................................................................57




                                                              v
                                                                   PAD DATA SHEET
                                                                 KINGDOM OF MOROCCO
                                            INTEGRATED COASTAL ZONE MANAGEMENT
                                                       PROJECT APPRAISAL DOCUMENT
.




                                                       MIDDLE EAST AND NORTH AFRICA
                                                                              MNSSD

.




                                                                    Basic Information
Date:                            June 13, 2012                     Sectors:            General agriculture, fisheries and forestry sector (90%);
                                                                                       water, sanitation (10%)
Country Director:                Simon Gray                        Themes:             Biodiversity (50%); Environmental policies and
                                                                                       institutions (30%); Climate change (20%)
Sector Manager/Director:         Junaid Kamal Ahmad                EA Category:        Partial Assessment
Project ID:                      P121271
Lending Instrument:              Grant
Team Leader(s):                  Song Li
Joint IFC:
.




Borrower:      The Kingdom of Morocco
Responsible Agency:     Ministry of Energy, Mines, Water and Environment/Environment Department (DE)
    Contact:             Rattal, Abdallah,                                             Title:          Directeur adjoint des Etudes de la planification
    Telephone No.:       212-(0) 537-57 66 39 +212-(0) 661-34 89                       Email:          rattal2005@yahoo.fr
                         41
.




Project Implementation Period:            Start Date:   October 1, 2012                    End Date:   September 30, 2016
Expected Effectiveness Date:          October 1, 2012
Expected Closing Date:                March 31, 2017
.




                                                           Project Financing Data(US$M)
[ ]      Loan          [X ]   Grant             [ ]      Other
[ ]      Credit        [ ]    Guarantee

For Loans/Credits/Others
Total Project Cost :                  25.18 million                               Total Bank Financing :

Total parallel financing :                20 million                              Financing Gap :


.




Financing Source                                                                                                                        Amount(US$M)
BORROWER/RECIPIENT                                                                                                                                  20.00



                                                                                  vi
IBRD
IDA: New
IDA: Recommitted
Others (GEF grant)                                                                                                                  5.18
Financing Gap
Total                                                                                                                              25.18
.




Expected Disbursements (in USD Million)
Fiscal Year     2013            2014            2015            2016                 2017
Annual          0.49            1.18            2.12            1.19                 0.20
Cumulative      0.49            1.67            3.79            4.98                 5.18
.




Project Development Objective(s)

The objective of the project is to pilot the application of the integrated coastal zone management (ICZM) approach in the
project area on the eastern Mediterranean coast of Morocco.
.




Components
Component Name                                                                                                       Cost (USD Millions)
                                                                                            GEF: 0.677
Component 1: Capacity building and institutional strengthening to
incorporate the ICZM approach into local development planning

                                                                                            GEF: 4.119
Component 2: Investments to improve coastal resource management and
livelihoods through co-management approach

                                                                                            GEF: 0.384
Component 3: Project management and M&E
.




                                                                           Compliance
Policy
Does the project depart from the CAS in content or in other significant respects?                         Yes [ ]      No [X ]
.




Does the project require any waivers of Bank policies?                                                    Yes [ ]      No [X ]
Have these been approved by Bank management?                                                              Yes [ X]     No
                                                                                                                            [ ]
Is approval for any policy waiver sought from the Board?                                                  Yes [ ]      No [ X]
Does the project meet the Regional criteria for readiness for implementation?                             Yes [ X]     No [ ]
           .




           Safeguard Policies Triggered by the Project                                                   Yes                 No
Environmental Assessment OP/BP 4.01                                                                            X
Natural Habitats OP/BP 4.04                                                                                    X

Forests OP/BP 4.36                                                                                                           X

Pest Management OP 4.09                                                                                                      X

Physical Cultural Resources OP/BP 4.11                                                                                       X



                                                                                    vii
Indigenous Peoples OP/BP 4.10                                                                                   X

Involuntary Resettlement OP/BP 4.12                                                                             X
Safety of Dams OP/BP 4.37                                                                                       X

Projects on International Waterways OP/BP 7.50                                                                  X

Projects in Disputed Areas OP/BP 7.60                                                                           X
.




Conditions and Legal Covenants
Effectiveness conditions:

     (i)       The Project Operations Manual, satisfactory to the World Bank, has been adopted by the Recipient, and has
               been posted on the website of MEMWE.
     (ii)      The PMU has been established in a manner satisfactory to the World Bank.
     (iii)     MEMWE has entered into Implementation Conventions, satisfactory to the World Bank, with HCWFFAD,
               MAMF, NADA, ADA, and MT.
Legal covenants:
        (i)    The Recipient shall vest: (i) MEMWE, through the PMU, with the overall responsibility for
               implementation of Parts 1 and 3 of the Project, and for the overall coordination of the implementation of
               the entire Project; (ii) HCWFFAD with the overall responsibility for implementation of Part 2.1 of the
               Project; (iii) MAMF with the overall responsibility for implementation of Part 2.2 (i) of the Project ; (iv)
               NADA with the overall responsibility for implementation of Part 2.2 (ii) and (iii) of the Project ; (v)
               ADA with the overall responsibility for implementation of Part 2.3 of the Project; and (vi) MT with the
               overall responsibility for implementation of Part 2.4 of the Project. The PMU shall provide all necessary
               assistance to HCWFFAD, MAMF, NADA, ADA and MT with respect to the procurement, financial
               management, and monitoring and evaluation of, and the preparation of progress reports regarding, the
               respective activities to be implemented by each of such entities under the Project.
        (ii)   The Recipient shall ensure that the PMU is maintained at all times during the implementation of the
               Project with qualified staff and adequate terms of reference and resources.
        (iii)  The Recipient shall ensure that all Ministries and entities involved in the implementation of the Project
               are maintained at all times during the implementation of the Project with qualified staff and adequate
               resources for the implementation of their respective parts of the Project.
        (iv)   The Recipient shall maintain at all times during the implementation of the Project the Implementation
               Conventions.
        (v)    The Recipient shall ensure that the Technical Coordination Committee is maintained at all times during
               the implementation of the Project with adequate terms of reference, members and resources. The
               Technical Coordination Committee shall serve as a technical forum for MEMWE, HCWFFAD, MAMF,
               NADA, ADA and MT in which such entities shall harmonize their actions regarding the implementation
               of the Project, share knowledge on Project implementation, and ensure that their annual work plans and
               budgets are well integrated with one another.
        (vi)   The Recipient shall take all necessary measures to implement the Project in accordance with the Project
               Operations Manual and the Implementation Conventions. The Recipient shall not amend, suspend,
               abrogate, repeal or waive any provision of the Project Operations Manual and the Implementation
               Convention without prior approval of the World Bank.
        (vii)  The Recipient shall ensure that HCWFFAD, MAMF, NADA, ADA and MT provide to the PMU: (i) not
               later than fifteen (15) days after the end of each calendar semester all necessary information regarding the
               implementation of the activities under their respective parts of the Project in order for the PMU to
               prepare the overall Project Report covering each calendar semester; (ii) not later than fifteen (15) days
               after the end of each calendar semester all necessary information regarding their respective parts of the


                                                           viii
                   Project in order for the PMU to prepare the overall interim unaudited financial report covering each
                   calendar semester; and (iii) not later than two (2) months after the end of each fiscal year of the
                   Recipient all necessary information in order for the PMU to prepare the Recipient’s Financial Statements
                   for the Project.
          (viii)   No proposed pilot implementation activity shall be eligible for financing under Part 2.2 of the Project
                   unless and until: (a) the Recipient has prepared the Site-Specific ESIAs and the Site-Specific ESMPs for
                   such pilot activity in accordance with the requirements of the ESMF, submitted such Site-Specific ESIA
                   and Site-Specific ESMP to the World Bank for approval and received such approval in writing prior to
                   disclosing same; and (b) the Recipient has determined on the basis of an assessment satisfactory to the
                   World Bank that such pilot activity: (i) would not involve any involuntary taking of land, causing any
                   restriction directly or indirectly resulting in involuntary resettlement, as referenced in the World Bank’s
                   operational policies and procedures set forth in the World Bank’s Operational Manual under OP/BP4.12
                   published under www.WorldBank.org/opmanual; and (ii) has been initiated by and with the support of
                   the communities involved.
          (ix)     The Recipient shall ensure that: (i) Parts 1 and 2 of the Project are implemented in accordance with the
                   ESIA, the ESMP, the Site-Specific ESIAs and the Site-Specific ESMPs; (ii) no provision of the ESIA,
                   the ESMP, the Site-Specific ESIAs and the Site-Specific ESMPs are amended, suspended, abrogated,
                   repealed or waived, without prior approval of the Bank; and (iii) adequate information on the
                   implementation of the ESIA, the ESMP, the Site-Specific ESIAs and the Site-Specific ESMPs is suitably
                   included in the Project Reports referred to in Section II.A.1 of this Schedule 2.
          (x)      No activity involving the involuntary taking of land, causing any restriction directly or indirectly
                   resulting in involuntary resettlement, as referenced in the World Bank’s operational policies and
                   procedures set forth in the World Bank’s Operational Manual under OP/BP4.12 published under
                   www.WorldBank.org/opmanual, would be financed under the Project.
          (xi)     The Recipient shall prepare and submit to the World Bank for approval a consultation plan for the Project
                   by no later than six (6) months after the Effective Date, and shall promptly implement such consultation
                   plan as approved by the World Bank.
.




                                                        Team Composition
Bank Staff
Name                           Title                           Specialization                 Unit         UPI
Song Li                        Environment Specialist          Task Team Leader               MNSEN

Andrew Losos                   Environment Specialist          Environmental safeguards       MNSEN
Marie Francoise How Yew        Language Program Assistant                                     MNSSD
Kin
Jean-Charles De Daruvar        Senior Counsel                  Lawyer                         LEGEM
Nathalie S. Munzberg           Senior Counsel                  Lawyer                         LEGEN
Hassine Hedda                  Finance Officer                 Financial Management           CTRLA
Anas Abou El Mikias            Sr. Financial Management        Financial Management           MNAFM
                               Specialist
Lamyae Hanafi Benzakour        Financial Management Specialist Financial Management           MNAFM
Abdoulaye Keita                Sr. Procurement Specialist      Procurement                     MNAPR
Monica Dorhoi                  Social Development Consultant   Social Development Team Member MNSEN
John Stewart                   Sr. Environment Specialist      Peer reviewer                  ENVGC
William Leeds Lane             Retired TTL for several ICZM    Peer reviewer

                                                               ix
                                projects
Non Bank Staff
Name                            Title                               Office Phone                   City
Charlotte de Fontaubert         Sr. Advisor for fisheries                                          Washington DC, USA
.




Locations
Country                   First Administrative     Location                         Plann Actual   Comments
                          Division                                                  ed
Morocco                   Ministry of Energy,      Four project sites on the
                          Mines, Water and         eastern Mediterranean coast:
                          Environment
                                                             Coast of Saidia-Ras
                                                              El Ma;

                                                             Rural commune of
                                                              Beni Chiker;

                                                             Nador lagoon and
                                                              its surrounding
                                                              communes; and

                                                             Rural Commune of
                                                              Boudinar.

.




                                                                    x
I.   STRATEGIC CONTEXT

     A. Country Context and Issues

 1.      Morocco’s population is largely concentrated along the coast and in plains areas of
 the country. It is also highly urbanized as 56% of the population lives in cities, most of
 which are located along the coast, both Atlantic and Mediterranean. This demographic
 concentration of people is to be expected given the nature of the local climate and because
 Morocco has a coastline that extends to 3,500 km, 500 km of which is by the Mediterranean Sea.
 The economy of the country is therefore dependent on the coastal zone and related ecosystems
 that have a high potential to provide food and employment, be it from tourism, agriculture,
 fisheries or other natural-resource based activities. With its strategic position as the gateway to
 Europe and its rich natural resources, the Mediterranean coast of Morocco has already been
 recognized as a priority target for future development by the Government of Morocco. Since
 1999, a series of coastal initiatives and programs of national significance have been launched,
 including the Government Initiative for the Development of the Eastern Region (2003) and the
 Program of Development of the Nador Lagoon (2008). The Eastern region is thus considered a
 driver of cross-sectoral development for Morocco.
 2.      The importance of the coast to Morocco’s economy, and the associated increase in
 population density and urbanization in the coastal zone, has come at a cost to the
 environment. As a result, these impacts have the potential to increase significantly conflicts
 between users of coastal natural resources in the future. For instance, sand mining for
 construction material for use in urban infrastructure, and sewage and solid waste disposal have
 become major environmental issues in the coast. Additionally, conflicting uses of natural
 resources along the coast have resulted in salinization of aquifers, water supply issues, loss of
 biodiversity, and ecologically sensitive areas1. Coastal ecosystems along the Nador Lagoon and
 Moulouya River estuary are under particular pressure of economic development and of coastal
 erosion ( Khattabi and Bellaghmouch, 2009. Vulnerability of coastal ecosystems in Northeast of
 Morocco to shoreline erosion and sea level rise. IOP Conf. Ser.: Earth Environ. Sci. 6 352025),
 and impacts there are more acutely felt because of the sensitive nature of the environment and
 areas that are internationally recognized as of great biodiversity significance.2
 3.      Impacts on the coast and coastal resources predicted to arise from future climate
 change are likely to aggravate existing natural resource conflicts, biodiversity loss,
 infrastructure construction and maintenance costs, and to impact the livelihoods of coastal
 residents. As noted in an article published in 2007: “The eastern part of the Mediterranean
 coast of Morocco is physically and socio-economically vulnerable to accelerated sea-level rise,
 due to its low topography and its high ecological and touristic value. Results indicate that 24%
 and 59% of the (coastal) area will be lost by flooding at minimum and maximum inundation
 levels, respectively. The most severely impacted sectors are expected to be the residential and
 recreational areas, agricultural land, and the natural ecosystem. Shoreline erosion will affect
 50% and 70% of the total (coastal) area in 2050 and 2100, respectively…�? (Snoussi et al., 2007).
 This prediction is supported by a recent World Bank study on the adaptation of fisheries to

 1
  Projet SMAP III Plan d’Action pour la cote de Nador (Février 2009, page 11).
 2
  There are 3 Ramsar sites in these areas. Ramsar sites are Wetlands of International Importance and are: Nador
 Lagoon, Cap des Trois Fourches, and the Moulouya River estuary.


                                                         1
climate change in Morocco (The World Bank, 2011)3 and a study on adaptation of the fisheries
sector to climate change in the EMC (Khattabi & Jobbins, 2011), which suggest that some of the
impacts of climate change on coastal areas are already being felt, and more are expected in the
medium to long term.4 The development of new, and maintenance of existing urban and rural
infrastructures, identification of long term sustainable land uses, and sitting of tourist
infrastructures all must recognize that the coastal topography and capability will evolve in the
face of the impacts of climate change, and particularly sea-level rise.
4.      Tourism development is driven by ambitious goals set up in the Plan Azur and the
Strategy for Tourism « Vision 2020 », fisheries activities are developed and encouraged by the
Département de la Peche Maritime within the Ministry of Agriculture and Fisheries, and further
coastal development is fostered and encouraged by municipalities, but the impact of each activity
is not necessarily shared or understood by decision-makers that champion the other sectors.
5.      Despite the fact that this limited space is managed by many state sectoral agencies,
the implementation of their various policies – often completely independent from one
another - is not very efficient and sometimes contradictory. What is needed is an integrated
approach to management in which all relevant government sectors work together, in a
transparent and decentralized way, and in close cooperation with coastal residents and
stakeholders. The objective of this locally based management is to ensure that any development
that occurs in this sensitive area does so in an environmentally and socially sustainable fashion.
Fortunately, a model for this type of management, known as Integrated Coastal Zone
Management –ICZM- is already being implemented and is recognized in Morocco, as embodied
in the bill on Zoning, Protection, Development and Conservation of Coastal Zones (also known
as the ICZM bill), which is currently pending before Parliament.
6.      ICZM evolved over time, both within the Bank and beyond, to address the almost
uniform failure of single sector management techniques to produce measurable benefits in
the coastal zone. Why? Because the coastal zone is a unique ecosystem in view of the diversity
of habitats present and of their inter-linkages. Managing one sector like agriculture without
consideration of coastal and marine fisheries almost always results in damage to the economic
value of the fishery. Managing terrestrial forests in the headwaters of rivers discharging through
coastal areas and into the ocean without consideration of the wetlands, marshes, mangrove areas
and near-shore aquatic environments often leads to unexpected and detrimental impacts on
biodiversity, growth and primary production in coastal wetlands, reduction in fish biomass, and
other impacts on biodiversity. The juxtaposition of terrestrial, freshwater, brackish and marine
environments in such a small area means that coastal zones are just too complex to be managed
sector by sector. ICZM requires that all development sectors (such as agriculture, fisheries,
tourism, forestry, public works, local government, etc.) plan and integrate their annual work
programs to be complementary and to recognize the very real possibility of “off-site impacts�?.
The World Bank has guidelines (Lundin and Post, 1996 and Hewawasam, 2002) that direct its
work in the coastal zone, as do almost all developed country and regional organizations. These
guidelines link development to sustainable management of ecologically sensitive and
protected/conservation areas, promote co-management of resources between government and
local stakeholders, and integrate management by government through cooperation of sectors.
3
 The World Bank, Changement Climatique et Secteur Halieutique, Impacts et Recommandations, Rabat, 2011.
4
 Khattabi & Jobbins, Vulnerability and adaptation of traditional fisheries to climate change. In Chuenpagdee R.
(Ed.) World Small-Scale Fisheries Contemporary Visions. Eburon Academic Publishers. Pp: 63-80)


                                                         2
Most importantly, the ICZM approach has been successfully applied through World Bank
projects with very positive results in several countries, such as, China, Indonesia5 and Tanzania.
7.       The Project has a regional focus and fits within the larger “Sustainable MED�?
program. The coastal countries of the Mediterranean face common and interlinked challenges
relating to natural resources management. This Large Marine Ecosystem (LME) is very
sensitive to land-based impacts from urban and industrial pollution, degradation of the quality
and amount of freshwater input from solid waste, and the resulting losses of coastal habitat and
marine and terrestrial resources, including fisheries. These Mediterranean countries have
responded to different challenges through various national and regional initiatives. Regional
initiatives include: the Barcelona Convention and UNEP-MAP Program, the Mediterranean
Technical Assistance Program (METAP), the Strategic Partnership for the Mediterranean Sea
Large Marine Ecosystem (MedPartnership), EC-funded LIFE, SMAP and Horizon 2020
Programs, and more recently the Union for the Mediterranean (UFM). These initiatives play a
key role in helping develop national and regional capacity and channeling investments towards
improved resources management. Ambitious and beneficial as they are, however, these
initiatives do not sufficiently or sustainably address major freshwater conflicts and
environmental changes to the marine, coastal and inland watersheds that are likely to arise from
the expected impacts of climate change. Thus the Sustainable MED program (Mediterranean
Sustainable Development Program), supported by the GEF and implemented by the World Bank,
takes the next step in addressing the sustainability of natural resources base in the Mediterranean
Sea.
8.      This Kingdom of Morocco Integrated Coastal Zone Management Project (The
Project) is also supported by the GEF, which sees its investment as helping the Government
of Morroco to meet its obligations under Sustainable MED. The Project therefore promotes
sustainable development in the coastal area as a way of enhancing protection of biodiverstiy,
ecologically sensitive areas such as RAMSAR sites, and ensuring that coastal resources are
managed both for the benefit of the country and for the overall good of the countries bordering
the Mediterranean. The Project will contribute to the Trans-boundary Action Plan and the
Strategic Action Programs within the Sustainable MED program by strengthening the resilience
of coastal communities to the impacts of climate change and also to regional efforts to address
declining biodiversity and fisheries. The project will focus on the Mediterranean coast to
"enhance and accelerate the implementation of trans-boundary pollution reduction, improved
water resources management, and biodiversity conservation measures in priority hotspots and
sensitive areas of selected countries of the Mediterranean basin�?.
9.     The Project investment is local and focused along the Mediterranean coast of
Morocco. It supports coastal development within the Sustainable MED framework through four
general types of investment: i) Promotion of local resource use planning through ICZM

5
  INDONESIA CORAL REEF MANAGEMENT PROGRAM (APL):-- COREMAP I represents the first time any
developing country has initiated a program of such scale to target the sustainable management of coral reefs and
associated ecosystems. It was designed to test approaches in several pilot sites, to generate lessons that could inform
the design of interventions in an expanded number of priority coral reef sites in COREMAP II and III. In particular,
the independent evaluation of COREMAP I suggested that coral reef ecosystem management activities supported by
the COREMAP program should take a greater development focus, placing community needs (rather than approaches
entirely devoted to conservation) at the center of coral reef ecosystem management.



