The World Bank Implementation Status & Results Report Angola Statistics Project (P157671) Angola Statistics Project (P157671) AFRICA EAST | Angola | Poverty and Equity Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 10 | ARCHIVED on 29-Oct-2021 | ISR48590 | Implementing Agencies: National Institute for Statistics of Angola (INE), Ministry of Finance Key Dates Key Project Dates Bank Approval Date: 07-Dec-2016 Effectiveness Date: 31-May-2017 Planned Mid Term Review Date: 30-Jul-2019 Actual Mid-Term Review Date: 06-Dec-2019 Original Closing Date: 30-Nov-2021 Revised Closing Date: 30-Nov-2021 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The PDO is to strengthen the capacity of the National Institute for Statistics to fill data gaps, improve statistical production and enhance statistical dissemination practices. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Institutional Reform and Capacity:(Cost $3.50 M) Data Production and Dissemination:(Cost $56.35 M) Project Management:(Cost $2.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions The Angola Statistics Project was approved by the Board of the World Bank on December 7, 2016, followed by the signing of the project on March 02, 2017. The effectiveness date of the project was May 31, 2017. The Instituto Nacional de Estadística (INE) is implementing the project that is organized into three components: Institutional and Human Capacity; Data Production and Dissemination; and Project Management. This ISR is based on the virtual implementation support mission that took place in Sept 2021, on continuous follow-up implementation support supervision activities held by the Bank's team during the period May to August 2021. In general, the project implementation is performing Moderately Satisfactory. Due to restrictions related to the COVID-19 pandemic and a change in INE's leadership in 2020, there were significant delays in the implementation of several key activities. At the same time, the cost increases incurred during the project mean that it will not be possible to finance some of the 10/29/2021 Page 1 of 6 The World Bank Implementation Status & Results Report Angola Statistics Project (P157671) originally planned activities. To complete project activities, a 9-month extension was agreed with the counterpart, in addition to the following steps: 1) Continued weekly project overview meetings between INE and the World Bank, with the participation of the Debt Management Unit of the Ministry of Finance; 2) Continued weekly procurement meetings with the participation of t he PIU, including its procurement staff, and the World Bank procurement team; and 3) Preparation of the new statistical project as requested during the mission for the Government of Angola. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Moderate Moderate Moderate Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Low Low Low Institutional Capacity for Implementation and Substantial Substantial Substantial Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Low Low Low Stakeholders Low Low Low Other -- Substantial Substantial Overall Substantial Moderate Moderate Results PDO Indicators by Objectives / Outcomes Increase the national statistical capacity of Angola IN01049533 ►Increase in the Statistical Capacity Index (SCI) score (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 42.20 45.60 45.60 60.00 Date 31-May-2017 30-Jul-2021 06-Oct-2021 31-Dec-2021 Data gaps on agriculture, welfare, employment and business covered surveys or censuses implemented IN01049534 10/29/2021 Page 2 of 6 The World Bank Implementation Status & Results Report Angola Statistics Project (P157671) ►Number of agriculture, welfare, employment and business surveys or censuses implemented (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 5.00 6.00 12.00 Date 31-May-2018 30-Jul-2021 08-Oct-2021 30-Dec-2021 Improved national accounts IN01049535 ►Improved national accounts (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 45.00 55.00 100.00 Date 31-May-2017 30-Jul-2020 08-Oct-2021 31-Dec-2021 Increase metadata and microdata dissemination IN01049536 ►Number of INE downloads of statistical materials and micro-datasets (Number (Thousand), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 6.00 24.00 150.00 Date 29-Apr-2016 30-Jul-2020 21-Oct-2021 30-Nov-2021 The WB team is counting all downloads from the INE catalog, considering all datasets in the catalog. The Household Survey (IDREA) is already published and there are 23971 views (October 2021), and the Comments: Employment survey (IEA) was recently uploaded has 824 views (October 2021) Intermediate Results Indicators by Components Project Management IN01049537 ►FM and procurement plan complied (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 70.00 90.00 100.00 Date 31-May-2017 06-Jul-2020 08-Oct-2021 31-Dec-2021 Data Production and Dissemination IN01049538 ►Number of published quarterly GDP statistics (Number, Custom) 10/29/2021 Page 3 of 6 The World Bank Implementation Status & Results Report Angola Statistics Project (P157671) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 15.00 16.00 10.00 Date 29-Apr-2016 30-Jul-2021 08-Oct-2021 30-Nov-2021 IN01049540 ►Number of survey and census micro-datasets available online (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 11.00 2.00 21.00 Date 29-Apr-2016 18-Dec-2020 28-Oct-2021 30-Nov-2021 The INE microdata catalog is open online with 13 datasets available to consult and download. As of now, only two of these datasets were produced under this project. Earlier higher values of this indicator included datasets produced outside this project. Comments: Institutional Reform and Capacity IN01049539 ►Number of statistical reports funded by the project available online, disaggregated by availability of gendered statistics (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 7.00 8.00 6.00 Date 29-Apr-2016 30-Jul-2021 08-Oct-2021 30-Nov-2021 Examples of statistical reports available online: Quick info sheet inquiry approved building permits (ILACE), GDP press release (quarterly reports), quick information sheet of foreign trade statistics, industrial production index quick datasheet, (IPI), quick export and import price index information sheet Comments: (IPEI), quick employment and unemployment information sheet (IEA) and economic environment; COVID impact from Labor Survey (IEA), Household Survey (IDREA) available through the NADA Catalog and the Gender Report based on IDREA Survey. IN01049541 ►The number of staff who have achieved improvements in skill/knowledge compared to a pre-training baseline (measured by test results and disaggregated by gender) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 227.00 375.00 750.00 Date 29-Apr-2016 30-Jul-2021 08-Oct-2021 30-Nov-2021 Performance-Based Conditions Data on Financial Performance Disbursements (by loan) 10/29/2021 Page 4 of 6 The World Bank Implementation Status & Results Report Angola Statistics Project (P157671) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P157671 IBRD-86690 Effective USD 62.00 62.00 0.00 49.26 12.74 79% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P157671 IBRD-86690 Effective 07-Dec-2016 02-Mar-2017 31-May-2017 30-Nov-2021 30-Nov-2021 Cumulative Disbursements PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History There has been no restructuring to date. Related Project(s) 10/29/2021 Page 5 of 6 The World Bank Implementation Status & Results Report Angola Statistics Project (P157671) There are no related projects. 10/29/2021 Page 6 of 6