The World Bank Implementation Status & Results Report Ferghana Valley Water Resources Management - Phase II (P149610) Ferghana Valley Water Resources Management - Phase II (P149610) EUROPE AND CENTRAL ASIA | Uzbekistan | Water Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 8 | ARCHIVED on 27-Apr-2021 | ISR46268 | Implementing Agencies: Project Implementation Unit under the Ministry of Water of Uzbekistan, Republic of Uzbekistan Key Dates Key Project Dates Bank Approval Date: 30-Jun-2017 Effectiveness Date: 29-Dec-2017 Planned Mid Term Review Date: 01-Feb-2022 Actual Mid-Term Review Date: Original Closing Date: 31-Aug-2024 Revised Closing Date: 31-Aug-2024 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to improve the quality of irrigation and drainage service delivery to agricultural users within the project area. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component A: Irrigation Modernization:(Cost $191.40 M) Component B: Support for Agricultural Modernization:(Cost $21.50 M) Component C: Project Management:(Cost $12.10 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions During the past six months, despite of COVID pandemics, construction and rehabilitation of six civil works contracts for the Podhaota-Chodak Irrigation Scheme, Isfayram-Shakhimardan Irrigation Scheme, and Savay-Akburasoy Irrigation scheme have been implemented and physical progress is satisfactory. COVID-19 related restrictions slowed down the overall implementation pace of the project. 4/27/2021 Page 1 of 6 The World Bank Implementation Status & Results Report Ferghana Valley Water Resources Management - Phase II (P149610) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial Substantial Substantial Macroeconomic Moderate Substantial Substantial Sector Strategies and Policies Substantial Moderate Moderate Technical Design of Project or Program Substantial Moderate Moderate Institutional Capacity for Implementation and Moderate Moderate Moderate Sustainability Fiduciary High High High Environment and Social High Substantial Substantial Stakeholders Substantial Moderate Moderate Other -- -- -- Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes To improve the quality of irrigation and drainage service delivery IN00979504 ►Improved quality of irrigation and drainage service delivery (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1.50 1.50 1.50 2.50 Date 29-Jan-2016 12-Oct-2020 15-Apr-2021 31-Aug-2024 IN00979505 ►Relative irrigation deficit (water deficit/water demand) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 30.00 30.00 30.00 20.00 Date 29-Jan-2016 12-Oct-2020 15-Apr-2021 31-Aug-2024 IN00979541 ►Irrigation efficiency (Water withdrawn used for crop production) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 30.00 30.00 30.00 35.00 4/27/2021 Page 2 of 6 The World Bank Implementation Status & Results Report Ferghana Valley Water Resources Management - Phase II (P149610) Date 29-Jan-2016 12-Oct-2020 15-Apr-2021 31-Aug-2024 Intermediate Results Indicators by Components Component A: Irrigation Modernization IN00979542 ►Area provided with new/improved irrigation or drainage services (Hectare(Ha), Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 103,000.00 Date 29-Jan-2016 12-Oct-2020 15-Apr-2021 31-Aug-2024 Component B: Support for Agricultural Modernization IN00979543 ►Percentage of beneficiaries reporting improved engagement (in planning and feedback) and responsiveness to Farmer Field Schools (Citizen Engagement Indicator) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 80.00 80.00 100.00 Date 24-Mar-2017 12-Oct-2020 15-Apr-2021 31-Aug-2024 Consultant for M&E (who is responsible for CE per PAD) is expected to start work starting November 2020. Meanwhile, PIU started to design selection criteria for interested hosting farmers of demonstration Comments: plots. A Beneficiary Feedback survey will be planned in November 2020 through the M&E consultants IN00979545 ►Farmers adopting improved agricultural technology (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 29-Jan-2016 12-Oct-2020 15-Apr-2021 31-Aug-2024 The award of Training and Capacity Building Consultancy is expected by August 2021. Comments: IN00979546 Farmers adopting improved agricultural technology - Female (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 250.00 IN00979547 ►Number of people receiving rural advisory services (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 4/27/2021 Page 3 of 6 The World Bank Implementation Status & Results Report Ferghana Valley Water Resources Management - Phase II (P149610) Value 0.00 0.00 0.00 2,000.00 Date 24-Mar-2017 12-Oct-2020 15-Apr-2021 31-Aug-2024 The award of Training and Capacity Building is expected by August 2021. Comments: IN00979548 ►Land area under sustainable landscape management practices (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 103,662.00 Date 24-Mar-2017 12-Oct-2020 15-Apr-2021 31-Aug-2024 IN00979549 ►Operational water user associations created and/or strengthened (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 46.00 Date 29-Jan-2016 12-Oct-2020 15-Apr-2021 31-Aug-2024 IN00979550 ►Asset management processes established by project BAISs, AISs and WCAs (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 49.00 Date 29-Jan-2016 12-Oct-2020 15-Apr-2021 31-Aug-2024 The award of Training and Capacity Building Consultancy is expected by end August 2021. Comments: IN00979551 ►Increased collection rate by the WCAs in the project area (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 40.00 40.00 40.00 60.00 Date 24-Mar-2017 12-Oct-2020 15-Apr-2021 31-Aug-2024 IN00979552 ►Female beneficiaries (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 29-Jan-2016 12-Oct-2020 15-Apr-2021 31-Aug-2024 Component C: Project Management IN00979544 4/27/2021 Page 4 of 6 The World Bank Implementation Status & Results Report Ferghana Valley Water Resources Management - Phase II (P149610) ►Grievances registered related to delivery of project benefits that are resolved (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 80.00 80.00 80.00 Date 29-Jan-2016 12-Oct-2020 15-Apr-2021 31-Aug-2024 The baseline value is set to zero (0) according to approved PAD. Currently, 80% of registered grievances are resolved by series of consultation and face-to-face meetings by PIU and construction supervision consultants. The total number of grievances received was eight. The following GRM types are reported and resolved. Comments: i) when irrigation wells will be completed and water will be available ii) what are compensation mechanisms for temporary by-pass routes along to-be-rehabilitated canals iii) what are selection criteria for farmers to be included as demonstration plots. Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P149610 IDA-60830 Effective USD 144.90 144.90 0.00 25.93 118.97 18% P149610 TF-A9862 Effective USD 11.82 11.82 0.00 1.18 10.64 10% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P149610 IDA-60830 Effective 30-Jun-2017 20-Sep-2017 29-Dec-2017 31-Aug-2024 31-Aug-2024 P149610 TF-A9862 Effective 13-Apr-2019 13-Apr-2019 13-Apr-2019 28-Feb-2024 28-Feb-2024 Cumulative Disbursements 4/27/2021 Page 5 of 6 The World Bank Implementation Status & Results Report Ferghana Valley Water Resources Management - Phase II (P149610) PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 4/27/2021 Page 6 of 6