                                                          3
methodology; ii) Linking ICZM methodology, climate change; and biodiversty preservation to
the national economic development processes; iii) Piloting real-world examples of how
sustainable development can succeed in the coastal area; and iv) creating a project
implementation structure that serves both the project and as an example of how the coastal zone
can be managed after the Project ends. This will be achieved in the Project by “integration�? of
government management (both technical and political), sharing of resource management by
promoting co-management with local stakeholders, and ensuring that development initiatives
within the coastal area are transparent and can be accommodated within local ICZM plans.

B.    Sectoral and Institutional Context
10.     The Project complements the vision of the Government of Morocco for rapid and
sustainable growth, improved governance, poverty eradication, and improvement of social
conditions, as implemented through the government program for the period 2012-2016. This
program includes actions to support integrated coastal zone management policies and planning,
in particular: i) the Development Program for the Nador Lagoon, including conservation of its
unique natural heritage; ii) the launch of a large-scale water purification station in Nador in June
2010; iii) approval by the Council of Government and Council of Ministers of the draft law on
Zoning, Protection, Development and Conservation of Coastal Zones (ICZM bill, still pending
before Parliament); and iv) membership in a series of international agreements in support of
coastal zone management and biodiversity conservation (e.g. the Regional Seas Barcelona
Convention for the Protection of the Marine Environment and the Coastal Region of the
Mediterranean, the Ramsar Convention for wetland conservation, and the Convention on
Biological Diversity). This project builds on the positive first steps that were taken by the
Government, and aims to demonstrate through a series of pilot projects the benefits that can be
derived from a more integrated approach.
11.     This project also represents an opportunity to complement the efforts of national
stakeholders and projects funded by other donors. Some of these outcomes could directly serve
the purpose of this project, particularly the ICZM action plans that were developed for each of
the four selected project sites in Nador, Driouch, and Berkane provinces under the Short and
Medium-term Priority Environmental Action Programme (SMAP III), and which were recently
updated to take into account climate change adaptation under the ACCMA project. In addition,
Bank activities on support to sustainable fisheries are of particular relevance: Support to small-
scale artisanal fishermen cooperatives (for which Japanese Social Development Fund support is
sought), and Adaptation of the Fisheries Sector to the Impacts of Climate Change. Moreover, the
Project’s fisheries component is directly relevant to the Government of Morocco’s current
emphasis on sustainable fisheries, which is embodied in the national strategy that was recently
adopted to that end (The “Halieutis Strategy�?). As part of Halieutis, the importance of
sustainability is highlighted, as is the need to anticipate and adapt to the growing threats of
climate change.
12.     The ICZM project also complements ongoing work under the government’s different
sectors, including, the national water strategy, the national tourism strategy (Plan Azur, Vision
2020), the national program on waste water collection and treatment - the National Sanitation
Program (NSP), and the national agricultural investment strategy (Plan Maroc Vert, or PMV).
This ICZM project thus represents a real opportunity to apply an integrated approach along the
Mediterranean cost of Morocco.


                                                 4
13.     Among these national programs, the ICZM project integrates both fiscally and technically
with the government’s National Sanitation Program (NSP), which was adopted in 2006. The
NSP provides a guiding policy framework for investments involving sanitation, pollution
control, and waste-water reuse in Morocco. The objective of the NSP is to increase the rate of
urban sanitation access from 70% to 80%, and pollution mitigation to 60%, including waste-
water treatment and waste-water reuse by 2020. The National Sanitation Program targets 260
cities covering more than 10 million inhabitants, including some in the Project area. As such, the
NSP will upgrade and expand waste-water collection and waste water treatment systems in the
cities and towns in the Project area along the Mediterranean coast. The ICZM project will
increase awareness and strengthen capacity building in the local governments and communities
of the coast to systematically address needed waste-water management, reuse and pollution
control, which integrates with and improves the implementation success rate of planned
depollution infrastructures in the Project area.
14.     The approved budget for the NSP (2012-2017) includes US$ 18 million assigned to five
specific investment projects in the Project area along the eastern Mediterranean coast. The ICZM
project will incorporate the ICZM planning approach into the implementation of these projects
and programs of NSP and heavily publicize the positive lessons of pollution control activities in
the coastal area. As Project pilots demonstrate the value of linkages between ICZM and national
investments in pollution control, the NSP will be strategically placed to scale up and share good
practices into other coastal areas of Morocco.6 The NSP will be the main disbursement channel
for the Government’s contribution to paralell financing for activities under the GEF ICZM
Project. It also provides a technical pool of Government expertise that will be tapped during
Project implementation. While the NSP pollution control investments are seen as having the
most important positive impacts on the Moroccan Mediterranean Coast in general, it also has
significant short and long-term benefits to the Mediterranean and other coastal countries. It
therefore serves not only as paralell financing of this Project but also as a link between the
Project and the GEF’s regional Sustainable Mediterranean Program.7


    C. Higher Level Objectives to which the Project Contributes

15.     The Mediterranean coastal zone in Morocco is an economic engine of national economic
growth. Bound by the Mediterranean Large Marine Ecosystem (LME), Morocco and other
coastal countries face interlinked challenges of managing shared marine resources. To respond
to the continued environmental challenges facing these countries, the Sustainable MED program
takes the next step in addressing long-term, cooperative, regional management by linking
resource management to support for an environmentally and socially sustainable economic
development that recognizes the intrinsic value of biodiversity and ecologically sensitive areas.


6
  Morocco has the coastline of 3,500km, which includes 500km by the Mediterranean Sea.
7
  The Government of Morocco also expects to invest another US$ 20 million in the ICZM Project through its “Plan
Maroc Vert�? that is implemented under the Ministry of Agriculture. This investment is specific to the Project’s
implementation areas along the Mediterranean Coast and serves as a pilot within the Project for demonstrating
linkages between the environmentally and socially sustainable Spatial Development Planning funded by the Project
and investments by the Ministry of Agriculture in alternative crops and cropping methods. Spatial Development
Planning pilots demonstrate that offsite agricultural impacts on the coast and the Mediterranean Sea can be
ameliorated without local environmental, social or livelihood impacts.


                                                       5
 16.     This project fits within the “Sustainable MED�? program, which is supported by the GEF
 and implemented by the World Bank. Morocco and other participating countries share a vision
 that proper national stewardship of the coastal area, and economic development therein, benefit
 not only the country implementing these strategies, but all other coastal countries of the
 Mediterranean.
 17.     In this context, the project’s higher-level objective is to contribute to the sustainability of
 natural resources base in the Mediterranean region within the Sustainable MED program. This
 project will contribute to the regional effort in addressing the issues raised in the Trans-boundary
 Action Plan and priorities defined in the Strategic Action Programs. The project will thus support
 the Government of Morocco as it pilots ICZM approach and coordinates with other countries in
 the region. Indeed, ICZM is identified as a key component in the 2012 Med Report, issued in
 December 2011.8 The project will also help Morocco explore innovative methods and measures
 for the sustainable development of the coastal zone in a changing climate, a top priority given the
 challenges caused by climate variability: longer lasting droughts, more aggressive floods, higher
 temperatures, and beach and soil erosion.
 18.    This project is fully aligned with the priorities and objectives outlined in the Country
 Partnership Strategy (CPS) for the period of 2010-2013 discussed by the Board on December 30,
 2009 and the CPS Progress Report to be discussed on June 12, 2012. One of the three pillars of
 the CPS is sustainable development in a changing climate. By targeting capacity building for
 sub-national levels of government and for local associations and cooperatives, this project
 responds to the three long-term development challenges identified in the CPS: (i) achieving
 higher growth and job creation; (ii) reducing social disparities; and (iii) ensuring sustainability.
 The Bank is thus strategically positioned to help with this project within the framework of the
 CPS.


II.    PROJECT DEVELOPMENT OBJECTIVES

       PDO

 19.     The objective of the Project is to pilot the application of the integrated coastal zone
 management (ICZM) approach in the project area on the eastern Mediterranean coast of
 Morocco. ICZM implemented at local level by all users of the coastal resources will leverage
 rural pollution reduction and protection of biodiversity and ecologically sensitive areas.
       PDO Level Results Indicators
 20.      Proposed key results include:
          (a) Number of approved local development plans that are revised to incorporate the
              ICZM approach; and




 8
  Toward Green Growth in Mediterranean Countries: Implementing Policies to Enhance the Productivity of Natural
 Assets, 2012 MED Report, December 2011.


                                                       6
     (b) Formulation and implementation of a public awareness campaign for the promotion of
         biodiversity conservation through co-management9 of the Ramsar wetlands of the
         Moulouya estuary.

III. PROJECT DESCRIPTION

 21.     Based on the lessons learned from successful coastal projects around the globe, the
 Project adopts a similar approach, which recognizes that environmental protection is rarely
 sustainable over the long term without linkages to economic development.
 22.    Geographical scope: Focused activities will be piloted in four project sites within the
 Oriental Region (administrative unit) of Morocco (see Figure 1 in Annex 2). These are:
          (a) The coast of Saidia-Ras El Ma, including the Ramsar site of the Moulouya River
              estuary. This area comprises two rural communes and two urban centers covering
              part of two provinces:
                 a. Nador Province: Urban center of Ras el Ma; and
                 b. Berkane Province: rural communes of Madagh, Laatamna, and the urban
                     center of Saidia;
          (b) The rural commune of Beni Chiker, including the SBEI of Cap des Trois Fourches
              and a part of the SBEI Gourougou Mountain. This commune is located in the Nador
              Province;
          (c) The Nador Lagoon. This area comprises two municipalities and two rural
              communes, all located within the Nador Province:
                 a. Municipalities of Nador and Beni Nsar;
                 b. Rural communes of Bouareg and Arekmane; and
          (d) The rural commune of Boudinar, located in the Driouech Province.

 23.     Rationale for the choice of Project area: The choice of Project area along the
 Mediterranean coast reflects the priorities of the Government of Morocco, and enables the
 Project to build on the results of projects funded by other donors (European Union,
 IDRC/DFID). The general area of the Project is the Eastern Mediterranean Coast (EMC), which
 is home to a number of ecologically important sites, recognized either as Ramsar sites (wetlands
 of international importance), or SBIE sites10. Selection of the four specific pilot areas was
 finalized after a series of public consultations with local stakeholders that were held to gauge
 their interest, and to select from a list of activities previously identified in the Coastal
 Management Action Plans,11 those that would be funded under the Project. The four sites were
 also selected for pilot projects because local conditions are indicative of the different resource-
 use challenges facing the whole of the Moroccan Mediterranean coast.


 9
   Co-management is a term that describes government's delegation of a specified set of its responsibilities to
 manage, including enforcement of regulations limiting use of natural resource, to local stakeholders (i.e. those that
 commonly "own" and use the resource). The resource is therefore "co-managed" by both the Government and
 empowered local stakeholders.
 10
    Sites of Biological and Ecological Interest – an official designation of the Government of Morocco indicating the
 intention to establish a future protected area on the site.
 11
    Coastal Management Plans of Action (also known as ICZM Plans of Action) were developed by local
 communities under the SMAP III financed by EU.


                                                           7
24.     Project Beneficiaries: The direct beneficiaries for this project range from small holder
farmers and fishermen to private sector investors, as project activities seek to promote more
profitable and sustainable use of natural resources while maintaining biodiversity and ecological
values upon which tourism is based. At the community level, primary beneficiaries are expected
to be small holder farmers, subsistence and semi-industrial fishermen, local residents employed
in the tourism sector, women’s groups involved in apiculture, young people who will be involved
in ecotourism activities and community planners who will benefit from project investment in
ICZM and linked spatial development planning. Altogether, direct beneficiaries are expected to
number about 7,500. In addition, the project is also expected to bring indirect benefits to all the
inhabitants of the project area. The population of the targeted areas is estimated at approximately
300,000 according to the last census on population and habitats (2004).
25.    Institutional beneficiaries of the ICZM project will include decision makers at the
national and regional levels, civil society, boards of communes, etc. who will gain experience in
applying the ICZM approach.


A.     Project Components
26.     Rationale and linkage between components. Project investment will occur through
three linked components. Earliest investments will come through Component 1, which largely
targets capacity building to enable the undertaking of technical activities under Component 2.
Component 2 activities come later in the project, once the Project Management Unit and the
Bank are confident that the technical skills, legal basis, and community involvement in support
of coastal resource management are strong enough to ensure successful implementation.
Component 3 supports project management and project sustainability.
27.     Participatory selection of activities. The activities to be implemented were selected
from existing Coastal Management Action Plans funded by other donors and took into account
the impacts of climate change. Participatory consultative meetings, sector-based interviews,
visits to proposed project locations, and discussions with beneficiaries were undertaken
throughout the identification of activities.
28.  A more detailed project description is found in Annex 2.                          Project components are
summarized below.
Component 1: Capacity building and institutional strengthening to incorporate the ICZM
approach into local development planning (GEF US$ 0.677 M). MEMEE (via DE) will be
responsible for implementation of Component 1.
29.     The objective of this component is to strengthen the capacity of government institutions
and local communities to incorporate the ICZM approach into their local development plans.
Under Article 36 of the Moroccan Communal Charter (Charte communale12), each commune
currently prepares and maintains its own local development plan, which is intended to guide its
development. These currently do not explicitly incorporate an ICZM approach. The plans are
prepared by the elected President of each commune in consultation with the population, are
developed by the community for the community, serve as a means of guiding development

12
  See the law published on February 18, 2009, article 36. (La loi n°17-08 modifiant et complétant la loi n° 78-00
portant charte communale).


                                                         8
within the community itself, and as a budgeting exercise in cooperation with higher levels of
government. These communal development plans are not meant as a means of restricting access
to lands and natural resources, or of constraining economic activity within each community.
30.   The investments of the Project will finance consultant services, training and workshops,
non-consultant services, works, and goods to be used in support of:
         (a) Promoting awareness of, and building capacity in, the application of the ICZM
         approach by provincial and local governments and local stakeholders in the Project Area,
         through the following: (i) carrying out of workshops; and (ii) carrying out of public
         education campaigns and the provision of training for trainers in primary and secondary
         education;
         (b) Mainstreaming the ICZM approach in the preparation of the development plan of six
         selected communes in the Project Area through the provision of technical advisory
         services to: (i) the communities located on the territory of the selected communes to
         support the preparation of their village-level economic development planning under the
         ICZM approach; and (ii) provincial governments to familiarize them with the outputs of
         such ICZM approach based development plans; and
         (c) Piloting spatial development planning method13 to prepare the communal
         development plans for one of the six communes referred to in (b) above through the
         carrying out of workshops and the provision of technical advisory services to the
         communities located on the territory of the selected communes.


              Expected results: The government and community participants have the awareness,
              tools, and background information they need to participate meaningfully in the
              formulation of an economic development plan at the local level. Three Specific
              permanent Coastal Commissions (Commission du Littoral) at provincial levels
              acquire the knowledge needed to become effective and to conduct regular bi-annual
              meetings.     Six communal development plans (including one spatial plan)
              incorporating local ICZM activities are prepared and/or revised. Public education
              material is prepared and distributed for use in the project area (e.g. guides, tool kits,
              website for ICZM information, etc.).

Component 2: Investments to improve coastal resource management and livelihoods
through co-management approach (GEF contribution: US$ 4.119 M)
31.     The objective of this component is to support specific and appropriate investments that
demonstrate the application of key tools available for use in an ICZM approach, within the
project area. This component is divided into four sub-components, which will: (i) improve
conservation and management of sensitive coastal areas; (ii) improve fisheries management; (iii)

13
   The purpose of spatial planning is to help mainstream ecosystem-based management (an ICZM approach) by
finding space for biodiversity conservation and sustainable economic development in marine and coastal
environments. One way to do this is through a locally based, participatory process that identifies, through technical
evaluation, what the land and marine units are “capable�? of supporting and then determining which of these options
“should�? be done by seeking input from local stakeholders and users of the resources. Spatial planning is a public
process of analyzing and allocating the spatial and temporal distribution of human activities in coastal and marine
areas to achieve ecological, economic and social objectives through a political process.


