Public Disclosure Copy

        The World Bank                                                                             Implementation Status & Results Report
        China: Kunming Urban Rail Project (P117656)


China: Kunming Urban Rail Project (P117656)

EAST ASIA AND PACIFIC | China | Transport & Digital Development Global Practice |
IBRD/IDA | Investment Project Financing | FY 2011 | Seq No: 13 | ARCHIVED on 28-Jun-2018 | ISR32943 |


Implementing Agencies: International Department, Ministry of Finance, Kunming Rail Transit Group Co., Ltd.




Key Dates

  Key Project Dates

  Bank Approval Date:10-May-2011                                             Effectiveness Date:19-Oct-2011
  Planned Mid Term Review Date:27-Oct-2014                                   Actual Mid-Term Review Date:27-Oct-2014
  Original Closing Date:30-Nov-2016                                          Revised Closing Date:30-Jun-2018




Project Development Objectives

 Project Development Objective (from Project Appraisal Document)
 To support compact, transit-oriented urban development by providing high quality, integrated public transport on the East-West Line3 corridor.

 Has the Project Development Objective been changed since Board Approval of the Project Objective?
 No

 PHRPDODEL



Components

Name
Civil Works:(Cost $209.40 M)
Equipment:(Cost $86.90 M)
Technical Assistance and Capacity Building:(Cost $3.00 M)



Overall Ratings
Name                                                                       Previous Rating                          Current Rating

Progress towards achievement of PDO                                         Satisfactory                            Satisfactory
Overall Implementation Progress (IP)                                        Satisfactory                            Satisfactory
Overall Risk Rating                                                         Moderate                                Moderate


Implementation Status and Key Decisions


6/28/2018                                                                                                                               Page 1 of 7
                                                          Public Disclosure Copy
                                                          Public Disclosure Copy

        The World Bank                                                                              Implementation Status & Results Report
        China: Kunming Urban Rail Project (P117656)


 The WB-financed metro line (Line 3) has started operations on August 29, 2017. All project objectives are close to be achieved by the project closing
 date. The overall Implementation Progress is rated Satisfactory. All civil works construction and equipment installation of the line have been completed.
 On June 25, 2018 the total disbursed loan from the Bank is USD 285 million (95% of the loan amount). All resettlement and land acquisition have been
 completed. The average daily ridership of the line reaches 154,000 passenger-trips, overseeing the target of 150,000 passengers only six months after
 commissioning of the system. Passenger satisfaction ratio for Line 3 was 91% in 2017 and on-time performance was close to 100% in 2018. In addition,
 KRTC completed two TA activities financed by the loan proceeds (passenger satisfaction survey and study on material management), and three other
 TA studies financed by counterpart funds (bus-rail integration plan, TOD study, and marketing plan) as well as several trainings and study tours.
 Kunming Transport Bureau prepared an integration plan and issued guidance in August 2017 to enhance bus-rail integration improvement upon Line 3
 opening which is being implemented.




6/28/2018                                                                                                                                Page 2 of 7
                                                          Public Disclosure Copy
                                                  Public Disclosure Copy

           The World Bank                                                          Implementation Status & Results Report
           China: Kunming Urban Rail Project (P117656)




Risks

 Systematic Operations Risk-rating Tool

 Risk Category                                     Rating at Approval      Previous Rating          Current Rating

 Political and Governance                           --                     Low                     Low
 Macroeconomic                                      --                     Low                     Moderate
 Sector Strategies and Policies                     --                     Low                     Low
 Technical Design of Project or Program             --                     Moderate                Moderate
 Institutional Capacity for Implementation and
 Sustainability
                                                    --                     Low                     Low
 Fiduciary                                          --                     Moderate                Moderate
 Environment and Social                             --                     Moderate                Low
 Stakeholders                                       --                     Moderate                Moderate
 Other                                              --                     --                      --
 Overall                                            --                     Moderate                Moderate


Results

 Project Development Objective Indicators




6/28/2018                                                                                                        Page 3 of 7
                                                  Public Disclosure Copy
                                                           Public Disclosure Copy

               The World Bank                                                                   Implementation Status & Results Report
               China: Kunming Urban Rail Project (P117656)

 PHINDPDOTBL




          Average daily weekday ridership on Line 3 after 6 months of operations (Number, Custom)


                                             Baseline                    Actual (Previous)       Actual (Current)     End Target

         Value                               0.00                        0.00                    153,800.00           150,000.00

         Date                                01-Apr-2012                 15-Nov-2017             01-Jun-2018          30-Apr-2018


 PHINDPDOTBL




          On-time performance (Percentage, Custom)


                                             Baseline                    Actual (Previous)       Actual (Current)     End Target

         Value                               0.00                        0.00                    99.00                98.00

         Date                                01-Apr-2012                 15-Nov-2017             06-Jun-2018          30-Apr-2018