                                                          9
diversify income-generating activities from agriculture; and (iv) promote the development of
ecotourism.
32.    The four sub-components are detailed as follows:
       2.1: Improved conservation and management of sensitive coastal areas. This sub-
       component will support: (a) fixation and restoration of about 20 ha of degraded wetland
       and coastal dune ecosystems at Moulouya; (b) carrying out an hydrological study of the
       Moulouya SBEI and the installation of water pipes to re-establish the flow of water from
       the Ain Chebbak spring to wetlands located in Douar Cherarba; (c) updating the
       ecological and social economic diagnostic of the Moulouya SBEI; and (d) preparation
       and implementation of a public awareness campaign for the conservation of the
       Moulouya SBEI. This sub-component will be implemented by HCWFFAD.

       Expected results: This subcomponent will result in the formulation of a coordinated
       public awareness action plan for the Moulouya SBEI, and the execution of works called
       for in that plan, including the fixation and restoration of 20 ha of coastal dunes,
       restoration of water flow toward wetlands, etc.

       In parallel, the HCWFFAD will invest some of its own resources in the planting of trees
       and management of watersheds, restoration of ecosystems and the construction of
       recreation facilities in the Moulouya-Saidia pilot site.

       2.2: Improved fisheries management. This sub-component will support (a) carrying
       out the feasibility study and preparation of the related Site-Specific ESIA and Site-
       Specific ESMP regarding the establishment on a pilot basis of one small artificial reef,
       and establishment of such reef, including the provision of technical advisory services for
       the co-management of such reef by the users of such reef; (b) carrying out the feasibility
       study and preparation of the related Site-Specific ESIA and Site-Specific ESMP
       regarding the establishment on a pilot basis of a small seaweed farm and seaweed
       processing and commercialization facilities, and establishment of such farm and seaweed
       processing and commercialization facilities; and (c) carrying out the feasibility study and
       preparation of the related Site-Specific ESIA and Site-Specific ESMP regarding the
       establishment on a pilot basis of one small shellfish farm and shellfish processing and
       commercialization facilities, and establishment of such farm and shellfish processing and
       commercialization facilities.

       Expected results: One artificial reef deployed and managed by local users under co-
       management regimes; seaweed farm feasibility confirmed and a small pilot farm
       developed along with village-level processing and associated activities; shellfish farm
       feasibility confirmed and one small pilot farm developed along with village-level
       processing and associated activities; and pilot public and private partnership to facilitate
       long-term viability of aquaculture activities.

       In parallel, government will finance with its own resources activities complementary to
       the investments described above, including the construction of small-scale infrastructure
       to support artisanal fishing (e.g. kiosks for the sale of fish, insulated boxes and ice, small




                                                10
       fuelling facilities, latrines, etc.) at the port of Ras Kebdana in Nador province. This sub-
       component (a) will be implemented by DMF, (b) and (c) by NADA.

       2.3: Soil and water conservation and income-generating activity. This sub-
       component will support (a) implementation of soil and water conservation measures in
       the communes of Beni Chiker and Boudinar; and (b) promotion of apiculture by
       supplying local women’s groups with hives and other equipment and technical advisory
       services.

       Expected results: The subcomponent is expected to create three functioning apicultural
       cooperatives; and restoration of soil and planting of fruit trees over a total of 500 ha in
       two communes.

       In parallel, the government will finance with its own resources under the NSP
       complementary to the investments described above which also aim to support rational
       utilisation of water, control of diffuse agricultural pollution through outreaching of good
       practices in using fertilisers and pesticides to farmers, subsistence agriculture and rural
       livelihoods. The NSP two stations of waste-water treatment will be located at Karia
       Arekmane and Ferkhana, and one station of waste collection and treatment will be at Ras
       El Ma. This sub-component will be executed by ADA.

       2.4: Promotion of ecotourism. This sub-component will support: (a) a feasibility study
       on ecotourism; (b) rehabilitation and furnishing of about six small-scale tourist lodges;
       and (c) training of tourist operators and promotion of tourist activities. This sub-
       component will be executed by MT.

       Expected results: The subcomponent will support the restoration of up to six small-scale
       tourist lodges and the training of tour operators.

       In parallel, the government will finance with its own resources activities under the NSP
       projects which are located in areas where tourism is an important sector and are one
       network of sanitation of waste-water for the tourist complex in Saidia, and a pipe to
       discharge the purified waste-water from the treatments station to Oued Cheraa. This
       activity does not involve any GEF financing. It receives financing from the Government
       of Morocco only, and is complementary to project activities.

Component 3: Project management and M&E (GEF contribution: US$ 0.384 M; Government
contribution US$ 0.625 M)
33.    The objective of this component is to ensure adequate management and coordination of
project activities by supporting capacity building within, and activities of, the PMU. This
component will finance consultant services, goods, training, non-consultant services and
incremental operating costs needed for:
       (a) Supporting the PMU, including for the implementation of the ESIA, the ESMP, the
       Site-Specific ESIAs and the Site-Specific ESMPs, the monitoring and evaluation of the
       Project and the coordination and knowledge sharing activities among the various entities
       involved in the implementation of the Project; and



                                               11
         (b) Financing of the Incremental Operating Costs for the Project.

         Expected results: The PMU is established and operational, a monitoring and evaluation
         system is established and operational over the life of the project and a project website
         created and maintained.

      B. Project Financing

Lending Instrument

34.      The Morocco ICZM Project will be a Specific Investment Grant.

Project Cost and Financing

35.     The Government of Morocco will provide funding totalling US$20 million to support a
US$5.18 million grant from the GEF. The Government contribution consists of (i) parallel
financing in the amount of US$19.375 million through related new investments under existing
projects and programs, such as the National Sanitation Program, forest works and fisheries
projects in the oriental region; ii) direct co-financing to the project; and iii) in-kind contribution
from the participating governmental agencies. The project also expects in-kind contributions
from beneficiaries to match the project grants in agricultural and fisheries activities.

Table 1: Project Cost
                                         Project cost (including                       Government co-
        Project Components                                         GEF Financing
                                         Government financing)                            financing
1. Capacity building and institutional        0.912 million         0.677 million       0.235 million
strengthening to incorporate the ICZM
approach into local development
planning
2. Investments to improve coastal            23.259 million         4.119 million        19.14 million
resource management and livelihoods
through co-management
3. Project management and M&E                 1.009 million         0.384 million        0.625 million

Total Project Costs                           25.18 million         5.18 million         0.625 million

                         14
Government Financing                          20.00 million




36.     Incremental operating costs15 of US$ 0.384 million under Component 3 will be covered
by the budget of the Project. The implementation of Component 3 will also be contributed by the


14
  Government parallel financing for this project includes activities underway in or near the project areas that are
complementary to the project activities and under the ICZM approach, which are financed entirely through the
national budget. These activities include: (i) a program of rehabilitation of signage and traffic control measures for
SBEIs, implemented by HCWFFAD; (ii) improvements to the artisanal fishing at the port of Ras Kebdana; (iii)
investments related to the NSP projects including: two waste-water treatment stations at Karia Arekmane and
Ferkhana; one waste collection and treatment station at Ras El Ma; one waste-water sanitation network for the
tourist complex in Saidia; and a pipe to discharge purified waste-water from the treatment station in Berkane to
Oued Cheraa.


                                                              12
MEMWE through government direct co-financing of US$ 0.625 million to the project. The total
budget for Component 3 is US$ 1.009 million.

      C. Lessons Learned and Reflected in the Project Design

37.     The project preparation team reviewed and studied good practices and lessons learned
from a number of similar projects, including the China Sustainable Coastal Resources
Development Project (SCRD - P003539), the Indonesia Coral Reef Rehabilitation and
Management Project phase 1 (COREMAP - P036048), the Tanzania Marine and Coastal
Environment Management project (MACEMP - P082492), the Kenya Coastal Development
Project (KCDP - P094692), and the recent Vietnam Coastal Resource Sustainable Development
project (P118979). Lessons have also been considered from related projects and programs
financed by the Moroccan Government and other donors.
38.      Main lessons learned and reflected in the project preparation and design include:
         (a) Building strong ownership by different Government agencies and sectors through
             consultations and participation in the project preparation. Cooperation among the
             relevant departments is the back-up force for future success of the Project under the
             ICZM approach.
         (b) This project will focus on pilot approaches and demonstration schemes to improve
             people’s life by increasing income for farmers/fishermen, and creating jobs for
             vulnerable groups through diversification of the coastal economy and increasing
             resilience of vulnerable ecosystems and local communities to climate change risks.
         (c) Co-management approach between government and local communities with broader
             participation from women and youth and management by farmers/fishermen
             associations and professional cooperatives.
         (d) Sustainability through the creation of a maintenance mechanism for each project
             activity has been stressed as a key aspect for the project design of the project
             activities based on Moroccan experiences and those from similar World Bank
             projects.
         (e) Climate change adaptation is an integral part of this coastal management project. This
             is particularly based on the increasing trend of climate change in coastal areas and on
             China’s CSRD project, which learned a hard lesson from not anticipating the
             occurrence of extreme natural disasters (typhoons) and heavy losses registered in
             some of the project areas.




15
   “Incremental Operating Costs�? cover the incremental operating costs incurred by the MEMWE on account of
project implementation, and comprise: communication, including postage and internet; procurement related
advertising costs; local transportation and fuel; office equipment and supplies; project related travel and per diem
allowance including accommodation and local transportation.


                                                          13
                           D. Institutional and Implementation Arrangements

Figure 1: Project Implementation Arrangements

                                Steering                   Implementation                           Advisory

                                                                      Other partners:          Technical Coordination
                                                      Project
                                                                                                    Committee
      National Level




                                                  Management Unit
                                                                        HCWFFAD
                                MEMWE                 (PMU)
                                                                       MAMF (DMF,
                                                   Central Office
                                                                       NADA, ADA)              National Environmental
                                                                                                    Observatory
                                                  Hosted within DE
                                                                         MEF, MT
                                                  (under MEMWE)




                             Specific Permanent       Project             Regional
     Regional/Provincial




                                  Coastal         Management Unit    representatives of           Eastern Region
                               Commissions            (PMU)            other partners:             Sustainable
                                                                                                   Development
                                                   Regional Office      HCWFFAD                    Observatory
                              Walis / Heads of
                                                                       MAMF (DMF,
                            regional government                        NADA, ADA,
                                                                         RDA)
     Commune level




                                                  Associations and
                                                                        Communes
                                                   Cooperatives




39.     The Ministry of Energy, Mines, Water and the Environment, through the PMU, will have
the overall responsibility for implementation of Project components 1 and 3, and for the overall
coordination of the implementation of the entire Project, including responsibility for financial
management, and procurement. As is the case for any other Word Bank project in Morocco, the
Ministry of General Affairs and Governance (MAGG) has the mandate to oversee general
project implementation, and ensure directions chosen, actions undertaken, and results achieved
are in accordance with relevant government policies and programs, and with project documents
and agreements. Besides the PMU, the other mechanisms and entities involved in project
implementation include: the Technical Coordination Committee (TCC) chaired by the MEMWE
(through its Department of Environment), various partner agencies or entities,16 and local
community groups or associations. The Project implementation will require collaboration
between institutions at the local, provincial/regional, and national levels. The roles and

16
 The partner entities include: MAGG, MEF, High Commission for Water, Forestry and the Fight Against
Desertification (HCWFFAD), National Aquaculture Development Agency (NADA), Agricultural Development
Agency (ADA), Ministry of Tourism (MT), and Municipal and Regional councils in the Project areas.


                                                                                          14
responsibilities of each of these entities are summarized below and described in more detail in
Annex 3.
40.     Technical Coordination Committee (TCC) (Comité de Coordination Technique),
which has been established for the purpose of ICZM under the chairmanship of MEMWE, will
serve as a technical forum for MEMWE, MAGG, MEF, HCWFFAD, MAMF, NADA, ADA and
MT in which such entities shall harmonize their actions regarding the implementation of the
Project, share knowledge on Project implementation, and ensure that their annual work plans and
budgets are well integrated with one another.
41.     Project Management Unit. A project management unit (PMU) will be established
within the Department of the Environment of the Ministry of Energy, Mines, Water and the
Environment. The PMU will have both the responsibility for day-to-day implementation of the
project and overall coordination for project implementation, with support, guidance and feedback
from the MAGG for higher-level inter-institutional issues, and from the Technical Coordination
Committee on inter-agency coordination and cooperation, work planning, and budgeting.
42.      The PMU will be solely responsible for handling all financial transactions and
procurement activities. It will be responsible for consolidating annual workplans, project
monitoring guides, and the various progress reports required by the World Bank. The PMU will
also ensure efficient coordination between project partners. It will be responsible for promoting
partnerships at the regional and local levels and facilitating the integration of ICZM project
activities with other partners’ development programs in the targeted areas. The PMU will have a
central office that will operate out of the main offices of the DE in Rabat and a Regional office
operating out of the regional DE office in Oujda.
43.     The ICZM project has been nationally developed under the direct supervision of the
Director of the Studies, Planning and Strategy Directorate (Direction des Etudes, de la
Planification et de la Prospective) of the DE, within MEMWE. The project’s Director should
have at least the rank of Director in the DE administrative hierarchy. Under the project Director,
the PMU will be headed by a Project Manager, expected be a senior professional civil servant of
the MEMWE (DE), and he will be assisted by a Project Coordinator (full-time consultant). The
Project Manager will oversee project implementation and monitoring at the national level.
Specifically, the Project Manager will be responsible for consolidating annual workplans, Project
monitoring guides, and the various progress reports required by the World Bank. The Project
Manager will also ensure efficient coordination between project partners, particularly on the
exchange of information and organization of common activities. The Project Coordinator will be
a technical expert in ICZM with experience in project management, and will support the Project
Director throughout project implementation, and will assume responsibilities for the application
of environmental and social safeguards both centrally and in the region. The PMU will also
include a financial management specialist.
44.     At the regional level, the Regional Representative of the DE in Oujda will be a member
of the PMU and serve as its Regional Project Manager in the region. The Regional Project
Manager will be assisted by a Regional Project Coordinator. The regional office of the PMU will
be responsible for coordinating the implementation of project activities to be implemented by the
DE across all four project pilot areas and will work in close collaboration with the regional staff
of the other participating partners and ministries implementing activities under this project.




                                                15
45.      Other participating partners entities. Other participating partner ministries and/or
institutions will be mostly responsible for the technical implementation of selected project
activities under component 2 and in accordance with the Implementation Conventions to be
signed with MEMWE. These partner entities include.
            (a) The High Commission for Water, Forestry and the Fight Against Desertification
            (HCWFFAD);
            (b) The Department of Maritime Fisheries (DMF) of the Ministry of Agriculture and
            Maritime Fisheries (MAMF) supported by the National Aquaculture Development
            Agency (NADA);
            (c) The Agricultural Development Agency (ADA); and
            (d) The Ministry of Tourism (MT).
46.      Other partner entities also include:
            (a) The Specific Permanent Coastal Commission in each of the provinces covered by
            the Project;
            (b) The National Environmental Observatory (NEO) and Eastern Region Sustainable
            Development Observatory (ERSDO);
            (c) The Wali and the provincial Governors of the Eastern region; and
            (d) NGOs (associations, cooperatives and other representatives of civil society).
47.    Operational procedures and Operations Manual. The Project will be implemented in full
compliance with the detailed procedures set out in the Project Operations Manual.

      E. Results Monitoring and Evaluation

Monitoring
48.     The PMU will be responsible for the monitoring and evaluation (M&E) of the project,
including analysis of M&E data and the finalization of progress reports. To this end, it will work
closely with the relevant staff and units of the other ministries and agencies participating in the
Project (i.e. DMF, NADA, ADA, RDA, HCWFFAD, and MT). These ministries and agencies
will provide all relevant data concerning the performance of the activities for which they are
responsible to DE for the purposes of M&E. The PMU will also be supported in this by the
ERSDO, the DE entity responsible for collection and analysis of environmental data. The
Observatoire Régional, in turn, may seek assistance from its national supervising authority, the
National Environmental Observatory, as needed.
49.     The PMU will have the overall responsibility for the preparation of Project reports and
their transmission to the World Bank each semester. The PMU will monitor the Project’s
intermediate results indicators (see Annex 1) and provide an update of these indicators to be
included in the Project’s regular reports per semester. Data collection, verification, and initial
analyses will be the responsibility of the regional office of the DE, with technical support from
the Observatoire Régional. The regional DE staff and/or consultants will be responsible for
making regular visits to the project area to monitor progress and collect data on environmental
performance. Funds for M&E will be drawn from Component 3. The PMU is responsible for


                                                16
incorporating detailed monitoring instructions in the Project Operations Manual. The following
table presents the reports, the involved entities, and the related calendar.
Table 2: M&E: Reports
           Prepared Transmitt              Consolida                 Transmitt Transmitt
Report                        Date                     Date                              Date
           by:        ed to:               ted by:                   ed to     ed to
                              Each                     Each
                              semester,                semester,
           DE
                              within 15                within 30
           regional
                      PMU     days after               days after
           office,                                                                       Each
                              the end of               the end of
           ERSDO                                                                         semester,
                              the                      the
                                                                                         within 45
Project                       semester                 semester
                                           PMU                       Recipient   WB      days after
Report                        Each
                                                                                         the end of
                              semester,
                                                                                         the
                              within 15
           Partner                                                                       semester
                      PMU     days after
           agencies
                              the end of
                              the
                              semester
                              Each                     Each                              Each
                              semester,                semester,                         semester,
Interim
                              within 15                within 30                         within 45
Unaudited                                                            Recipient
           PMU                days after   PMU         days after                WB      days after
Financial
                              the end of               the end of                        the end of
Report
                              the                      the                               the
                              semester                 semester                          semester
Financial
                              Each year,               Each year,    Recipient           Each year,
Statement PMU                              PMU                                   WB
                              by May 1st               by June 1st                       by July 1st
(FS)



50.     Regional PMU staff will share the semester reports with the local cooperatives involved
in co-management. This is for the benefit of informing the decision-making of those
cooperatives and for seeking their feedback on the monitoring and evaluation of the project as it
pertains to their activities.

Evaluation

51.     Substantial baseline data exist in the form of studies conducted on coastal zone
management in the Eastern region, including output from previous projects such MedWetCoast,
SMAP III and ACCMA. Project baseline data, reports and lessons learned from ongoing and
previous projects comprising Project parallel finance that are executed by other agencies
participating in the Project shall be presented to the PMU within six months of project
effectiveness.
52.     The PMU will be responsible for contracting independent consultants to conduct the mid-
term and end-of-project evaluations, including updated surveys of socioeconomic conditions and
fisheries and agricultural resources in the project area. The mid-term evaluation will assess the
operational aspects of the project, namely progress in the completion of activities and the
achievement of the PDO. The mid-term evaluation will also include recommendations for


                                               17
corrective measures, if needed, for project implementation to remain on track. The end-of-project
evaluation will have the same scope as the mid-term review but will focus particularly on project
outcomes and results at the local, regional, and national level. The end-of-project evaluation will
also provide recommendations in terms of M&E and replication of best practices, especially for
the sustainable management of coastal resources and the preservation of internationally
recognized wetlands. Terms of reference for the mid-term and end-of-project reviews will be
agreed upon with the World Bank and included in the Project Operations Manual.

      F. Sustainability

53.     Sustainability is critically important and a key consideration in Project design.
Specifically, the Project is designed to integrate and coordinate the actions of various
government agencies with mandates to manage different sectors in the coast.                  The
implementation structures to be set up to that end under the Project are expected to remain in
place, either as they are or under different names, and to carry on functioning after the project
finishes.
54.      Special characteristics that make the project sustainable include:
             (a) The Project helps address the Moroccan Government’s priority goal of
             sustainable management of coastal resources for rapid and sustainable growth,
             improved governance, poverty eradication, and better social conditions. This also
             includes piloting the application of the draft ICZM bill once it becomes law, and
             direct involvement of the project in the government long-term programs and
             strategies – National Sanitation Program, Plan Maroc Vert, Vision 2020 of tourism,
             the national water strategy and the Plan Halieutis for sustainable fisheries;
             (b) The Project has support from the local stakeholders who are eager to see action
             follow from the many studies and consultations conducted in the past. The Project
             also promotes locally based development planning, which places special emphasis on
             local stakeholders;
             (c) The Project will institutionalize the ICZM approach that incorporates climate
             change and planning for adapting to its impacts into local economic development
             plans;
             (d) The Project expects to encourage the creation of jobs and diversify the local
             economy because it focuses on environmentally and socially sustainable economic
             development and co-management of fisheries, agriculture and tourism resources, thus
             strengthening and improving cost-efficiency in the conservation of coastal
             ecosystems;
             (e) The Project will also encourage entrepreneurship of micro, small and medium-
             sized enterprises through capacity building and piloting public and private
             partnerships; and
             (f) Improved conservation and management of natural resources will strengthen and
             sustain local economies, particularly those based on tourism, fisheries and agriculture.
             It will also strengthen the ability of local communities to adapt to the impacts of
             climate change and climate variability.


                                                  18
 55.      The Project is also highly sustainable because its beneficiaries do not see the Project as a
 government “handout�?.          Direct assistance to stakeholders generally requires matching
 contributions from participating beneficiaries, which helps to ensure the sustainability of these
 activities.

IV. KEY RISKS AND MITIGATION MEASURES

    A. Risk Ratings Summary Table

               1.Project Stakeholder Risk
                    Stakeholder Risk                            Rating: Low
               2. Implementing Agency (IA) Risks
                    Capacity                                    Rating: Substantial
                    Governance                                  Rating: Moderate
               3. Project Risk
                    Design                                      Rating: Low
                    Social and Environmental                    Rating: Moderate
                    Program and Donor                           Rating: Low
                    Delivery Monitoring and Sustainability      Rating: Moderate
               4. Overall Risk                                  Rating: Moderate



    B. Overall Risk Rating Explanation

 56.     Potential risks are summarized in the Risk Ratings Summary Table above and discussed
 in the Operational Risk Assessment Framework (ORAF) in Annex 4. The overall implementing
 risk for this project is rated moderate. However there is a high capacity risk due primarily to the
 inexperience of the Agency in managing World Bank projects. The Project activities by
 themselves do not pose major technical difficulties. The environmental and social project risks
 are rated as medium. Regarding social safeguards, no activity involving involuntary resettlement
 will be financed under this project. Any activity involving land will only be carried out on public
 lands from which resettlement is not required or on private lands where voluntary participation
 of the landholder is documented in writing. The Project will not involve involuntary land taking
 resulting in relocation or loss of shelter; loss of assets or access to assets; or loss of income
 sources or means of livelihood (whether or not the affected person needs to move to another
 location). The development planning to incorporate ICZM principles at the level of the
 communes makes use of existing institutions or expands upon them. The government’s strong
 commitment to the ICZM approach is helpful in lending weight to this project. The overall
 project risks are rated moderate. Identified risks are manageable and mitigation measures have
 been planned.




                                                     19
V.   APPRAISAL SUMMARY

     A. Economic and Financial Analyses

 57.     The US$5.18 million GEF grant will strengthen the capacity of relevant stakeholders to
 incorporate ICZM methodology and climate change adaptation into local development planning
 in the eastern Mediterranean coastal areas of Morocco. While about 80 percent of the grant will
 be used to test win-win approaches to improve the quality of life of coastal communities through
 environmentally and socially sustainable use of natural resources, the project will also pilot
 climate change adaptation among farmers and fishermen to demonstrate comparative advantages
 of ICZM when compared to business as usual.
 58.     These activities are closely linked with relevant existing government projects and
 programs, such as the National Sanitation Program, fisheries projects, waste-water treatment and
 wetland conservation programs. Activities already identified under the national plan for waste-
 water treatment, the Plan Maroc Vert, together with contribution from the fisheries, water and
 forestry sectors bring total Government parallel financing of the Project to more than US$20
 million.
 59.     Since this is a GEF grant, incremental Cost Analysis (see Annex 6) was conducted in lieu
 of standard economic and financial rates of return.

     B. Technical

 60.     The Project aims to help develop an appropriate skills mix, associated technical and
 physical capacity building, and policies and guidelines needed for effective piloting of ICZM and
 climate change adaptation. Identification of these is based on: i) national priority needs and on-
 going and previous work undertaken by the Government of Morocco and its donors, including
 the draft ICZM bill and the coastal zone management actions plans under SMAP III; and ii) on
 the need to improve governance and transparent resource management. This includes promotion
 of cooperation among different sectors and local communities in natural resources management -
 including the most vulnerable groups, such as women and youths.
 Some of the most important areas to be covered are:
        (a) Restoration of wetland ecosystems and coastal dunes at the estuary of the Moulouya
            river through: i) restoration of 20 ha of coastal dunes; and ii) rehabilitation of the
            hydrological functions of the Moulouya SBEI through conducting studies and
            subsequent installation of water pipes to drain water from the Ain Chebbak spring to
            wetlands located in the douar Cherarba;

        (b) Fisheries management improvements through support to artisanal fishermen,
            including the deployment of a pilot project an artificial reef, and seaweed and
            shellfish farming. However, the Project takes a precautionary approach and requires
            preliminary studies before actual field trials are allowed to begin;

        (c) Agriculture and diversification through environmentally and socially sustainable
            revenue generating activities will include plantation of fruit trees and land
            rehabilitation. Specific techniques include: i) planting of fruit trees adapted to local


                                                20
            climatic conditions (olive, carob and almond trees; ii) building rock terraces on
            private eroded land to increase the arable surface area, and iii) mitigating water
            erosion effects by improving water conservation.


   C. Financial Management

61.     The financial management system within the Ministry of Energy, Mines, Water and the
Environment (MEMWE), through its Department of the Environment (DE) was appraised to
determine if it complies with the requirements of the Bank in respect to OP/BP10.02. The
financial management assessment of the Department of Environment covered the areas of
accounting and financial management as well as the reporting and auditing processes of the
Project. The financial management system in place including necessary arrangements to respond
to the needs of the financial monitoring of the Project, satisfies the minimum requirements of the
Bank.
62.      The assessment concluded that the DE has sufficient capacity to manage Project related
financial matters and administer grant funds. The main responsibilities will include Project
budgeting, treasury, general accounting and reporting. The FM inherent risk for the country, the
entity, and the project is considered moderate.
63.     Disbursement will be handled through the MEF following established procedures.
Interim unaudited financial report, which will cover all the activities and sources of funds of the
project, will be prepared biannually by the DE and transmitted to the World Bank 45 days after
the end of each period.
64.    The DE will ensure that interim unaudited financial reports for the Project are prepared
and furnished to the World Bank no later than forty five (45) days after the end of each calendar
semester, covering the semester, in form and substance satisfactory to the World Bank.
65.     The DE shall have its Financial Statements for the Project audited in accordance with the
provisions of Section 2.07 (b) of the Standard Conditions. Each such audit of the Financial
Statements shall cover the period of one fiscal year of the Recipient. The audited Financial
Statements for each such period shall be provided to the World Bank no later than six months
after the end of such period.
66.     Financial flow of funds will come from the grant funds of the Bank. Financial flows
between the World Bank and the DE will be organized according to the disbursement procedures
of the Bank.

   D. Procurement

67.     Procurement within the Project is mostly for the selection of consultants for technical
assistance, capacity building, training, communication, economic studies and feasibility studies,
for goods and non-consulting services (e.g. equipment, material and office supplies for the PMU,
workshops). Works contracts are expected for activities such as rehabilitation and restoration of
degraded wetland ecosystems and coastal dunes, construction of the artificial reef, and building
of rock terraces on eroded land. The Department of the Environment (DE) will be in charge of
the Project procurement. A dedicated PMU will be set up for the implementation of the Project.


                                                21
The relevant sub-units and entities under the Ministry of Agriculture and Maritime Fisheries,
HCWFFAD and MT will be involved in the project. At the decentralized level, the provincial
directorate of the DE will also be involved in implementation of the Project, in relation with
local communities and beneficiaries. The capacity assessment carried out in June 2010, during
project preparation of the PPG showed that the DE does not have experience in implementing
Bank projects in recent years and thus staff currently in place has not been trained in Bank
procurement procedures, even though the DE benefitted in the past from other donor support
(e.g. from the EU, UNDP).
68.     The overall risk for procurement is considered substantial. This is because of: (i) the lack
of experience in Bank procedures of the DE and its staff working directly on project
implementation; and (ii) the absence of training in Bank procurement procedures for those staff.
To help better mitigate the risk and facilitate project implementation, the following measures are
recommended: (i) organization of training workshop(s) for DE and staff from all other entities
involved in the project implementation, before project effectiveness, (ii) preparation of Standard
bidding documents (SBD) for National Competitive Bidding (NCB) complying with procedures
for NCB acceptable to the Bank; and (iii) preparation of a Project Operational Manual. More
details are provided in Annex 3.

   E. Social (including Safeguards)

69.      OP/BP 4.12 on Involuntary Resettlement will not be triggered by the project as activities
involving involuntary resettlement will not be financed under this project. Any activity involving
lands will only be carried out on public lands from which resettlement is not required or on
private lands where voluntary participation of the landholder is documented in writing. The
project will not involve involuntary land taking resulting in relocation or loss of shelter; loss of
assets or access to assets; or loss of income sources or means of livelihood (whether or not the
affected person needs to move to another location). Project legal agreement has included a clause
to this end.
70.     An environmental and social impact assessment (ESIA) was prepared and has been
disclosed in country and in French on February 16, 2012, and lodged in the InfoShop after the
country’s disclosure on February 16, 2012. The ESIA identifies the impacts and mitigation
measures related to social impacts. A public consultation plan will have to be devised at the early
stages of implementation, in line with the World Bank requirements on consultations and to
make sure that all involved stakeholders are consulted and vulnerable groups are given fair
access to express their points of view. The plan should be made available to the Bank by no later
than six months after the Effective Date of the Project and the consultation plan shall be
promptly implemented as approved by the World Bank.
71.     There are no major negative social impacts expected to affect the livelihoods of artisanal
fishermen. In addition, the feasibility studies that are required will further assess the risks related
to this issue and provide specific measures to mitigate any negative social impacts. Social and
environmental impact assessments sections will also be included in the feasibility studies for the
deployment of the artificial reef and two aquaculture facilities. Special attention will be given to
the fact that the fishermen and their newly formed cooperative will have to manage the reef and
related fishing activities to ensure their livelihood. In this context, it is fundamental that open and
transparent consultations be conducted with all the involved stakeholders.


                                                  22
Vulnerable groups

72.     The Project will involve a series of revenue-generating activities under Component
2.3 that will specially address the needs of vulnerable groups. For example, it will promote
apiculture activities by supplying local women with full hives, training them in modern
beekeeping and marketing techniques and teaching them how to organize in associations or
cooperatives (Sites of Saidia Ras El Ma, Beni Chiker, and Boudinar).
73.    The Project will also target its activities to vulnerable groups (such as poor people,
women, elderly, and children) in its subcomponent on restoration of degraded soils through
planting of fruit trees adapted to local climate conditions (olive, carob and almond).
74.     The trainings developed under the Component 1 will also focus on raising awareness on
how climate change might impact coastal zones, particularly on potential loss of agricultural
land, threats to human habitation, near-shore fisheries, etc., so that those dependent on these
areas have the time and the knowledge to adapt and alter their livelihoods and dwellings.

On implementation capacity

75.    The Department of the Environment (DE) will be responsible for the implementation and
monitoring of environmental and social safeguards aspects of the Project. Because the DE does
not have prior experience with the World Bank social and environmental standards or
consultation and disclosure requirements, some reinforcement of capacity will be required. To
compensate for implementation capacity risk, the Grant will finance a portion of the cost of a
Program Coordinator, a consultant and member of the PMU among whose responsibilities will
be the execution of all environmental and social safeguards functions, including the
implementation of the ESMP. In addition, the Grant will finance a member of the PMU, whose
responsibility will encompass implementing the M&E system for the project, including such
aspects of M&E pertaining to safeguards and the ESMP.

76.     A particular concern is community outreach and public consultation. A public
consultation plan will have to be devised as part of the implementation to make sure that all
involved stakeholders are consulted and vulnerable groups are given fair access to express their
points of view. This plan will be made available to the Bank no later than six months after the
Effective Date of the Project.

77.      The Site-Specific ESIA and Site-Specific ESMPs required for the activities under
Component 2.2 will be prepared using the same methodology as the Project ESIA and ESMP.
Section 2.3 of that document specifies the applicability of the analytical methodology to the
activities of the Project and that the Site-Specific ESIAs and ESMPs so prepared will become
part of the feasibility studies for their respective activities under Component 2.2. These Site-
Specific ESIA/ESMPs will:

           (a) Take into account all applicable environmental and social safeguard policies of
           the World Bank;




                                              23
           (b) Ensure that the activity in question will not cause involuntary displacement of
           persons or any new restriction of access to natural resources, in accordance with OP
           4.12 of the World Bank;
           (c) Hold formal consultations with stakeholders and local populations during the
           preparation of the Site-Specific ESIA/ESMP, as required by the World Bank’s
           guidelines on consultation; and
           (d) Be published in their final form on the websites of the Moroccan government and
           the World Bank.

   F. Environment (including Safeguards)

78.     The Project is expected to have significant positive environmental and social impacts.
However, because of the nature of the activities planned under the project, it has been assigned
an environmental Category B. An environmental and social impact assessment (ESIA) has
therefore been prepared in French under the World Bank’s Operational Policy on environmental
assessment (OP 4.01). In accordance with the World Bank’s disclosure policy and guidelines,
the ESIA was disclosed at the World Bank’s Infoshop before project appraisal, and disclosed in-
country on the website of the DE. The disclosure date in Morocco was February 16, 2012. The
objective of the ESIA is to assess the expected positive and negative impacts that the project will
have on the environment and on society in the affected areas, and to propose an environmental
and social management plan (ESMP) to manage the risk of those negative impacts.

79.     The ESIA investigated the impact of each of the project’s activities on the environment
and local society. Its results reveal that many of the expected environmental impacts will be
positive, as described above, and that the project will not create significant or irreversible
negative impacts on the environment. Most potential negative environmental impacts are
expected to be minor, temporary and site-specific in nature and can be mitigated by
implementation of and compliance with the ESMP. There are no major social impacts expected
to affect the livelihoods of artisanal fisherman.

80.     As part of the project’s activities, feasibility studies will be conducted for the eventual
establishment of one artificial reef, one seaweed farming facility, and one aquaculture (shell fish
farming) facility. These feasibility studies will contain environmental assessments in accordance
with applicable Moroccan law, but will also be required to comply with the requirements of the
ICZM project’s ESIA/ESMP.

81.   The ESMP (Chapter 6 of the ESIA) will be incorporated into the Project Operations
Manual and will guide the day-to-day implementation of the project.
82.    The Department of the Environment (DE) within the Ministry of Energy, Mines, Water
and the Environment (MEMWE) will be responsible with implementing and monitoring
compliance of environmental issues (including environmental safeguards issues).
83.    Public consultations were carried out during the preparation of the project, and the results
of the ESIA were presented to a public forum of stakeholders in Nador on November 1, 2011.
The record of that public consultation is included in the annexes of the ESIA.




                                                24
84.     Concerning environmental safeguard policies, the ICZM project involves environmental
interventions and therefore triggers the World Bank environmental assessment Operational
Policy (OP 4.01). OP/BP 4.04 on Natural Habitats is also triggered, due to the fact that work
will be undertaken to enhance biodiversity protection and co-management regimes that will
include at least one Ramsar wetland site. However, the activities in question are designed to
conserve these ecosystems, and no significant conversion or degradation of critical natural
habitats will occur; quite the contrary.
85.    As noted in the preceding section, all Site-Specific ESIAs and Site-Specific ESMPs
prepared for Project activities under Component 2.2 will be required to take all environmental
(and social) safeguard policies into account.
86.     No other safeguard policies are expected to be triggered by the project, considering also
that Morocco has adequate environmental legislation, institutional capacity, and mechanisms to
deal with environmental issues during project preparation and implementation, particularly in the
area of wetland conservation, fisheries, agriculture and climate change. There are no additional
environmental issues that go beyond the ambit of the safeguard policies.