 PHINDPDOTBL




          Peak period travel time between origin/destination pairs along Line 3 (i) (Minutes, Custom)


                                             Baseline                    Actual (Previous)       Actual (Current)     End Target

         Value                               43.00                       0.00                    14.00                22.50

         Date                                01-Sep-2010                 15-Nov-2017             06-Jun-2018          30-Apr-2018


 PHINDPDOTBL




          Peak period travel time between origin/destination pairs along Line 3 (ii) (Minutes, Custom)


                                             Baseline                    Actual (Previous)       Actual (Current)     End Target

         Value                               38.00                       0.00                    15.00                17.50

         Date                                01-Sep-2010                 26-Apr-2017             06-Jun-2018          30-Apr-2018


 PHINDPDOTBL




          User satisfaction (Percentage, Custom)


                                             Baseline                    Actual (Previous)       Actual (Current)     End Target

         Value                               0.00                        0.00                    91.20                80.00



6/28/2018                                                                                                                     Page 4 of 7
                                                           Public Disclosure Copy
                                                               Public Disclosure Copy

                  The World Bank                                                                       Implementation Status & Results Report
                  China: Kunming Urban Rail Project (P117656)



               Date                              01-Apr-2012                15-Nov-2017                31-Dec-2017           30-Apr-2018




 PHINDPDOTBL




              FAR along Line 3 relative to district FAR in terms of new development (Text, Custom)


                                                 Baseline                   Actual (Previous)          Actual (Current)      End Target

               Value                             1.00                       1.60                       1.60                  >1.0

               Date                              31-Dec-2008                15-Nov-2017                15-Nov-2017           30-Apr-2018




 Overall Comments




 Intermediate Results Indicators
 PHINDIRITBL




              Number of stations with bus/bicycle facilities within 50m of an exit (Number, Custom)

                                                 Baseline                   Actual (Previous)          Actual (Current)      End Target

               Value                             0.00                       0.00                       10.00                 17.00

               Date                              01-Apr-2012                15-Nov-2017                06-Jun-2018           30-Apr-2018




 PHINDIRITBL




              Number of stations built (Number, Custom)

                                                 Baseline                   Actual (Previous)          Actual (Current)      End Target

               Value                             0.00                       17.00                      17.00                 17.00

               Date                              01-Apr-2012                15-Nov-2017                06-Jun-2018           30-Apr-2018




6/28/2018                                                                                                                            Page 5 of 7
                                                               Public Disclosure Copy
                                                                   Public Disclosure Copy

                  The World Bank                                                                        Implementation Status & Results Report
                  China: Kunming Urban Rail Project (P117656)

 PHINDIRITBL




              Number of km track built (Number, Custom)

                                                     Baseline                   Actual (Previous)       Actual (Current)              End Target

               Value                                 0.00                       38.20                   38.20                         38.20

               Date                                  01-Apr-2012                15-Nov-2017             06-Jun-2018                   30-Apr-2018




 PHINDIRITBL




            Bus/Rail integration: bus routes restructred to support integrated public transport as per the results of the route restructuring
           report (Text, Custom)

                                                     Baseline                   Actual (Previous)       Actual (Current)              End Target

               Value                                 N/A                        not yet                 partially yes                 yes

               Date                                  01-Apr-2012                15-Nov-2017             06-Jun-2018                   30-Apr-2018



 PHINDIRITBL




              Bus/Rail integration: shared I/C card for both rail and bus use (Text, Custom)

                                                     Baseline                   Actual (Previous)       Actual (Current)              End Target

               Value                                 In Planning                yes                     yes                           yes

               Date                                  01-Apr-2012                15-Nov-2017             06-Jun-2018                   01-Apr-2015




 Overall Comments




Data on Financial Performance

Disbursements (by loan)

Project                Loan/Credit/TF    Status        Currency      Original   Revised     Cancelled   Disbursed       Undisbursed                 Disbursed

P117656                IBRD-80370        Effective     USD            300.00     300.00          0.00      285.11             14.89                         95%


Key Dates (by loan)


6/28/2018                                                                                                                                     Page 6 of 7
                                                                   Public Disclosure Copy
                                                        Public Disclosure Copy

           The World Bank                                                                    Implementation Status & Results Report
           China: Kunming Urban Rail Project (P117656)



 Project       Loan/Credit/TF     Status      Approval Date   Signing Date   Effectiveness Date   Orig. Closing Date   Rev. Closing Date

 P117656       IBRD-80370         Effective   10-May-2011     28-Jul-2011    19-Oct-2011          30-Nov-2016          30-Jun-2018



Cumulative Disbursements




 Restructuring History

  Level 2 Approved on 23-Nov-2015




 Related Project(s)

 There are no related projects.




6/28/2018                                                                                                                     Page 7 of 7
                                                        Public Disclosure Copy