Safeguard Policies Triggered                                           Yes           No
Environmental Assessment (OP/BP 4.01)                                  X
Natural Habitats (OP/BP 4.04)                                          X
Forests (OP/BP 4.36)                                                                 X
Pest Management (OP 4.09)                                                            X
Indigenous Peoples (OP/BP 4.10)                                                      X
Physical Cultural Resources (OP/BP 4.11)                                             X
Involuntary Resettlement (OP/BP 4.12)                                                X
Safety of Dams (OP/BP 4.37)                                                          X
Projects on International Waterways (OP/BP 7.50)                                     X
Projects in Disputed Areas (OP/BP 7.60)                                              X




                                               25
                                                        Annex 1: Results Framework and Monitoring
                                                             MOROCCO:
                                            INTEGRATED COASTAL ZONE MANAGEMENT PROJECT
Project Development Objective (PDO): The objective of the project is to pilot the application of the integrated coastal zone management approach in the project area on the
eastern Mediterranean coast of Morocco.
                                                                       Cumulative Target Values**                                                                    Description
                                                                                                                                                  Responsibility


                              Core
    PDO Level Results                 Unit of                                                                                     Data Source/                        (indicator
                                                 Baseline                                           Yr               Frequency                       for Data
        Indicators*                  Measure                  Yr 1          Yr 2         Yr 3               Yr 5                  Methodology                         definition
                                                                                                     4                                              Collection
                                                                                                                                                                         etc.)
Indicator One: Number             Number of      0          0             6            6           6       6         Semester     PMU report      PMU                Success
of approved local                 ICZM-                                                                              reports,                                        will be
development plans that are        friendly local                                                                     Mid –term                                       measured
revised to incorporate the        plans created                                                                      review                                          by inclusion
ICZM approach                                                                                                                                                        of key
                                                                                                                                                                     ICZM
                                                                                                                                                                     concepts in
                                                                                                                                                                     revised
                                                                                                                                                                     plans
Indicator Two:                    Number of      0          0             0            1           1       1         Semester     HCWFFAD         HCWFFAD
Formulation and                   public                                                                             reports,     report          and PMU
implementation of a               awareness                                                                          Mid –term
public awareness                  campaigns                                                                          review
campaign for the                  promoting
promotion of biodiversity         conservation
conservation through co-          of Ramsar
management of the                 wetlands
Ramsar wetlands of the
Moulouya estuary

                                                                 INTERMEDIATE RESULTS

Intermediate Result (Component 1):

1. (a) Government                    Number of      0           8           18         28         38      48        Semester      Reporting by     PMU
officials and members of             training                                                                       reports,      PMU
local communities                    workshops                                                                      Mid –term
involved in development              delivered                                                                      review
planning receive training
and regular refreshers in
ICZM and co-
management
1. (b) Specific permanent            Number of      0           3           9          15         21      27        Semester      Reports from     PMU              One
Coastal Commissions at               meetings of                                                                    reports,      Coastal                           meeting per



                                                                                      26
the provincial level hold      Coastal                                                          Mid-term    Commissions               CC in the
regular meetings and           Commissions                                                      review      (e.g. meeting             first year,
discharge their mandate                                                                                     minutes)                  two
                                                                                                                                      meetings
                                                                                                                                      per year
                                                                                                                                      thereafter
1. (c) Training of trainers    Number of        0   10        30          50          70   90   Semester    Reports by      PMU       Training of
in ICZM principles             educators                                                        reports,    PMU                       trainers is
                               trained                                                          Mid-term                              based on
                                                                                                review                                the use of
                                                                                                                                      materials
                                                                                                                                      developed
                                                                                                                                      over the
                                                                                                                                      course of
                                                                                                                                      the project
1.(d) Number of approved       Number of        0   0         6           6           6    6    Semester    PMU report      PMU       Success
local development plans        ICZM-                                                            reports,                              will be
that are revised to            friendly local                                                   Mid –term                             measured
incorporate the ICZM           plans created                                                    review                                by inclusion
approach                                                                                                                              of key
                                                                                                                                      ICZM
                                                                                                                                      concepts in
                                                                                                                                      revised
                                                                                                                                      plans
Intermediate Result (Sub-Component 2.1):

2.1. Rehabilitation of        Number of         0   0         5           10          18   20   Semester    HCWFFAD         HCWFFAD
degraded wetlands and         hectares                                                          reports,    report          and PMU
dune ecosystems at            rehabilitated                                                     Mid-term
Moulouya                                                                                        review
Intermediate Result (Sub-Component 2.2):

2.2. (a) Artificial reef is    Number of        0   0         0           1           1    1    Semester    DMF             DMF
deployed in project area       deployed reef                                                    reports,
and operating under co-                                                                         Mid-term
management regimes                                                                              review

2.2. (b) and (c) Feasibility   Number of        0   1–        2–          2           2    2    Semester    NADA            NADA
of establishing seaweed        feasibility          seaweed   shellfish                         reports,
and shellfish farms is         studies                                                          Mid-term
studied                        completed                                                        review
2.2. (d) and (e) Pilot         Number of        0   0         1–          2–          2    2    Semester    NADA            NADA
seaweed and shellfish          pilot farms                    seaweed     shellfish             reports,



                                                                          27
farms successfully                                                                   Mid-term
launched and operating                                                               review
under co-management
Intermediate Result (Sub-Component 2.3):

2.3. (a) Restoration of        Number of        0   0         50   150   400   500   Semester   ADA   ADA
degraded areas through         hectares                                              reports,
soil and water                 receiving                                             Mid-term
conservation (SWC)             SWC                                                   review
measures                       measures


2.3. (b) Number of            Number of         0   0         1    2     3     3     Semester   ADA   ADA
associations or               associations                                           reports,
cooperatives of women         or                                                     Mid-term
involved in apiculture        cooperatives                                           review
Intermediate Result (Sub-Component 2.4):

2.4. Small-scale ecolodges     Number of        0   0         2    3     4     6     Semester   MT    MT
are                            ecolodges                                             reports
established/rehabilitated      established
and operating                  and operating

Intermediate Result (Component 3):


3. (a) and (b) Progress        Number of        0   7         14   21    28    35    Semester   PMU   PMU   Three
reports are submitted in a     progress                                              reports,               reports
timely manner and project      reports                                               Mid-term               twice per
website created/updated        submitted            Project                          review                 year, plus
                               (technical,          web                                                     annual
                               fiduciary, and       created                                                 summary
                               safeguards)                                                                  report
3. (c) Project adheres to      % completion     0   90        90   95    95    95    Semester   PMU   PMU   Non-
annual work program and        of annual                                             reports,               cumulative
budget                         work program                                          Mid-term
                               and budget                                            review
3. (d) Monitoring site         Number of        0   24        72   120   168   216   Semester   PMU   PMU   Target rate
visits are proceeding.         site visits                                           reports,               of one visit
Measurements and               completed                                             Mid-term               per project
observations of progress       with                                                  review                 area per
and indicator values are       measurements                                                                 month
being recorded                 observed




                                                                   28
                                  Annex 2: Detailed Project Description
       MOROCCO: INTEGRATED COASTAL ZONE MANAGEMENT PROJECT

1.     This annex presents the detailed description of the ICZM project’s activities, along with a
map showing the geographical locations of the project area (Figure 1, below) and a table
showing the detailed breakdown of project financing between components, sub-components, and
individual project activities (Table 1, below).




Figure 1 - Map of Morocco's Oriental Region, showing project area circled (Source: Khattabi and Ghazi, 2009.
Socioeconomic aspects of the EMC, ACCMA project, 45p.)



Component 1: Capacity building and institutional strengthening to incorporate the ICZM
approach into local development planning (Total cost: US$ 0.677 M, government
contribution: US$ 0.235 M)
2.      The objective of this component is to strengthen the capacity of government institutions
and local communities to incorporate the ICZM approach into their local development plans.
Under Article 36 of the Moroccan Communal Charter (Charte communale), each commune
currently prepares and maintains its own communal development plan, which is intended to
guide the development of that commune. These are currently not produced based on spatial
information, and do not take explicit account of ICZM. These plans are prepared by the elected
President of each commune in consultation with the population and serve as a means of guiding
development within the community itself and as a budgeting exercise in cooperation with higher




                                                         29
levels of government. These communal development plans are not a means of restricting access
to lands and natural resources, or of constraining economic activity within a community.
3.      The intended audience is the citizens and officers of the communes, as well as
government officials at various levels. This component will align with the strategic ICZM bill
currently under review by Parliament. It also represents an opportunity to take a crosscutting
approach to helping local communities adapt to predicted climate change impacts.
4.     This component will finance consultant services, training and workshops, non-consultant
services, works, and goods to be used in support of the following activities:
       (a) Promoting awareness of, and building capacity in, the application of the ICZM
           approach, including solid waste and waste-water management, by provincial and local
           governments and local stakeholders in the project, after development of a
           communication plan for the project area through:
            (i) Organization of workshops targeting government managers of the coastal
                 resources and economic development planning on the benefits, application and
                 operation of co-management between the Government and local residents as part
                 of the ICZM approach. Since ICZM and associated spatial planning is a locally
                 based activity, the main audience will include members of the three provincial
                 Specific Permanent Coastal Commissions.
            (ii) Organization of community-oriented workshops that explain the benefits,
                 obligations and application of natural resource co-management and the ICZM
                 approach to local users of the resources to be involved in co-management.
            (iii)A broader-based public education campaign to build long-term awareness among
                 local populations, decision-makers, and other stakeholders of the ICZM
                 approach. This community outreach will include workshops including launching
                 and closing events, communications materials, the press, and training for trainers
                 in primary and secondary education (teachers of children under the age of 18) on
                 topics related to ICZM and climate change.
            (iv) coordinating and sharing knowledge among the project’s various partner
                 agencies, which includes learning and good practices sharing through IW-
                 LEARN.

       (b) Mainstreaming the ICZM approach in the preparation of the development plans of six
           selected communes in the project area during required periodic update. Coastal
           communes will first undertake village-level ICZM resource planning. These plans
           would then feed into Government-mandated spatial development plans required as
           part of its annual assessment of the needs and distribution of its national development
           budget. The Project will finance the provision of technical assistance to the involved
           communities preparing village-level resource allocation strategies under ICZM, and
           provincial governments to familiarize them with the outputs of these ICZM-based
           plans in the four project sites.

       (c) Piloting spatial development planning method in one of the six communes targeted in
           (b) above, where local residents and communal officials will work together in a two-
           step process to identify the most profitable, environmentally and socially sustainable
           use for each land unit in a political division (province-district-commune). The first


                                               30
             step is to assess land and near shore capability,17 which will provide sound guidance
             to local residents and communal officials on what is possible. But being possible
             does not mean that a use is environmentally and socially sustainable- particularly with
             the local community of stakeholders. The output of land capability studies will be
             overlays on a 1:50,000 (or better) topographic map in a computer-based Geographical
             Information System (GIS). This tool makes it possible for everyone to understand
             what is possible in each land unit. The second stage of spatial development planning
             is a transparent, locally-based process of presenting the land capability GIS
             information to local stakeholders and through an interactive process, identifying the
             most profitable, environmentally and socially sustainable use of each land unit that is
             acceptable to the community. Workshops and technical assistance specific to spatial
             development planning will be financed.

         Expected results: The government and community participants have the awareness,
         tools, and background information that they need to participate meaningfully in the
         formulation of a development plan at the local level. Specific Permanent Coastal
         Commissions acquire the knowledge needed to become effective and to conduct regular
         meetings twice per Commission per year. Communal development plans will be
         prepared and/or revised in a manner that incorporates the principles of ICZM and climate
         change adaptation. Public education material will be prepared and distributed for use in
         the project area (e.g. guides, tool kits, website for ICZM information, etc.).

Component 2: Investments to improve coastal resource management and livelihoods
through co-management approach (GEF contribution: US$ 4.119 M, and government
contribution US$ 19.14 M)
5.     The objective of this component is to support biodiversity and ecosystem conservation
while simultaneously undertaking specific and appropriate pilot investments that demonstrate the
value of environmental and social sustainability (as introduced through ICZM-linked spatial
development planning) in improved use of local natural resources. This component, through its
four sub-components, will finance consultant services, works, small works, goods, training and
non-consultant services to support:
         (a) Sub-component 2.1: Improved conservation and management of sensitive
             coastal areas. This sub-component will be implemented by project partners
             HCWFFAD. Activities include:
             (i) Rehabilitation and restoration of degraded wetland and coastal dune ecosystems
                 at Moulouya. This will be carried out by 1) fixation and restoration of coastal
                 dunes through the fixation of an area of 20 ha, 2) a hydrological study of the
                 SBEI and the installation of water pipes to re-establish the flow of water from the
                 Ain Chebbak spring to wetlands located in douar Cherarba; and 3) the updating
                 of the ecological and socio-economic diagnostic of the affected area.

17
   Capability of a land or water unit is defined by its physical and environmental characteristics (soil, climate,
topography, conservation value, etc.) and the environmental requirements of the various uses (various horticulture,
livestock, various types of aquaculture, plantation forestry, etc.) that are possible. Land capability should not be
confused with land use. Land use is how a spatial unit is currently used, whether that use is appropriate or even
environmentally possible. There are standard FAO methodologies for determining land capability.


                                                         31
    (ii) Preparation and implementation of public awareness campaign for the
         conservation of the Moulouya SBEI. This activity will include the preparation
         and development of public awareness campaign action plan for the conservation
         of the Moulouya SBEI through direct consultation and cooperation with the local
         population and users of the SBEI.

Expected results: Outputs include formulation of a public awareness campaign action
plan for the conservation of the Moulouya SBEI, fixation of 20 ha of coastal dunes, and
restoration of proper drainage to the Ain de Chebbak spring.

    Government will finance in parallel with the project, activities complementary to the
    investments described above. These will include reforestation activities at the
    Moulouya SBEI and restoration of walking trails, lookouts and signage at Moulouya.
    For example, specific and budgeted reforestation activities include: i) the
    reforestation work in the Oulad Mansour hills which consists of planting 420 ha in
    scrub, 4500 m3 of dikes and terraces against erosion and the production of 250,000
    forest plants; ii) reforestation of a 24 ha area within the El Halgue area (Moulouya
    SBEI); and iii) repairing walkways, two observation pavilions and road signs at
    Moulouya. These projects are planned by HCWFFAD for fiscal year 2012. These
    activities do not involve any GEF financing. They receive parallel financing
    from the Government of Morocco only, and are complementary to project
    activities but not required for the achievement of project objectives.


(b) Sub-component 2.2: Improved fisheries management. This sub-component will
    be implemented by project partners DMF, and NADA. The activities to be funded
    include:
    (i) Feasibility study including preparation of the related Site-Specific ESIA and
         Site-Specific ESMP regarding the establishment on a pilot basis of an artificial
         reef off the EMC between Boudinar and Saidia, and also including technical
         support for the co-management approach by the users of the resource.
    (ii) Feasibility study including preparation of the related Site-Specific ESIA and
         Site-Specific ESMP regarding the establishment on a pilot basis of a small
         seaweed farm, seaweed processing and commercialisation facilities in one
         community on the EMC. Feasibility study will also include exploring
         partnerships between the cooperative and the private sector.
    (iii) Feasibility study including preparation of the related Site-Specific ESIA and
         Site-Specific ESMP regarding the establishment on a pilot basis of one small
         shellfish farm, shellfish processing and commercialisation facilities in
         communities on the EMC. This activity will focus on the feasibility of mussel
         and oyster farming in the EMC and investigation of partnerships between the
         cooperative and the private sector.

Expected results: One artificial reef established and managed by local users under co-
management regimes; seaweed farm feasibility confirmed and a small pilot farm
established along with processing and commercialisation activities; shellfish farm



                                       32
feasibility confirmed and one small pilot farm established along with processing and
commercialisation activities; and partnerships with private sector explored.

    In parallel, government will finance with its own resources activities complementary
    to the investments described above, including construction of small-scale artisanal
    fishing facilities and infrastructure at the port of Ras Kebdana, a small port in Nador
    province. This activity does not involve any GEF financing. It receives parallel
    financing from the Government of Morocco only, and is complementary to
    project activities but not required for the achievement of project objectives.


(c) Sub-component 2.3: Soil and water conservation and income-generating
    activity. This sub-component will be implemented by project partners ADA and by
    DE. The planned activities include:
    (i) Soil and water conservation measures (e.g. terrace construction or rehabilitation,
         fruit tree planting, small physical works to facilitate water infiltration and reduce
         runoff and erosion, etc., after conducting of the related Site-Specific ESIAs and
         Site-Specific ESMPs regarding the establishment of the activities). It aims at
         improving the livelihoods of the rural population while mitigating the effects of
         erosion, the conservation of water resources and the promotion of good practices
         on controlling agricultural pollution. Targeted communities are the communes of
         Beni Chiker and Boudinar.
    (ii) Promotion of apiculture by supplying local women’s groups with materials
         (hives and equipment) and technical assistance. This activity fits perfectly into
         the vision of the Plan Maroc Vert implemented by the Ministry of Agriculture
         and Maritime Fisheries for the development of beekeeping. The objective of this
         activity is to increase the income of the population, especially women, through
         the development of beekeeping and the promotion of its products. Technical
         assistance will also include investigation of partnerships between the
         cooperatives and the private sector.

Expected results: Creation of three functioning apicultural cooperatives; restoration of
soil and planting of fruit trees over a total of 500 ha in two communes.

        In parallel, the government will finance with its own resources activities under
        the NSP projects that are located in areas where agriculture is the dominant
        activity and include two waste-water treatment stations at Karia Arekmane and
        Ferkhana and one waste collection and treatment station at Ras El Ma. This
        activity does not involve any GEF financing. It receives financing from the
        Government of Morocco only, and is complementary to project activities.

(d) Sub-component 2.4: Promotion of ecotourism. This sub-component will be
    implemented by project partners MT. The planned activities include:
    (i) A feasibility study on ecotourism in the project area.
    (ii) The rehabilitation and furnishing, including adapted equipment of solid waste
         and waste-water for small scale lodges, of up to six small-scale tourist lodges



                                         33
                 (Bed and Breakfast) in locations based on the results of the feasibility study and
                 an open, transparent and participatory process to select beneficiaries.
            (iii)Training of tour operators, and promotion of sustainable tourism activities,
                 including raising awareness on effective waste and waste-water resulting from
                 the activity.

       Expected results: Restoration of up to six small-scale tourist lodges; training of key
       personnel (tour guides and ecolodge management staff).

                In parallel, the government will finance with its own resources activities under
                the NSP projects that are located in areas where tourism is an important sector,
                and include one network of sanitation of waste-water for the tourist complex in
                Saidia, and a pipe to discharge the purified waste-water from the treatment
                station to OuedCheraa. This activity does not involve any GEF financing. It
                receives financing from the Government of Morocco only, and is
                complementary to project activities.


Component 3: Project management and M&E (GEF contribution: US$ 0.384 M; Government
contribution US$ 0.625 M)
6.      The objective of this component is to ensure adequate management and coordination of
project activities, and in so doing, laying the groundwork for long term management of the
coastal zone by supporting the capacity and activities of the PMU.
7.     This component will finance consultant services, goods, training, non-consultant services
and incremental operating costs needed for
(a) The operations of the PMU; and
(b) Project monitoring and evaluation.
Incremental costs to be financed include incremental contractual staff, office equipment and
operations, transportation services (excluding purchase of vehicles), domestic travel,
international travel for training, etc. It will also cover the cost of establishing and operating an
M&E system for the project.

       Expected results: PMU established and operational; monitoring and evaluation system
       established and operational; the project website created. As management will mainly
       comprise public servants and be implemented through existing institutions, the project
       management structure will provide a working example of how long-term integrated
       coastal management might be organized in the future.




                                                34
                              Annex 3: Implementation Arrangements

       MOROCCO: INTEGRATED COASTAL ZONE MANAGEMENT PROJECT


Project Institutional and Implementation Arrangements

1. Even though the geographical scope of the project is essentially limited to the eastern part of
the Mediterranean coast, national Moroccan institutions will be involved in the implementation
of the project at the highest level. This is particularly important in view of the fact that the
project taps directly into five major Moroccan initiatives currently being implemented: the
National Sanitation Program, the Plan Maroc Vert for Agriculture, the Stratégie Halieutis for
fisheries, the 2020 vision for tourism, and the national strategy on climate change.

Project Administration Mechanisms

2. The Ministry of Energy, Mines, Water and the Environment, through the PMU, will have the
overall responsibility for implementation of Project Components 1 and 3, and for the overall
coordination of the implementation of the entire Project, including responsibility for FM, and
procurement. As is the case for any other Word Bank project in Morocco, the Ministry of
General Affairs and Governance (MAGG) has the mandate to oversee general project
implementation, and ensure directions chosen, actions undertaken, and result achieved are in
accordance with relevant government policies and programs, and with project documents and
agreements. Besides the PMU, the other mechanisms and entities involved in project
implementation include: the Technical Coordination Committee (TCC) chaired by the MEMWE
(through its Department of Environment), various partner agencies or entities18, and local
community groups or associations. The Project implementation will require collaboration
between institutions at the local, provincial/regional, and national levels.
3. The Technical Coordination Committee (TCC) (Comité de Coordination Technique)
which has been established for the purpose of ICZM under the chairmanship of MEMWE will
serve as a technical forum for MEMWE, MAGG, MEF, HCWFFAD, MAMF, NADA, ADA and
MT, in which such entities shall harmonize their actions regarding the implementation of the
Project, share knowledge on Project implementation, and ensure that their annual work plans and
budgets are well integrated with one another. Membership to the TCC will be as follows:
MEMWE (Chair, delegated to DE), MAGG, MEF, HCWFFAD, MAMF, MT, NANA, and
ADA.
4. Project Management Unit. A project management unit (PMU) will be established within
the Department of the Environment of the Ministry of Energy, Mines, Water and the
Environment. The PMU will have both the responsibility for day-to-day implementation of the
project and overall coordination for project implementation, with support, guidance and feedback


18
 The partner entities include: MAGG, MEF, High Commission for Water, Forestry and the Fight Against
Desertification (HCWFFAD), MAMF, National Aquaculture Development Agency (NADA), Agricultural
Development Agency (ADA), Ministry of Tourism (MT), and Municipal and Regional councils in the Project areas.


                                                     35
from the MAGG for higher-level inter-institutional issues, and from the Technical Coordination
Committee on inter-agency coordination and cooperation, work planning, and budgeting.
5. The PMU will be solely responsible for handling all financial transactions and procurement
activities. It will be responsible for consolidating annual work plans, project monitoring guides,
and the various progress reports required by the World Bank. The PMU will also ensure efficient
coordination between project partners, particularly on the exchange of information and
organization of common activities. It will also be responsible for promoting partnerships at the
regional and local levels and facilitating the integration of ICZM project activities with any other
partners’ development programs and investment plans in the targeted areas. The PMU will have
a central office that will operate out of the main offices of the DE in Rabat and a Regional office
to operate out of the regional DE office in Oujda. It will be responsible for day-to-day project
management and implementation, including the carrying out of all selected community
investments and subprojects.
6. The ICZM project’s has been nationally developed under the direct supervision of the
Director of the Studies, Planning and Strategy Directorate (Direction des Etudes, de la
Planification et de la Prospective) of the DE within MEMWE. The project’s Director should
have at least the rank of Director in the DE administrative hierarchy. Under the project Director,
the PMU will be headed by a Project Manager, who would be a senior professional civil servant
of the MEMWE (DE), and he will be assisted by a Project Coordinator (full-time consultant).
The Project Manager will oversee project implementation and monitoring at the national level.
Specifically, the Project Manager will be responsible for consolidating annual work plans,
Project monitoring guides, and the various progress reports required by the World Bank. The
Project Manager will also ensure efficient coordination between project partners, particularly on
the exchange of information and organization of common activities. The Project Coordinator will
be a technical expert in ICZM with the competence of project management who will support the
Project Director throughout project implementation, and will be responsible for the application
of environmental and social safeguards both centrally and in the region, including the
implementation of the ESMP. The PMU will also include a financial management specialist.
7. At the regional level, the Regional Representative of the DE in Oujda will be a member of
the PMU and serving as its Regional Project Manager in the region. The Regional Project
Manager will be assisted by a Regional Project Coordinator (full-time consultant). The regional
office of the PMU will be responsible for coordinating the implementation of project activities to
be implemented by the DE across all four project pilot areas; and will work in close collaboration
with the regional staff of the other participating partners and ministries implementing activities
under this project. Staff of other ministries may not be seconded to the PMU directly, but will be
close partners of the PMU and daily points of contact for coordination of work.
8. Other participating partners entities. Other participating partner ministries and/or
institutions will be mostly responsible for the technical implementation of selected project
activities under Component 2 and in accordance with the Implementation Conventions to be
established with the MEMWE. These partner entities include.
         (a) The High Commission for Water, Forestry and the Fight Against Desertification
         (HCWFFAD) for subcomponent 2.1 to improve conservation and management of
         sensitive coastal areas;




                                                36
         (b) The Department of Maritime Fisheries (DMF) of the Ministry of Agriculture and
         Maritime Fisheries (MAMF) for subcomponent 2.2 dealing with improvement of
         fisheries management. DMF will benefit from support of the National Aquaculture
         Development Agency (NADA);
         (c) The Agricultural Development Agency (ADA) through the RDA for
         subcomponent 2.3; and
         (d) The Ministry of Tourism (MT) for subcomponent 2.4 aiming at promoting
         ecotourism.
9. Other partner entities include also:
         (a) The Specific Permanent Coastal Commission of each of the provinces covered by
         the the Project will organize regular meetings and discharge their mandate as the ICZM
         coordination mechanism;
         (b) The National Environmental Observatory (NEO) and Eastern Region Sustainable
         Development Observatory (ERSDO) will be called upon to help coordinate the
         monitoring of indicators at the national and regional levels, respectively;
         (c) The Wali and the provincial Governors of the Eastern region may be called upon
         to participate in sensitisation and training activities, and to support implementation of
         project activities within their jurisdictions; and
         (d) At the local level, the associations and cooperatives are recognized as full partners
         in implementing and maintaining the investments carried out on behalf of the
         communities.
10. Operational procedures and Operations Manual.           The proposed project would be
implemented according to detailed procedures defined in the Operations Manual.


Financial Management, Disbursements and Procurement

Financial Management

General framework

11. The project is financed by the GEF for $5.18 million with a government parallel financing of
$20 million.

Public Financial Management
12. The Bank’s experience in Morocco and the main conclusions of the 2009 PEFA indicate that
the Moroccan public finance system is governed by an elaborate legal and regulatory framework.
The financial management risk of the Moroccan public finance system is considered low.

Assessment of the Financial Management System




                                               37
13. An assessment of the financial management system in place at the Department of
Environment of the MEMWE was carried out to determine if it complies with the Bank
minimum requirements for the project management in respect to the OP/BP10.02.

14. The Financial Management System (FMS) in place in the DE of the MEMWE is based on
principles and procedures defined by the legal framework applicable to the public sector and
more specifically to governmental institutions.

Project Risk identified

15. The following risks have been identified:

         (a) The project staff does not have experience in Bank procedures.
         (b) The project does not have an FM manual.
         (c) The project involves activities with multiple ministries, which increases the risk
         of delays in project execution.


Risk Mitigation measures

16. Intensive training and assistance will be provided to the project staff by the World Bank
Project Task Team.

17. The project will prepare the Project Operations Manual, which should include financial
management, and submit it to the Bank for approval. This completion and approval of the
Project Operations Manual is a condition of the project effectiveness.

18. The Implementation Conventions between the MEMWE (DE) and the other parties involved
in the project will be drafted and submitted for Bank approval. These Conventions will specify
the relationship between the MEMWE (DE) and the other involved parties.

Budget

19. The grant will be received by the Government of Morocco for the project. However, each
Ministry prepares its own budget and submits it to the Ministry of Economy and Finance for
approval through the “Loi de Finance�?. In this case, the MEMWE (DE) will include the amount
of the grant in its budget and submit it to the MEF through “la Loi de Finance�? or through “les
fonds de concours�? for approval.

20. All projects activities must be clearly identified in separate lines while preparing the budget
in order to allow the tracking of project activities.




                                                38
Staffing

21. The PMU will manage day-to-day implementation of the Project. The PMU will be housed in
the MEMWE (DE) and composed of no less than seven persons of its own staff who will be
assigned for a share of their time to the Project while keeping working on other activities in
parallel.

22. The procurement and financial management of the project will be managed by two qualified
and experienced staff (The head of the budget department and his assistant).

23. The PMU staff does not have knowledge of the World Bank procedures, thus the PMU will
receive intensive training and assistance from the World Bank Project Task Team.


Accounting

24. An acceptable cash-based accounting system with the outline of budget components is
operational according to the regulation described in the public accounting law. The transactions
in terms of commitments and disbursements are reflected in the well functioning Integrated
Financial Management Information System (IFMIS) named GID (Gestion intégrée des
dépenses).

25. The overall principles for Project accounting are outlined below: (a) Books of accounts for
the Project will be maintained on cash basis principles. Maintaining the reporting financial
system to reflect all the transaction flow of funds and issuing of the Interim unaudited financial
report (IUFR) each semester will complete this system; and (b) Project accounting will cover all
sources and utilization of Project funds. This will include payments made and expenditures
incurred. All project-related transactions will be taken into account in the reporting system.
Disbursements made will also be included in the Project accounting system.

Reporting

26. Interim unaudited financial report (IUFR) for the Project will be generated from GID every
semester if the budget submitted for this project is well presented. The DE needs to present the
budget line items as follows: each budget line item related to the project will represent a
component and each sub-line item will represent different categories. Hence, it will allow the
tracking of the project financial information through the system. The PMU will produce the
IUFRs every semester and send them to the World Bank within 45 days from the end of each
semester.

27. The Financial Reporting will include the following:

           (a)   Summary of funding sources and uses of funds;


                                               39
           (b)   Uses of funds by project component and by project category;
           (c)   Cash withdrawal; and
           (d)   Cash forecast.


28. Annually: Audited Project Financial Statements (PFS) will be submitted to the Bank. PFS
will include: (i) a statement of sources and utilization of funds or Balance Sheet, indicating funds
received from various sources, Project expenditures, and assets and liabilities of the Project; (ii)
schedules classifying project expenditures by components, expenditure categories; and (iii) a
Statement of reimbursement made on the basis of Statements of Expenditure (SOEs).

Controls

29. In Morocco, the rules governing funds commitment and payment authorization are clear, well
known, and enforced. The control framework is based on the segregation of duties between the
commitment (ordonnateur) and payment (comptable).

30. The MEMWE (DE) does not have formalized internal control procedures. A Project
Operations Manual will be prepared and submitted to the Bank before effectiveness in order to
document the control environment. The Project Operations Manual will describe, among others:
control mechanisms at central and decentralized level, transfer and accountability mechanisms
for beneficiaries

31. Fiduciary responsibility for control of budget execution and monitoring is assigned to the
General Inspectorate of Finance (IGF) and to the Audit Court. The Budget Directorate within the
MEF plays an important role in controlling transactions financed by external donors.

External Audit

32. Audit Arrangements. Annual Project financial statements audited by auditors acceptable to
the Bank will be submitted to the Bank within 6 months after the end of each Fiscal Year. The
audit will be comprehensive and cover all aspects of the Project (i.e., all sources and utilization
of funds, and expenditures incurred). The audit will be carried out in accordance with
International Standards on Auditing. The Project team will provide the auditor with access to
project related documents and records, and information required for the purposes of the audit.


Flow of funds

33. The funds after their budgeting in the “Loi de Finance�? will be transferred to the FNE (Fonds
National de l’Environnement) that is managed by the MEMWE (DE). As this project involves
different parties, the Implementation Conventions will be signed in order to assign the activities
to be performed by each entity. All the supporting documents will be submitted to the DE for


                                                40
payment. No funds will be transferred to other entities and the DE will be the only entity
managing the funds through the FNE. The payment justifications supporting documents will be
sent to the Directorate of Budget (MEF) for verification, approval and submission to the Bank
for reimbursement. As the DE assessment ensured that it has the capacity to manage the funds,
in addition to the MEF controls, the risk of misuse of funds is fairly covered.

34. There will be no designated account opened for this project. Expenses will be financed on
the government budget and then a request for reimbursement will be submitted to the Bank.

Planning of Supervision

35. A supervision mission will be conducted every six months based on the risk assessment of
the project. The mission’s objectives will include: (i) ensuring that strong financial management
systems are maintained for the project throughout its life; and (ii) semi-annual review of IUFRs,
review of annual audited financial statements and management letters.

Disbursements

36. The proceeds of the grant would be disbursed in accordance with the traditional disbursement
procedures of the Bank and will be used to finance project activities through the disbursement
procedures currently used, that is Direct Payment and Reimbursement accompanied by
appropriate supporting documentation (Summary Sheets with records and/or SOEs) in
accordance with the procedures described in the Disbursement Letter and the Bank's
“Disbursement Guidelines�?. The minimum application size for direct payment and
reimbursement will be the equivalent of US$ 50,000.

37. In order to allow a continuation of related activities, retroactive financing is allowed to
finance eligible expenditures made prior to the Grant signing date but on or after March 23,
2012. The aggregated amount should not exceed US$37,000 equivalent.

38. The Bank will honor eligible expenditures for services rendered and goods delivered by the
Project closing date. A four months' grace period will be granted to allow for the payment of any
eligible expenditure incurred before the grant closing dates.

39. Necessary supporting documents will be sent to the Bank in connection with contracts that
are above the prior review threshold, except for expenditures under contracts with an estimated
value of (i) US$100,000 or less for works, goods and consulting firms; (ii) US$50,000 or less for
individual consultants, as well as all operating costs, training, workshops and field visits, which
will be claimed on the basis of SOEs. The documentation supporting expenditures will be
retained at the DE and will be readily accessible for review by the external auditors and periods
Bank supervision missions. All disbursements will be subject to the conditions of the Grant
Agreements and disbursement procedures as defined in the Disbursement Letter.




                                                41
40. The frequency and scope of World Bank supervisory missions will be adapted to the needs of
the DE and will be delivered both at central and regional levels. Supervisory frequency will be
half-yearly, though this may be increased if needed.

Procurement

General

41. Procurement for the proposed project would be carried out in accordance with the “World
Bank’s Procurement of Goods, Works, and Non-Consulting Services under IBRD Loans and
IDA Credits & Grants By World Bank Borrowers�? dated January 2011 (“Procurement
Guidelines�?), and the provisions stipulated in the legal agreements between the Bank and the
borrower (GoM). The various items under different expenditure categories are described in
general below. For each contract to be financed by the grant, the different procurement methods
or consultant selection methods, the estimated costs, prior review requirements, and time frame
are agreed between the recipient and the Bank in the Procurement Plan. The procurement
procedures and Standard Bidding Documents (SBD) that will be used by the recipient will also
be well defined in the Project Operations Manual, which will include specific and detailed
sections regarding Procurement.


42. National Competitive Bidding (NCB) procedures adjusted as indicated below will be used for
all Works contracts, and for Goods and for Non-Consulting Services contracts estimated to cost
less than the equivalent of three million US dollars (US$ 3,000,000).

43. To ensure broad consistency with the Procurement Guidelines, the following provisions will
apply when using NCB under this project. These procedures shall ensure that, inter alia:
    a) The bidding documents include explicitly the bid evaluation method, award criteria and
       bidder qualification criteria;
    b) Technical, administrative and financial envelopes are opened immediately after the bid
       opening session has started and prices are read aloud;
    c) The bids are evaluated on the basis of the price and any other criteria expressed either in
       pass/fail terms or in monetary terms;
    d) Contracts are awarded to the qualified bidder who has submitted the least-cost evaluated
       and substantially responsive bid as stipulated in the bidding document; and
    e) Standard bidding documents and bid evaluation reports found acceptable by the Bank are
       used.

44. Moreover, it has been agreed with the borrower that each contract financed from the
proceeds of this grant shall provide that suppliers, contractors and subcontractors shall permit the
Bank, at its request, to inspect their accounts and records relating to the bid submission and
performance of the contract and to have said accounts and records audited by auditors appointed
by the Bank. The deliberate and material violation by the supplier, contractor or subcontractor of
such provision may amount to “obstructive practice�?.


                                                42
45. The procedures and standard bidding documents (SBD) of the borrower adjusted to be
acceptable by the Bank will be used under National Competitive Bidding (NCB). Thus prior to
issuing the first call for bids, a draft SBD to be used under NCB procurement must be submitted
to the Bank for approval;

46. Advertisement and Procurement Plan: In addition to advertising pertaining to each
contract, a General Procurement Notice (GPN) will be published, in United Nations
Development Business, and in at least two national newspapers. The GPN will be published after
project is approved by the Bank and prior to the project Effectiveness. The GPN will provide a
description of the project and information on related procurement.

47. A Project Procurement Plan in a format acceptable to the Bank will be prepared and updated
at least once a year. The procurement plan for the first eighteen (18) month period will be agreed
during the negotiations. The procurement plan shall indicate which contracts shall be subject to
the Bank’s prior review. All other contracts shall be subject to Post Review.

Procurement Arrangements

48. Procurement of Works: Procurement of Works comprising rehabilitation and restoration of
degraded wetland ecosystems and coastal dunes, construction of an artificial reef, building of
rock terraces on eroded land, will be carried out using the National Competitive Bidding (NCB)
method adjusted to be acceptable to the Bank. Standard Bidding Documents acceptable to the
World Bank will be used.

49. Small works: Small works, including, rehabilitation and furnishing small scale tourist lodges
under Component 2 would be carried out through agreements (conventions) with
beneficiary/cooperative commitments and funded by project subsidies. Small works for the
purpose of this project is less than $50,000, and shopping procedures will be used. The total
amount of small works for the entire project will be within the total amount of $350,000. More
details will be provided in the project implementation manual.

50. Procurement of Goods and non-consulting Services: Procurement of Goods and Non
consulting services comprising the acquisition of equipment, material and office supplies for the
PMU, logistics for workshops among others, will be carried out using the following methods:
    a) National Competitive Bidding (NCB): Each package estimated to cost less than the
       equivalent of US$ 3,000,000 may be procured on the basis of NCB procedures as found
       acceptable by the Bank. Bidding documents acceptable to the Bank will be used.

   b) Shopping: Works, Goods and non-consulting services estimated to cost US$ 200,000 or
      less may be procured using Shopping procedures.

   c) Direct Contracting: Under circumstances that meet the requirements of paragraph 3.7 of
      the Procurement Guidelines, goods, non-consulting Services and works may be procured
      in accordance with the paragraph 3.7 of the Procurement Guidelines using the Direct
      Contracting procurement method.



                                               43
51. Selection of Consultants: Consultants services comprise mostly technical assistance,
capacity building training, communication, economic studies and feasibility studies, activities in
support to the implementation of the different components of the project, including project
management and monitoring. The following Bank methods and corresponding standard
documents will be used:

   a) Quality & Cost Based Selection (QCBS) for all types of consultant services.

   b) Least-cost Selection. Services for assignments that meet the requirements of paragraph
      3.6 of the Consultant Guidelines may be procured using the Least-cost Selection method
      in accordance with the provision of paragraphs 3.1 and 3.6 of the Consultant Guidelines.

   c) Selection Based on Consultant’s Qualifications (CQS). Services estimated to cost less
      than US$100,000 equivalent per contract may be procured in accordance with the
      provisions of paragraphs 3.1 and 3.7 of the Consultant Guidelines.

   d) Single Source Selection. Under circumstances that meet the requirements of paragraph
      3.8 of the Consultant Guidelines for Single Source Selection, consultant services may be
      procured in accordance with the provisions of paragraph 3.8 through 3.11 of the
      Consultant Guidelines, with the Bank’s prior agreement.

   e) Individual Consultants (IC). Services for assignments that meet the requirements set forth
      in the paragraph 5.1 of the Consultant Guidelines may be procured under contracts
      awarded to individual consultants in accordance with the provision of paragraph 5.2 and
      5.3 of the Consultant Guidelines. Under the circumstances described in paragraph 5.6 of
      the Consultant Guidelines, such contracts may be awarded to individual consultants on a
      sole-source basis.

52. Short lists may be composed entirely of national consultants for contracts of less than US$
200,000 equivalent per contract, complying with the remarks mentioned above.

Publication of Results and Debriefing

53. Online (UN Development Business, and /or Client Connection) publication of contract
awards would be required for all Direct Contracting, and the Selection of Consultants for
contracts exceeding a value of US$200,000. All consultants competing for an assignment
involving the submission of separate technical and financial proposals, irrespective of its
estimated contract value, should be informed of the result of the technical evaluation (number of
points that each firm received) before the opening of the financial proposals. The borrower
would be required to offer debriefings to unsuccessful bidders and consultants should the
individual firms request such a debriefing.

Fraud, Coercion, and Corruption
54. All procuring entities, as well as bidders, suppliers, and contractors shall observe the highest
standard of ethics during the procurement and execution of contracts financed under the project



                                                44
in accordance with paragraphs 1.16 & 1.17 of the Procurement Guidelines and paragraphs 1.23
& 1.24 of the Consultants Guidelines.

Frequency of Procurement Supervision
55. Supervision of Procurement by the World Bank is an integral part of Project supervision and
implementation monitoring. In addition to the prior review supervision to be carried out from
Bank offices, it is recommended that two (2) supervision missions take place during a year to
visit the project and to carry out post review of procurement actions.

56. Based on the risk associated with procurement (substantial), the following actions need to be
implemented by set date (date to be determined base on project timetable) in order to reduce
risks:
       a. Inclusion of the procurement procedures in the Project Operations Manual. The
            Operations Manual will clearly describe procurement procedures, responsibility
            sharing and document flow among the parties involved in Project implementation.
            The Operations Manual should comprise in annex, all standard bidding documents
            that will be used under the project.
       b. Preparation of Standard Bidding Documents for NCB in accordance with the
            Procurement Guidelines and found acceptable by the World Bank for Works, Goods
            and Non-consulting Services; these documents, taking into consideration required
            adjustment in order to be acceptable to the Bank, will be submitted for review and
            approval to the World Bank by project effectiveness.
       c. Organization of procurement training workshops for staff from all entities involved
            in project implementation and to raise their awareness on applicable procedures,
            before project effectiveness.
       d. Preparation of the procurement plan for the first eighteen (18) month before
            negotiations.


Environmental and Social (including safeguards)

57. The ICZM project is expected to have significant positive environmental and social impacts.
By focusing on small-scale projects in the targeted coastal area, the project will address
independent fishermen and farmers, their families and their rural communities, traditionally
characterized by high poverty rates, low levels of education and low productivity. The project
will help to improve the resilience of these communities to climate change and to conserve the
natural resources upon which they depend, initiating a system of co-management that gives the
local users of the resource a collective means of managing its use and conservation. In
particular, Component 1 of the project will raise awareness among farmers, fishermen, and
planners as well as vulnerable groups (poor people, women, children and elderly) at the
commune and province levels about the risks of climate change and resource mismanagement,
and will provide training and tools in the form of ICZM training to reduce their risk through
integrated planning and management. This will make coastal fishing and agriculture and their
associated activities more resilient to climate change, the project will help to make them more
sustainable in the long term.


                                               45
58. Concerning environmental safeguard policies, the ICZM project involves environmental
interventions and therefore it triggers the World Bank environmental assessment Operational
Policy (OP 4.01). Because of the nature of the activities planned under the project, it has been
assigned an environmental Category B. OP/BP 4.04 on Natural Habitats is also triggered, due to
the fact that work will be undertaken to establish co-management regimes that will include at
least one Ramsar wetland site. However, the activities in question are designed to conserve these
ecosystems, and no significant conversion or degradation of critical natural habitats will occur,
quite the contrary. No other safeguard policies are expected to be triggered by the project,
considering also that Morocco has adequate environmental legislation, institutional capacity, and
mechanisms to deal with environmental issues during project preparation or implementation,
particularly in the area of fisheries, agriculture and climate change. There are no additional
environmental issues that go beyond the ambit of the safeguard policies.

59. OP/BP 4.12 on Involuntary Resettlement will not be triggered by the project. Activities
involving involuntary resettlement will not be financed under this project. Any activity involving
lands will only be carried out on public lands from which resettlement is not required or on
private lands where voluntary participation of the landholder is documented in writing. The
project will not involve involuntary land taking resulting in relocation or loss of shelter; loss of
assets or access to assets; or loss of income sources or means of livelihood (whether or not the
affected person needs to move to another location).

60. An environmental and social impact assessment (ESIA) has already been prepared and has
been disclosed in French, in-country on February 16, 2012 and at InfoShop after the in-country
disclosure on February 16, 2012.

61. The objective of the ESIA is to assess the expected positive and negative impacts that the
project will have on environment and on society in the affected areas, and to propose an
environmental and social management plan (ESMP) to manage the risk of those negative
impacts.

62. The ESIA investigated the impact of each of the project’s activities on the environment and
local society. Its results reveal that many of the expected environmental impacts will be positive,
as described above, and that the project will not create significant or irreversible negative
impacts on the environment. Most potential negative environmental impacts are expected to be
minor, temporary and site-specific in nature and can be mitigated by implementation of and
compliance with the ESMP.

63. The Site-Specific ESIA and Site-Specific ESMPs required for the activities under
Component 2.2 will be prepared using the same methodology as the Project ESIA and ESMP.
Section 2.3 of that document specifies the applicability of the analytical methodology to the
activities of the Project and that the Site-Specific ESIAs and ESMPs so prepared will become
part of the feasibility studies for their respective activities under Component 2.2. These Site-
Specific ESIA/ESMPs will:


                                                46
         (a) Take into account all applicable environmental and social safeguard policies of
         the World Bank;
         (b) Ensure that the activity in question will not cause involuntary displacement of
         persons or any new restriction of access to natural resources, in accordance with OP
         4.12 of the World Bank;
         (c) Hold formal consultations with stakeholders and local populations during the
         preparation of the Site-Specific ESIA/ESMP, as required by the World Bank’s
         guidelines on consultation; and
         (d) Be published in their final form on the websites of the Moroccan government and
         the World Bank.

64. The ESMP (Chapter 6 of the ESIA) will be incorporated into the Operations Manual and will
guide the implementation of the project from day to day.

Vulnerable groups

65. The project will involve a series of revenue-generating activities under component 2.3
that will specially address the needs of vulnerable groups. For example, it will promote
apiculture activities by supplying local women with full hives, training them in modern
beekeeping and marketing techniques and teaching them how to organize within associations or
cooperatives (Sites of Saidia Ras El Ma, Beni Chiker, and Boudinar); and its subcomponent on
restoration of degraded soils through planting of fruit trees adapted to local climatic conditions
(olive, carob and almond).

66. The trainings developed under Component 1 will also focus on raising awareness on how
climate change might impact coastal zones and thus, affect its vulnerable groups (people at
poverty line, women, children and elderly) and the adaptation measures that could be developed
to mitigate them.

Consultations

67. Public consultations have been carried out over a number of years in the context of previous
work done in the project area in view of coastal zone management, e.g. SMAP III and ACCMA.
In addition, public consultations specific to this project were carried out during preparation, and
the results of the ESIA were presented to a public forum of stakeholders in Oujda on November
1, 2011. Annex A of the ESIA includes information on the public consultations.

68. The capacity of the DE to plan and execute a project-wide, ongoing consultation process as
part of implementation is untested, but is particularly important given the co-management
emphasis of the ICZM project. A consultation plan will therefore be devised as part of the
implementation to make sure that all involved stakeholders are consulted and vulnerable groups
are given fair access to express their points of view. The plan should be made available to the
Bank no later than six months after the Effective Date of the Project and the consultation plan
shall be promptly implemented as approved by the World Bank.




                                                47
On implementation capacity

69. The Department of the Environment (DE) within the Ministry of Energy, Mines, Water and
the Environment (MEMWE) will be responsible with implementing and monitoring compliance
of both environmental and social safeguards.

70. Because the DE does not have prior experience with the World Bank social and
environmental standards or consultation and disclosure requirements, some reinforcement of
capacity will be required. For this reason, and at the request of the DE following its own internal
assessment of capacity, the project will enlist the assistance of the ERSDO and NEO in
monitoring safeguards performance. Additional expertise is available through other departments
of the Government of Morocco and may be made available to DE through the MAGG. To
compensate for implementation capacity risk, the Grant will finance a portion of the cost of a
Program Coordinator, a consultant and member of the PMU among whose responsibilities will
be the implementation of all environmental and social safeguards functions, including the
implementation of the ESMP. In addition, the Grant will finance a member of the PMU, whose
responsibility will encompass implementing the M&E system for the project, including such
aspects of M&E pertaining to safeguards and the ESMP.


Safeguard Policies Triggered                                             Yes           No
Environmental Assessment (OP/BP 4.01)                                    X
Natural Habitats (OP/BP 4.04)                                            X
Forests (OP/BP 4.36)                                                                   X
Pest Management (OP 4.09)                                                              X
Physical Cultural Resources (OP/BP 4.11)                                               X
Indigenous Peoples (OP/BP 4.10)                                                        X
Involuntary Resettlement (OP/BP 4.12)                                                  X
Safety of Dams (OP/BP 4.37)                                                            X
Projects on International Waterways (OP/BP 7.50)                                       X
Projects in Disputed Areas (OP/BP 7.60)                                                X

Monitoring

71. The PMU will be responsible for the monitoring and evaluation (M&E) of the project,
including analysis of M&E data and the finalization of progress reports. To this end, it will work
closely with the relevant staff and units of the other ministries and agencies participating in the
implementation of the ICZM project (i.e. DMF, NADA, ADA, RDA and HCWFFAD). These
ministries, in turn, will provide all relevant data concerning the performance of the activities for
which they are responsible to DE for the purposes of M&E. To provide critical capacity in data
collection, it will also be supported by the ERSDO, another entity of the DE whose mandate
includes the collection and analysis of environmental data. The ERSDO, in turn, may seek
assistance from its national parent, the National Environmental Observatory, as needed.

72. The PMU will monitor the project’s intermediate results indicators (see Annex 1) and
provide a semi-annual update of these indicators to be included in the project’s regular reports.


                                                48
Data collection, verification, and initial analyses will be the responsibility of the regional office
of the DE, with technical support from the ERSDO. The regional DE staff and/or consultants
will be responsible for making regular visits to the project area to monitor progress and collect
data on environmental performance. Funds for M&E will be drawn from Component 3. The
PMU will be responsible for incorporating detailed monitoring instructions in the Project
Operations Manual.

73. Regional PMU staff will share the semi-annual reports with the local cooperatives involved
in co-management with the government. This is for the benefit of informing the decision-
making of those cooperatives and for seeking their feedback on the monitoring and evaluation of
the project as it pertains to their activities.

Evaluation

74. Substantial baseline data exist in the form of numerous studies conducted on coastal zone
management in the Eastern region, including as part of previous projects such as SMAP III. For
co-financed activities executed by other agencies participating in the ICZM project, those
agencies shall present baseline data relevant to their activities to the PMU within six months of
project effectiveness.

75. The PMU will be responsible for contracting independent consultants to conduct the mid-
term and end-of-project evaluations, including updated surveys of socioeconomic conditions and
fisheries and agricultural resources in the project area.

76. The mid-term evaluation will assess the operational aspects of the project, namely progress in
the completion of activities and the achievement of the PDO. The mid-term evaluation will also
include recommendations for corrective measures, if needed, for project implementation to
remain on track.

77. The end-of-project evaluation will have the same scope as the mid-term review but will focus
particularly on project outcomes and results at the local, regional, and national level. The end-of-
project evaluation will also provide recommendations in terms of M&E and replication of best
practices, especially for the sustainable management of coastal resources and the preservation of
internationally recognized wetlands. Terms of reference for the mid-term and end-of-project
reviews will be agreed upon with the World Bank and included in the Project Operations
Manual.

78. The mid-term and end-of-project evaluations will need to measure the progress against the
PDO Level Results Indicators (see Annex 1). This will be important to the PMU in compiling the
necessary baseline data from existing studies as discussed above. Baseline information will also
need to be collected for Intermediate Results Indicators. The list of these PDO Level and
Intermediate Results Indicators will need to be included in the TORs for the mid-term and end-
of-project reviews.




                                                 49
79. Evaluation Schedule

      (i)     Baseline of outcome indicators
              a. The baseline information on the PDO Level Indicators will be established
                 from data contained in existing studies of the relevant sectors, resources and
                 geographical areas;
              b. Baseline information on Intermediate Results Indicators will be established
                 from data contained in existing studies of the relevant sectors, resources and
                 geographical areas.
      (ii)    Mid-term evaluation
              a. The PMU will recruit a consultant (firm) to prepare, under terms of reference
                 agreed with the World Bank, a mid-term evaluation report including a review
                 of progress achieved in all components (results evaluation), and review the
                 effectiveness of the project, cost-effectiveness, implementation of the
                 participatory methodology, alignment of the project with actual government
                 policies, Bank project supervision performance, as well as all intermediate
                 outcome monitoring indicators;
              b. The mid-term evaluation will also include a limited beneficiary assessment
                 (project beneficiaries, partners, Government) through a rapid appraisal survey
                 or using focus groups; and
              c. The evaluation report will make recommendations for further project
                 implementation.
      (iii)   End-of-project evaluation
              a. As is the case for the mid-term evaluation, the PMU will recruit a consultant
                 (firm) to prepare, under terms of reference agreed with the World Bank, an
                 end-of-project evaluation report including:
                    i.A review of the achievements in all components (results evaluation);
                   ii.A review of the effectiveness of the project;
                  iii.An evaluation of the cost-effectiveness of the project;
                  iv. An evaluation of the implementation of the participatory methodology;
                   v. An evaluation of the project impact on the basis of the outcome
                      indicators and other relevant results; and
                  vi. An evaluation of the relevance of the Project within the government
                      economic and social policies.
              b. The independent evaluator will carry out a full beneficiary assessment of the
                 project (by participants, partners, local, and central government) as well as an
                 evaluation of the Bank’s performance during preparation and implementation;
                 and
              c. The evaluator will also present lessons learned at the technical, financial,
                 institutional, and natural resource management level.




                                               50
80. Communication strategy. The PMU will need to define, from the project start, the
communication strategy in terms of information to be provided to different partner institutions
involved in project implementation. The PMU will need to establish a detailed list of all
information recipients as well as their information needs. In addition to written reports, M&E
results can be communicated during the workshops and meetings organized for project
implementation and supervision.




                                              51
                                               Annex 4: Operational Risk Assessment Framework (ORAF)
                                 MOROCCO: INTEGRATED COASTAL ZONE MANAGEMENT PROJECT
                                                       Stage:Board

    Project Stakeholder Risks
          Stakeholder Risks                                                 Rating: Low
Description : Morocco’s engagement with the Bank is strong. The
Government sees the Bank as a reliable partner and has requested
Bank support in a broad range of sectors. The Bank works regularly
with a range of stakeholders as part of its program in Morocco.
                                                                            Risk Management: None deemed necessary.
On governance indicators, Morocco scores above average for "Voice and
Accountability", indicating that stakeholder implication in the country’s
development is satisfactory
     Implementing Agency (IA) Risks
            Capacity                                                        Rating: Substantial
Description : The MEMWE is designated as the Agency to implement            Risk Management :
project activities and to host the PMU. There are procedures of the         i) MEMWE has entered into implementation conventions with other project participating agencies in view of
World Bank for MEMWE to learn because of lack of previous Bank              specifying respective implementation responsibilities.
project experiences.
                                                                            Resp: Government           Stage: Implementation       Due Date : Ongoing         Status: In progress

The MEMWE may encounter difficulties in coordinating with larger,           ii) Support of MAGG and MEF is available through the government structure for implementation and
older, and more prestigious ministries.                                     coordination problems through the Technical Coordination Committee; and
                                                                            Resp: Government           Stage: Implementation       Due Date : Ongoing         Status: In progress
                                                                            iii) Training for procurement and FM for DE is on-going based on the capacity assessment undertaken by the
                                                                            team’s procurement Specialist.
                                                                            Resp: Bank                 Stage: Implementation       Due Date : Ongoing         Status: In progress
           Governance                                                       Rating: Moderate
Description : The MEMWE’s oversight process is generally good for
the project implementation.                                                 Risk Management :
                                                                            Given the MAGG’s mandate, it will work to help the MEMWE to oversee the project implementation.
The MEMWE is selected as the Agency to host the PMU for project
implementation because: i) they are the coordinating agency for the
ICZM; and ii) the unit which was responsible for the project showed a
great interest.                                                             Resp: Government           Stage: Implementation       Due Date : Ongoing         Status: In progress




                                                                                       52
    Project Risks
            Design                                                       Rating: Low
Description : It is difficult for Morocco to implement an ICZM           Risk Management : i) Where possible, activities and coastal resources will be managed through local
approach in a comprehensive manner. The approach the team                cooperatives with the assistance of the project.
suggested is to pilot the approach at the provincial and local levels.
The project also has the flexibility to adjust if necessary.             Resp: Government              Stage: Implementation          Due Date : Ongoing        Status: In progress
To address the key gap which is sustainable conservation and             ii) The project will have the ability to adjust because of the proposed pilot and decentralized approach, and the
management of coastal resources, the Project is to test the ICZM         ability to reallocate funds between activities.
method - co-management intended to link conservation and use and
improve the livelihoods of local people                                  Resp: Government and
                                                                                                      Stage: Implementation        Due Date : Ongoing      Status: In progress
                                                                         Bank
          Social & Environmental                                         Rating: Moderate
Description : Generally speaking, Morocco has adequate standards         Risk Management : i) Co-management of resources in protected areas between government and
for environment as the WB has used country system for Morocco.           cooperatives of local resource users will have a protective effect on the resource and on environmental
                                                                         quality. Shared responsibility between government and users will favour greater transparency and
The project will focus on helping the provincial governments and         better conservation of the resource, leading to stronger support of local livelihoods;
local people better manage their coastal resources and make a direct
linkage between conservation of coastal resources and economic           ii) The MEMWE will develop a consultation plan and strategy to make sure that open and transparent
benefits. Low risks are expected from environment perspectives.          consultations will take place;
However, potentially regulated access to certain protected areas
may have social implications.                                            iii) Due to inexperience with the implementation of World Bank projects, some weakness has been
                                                                         identified in the capacity of the PMU to monitor and evaluate project activities, and to implement the
An environmental and social impact assessment has been carried           ESMP. Accordingly, the Grant will finance a portion of the cost of a Program Coordinator, a consultant
out by the client.                                                       and member of the PMU among whose responsibilities will be the execution of all environmental and
                                                                         social safeguards functions, including the implementation of the ESMP. In addition, the Grant will
Activities involving involuntary resettlement will not be financed       finance a portion of the cost of a Monitoring and Evaluation Specialist, a consultant and member of the
under this project. Any activity involving lands will only be carried    PMU whose responsibility will encompass implementing the M&E system for the project, including such
out on public lands from which resettlement is not required or on        aspects of M&E pertaining to safeguards and the ESMP; and
private lands where voluntary participation of the landholder is
documented in writing. The project will not involve involuntary land     iv) The project activities will take place only on public lands from which resettlement is not required or on
taking resulting in relocation or loss of shelter; loss of assets or     private lands where voluntary participation of the landholder is documented in writing.
access to assets; or loss of income sources or means of livelihood
(whether or not the affected person needs to move to another
                                                                         Resp: Government              Stage: Implementation          Due Date : Ongoing        Status: In progress
location).
             Program & Donor
                                                                         Rating: Low
Description : Bank systems will be used. The project is embedded
within a few recently completed projects (financed by other donors)
                                                                         Risk Management : None required.
and Government programs in Nador and Moulouya.
            Delivery Monitoring & Sustainability
                                                                         Rating: Moderate
Description : Effective M&E: ICZM is supposed to use a cross cutting     Risk Management : i) assign responsibility at each level for data collection and entry into the system;




                                                                                     53
approach covering different sectors. This may make monitoring            Resp: Government            Stage: Implementation         Due Date : Ongoing   Status: In progress
difficult at local levels.
                                                                         ii) Public awareness and training for local people; and
The project is designed to strengthen the institutional capacity to
use ICZM approach while piloting improved conservation and               Resp: Government            Stage: Implementation         Due Date : Ongoing   Status: In progress
livelihood at four project sites. There is a risk of not being able to   iii) Use the draft ICZM law as the policy framework for M&E and once the law has been passed, the
replicate this ICZM approach after the project completion.               project practice would become a model.
                                                                         Resp: Government              Stage: Implementation      Due Date : Ongoing Status: In progress
     Overall Risk
          Implementation Risk                                            Rating: Moderate




                                                                                    54
                           Annex 5: Implementation Support Plan
      MOROCCO: INTEGRATED COASTAL ZONE MANAGEMENT PROJECT

Strategy and Approach for Implementation Support

1.      The strategy for implementation support (IS) has been developed based on the nature of
the project and its risk profile. It aims at making implementation support to the client more
flexible and efficient, and will focus on implementation of the risk mitigation measures defined
in the ORAF.


2.     Procurement. Implementation support will include: (a) providing training to members of
the procurement-related staff of the PMU (central and regional offices); (b) reviewing
procurement documents and providing timely feedback to the PMU; (c) providing detailed
guidance on Bank Procurement Guidelines to the PMU; and (d) monitoring procurement
progress against the detailed Procurement Plan.


3.      Financial management. Supervision will review the project’s financial management
system, including, but not limited to, accounting, reporting, and internal controls. Supervision
will also cover specific activities on a random sample basis. The World Bank team will also
work with the PMU to assist in improving coordination among different ministries and units for
financial management and reporting.


4.      Environmental and Social Safeguards. The World Bank team will supervise the
implementation of the agreed Environmental and Social Management Plan and provide guidance
to the PMU to address any issues.


5.     Other Issues. Sector-level risks, such as proper coordination, will be addressed through
dialogue with the Government and PMU.


Implementation Support Plan


6.      The WB team members will be based in the headquarters office and the Morocco country
office to ensure timely, efficient, and effective implementation support to the client. Formal
supervision and field visits will be carried out semi-annually. Detailed inputs from the Bank
team are outlined below:
       (a) Technical inputs. Technical supervision is required to ensure technical contractual
           obligations are met. The team will conduct site visits on a semi-annual basis
           throughout project implementation.




                                              55
(b) Fiduciary requirements and inputs. Training will be provided by the Bank’s
    Financial Management Specialist and the Procurement Specialist before the
    commencement of project implementation. The team will also help the DE identify
    capacity building needs to strengthen its M&E capacity and to provide further
    technical support as required to support the PMU during implementation. Both the
    Financial Management and the Procurement Specialist will be based in the country
    office to provide timely support. Formal supervision of financial management will be
    carried out semi-annually, while procurement supervision will be carried out on a
    timely basis as required by the client.

(c) Safeguards. Inputs from an Environment Specialist and a Social Specialist are
    required. On one hand, this is the first WB project in which the DE has been
    involved, meaning that the PMU lacks familiarity with World Bank safeguards
    operational policies; on the other hand, the project relies on a community-driven and
    participatory approach. Field visits are required on a semi-annual basis.

(d) Operations. The TTL, based at headquarters, will provide day-to-day supervision of
    all operational aspects, as well as coordination with the client and among WB team
    members.




                                       56
                                 Annex 6: Incremental Cost Analysis

       MOROCCO: INTEGRATED COASTAL ZONE MANAGEMENT PROJECT
1.      The Mediterranean coastal zone in Morocco is an economic engine of national economic growth.
Being bound by the Large Marine Ecosystem (LME) of the Mediterranean, Morocco and other coastal
countries face interlinked challenges of managing the resources of the Mediterranean Sea. To respond to
the continued environmental challenges facing the Mediterranean countries, the Sustainable MED
program takes the next step in addressing long-term, cooperative, regional management of the
Mediterranean Sea by linking resource management to support for environmentally and socially
sustainable economic development that recognizes the intrinsic value of biodiversity and ecologically
sensitive areas.
2.       This project fits within the “Sustainable MED�? program that is supported by the GEF and
implemented by the World Bank. Morocco and other countries that participate in Sustainable MED, have
a shared vision that proper national stewardship over the coastal environment, and economic development
therein, benefit not only the country implementing these strategies, but all other coastal countries of the
Mediterranean Sea.
3.       In this context, the project’s higher-level objective is to contribute to the sustainability of natural
resources base in the Mediterranean region within the Sustainable MED program. This project will
contribute to the regional effort in addressing the issues raised in the Trans-boundary Action Plan and
priorities defined in the Strategic Action Programs. The project will thus facilitate the Government of
Morocco in piloting an ICZM approach and in coordination with other countries in the region. The project
will also help Morocco explore innovative methods and measures for the sustainable development of the
coastal zone in a changing climate, a top priority given the challenges caused by climate variability:
longer lasting droughts, more aggressive floods, higher temperatures, sea-level rise, and beach and soil
erosion.
4.      The objective of the project is to pilot the application of an integrated coastal zone management
(ICZM) approach in the project area along the eastern Mediterranean coast of Morocco. ICZM
implemented at local level by all users of the coastal resources will leverage rural pollution reduction and
increase protection of biodiversity and ecologically sensitive areas.
5.      Proposed key results include:
           Number of approved local development plans that are revised to incorporate the ICZM
            approach; and

           Promotion of biodiversity protection in Ramsar sites and the institution of a co-management
            approach for the area.

6.      This Project consists of a set of activities under three project components: Component 1: Capacity
Building and Institutional Strengthening to Incorporate the ICZM Approach into Local Development
Planning; Component 2: Investments to Improve Coastal Resource Management and Livelihoods through
Co-Management Approach; and Component 3: Project management and M&E. The Project financing is
US$5.18 million from GEF, with co-financing to be provided by the Government of Morocco (US$20.00
million), including cash financing from the relevant sectors contribution.

7.       Without GEF grant support, the following priorities identified by the national and local
governments, as well as by local communities might not be implemented until it was too late to preserve
all ecologically and culturally important sites in the coastal zone. Particular areas needed to be urgently
addressed include: (a) incorporating ICZM approach into development planning with leverage of rural


                                                      57
pollution reduction and protection of biodiversity and ecologically sensitive areas; (b) more effective
conservation of wetlands and other key environmental sensitive areas along the Mediterranean coasts; c)
improving the effective use of key coastal zone natural resources, such as fisheries, land and water, by
diversifying economic and livelihoods for local populations; d) strengthening reduction of waste and
waste-water in the context of the National Sanitation Program in the Project Area; and e) addressing
negative impacts created by climate variability to local communities and related coastal ecosystems. The
GEF incremental support will make ICZM and climate change adaptation more of a reality and promote
improved governance capacity, cross-sector coordination, and the budget available for demonstrative
investments and environmental protection.

8.      The proposed project is thus designed to provide innovative and working examples needed to
catalyze the critical mass of investment needed to create sustainable growth in coastal provinces. For
example, project pilots are designed so that they can be replicated along both the Mediterranean and
Atlantic coasts of Morocco. Replication of successful project pilots may also take place in other countries
in the region through knowledge dissemination under the support of the “Governance and Knowledge
Generation project�? which is part of the Mediterranean Sustainable Development Program (Sustainable
MED). The proposed project also provides incremental input into several national and donor funded
programs and projects.

9.       Incremental cost analysis requires that a baseline “without GEF�? scenario be determined and that
its cost be compared to a “with GEF�? scenario. The difference in design between the GEF and non-GEF
alternatives is that the GEF scenario incurs incremental costs to address global externalities.

10.      A qualitative analysis of the costs and benefits of the Project activities below consists of an
attempt to separate a baseline set of activities, which would be carried out independently of the
availability of GEF resources, and then an additional set of activities that are contained in the proposed
Project. These are the incremental activities whose costs and benefits need to be compared with those of
the baseline. The analyses are separated according to the Project’s components, and for each component
with reference to the respective sets of activities.




                                                    58
                                           Incremental Cost Analysis

Activity                 Baseline                GEF Alternative           Global Benefits    Incremental Costs
                                                                                                   (US$)
Component 1: Capacity building and institutional strengthening to                               GEF alternative:
incorporate the ICZM approach into local development planning                                            912,000
                                                                                                    Incremental:
                                                                                                         677,000
                                                                                                   Co-financing:
                                                                                                         235,000
1.1: promoting       Management is          The activities include:        Strengthened
awareness of and     based on sectors                                      ecosystems
building capacity    and there is little    - training in terms of         conservation and
in the application   coordination in        ICZM and climate change        management
of the ICZM          the provinces of       adaptation;                    along the
approach among       Berkane, Nador                                        Mediterranean
key stakeholders     and Driouch            -Training and raising          coast.
including                                   awareness of coastal           Increased
government and                              territory developers (policy   resilience of
local communities                           makers and stakeholders)       ecosystems to
through training                            on the vulnerability of the    CC along the
workshops and                               coast to CC effects and the    Mediterranean
public education                            adaptation measures            coast.
campaigns                                   developed;

                                            - capacity building for co-
                                            management (how to set
                                            up associations and
                                            cooperatives; how to
                                            manage associations and
                                            cooperatives; etc.) and
                                            monitoring changes in the
                                            coastline;

                                            -coordinating and sharing
                                            knowledge among the
                                            project’s various partner
                                            agencies, including
                                            through IW-LEARN

1.2. Institutional   Specific               - making functional the        Better
capacity building    Permanent              Specific Permanent             management of
to mainstream        Coastal                Coastal Commissions as         coastal
ICZM approach at     Commissions            the mechanism to               ecosystems and
provincial level     exist on paper at      coordinate different sectors   resources.
                     the provinces of       to apply ICZM;
                     Berkane, Nador
                     and Driouch            - organization of
                                            workshops to help the
                                            Specific Permanent
                                            Coastal Commissions
                                            coordinate among different
                                            sectors, including ICZM




                                                          59
                                           and adaptation to CC.


1.3: piloting of                           - providing technical            This will help
spatial                                    assistance (expertise) to the    local
development                                municipalities and rural         communities to
planning and                               communes to help them            take into
including ICZM                             use the spatial planning;        consideration the
into the communal                                                           limited capacity
development                                - providing training and         of nature and
plans.                                     technical assistance to help     help better
                                           them incorporate ICZM            management
                                           into in the 6 Communal           (reduction of
                                           Development Plans.               pollution,
                                                                            conservation of
                                                                            wetlands, related
                                                                            ecosystems).
Component 2: Investments to improve coastal resource management                                 GEF alternative:
and livelihoods through co-management approach                                                       23,259,000
                                                                                                  Incremental:
                                                                                                       4,119,000
                                                                                                  Co-financing:
                                                                                                     19,140,000
2.1: Improved       Ramsar sites are                                        Improved
                                           The project will support
conservation and    designated.                                             conservation of
                                           conservation and restoration
management of                                                               Ramsar sites at
                                           of key coastal
sensitive coastal                                                           Moulouya.
                                           ecosystems/areas (dunes,
areas
                                           Ramsar sites). Activities
                                           include:
                                           -Preparation of a public
                                           awareness action plan for
                                           the conservation of the
                                           Moulouya SBEI;

                                           -Rehabilitating and restoring
                                           degraded wetland
                                           ecosystems and coastal
                                           dunes at the Moulouya
                                           estuary.


2.2: Improved       Some studies on        The Project will help pilot      Fisheries are
fisheries           artificial reefs and   different types of win-win       better managed
management          algae and tests        models for management of         because local
                    have been started.     the protected fishery area for   people increase
                                           conservation and economic        revenue through
                                           revenues. The activities         alternative
                                           include:                         livelihoods and
                                                                            more sustainable
                                           - studying and installing one    fisheries.
                                           artificial reef between
                                           Boudinar and Saidia;

                                           -studying the feasibility of



                                                          60
                                          algae cultivation and
                                          development of a pilot algae
                                          farm, along with associated
                                          value-added activities in the
                                          community;

                                          -designing and testing small
                                          shellfish farming project for
                                          the benefit of a cooperative
                                          of local fishermen.

2.3: Soil and water   The project will    The project will support         Land degradation
conservation and      be undertaken       those activities that use less   reduced; fresh
income-generating     based on Maroc      water while generating           water use reduced
activity              Plan Vert at        revenues, and/or making          for agriculture;
                      Saidia Ras El Ma,   local people less vulnerable     related coastal
                      Beni Chiker, and    to natural disasters. The        ecosystems better
                      Boudinar            activities will also include     protected.
                                          the promotion of good
                                          practices on controlling
                                          agricultural pollution. The
                                          planned activities concern:

                                          (a) soil and water
                                          conservation measures (e.g.
                                          terrace construction or
                                          rehabilitation, fruit tree
                                          planting, small physical
                                          works to facilitate water
                                          infiltration and reduce
                                          runoff and erosion; and

                                          (b) promotion of apiculture
                                          by supplying local women’s
                                          groups with materials and
                                          technical assistance.

2.4: Promotion of                         This sub-component will          Better conserved
ecotourism                                include:                         coastal resources,
                                                                           including
                                          (a) a feasibility study on       wetlands because
                                          ecotourism;                      they are assets
                                                                           for tourism and
                                          (b) the rehabilitation and       biodiversity.
                                          furnishing of six small-scale    Pollution reduced
                                          tourist lodges, including        out of better
                                          adapted equipment of solid       education, better
                                          waste and waste-water in         coordination
                                          locations based on the           among different
                                          results of the feasibility       sectors, and
                                          study; and                       better
                                                                           organization.
                                          (c) training of tour operators
                                          and promotion of
                                          sustainable tourism



                                                         61
                                   activities, including raising
                                   awareness on effective
                                   waste and waste-water
                                   resulting from the activity


Component 3: Project management and M&E                                                   GEF alternative:
                                                                                                 1,009,000
                                                                                            Incremental:
                                                                                                   384,000
                                                                                            Co-financing:
                                                                                                   625,000
Operation of the   Focus of M&E    The objective of this           Common
PMU.               and Knowledge   component is to ensure          knowledge
                   production      adequate management and         strengthened and
                                   coordination of Project         stronger focus on
                                   activities by supporting        Mediterranean
                                   capacity building within,       pollution in
                                   and activities of, the PMU.     knowledge
                                   This component will             production.
                                   finance incremental
                                   operating costs needed for:     Good practices of
                                                                   ICZM scaled up.
                                   (a) the operation of the
                                   PMU; and

                                   (b) project monitoring and
                                   evaluation.

                                                                                       GEF:
TOTAL                                                                                  5,180,000
                                                                                       Co-financing:
                                                                                       20,000,000




                                                  62